Professional Documents
Culture Documents
1 of 19
- SDCC : Original
- All Div. : Copy
- All Dept. : Copy
EFFECTIV
REV. NO ISSUED DATE BRIEF OF REVISION
E DATE
0 08 Nov 2022 08 Nov For Review and Approval
2022
TABLE OF CONTENT
COVER PAGE 1 OF 19
TABLE OF CONTENT 2 OF 19
1.0 TITLE 3 OF 19
2.0 SCOPE 3 OF 19
3.0 REFERENCE 3 OF 19
6.0 FABRICATION 4 OF 19
11.0 ATTACHMENTS 17 OF 19
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
1. TITLE
2. SCOPE
2.1 This procedure covers the general requirements for the CW piping
construction works which consist of fabrication, assembling and erection
for CW piping work at Smelting Project Gresik.
2.2 This procedure supplements or modifies to the requirement of ASME B31.3
“ Process Piping” for the piping system and Project Specification from
Linde, where applied
3. REFERENCES
3.1 Code and Standard
3.2.1. ASME Sect IX : Qualification Standard for Welding and Brazing, and
fusing Procedures; Welders; Brazers; and Welding and Brazing
Fusing Operators.
3.2.2. ASME Sect. II : Material Specification
3.2.3. ASME B31.3 : Piping Process
5. GENERAL REQUIREMENT
5.1. QUALIFICATION
5.1.1. Persons who are engaged for welding including tack welding and
support welding shall pass the qualification test as per procedure.
5.1.2. All welding works shall be performed in accordance with the
Approved Welding Procedure Specification supported with
Procedure Qualification Record.
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
5.1.3. Persons who are engaged for alignment, assembling, erection, etc.
shall be fully trained and shall have the qualification of Sub-
Contractor.
5.2. MATERIAL
5.2.1. All piping material shall be in accordance with project specification
or code & standard ASME Sect. II to be followed.
5.2.2. Temporary support are not to be tack welded to the pipe walls. In
cases where this is unavoidable the tack area is to be repaired and
check Visual.
5.2.3. All welding consumables selection shall be in accordance with
drawing and approved Welding Procedures. Consumables are to be
segregated as to type and are to be stored as the manufacturer
recommendation. The mill certificate of welding electrode shall be
filed and documented.
6. FABRICATION
6.1. GENERAL
6.1.1. Stainless steel or High alloy steel fabrication work shall be separated
from low alloy and carbon steel fabrication work.
6.1.2. Tools and equipment used in stainless steel fabrication shall be lined
by using suitable with stainless steel material (not affect the
properties) and not used on other than stainless steel fabrication.
6.1.3. The bolt holes of flanges shall be located symmetrically from a
vertical center line in a horizontal pipe line, and from plant north in
a vertical pipe line unless otherwise indicated in the drawing.
6.1.4. Piping materials shall be color-coded in accordance with the
procedure or project specification.
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
6.2. CUTTING
To mention all information 6.2.1. All of cuts are to be remarked as per procedure or project
about material preparation
stage before point 6.2 specification
Cutting
6.2.2. The schedule and heat number are to be transferred to all off cuts.
6.2.3. In case of gas cutting, cutting surface shall be ground off to remove
any edge and roughness and be made flush and smooth so as not
to harm welding quality. The angles of preparations shall be within
the code tolerances or welding procedure specification. In case of
unequal thickness there are to be no angle deviations around off
cut.
6.2.4. If pipe is cut using the oxy acetylene process all cut edges are to be
ground back to remove any drag lines or imperfections.
6.2.5. Abrasive disc used for cutting and grinding of austenitic stainless
steels or other high Cr-Ni steel shall be iron free.
6.2.6. Plasma arc cutting may be applied for stainless steel. After cutting
to add dimension control Check by plasma cutting, the cut edges are to be ground back to remove
and report after cutting Pipes
base on spool shop drawing
burnt areas and imperfections.
6.3.1. End preparation for groove weld specified in ASME B16.25 or any
other end preparation which meets the Welding Procedure
Specification are acceptable.
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
6.3.2. If piping component ends are bored, such boring shall not result in
the finished wall thickness after welding less than the minimum
design thickness.
6.3.3. If the piping component ends are upset, they may be bored to allow
for a completely recessed backing ring, provided the remaining net
thickness of the finished ends is not less than the minimum design
thickness.
6.3.4. Preparation of brand connection shall follow to Fig. 328.4.4. (ASME
B31.3) To Add Preparation of
Reinforcement Pad Works
(fit up, and Welding)
Surfaces for welding shall be clean and shall be free from paint, oil, rust,
scale, or other material which is detrimental to welding.
The root opening of the joint shall be given in the Welding Procedure
Specification.
6.7.2. The limits above shall also apply to all flanged joints made
with nonductile materials (for example, cast iron and
glass).
6.7.3. The lateral translation of flanges in any direction from the
specified location shall not exceed 1/16 in. (1.5 mm).
6.7.4. For all pipe sizes, the tolerances on linear dimensions shall
not exceed 1/8 in. (3 mm). Tolerances shall not be
cumulative
In assembly of the joint before welding, the pipe shall be inserted into the
socket to the maximum depth and then withdrawn approximately 1/16
inch up to ¼ inch. (1.5 mm – 6 mm) away from contact between the end
of the pipe and the shoulder of the socket (See Fig. 328.5.2B). In sleeve
type joints without internal shoulder, there shall be a distance of
approximately 1/16 in. (1.6 mm) between the butting ends of the pipe.
Fig. 328.5.2B Typical Details for Double-Welded Slip-On and Socket Welding Flange Attachment
Welds
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
6.9. PREHEATING
6.9.1. Preheating, if required shall be in accordance with approved
WPS
6.9.2. Preheating temperatures are to be controlled using temperature
crayons or digital temperature.
6.9.3. Preheat shall be uniform and involve the entire weld preparation.
When electric resistance heaters are used, they shall be covered
with a minimum of 1 inch (25 mm) of insulation. Preheat shall
be verified with either thermocouples or temperature-indicating
crayons (for example, Temp sticks).
6.10. WELDING
6.10.1. GENERAL REQUIREMENT
6.10.1.1. Circumferential butt-welding shall be performed
without the use of backing ring. Back shielding with
argon gas shall be required according to the WPS.
6.10.1.2. The maximum inter-pass temperature shall be in
accordance with the approved WPS/PQR
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
to Add Paragraph Number for Leak Testing for Reinforcement Pad after
NDT
Where Paragraph for NDT
Activity and NDT
Requirements
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
7.1. GENERAL
7.1.1. Fit-up tolerances shall be kept as per WPS or project
specification.
7.1.2. If hot work to be performed in the vicinity of instrument control
or power cable duct, an adequate protective cover shall be
provided in advance so as not to damage the cables.
7.1.3. When work is carried out in the vicinity of piping made of, or
lined with special materials such as plastics, rubber, glass, etc.
care shall be taken so as not to damage them.
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
7.2.11. NOTE
(1) following system hydrostatic, this is the minimum acceptable
torque for a flanged joint containing a spiral wound gasket.
(2) Recommended minimum for ASTM A 193 B7M stud Bolts.
(3) Recommended minimum for ASTM A 193 B stud Bolts.
(4) Recommended minimum for ASTM A 193 B7 bolts in system
operating at temperature of 500oF or higher.
(5) The torque data is based upon the nut bearing surfaces
being in good condition and the bolt threads and nut bearing
surfaces being well lubricated.
DOCUMENT NO. :
PIPING FABRICATION AND ERECTION P-T5116-QC-07
ISSUED DATE :
PROCEDURE 08 Nov 2022
Prior, during, and after completion of the work of piping system , the inspection
and test shall be performed in accordance with procedure, inspection & test
plan (ITP) or project specification.
All flushing works (Water, Air Blowing, Hand Cleaning, Chemical Cleaning)
shall be follow to Procedure or project specification.
All painting and wrapping works shall be performed as per procedure or project
specification
11. ATTACHMENTS
ATTACHMENT 1