PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Painting dinding luar porta camp kamar mandi PORTA CAMP PDSI Sunny NKT - A
- Dismantle & install handle pintu & drain air kamar mandi N. 1 - 4
Page 1 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/5/2019
Project Name : Porta Camp PDSI
Page 2 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/5/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 Triplek melamin 1 lembar
2. Supervisor 1 Welding Machine Paint putih 7.5 kg
3. Foreman 1 Generator Paint biru 1 kg
4. Permit Holder Inventer 1 tinner 10 liter
5. Engineer Blower 1 Dempul 2 galon
6. HSE & Leader 1 Hand drill 3 Amplas 1 meter
7. QAQC Grinding Machine 6 List triplek melamin 2 batang
8. Mekanik Paku rig pad 1 box
9. Welder Stang rig pad 2 ea
10. Fitter Kapi 5 ea
11. Mason Slipper 5 ea
12. Painter 4 Batu gerinda 4" 2 ea
13. Helper 13 Brush 2 ea
Page 3 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/5/2019
Project Name : Porta Camp PDSI
- Pendempulan, pengamplasan, painting dinding dalam porta camp 5 5 10 10% 10% 20%
N. 1-4
- Modification daun pintu (cutt & full weld) & dismantle pintu kamar mandi 4 4 100%
porta camp N. 1 - 4
- Pendempulan, pengamplasan, painting & repair list dinding dalam 2 9 11 15% 30% 45%
porta camp VIV
- Pendempulan, pengamplasan, & cleaning porta camp medik 2 4 6 10% 30% 40%
- Dismantle & install handle pintu & drain air kamar mandi N. 1 - 4 2 2 20% 20%
SOCIAL ISSUE
Page 4 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/5/2019
Project Name : Porta Camp PDSI
Problem Solution
Page 5 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/5/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 6 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Painting dinding luar dalam porta camp & cleaning kamar mandi Porta camp PDSI Sunny
porta camp
- Painting dinding dalam, luar ,cleaning porta camp P. 5-8
- Dismantle lantai & install lantai triplek , brushing dinding & install
besi pengeoran lantai kamar mandi porta camp N. 1-4
- Dismantle & install lantai vinyl, repair list dinding & cleaning porta camp
N. 1-4
- Dsimantle & install dinding triplek melamin, repair lantai kamar mandi
porta camp medik
- Painting dinding dalam porta camp N. 1-4
Page 7 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
Page 8 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 Triplek 18 mm 4 lembar
2. Supervisor 1 Welding Machine Screw 3 cm 55 ea
3. Foreman 1 Generator Gergaji besi 4 kayu 3 ea
4. Permit Holder Inventer Rebbar 1 batang
5. Engineer Blower 1 Paint (Putih) 5 kg
6. HSE & Leader 1 Hand drill 3 Paint (hitam) 1 kg
7. QAQC Grinding Machine 6 Tinner 10 liter
8. Mekanik Baut drill 10 ea
9. Welder Paku rig pad 45 ea
10. Fitter stang rig pad 2 ea
11. Mason Triplek melamin 1 lembar
12. Painter 4 Cable power 3 roll
13. Helper 13 Wire brush 1 ea
Page 9 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
Jumlah 20
Qty
Indicator Remark
Prev Today Total
1. POB 217 20 237
2. Manhours 1953 180 2133
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Painting dinding luar dalam porta camp & cleaning kamar mandi 80 25 105 80% 15% 95%
- Painting dinding dalam, luar ,cleaning porta camp P. 5-8 63 m 9m 72 85% 10% 95%
- Dismantle lantai & install lantai triplek , brushing dinding & install 2 lembar
besi pengeoran lantai kamar mandi porta camp N. 1-4 3m, 1 ea
- Dismantle & install lantai vinyl, repair list dinding & cleaning porta camp 1 lembar
N. 1-4
- Dsimantle & install dinding triplek melamin, repair lantai kamar mandi 2m, 1 ea 30% 30%
porta camp medik
- Painting dinding dalam porta camp N. 1-4 5m 10% 10%
SOCIAL ISSUE
Page 10 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
Problem Solution
- Jam 15.25 hujan turun - Jam 16.05 hujan reda & aktifitas mulai kembali
Page 11 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number : RIG PDSI#403/DS1500.E
Date : 2/4/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 12 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Dismantle & install kembali triplek melamin pintu, list & cleaning Porta camp PDSI Sunny
porta camp VIV
- Brushing, pendempulan, pengamplasan & cleaning kamar mandi
porta camp P. 3 & 4
- Install pintu kamar mandi, install lantai (vinyl), install list &
cleaning porta camp P. 7 & 8
- Modification drain air kamar mandi porta camp P.5 & 6 &
Full weld
- Finishing lantai kamar mandi & cleaning porta camp
Page 13 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
Page 14 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 unit Dempul 2 galon
2. Supervisor 1 Welding Machine Semen putih 2 kg
3. Foreman 1 Generator Amplas 1 meter
4. Permit Holder Inventer Paint 10 kg
5. Engineer Blower 1 ea Tinner 10 liter
6. HSE & Leader 1 Hand drill 2 ea Screw bolt 100 pcs
7. QAQC Grinding Machine 6 ea Lem fox 3 kaleng
8. Mekanik Gergaji kayu 2 ea Wire brush 2 ea
9. Welder Kabel power 3 roll Triplek melamin 2 lembar
10. Fitter Rig pad 1 ea Batu gerinda 4" 1 ea
11. Mason 1 Cetok 2 ea Kawat las karbon 4 ea
12. Painter 4 Mata bor 4 ea
13. Helper 13 stang rig pad 1 ea
Page 15 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
Jumlah 21
Qty
Indicator Remark
Prev Today Total
1. POB 196 21 217
2. Manhours 1764 189 1953
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Dismantle & install kembali triplek melamin pintu, list & cleaning
porta camp VIV
- Brushing, pendempulan, pengamplasan & cleaning kamar mandi
porta camp P. 3 & 4
- Install pintu kamar mandi, install lantai (vinyl), install list &
cleaning porta camp P. 7 & 8
- Modification drain air kamar mandi porta camp P.5 & 6 &
Full weld
- Finishing lantai kamar mandi & cleaning porta camp
SOCIAL ISSUE
Page 16 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
Problem Solution
Page 17 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/2/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 18 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/1/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Aduk secara manual, cutt & install keramik finishing kamar mandi Porta camp PDSI Sunny
porta camp P. 7-8
- Finishing keramik lantai kamar mandi porta camp
- Install plate stainless siku untuk pintu porta camp kamar mandi
Page 20 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/1/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 unit Dempul 1 galon
2. Supervisor 1 Welding Machine Vinyl 1 roll
3. Foreman 1 Generator Keramik lantai 1 kardus
4. Permit Holder Inventer Baut drill 45 biji
5. Engineer Blower 1 ea Paku rig pad 40 biji
6. HSE & Leader 1 Hand drill 2 ea Pasir 0.2 m3
7. QAQC Grinding Machine 6 ea Lem fox 1 kaleng
8. Mekanik Ember 4 ea
9. Welder Kabel power 3 roll
10. Fitter Rig pad 1 ea
11. Mason Cetok 2 ea
12. Painter 4 Mata bor 4 ea
13. Helper 13 Skop 1 ea
Page 21 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/1/2019
Project Name : Porta Camp PDSI
Jumlah 20
Qty
Indicator Remark
Prev Today Total
1. POB 176 20 196
2. Manhours 1584 180 1764
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Aduk secara manual, cutt & install keramik finishing kamar mandi
porta camp P. 7-8
- Finishing keramik lantai kamar mandi porta camp
- Install plate stainless siku untuk pintu porta camp kamar mandi
SOCIAL ISSUE
Page 22 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/1/2019
Project Name : Porta Camp PDSI
Problem Solution
Page 23 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 2/1/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 24 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/31/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Aduk secara manual, cutt & install keramik lantai kamar mandi Porta camp PDSI Sunny
porta camp
- Pendempulan & pengamplasan dinding dalam kamar mandi
porta camp
- Install triplek melamin untuk dinding dalam porta camp
P.5 & 8
- Cleaning vinyl / lantai porta camp P.5 & 6
gerinda mesin
- Install keramik kamar mandi porta camp P. 7-8
Page 26 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/31/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 unit Dempul 1 galon
2. Supervisor 1 Welding Machine Amplas 1 meter
3. Foreman 1 Generator Keramik lantai 3 kardus
4. Permit Holder Inventer Triplek 0.6 mm 2 lembar
5. Engineer Blower 1 ea Paint 5 kg
6. HSE & Leader 1 Hand drill 2 ea Pasir 0.2 m3
7. QAQC Grinding Machine 6 ea Triplek 18 mm 1 lembar
8. Mekanik Soft dream Silent 1 pak
9. Welder Gergaji besi 1 ea Lem fox 1 kaleng
10. Fitter Gergaji kayu 1 ea Paku rig pad 20 ea
11. Mason 1 Cetok 2 ea Baut drill 10 ea
12. Painter 4 Cangkul 1 ea
13. Helper 12 Skop 1 ea
Page 27 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/31/2019
Project Name : Porta Camp PDSI
Jumlah 20
Qty
Indicator Remark
Prev Today Total
1. POB 156 20 176
2. Manhours 1404 180 1584
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Aduk secara manual, cutt & install keramik lantai kamar mandi
porta camp
- Pendempulan & pengamplasan dinding dalam kamar mandi
porta camp
- Install triplek melamin untuk dinding dalam porta camp
P.5 & 8
- Cleaning vinyl / lantai porta camp P.5 & 6
SOCIAL ISSUE
Page 28 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/31/2019
Project Name : Porta Camp PDSI
Problem Solution
Page 29 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/31/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 30 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/30/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Aduk secara manual, cutt & install keramik lantai kamar mandi Porta camp PDSI Sunny
porta camp
- Pendempulan & pengamplasan dinding dalam kamar mandi
porta camp
- Install triplek melamin untuk dinding dalam porta camp
P.5 & 8
- Cleaning vinyl / lantai porta camp P.5 & 6
gerinda mesin
- Install keramik kamar mandi porta camp P. 7-8
Page 32 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/30/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 unit Dempul 1 galon
2. Supervisor 1 Welding Machine Amplas 2 meter
3. Foreman 1 Generator Keramik lantai 3 kardus
4. Permit Holder Inventer 1 ea Mata cutt keramik 1 ea
5. Engineer Blower 1 ea Paint 10 kg
6. HSE & Leader 1 Hand drill 2 ea Pasir 0.2 m3
7. QAQC Grinding Machine 6 ea Triplek 18 mm 2 lembar
8. Mekanik Soft dream Paku 3 cm 0.5 kg
9. Welder Wire brus 2 ea
10. Fitter Kain masun 2 kg
11. Mason 1 Semen 1 sak
12. Painter 4 Lem 1 kg
13. Helper 12
Page 33 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/30/2019
Project Name : Porta Camp PDSI
Jumlah 20
Qty
Indicator Remark
Prev Today Total
1. POB 136 20 156
2. Manhours 1224 180 1404
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Aduk secara manual, cutt & install keramik lantai kamar mandi
porta camp
- Pendempulan & pengamplasan dinding dalam kamar mandi
porta camp
- Install triplek melamin untuk dinding dalam porta camp
P.5 & 8
- Cleaning vinyl / lantai porta camp P.5 & 6
SOCIAL ISSUE
Page 34 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/30/2019
Project Name : Porta Camp PDSI
Problem Solution
Page 35 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/30/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 36 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/29/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Install keramik lantai kamar mandi dan cleaning dinding Porta camp PDSI Sunny
dan aduk semen
- Pendempulan & pengamplasan, painting porta camp
kamar mandi
- Dismantle & install kembali lantai porta camp P.5 & 6,
cleaning dinding
- Cleaning dinding porta camp P.7,8 & install melamin
untuk dinding
- Repair lantai kamar mandi P.5&6
Page 37 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/29/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 2 unit Dempul 2 galon
2. Supervisor 1 Welding Machine Amplas 2 meter
3. Foreman 1 Generator Keramik lantai 6 kardus
4. Permit Holder Inventer Mata cutt keramik 1 ea
5. Engineer Blower 1 ea Paint 2 kg
6. HSE & Leader 1 Hand drill 2 ea Tinner 3 liter
7. QAQC Grinding Machine 6 ea Triplek melamin 2 lembar
8. Mekanik Soft dream 4 unit Silent 2 ea
9. Welder Paku ring pad 12 ea
10. Fitter Amplas 1 meter
11. Labour
12. Painter 4
13. Helper 14
Page 38 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/29/2019
Project Name : Porta Camp PDSI
Jumlah 21
Qty
Indicator Remark
Prev Today Total
1. POB 115 21 136
2. Manhours 1035 189 1224
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Install keramik lantai kamar mandi dan cleaning dinding
dan aduk semen
- Pendempulan & pengamplasan, painting porta camp
kamar mandi
- Dismantle & install kembali lantai porta camp P.5 & 6,
cleaning dinding
- Cleaning dinding porta camp P.7,8 & install melamin
untuk dinding
- Repair lantai kamar mandi P.5&6
SOCIAL ISSUE
Problem Solution
Page 39 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/29/2019
Project Name : Porta Camp PDSI
Page 40 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/29/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 41 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/28/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Install form work, rebar & poruing concrete lantai kamar mandi Porta camp PDSI Sunny
porta camp p-7 & 8
- Pendempulan, amplas & painting kamar mandi porta camp
- Modification dinding kamar mandi porta camp menggunakan
gerinda mesin & full weld
- Repair canopy pintu P.S & repair anak tangga kamar mandi porta camp
(full weld)
- Install triplek lantai P.S & install dinding porta camp P.8
Page 42 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/28/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 1 unit Dempul 2 galon
2. Supervisor 1 Welding Machine Amplas 2 meter
3. Foreman 1 Generator Baut drill 25 ea
4. Permit Holder Inventer 1 ea Batu gerinda cutt 4" 3 ea
5. Engineer Blower 1 ea Triplek melamin 5 lembar
6. HSE & Leader 1 Hand drill 2 ea Tinner 5 liter
7. QAQC Grinding Machine 6 ea Paku ring pad 15 ea
8. Mekanik Dryer Pasir 0.3 m3
9. Welder 1 Cetok 2 ea Semen 1 sak
10. Fitter 2 Ember 6 ea Brush 2 ea
11. Labour Gergaji besi 1 ea Triplek 18mm 5 lembar
12. Painter 4 Skop 1 ea Paint 5 kg
13. Helper 13 Cangkul 1 ea
Page 43 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/28/2019
Project Name : Porta Camp PDSI
Jumlah 23
Qty
Indicator Remark
Prev Today Total
1. POB 92 23 115
2. Manhours 828 207 1035
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Install form work, rebar & poruing concrete lantai kamar mandi
porta camp p-7 & 8
- Pendempulan, amplas & painting kamar mandi porta camp
- Modification dinding kamar mandi porta camp menggunakan
gerinda mesin & full weld
- Repair canopy pintu P.S & repair anak tangga kamar mandi porta camp
(full weld)
- Install triplek lantai P.S & install dinding porta camp P.8
SOCIAL ISSUE
Problem Solution
Page 44 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/28/2019
Project Name : Porta Camp PDSI
Page 45 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/28/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 46 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/27/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Install formwork, rebar & pouring concrete lantai kamar mandi Porta camp PDSI Sunny
- Pendempulan dan pengamplasan dinding porta camp kamar mandi
- Modification dinding porta camp kamar mandi dan vinylasi
- Bongkar dan install kembali dinding porta camp & lantai
- Modification & cut lantai kamar mandi menggunakan gerinda
potong
Page 47 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/27/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Unit
1. Project Manager Kompressor 1 unit Dempul 1 ea
2. Supervisor 1 Welding Machine Amplas 2 lembar
3. Foreman 1 Generator Batu gerinda poles 3 ea
4. Permit Holder Inventer Batu gerinda cutt 3 ea
5. Engineer Blower 1 ea Kawat las karbon 3 ea
6. HSE & Leader 1 Hand drill Bendrat 0.5 kg
7. QAQC Grinding Machine 6 ea Besi ø8 4 batang
8. Mekanik Dryer Pasir 50 m3
9. Welder 1 Semen 2 karung
10. Fitter 2 Paku 1 kg
11. Labour Triplek 18mm 5 lembar
12. Painter 4
13. Helper 12
Page 48 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/27/2019
Project Name : Porta Camp PDSI
Jumlah 22
Qty
Indicator Remark
Prev Today Total
1. POB 70 22 92
2. Manhours 630 198 828
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Install formwork, rebar & pouring concrete lantai kamar mandi
- Pendempulan dan pengamplasan dinding porta camp kamar mandi
- Modification dinding porta camp kamar mandi dan vinylasi
- Bongkar dan install kembali dinding porta camp & lantai
- Modification & cut lantai kamar mandi menggunakan gerinda
potong
SOCIAL ISSUE
Problem Solution
Page 49 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/27/2019
Project Name : Porta Camp PDSI
Page 50 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/27/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 51 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/26/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Pendempulan & pengamplasan dinding porta camp K Porta camp PDSI Sunny
- Painting porta camp sliper & kamar mandi
- Puring concrete untuk lantai kamar mandi porta camp
- Instal form work & rebar
Page 52 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/26/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Remarks
1. Project Manager Kompressor 1 unit Dempul 2 ea
2. Supervisor 1 Welding Machine Amplas 1 lembar
3. Foreman 1 Generator Kaso 10 ea
4. Permit Holder Inventer Triplek 1 ea
5. Engineer Blower 1 ea Paint 2 kg
6. HSE & Leader 1 Hand drill Tinner 2 liter
7. QAQC Grinding Machine 6 ea Besi rebar 3 batang
8. Mekanik Dryer Pasir 0.5 m3
9. Welder 1 Semen 5 karung
10. Fitter 2
11. Labour
12. Painter 3
13. Helper 13
Page 53 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/26/2019
Project Name : Porta Camp PDSI
Jumlah 22
Qty
Indicator Remark
Prev Today Total
1. POB 48 22 70
2. Manhours 432 198 630
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Pendempulan & pengamplasan dinding porta camp K
- Painting porta camp sliper & kamar mandi
- Puring concrete untuk lantai kamar mandi porta camp
- Instal form work & rebar
SOCIAL ISSUE
Problem Solution
Page 54 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/26/2019
Project Name : Porta Camp PDSI
Page 55 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/26/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 56 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/25/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Pendempulan & pengamplasan dinding porta camp Porta camp PDSI Sunny
- Brush porta camp kamar mandi
- Painting porta camp sliper
Page 57 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/25/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Remarks
1. Project Manager Kompressor Dempul 1 ea
2. Supervisor 1 Welding Machine Amplas 2 ea
3. Foreman 1 Generator Kapi 5 ea
4. Permit Holder Inventer Sliper 5 ea
5. Engineer Blower Paint 5 kg
6. HSE & Leader Hand drill Tinner 5 liter
7. QAQC Grinding Machine
8. Mekanik Dryer
9. Welder
10. Fitter 2
11. Labour
12. Painter 3
13. Helper 13
Page 58 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/25/2019
Project Name : Porta Camp PDSI
Jumlah 20
Qty
Indicator Remark
Prev Today Total
1. POB 28 20 48
2. Manhours 252 180 432
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Pendempulan & pengamplasan dinding porta camp
- Brush porta camp kamar mandi
- Painting porta camp sliper
SOCIAL ISSUE
Problem Solution
Page 59 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/25/2019
Project Name : Porta Camp PDSI
Page 60 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/25/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 61 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/24/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Pendempulan & pengamplasan dinding porta camp Porta camp PDSI Sunny
- Brush & penggrindaan dinding porta camp
- Pembongkaran kamar mandi porta camp toilet
Page 62 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/24/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Remarks
1. Project Manager Kompressor Dempul 1 ea
2. Supervisor 1 Welding Machine Amplas 2 ea
3. Foreman 1 Generator Kapi 5 ea
4. Permit Holder Inventer Sliper 5 ea
5. Engineer Blower Mata brush 2 ea
6. HSE & Leader Hand drill Mata gerinda poles 1 ea
7. QAQC Grinding Machine
8. Mekanik Dryer
9. Welder
10. Fitter 2
11. Labour
12. Painter 3
13. Helper 7
Page 63 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/24/2019
Project Name : Porta Camp PDSI
Jumlah 14
Qty
Indicator Remark
Prev Today Total
1. POB 14 14 28
2. Manhours 126 126 252
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Pendempulan & pengamplasan dinding porta camp toilet
- Brush & penggrindaan dinding dalam porta camp toilet
- Pembongkaran dinding kamar mandi porta camp toilet
SOCIAL ISSUE
Problem Solution
Page 64 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/24/2019
Project Name : Porta Camp PDSI
Page 65 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/24/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 66 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/23/2019
Project Name : Porta Camp PDSI
PROJECT ACTIVITIES
Description
Activity Today Location Weather Overtime Next Activity Area
- Pendempulan & pengamplasan dinding porta camp Porta camp PDSI Sunny
- Brush & penggrindaan dinding porta camp
- Pembongkaran kamar mandi porta camp toilet
Page 67 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/23/2019
Project Name : Porta Camp PDSI
Material / Tools
Manpower Total Equipment Involve Total
Description Issued Remarks
1. Project Manager Kompressor Dempul 1 ea
2. Supervisor 1 Welding Machine Amplas 2 ea
3. Foreman 1 Generator Kapi 5 ea
4. Permit Holder Inventer Sliper 5 ea
5. Engineer Blower
6. HSE & Leader Hand drill
7. QAQC Grinding Machine
8. Mekanik Dryer
9. Welder
10. Fitter 2
11. Labour
12. Painter 3
13. Helper 7
Page 68 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/23/2019
Project Name : Porta Camp PDSI
Jumlah 14
Qty
Indicator Remark
Prev Today Total
1. POB 0 14 14
2. Manhours 0 126 126
PROGRESS SUMMARY
Progress Qty Progress (%)
Activity Name Remarks
Prev Today cum Prev(%) Today (%) Cum
- Pendempulan & pengamplasan dinding porta camp toilet
- Brush & penggrindaan dinding porta camp toilet
- Pembongkaran kamar mandi porta camp toilet
SOCIAL ISSUE
Problem Solution
Page 69 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/23/2019
Project Name : Porta Camp PDSI
Page 70 of 71
DAILY PROGRESS REPORT
Starting Date : 1/23/2019 SI Number :
Date : 1/23/2019
Project Name : Porta Camp PDSI
PHOTO'S ACTIVITIES
____________________________ ____________________________
Page 71 of 71