Professional Documents
Culture Documents
(ii) The specific clearance between power and telcom lines, earth wires and earth-structures are
to be adhered to. The minimum clearance between lines of various voltages to be maintained are
as follows :
(iii) Guardians are to be provided at crossings of telecom lines with power lines upto 33 KV.
(iv) Maximum value of induced electromagnetic volt - 250 volts (faults duration equal to or less than
200 ms.)
(v) Maximum value of induced noise (noise interference) -200 microvolts. (to be taken congnizance
if noise is persistent)
EHV - SUB-STATION
v SUB-STATION PLANNING CRITERIA
v The maximum fault level on any new Sub-Station Bus should not exceed 80% of the rated
rupturing capacity of the Circuit Breaker. The 20% margin is intended to take care of the increase
in short circuit level as the system grows. The rate of breaking current and making currnt including
fault clearing time capability of Switch-gear at different voltage levels may be taken as :-
Fault cleaning Voltage Operating Breaking Acking
Time level Time current current
v A stuck breaker condition shall not cause disruption of more-than four feeders for 220 KV.
system and Two Feeders for 400 KV. system and one Feeder for 765 KV. system.
65
Please purchase PDFcamp Printer on http://www.verypdf.com/ to remove this watermark.
EHV SUB-STATION
SYSTEM REQUIREMENT
Sl No. Description of Technical Parameter Unit System
66
Please purchase PDFcamp Printer on http://www.verypdf.com/ to remove this watermark.
STUDY ON SUB-STATIONS
1. Nomenclature 2. General
Reliability : Substations or switching stations are integral part of
The reliability of a power system means supply of the transmission system, and function as a connection or
uninterrupted power at the specified voltage and frequency. switching point for transmission lines, sub-transmission
feeders, generating circuits and step-up and step -down
The reliability of a substation depends on the reliability transformers Substations of voltages 66 KV to 40KV are
of associated equipment such as busbars, circuit breakers, termed as EHV sub-stations. Above 500KV, they come under
transformers, isolators and controlling devices. the terminology of UHV system.
Failure Rate : The design considerations and procedures are almost
It is the average number of failures per year. the same for the sub-stations in the EHV range except that
Outage time : certain factors become predominant at different voltage levels.
It is the time taken to repair the failed component or Switching surges are very important at 345 KV and above,
restore supply from an alternative source by switching. whereas it can be safely neglected upto 220 KV level.
Switching time 3. Design Criteria and Studies.
It is the time taken from the initiation of outage to The following studies are to be performed to establish
restoration of service by switching action. the design criteria for a substation.
Switching scheme 1. Load flow studies
It is the type of arrangement of bus bars and The purpose of a substation is to provide a path for
equipments considering cost, flexibility of operation and reliable delivery of power to system loads. Load flow studies
reliability of the system. establish the current carrying requirements of the new
substation or switching station, when all lines are in and
Phase to ground clearance
when selected lines are out for maintenance. After studying
The phase to ground clearance in a substation are, (a) a number of load flow cases, the continues and emergency
distance between the conductor and the structures. (b) ratings required for various equipment can be determined.
distance between the live parts of the equipment and structures
2. Short circuit studies.
and (c) distance between the live conductor and ground.
In addition to the continuous current ratings, the
Phase to phase clearance
substation equipment must have short time ratings,. These
The phase to phase clearances in a substation are (a) must be adequate to permit the equipment to sustain, without
distance between the live conductors (b) distance between damage, the severe thermal and mechanical stresses of short
the live conductors and apparatus and (c) distance between circuit currents. In order to provide adequate interrupting
the live terminals in equipment like, circuit breakers, isolators capability in the breakers, strength in post insulators and
etc. appropriate setting for protective relays, which sense the
Ground clearance fault, the maximum and minimum short circuit currents which
will flow for various types and locations of short circuits and
It is defined as the minimum clearance from any point, where a for different system configuration must be established.
person may be required to stand, to the nearest part (which is
3. Transient Stability Studies.
not at earth potential) of an insulator supporting the live
conductor. Under normal conditions, the mechanical input to a
generator will be equal to the electrical output plus generator
Sectional Clearance losses. So long as this is continues, the system generators
It is defined as the minimum clearance from any point, rotate at 50 Hz. If this balance is destroyed by upsetting either
where a person may be required to stand, to the nearest the mechanical or the electrical flow, the generator speed
unscreened live conductor. The basis for fixing the sectional deviates from 50Hz. and begins to oscillate about a new
clearance is to take the height of a man with stretched hands equilibrium point.
plus the phase to ground clearance. The most common disturbance is a short circuit. When
Safety Clearance a short circuit occurs close to the generator, the terminal
voltage drops and the machine accelerates. When the fault is
This comprises of ground clearance and sectional cleared, the unit will try to revert to its original state by feeding
clearance. the excess energy into the power system. If the electrical ties
Electro static Field in Substations are strong, the machine will quickly decelerate and became
An energised conductor or metallic part of the stable. If the ties are weak, the machine will become unstable.
equipment produces electrostatic field. The magnitude of the The factors which affect the stability are
electrostatic field varies at different points in an EHV sub- i. Severity of the fault.
station (above 400 KV), depending on the geometry of ii. Speed with which the fault is cleared.
energised conductor/metallic part and the nearby earthed
iii. Ties between the machine and the system after the
object or ground. fault is cleared.
67
Please purchase PDFcamp Printer on http://www.verypdf.com/ to remove this watermark.
The aspects of transient stability that are important in (iv) Ability to limit short circuit levels
substation design are, (a) the type and speed of the line and Any arrangement which incorporates means of
bus protection relaying, (b) the interrupting time of the breaker providing a substation into two separate sections either
and (c) the bus configuration after the fault has been cleared. completely or through reactor coupling, is suitable for limiting
The last point has a considerable bearing on the bus short circuit levels. By careful use of circuit breakers in ring
arrangement. If a fault is cleared in the primary relaying time, system, a similar facility can be provided.
only one line will be lost. If the fault is cleared in breaker failure (v) Maintenance facilities
relaying time, owing to a stuck breaker, more than one line
During the operation of the substation, maintenance
may be lost which will weaken the tie to the system.
will have to be carried out, either planned or emergency. The
4. Transient over-voltage studies. performance of the substation during maintenance is also
Transient overvoltage may be due to lightning stroke dependent on the protection arrangements.
or circuit switching . The most reliable means to establish (vi) Ease of extension
switching over voltage is through the use of a Transient
The substation arrangement shall be such that
Network Analyser (TNA) study.
extension of bays for new feeders are possible. As the system
4. Substation Arrangement expands, there may be need to convert a single bus
The substation arrangement depends on physical and arrangement to double bus system, or to expand a mesh
electrical aspects and is influenced by the following factors. station to a double bus station. There shall be space and
(i) System Security. expansion facilities.
The ideal sub-station is one were each circuit is (vii) Site considerations
controlled by a separate breaker with facilities for replacement The availability of site plays an important role in
of bus-bar or breaker in the event of a fault or during planning the substations. When the areas is limited, a station
maintenance. System security may be specified, based on with less flexibility may have to be constructed. The substation
whether complete reliance on the integrity of the substation which are simple in diagram and use least number of breakers
or a percentage of outage due to periodic faults or maintenance occupy the least site.
is permissible. (vii) Economy
Double bus-bar system with double breaker A better switching arrangement on technical
arrangement comes to near ideal, but the cost of such a requirements can be constructed, if the economics are
substation is prohibitively high. reasonable.
(ii) Operational flexibility 5. Substation Layout and Switching arrangement.
For the efficient loading of the generators it is A number of factors are to be considered while
necessary to control the MVA and MVAR loading under all finalizing the layout and switching arrangements of an EHV
conditions of circuit connections. The grouping of load circuits substation. It must be reliable, safe and must provide a high
requires to be capable of being arranged to give the best level of service continuity.
control under normal and emergency conditions.
Normally used substation schemes are detailed below.
(iii) Simplicity of protection arrangements
1. Single Bus arrangement
If more than one circuit is to be controlled from one
This arrangement is a simple scheme adopted in less
circuit breaker or greater number of circuit breakers are to be
important substations. A breaker or bus failure can cause
tripped during fault conditions, the protection arrangements
total outage. By providing a bus sectionalism scheme, this
are complex. The most advantageous arrangement is single
can be overcome to some extent. Even though the protective
bus-bar with no sectionalising. Ring bus arrangement where
relaying is simple, single bus scheme is inflexible (Fig. 1)
each circuit breaker can be in two zones of protection, causes
for complex protection scheme.
Sectionaliser
LA
Trans
E.Sw
PT
Feeder
68
2. Main and Transfer Bus breaker relaying must be so arranged to protect the
A transfer bus is added to the single bus scheme. transmission line or transformer, if the protective relays
An extra bus-tie breaker is provided to tie the main and also are not transferred. As the relaying selectivity is
transfer buses together. poor this scheme is considered as unsatisfactory. Failure
of the main bus can cause for total outage of the
When a circuit breaker is in maintenance, the bus-
substation (Fig-2)
tie breaker can be used for energising the circuit . Bus-tie
Ttrans
MAIN BUS
BI
CT
CB
LI
LA E.Sw
LA
PT BI
TRANSFER BUS
Feeder Feeder
Feeder
3. Double Bus, Single Breaker The circuit may operate all from one bus, of half of
This is superior to the single bus and main and transfer the circuit connected in each bus. For a bus fault, only half
bus schemes. There are two main buses and each circuit can the no. of circuits will be lost. In some cases the tie breaker is
be connected to either of the buses by bus isolators. A bus-tie permanently closed and both the buses stand connected. A
breaker connects the two main buses when closed allows bus protection scheme will be necessary for opening the tie
the transfer of a circuit from one bus to the other without a breaker in the event of a bus fault.
break in supply (Fig.3) Possibility of operator error is more as two bus
isolators are involved for every circuit.
BUS 1
BUS 2
BI
CT
CB
LI
Bus
E.Sw Coupler
PT
Trans
LA Feeder
Fig. 3. Double Bus Arrangement
69
4. Double bus, Double breaker Arrangement breakers for every circuit. The use of two circuit breakers per
This scheme involves two main buses and two circuit circuit makes the arrangement very expensive, but this provides
a very high order of reliability (Fig.4)
BUS 1
BI
CT
CB
Feeder
LA
ESW
PT BI
Trans
BUS 2
Fig. 4. Double Bus, Double Breaker Arrangement
BUS 1
BI Line
CB LA
CT
PT
ESW
Trans
Trans
BUS 2
Fig. 5. Breaker and A Half Scheme
70
6. Ring Bus arrangement During a breaker maintenance, the ring is broken,
In this scheme (Fig-7) the breakers are arranged in a but the service is fully maintained. The circuits are generally
ring with circuits connected between the breakers. There arranged such that sources and loads are alternated.
are some number of breakers as the number of circuits. For a Where five or six circuits are to be provided, ring
circuit fault, two breakers are tripped. In the event of a breaker bus arrangement is ideal. This scheme is economical and
failure during a line fault, an additional breaker trips as backup provide good reliability, safety and flexibility. Protective
protection. In that case an additional feeder will also be out of relaying and automatic reclosing schemes are complex in
service. the case of ring bus arrangement.
Feeder
LA Trans
ESW PT
BI
CT
Fig. 6. Ring Bus
CB
LI
Trans
ESW
Feeder LA
7. Other Layout Designs bus with bypass arrangement. These arrangements are
In additional to the above mentioned common bus mostly used in gas filled substations where more flexibility is
arrangements, some other layouts are also employed. They ensured.
are (i) Double bus arrangement with transfer bus (ii) Triple Simple schematics are as given below. All equipment
bus arrangement (iii) Double bus with bypass and (iv) Triple are not shown.
BUS 1
BUS 2
TRANSFER BUS
CT
CB
Feeder Coupler
Fig. 7. Double Bus with Transfer Bus
71
7. Switchyard Structures and (vii) Impact load, if any, during operation of equipment.
Structures are required to support and install buses, The substation gantry structures shall be designed
electrical equipment and to terminate transmission line to terminate the overhead line download span. Which may
conductors. The structures may be of steel, wood, RCC or enter + 30 degrees horizontally and +15 degrees vertically.
PSC. They need foundations according to the soil conditions The yard structures may be hot dip galvanized or
of the side. Generally, fabricated steel structures are used in painted. Galvanized structures require less maintenance. But
the substations due to various advantages. The design of the in some highly polluted locations, painted structures provided
structures is affected by the phase clearance, ground more corrosion resistance.
clearance, types of insulators, length and weight of buses
Normally adopted phase spacings
and other equipment.
11 KV 1.3 m
Steel beams and girders shall be designed to prevent
failure by bending, flange buckling vertical and horizontal shear 33 KV 1.5 m
and web crippling. The depth of the lattice box girders shall be 66 KV 2.0 to 2.2 m
about 1/10 to 1/15 of the span and square in section. Maximum 110 KV 2.4 to 3 m
beam defluxion shall not normally exceed 1/250 of the span
220 KV 4.5 m
length. All bolts and nuts for structures shall be not less than
400 KV 7.0 m
16 mm diameter, except in light loaded section, where they
may be 12 mm dia. 8. Bus Design
The design load on columns and girders shall include The present day trend is to use rigid bus rather than
(i) Conductor tension (ii) Earth wire tension (iii) Wt. of insulators strain bus due to various reasons. Rigid bus can be constructed
and hardwares (iv) Fraction load (about 350 kg) (v) Weight of at a lower profile and are aesthetically pleasing. Increased capacity
man & tools to works on them (about 200 kg) (vi) Wind load for the bus can be provided and corona level is lower.
72
Please purchase PDFcamp Printer on http://www.verypdf.com/ to remove this watermark.
8.3 Vibration 2
43.2.I
sc
A span of rigid bus has a natural frequency expressed f =
7
as follows : 10 ( D)
73
Please purchase PDFcamp Printer on http://www.verypdf.com/ to remove this watermark.
For a 3 phase fault, the maximum instantaneous 8.8 Substation Bus Accessories
Where bundled conductors are used in strain bus, the Line termination 2000 1000 1000
Main Bus/Sub Bus 1000 900 800
types of spacers used may have an influence on the resulting
Interconnections
tension. If rigid spacers are used, then during short circuit, 1000 900 800
between yards
the two conductors will attempt to draw together and can Earth wire 800 600 600
cause for increase tension in the strain bus.
74