Professional Documents
Culture Documents
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Task No.: 01- General Preparatory Works such as accessing to site operational areas for routine works, inspection and other normal visits.
Falling objects due Personal Site Workers Ministerial All personnel are safety inducted 3 5 5 75 Visitor will be escorted with 3 5 1 1
to Site specific Injuries and staff Order 32 and security formalities have been HSE team or site Engineer.
issues: Congestion Injuries Visitors /1982. fulfilled. RA and Emergency Response
(space restriction/ caused by Medical health Check formalities Protocol shall be communicated
Simultaneous stumbles, DM are completed after the induction to the inspectors and other
activities, loose slips, trips Construction to ensure that the staff & other visitors.
falling objects and and falls Code of Safety personnel are physically Fit for All site personnel should refrain
other structural Practice carrying out the job. from having hands in pockets
elements such as Chapters 2, 4, All site visitors and employees when walking about the site.
scaffolding 20 and others stay within the designated Obtain site specific information
accessories. as applicable pedestrian areas where possible at from the ESC before the survey
Walking on all times. takes place wherever possible.
unlevelled ground, All employees are advised to keep If any new hazards are identified
soft ground, crush away from adjacent activities on site, then controls will be
and rubble, open specially erected scaffolding, established/implemented through
floor holes crane & MEWP operational areas. STARRT card and
Accesses and aisle ways are kept communicated to all involved
free of obstacles. parties during Tool Box Talks.
Good housekeeping and material If weather conditions change
stacking is ensured in operational during the task, then a decision
areas and overhead elevated must be made as to whether to
works. Loose objects are secured carry on with the survey.
to prevent falling from higher
elevation.
Weather conditions have been
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
serious 2,3,4,6, 20,21 place to avoid causing visual pick up and drop off points.
injuries. and 22 obstructions for intersections, Ensure adequate lighting is
and others as driveways or pedestrians. available at all times.
applicable Considered authorizing any Ensure that any lighting does not
supervision of unloading to a reflect on the driver causing
specific employee. blind vision.
Segregated vehicles and Ensure no-one can access area
pedestrians as reasonably during loading and unloading
practicable. activity.
Appointed competent banksman / Strict disciplinary action will be
flagman are assigned for traffic taken for traffic speed offenders.
control. Further Action Needed /
Ensured all workers are properly Additional Control Measures to
trained and supervised. be decided after site assessment
Speed limit adherence i.e. or vehicle inspection by the
15km/h. concerned sub-contractor or
Receiving of raw materials are security.
stored in designated / isolated Suitable ladder shall be provided
places. to climb over the flatbed trailer
Reverse alarm is fitted in all or loaded vehicle.
vehicles and Equipment’s
Ensured The working area is
barricaded off with rope / warning
tapes.
Lashing belts are used for
securing load to prevent it from
moving or falling off the vehicle.
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Task No.:03- Use of Lifting Equipment -Tower Crane / Mobile Crane /Crawler crane for shifting, erecting/retrieving, positioning and storage of various precast elements & pane
(columns, beams, walls, slabs, staircases.).
Fall of Precast Fall of Site Workers DM 2 10 5 100 Use of mobile phone is 2 10 1 2
elements load may Site Staff. Construction Planning involves inspection of prohibited while operation.
code of the site, consultation with all
(columns, cause Ensure crane operator is
practice. persons involved in the work
beams, walls, serious medically fit with emphasis on
Chapters such as lifting supervisor, site
slabs, staircases) injuries/ eyesight, hearing and speaking.
2,4,6,7, 21 & engineer/supervisor and safety
during mobile fatalities, supervisors. Lifting lugs should be rechecked
crane operation property 22 and others by lifting supervisor/site
because of damage as applicable. Operators are competent having engineer to ensure the object is
RTA/Dubai required UAE license, third
Operator/Human and other safe for lifting.
Traffic Police party certificates and ensured
error or delays or
medically fit to perform crane Attached prop jack should be
negligence or hindrances & EIAC secured to avoid the touch with
guidelines operations.
Failure of to the nearby structure.
Lifting Operation Safety
controls and/or operation Supervisor should make sure
Procedural requirements are
mechanical parts Overturnin that no lose concrete debris are
followed by lifting supervisor on
of plant. g of crane. stuck with any element before
field.
Wrong lifting.
PTW and other relevant
positioning of Check all safety and warning
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Mobile/Crawler devices.
documents are in place.
crane or Operator shall not operate the
Conducted STARRT card/TBT
inadequate crane if he is tired or cannot
prior to start activity.
ground concentrate on the job.
conditions Equipment’s inspected and Lifting supervisor shall always
certified by DM approved 3rd be alert and watch that the boom
party. or the suspended load does not
collide with people or buildings
Exclusion zone is set up around and the load does not collide
the crane operational areas and with the boom.
provided warning & safety
Operator shall read the
information signs.
Operators Manual & Risk
No other works are executed Assessment thoroughly for
near to the crane operational familiarizing with all controls
area. before they start operating the
The area foreman ensures that crane.
the required control measures Crane must not be assembled or
are adhered too. use a crane unless ground
Personnel advised of trapping conditions are firm, drained, and
hazards and hazards of falling graded to a sufficient extent so
objects, i.e. no personnel are that, in conjunction (if
allowed to walk under or near necessary) with the use of
swinging loads. supporting materials (such as
Sufficient Banksmen are blocking, mats, cribbing, or
deployed adjacent to the lifting marsh buggies (in
operation/unloading area to marshes/wetlands), the
restrict unnecessary movement equipment manufacturer's
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
crane operations are ongoing.
Personnel advised of trapping
hazards and hazards of falling
objects, i.e. no personnel are
below the moving loads.
Banks man/rigger are mobilized
adjacent to lifting
operation/unloading area to
restrict unnecessary movement
of pedestrians, Use
whistle/mega phone to warn
people.
Isolation of working radius of
the crane. Stabilizing and set-up
of the mobile crane.
Cranes, wherever possible to be
sited at a minimum distance of
1.5m to 2.5 from fixed objects to
avoid contact and collision.
Possible pinch Hand and Riggers DM 2 5 5 50 STARRT card briefing and TBT 2 5 1 1
Erection Construction Used mechanical bars in
points while finger shall be conducted before
Crew. code of pushing and retrieving wooden
handling precast crushing carrying out the task.
Foreman practice. dunnage to avoid finger
units or inserting injuries Supervisor will check the PPE
chapters 2, 4 trapping/ crushing injuries.
wooden dunnage. and other resources before the
and others as Operatives are advised not to
task begins.
applicable place hands/fingers under
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
suspended load.
No one is allowed to stay
between the elements while
stacking and placing precast.
Operatives wearing suitable
heavy rigging gloves while
handling the load.
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Contact with grout Skin Masons and DM 2 5 5 50 Workers Occupation check shall 2 5 1 1
Repair crew. Construction COSHH assessment conducted
or sealant and allergies. be carrying as per DHA required
Code of safety for chemicals before
concrete while Respirator or work exposed to hazardous
Practice. commencing to work as per SDS
handling grouting y allergies chemical and fumes.
CHAPTER 10 information.
materials Environme Wash effected skin with water
& 18 Avoided skin contact with grout.
ntal and seek for medical attention.
Concrete and Chemicals stored adequately to
Pollution. prevent ground contamination. Eye wash station shall be
Masonry available nearby in case of eye
Spills cleaned off immediately.
Waste to be disposed as per the contact. Wash accidental
site requirements. splashes with clean water
Supervisor monitoring is immediately.
ensured.
Conducted TBT to all crew
before commencing to work.
Suitable PPE.s worn /used by
operatives such as rubber
gloves, chemical masks etc, Do
not inhale dust/ fumes while
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Task No: 6: Use of electrical appliances and power tools such as grinding / Cutting Machine, Drilling Machine, screwdriver pan and grout mixer etc.
Use of power tools Personal Site Workers DM Code of 2 5 1 10
Untrained workers are not
by Inexperienced or Injuries Erection construction
allowed to use the power
incompetent person Property Crew safety Practice
operated tools.
Damage Mason CHAPTER 14
In-house training and required
Hand and
training are conducted about
power
power tools operations.
Operated tools.
All hand and power-operated
tools are maintained in safe
operating condition and are used
only for the purpose for which
they are designed.
Every person who supplies,
lease or maintain any industrial
machinery, equipment or tools
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Cutting & Grinding Eye and Site Workers DM Code of 2 5 5 50 Competent person shall be 2 5 1 1
Obtained a permit prior to
Operations: Disc body Erection construction assigned to the mounting, care,
perform steel cutting and ensure
bursting due to disc injuries Crew safety Practice and inspection of abrasive
all required control measures
fitted incorrectly, Repair CHAPTER 14 wheels and grinding machines.
and precautions as per permit to
wrong disc fitted / Mason Hand and Manuals and operating
work system are observed. Area
used for purpose power instructions for the grinding
are free from any combustible
Operated tools. machine shall be made available
materials.
Ensured the Operator undergo to all workers.
related training. Check the manufacturing date on
Guards fitted in good order and the grindstone label; dispose of
do not remove guard in any expired ones.
circumstances. A grinding machine shall be
The cutting disk is fixed provided with protective hoods
properly and used as per the that enclose the wheel (as close
manufacture requirements. to the wheel as the work will
A grinding machine is inspected permit); transparent guards still
for defects prior to mounting (by enable the operator to see what
conducting a ring test), and is going on.
mounted in accordance with the Make sure that electrical
manufacturer’s specifications equipment is properly grounded
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
and certified.
(wheel properly mounted
Report any defects or poor safety
between flanges; guard(s)
conditions to your supervisor as
securely in place etc.).
soon as possible.
All rotating motor components
are enclosed with adequate
guarding materials.
Do not use excess force on
power tools.
Checked condition of lead and
plug before use.
Used 110v or battery tools or
RCD where practicable.
All workers operating a grinding
machine wear the appropriate
personal protective equipment
relevant to the particular hazards
(safety glasses, face shield,
respirator, hearing protection
etc.)
Using Damaged Electrocuti Site Workers DM Code of 2 5 5 50 All hand tools and power tools 2 5 1 1
Power tools are well maintained
Power tool machine on/ Shock. Erection construction are tethered while working at
– if damaged / faulty they are to
or incorrect disc, Injury Crew safety Practice height.
be tagged immediately and
flying objects, Mason CHAPTER 14 Disconnect before adjusting and
repaired without delay.
entanglement Hand and fixing drill bits on the machine.
Maintained handheld power
power The drill bits are the right type
tools with approved spare parts
Operated tools. for the material to be drilled and
and fittings including electrical
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Task No.7: Work at Height (Aluminum Scaffolds, Mobile Elevated Work Platforms/MEWPs and ladder if required )
Unsafe working Serious Erection DM 2 5 5 50 Approved lifeline shall be 2 5 1 1
Workers are competent and
practice may cause personal Crew/rigger Construction provided while working height.
supervised by engineer.
workers to fall from Injuries and Code of safety No work shall be allowed on
A safe /Suitable access
height/ Unsafe due to fall supervisors Practice. scaffolds working on extreme
(scaffolds/ man lift) is provided
leading edges. from 4-3-2 weather condition.
for grouting and sealant work.
. elevated Scaffolds, Site rules and other working at
(If required to work at height).
platforms. Platforms. height safety precautions are
Inspected and green tag
Gangways, and briefed during tool box talks.
scaffolds used for work at
Fall Prevention
height.
Avoided overloading the
platform.
While working on Scaffolds,
working platform is ensured free
of concrete debris or any
unwanted waste /materials.
All workers and staff have
received work at height training
before commencing to work.
Full body harness is worn and
hooked in retractable fall
arrestor, lifeline or suitable
anchorage point while working
at height.
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
accordingly.
While extending platform and
Ensure the relevant maintenance
moving up looked for overhead
and service records of the
objects.
MEWP are up to date and
Only IPAF competent operator
available upon request from the
to use for MEWP Operation.
rental company.
The hazards and risks associated
to job is well communicated MEWPs should be stored in a
with erection and repair crew. secure compound or in a
MEWP movements are designated area with the keys
controlled by Flagman to avoid removed.
collision and contact with other The brakes should be fully
objects. operational and in use and the
MEWP are inspected and working platform lowered into
maintained properly. the parked position.
Pre-operational check is Identify the presence of
conducted by competent person. personnel (authorized or
Barricaded around area and unauthorized) and other mobile
warning signs to be displayed. equipment.
Worn Full body harness and
hooked it while work at height
(scaffolds, elevating platform
and loading/offloading precast
elements.
Untrained workers are not
allowed to use MEWP.
Trained flagman and rigger are
assigned for the safe use of
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
MEWP Operation.
Exclusion zone is maintained
and work sign are displayed.
Max weight capacity is marked
on platform.
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Stress activity.
developed and implemented.
Daily equipment check list to be
Nominated person responsible
filled prior to start.
per shift ensured that all lighting
is compliant. Hard barricade with reflective
Tower lights are set up properly warning tape must be provided
so the light beam shines demonstrating the closed access.
downwards to avoid any Clear glass must be worn at all
nuisance to other stakeholders / times.
members of the public. Tool Box Talk to highlight the
Used manned access/pedestrian hazards when working in poor
access way only. light and during darkness.
Hard Barricaded the hazardous First aider and First Aid kit are
area adequately. made available at site.
Adequate reflective safety Standby Vehicle to be available
signs/Electronic form of safety at all times near work spot for
signs have been displayed. any emergency.
Precautions are taken about the Emergency response procedure
presence of dangerous desert to be communicated to all
reptiles, flora and fauna. workmen.
All the workers and staff know
about the assembly point and
emergency escape route.
Roaster duties are put in place.
Continuous night shift works are
prohibited.
Mandatory PPEs are used during
DUBAI ELECTRICITY AND WATER AUTHORITY
Health and Safety Risk Assessment Form
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
the activity.
Lone working is prohibited.
Only allowed works in groups.
Frequent break for workers who
work additional work hours.
Name: Raveendran Pillai/Khaled Name: Syed Qaisar/ Islam Satey Name: Hazem Abdin
Safety Inspector/Site Engineer HSE Manager/Project Manager Projects Manager
Date: 28 April 2020 Date: 28 April 2020 Date: 28 April 2020
Signature: Signature: Signature:
Project Name. Aweer Power Station "H" Phase IV Assessment Date: 28-04-2020
Activity/Area/Equipment: Erection of Precast Elements at BOP Building / as Listed in MS Ref. No.: 3761800008-R-01-C-E-69047_A
Assessor(s): Raveendran Pillai (Safety Officer), Khalid Jalghoum (Site Engineer) Rev. No.: A Date: 28-04-2020
Reviewed By: Islam Satey (Project Manager) & Syed Qaisar (HSE Manager) Next Rev. Date: 28-10-2020
SP06 : Annexure III B
Likelihood
Likelihood
Hazard Person(s) at
Severity
Severity
Number
Number
HAZARDS To be mechanism from hierarchy of mechanism from hierarchy of
Risk
Effect risk
complied control for each identified hazard control for each identified hazard
(Yes/No)
Up to 20 Risk is low
21-50 Risk is medium & additional control measures required to control the risk
51-100 Risk is high & unacceptable
100+ Risk is totally unaccepted