You are on page 1of 4

Classification: Internal SF/FR-23

EMCO FACILITIES MANAGEMENT Doc. No:

DAILY HSE REPORT Revision No: 01 25/01/16

Report No.: MS / 98 / 22020 / 2023 Date: 04/06/2023

Name of the Project / Factory / Workshop / Job No:22020 – Qatargas- BARZAN Division/ Area: Plant, Admin, BFOC & NFXP
Name of the Project Director / Site / Workshop Manager: Mr.K.M.Shadab / Staff No.90128
SECTION A: Project HSE Lead
Avg. No of
No. of
man No. of Man days
- No. of LTI - - Hospital -
days lost
Ref.cases
worked
No. of Near Miss No. of
No. of First
Man-hours -
Aid cases
- Incidents - HSEMeeting -
worked reported conducted
SECTION B: Project HSE Officer/Engineer
D Dang Remedial Action
Hazard
at Equipment/ Doc
er Dang Proposed/ Additional Action
Action By with Target
Sl. No. a Observations Level er control measure / taken
Ref. Staff No& Name. date
ty (LXSX code Applicable Legal on
pe E) requirement to comply
Landscape equipment was stored in an Improper Advised the concerned person to 1 week Open-
open area as no shaded storage places storage of store all this gasoline operated On
1 UC BXK-1 are available for landscape equipment in equipment M 8 equipment under a shed to protect Landscape RT approv
it from getting exposed to the al
admin areas. sunlight. stage
The rest shelter roof sheets support have Damaged 3 Days
Open-
visible signs of damage and mold, and the roof/ceiling
The concerned person was On
2 wooden sheets seem swollen and puffy. supports
UC BSS-1 M 8 advised to replace the roof sheets Civil/Landscape approv
can fall off ASAP. al
and sustain
stage
injury.
It was noticed that a few essential first aid Lack of first The issue was notified to the 1 Week
3 aid kits Intend
UC BZ-Yard kits were not available inside the box at L 4 concerned person for the filling of HSE-Management
raised
BZ Yard. first aid kits.
All fire extinguisher external service is Delay in
overdue, the FE was supposed to be sent equipment’ The concerned person was
4 s service Intend
UC BZ-Yard on or before May 23, 2023, which was the M 8 informed regarding this standing HSE
raised
recommended date for external issue.
inspection.

Page 1 of 4
Classification: Internal SF/FR-23
EMCO FACILITIES MANAGEMENT Doc. No:

DAILY HSE REPORT Revision No: 01 25/01/16

TBT/LMRA was conducted by PH to the


workers and all are aware of the
emergency procedure, Tools were found
in good condition, workplace hazards &
control measures were captured in JSA,
Permit No. Site controls – Work location barricaded,
CWP 2236348,
Signages and Barricade owner
information tags were displayed,
Activity:
Appropriate PPE’s used by the workforce.
1 Landscaping RT No Action Required Abrar-(PH)
Special PPE: Nil
Location: 1 to 24
SWP Checklist: The relevant checklist
were attached to the permit
JSA: Attached with the permit- 2236349
MSDS: Attached to the permit- QAFCO –
Urea Granules, Urea Prills,

Isolation: Personal Plumbing


Certification: Nil
TBT/LMRA was conducted by PH to the
workers and all are aware of the
emergency procedure, Tools were found
in good condition, workplace hazards &
Permit No. control measures were captured in JSA,
GWP 2240277, Site controls – Work location barricaded,
Signages and Barricade owner
Activity: Fixing of information tags were displayed,
2 Shahnawaz-(PH)
PVC Net Appropriate PPE’s used by the workforce. No Action Required
Location: BSB Special PPE: Nil
SWP Checklist: The relevant checklist
were attached to the permit
JSA: Attached with the permit- 2249278
MSDS: Attached to the permit.
Isolation: Nil
Certification: Nil
Permit No. TBT/LMRA was conducted by PH to the
CWP 2249289, workers and all are aware of the
3 emergency procedure, Tools were found Niyazh-(PH)
Activity: Roof in good condition, workplace hazards & No Action Required
concrete repair control measures were captured in JSA,
Location: BXK-1
Page 2 of 4
Classification: Internal SF/FR-23
EMCO FACILITIES MANAGEMENT Doc. No:

DAILY HSE REPORT Revision No: 01 25/01/16

Site controls – Work location barricaded,


Signages and Barricade owner
information tags were displayed,
Appropriate PPE’s used by the workforce.
Special PPE: Nil
SWP Checklist: The relevant checklist
were attached to the permit
JSA: Attached with the permit- 2249290
MSDS: Attached to the permit
Isolation: Nil
Certification: Nil
TBT/LMRA was conducted by PH to the
workers and all are aware of the
emergency procedure, Tools were found
in good condition, workplace hazards &
Permit No. control measures were captured in JSA,
CWP 2243707, Site controls – Work location barricaded,
Signages and Barricade owner
Activity: Civil RT information tags were displayed,
4 Wasim-(PH)
Location: BXK-2- Appropriate PPE’s used by the workforce. No Action Required
8 Special PPE: Nil
SWP Checklist: The relevant checklist
were attached to the permit
JSA: Attached with the permit- 2243708
MSDS: Attached to the permit
Isolation: Plumbing Personal
Certification: Nil
TBT/LMRA was conducted by PH to the
workers and all are aware of the
Permit No. emergency procedure, Tools were found
CWP 2241589, in good condition, workplace hazards &
control measures were captured in JSA,
5
Activity: Electrical Site controls – Work location barricaded,
No Action Required Safiullah-(PH)
RT PPM, CM Signages and Barricade owner
Location: BXK-2 information tags were displayed,
Appropriate PPE’s used by the workforce.
Special PPE: Nil
SWP Checklist: The relevant checklist
were attached to the permit

Page 3 of 4
Classification: Internal SF/FR-23
EMCO FACILITIES MANAGEMENT Doc. No:

DAILY HSE REPORT Revision No: 01 25/01/16

JSA: Attached with the permit- 2241590


MSDS: Attached to the permit
Isolation: Nil
Certification: Nil
TBT/LMRA was conducted by PH to the
workers and all are aware of the
emergency procedure, Tools were found
in good condition, workplace hazards &
Permit No. control measures were captured in JSA,
CWP 2250289,
Site controls – Work location barricaded,
Signages and Barricade owner
Activity:
information tags were displayed,
6 Scaffolding Work Shahnawaz-(PH)
Appropriate PPE’s used by the workforce. No Action Required
Location: BXK-5
Special PPE: Nil
WH
SWP Checklist: The relevant checklist
were attached to the permit
JSA: Attached with the permit- 2250290
MSDS: Attached to the permit.
Isolation: Nil
Certification: Nil

Prepared by: Submitted to:


Name/Staff No. / Designation: Mohd Sayeed / HSE Officer-91374 Name/Staff No. K.M. Shadab / 90128

Page 4 of 4