Replacement of Ended Life Time Technologies

and Assets for Shuqaiq Phase 1 Desalination Transmittal No.:EEPSP-


Plant RA-SWRO-007

Submission Date: 27/11/2022


TRANSMITTAL

Submitted To: ACCIONA/RTCC (JV) Subject: Risk Assessment for civil Work

Submitted From: Elsewedy Electric Received by:

DISCIPLINE:
Civil General Process Quality
Mechanical Instrumentation Project Management
Electrical Piping Safety and Environment.

DOCUMENT ISSUED FOR:

Preliminary For Inter-discipline Check As Built


For Design For final Check For use
For Purchase For Client Review/ Approval For Information
For Enquiry For Construction

ACTION TAKEN

A: Reviewed with comments D: Reviewed, no comments G: Documents listed below


B: Approved with comments E: Approved, no comments H: Comments on Attachment
C: Not approved F: Comments noted below I: Document list attached
Others (Specify)

Document List:

1. EEPSP-RA-SWRO-007 Risk Assessment for for civil Work

2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Comments:

Insert internal Code


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:1 of 11

Ref. N°: JAB/RA/009 Participants Name Job Title Signature


Abdel Aziz Anter Construction Manager
Activity/Task Mohamed Fayaz Safety officer
concerned and its CIVIL WORKS
location

Required level of  Minimum (at start


 Permanent  Other:
Supervision: and end of task)
Risk Rating (RR) guideline:

IMPORTANT NOTE : By signing this document, it is acknowledged by each


person involved in this risk assessment that all reasonable attempts have been
made as a first priority to identify any potential to eliminate all the significant
hazards listed, e.g. by preventing working at height or entering into a confined
space.

Likelihood (L): Probability of the undesired event to happen (shall consider the frequency and duration of exposure and Severity (S): Importance of harm, damage or impact caused by the event.
the potential for the undesired event to happen).

Value Definition Severity Value Definition


Negligible the occurrence is extremely unlikely to happen and has never happened according to Minor None or very limited consequences on people (e.g. first aid injury), property (e.g. scratch on equipment painting) or the
(1) our knowledge (1) environment (e.g. small quantity of biodegradable waste dispersed)
Low the occurrence is unlikely to happen in the foreseeable future but has already been Moderate Injury requiring medical treatment without lost workdays, reversible environmental negative impact or property damage /
(2) experienced (2) business interruption below 50 k€ of cost involved
Moderate the occurrence is predictable to happen in the mid-term High Lost Time Injuries, with full recovery, or reversible environmental negative impact or property damage/business interruption
(3) (3) below 200 k€ of cost involved
High the occurrence is predictable to happen in the short term Major Severe Accident as per ACCIONA & RTCC General Electric criteria.
(4) (4)
Definite The occurrence is certain and immediate. Catastrophic Potential for several fatalities (or other type of severe accident)
(5) (5)

Approved by

Competent Discipline Engineer EHS Representative (Name,


(Name, Signature and Date) Signature and Date)

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:2 of 11

Activity Step Hazard Risk and affected Existing Control Measures (L) (S) (RR) Additional Control Measures (L) (S) (RR) Check
Persons
Permit to Work shall be obtained as a pre-requisite to 3 3 9 Site Manager, Supervising Engineer, 2 1 2 HSE
perform work. Foreman shall designate a Permit Receiver Supervisor
competent enough to take responsibility in
Work shall not be started until duly approved Permit securing the Permit to Work. Construction
to Work is available at site and that Safety Toolbox Permit Receiver shall be trained and Supervisor
-Accident resulting meeting was conducted. authorized to receive a Permit to Work.
serious injury or death Permit Receiver shall be responsible to
to worker. A safe work practice shall be implemented to reduce oversee for the safety of all workers under
-Significant property the possibilities of accident / incident. his Permit to Work.
Unauthorized work. and appurtenances
Unauthorized damage Permit Receiver and Permit Issuer shall visit together Manager, Supervisor, Foreman, and all
personnel entering a -Loss of production at the site to ensure that workplace hazards are workers shall adhere to all requirements
restricted location Significant cost due to adequately identified and mitigating measure shall be set forth in the Permit to Work, Risk
Without permit. damages established. Assessment and other relevant safety
1-Obtain Unidentified hazards -Governmental practices and standards.
with unplanned safety violation Permit to Work shall be displayed at the worksite.
Permit to mitigating measures Environmental All workers shall attend the toolbox
Work Improper complaint. Permit Receiver shall not leave the area for the whole meeting daily conducted by the
communication duration of work. Supervising Engineer, Foreman and
between permit Permit Receiver
receives and issuer. Work shall not proceed without the presence of
Incorrect equipment approved Permit to Work with the Permit Receiver All workers attending the toolbox meeting
identification overseeing the activity. shall sign on the attendance sheet.
- Permit receiver must be trained and able
Permit Receiver shall account all workers under his to communicate each and everything
Permit to Work before the start of work. related to his job.
-
Joint site visit should be done before issuing work
permit.

Clearly identify the equipment number and location


to be worked.
2-Mobilization • Struck with sharp "• Accident resulting 3 4 12 3 1 3 HSE
and hard object injury to personnel Housekeeping shall be done before, during and Site management plan shall be prepared Supervisor
Tools • Vehicular accident after the job indicating all the location of personnel
Equipment • Property damage to and equipment access, parking areas, Construction
and materials. equipment or Designated access shall be free from any offices, materials storage area, disposal Supervisor
materials obstruction area, hazardous waste disposal and
storage area, rest shelter, evacuation
Designate location for unloading of personnel and area and etc.
materials be stored only on a designated storage
area Designate a dedicated personnel who is
familiar with the site management plan
Designate material disposal area with secondary to guide all personnel and equipment in
containment intended for the hazardous liquid loading and unloading of materials and
material equipment

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:3 of 11

• Unorganized "• Accident resulting All material location and storage shall be barricaded
materials and access injury to personnel and provided with adequate signage.
• Vehicular accident "• Site management plan shall be
• Property damage to prepared indicating all the location of
equipment or materials Housekeeping shall be done before, during and after personnel and equipment access,
the job parking areas, offices, materials storage
area, disposal area, hazardous waste
Designated access shall be free from any obstruction disposal and storage area, rest shelter,
evacuation area and etc.
Designate location for unloading of personnel and
materials be stored only on a designated storage area Regular tool box talk should be
conducted
Designate material disposal area with secondary
containment intended for the hazardous liquid Erection of working platform conforms
material to the standard base on height
requirements.
All material location and storage shall be barricaded
and provided with adequate signage Tagging system should be observed and
4 3 12 implemented.
Falling objects Working platform 3 1 3
erected in an unstable
surface/ ground could
cause collapse and
property damage Working platform should be erected on a compacted
and stable ground
Objects falling during
erection of working Install adequate barricade and signage
platform could cause
injury to persons in the Conduct thorough material inspection prior to
vicinity material utilization

Installing substandard Working platform should be erected by certified and


components may cause competent personnel and regular inspection
collapse of the conducted by certified inspector
platform.
Personal protective equipment must be observed like
Mobilizing untrained coverall clothing, rubber gloves, safety goggles and
workers may cause etc.
severe accident
Close supervision by the engineer, supervisor or
foreman must observe.

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:4 of 11

3-Cutting of Use of electrical steel • Physical injury due 4 3 12 Moving parts protection must be 3 1 3 HSE
cutter machine to contacts from All rotating parts shall be provided with adequate inspected periodically. Supervisor
ply wood, rotating and cutting machine guarding Emergency stop button must be
Preparing Energized electricity part of the provided Use cotton gloves with rubber palm Construction
shuttering. equipment gloves for cutting works. Supervisor
Incorrect manual • electric shock due Ensure all tools are inspected and color coded
handling/ lifting of to contact with All defective tools must be brought to
material energized electricity Issuance of appropriate PPE such as safety shoes (BS store for replacement, repair and
Poor Access/Egress "• Muscular injuries 1970 or ANSI Z41.1) safety glasses (BS 29092 or quarantined.
(Back pain, strain, ANSI Z 87.1) and rubberized hand gloves for
Use of electrical tools fractures) protection on sharp edges. Emergency stop button must be
(bending machine) • pinch/crash points inspected periodically.
resulting hand Equipment manual must be available.
injuries Designate a proper fabrication area in
" Keep hands & fingers away from trapping/pinch performing this task.
• Physical injury points. Use hand protection • Secure cables by hanging to avoid
from slip, trips & obstructing the access way & from
fall No loose clothing and remove all jewelry to prevent damage.
• Physical injury due being entangled on the rotating part of the tools. "
to pinch point and "• Defective tools and equipment shall
crushed by moving Only qualified and competent persons to work on not be used and must be return to store
part of the machine electrical equipment. for replacement, repair or quarantined.
• Conduct training regarding electrical
Protruding Ensure all electrical equipment/tools to be used are in safety to all workers to increase their
good condition. awareness.
nails is • Post some campaigns regarding
always a Apply lock out / tag out if necessary electrical safety.
• Use cotton gloves with rubber palm
high risk in Inspect the power tools and its plug and cable prior to gloves for grinding and cutting works.
shuttering use to ensure it is in safe working condition. "
"• Provide material handling equipment
and form Provide colour coding to ensure the tools is inspected for transport of heavy and large
work areas. and safe to use. Use of hand protection (rubber materials / equipment
gloves). • Provide proper workbench table to
" avoid over reaching and repetitive
Ensure to plan correct manual lifting procedures and twisting and bending of the body.
body positioning before the actual lift. • Inspection oh Material Handling
equipment prior to use
Only 20 kg allowed lifting by an individual. "
"• Any obstructions shall be moved and
Use buddy system if load exceed. kept materials away from any access.
Keep work area free from loose tools
Use hand protection (cotton gloves minimum) during and materials.
handling of materials. • Supervisor and foreman must ensure
clear and safe access/egress
Keep hands away from pinch/crash points "
" "• Moving parts protection must be
Access pathways to be kept clear from any inspected periodically.
obstruction. • Use cotton gloves with rubber palm
Risk assessment reference number: JAB/RA/009
HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:5 of 11

• Conduct housekeeping before, during and after gloves for grinding and cutting works.
work to ensure free access/egress. • All defective tools must be brought to
• Provision of proper work access (i.e. ladder or store for replacement, repair and
scaffold) quarantined.
" • Secure cables by hanging to avoid
"• All rotating parts shall be provided with obstructing the access way & from
mechanical cover. damage.
• Emergency stop button must be provided
• Ensure all tools are inspected and color coded. A de-nailing area provided and
• Keep hands & fingers away from trapping/pinch
points. Use hand protection.
all the shuttering wood must be
" shifted to de nailing yard to
remove the nails.
4- • Fabricated hand tools Cuts, laceration "• Keep eyes on task 4 3 12 Inspect all PPE issued 3 1 3
used Protruding nails, • Provide proper steel fixing hand tools All hand tools to be used must be
Reinforement • Incorrect manual steel bars and sharp • Improvised and fabricated hand tools shall not be inspected.
work. handling/ lifting of edges use
material • Supervisor and Foreman shall ensure that workers Barricade the area where activity is
• Sharp & protruding Muscular injuries are provided with proper hand tools happening.
materials/ objects (Back pain, strain, • Wear rubberized hand gloves
fractures) • Provision for barricade and signage Provision for rebar caps as needed only
pinch/crash points • Refer to engineering drawing "Provide material handling equipment for
resulting hand "
injuries "• Ensure to plan correct manual lifting procedures Transport of heavy and large materials /
and body positioning before the actual lift. equipment.
Hand injuries due to • Only 20 kg allowed lifting by an individual.
contacts with sharp • Use buddy system if load exceed. Inspection of Material Handling
tools and object • Use hand protection (cotton gloves minimum) equipment prior to use
during handling of materials.
• Keep hands away from pinch/crash points Hand protection safety awareness training
" and campaign posters.
"• All workers engage in task must be provided with
required Hand gloves. Rubberized gloves shall be used for this
• Supervisor / foreman to ensure proper monitoring of activity
their activities for safe operation.
"
Incompetent personnel Verification of third party certificate of both 4 3 12 Barricade the area where the concrete 3 1 3
Sharp & protruding operator and equipment. pouring is going on.
materials/ objects Defective equipment
Unassisted Pre-inspection of all equipment to ensure all are in Arrange a banks man for each truck or
5-Setting up Hitting by moving manoeuvring good and safe working condition. equipment for manoeuvring. HSE
of concrete equipment Supervisor
pump and Congestion due to Proper planning and coordination with other Monitoring by site supervisor and safety
arranging the Injuries. vehicle traffic and working teams to avoid any conflicts. personnel. Construction
Other on-going Supervisor
concrete truck Poor Access/Egress activities. Assign trained flagman to control traffic on the
Use of electrical tools area and route to be taken by trucks.
(bending machine) Unlevelled and un-
compacted ground. Assign trained banksman to assist operator/driver
Risk assessment reference number: EEPSP/RA/007
HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:6 of 11

during manoeuvring.

Survey of the area and route to be taken to ensure


grounds are well levelled and compacted.

Incompetent Proper hand signals shall be established and used. 4 3 12 Barricade the area where the concrete 2 2 4 HSE
personnel pouring is going on. Supervisor
6- Concrete Poor Access/Egress Miscommunication The only trained and competent operator shall be
to operator. assigned to control equipment during discharging of Arrange a banks man for each truck or Construction
pouring. Use of electrical tools cement. equipment for manoeuvring. Supervisor
(bending machine) Obstructions in the
path of the The operator should be positioned in an area where he Monitoring by site supervisor and safety
Hit by equipment boom/placing hose. can see the movement of the discharge pipe and the personnel.
workers.
Vehicular accidents. Unauthorized Arrange suitable ppe’s for the task like,
personnel No unauthorized personnel or not part of the team 1. Gum boots
shall be allowed inside the working area. 2. Rubber gloves
Adverse weather 3. N-95 Mask
condition. 4. Safety glasses
4 3 12 3 1 3 HSE
7-Concrete Poor Access/Egress Incompetent The only trained and competent operator shall be Supervisor
personnel assigned to perform curing job. Monitoring by site supervisor and safety
curing. Slip and tripping personnel. Construction
hazards. Miscommunication Provided the suitable ppe’s Supervisor
to operator. Arrange suitable ppe’s for the task like,
Arranged a competent Driver and a Banks man to 1. Rubber gloves
Water tanker may hit guide the tanker. 2. N-95 Mask
the existing facility. 3. Safety glasses

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:7 of 11

Inhalation of toxic • Special personal protective equipment must be 4 3 12 Only trained and competent workers 3 1 3 HSE
8- Surface fumes causes observed like coverall clothing, rubber gloves, should do the job. Supervisor
Presence of toxic dizziness irritation respiratory equipment, clear goggles and etc.
preparation. fumes, Chemical in of nose and throat • Close supervision by the engineer, supervisor/ Reduce the exposure of workers by Construction
contact with skin. and chronic diseases foreman must be observed. observing frequent rotation and breaks. Supervisor

Improper waste The following items must be provided. Monitoring by site supervisor and safety
disposal may cause personnel.
Exposure to dust. environmental N95 Masks
contamination Face shields
Blower
Chemical suit
Exhaust fan
Presence of toxic Inhalation of toxic Provision of appropriate waste container 4 3 12 3 1 3
fumes, Chemical in fumes causes Only trained and competent workers
contact with skin. dizziness irritation should do the job
9-Concrete of nose and throat Observe proper segregation and disposal of waste.
repair works. No adequate PPE and chronic diseases Close supervision by the engineer, supervisor/ Reduce the exposure of workers by
foreman must be observed. observing frequent rotation and breaks
Awkward position Improper waste
disposal may cause
Contact with cement environmental Special personal protective equipment must be
chemical through contamination. observed like coverall clothing, rubber gloves,
inhalation, skin respiratory equipment, clear goggles and etc.
absorption or Only trained and competent workers
ingestion. should do the job
Close supervision by the engineer, supervisor/
foreman must be observed. Reduce the exposure of workers by
observing frequent rotation and breaks.
In poorly ventilated areas, a respirator suitable for
organic vapours should be used. Air supplied
respirators should be used in areas with inadequate
oxygen and high vapour concentrations. Ensure good
ventilation, maintenance, and housekeeping. Ensure workers involved in the job are
given with adequate information
regarding the chemical content of
cement

Provision of effective ventilation


(blower and exhaust fan) if inside
confined space or basement

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:8 of 11

The selection of suitable gloves does


not only depend on the material, but
also on further marks of quality which
vary from manufacturer to
manufacturer.

Personal hygiene is a key element of


effective hand care. Wear chemical
protective gloves, e.g. PVC.

Supervisor and Foreman shall discuss


SDS with all the workers and the risk
involve from the activity

Safety Officer shall ensure that all


workers have received proper awareness
on safe handling of cement.
Presence of toxic Improper waste Provision of appropriate waste container 3 3 9 3 1 3
10- fumes, Chemical in disposal may cause
contact with skin. environmental Only trained and competent workers
Inspection contamination. Observe proper segregation and disposal of waste. should do the job
and testing. No adequate PPE Close supervision by the engineer, supervisor/
foreman must be observed. Reduce the exposure of workers by
Awkward position observing frequent rotation and breaks.

Contact with cement Special personal protective equipment must be Arrange a temporary shelter
chemical through observed like coverall clothing, rubber gloves,
inhalation, skin respiratory equipment, clear goggles and etc. for testing team to take rest
absorption or in standby time between
ingestion.
Close supervision by the engineer, supervisor/
concrete trucks.
foreman must be observed.
Provide sufficient drinking
water.

Use polyethylene cover to


avoid contamination of soil.

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:9 of 11

Unwanted Material Slip/Trip Ensure frequent cleaning of workstation from 3 3 9 Supervisor should ensure that all tools 2 1 2 HSE officer
Material not properly Physical Injury obstructing, unwanted material / objects, and and equipment’s are in designated Area.
store in designated slippery floor. Construction
area. Any spillage should be cleaned up immediately and Supervisor
stored into approved container.
Keep the area clean and tidy all the time.
11- Generated trash/garbage shall be collected and
Housekeeping disposed daily to the central collecting station.

3 3 9 2 1 2
Unsecured electrical Supervising Engineer and Foreman
equipment, energized Significant property Permit Receiver shall ensure that housekeeping in shall adhere to the proper housekeeping
equipment and appurtenances done before, during and after the work and storage of materials at the
damage. designated location. HSE officer
12-Closing Electrical equipment shall be properly secured,
of Permit to Undisposed waste Governmental distribution board closed and padlocked" Construction
materials violation Supervisor
Work. All waste materials generated from the work shall
Unaccounted workers Accident resulting be disposed properly and shall not be left Mobile equipment shall properly parked
serious injury or unattended at the worksite on a designated equipment laydown.
Inadequate death to worker
communication Permit Receiver shall account all worker under his
Loss of production Permit to Work and ensure all have signed out on
Poor storage of the attendance sheet and clear of the area
chemical, flammable Environmental
and combustible complaint Site Manager shall be responsible on the effective
materials and etc. implementation of the Permit to Work
Significant cost due
Unattended unsafe to damages All materials used at the site such as chemicals,
condition flammable and combustible materials shall be
stored at the designated storage at the end of each
day

Permit Issuer shall visit the work location to


verify good housekeeping was conducted before
closing the Permit to Work.

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:10 of 11

COMMUNICATION TO WORKING PARTY


By signing this sheet, each individual acknowledge that he received information on the risks and control measures associated to the identified activity, that he will adhere to these
control measures and that he will report any discrepancy to its content and stop the work whenever necessary.
Full Name Job Title Signature Date Full Name Job Title Signature Date

Risk assessment reference number: EEPSP/RA/007


HSE Risk Assessment
Revision: 0 Date: 2022/04/07 Page:11 of 11

Risk assessment reference number: EEPSP/RA/007