Professional Documents
Culture Documents
0-1
August 2013
Sheet 01 001
Power Distribution
Systems
Contents i
Power Distribution Systems Suggested Ground
System Design Fault Settings . . . . . . . . . . . . . 1.4-6 ii
Basic Principles. . . . . . . . . . . 1.1-1 Grounding/Ground Fault Protection
Modern Electric Power Grounding—Equipment,
Technologies . . . . . . . . . . . 1.1-1 System, MV System, 1
Goals of System Design . . . 1.1-2 LV System . . . . . . . . . . . . . . 1.4-9
Voltage Classifications; BILs— Ground Fault Protection . . . . 1.4-11
Basic Impulse Levels . . . . . 1.1-4 Lightning and Surge 2
Three-Phase Transformer Protection . . . . . . . . . . . . . . 1.4-14
Winding Connections . . . . 1.1-5 Grounding Electrodes. . . . . . 1.4-14
Types of Systems—Radial, MV Equipment Surge 3
Loop, Selective, Two-Source, Protection Considerations . 1.4-14
Sparing Transformer, Spot Surge Protection . . . . . . . . . . 1.4-14
Network, Distribution . . . . 1.1-6 Types of Surge
4
Health Care Facility Protection Devices . . . . . . . 1.4-15
Design Considerations . . . 1.1-14 Power Quality 5
Generator Systems . . . . . . 1.1-17 Terms, Technical Overview . . 1.4-18
Generator System Design SPD. . . . . . . . . . . . . . . . . . . . . 1.4-19
Types of Generators . . . . . . . 1.2-1 Harmonics and 6
Generator Systems . . . . . . . 1.2-2 Nonlinear Loads . . . . . . . . . 1.4-21
Generator Grounding. . . . . . 1.2-3 UPS . . . . . . . . . . . . . . . . . . . . 1.4-25
Generator Controls. . . . . . . . 1.2-4 Other Application Considerations
7
Generator Short-Circuit Secondary Voltage . . . . . . . . 1.4-31
Characteristics . . . . . . . . . . 1.2-4
Generator Protection . . . . . . 1.2-5
Energy Conservation . . . . . . 1.4-32 8
Building Control Systems . . 1.4-33
System Analysis Distributed Energy
Systems Analysis . . . . . . . . . 1.3-1 Resources . . . . . . . . . . . . . . 1.4-33 9
Short-Circuit Currents . . . . . 1.3-2 Cogeneration. . . . . . . . . . . . . 1.4-33
Fault Current Waveform PV System Design
Relationships . . . . . . . . . . . 1.3-3 Considerations . . . . . . . . . . 1.4-34 10
Fault Current Calculations Emergency Power. . . . . . . . . 1.4-35
and Methods Index . . . . . . 1.3-4 Peak Shaving. . . . . . . . . . . . . 1.4-36
Determine X and R from 11
Sound Levels. . . . . . . . . . . . . 1.4-36
Transformer Loss Data . . . 1.3-19
Reference Data
Voltage Drop
Considerations . . . . . . . . . . 1.3-20
IEEE Protective Relay 12
Numbers . . . . . . . . . . . . . . . 1.5-1
System Application Considerations
Codes and Standards . . . . . . 1.5-6
Capacitors and
Motor Protective 13
Power Factor . . . . . . . . . . . 1.4-1
Device Data . . . . . . . . . . . . . 1.5-7
Overcurrent Protection Chart of Short-Circuit
and Coordination . . . . . . . . 1.4-3 Currents for Transformers . . 1.5-9 14
Protection of Conductors . . . 1.4-5 Transformer Full Load
Circuit Breaker Cable Amperes . . . . . . . . . . . . . . . 1.5-10
Temperature Ratings . . . . . 1.4-5 Impedances Data . . . . . . . . . 1.5-11
15
Zone Selective Interlocking . 1.4-5 Transformer Losses,
Ground Fault Protection . . . 1.4-6 TP-1 Losses . . . . . . . . . . . . . 1.5-12 16
Power Equipment Losses . . . 1.5-13
NEMA Enclosure Definitions . . 1.5-13
Cable R, X, Z Data . . . . . . . . . 1.5-14 17
Conductor Ampacities . . . . . 1.5-16
Conductor Temperature
Ratings . . . . . . . . . . . . . . . . 1.5-16
18
Formulas and Terms . . . . . . . 1.5-19
Seismic Requirements . . . . . 1.5-20 19
20
Designing a Distribution System
21
ii
10
11
12
13
14
15
16
17
18
19
20
21
Basic Principles The basic principles or factors requir- Modern Electric Power i
ing consideration during design of
The best distribution system is one the power distribution system include: Technologies
that will, cost-effectively and safely,
■ Functions of structure, present Several new factors to consider in ii
supply adequate electric service to
and future modern power distribution systems
both present and future probable
■ Life and flexibility of structure result from two relatively recent
loads—this section is included to aid
in selecting, designing and installing ■ Locations of service entrance and
changes. The first recent change is 1
utility deregulation. The traditional
such a system. distribution equipment, locations
dependence on the utility for problem
and characteristics of loads,
The function of the electric power locations of unit substations
analysis, energy conservation mea- 2
distribution system in a building or surements and techniques, and a
■ Demand and diversity factors simplified cost structure for electricity
an installation site is to receive power
of loads
at one or more supply points and
■ Sources of power; including
has changed. The second change is less 3
to deliver it to the individual lamps, obvious to the designer yet will have
motors and all other electrically normal, standby and emergency an impact on the types of equipment
operated devices. The importance (see Tab 40) and systems being designed. It is the 4
of the distribution system to the ■ Continuity and quality of diminishing quantity of qualified build-
function of a building makes it almost power available and required ing electrical operators, maintenance
imperative that the best system be (see Tab 33) departments and facility engineers. 5
designed and installed. ■ Energy efficiency and management Modern electric power technologies
In order to design the best distribution ■ Distribution and utilization voltages may be of use to the designer and
system, the system design engineer ■ Bus and/or cable feeders building owner in addressing these
6
must have information concerning the ■ Distribution equipment and new challenges. The advent of micro-
loads and a knowledge of the various processor devices (smart devices)
types of distribution systems that are
motor control
into power distribution equipment has
7
■ Power and lighting panelboards
applicable. The various categories of expanded facility owners’ options and
and motor control centers
buildings have many specific design capabilities, allowing for automated
challenges, but certain basic principles ■ Types of lighting systems communication of vital power system
8
are common to all. Such principles, ■ Installation methods information (both energy data and
system operation information) and
if followed, will provide a soundly ■ Power monitoring systems
electrical equipment control.
9
executed design. ■ Electric utility requirements
These technologies may be grouped as:
10
■ Power monitoring and control
■ Building management systems
interfaces 11
■ Lighting control
■ Automated energy management
12
■ Predictive diagnostics
Various sections of this guide cover
the application and selection of such 13
systems and components that may be
incorporated into the power equip-
ment being designed. See Tabs 2, 3, 4, 14
23 and 41.
15
16
17
18
19
20
21
21
16
17
18
19
20
21
19
20
21
DELTA-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources. ii
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor H2 X2
Diagram:
1
H1 H3 X1 X3 2
Angular Displacement (Degrees): 0
DELTA-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources. 3
2. Suitable for a three-wire service or a four-wire grounded service with
Phasor H2 X2 XO grounded.
Diagram:
3. With XO grounded, the transformer acts as a ground source for the 4
secondary system.
X1 X0
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
lines supplied by the transformer do not flow in the primary lines. Instead the 5
H1 H3 X3 zero sequence currents circulate in the closed delta primary windings.
5. When supplied from an effectively grounded primary system does not see load
Angular Displacement (Degrees): 30 unbalances and ground faults in the secondary system. 6
WYE-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire delta service with a mid-tap ground.
Phasor
Diagram:
H2 X2 3. Grounding the primary neutral of this connection would create a ground source 7
for the primary system. This could subject the transformer to severe overloading
during a primary system disturbance or load unbalance.
X1
4. Frequently installed with mid-tap ground on one leg when supplying 8
combination three-phase and single-phase load where the three-phase
H1 H3 load is much larger than single-phase load.
X3
Angular Displacement (Degrees): 30
5. When used in 25 kV and 35 kV three-phase four-wire primary systems,
ferroresonance can occur when energizing or de-energizing the transformer
9
using single-pole switches located at the primary terminals. With smaller kVA
transformers the probability of ferroresonance is higher.
WYE-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
10
2. Suitable for a three-wire service only, even if XO is grounded.
Phasor H2 X2 3. This connection is incapable of furnishing a stabilized neutral and its use may
Diagram:
result in phase-to-neutral overvoltage (neutral shift) as a result of unbalanced 11
phase-to-neutral load.
X0 4. If a three-phase unit is built on a three-legged core, the neutral point of the
primary windings is practically locked at ground potential. 12
H1 H3 X1 X3
i Types of Systems Low voltage feeder circuits run from A fault on the secondary low voltage
the switchgear or switchboard assem- bus or in the source transformer will
In many cases, power is supplied by blies to panelboards that are located interrupt service to all loads. Service
the utility to a building at the utilization closer to their respective loads as cannot be restored until the necessary
ii voltage. In these cases, the distribution shown in Figure 1.1-1. repairs have been made. A low voltage
of power within the building is achieved feeder circuit fault will interrupt service
Each feeder is connected to the switch- to all loads supplied over that feeder.
through the use of a simple radial
1 distribution system.
gear or switchboard bus through a
circuit breaker or other overcurrent A modern and improved form of the
In cases where the utility service voltage protective device. A relatively small conventional simple radial system
2 is at some voltage higher than the number of circuits are used to distribute distributes power at a primary voltage.
utilization voltage within the building, power to the loads from the switch- The voltage is stepped down to
the system design engineer has a choice gear or switchboard assemblies and utilization level in the several load
3 of a number of types of systems that panelboards. areas within the building typically
may be used. This discussion covers through secondary unit substation
Because the entire load is served from transformers. The transformers are
several major types of distribution
a single source, full advantage can be
4 systems and practical modifications
taken of the diversity among the loads.
usually connected to their associated
of them. load bus through a circuit breaker, as
This makes it possible to minimize the shown in Figure 1.1-2. Each secondary
1. Simple radial installed transformer capacity. However,
5 the voltage regulation and efficiency
unit substation is an assembled unit
2. Loop-primary system— consisting of a three-phase, liquid-
of this system may be poor because filled or air-cooled transformer, an
radial secondary system of the low voltage feeders and single
6 3. Primary selective system— source. The cost of the low voltage-
integrally connected primary fused
switch, and low voltage switchgear or
secondary radial system feeder circuits and their associated circuit switchboard with circuit breakers or
breakers are high when the feeders are
7 4. Two-source primary— long and the peak demand is above
fused switches. Circuits are run to
secondary selective system the loads from these low voltage
1000 kVA. protective devices.
8 5. Sparing transformer system
6. Simple spot network
Primary Fused Switch
9 7. Medium voltage distribution
system design Transformer
Because each transformer is located In addition, if only one primary fuse on break switches with load side bus
within a specific load area, it must a circuit opens, the secondary loads are connection) sectionalizing switches i
have sufficient capacity to carry the then single phased, causing damage to and primary load break fused switch
peak load of that area. Consequently, low voltage motors. as shown in Figure 1.1-4.
if any diversity exists among the load ii
area, this modified primary radial Another approach to reducing costs When pad-mounted compartmental-
system requires more transformer is to eliminate the primary feeder ized transformers are used, they are
capacity than the basic form of the breakers completely, and use a single furnished with loop-feed oil-immersed 1
simple radial system. However, primary main breaker or fused switch gang-operated load break sectionalizing
because power is distributed to the for protection of a single primary switches and drawout current limiting
load areas at a primary voltage, losses feeder circuit with all secondary unit fuses in dry wells as shown in Figure 2
are reduced, voltage regulation is substations supplied from this circuit. 1.1-5. By operating the appropriate
improved, feeder circuit costs are Although this system results in less sectionalizing switches, it is possible
reduced substantially, and large initial equipment cost, system reliability to disconnect any section of the loop 3
low voltage feeder circuit breakers is reduced drastically because a single conductors from the rest of the system.
are eliminated. In many cases the fault in any part of the primary conductor In addition, by opening the transformer
interrupting duty imposed on the would cause an outage to all loads primary switch (or removing the load 4
load circuit breakers is reduced. within the facility. break drawout fuses in the pad-mounted
transformer) it is possible to disconnect
This modern form of the simple radial 2. Loop Primary System— any transformer from the loop. 5
system will usually be lower in initial Radial Secondary System
investment than most other types of A key interlocking scheme is normally
This system consists of one or more recommended to prevent closing all
primary distribution systems for build-
“PRIMARY LOOPS” with two or more sectionalizing devices in the loop. Each
6
ings in which the peak load is above
1000 kVA. A fault on a primary feeder transformers connected on the loop. primary loop sectionalizing switch and
the feeder breakers to the loop are
circuit or in one transformer will cause This system is typically most effective
when two services are available from interlocked such that to be closed they
7
an outage to only those secondary
loads served by that feeder or trans- the utility as shown in Figure 1.1-3. Each require a key (which is held captive
until the switch or breaker is opened)
former. In the case of a primary main primary loop is operated such that one
and one less key than the number of
8
bus fault or a utility service outage, of the loop sectionalizing switches is
service is interrupted to all loads until kept open to prevent parallel operation key interlock cylinders is furnished.
the trouble is eliminated. of the sources. When secondary unit An extra key is provided to defeat the 9
substations are used, each trans- interlock under qualified supervision.
Reducing the number of transformers former has its own duplex (2-load
per primary feeder by adding more 10
primary feeder circuits will improve
the flexibility and service continuity
of this system; the ultimate being one 11
Primary Main Breaker 1 52 52 Primary Main Breaker 2
secondary unit substation per primary
feeder circuit. This of course increases 52
the investment in the system but Tie 12
minimizes the extent of an outage 52 52 Breaker 52 52 Loop Feeder Breaker
resulting from a transformer or
primary feeder fault. Loop A
Loop B
13
Primary connections from one secondary
unit substation to the next secondary
unit substation can be made with
NC NO NC NC
Fault Sensors
14
“double” lugs on the unit substation
primary switch as shown, or with
separable connectors made in 15
manholes or other locations.
Depending on the load kVA connected 16
to each primary circuit and if no ground
fault protection is desired for either the
primary feeder conductors and trans- NC NC NO NC NC NC 17
formers connected to that feeder or
the main bus, the primary main and/or
feeder breakers may be changed to 18
primary fused switches. This will sig-
nificantly reduce the first cost, but also
decrease the level of conductor and 19
equipment protection. Thus, should
a fault or overload condition occur,
downtime increases significantly and Secondary Unit Substations Consisting of:
20
higher costs associated with increased Duplex Primary Switches/Fused Primary Switches/
Transformer and Secondary Main Feeder Breakers
damage levels and the need for fuse
replacement is typically encountered. 21
Figure 1.1-3. Loop Primary—Radial Secondary System
Switchgear Lineup
and primary tie breaker, which is 52 52 Primary Main Breaker
normally open, are either mechanically
14 or electrically interlocked to prevent Bus A 52 Bus B
paralleling the incoming source lines.
For slightly added cost, an automatic 52 52 52 52 Primary Feeder Breaker
15 throw-over scheme can be added
between the two main breakers and Feeder A1 Feeder B1 Feeder B2
tie breaker. During the more common To Other
16 event of a utility outage, the automatic
Feeder A2 Substations
designed so that when one primary or most of the loads, may more than
circuit is out of service, the remaining Primary offset the greater cost. Having two i
feeder or feeders have sufficient Feeders sources allows for either manual or
capacity to carry the total load. Half automatic transfer of the two primary
of the transformers are normally Non-Load Break main breakers and tie breaker should ii
connected to each of the two feeders. Selector Switches one of the sources become unavailable.
When a fault occurs on one of the Inter-
primary feeders, only half of the
lock Load Break
Disconnect
The primary selective-secondary radial 1
load in the building is dropped. system, however, may be less costly or
Fuses
more costly than a primary loop—
Duplex fused switches as shown in secondary radial system of Figure 1.1-3 2
Figure 1.1-7 and detailed in Figure 1.1-8 depending on the physical location
are the normal choice for this type of of the transformers while offering
system. Each duplex fused switch comparable downtime and reliability. 3
consists of two (2) load break three- The cost of conductors for the two
pole switches each in their own types of systems may vary greatly
separate structure, connected together depending on the location of the 4
by bus bars on the load side. Typically, transformers and loads within the
the load break switch closest to the facility and greatly override primary
Figure 1.1-9. Fused Selector Switch in
transformer includes a fuse assembly
One Structure
switching equipment cost differences 5
with fuses. Mechanical and/or key between the two systems.
interlocking is furnished such that This means limited cable space espe-
both switches cannot be closed at cially if double lugs are furnished for 4. Two-Source Primary— 6
the same time (to prevent parallel each line as shown in Figure 1.1-7 and Secondary Selective System
operation) and interlocking such should a faulted primary conductor
that access to either switch or fuse have to be changed, both lines would This system uses the same principle
of duplicate sources from the power
7
assembly cannot be obtained unless have to be de-energized for safe
both switches are opened. changing of the faulted conductors. supply point using two primary main
breakers and a primary tie breaker. 8
In Figure 1.1-7 when a primary feeder The two primary main breakers and
Primary fault occurs, the associated feeder primary tie breaker being either
Feeders breaker opens and the transformers manually or electrically interlocked 9
normally supplied from the faulted to prevent closing all three at the same
Load Break feeder are out of service. Then manu- time and paralleling the sources. Upon
Switches ally, each primary switch connected to loss of voltage on one source, a manual 10
the faulted line must be opened and or automatic transfer to the alternate
then the alternate line primary switch source line may be used to restore
can be closed connecting the trans- power to all primary loads. 11
Fuses former to the live feeder, thus restoring
service to all loads. Note that each of the Each transformer secondary is
arranged in a typical double-ended
primary circuit conductors for Feeder
unit substation arrangement as shown
12
A1 and B1 must be sized to handle the
sum of the loads normally connected in Figure 1.1-10. The two secondary
main breakers and secondary tie
to both A1 and B1. Similar sizing of
breaker of each unit substation are
13
Feeders A2 and B2, etc., is required.
again either mechanically or electrically
If a fault occurs in one transformer, interlocked to prevent parallel operation.
the associated primary fuses blow Upon loss of secondary source voltage
14
Figure 1.1-8. Duplex Fused Switch in
Two Structures and interrupt the service to just on one side, manual or automatic
the load served by that transformer. transfer may be used to transfer the
As an alternate to the duplex switch Service cannot be restored to the loads to the other side, thus restoring
15
arrangement, a non-load break selector loads normally served by the faulted power to all secondary loads.
switch mechanically interlocked with a transformer until the transformer 16
load break fused switch can be used as is repaired or replaced. This arrangement permits quick
shown in Figure 1.1-9. The non-load restoration of service to all loads when
break selector switch is physically Cost of the primary selective— a primary feeder or transformer fault
located in the rear of the load break secondary radial system is greater occurs by opening the associated 17
fused switch, thus only requiring one than that of the simple primary radial secondary main and closing the
structure and a lower cost and floor system of Figure 1.1-1 because of the secondary tie breaker. If the loss of
space savings over the duplex additional primary main breakers, tie secondary voltage has occurred 18
arrangement. The non-load break breaker, two-sources, increased number because of a primary feeder fault
switch is mechanically interlocked to of feeder breakers, the use of primary- with the associated primary feeder
prevent its operation unless the load duplex or selector switches, and the breaker opening, then all secondary 19
break switch is opened. The main greater amount of primary feeder loads normally served by the faulted
cable required. The benefits from the feeder would have to be transferred
disadvantage of the selector switch is
that conductors from both circuits are reduction in the amount of load lost to the opposite primary feeder. This 20
terminated in the same structure. when a primary feeder is faulted, plus means each primary feeder conductor
the quick restoration of service to all must be sized to carry the load on both
sides of all the secondary buses it is 21
serving under secondary emergency emergency conditions, the in-service transformers are furnished with
i transfer. If the loss of voltage was due transformer of a double-ended unit fan-cooling and/or lower than normal
to a failure of one of the transformers in substation would have to have the temperature rise such that under
the double-ended unit substation, then capability of serving the loads on emergency conditions they can carry
ii the associated primary fuses would both sides of the tie breaker. For this on a continuous basis the maximum
open taking only the failed transformer reason, transformers used in this load on both sides of the secondary tie
out of service, and then only the application have equal kVA rating breaker. Because of this spare trans-
1 secondary loads normally served by on each side of the double-ended former capacity, the voltage regulation
the faulted transformer would have unit substation and the normal provided by the double-ended unit
to be transferred to the opposite operating maximum load on each substation system under normal
2 transformer. In either of the above transformer is typically about 2/3 base conditions is better than that of the
nameplate kVA rating. Typically these systems previously discussed.
Referring to Figure 1.1-11, it is appar- In facilities without qualified electrical The major advantage of the secondary
ent that the sparing concept backs up power operators, an open transition network system is continuity of i
primary switch and primary cable fail- with key interlocking is often a service. No single fault anywhere
ure as well. Restoration of lost or failed prudent design. on the primary system will interrupt
utility power is accomplished similarly
Note: Each pair of “main breaker/tie breaker”
service to any of the system’s loads. ii
to primary selective scheme previously Most faults will be cleared without
key cylinders should be uniquely keyed to
discussed. It is therefore important to prevent any paralleled source operations. interrupting service to any load.
use an automatic throwover system Another outstanding advantage that 1
in a two source lineup of primary Careful sizing of these transformers the network system offers is its flexi-
switchgear to restore utility power as well as careful specification of the bility to meet changing and growing
as discussed in the “Two-Source transformers is required for reliability. load conditions at minimum cost and 2
Primary” scheme—see Figure 1.1-10. Low temperature rise specified with minimum interruption in service to
continuous overload capacity or other loads on the network. In addition
A major advantage of the sparing
transformer system is the typically upgraded types of transformers to flexibility and service reliability, the 3
should be considered. secondary network system provides
lower total base kVA of transformation.
exceptionally uniform and good
In a double-ended substation design, One disadvantage to this system is 4
voltage regulation, and its high
each transformer must be rated to the external secondary tie system, efficiency materially reduces the
carry the sum of the loads of two busses see Figure 1.1-11. As shown, all single-
and usually requires the addition of costs of system losses.
cooling fans to accomplish this rating.
ended substations are tied together on 5
the secondary with a tie busway or Three major differences between the
In the “sparing” concept, each trans- cable system. Location of substations network system and the simple radial
former carries only its own load, which is therefore limited because of voltage system account for the outstanding 6
is typically not a fan-cooled rating. Major advantages of the network. First,
drop and cost considerations.
space savings is also a benefit of this a network protector is connected in
system in addition to first cost savings. Routing of busway, if used, must be the secondary leads of each network 7
carefully layed out. It should also be transformer in place of, or in addition
The sparing transformer system
noted, that a tie busway or cable fault to, the secondary main breaker, as
operates as follows:
will essentially prevent the use of the shown in Figure 1.1-12. Also, the 8
■ All main breakers, including sparing transformer until it is repaired. secondaries of each transformer in
the sparing main breaker, are Commonly, the single-ended substa- a given location (spot) are connected
normally closed; the tie breakers tions and the sparing transformer together by a switchgear or ring bus 9
are normally open must be clustered. This can also be from which the loads are served over
■ Once a transformer (or primary an advantage, as more kVA can be short radial feeder circuits. Finally, the
cable or primary switch/fuse) fails, supported from a more compact primary supply has sufficient capacity 10
the associated secondary main space layout. to carry the entire building load with-
breaker is opened. The associated out overloading when any one primary
tie breaker is then closed, which 6. Simple Spot Network Systems feeder is out of service. 11
restores power to the single-ended The AC secondary network system A network protector is a specially
substation bus is the system that has been used for designed heavy-duty air power breaker, 12
■ Schemes that require the main to many years to distribute electric power spring close with electrical motor-charged
be opened before the tie is closed in the high-density, downtown areas mechanism, with a network relay to
(“open transition”), and that allow of cities, usually in the form of utility
any tie to be closed before the grids. Modifications of this type of
control the status of the protector
(tripped or closed). The network relay
13
substation main is opened, (“closed system make it applicable to serve is usually a solid-state microprocessor-
transition”) are possible loads within buildings. based component integrated 14
With a closed transition scheme, it is
common to add a timer function that
opens the tie breaker unless either Typical Feeder 15
main breaker is opened within a time Primary Circuit
interval. This closed transition allows To Other
power to be transferred to the sparing Network Transformer
Networks
16
transformer without interruption, such
as for routine maintenance, and then Network Protector
back to the substation. This closed Fuses 17
transition transfer has an advantage in Optional Main, 50/51
some facilities; however, appropriate Relaying and/or
Network Disconnect
interrupting capacities and bus bracing Tie Tie
Drawout
18
must be specified suitable for the Low Voltage
momentary parallel operation. LV Feeder NC NC Switchgear
19
Customer Customer Customer
Loads Loads Loads
20
Figure 1.1-12. Three-Source Spot Network
21
into the protector enclosure that with that feeder circuit. This operation They are also economical when
i functions to automatically close the does not interrupt service to any loads. compared to two transformer double-
protector only when the voltage After the necessary repairs have been ended substations with normally
conditions are such that its associated made, the system can be restored to opened tie breakers.
ii transformer will supply power to the normal operating conditions by closing
secondary network loads, and to auto- the primary feeder breaker. All network Emergency power should be connected
matically open the protector when protectors associated with that feeder to network loads downstream from
1 power flows from the secondary to the will close automatically. the network, or upstream at primary
network transformer. The purpose of voltage, not at the network bus itself.
the network protector is to protect the The chief purpose of the network bus
2 integrity of the network bus voltage normally closed ties is to provide for 7. Medium Voltage Distribution
and the loads served from it against the sharing of loads and a balancing System Design
transformer and primary feeder faults of load currents for each primary ser-
3 by quickly disconnecting the defective vice and transformer regardless of A. Single Bus, Figure 1.1-13
feeder-transformer pair from the the condition of the primary services.
The sources (utility and/or generator(s))
network when backfeed occurs. Also, the ties provide a means for are connected to a single bus. All feeders
4 isolating and sectionalizing ground are connected to the same bus.
The simple spot network system
resembles the secondary-selective fault events within the switchgear
network bus, thereby saving a portion
5 radial system in that each load area
of the loads from service interruptions, Utility
is supplied over two or more primary
feeders through two or more trans- yet isolating the faulted portion for
G
corrective action.
6 formers. In network systems, the
transformers are connected through The use of spot network systems
network protectors to a common provides users with several important
7 bus, as shown in Figure 1.1-12, from advantages. First, they save trans-
which loads are served. Because the former capacity. Spot networks permit
transformers are connected in parallel, equal loading of transformers under 52 52
8 a primary feeder or transformer fault all conditions. Also, networks yield
does not cause any service interrup- lower system losses and greatly Main Bus
tion to the loads. The paralleled improve voltage conditions. The
9 transformers supplying each load voltage regulation on a network
bus will normally carry equal load system is such that both lights and
currents, whereas equal loading of power can be fed from the same
10 the two separate transformers supply- load bus. Much larger motors can
52
ing a substation in the secondary- be started across-the-line than on a
selective radial system is difficult to simple radial system. This can result in One of Several Feeders
11 obtain. The interrupting duty imposed simplified motor control and permits
on the outgoing feeder breakers in the the use of relatively large low voltage
network will be greater with the spot Figure 1.1-13. Single Bus
motors with their less expensive
12 network system. control. Finally, network systems This configuration is the simplest
The optimum size and number of provide a greater degree of flexibility system; however, outage of the utility
in adding future loads; they can be results in total outage.
13 primary feeders can be used in the
connected to the closest spot
spot network system because the Normally the generator does not have
loss of any primary feeder and its network bus.
adequate capacity for the entire load.
14 associated transformers does not Spot network systems are economical A properly relayed system equipped
result in the loss of any load even for buildings that have heavy concen- with load shedding, automatic voltage/
for an instant. In spite of the spare trations of loads covering small areas, frequency control may be able to
15 capacity usually supplied in network with considerable distance between maintain partial system operation.
systems, savings in primary switch- areas, and light loads within the
gear and secondary switchgear costs distances separating the concentrated Any future addition of breaker sections
16 often result when compared to a radial loads. They are commonly used in to the bus will require a shutdown of
system design with similar spare hospitals, high rise office buildings, the bus, because there is no tie breaker.
capacity. This occurs in many radial and institutional buildings where a B. Single Bus with Two Sources from the
17 systems because more and smaller high degree of service reliability is Utility, Figure 1.1-14
feeders are often used in order to required from the utility sources.
minimize the extent of any outage Spot network systems are especially Same as the single bus, except that
18 when a primary fault event occurs. economical where three or more two utility sources are available.
primary feeders are available. This system is operated normally with
In spot networks, when a fault occurs the main breaker to one source open.
on a primary feeder or in a transformer, Principally, this is due to supplying
19 the fault is isolated from the system each load bus through three or Upon loss of the normal service, the
more transformers and the reduction transfer to the standby normally
through the automatic tripping of the open (NO) breaker can be automatic
primary feeder circuit breaker and all in spare cable and transformer
20 of the network protectors associated capacity required. or manual. Automatic transfer is
preferred for rapid service restoration
especially in unattended stations.
21
Again, the closing of the tie breaker can The third tie breaker allows any bus
Utility #1 Utility #2 be manual or automatic. The statements to be fed from any utility source. i
made for the retransfer of scheme B
apply to this scheme also. Caution for Figures 1.1-14, 1.1-15 and
Normal Standby
1.1-16: If continuous paralleling of ii
Utility #1 Utility #2 sources is planned, reverse current,
reverse power and other appropriate
relaying protection should be added. 1
When both sources are paralleled for
any amount of time, the fault current
52 NC 52 NO available on the load side of the main 2
device is the sum of the available
52 NC 52 NC fault current from each source plus
the motor fault contribution. It is 3
Loads required that bus bracing, feeder
NO
Bus #1 Bus #2 breakers and all load side equipment
Figure 1.1-14. Single Bus with Two-Sources
52
is rated for the increased available 4
fault current.
Retransfer to the “Normal” can be
closed transition subject to the approval 52 52
Summary
5
of the utility. Closed transition momen-
tarily (5–10 cycles) parallels both The medium voltage system configura-
utility sources. Caution: when both Load Load
tions shown are based on using metal- 6
sources are paralleled, the fault current clad drawout switchgear. The service
available on the load side of the main Figure 1.1-15. Two-Source Utility with continuity required from electrical
device is the sum of the available fault Tie Breaker systems makes the use of single-source 7
current from each source plus the motor systems impractical.
fault contribution. It is recommended If looped or primary selective distribu-
tion system for the loads is used, the In the design of a modern medium 8
that the short-circuit ratings of the voltage system, the engineer should:
bus, feeder breakers and all load side buses can be extended without a shut-
equipment are rated for the increased down by closing the tie breaker and 1. Design a system as simple as
available fault current. If the utility transferring the loads to the other bus. possible. 9
requires open transfer, the disconnec- This configuration is more expensive
tion of motors from the bus must be 2. Limit an outage to as small a
than B. The system is not limited to two portion of the system as possible. 10
ensured by means of suitable time delay buses only. Another advantage is that
on reclosing as well as supervision the design may incorporate momentary 3. Provide means for expanding the
of the bus voltage and its phase with paralleling of buses on retransfer after system without major shutdowns.
respect to the incoming source voltage. the failed line has been restored to pre-
11
vent another outage. See the Caution 4. Relay the system so that only the
This busing scheme does not preclude faulted part is removed from
the use of cogeneration, but requires for Figures 1.1-14, 1.1-15 and 1.1-16. 12
service, and damage to it is mini-
the use of sophisticated automatic syn- In Figure 1.1-16, closing of the tie mized consistent with selectivity.
chronizing and synchronism checking breaker following the opening of a
controls, in addition to the previously main breaker can be manual or auto- 5. Specify and apply all equipment 13
mentioned load shedding, automatic matic. However, because a bus can within its published ratings and
frequency and voltage controls. be fed through two tie breakers, the national standards pertaining to
This configuration is more expensive control scheme should be designed the equipment and its installation. 14
than the scheme shown in Figure 1.1-13, to make the selection.
but service restoration is quicker. Again,
a utility outage results in total outage to
15
Utility #1 Utility #2 Utility #3
the load until transfer occurs. Extension
of the bus or adding breakers requires 16
a shutdown of the bus.
If paralleling sources, reverse current,
reverse power and other appropriate 17
relaying protection should be added
as requested by the utility. 52 NC 52 NC 52 NC
18
C. Multiple Sources with Tie Breaker, NO NO
Bus #1 Bus #2 Bus #3
Figure 1.1-15 and Figure 1.1-16 52 52
This configuration is similar to configu- 19
ration B. It differs significantly in that
both utility sources normally carry the 52 NO 52 Typical Feeder 52 52 52 NO
loads and also by the incorporation 20
of a normally open tie breaker. The Tie Busway
outage to the system load for a utility
outage is limited to half of the system. 21
Figure 1.1-16. Triple-Ended Arrangement
i Health Care Facilities ■ NFPA 101-2009—Life Safety Code The electrical system requirements for
■ NFPA 110-2010—Standard for Emer- the essential electrical system (EES)
Health care facilities are defined by gency and Standby Power Systems vary according to the type of health
NFPA (National Fire Protection Agency) ■ NFPA 111-2010—Standard on
care facility. Health care facilities are
ii as “Buildings or portions of buildings Stored Electrical Energy Emergency categorized by NFPA 99 as Type 1,
in which medical, dental, psychiatric, and Standby Power Systems Type 2 or Type 3 facilities. Some
nursing, obstetrical, or surgical care example health care facilities, classified
1 are provided.” Due to the critical These NFPA guidelines represent the by type, are summarized in the
nature of the care being provided at most industry recognized standard following Table 1.1-8.
these facilities and their increasing requirements for health care electrical
2 dependence on electrical equipment design. However, the electrical design Table 1.1-8. Health Care Facilities
for preservation of life, health care engineer should consult with the Description Definition EES Type
facilities have special requirements for authorities having jurisdiction over
3 the design of their electrical distribu- the local region for specific electrical
Hospitals NFPA 99 Chap. 13 Type 1
Nursing homes NFPA 99 Chap. 17 Type 2
tion systems. These requirements are distribution requirements. Limited care
typically much more stringent than facilities NFPA 99 Chap. 18 Type 2
4 commercial or industrial facilities. Health Care Electrical System Ambulatory
The following section summarizes Requirements surgical
some of the unique requirements facilities NFPA 99 Chap. 14 Type 3
5 of health care facility design. Health care electrical systems usually Other health
consist of two parts: care facilities NFPA 99 Chap. 14 Type 3
There are several agencies and organi- If electrical life support or critical care areas
6 zations that develop requirements 1. Non-essential or normal are present, then facility is classified as Type 1.
for health care electrical distribution electrical system.
system design. The following is a 2. Essential electrical system.
Type 1 Essential Electrical
7 listing of some of the specific NFPA Systems (EES)
(National Fire Protection Agency) All electrical power in a health care
standards that affect health care facility is important, though some Type 1 essential electrical systems
8 facility design and implementation: loads are not critical to the safe opera- (EES) have the most stringent require-
tion of the facility. These “non-essential” ments for providing continuity of
■ NFPA 37-2010—Standard for or “normal” loads include things such electrical service and will, therefore,
9 Stationary Combustion Engines as general lighting, general lab equip- be the focus of this section. Type 1
and Gas Turbines ment, non-critical service equipment, EES requirements meet or exceed
■ NFPA 70-2011—National patient care areas, etc. These loads are the requirements for Type 2 and
10 Electrical Code not required to be fed from an alternate Type 3 facilities.
■ NFPA 99-2005—Health Care Facilities source of power.
11
Normal Source Normal Source Normal Source Emergency Power Supply
12 G
13
14
15
16
Non-Essential Loads Non-Essential Loads
17
Sources: Type 1 systems are required Table 1.1-9. Type 1 EES Applicable Codes B. Critical branch—supplies power
to have a minimum of two independent Description Standard Section for task illumination, fixed equip- i
sources of electrical power—a normal ment, selected receptacles and
source that generally supplies the Design NFPA 99 4.4.1.1.1 selected power circuits for areas
entire facility and one or more alter- Sources NFPA 99 4.4.1.1.4 thru
4.4.4.1.1.7.2
related to patient care. The ii
nate sources that supply power when Uses NFPA 99 4.4.1.1.8 (1-3)
purpose of the critical branch
the normal source is interrupted. The Emergency is to provide power to a limited
alternate source(s) must be an on-site Power Supply number of receptacles and loca- 1
generator driven by a prime mover Classification NFPA 110 4 tions to reduce load and minimize
unless a generator(s) exists as the Distribution NFPA 99 4.4.2 the chances of fault conditions.
normal power source. In the case NEC 517.30 The transfer switch(es) feeding the 2
where a generator(s) is used as the critical branch must be automatic
normal source, it is permissible for the Systems and Branches of Service: The type. They are permitted to have
alternate source to be a utility feed. Type 1 EES consists of two separate appropriate time delays that will 3
Alternate source generators must be power systems capable of supplying follow the restoration of the life
classified as Type 10, Class X, Level 1 power considered essential for life safety branch, but should have
gensets per NFPA 110 Tables 4.1(a) safety and effective facility operation power restored within 10 seconds 4
and 4.2(b) that are capable of providing during an interruption of the normal of normal source power loss.
power to the load in a maximum of power source. They are the emergency The critical branch provides power
10 seconds. Typically, the alternate system and the equipment system. to circuits serving the following 5
sources of power are supplied to the areas and functions:
1. Emergency system—consists of
loads through a series of automatic
and/or manual transfer switches (see
circuits essential to life safety and 1. Critical care areas. 6
critical patient care.
Tab 25). The transfer switches can 2. Isolated power systems in
be non-delayed automatic, delayed The emergency system is an electrical special environments.
automatic or manual transfer depending sub-system that must be fed from an 3. Task illumination and selected
7
on the requirements of the specific automatic transfer switch or series of receptacles in the following
branch of the EES that they are feeding. automatic transfer switches. This patient care areas: infant
It is permissible to feed multiple emergency system consists of two nurseries, medication prep
8
branches or systems of the EES from mandatory branches that provide power areas, pharmacy, selected
a single automatic transfer switch to systems and functions essential to acute nursing areas, psychiatric
provided that the maximum demand life safety and critical patient care. bed areas, ward treatment
9
on the EES does not exceed 150 kVA. rooms, nurses’ stations.
This configuration is typically seen A. Life safety branch—supplies
in smaller health care facilities that power for lighting, receptacles 4. Specialized patient care task 10
must meet Type 1 EES requirements and equipment to perform the illumination, where needed.
(see Figure 1.1-18). following functions: 5. Nurse call systems.
6. Blood, bone and tissue banks.
11
1. Illumination of means of egress.
Normal Source 2. Exit signs and exit direction signs. 7. Telephone equipment rooms
3. Alarms and alerting systems.
and closets. 12
Alternate 8. Task illumination, selected
4. Emergency communications
Source receptacles and selected power
systems.
circuits for the following: general 13
G 5. Task illumination, battery care beds (at least one duplex
chargers for battery powered receptacle), angiographic labs,
lighting, and select receptacles cardiac catheterization labs, 14
at the generator. coronary care units, hemodialysis
6. Elevator lighting control, com- rooms, selected emergency
munication and signal systems. room treatment areas, human 15
7. Automatic doors used for egress. physiology labs, intensive care
units, selected postoperative
Non-Essential
Loads These are the only functions recovery rooms. 16
permitted to be on the life safety 9. Additional circuits and single-
Entire Essential branch. Life safety branch equip-
Electric System ment and wiring must be entirely
phase fraction motors as needed
for effective facility operation.
17
(150 kVA or Less) independent of all other loads
and branches of service. This
Figure 1.1-18. Small Hospital Electrical includes separation of raceways, 18
System—Single EES Transfer Switch boxes or cabinets. Power must be
supplied to the life safety branch
from a non-delayed automatic
19
transfer switch.
20
21
Table 1.1-10. Type 1—Emergency System The following equipment must be and must be shed in the event the
i Applicable Codes arranged for delayed automatic or generator enters an overload condition.
Description Standard Section manual transfer to the emergency
power supply: Ground fault protection—per NFPA 70
ii General NFPA 99 4.4.2.2.2 NEC Article 230.95, ground fault
NEC 517.31 1. Select heating equipment. protection is required on any feeder or
Life safety NFPA 99 4.4.2.2.2.2 2. Select elevators. service disconnect 1000A or larger on
1 branch NEC 517.32
3. Supply, return and exhaust
systems with line to ground voltages
Critical branch NFPA 99 4.4.2.2.2.3 of 150V or greater and phase-to-phase
NEC 517.33 ventilating systems for surgical, voltages of 600V or less. For health care
obstetrical, intensive care,
2 Wiring NFPA 99 4.4.2.2.4
coronary care, nurseries and
facilities (of any type), a second level of
NEC 517.30(C) ground fault protection is required to
emergency treatment areas. be on the next level of feeder down-
3 2. Equipment system—consists of 4. Supply, return and exhaust stream. This second level of ground
major electrical equipment necessary ventilating systems for airborne fault is only required for feeders that
for patient care and Type 1 operation. infectious/isolation rooms, labs and serve patient care areas and equipment
4 The equipment system is a subsystem
medical areas where hazardous intended to support life. 100% selective
materials are used. coordination of the two levels of ground
of the EES that consists of large electrical fault protection must be achieved with a
equipment loads needed for patient 5. Hyperbaric facilities.
5 care and basic hospital operation. 6. Hypobaric facilities.
minimum six-cycle separation between
the upstream and downstream device.
Loads on the equipment system that 7. Autoclaving equipment.
are essential to generator operation are New in the 2011 NEC, ground fault
6 required to be fed by a non-delayed 8. Controls for equipment listed above. protection is now allowed between
automatic transfer switch. 9. Other selected equipment in the generator(s) and the EES transfer
kitchens, laundries, radiology switch(es). However, NEC 517.17(B)
7 The following equipment must be rooms and central refrigeration prohibits the installation of ground fault
arranged for delayed automatic transfer as selected. protection on the load side of a transfer
to the emergency power supply: switch feeding EES circuits (see Figure
8 Table 1.1-11. Type 1—Equipment System
1.1-19—additional level of ground fault).
1. Central suction systems for medical Applicable Codes
and surgical functions. Careful consideration should be used in
Description Standard Section applying ground fault protection on the
9 2. Sump pumps and other equipment
essential electrical system to prevent
required for the safe operation of General NFPA 99 4.4.2.2.3
NEC 517.34 a ground fault that causes a trip of the
a major apparatus.
10 Equipment NFPA 99 4.4.2.2.3 (3-5) normal source to also cause a trip on
3. Compressed air systems for NEC 517.34(A)-(B) the emergency source. Such an event
medical and surgical functions. could result in complete power loss of
11 4. Smoke control and stair Any loads served by the generator that both normal and emergency power
pressurization systems. are not approved as outlined above as sources and could not be recovered
part of the essential electrical system until the source of the ground fault
5. Kitchen hood supply and exhaust
12 systems, if required to operate must be connected through a separate was located and isolated from the
system. To prevent this condition,
during a fire. transfer switch. These transfer switches
must be configured such that the loads NEC 700.26 removes the ground fault
13 will not cause the generator to overload protection requirement for the
19
GF = Ground Fault Protection Required Additional Level of Ground Fault is
not
20 Essential Electrical System Transfer Switches. (NEC 517.17a(2))
emergency system source. Typically, Maintenance and Testing trained in development and execution
the emergency system generator(s) Regular maintenance and testing of of annual preventative maintenance i
are equipped with ground fault alarms the electrical distribution system in procedures of health care facility
that do not automatically disconnect a health care facility is necessary to electrical distribution systems.
power during a ground fault. ensure proper operation in an emer- ii
gency and, in some cases, to maintain Paralleling Emergency Generators
Table 1.1-12. Ground Fault Protection
government accreditation. Any health
Applicable Codes
care facility receiving Medicare or Without Utility Paralleling 1
Description Standard Section In many health care facilities (and
Medicaid reimbursement from the
government must be accredited by the other large facilities with critical
Services
Feeders
NEC
NEC
230.95
215.10 Joint Commission on Accreditation of loads), the demand for standby 2
Additional level NEC 517.17 Health Care Organizations (JCAHO). emergency power is large enough
NFPA 99 4.3.2.5 JCAHO has established a group of to require multiple generator sets to
Alternate source NEC 700.26 standards called the Environment of power all of the required essential 3
NEC 701.26 Care, which must be met for health electrical system (EES) loads. In many
care facility accreditation. Included in cases, it becomes more flexible and
Wet procedure locations—A wet these standards is the regular testing easier to operate the required multiple 4
procedure location in a health care of the emergency (alternate) power generators from a single location using
facility is any patient care area that system(s). Diesel-powered EPS instal- generator paralleling switchgear.
is normally subject to wet conditions lations must be tested monthly in Figure 1.1-20 on Page 1.1-18 shows 5
while patients are present. Typical wet accordance with NFPA 110 Standard an example of a typical one-line for a
procedure locations can include oper- for Emergency and Standby Power paralleling switchgear lineup feeding
ating rooms, anesthetizing locations, Systems. Generators must be tested the EES. 6
dialysis locations, etc. (Patient beds, for a minimum of 30 minutes under
A typical abbreviated sequence of
toilets and sinks are not considered the criteria defined in NFPA 110.
wet locations.) These wet procedure
operation for a multiple emergency 7
One method to automate the task of generator and ATS system follows.
locations require special protection
monthly generator tests is through the Note that other modes of operation
to guard against electric shock. The
ground fault current in these areas use of Power Xpert® communications. such as generator demand priority and 8
With the Power Xpert integrated meter- automated testing modes are available
must be limited to not exceed 6 mA.
ing, monitoring and control system, a but are not included below. (Reference
In areas where the interruption of power facility maintenance director can ini- Tab 41 for complete detailed 9
is permissible, ground fault circuit tiate a generator test, control/monitor sequences of operation.)
interrupters (GFCI) can be employed. loads, meter/monitor generator test
GFCIs will interrupt a circuit when points and create a JCAHO compliant
1. Entering emergency mode 10
ground fault current exceeds 5 mA report automatically from a central PC. a. Upon loss of normal source,
(±1 mA). The report contains all metered values, automatic transfer switches
test results, date/time information, etc. send generator control system 11
In areas where the interruption of necessary to satisfy JCAHO require- a run request.
power cannot be tolerated, protection ments. This automated generator testing
from ground fault currents is accom- procedure reduces the labor, training
b. All available generators are 12
plished through the use of an isolated started. The first generator up
and inaccuracies that occur during to voltage and frequency is
power system. Isolated power systems manual emergency power system tests.
provide power to an area that is iso- (See Power Monitoring Tab 2.)
closed to the bus. 13
lated from ground (or ungrounded). c. Unsheddable loads and load
This type of system limits the amount Table 1.1-14. Maintenance and Testing shed Priority 1 loads are pow-
of current that flows to ground in Applicable Codes ered in less than 10 seconds. 14
the event of a single line-to-ground Description Standard Section d. The remaining generators are
fault and maintains circuit continuity.
synchronized and paralleled
Electronic line isolation monitors (LIM) Grounding NFPA 99 4.3.3.1
to the bus as they come up to 15
are used to monitor and display leakage Emergency power NFPA 99 4.4.4.1.1
system JCAHO EC.2.14(d) voltage and frequency.
currents to ground. When leakage
current thresholds are exceeded, visible Generator NFPA 110 8.4 e. As additional generators are 16
and/or audible alarms are initiated to Transfer switches NFPA 110 8.3.5, 8.4.6 paralleled to the emergency
alert occupants of a possible hazardous bus, load shed priority levels
Breakers NFPA 99 4.4.4.1.2
condition. This alarm occurs without NFPA 110 8.4.7 are added, powering their 17
interrupting power to allow for the associated loads.
safe conclusion of critical procedures. Routine maintenance should be per- f. The system is now in
Table 1.1-13. Wet Procedure Location
formed on circuit breakers, transfer emergency mode. 18
switches, switchgear, generator equip- 2. Exit from emergency mode
Applicable Codes
ment, etc. by trained professionals
Description Standard Section to ensure the most reliable electrical a. Automatic transfer switches 19
General NFPA 99 4.3.2.2.9 system possible. See Tab 41 for sense the utility source is
NEC 517.20 Eaton’s Electrical Services & Systems within acceptable operational
Isolated power NFPA 99 4.3.2.6 (EESS), which provides engineers, tolerances for a time duration 20
systems NEC 517.160 set at the automatic transfer
switch.
21
b. As each automatic transfer With Utility Paralleling Many health care facilities are taking
i switch transfers back to utility Today, many utilities are offering their advantage of these utility incentives
power, it removes its run customers excellent financial incen- by adding generator capacity over
request from the generator tives to use their on-site generation and above the NFPA requirements.
ii plant. capacity to remove load from the utility Figure 1.1-21 on Page 1.1-19 shows
c. When the last automatic trans- grid. These incentives are sometimes an example one-line of a health care
fer switch has retransferred to referred to as limited interruptible facility with complete generator
1 the utility and all run requests rates (LIP). Under these incentives, backup and utility interconnect.
have been removed from the utilities will greatly reduce or eliminate NFPA 110 requirements state that the
generator plant, all generator kWhr or kW demand charges to their
2 circuit breakers are opened. customers with on-site generation
normal and emergency sources must
be separated by a fire-rated wall.
d. The generators are allowed capabilities. In exchange, during times
of peak loading of the utility grid, the The intent of this requirement is so that
3 to run for their programmed
utility can ask their LIP rate customers a fire in one location cannot take out
cool-down period.
to drop load from the grid by using both sources of power. To meet this
e. The system is now back in their on-site generation capabilities. requirement, the paralleling switchgear
4 automatic/standby mode. must be split into separate sections
Health care facilities are ideally suited with a tie bus through a fire-rated wall.
to take advantage of these programs For more information on generator
5 because they already have significant paralleling switchgear, see Tab 40.
on-site generation capabilities due to
the code requirements described.
6
Utility
7
Transformer Generators X = Number of Units
8
Utility G1 G2 Gx
Metering
9
Typical
Generator
Breaker
10 Service Main
14
Equipment Life Safety Critical Load Shed/Load
ATS # 1 ATS # 2 ATS # X Add ATS Units
15 Non-Essential
Loads
Optional Closed
16 EP1 EP2 Typical
Panelboards
EPX Transition
Paralleling of
Generators and
Utility
17
Figure 1.1-20. Typical One-Line for a Paralleling Switchgear Lineup Feeding the Essential Electrical System (EES)
18
19
20
21
Transformer
Generators X = Number of Units ii
Utility G1 G2 Gx
Metering 1
Utility
Closed
Protective Typical
Relay Transition
Paralleling of Generator
2
Generators and Breaker
Service Main Utility, Plus
Soft Loading/ 3
Unloading
Normal Bus Emergency Bus
TIE Optional TIE 4
Optional Electrically Operated
Electrically Stored Energy
Operated
Field Installed
Cable or Busway
Breakers 5
Stored F1 F2 Fx EF1 EF2 EFx
Energy
Breakers 6
11
12
13
14
15
16
17
18
19
20
21
ii
10
11
12
13
14
15
16
17
18
19
20
21
21
Generator Systems Multiple Isolated Standby Generators Multiple generator systems have a
i The second type of generator system more complex control and protection
Emergency Standby Generator System is a multiple isolated set of standby requirement as the units have to be
There are primarily three types of generators. Figure 1.2-2 shows synchronized and paralleled together.
ii generator systems. The first and multiple generators connected to The generators are required to share
simplest type is a single generator a paralleling bus feeding multiple the load proportionally without swings
that operates independently from transfer switches. The utility is the or prolonged hunting in voltage or
1 the electric utility power grid. normal source for the transfer switches. frequency for load sharing. They may
This is typically referred to as an The generators and the utility are never also require multiple levels of load
emergency standby generator continuously connected together in this shedding and/or load restoration
2 system. Figure 1.2-1 shows a single scheme. Multiple generators may be schemes to match generation capacity.
standby generator, utility source required to meet the load requirements Multiple Generators Operating in
and a transfer switch. In this case, the (N system). Generators may be applied
3 load is either supplied from the utility in an N+1 or a 2N system for improved
Parallel with Utility System
or the generator. The generator and system reliability. The third type of system is either one
the utility are never continuously with a single or multiple generators
4 connected together. This simple radial that operate in parallel with the utility
system has few requirements for Utility system. Figure 1.2-3 shows two
protection and control. It also has the G1 G2 generators and a utility source feeding
5 least impact on the complete electric a switchgear lineup feeding multiple
power distribution system. It should Switchgear
loads. This system typically requires
be noted that this type of generator generator capacity sufficient to carry
6 system improves overall electrical the entire load or sophisticated load
reliability but does not provide the shedding schemes. This system will
ATS-1 ATS-2
redundancy that some facilities require a complete and complex
7 require if the generator fails to protection and control scheme. The
start or is out for maintenance. electric utility may have very stringent
Load 1 Load 2 and costly protection requirements
8 for the system. IEEE standard 1547
Utility describes the interconnection require-
Figure 1.2-2. Multiple Isolated Set of ments for paralleling to the utility.
G1
9 Standby Generators
In an N system, where N is the number
Utility
of generators required to carry the
10 load; if a generator fails or is out for
G1 G2
16
17
18
19
20
21
Generator Fundamentals The application of generators requires derived system and a four-pole transfer
A generator consists of two primary
special protection requirements. switch is required or ground fault relays i
The size, voltage class, importance could misoperate and unbalanced
components, a prime mover and an and dollar investment will influence neutral current may be carried on
alternator. The prime mover is the the protection scheme associated with ground conductors. ii
energy source used to turn the rotor the generator(s). Mode of operation
of the alternator. It is typically a An IEEE working group has studied the
will influence the utility company’s practice of low resistance grounding
diesel combustion engine for most interface protection requirements. 1
emergency or standby systems. of medium voltage generators within
Paralleling with the electric utility is the general industry. This “working
In cogeneration applications, the the most complicated of the utility
prime mover may come from a steam group” found that, for internal generator
driven turbine or other source. On
inter-tie requirements. IEEE ANSI 1547 ground faults, the vast majority of the 2
provides recommended practices. damage is done after the generator
diesel units, a governor and voltage
regulator are used to control the speed breaker is tripped offline, and the field
and power output.
Generator Grounding and Bonding and turbine are tripped. This is due to 3
(Ref. NEC 2011, Article 250.30(A)(1) the stored energy in the generator flux
The alternator is typically a synchro- that takes several seconds to dissipate
nous machine driven by the prime and (2)) 4
after the generator is tripped offline.
mover. A voltage regulator controls its Generator grounding methods need It is during this time that the low
voltage output by adjusting the field. to be considered and may affect the resistance ground allows significant
The output of a single generator or distribution equipment and ratings. amounts of fault current to flow into 5
multiple paralleled generator sets is Generators may be connected in delta the ground fault. Because the large fault
controlled by these two inputs. The or wye, but wye is the most typical currents can damage the generator’s
alternator is designed to operate at a connection. A wye-connected generator winding, application of an alternate 6
specified speed for the required output can be solidly grounded, low impedance protection method is desirable during
frequency, typically 60 or 50 Hz. The grounded, high impedance grounded this time period. One of the solutions
voltage regulator and engine governor or ungrounded. Section 1.4 discusses set forth by this “working group” is 7
along with other systems define the general grounding schemes, benefits a hybrid high resistance grounding
generator’s response to dynamic of each and protection considerations. (HHRG) scheme as shown in
load changes and motor starting A solidly grounded generator may have Figure 1.2-4. In the HHRG scheme, 8
characteristics. a lower zero sequence impedance than the low resistance ground (LRG)
its positive sequence impedance. In this is quickly tripped offline when the
Generators are rated in power and
case, the equipment will need to be rated generator protection senses the 9
voltage output. Most generators are
for the larger available ground fault ground fault. The LRG is cleared
designed to operate at a 0.8 power
current. The generator’s neutral may at the same time that the generator
factor. For example, a 2000 kW
generator at 277/480V would have a be connected to the system-neutral; if breaker clears, leaving the high 10
it is, the generator is not a separately resistance ground portion connected
kVA rating of 2500 kVA (2000 kW/ 08 pf)
derived system and a three-pole transfer to control the transient overvoltages
and a continuous current rating
˙˙˙
of 3007A ( 2500 kVA ⁄ 480V 3 ) . switch is used. If the generator’s neutral during the coast-down phase of the 11
is bonded to ground separate from the generator, thereby all but eliminating
Typical synchronous generators system-neutral, it is a separately generator damage.
for industrial and commercial 12
power systems range in size from
100–3000 kVA and from 208V–13,800V.
Other ratings are available and these
HRG 13
discussions are applicable to those 51G
ratings as well. Gen R 59G
86
R LRG
14
Generators must be considered in the Phase 87GN
short-circuit and coordination study Relays
as they may greatly impact the rating 15
of the electrical distribution system.
This is especially common on large
installations with multiple generators 16
and systems that parallel with the
utility source. Short-circuit current
contribution from a generator 17
typically ranges from 8 to 12 times
Figure 1.2-4. Hybrid High Resistance Grounding Scheme
full load amperes.
18
19
20
21
Generator Controls A synch-scope is typically supplied The subtransient reactance Xd” will
i The engine generator set has controls
on paralleling gear. The synch-scope range from a minimum of approxi-
displays the relative relationship mately 9% for a two-pole, wound-rotor
to maintain the output frequency between voltage phasors on the machine to approximately 32% for a
ii (speed) and voltage. These controls
consist of a governor and voltage
generator to be paralleled and the low-speed, salient-pole, hydro-generator.
bus. If the generator is running slower The initial symmetrical fault current can
regulator. As loads change on the than the bus (less than 60 Hz) then the be as much as 12 times full load current.
1 system, the frequency and voltage needle on the scope will spin in the
will change. The speed control will counterclockwise direction. If it is Depending on the generator type,
then adjust the governor to correct running faster, then it will rotate in the zero sequence impedance may be
2 for the load (kW) change. The the clockwise direction. The greater less than the subtransient reactance
voltage regulator will change the the frequency difference, the faster and the ground fault current substan-
field current to adjust the voltage is the rotation. It is important that the tially higher than the three-phase
3 to the desired voltage value. These generators are in phase before they short-circuit current. For example, a
are the basic controls found on all are paralleled. Severe damage will 2500 kVA, 480/277V, four-pole, 2/3 pitch
synchronous generators. occur if generators are paralleled standby generator has a 0.1411 per
4 Multiple generator systems require out-of-phase. unit subtransient reactance Xd” and
a 0.033 per unit zero sequence X o
more sophisticated controls. reactance. The ground current is
Generators are paralleled in a multi- Generator Short-Circuit
5 generator system and they must share
approximately a third larger than the
Characteristics three-phase fault current. The ground
the load. These systems often have fault current can be reduced to the
a load shed scheme, which adds to
6 the complexity. If a short circuit is applied directly to three-phase level by simply adding a
the output terminals of a synchronous small reactance between the generator
Multiple generator schemes need a generator, it will produce an extremely neutral and ground while still being
7 master controller to prevent units from high current initially, gradually decaying considered solidly grounded.
being connected out-of-phase. The to a steady-state value. This change The electric power system analysis
sequence of operation is to send a is represented by a varying reactive must be performed based on the worst-
8 start signal to all generators simulta- impedance. Three specific reactances case operating conditions. Typically
neously. The first unit up to frequency are used for short-circuit fault currents. this is when all sources are paralleled.
and voltage will be permitted to close They are: If the system can operate with both
9 its respective breaker and energize the the utility supply and generators in
paralleling bus. Breakers for the other ■ Subtransient reactance Xd”, which
is used to determine the fault parallel, then the equipment must be
generators are held open, not permit- rated for the combined fault current
10 ted to close, until certain conditions current during the first 1 to 5 cycles
plus motor contribution. If the generator
are met. Once the paralleling bus is ■ Transient reactance Xd’, which is
used to determine the fault current and utility will not be paralleled, then
energized, the remaining generators both cases will need to be looked at
11 must be synchronized to it before during the next 5 to 200 cycles
independently and the worst case used
the generators can be paralleled. ■ Synchronous reactance Xd”, which
for selecting the equipment ratings.
Synchronization compares the voltage is used to determine the steady-
12 phasor’s angle and magnitude. Both state fault current
generators must be operating at the
same frequency and phase-matched
13 within typically 5 to 10 degrees with
each other. The voltage magnitude
typically must be within 20 to 24%.
14
15
16
17
18
19
20
21
Generator Protection
Generator protection will vary and
Generator Protection ANSI/IEEE i
Std 242-1986
depend on the size of the generator,
type of system and importance of the ii
generator. Generator sizes are defined
1 1 1 1
as: small—1000 kVA maximum up
Alternate
to 600V (500 kVA maximum when 51
Location
51V 32 40
1
above 600V); medium over 1000 kVA
to 12,500 kVA maximum regardless
of voltage; large—from 12,500– 2
50,000 kVA. The simplest is a single
generator system used to feed emer- 1 3
gency and/or standby loads. In this
Gen 51G 87 3
case, the generator is the only source
available when it is operating and 1
it must keep operating until the
51 Preferred 4
normal source returns. Location Gen
21
9
To Main Bus OC = Operating coil
PC = Permissive coil
10
Figure 1.2-7. Generator Percentage Differential Relay (Phase Scheme)
and Ground Differential Scheme Using a Directional Relay
11
12
13
14
15
16
17
18
19
20
21
18
19
20
21
i Generator Set Sizing Typical rating definitions for diesel Electrical rating definitions for natural
gensets are: standby, prime plus 10, gas powered gensets are typically
and Ratings continuous and load management defined as standby or continuous with
(paralleled with or isolated from definitions similar to those mentioned
ii Many factors must be considered utility). Any diesel genset can have above for diesels. Natural gas gensets
when determining the proper size or several electrical ratings depending recover more slowly than diesel
electrical rating of an electrical power on the number of hours of operation gensets when subjected to block
1 generator set. The engine or prime per year and the ratio of electrical loads. Diesel engines have a much
mover is sized to provide the actual load/genset rating when in operation. more direct path from the engine gov-
or real power in kW, as well as speed The same diesel genset can have a ernor and fuel delivery system to the
2 (frequency) control through the use
of an engine governor. The generator
standby rating of 2000 kW at 0.8 power combustion chamber and this results
factor (pf) and a continuous rating of in a very responsive engine-generator.
is sized to supply the kVA needed at 1825 kW at 0.8 pf. The lower continu- A natural gas engine is challenged
3 startup and during normal running ous rating is due to the additional with air-fuel flow dynamics and a
operation and it also provides voltage hours of operation and higher load much more indirect path from the
control using a brushless exciter and that the continuous genset must engine governor (throttle actuator)
4 voltage regulator. Together the engine carry. These additional requirements and fuel delivery system (natural
and generator provide the energy put more stress on the engine and gas pressure regulator, fuel valve and
necessary to supply electrical loads generator and therefore the rating actuator, carburetor mixer, aftercooler,
5 in many different applications is decreased to maintain longevity intake manifold) to the combustion
encountered in today’s society. of the equipment. chamber and this results in a
The generator set must be able to less responsive engine-generator.
6 supply the starting and running
Different generator set manufacturers Diesel gensets recover about twice
use basically the same diesel genset as fast as natural gas gensets.
electrical load. It must be able to electrical rating definitions and these
pick up and start all motor loads and
7 low power factor loads, and recover
are based on international diesel For the actual calculations involved
fuel stop power standards from for sizing a genset, there are readily
without excessive voltage dip or organizations like ISO, DIN and others. accessible computer software programs
extended recovery time. Nonlinear
8 loads like variable frequency drives,
A standby diesel genset rating is that are available on the genset manu-
typically defined as supplying varying facturer’s Internet sites or from the
uninterruptible power supply (UPS) electrical loads for the duration of a manufacturer’s dealers or distributors.
systems and switching power supplies
9 also require attention because the SCR
power outage with the load normally These programs are used to quickly
connected to utility, genset operating and accurately size generator sets for
switching causes voltage and current <100 hours per year and no overload their application. The programs take
waveform distortion and harmonics.
10 The harmonics generate additional
capability. A prime plus 10 rating is into consideration the many different
typically defined as supplying varying parameters discussed above, including
heat in the generator windings, and electrical loads for the duration of a the size and type of the electrical loads
the generator may need to be upsized
11 to accommodate this. The type of
power outage with the load normally (resistive, inductive, SCR, etc.), reduced
connected to utility, genset operating voltage soft starting devices (RVSS),
fuel (diesel, natural gas, propane, etc.) ≤500 hours per year and overload motor types, voltage, fuel type, site
12 used is important as it is a factor in capability of 10% above its rating for conditions, ambient conditions and
determining generator set transient 1 hour out of 12. A continuous rating other variables. The software will
response. It is also necessary to is typically defined as supplying optimize the starting sequences of the
13 determine the load factor or average unvarying electrical loads (i.e., base motors for the least amount of voltage
power consumption of the generator loaded) for an unlimited time. The load dip and determine the starting kVA
set. This is typically defined as the load management ratings apply to gensets needed from the genset. It also provides
14 (kW) x time (hrs. while under that in parallel operation with the utility transient response data, including
particular load) / total running time. or isolated/islanded from utility and voltage dip magnitude and recovery
When this load factor or average these ratings vary in usability from duration. If the transient response is
15 power is taken into consideration <200 hours per year to unlimited unacceptable, then design changes can
with peak demand requirements usage. Refer to generator set manufac- be considered, including oversizing
and the other operating parameters turers for further definitions on load the generator to handle the additional
16 mentioned above, the overall electrical
rating of the genset can be deter-
management ratings, load factor or kVAR load, adding RVSS devices to
average power consumption, peak reduce the inrush current, improving
mined. Other items to consider include demand and how these ratings are system power factor and other methods.
17 the unique installation, ambient, and typically applied. Even though there is The computer software programs are
site requirements of the project. These some standardization of these ratings quite flexible in that they allow changes
will help to determine the physical across the manufacturers, there also to the many different variables and
18 configuration of the overall system. exists some uniqueness with regard to parameters to achieve an optimum
how each manufacturer applies their design. The software allows, for
generator sets. example, minimizing voltage dips
19 or using paralleled gensets vs. a
single genset.
20
21
ii
10
11
12
13
14
15
16
17
18
19
20
21
11
12
13
14
15
16
17
18
19
20
21
i Short-Circuit Currents— The AC component is not constant rated secondary current. Limiting the
if rotating machines are connected power source fault capacity will thereby
General to the system because the impedance reduce the maximum fault current from
of this apparatus is not constant. The the transformer.
ii The amount of current available in a
short-circuit fault is determined by the
rapid variation of motor and generator
impedance is due to these factors: The electric network that determines
capacity of the system voltage sources the short-circuit current consists of an
1 and the impedances of the system, Subtransient reactance (x d" ), deter- AC driving voltage equal to the pre-fault
including the fault. Voltage sources mines fault current during the first system voltage and an impedance
include the power supply (utility or cycle, and after about 6 cycles this corresponding to that observed when
2 on-site generation) plus all rotating value increases to the transient reac- looking back into the system from the
machines connected to the system at tance. It is used for the calculation fault location. In medium and high
the time of the fault. A fault may be of the momentary interrupting and/or voltage work, it is generally satisfactory
3 either an arcing or bolted fault. In an momentary withstand duties of to regard reactance as the entire
arcing fault, part of the circuit voltage is equipment and/or system. impedance; resistance may be
consumed across the fault and the total neglected. However, this is normally
Transient reactance (x d' ), which deter-
4 fault current is somewhat smaller than
mines fault current after about 6 cycles
permissible only if the X/R ratio of the
for a bolted fault, so the latter is the medium voltage system is equal to or
worst condition, and therefore is the and this value in 1/2 to 2 seconds more than 25. In low voltage (1000V
increases to the value of the synchro-
5 value sought in the fault calculations.
nous reactance. It is used in the setting
and below) calculations, it is usually
worthwhile to attempt greater accuracy
Basically, the short-circuit current is of the phase OC relays of generators by including resistance with reactance
determined by applying Ohm’s Law and medium voltage circuit breakers.
6 to an equivalent circuit consisting of
in dealing with impedance. It is for this
Synchronous reactance (xd ), which reason, plus ease of manipulating the
a constant voltage source and a time- various impedances of cables and
varying impedance. A time-varying determines fault current after steady-
7 impedance is used in order to account state condition is reached. It has no buses and transformers of the low
effect as far as short-circuit calculations voltage circuits, that computer studies
for the changes in the effective voltages are recommended before final selection
of the rotating machines during the are concerned, but is useful in the
8 fault. In an AC system, the resulting determination of relay settings. of apparatus and system arrangements.
short-circuit current starts out higher Transformer impedance, in percent, is When evaluating the adequacy
in magnitude than the final steady- of short-circuit ratings of medium
9 state value and asymmetrical (due
defined as that percent of rated primary
voltage circuit breakers and fuses,
voltage that must be applied to the
to the DC offset) about the X-axis. transformer to produce rated current both the rms symmetrical value and
10 The current then decays toward a flowing in the secondary, with second- asymmetrical value of the short-circuit
lower symmetrical steady-state value. ary shorted through zero resistance. current should be determined.
The time-varying characteristic of the Therefore, assuming the primary
impedance accounts for the symmetri- For low voltage circuit breakers and
11 cal decay in current. The ratio of the
voltage can be sustained (generally fuses, the rms symmetrical value
referred to as an infinite or unlimited should be determined along with
reactive and resistive components (X/R supply), the maximum current a trans-
ratio) accounts for the DC decay, see either: the X/R ratio of the fault
12 Figure 1.3-1. The fault current consists
former can deliver to a fault condition is at the device or the asymmetrical
the quantity of (100 divided by percent short- circuit current.
of an exponentially decreasing direct- impedance) times the transformer
13 current component superimposed
upon a decaying alternating-current.
The rate of decay of both the DC and Total Current—A Wholly Offset
Asymmetrical Alternating Wave
14 AC components depends upon the
ratio of reactance to resistance (X/R) 3.0
rms Value of Total Current
of the circuit. The greater this ratio, Alternating Component -
2.5
15 the longer the current remains higher Symmetrical Wave
than the steady-state value that it rms Value of
2.0
would eventually reach. Alternating Component
16 The total fault current is not symmetrical 1.5
Scale of Curent Values
– ωt
------------
( – 2 ) ( 2 π 60 )
-------------------------------
120 –2 π
2
1. Ip = I 2 1 + e X ⁄ R I rms asym -------------------------------
X⁄R
------------
X⁄R
rms multiplication factor = ------------------------------ = 1 + 2e = 1 + 2e
I 3
– 2ωt Example for X/R =15
---------------
X⁄R
2. I rms asym = I 1 + 2e –π 4
-------
15
Peak mf = 2 1 + e
= 2.5612
Where: 5
I = Symmetrical rms current
–2 π
Ip = Peak current ----------
rms mf = 1 + 2e
15
= 1.5217 6
e = 2.718
ω=2πf 7
f = Frequency in Hz
t = Time in seconds 8
2.8
9
2.7 10
PEAK MAXIMUM ASYMMETRICAL
RMS SYMMETRICAL
2.5
2.4 12
2.3
13
2.2 1.8
R
O
CT
14
FA
2.1 1.7
N
PEAK MULTIPLICATION FACTOR =
O
TI
2.0 1.6
15
LI
IP
LT
1.9 1.5
U
M
OR
AK
CT 16
PE
1.8 FA 1.4
TION
1.7 LICA 1.3
UL
TIP 17
M
1.6 RMS 1.2
1.5 1.1
18
1.4
1 1.5 2 2.5 3 4 5 6 7 8 9 10 15 20 25 30 40 50 60 70 80 90 100 19
CIRCUIT X/R RATIO (TAN PHASE)
20
Figure 1.3-2. Relation of X/R Ratio to Multiplication Factor
21
i Fault Current Calculations Synchronous motors—use 5.0 times Medium Voltage Motors
motor full load current (impedance
value of 20%). If known, use actual values otherwise
The calculation of asymmetrical
use the values indicated for the same
currents is a laborious procedure since
ii the degree of asymmetry is not the
When the motor load is not known, type of motor.
the following assumptions generally
same on all three phases. It is common
practice for medium voltage systems,
are made: Calculation Methods
1 to calculate the rms symmetrical fault 208Y/120V Systems The following pages describe various
current, with the assumption being methods of calculating short-circuit
■ Assume 50% lighting and 50%
made that the DC component has currents for both medium and low
2 decayed to zero, and then apply
motor load
voltage systems. A summary of
a multiplying factor to obtain the first or the types of methods and types of
half-cycle rms asymmetrical current, calculations is as follows:
3 which is called the “momentary ■ Assume motor feedback contribu-
tion of twice full load current of ■ Medium voltage
current.” For medium voltage systems
transformer switchgear—exact
(defined by IEEE as greater than 1000V
4 up to 69,000V) the multiplying factor or
method . . . . . . . . . . . . . . Page 1.3-5
is established by NEMA® and ANSI ■ Medium voltage
standards depending upon the 240/480/600V Three-Phase, Three-Wire or switchgear—quick
5 operating speed of the breaker. For Four-Wire Systems check table . . . . . . . . . . . Page 1.3-7
low voltage systems, short-circuit ■ Assume 100% motor load ■ Medium voltage
study software usually calculates the switchgear
6 symmetrical fault current and the or Example 1—verify
faulted system X/R ratio using ANSI ratings of breakers. . . . . Page 1.3-8
■ Assume motors 25% synchronous
guidelines. If the X/R ratio is within the ■ Medium voltage
7 standard, and the breaker interrupting
and 75% induction
switchgear
current is under the symmetrical fault or Example 2—verify
value, the breaker is properly rated. ratings of breakers
8 If the X/R ratio is higher than ANSI ■ Assume motor feedback contribu- with rotating
standards, the study applies a multi- tion of four times full load current loads . . . . . . . . . . . . . . . . Page 1.3-9
plying factor to the symmetrical of transformer
9 calculated value (based on the
■ Medium voltage
480Y/277V Systems in Commercial Buildings switchgear Example 3
X/R value of the system fault) and —verify ratings of
compares that value to the breaker ■ Assume 50% induction motor load
10 symmetrical value to assess if it is
breakers with
or generators . . . . . . . . . . . Page 1.3-10
properly rated. In the past, especially
using manual calculations, a multiply- ■ Assume motor feedback contribu- ■ Medium voltage
11 ing factor of 1.17 (based on the use tion of two times full load current fuses—exact method. . . Page 1.3-11
of an X/R ratio of 6.6 representing of transformer or source ■ Power breakers—
a source short-circuit power factor asymmetry
12 of 15%) was used to calculate the derating factors . . . . . . . Page 1.3-11
asymmetrical current. These values ■ Molded-case
take into account that medium voltage breakers—asymmetry
13 breakers are rated on maximum derating factors . . . . . . . Page 1.3-12
asymmetry and low voltage breakers ■ Short-circuit
are rated average asymmetry.
14 calculations—
To determine the motor contribution short cut method
during the first half-cycle fault current, for a system . . . . . . . . . . Page 1.3-13
15 when individual motor horsepower ■ Short-circuit
load is known, the subtransient calculations—short
reactances found in the IEEE Red Book cut method for
16 should be used in the calculations. end of cable . . . . . . . . . . Page 1.3-15
When the system motor load is ■ Short-circuit
unknown, the following assumptions calculations—
17 generally are made: short cut method
for end of cable
Induction motors—use 4.0 times chart method . . . . . . . . . Page 1.3-16
18 motor full load current (impedance
■ Short-circuit currents—
value of 25%).
chart of transformers
Note: For motors fed through adjustable 300–3750 kVA . . . . . . . . . Page 1.5-9
19 frequency drives or solid-state soft starters,
there is no contribution to fault current, unless
1) they have an internal run contactor or
20 2) they have a bypass contactor.
21
The Close and Latch Capability The ANSI Standard C37.010 allows the Step 3: Reduce the reactance network
i This is also a related quantity use of the X values only in determin- to an equivalent reactance. Call this
expressed in rms asymmetrical ing the E/X value of a fault current. The reactance XI.
amperes by 1.6 x maximum R values are used to determine the X/R
ii symmetrical interrupting capability. ratio, in order to apply the proper Step 4: Set up the same network for
multiplying factor, to account for the resistance values.
For example, 1.6 x 36 = 57.6 or 58 kA,
or 1.6 K x rated short-circuit current. total fault clearing time, asymmetry, Step 5: Reduce the resistance network
1 and decrement of the fault current. to an equivalent resistance. Call this
Another way of expressing the close resistance RI. The above calculations
and latch rating is in terms of the peak The steps in the calculation of fault
of XI and RI may be calculated by
2 current, which is the instantaneous currents and breaker selection are
several computer programs.
value of the current at the crest. ANSI described hereinafter:
Standard C37.09 indicates that the Step 1: Collect the X and R data of the Step 6: Calculate the E/XI value, where
3 ratio of the peak to rms asymmetrical circuit elements. Convert to a common E is the prefault value of the voltage at
value for any asymmetry of 100% to kVA and voltage base. If the reactances the point of fault nominally assumed
20% (percent asymmetry is defined as and resistances are given either in 1.0 pu.
4 the ratio of DC component of the fault ohms or per unit on a different voltage X
in per unit to 2 ) varies not more than Step 7: Determine X/R = ------I as
or kVA base, all should be changed previously calculated. RI
±2% from a ratio of 1.69. Therefore, to the same kVA and voltage base.
5 the close and latch current expressed This caution does not apply where Step 8: Go to the proper curve for
in terms of the peak amperes is = 1.6 x the base voltages are the same as the type of fault under consideration
1.69 x K x rated short-circuit current. the transformation ratio. (three-phase, phase-to-phase, phase-
6 to-ground), type of breaker at the loca-
In the calculation of faults for the pur- Step 2: Construct the sequence
poses of breaker selection, the rotating tion (2, 3, 5 or 8 cycles), and contact
networks and connect properly for parting time to determine the multi-
7 machine impedances specified in ANSI the type of fault under consideration. plier to the calculated E/XI.
Standard C37.010 Article 5.4.1 should Use the X values required by ANSI
be used. The value of the impedances Standard C37.010 for the “interrupting” See Figures 1.3-3, 1.3-4 and 1.3-5 for
8 and their X/R ratios should be obtained duty value of the short-circuit current. 5-cycle breaker multiplying factors.
from the equipment manufacturer. At Use Figure 1.3-5 if the short circuit is
initial short-circuit studies, data from fed predominantly from generators
9 manufacturers is not available. Typical removed from the fault by two or more
values of impedances and their X/R
ratios are given in Table 1.3-1.
10
130 130 130
7
5
110 110
12 110
4
6
12
10
5
8
6
100 100 100
4
13 4
3
90 90 90 3
14 80 80 80
TIME
Ratio X/R
Ratio X/R
Ratio X/R
TIME
70 70 70
ING
15
RT
ING
60 60 60
PA
T
PAR
16
AC
50 50 50
NT
T
AC
CO
40
NT
40 40
17
CO
30 30 30
5-CYCLE 5-CYCLE 5-CYCLE
BREAKER BREAKER BREAKER
18 20 20 20
10 10 10
19
1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4
20 Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes
Figure 1.3-3. Three-phase Fault Multiplying Figure 1.3-4. Line-to-Ground Fault Multiplying Figure 1.3-5. Three-phase and Line-to-Ground
21 Factors that Include Effects of AC and Factors that Include Effects of AC and Fault Multiplying Factors that Include Effects
DC Decrement DC Decrement of DC Decrement Only
transformations or the per unit reac- The ANSI standards do not require the Application Quick Check Table i
tance external to the generation is 1.5 inclusion of resistances in the calcula-
times or more than the subtransient tion of the required interrupting and For application of circuit breakers in a
reactance of the generation on a com- close and latch capabilities. Thus the radial system supplied from a single
mon base. Also use Figure 1.3-5 where calculated values are conservative. source transformer. Short-circuit duty ii
the fault is supplied by a utility only. However, when the capabilities of was determined using E/X amperes
existing switchgears are investigated, and 1.0 multiplying factor for X/R ratio
Step 9: Interrupting duty short-circuit the resistances should be included. of 15 or less and 1.25 multiplying 1
current = E/XI x MFx = E/X2.
factor for X/R ratios in the range of
For single line-to-ground faults, the
Step 10: Construct the sequence 15 to 40.
(positive, negative and zero) networks
symmetrical interrupting capability 2
is 1.15 x the symmetrical interrupting Application Above 3,300 ft (1,000m)
properly connected for the type of capability at any operating voltage,
fault under consideration. Use the The rated one-minute power frequency
X values required by ANSI Standard
but not to exceed the maximum withstand voltage, the impulse with- 3
symmetrical capability of the breaker. stand voltage, the continuous current
C37.010 for the “Close and Latch”
duty value of the short-circuit current. Section 5 of ANSI C37 provides rating, and the maximum voltage rating
further guidance for medium voltage must be multiplied by the appropriate 4
Step 11: Reduce the network to an breaker application. correction factors below to obtain
equivalent reactance. Call the reac- modified ratings that must equal or
tance X. Calculate E/X x 1.6 if the Reclosing Duty exceed the application requirements. 5
breaker close and latch capability is ANSI Standard C37.010 indicates the
given in rms amperes or E/X x 2.7 if Note: Intermediate values may be obtained
reduction factors to use when circuit
the breaker close and latch capability breakers are used as reclosers. Eaton
by interpolation. 6
is given in peak or crest amperes. VCP-W breakers are listed at 100% Table 1.3-3. Altitude Derating
rating factor for reclosing.
Step 12: Select a breaker whose: Altitude in Correction Factor 7
Feet (Meters) Current Voltage
a. Maximum voltage rating exceeds
the operating voltage of the system: 3300 (1006) (and below)
5000 (1524)
1.00
0.99
1.00
0.95
8
E V max 10,000 (3048) 0.96 0.80
b. ------- ≤ I × -------------- ≤ KI
X2 Vo
Table 1.3-4. Application Quick Check Table 9
See Table 6.0-1, Tab 6. Source Operating Voltage
Transformer kV
Where: MVA Rating 10
I = Rated short-circuit current Motor Load 2.4 4.16 6.6 12 13.8
19
20
21
21
2 1 1 1 1 3 1 1 1 1 3
−−−− = −− + −− + −− = −− and −−− = −− + −− + −− = −−
XS X X X X RS R R R R
3 XS = X
G1 G2 G3
or X S = X R
----- and R S = ---- Therefore, System --------
X- = 30
----- = Gen ----
3 3 RS R R
4
Since generator neutral grounding reactors are used to limit the I LG to I3-phase or
below, we need only check the I3 short-circuit duty.
5
I I I 31
I B Phase = ----B- + ----B- + ----B- + ----------B- = 3(1.04)
4.16 kV
----------------------- = 28.4 kA Symmetrical E/X amperes
X X X X 0.11
6
System X
----- of 30 is a Multiplying Factor of 1.04 from Table 1.3-6.
7 R
Short-circuit duty is 28.4 (1.04) = 29.5 kA Symmetrical
8 Three-Phase Symmetrical Interrupting Capability Figure 1.3-8. Example 3—One-Line Diagram
Breaker Type V Max. at V Max. Max. KI at 4.16 kV Oper. Voltage
50VCP-W250 4.76 kV 29 kA 36 kA 4.76
9 4.16
(29) = 33.2 kA
10
11
12
13
14
15
16
17
18
19
20
21
Medium Voltage Fuses— Step 4—Construct the sequence includes induction and synchronous
motor loads. The assumption is made i
networks using resistances and
Fault Calculations connect properly for the type of that in 208Y/120V systems the contri-
fault under consideration and reduce bution from motors is two times the full
There are two basic types of medium to a single equivalent resistance. load current of step-down transformer. ii
voltage fuses. The following definitions This corresponds to an assumed 50%
are taken from ANSI Standard C37.40. Step 5—Calculate the E/XI value, motor aggregate impedance on a kVA
Expulsion Fuse (Unit)
where E is the prefault value of the base equal to the transformer kVA 1
voltage at the point of fault normally rating or 50% motor load. For 480V,
A vented fuse (unit) in which the assumed 1.0 in pu. For three-phase 480Y/277V and 600V systems, the
expulsion effect of the gases produced faults E/XI is the fault current to be assumption is made that the contribution 2
by internal arcing, either alone or aided used in determining the required inter- from the motors is four times the full
by other mechanisms, results in current rupting capability of the fuse. load current of the step-down trans-
interruption. former, which corresponds to an assumed 3
Note: It is not necessary to calculate a
Current-Limiting Fuse (Unit) single phase-to-phase fault current. This 25% aggregate motor impedance on a
current is very nearly 3 /2 x three-phase kVA base equal to the transformer kVA
A fuse unit that, when its current-
responsive element is melted by a
fault. The line-to-ground fault may exceed rating or 100% motor load. 4
the three-phase fault for fuses located in
current within the fuse’s specified generating stations with solidly grounded In low voltage systems that contain
current-limiting range, abruptly neutral generators, or in delta-wye trans- generators, the subtransient reactance 5
introduces a high resistance to formers with the wye solidly grounded, should be used.
reduce current magnitude and where the sum of the positive and negative
duration, resulting in subsequent sequence impedances on the high voltage If the X/R to the point of fault is greater
current interruption. side (delta) is smaller than the impedance of than 6.6, a derating multiplying factor 6
the transformer. (MF) must be applied. The X/R ratio is
There are two classes of fuses; calculated in the same manner as that
power and distribution. They are For single line-to-ground fault: for medium voltage circuit breakers. 7
distinguished from each other by X I = X I (+) + X I (–) + X I (0) Calculated symmetrical amperes x
the current ratings and minimum
MF ≤ breaker interrupting rating. 8
melting type characteristics.
E ×3
I f = ------ The multiplying factor MF can be
The current-limiting ability of a XI calculated by the formula:
current-limiting fuse is specified by 9
its threshold ratio, peak let-through – ( π ) ⁄ ( X/R )
current and I2t characteristics.
Step 6—Select a fuse whose 2 [ 1 + 2.718 ]
published interrupting rating MF = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
Interrupting Ratings of Fuses exceeds the calculated fault current.
2.29 10
If the X/R of system feeding the
Modern fuses are rated in amperes Figure 1.3-2 should be used where breaker is not known, use X/R = 15.
rms symmetrical. They also have a older fuses asymmetrically rated are 11
listed asymmetrical rms rating that involved. For fused breakers by the formula:
is 1.6 x the symmetrical rating.
The voltage rating of power fuses used
1 + 2 × ( 2.718 )
– ( 2π ) ⁄ ( X/R ) 12
Refer to ANSI/IEEE C37.48 for fuse on three-phase systems should equal MF = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
interrupting duty guidelines. or exceed the maximum line-to-line 1.25
20
21
Note: These are derating factors applied to the breaker and are the inverse of MF.
13
14
15
16
17
18
19
20
21
(b) % impedance = % Z =
(ohms impedance) (kVA base)
−−−−−−−−−−−−−−−−2−−−−−−−−−− −−−−−−−−−−−−−−
( kV ) ( 10 )
5
(% impedance) ( kV )2
(c) Ohms impedance = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−(10)
−−−−
kVA base 6
4. Change power-source impedance to per unit (a) —if utility fault capacity given in kVA
or percent impedance on kVA base as selected
for this study: kVA base in study
7
Per-unit impedance = pu Z = ------------------------------------------------------------------------------------------
-
power-source kVA fault capacity
(b) —if utility fault capacity given in rms symmetrical short circuit amperes 8
kVA base in study
Per-unit impedance = pu Z = ---------------------------------------------------------------------------------------------------------------
-
(short-circuit current) ( 3 )(kV of source) 9
5. Change motor rating to kVA: (a) —motor kVA — ( 3 ) (kV) (I) where I = motor nameplate full-load amperes
(b) —if 1.0 power factor synchronous motor kVA = (0.8) (hp)
10
(c) —if 0.8 power factor synchronous motor kVA = (1.0) (hp)
(d) —if induction motor kVA = (1.0) (hp)
(g)
(kV) (1000)
= ----------------------------------- 15
3 (ohms Z)
(a) Symmetrical short-circuit kVA = kVA base (kVA base) (100) ( kV )2 ( 1000 )
-------------------------- = ---------------------------------------------- = ----------------------------------
7. Determine symmetrical short-circuit kVA: ( puZ ) %Z ohms Z 16
3(line-to-neutral kV) 2 ( 1000 )
(b) = -----------------------------------------------------------------------------
(ohms Z)
17
8. Determine line-to-line short-circuit current: (a) —from three-phase transformer—approx. 86% of three-phase current
(b) —three single-phase transformers (e.g., 75 kVA, Z = 2%) calculate same as one three-phase
unit (i.e., 3 x 75 kVA = 225 kVA, Z = 2%). 18
(c) —from single-phase transformer—see Page 1.3-15.
19
9. Determine motor contribution (or feedback) as
source of fault current:
(a) —synchronous motor—5 times motor full load current (impedance 20%)
(b) —induction motor—4 times motor full-load current (impedance 25%)
See IEEE
Standard No. 141
(c) —motor loads not individually identified, use contribution from group of motors as follows:
—on 208Y/120V systems—2.0 times transformer full-load current 20
—on 240-480-600V three-phase, three-wire systems—4.0 times transformer full-load current
—on 480Y/277V three-phase, four-wire systems
—In commercial buildings, 2.0 times transformers full-load current (50% motor load)
—In industrial plants, 4.0 times transformer full-load current (100% motor load) 21
Example Number 1
i
How to Calculate Short-Circuit Currents at Ends of Conductors
ii A. System Diagram B. Impedance Diagram (Using “Short Cut” Method for Combining Impedances
and Sources).
1 A B C
Utility Source 500 MVA
Major Contribution
Utility
2
Cables
Transformer
3 1000 kV A
Switchboard Fault
5.75%
480V Cables
4
Cable Fault
Switchboard Fault
13 Equation
Step (See) Calculation
1 – Select 1000 kVA as most convenient base, since all data except utility source is on
secondary of 1000 kVA transformer.
14
2 4(a) kVA base
Utility per unit impedance = Z pu = ------------------------------------------ 1000
- = --------------------- = 0.002 pu
utility fault kVA 500.000
15 %Z = 5.75 = 0.0575 pu
3 3(a) Transformer per unit impedance = Z pu = ---------
- -----------
100 100
Example Number 2
i
Fault Calculation—Secondary Side of Single-Phase Transformer
30
kcmil
Step Two
25
Select the applicable chart from the following pages. The
16 charts are grouped by secondary system voltage, which is #4 A F 50,000
15
Step Three
18 Select the family of curves that is closest to the “available 10
source kVA.” The black line family of curves is for a source of
500,000 kVA. The lower value line (in red) family of curves is
19 for a source of 50,000 kVA. You may interpolate between
5
Select the specific curve for the conductor size being used. If Figure 1.3-13. 300 kVA Transformer/4.5% Impedance/208V
21 your conductor size is something other than the sizes shown
on the chart, refer to the conductor conversion Table 1.3-10.
B i
KV A
Fault Current in Thousands of Amperes (Sym.)
30 120
F
ii
25 100
F 50,000
W
WG
20 80 B
1
15 60 F 2
4
2
10 40
3
5 20 #4 AWG
A
4
0 0
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T
5
Figure 1.3-14. 500 kVA Transformer/4.5% Impedance/208V Figure 1.3-17. 1500 kVA Transformer/5.5% Impedance/208V
6
A A
7
Fault Current in Thousands of Amperes (Sym.)
60 120 –
– B
50 100 W
WG
W
WG
F 50,000 F 50,000 8
40 B 80
F
F 9
30 60
20 40
10
4– kcmil
10 20 11
0 0
0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000
12
Figure 1.3-15. 750 kVA Transformer/5.5% Impedance/208V Figure 1.3-18. 2000 kVA Transformer/5.5% Impedance/208V
13
kcmil A A
14
kcmil
Fault Current in Thousands of Amperes (Sym.)
60 12
50
B
10
15
F 50,000 B F 50,000
F
40 8 16
30 6 4
2 17
20 W
WG 4
18
10 2
0 0
19
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T
Figure 1.3-16. 1000 kVA Transformer/5.5% Impedance/208V Figure 1.3-19. 300 kVA Transformer/4.5% Impedance/480V
20
21
i
A A
Fault Current in Thousands of Amperes (Sym.)
2 15 B #1/0 AWG
#4 A
A
AWG
30
F
10 20
3 4 750 kcmil
5 10
4
0 0
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T
5
Figure 1.3-20. 500 kVA Transformer/4.5% Impedance/480V Figure 1.3-23. 1500 kVA Transformer/5.5% Impedance/480V
6
A A
7
Fault Current in Thousands of Amperes (Sym.)
30 60 4– kcmil
750
25 50 B W
WG
8 500
F 50,000 F 50,000
20 B 40
9 F
F
15 30
10 10
4– kcmil
20
#4 A
11 5 10
0 0
12 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000
Figure 1.3-21. 750 kVA Transformer/5.5% Impedance/480V Figure 1.3-24. 2000 kVA Transformer/5.5% Impedance/480V
13
14 A
Fault Current in Thousands of Amperes (Sym.)
30
W
WG
15 25
B
F 50,000
F
16 20
15
17 4 – 750 kcmil
2
10
18
5
19 0
0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T
21
10
11
12
13
14
15
16
17
18
19
20
21
21
Engine Generator Systems From the nameplate data on the motor, Example: 7
With an engine generator as the the full-load amperes of a 7-1/2 hp. Assuming a project having a
source of power, the type of starter 220V, 1750 rpm, three-phase, squirrel- 1000 kVA generator, where the
that will limit the inrush depends on cage motor is 19.0A. Therefore: voltage variation must not exceed
8
the characteristics of the generator. Starting current (%F.L.) = 10%. Can a 75 hp, 1750 rpm, 220V,
Although automatic voltage regulators three-phase, squirrel-cage motor be 9
are usually used with all AC engine- 10 × 100 × 1000 started without objectionable lamp
−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−− = 3.45 or 345%.
generators, the initial dip in voltage is 19.0 × 220 × 3 × 0.40 flicker (or 10% voltage drop)?
caused by the inherent regulation of 10
the generator and occurs too rapidly From tables in the circuit protective
From Table 1.3-11, a NEMA design C or
for the voltage regulator to respond. devices reference section, the full-load
NEMA design D motor with an autotrans-
It will occur whether or not a regulator amperes of this size and type of motor
is installed. Consequently, the percent
former starter gives approximately this
is 158A. To convert to same basis as 11
starting ratio. It could also be obtained
of initial voltage drop depends on the column 7, 158A must be divided by
from a properly set solid-state adjust-
ratio of the starting kVA taken by the the generator capacity and % voltage
motor to the generator capacity, the
able reduced voltage starter.
drop, or: 12
inherent regulation of the generator, The choice will depend upon the
158 = 0.0158A per kVA
torque requirements of the load since
the power-factor of the load thrown
on the generator, and the percentage the use of an autotransformer starter
1000 x 10 per 1% voltage drop 13
load carried by the generator. reduces the starting torque in direct Checking against the table, 0.0158 falls
proportion to the reduction in starting within the 0.0170–0.0146 range. This
A standard 80% power-factor engine- current. In other words, a NEMA indicates that a general-purpose motor
14
type generator (which would be design C motor with an autotrans- with autotransformer starting can
used where power is to be supplied former would have a starting torque be used.
to motor loads) has an inherent of approximately full-load (see Table
15
regulation of approximately 40% 1.3-11) whereas the NEMA design D Note: Designers may obtain calculated
from no-load to full-load. This means information from engine generator
motor under the same conditions
that a 50% variation in load would would have a starting torque of
manufacturers. 16
cause approximately 20% variation approximately 1-1/2 times full-load. The calculation results in conservative
in voltage (50% x 40% = 20%).
Note: If a resistance starter were used for results. The engineer should provide 17
Assume that a 100 kVA, 80% PF the same motor terminal voltage, the start- to the engine-generator vendor the
engine-type generator is supplying ing torque would be the same as that starting kVA of all motors connected to
the power and that the voltage drop obtained with autotransformer type, but the the generator and their starting sequence. 18
should not exceed 10%. Can a 7-1/2 hp, starting current would be higher, as shown. The engineer should also specify the
220V, 1750 rpm, three-phase, squirrel- maximum allowable drop. The engineer
cage motor be started without Shortcut Method should request that the engine-generator 19
exceeding this voltage drop? Column 7 in Table 1.3-11 has been vendor consider the proper generator
worked out to simplify checking. size when closed-transition autotrans-
Starting ratio =
The figures were obtained by using former reduced voltage starters, and 20
the formula above and assuming soft-start solid-state starter are used;
Percent voltage drop × gen. kVA × 1000
−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−− 1 kVA generator capacity and 1% so the most economical method of
F.L. amperes × volts × 3 × reg. of gen. voltage drop. installation is obtained. 21
Voltage Drop Formulas If the receiving end voltage, load current and power factor
i (PF) are known.
Approximate Method
2 2
Voltage Drop E VD = ( E R cosθ + I R ) + ( E R sinθ + I X ) – E R
ii
E VD = IR cosθ + IX sinθ
ER is the receiving end voltage.
1 where abbreviations are same as below “Exact Method.” Exact Method 2—If receiving or sending mVA and its power
factor are known at a known sending or receiving voltage.
Exact Methods
2 Voltage drop
2 2 ( ZMVA R )
2
- + 2ZMVA R cos ( γ – θ R )
E S = E R + ---------------------------------
Exact Method 1—If sending end voltage and load PF 2
ER
3 are known.
or
2 2
E VD = E S + IR cosθ + IX sinθ – E S – ( IX cosθ – IR sinθ )
4 2 2 ( ZMVA R )
2
- – 2ZMVA S cos ( γ – θ S )
E R = E S + ---------------------------------
where: 2
ES
5 EVD = Voltage drop, line-to-neutral, volts
where:
ES = Source voltage, line-to-neutral, volts
ER = Receiving line-line voltage in kV
6 I = Line (Load) current, amperes
ES = Sending line-line voltage in kV
R = Circuit (branch, feeder) resistance, ohms
7 X = Circuit (branch, feeder) reactance, ohms
MVAR = Receiving three-phase mVA
MVAS = Sending three-phase mVA
cosθ = Power factor of load, decimal
8 Z = Impedance between and receiving ends
sinθ = Reactive factor of load, decimal
γ = The angle of impedance Z
9 θR = Receiving end PF
θS = Sending end PF, positive when lagging
10
11
12
13
14
15
16
17
18
19
20
21
19
20
21
Table 1.3-13. Voltage Drop—Volts per Ampere per 100 Feet (30 m); Three-Phase, Phase-to-Phase
i Conductor Size Magnetic Conduit (Steel) Nonmagnetic Conduit (Aluminum or Nonmetallic)
AWG Load Power Factor, % Load Power Factor, %
or kcmil
ii 60 70 80 90 100 60 70 80 90 100
Copper Conductors
14 0.3390 0.3910 0.4430 0.4940 0.5410 0.3370 0.3900 0.4410 0.4930 0.5410
1 12 0.2170 0.2490 0.2810 0.3130 0.3410 0.2150 0.2480 0.2800 0.3120 0.3410
10 0.1390 0.1590 0.1790 0.1980 0.2150 0.1370 0.1580 0.1780 0.1970 0.2150
8 0.0905 0.1030 0.1150 0.1260 0.1350 0.0888 0.1010 0.1140 0.1250 0.1350
2 6
4
0.0595
0.0399
0.0670
0.0443
0.0742
0.0485
0.0809
0.0522
0.0850
0.0534
0.0579
0.0384
0.0656
0.0430
0.0730
0.0473
0.0800
0.0513
0.0849
0.0533
2 0.0275 0.0300 0.0323 0.0342 0.0336 0.0260 0.0287 0.0312 0.0333 0.0335
1 0.0233 0.0251 0.0267 0.0279 0.0267 0.0218 0.0238 0.0256 0.0270 0.0266
3 1/0 0.0198 0.0211 0.0222 0.0229 0.0213 0.0183 0.0198 0.0211 0.0220 0.0211
2/0 0.0171 0.0180 0.0187 0.0190 0.0170 0.0156 0.0167 0.0176 0.0181 0.0169
3/0 0.0148 0.0154 0.0158 0.0158 0.0136 0.0134 0.0141 0.0147 0.0149 0.0134
4 4/0 0.0130 0.0134 0.0136 0.0133 0.0109 0.0116 0.0121 0.0124 0.0124 0.0107
250 0.0122 0.0124 0.0124 0.0120 0.0094 0.0107 0.0111 0.0112 0.0110 0.0091
300 0.0111 0.0112 0.0111 0.0106 0.0080 0.0097 0.0099 0.0099 0.0096 0.0077
5 350 0.0104 0.0104 0.0102 0.0096 0.0069 0.0090 0.0091 0.0091 0.0087 0.0066
500 0.0100 0.0091 0.0087 0.0080 0.0053 0.0078 0.0077 0.0075 0.0070 0.0049
600 0.0088 0.0086 0.0082 0.0074 0.0046 0.0074 0.0072 0.0070 0.0064 0.0042
6 750
1000
0.0084
0.0080
0.0081
0.0077
0.0077
0.0072
0.0069
0.0063
0.0040
0.0035
0.0069
0.0064
0.0067
0.0062
0.0064
0.0058
0.0058
0.0052
0.0035
0.0029
Aluminum Conductors
7 12 0.3296 0.3811 0.4349 0.4848 0.5330 0.3312 0.3802 0.4328 0.4848 0.5331
10 0.2133 0.2429 0.2741 0.3180 0.3363 0.2090 0.2410 0.2740 0.3052 0.3363
8 0.1305 0.1552 0.1758 0.1951 0.2106 0.1286 0.1534 0.1745 0.1933 0.2115
8 6 0.0898 0.1018 0.1142 0.1254 0.1349 0.0887 0.1011 0.1127 0.1249 0.1361
4 0.0595 0.0660 0.0747 0.0809 0.0862 0.0583 0.0654 0.0719 0.0800 0.0849
2 0.0403 0.0443 0.0483 0.0523 0.0535 0.0389 0.0435 0.0473 0.0514 0.0544
1 0.0332 0.0357 0.0396 0.0423 0.0428 0.0318 0.0349 0.0391 0.0411 0.0428
9 1/0 0.0286 0.0305 0.0334 0.0350 0.0341 0.0263 0.0287 0.0322 0.0337 0.0339
2/0 0.0234 0.0246 0.0275 0.0284 0.0274 0.0227 0.0244 0.0264 0.0274 0.0273
3/0 0.0209 0.0220 0.0231 0.0241 0.0217 0.0160 0.0171 0.0218 0.0233 0.0222
10 4/0 0.0172 0.0174 0.0179 0.0177 0.0170 0.0152 0.0159 0.0171 0.0179 0.0172
250 0.0158 0.0163 0.0162 0.0159 0.0145 0.0138 0.0144 0.0147 0.0155 0.0138
300 0.0137 0.0139 0.0143 0.0144 0.0122 0.0126 0.0128 0.0133 0.0132 0.0125
11 350 0.0130 0.0133 0.0128 0.0131 0.0100 0.0122 0.0123 0.0119 0.0120 0.0101
500 0.0112 0.0111 0.0114 0.0099 0.0076 0.0093 0.0094 0.0094 0.0091 0.0072
600 0.0101 0.0106 0.0097 0.0090 0.0063 0.0084 0.0085 0.0085 0.0081 0.0060
12 750 0.0095 0.0094 0.0090 0.0084 0.0056 0.0081 0.0080 0.0078 0.0072 0.0051
1000 0.0085 0.0082 0.0078 0.0071 0.0043 0.0069 0.0068 0.0065 0.0058 0.0038
13
14
15
16
17
18
19
20
21
Capacitors and Power Factor ANSI Standard C37.06 (indoor oilless Low Voltage Capacitor Switching
i
circuit breakers) indicates the preferred
ratings of Eaton’s Type VCP-W vacuum Circuit breakers and switches for use
Capacitor General Application breaker. For capacitor switching, with a capacitor must have a current
Considerations careful attention should be paid to rating in excess of rated capacitor ii
the notes accompanying the table. current to provide for overcurrent from
Additional application information overvoltages at fundamental frequency
is available in Tab 35 regarding The definition of the terms are in ANSI
capacitors and harmonic filters Standard C37.04 Article 5.13 (for the and harmonic currents. The following 1
latest edition). The application guide percent of the capacitor-rated current
as follows: should be used as a general guideline:
ANSI/IEEE Standard C37.012 covers
■ Capacitor selection the method of calculation of the Fused and unfused switches. . . . 165% 2
■ Where to install capacitors in a plant quantities covered by C37.06 Standard.
distribution system Molded case breaker or
■ Locating capacitors on reduced
Note that the definitions in C37.04 equivalent . . . . . . . . . . . . . . . . . 150% 3
make the switching of two capacitors
voltage and multi-speed starters banks in close proximity to the switch- DSII power circuit breakers. . . . . 135%
■ Harmonic considerations gear bus a back-to-back mode of
Magnum DS power 4
■ Eliminating harmonic problems switching. This classification requires
circuit breaker . . . . . . . . . . . . . . 135%
■ National Electrical Code a definite purpose circuit breaker
requirements (breakers specifically designed for Contactors: 5
capacitance switching). Open type . . . . . . . . . . . . . . . . . . . 135%
Medium Voltage We recommend that such application
Capacitor Switching be referred to Eaton.
Enclosed type . . . . . . . . . . . . . . . . 150% 6
Capacitance switching constitutes The NEC, Section 460.8(C), requires
A breaker specified for capacitor the disconnecting means to be rated not
severe operating duty for a circuit switching should include as applicable: less than 135% of the rated capacitor
7
breaker. At the time the breaker opens
at near current zero, the capacitor is 1. Rated maximum voltage. current (for 600V and below).
fully charged. After interruption, when 2. Rated frequency. See Tab 35 for switching device 8
the alternating voltage on the source ampere ratings. They are based on
side of the breaker reaches its opposite 3. Rated open wire line charging percentage of capacitor-rated current
maximum, the voltage that appears switching current. as indicated (above). The interrupting 9
across the contacts of the open breaker rating of the switch must be selected
is at least twice the normal peak line- 4. Rated isolated cable charging and
to match the system fault current
to-neutral voltage of the circuit. If a shunt capacitor switching current.
available at the point of capacitor 10
breakdown occurs across the open 5. Rated back-to-back cable application. Whenever a capacitor
contact, the arc is re-established. Due charging and back-to-back bank is purchased with less than the
to the circuit constants on the supply capacitor switching current. ultimate kVAR capacity of the rack 11
side of the breaker, the voltage across or enclosure, the switch rating should
the open contact can reach three times 6. Rated transient overvoltage factor. be selected based on the ultimate
the normal line-to-neutral voltage. kVAR capacity—not the initial 12
After it is interrupted and with 7. Rated transient inrush current and
its frequency. installed capacity.
subsequent alternation of the supply
side voltage, the voltage across the 8. Rated interrupting time. Refer to Tab 35 for recommended 13
open contact is even higher. selection of capacitor switching
9. Rated capacitive current devices; recommended maximum
switching life. capacitor ratings for various motor 14
types and voltages; and for required
10. Grounding of system and multipliers to determine capacitor
capacitor bank. kVARs required for power factor 15
Load break interrupter switches correction.
are permitted by ANSI/IEEE Standard
C37.30 to switch capacitance, but they 16
must have tested ratings for the purpose.
Refer to Eaton Type MVS ratings.
17
18
19
20
21
i Motor Power Factor % AR—percent reduction in line To derate a capacitor used on a system
current due to the capacitor. A voltage lower than the capacitor
Correction capacitor located on the motor side voltage rating, such as a 240V
of the overload relay reduces line capacitor used on a 208V system,
ii See Tab 35 containing suggested
maximum capacitor ratings for
current through the relay. Therefore, a use the following formula:
different overload relay and/or setting
induction motors switched with the may be necessary. The reduction in Actual kVAR =
1 capacitor. The data is general in nature line current may be determined by
( Applied Voltage )
2
and representative of general purpose measuring line current with and Nameplate kVAR × ---------------------------------------------------------------------
-
induction motors of standard design. 2
without the capacitor or by calculation ( Nameplate Voltage )
2 The preferable means to select capacitor as follows:
ratings is based on the “maximum For the kVAC required to correct the
recommended kVAR” information (Original PF) power factor from a given value of
% AR = 100 – 100 × −−−−−−−−−−−−−−−−−−−−−−− COS φ1 to COS φ2, the formula is:
3 available from the motor manufacturer. (Improved PF)
If this is not possible or feasible, the
tables can be used. kVAC = kW (tan phase1–tan phase2)
If a capacitor is used with a lower kVAR
4 An important point to remember
rating than listed in tables, the % AR Capacitors cause a voltage rise.
can be calculated as follows: At light load periods the capacitive
is that if the capacitor used with the
motor is too large, self-excitation Actual kVAR voltage rise can raise the voltage at
5 may cause a motor-damaging over-
% AR = Listed % AR × −−−−−−−−−−−−−−−−−−−−−−−−
kVAR in Table
the location of the capacitors to an
voltage when the motor and capacitor unacceptable level. This voltage rise
combination is disconnected from the The tables can also be used for other can be calculated approximately by
6 line. In addition, high transient torques motor ratings as follows: the formula:
capable of damaging the motor shaft A. For standard 60 Hz motors MVA r
or coupling can occur if the motor is % VR = −−−−−−−−−−−
−
7 reconnected to the line while rotating
operating at 50 Hz: MVA SC
kVAR = 1.7–1.4 of kVAR listed
and still generating a voltage of % AR = 1.8–1.35 of % AR listed
self-excitation. MVAR is the capacitor rating and MVASC
8 B. For standard 50 Hz motors is the system short-circuit capacity.
Definitions operating at 50 Hz: With the introduction of variable speed
kVAR—rating of the capacitor in kVAR = 1.4–1.1 of kVAR listed
9 reactive kilovolt-amperes. This value % AR = 1.4–1.05 of % AR listed
drives and other harmonic current
generating loads, the capacitor
is approximately equal to the motor
C. For standard 60 Hz wound-rotor impedance value determined must
no-load magnetizing kilovars.
10 motors: not be resonant with the inductive
kVAR = 1.1 of kVAR listed reactances of the system.
% AR= 1.05 of % AR listed
11
Note: For A, B, C, the larger multipliers
apply for motors of higher speeds; i.e.,
12 3600 rpm = 1.7 mult., 1800 rpm = 1.65
mult., etc.
13
14
15
16
17
18
19
20
21
10,000
systems, communications systems,
1000
2000
3000
4000
5000
6000
7000
8000
9000
100
200
300
400
500
600
700
800
900
70
80
90
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
1000 1000
and the like. In addition, economic loss 900
800
700
4.16 kV 250 MVA
900
800
700
8
from outages can be extremely high 600
500
600
500
as a result of computer downtime, 400 400
TIME IN SECONDS
TIME IN SECONDS
6 6
the overcurrent disturbance so that the 5
20,000A
5
4 4
protective device closest to the fault
3 3
on the power-source side has the first A 175A
14
chance to operate; but each preceding 2 B C 2
.3
including motor
contribution.
.4
.3
16
of coordination is the degree to which Ground
the protective devices can minimize .2 Fault Trip .2
C
the damage to the faulted equipment.
.1 .1
17
.09 .09
To study and accomplish coordination .08
.07
.08
.07
requires (a) a one-line diagram, the .06 Transformer .06
.05
B Inrush .05
18
Max. Three-Phase
.03 .03
A
480V Fault
200
300
400
500
600
700
800
900
1000
2000
3000
4000
5000
6000
7000
8000
9000
10,000
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
A—CB (175A) coordinates selectively Maximum 480V three-phase fault available fault current at their point of
i with motor M on starting and running indicated on the horizontal current axis. application. All breakers are equipped
and with all upstream devices, except with long-time-delay (and possibly
that CB B will trip first on low level Maximum 4160V three-phase fault short delay) and instantaneous over-
ii ground faults. indicated, converted to 480V basis. current trip devices. A main breaker
4160 may have short time-delay tripping to
B—CB (600A) coordinates selectively I 480 V = I 4160 V × −−−−−−− allow a feeder breaker to isolate the
1 with all upstream and downstream 480
fault while power is maintained to all
devices, except will trip before A on the remaining feeders.
The ANSI protection curves are
limited ground faults, since A has no
specified in ANSI C57.109 for liquid-
2 ground fault trips.
filled transformers and C57.12.59 for
A selective or fully coordinated system
permits maximum service continuity.
C—Main CB (1600A) coordinates dry-type transformers.
The tripping characteristics of each
selectively with all downstream
3 devices and with primary fuse D,
Illustrative examples such as shown overcurrent device in the system must
here start the coordination study from be selected and set so that the breaker
for all faults on load side of CB. nearest the fault opens to isolate the
the lowest rated device proceeding
4 D—Primary fuse (250A, 4160V) coordi- upstream. In practice, the setting or faulted circuit, while all other breakers
nates selectively with all secondary rating of the utility’s protective device remain closed, continuing power to
protective devices. Curve converted to sets the upper limit. Even in cases the entire unfaulted part of the system.
5 480V basis. Clears transformer inrush where the customer owns the medium
The National Electrical Code
point (12 x FLC for 0.1 sec.), indicating voltage or higher distribution system,
contains specific requirements for
that fuse will not blow on inrush. the setting or rating of the lowest set
designing certain circuits with selective
6 Fuse is underneath right-half of ANSI protective device at the source deter-
coordination. Article 100 defines
three-phase withstand curve, indicating mines the settings of the downstream
selective coordination: Coordination
fuse will protect transformer for high- devices and the coordination.
(Selective), the following definition:
7 magnitude faults up to ANSI rating.
Therefore the coordination study “Localization of an overcurrent condi-
Delta-wye secondary side short should start at the present setting tion to restrict outages to the circuit or
equipment affected, accomplished by
8 circuit is not reflected to the primary or rating of the upstream device and
work toward the lowest rated device. If the choice of overcurrent protective
by the relation
this procedure results in unacceptable devices and their ratings or settings.”
9 V
I P = −−−S × I S
settings, the setting or rating of the NEC 2011 NFPA 70: National Electrical Code
VP upstream device should be reviewed. International Electrical Code Series.
Where the utility is the sole source,
Article 620.62 (elevators, dumbwaiters,
10 for L-L and L-G faults. For line-to-line they should be consulted. Where the
escalators, moving walks, wheelchair
fault, the secondary (low voltage) side owner has its own medium or higher
voltage distribution, the settings or lifts, and stairway chair lifts) requires
fault current is 0.866 x I three-phase
11 ratings of all upstream devices should “Where more than one driving machine
fault current.
be checked. disconnecting means is supplied by a
However, the primary (high voltage) single feeder, the overcurrent protective
If perfect coordination is not feasible, devices in each disconnecting means
12 side fault is the same as if the secondary
then lack of coordination should be shall be selectively coordinated with
fault was a three-phase fault. Therefore
in coordination studies, the knee of the limited to the smallest part of the system. any other supply side overcurrent
13 short-time pickup setting on the sec- Application data is available for all protective device.” A similar require-
ondary breaker should be multiplied by protective equipment to permit ment under Article 700.27 is as follows;
systems to be designed for adequate “Emergency system(s) overcurrent
14 −−−−1−−−− or 1.1547 overcurrent protection and coordina- devices shall be selectively coordinated
0.866 with all supply side overcurrent
tion. For circuit breakers of all types,
time-current curves permit selection of protective devices.” Article 701.27
before it is compared to the minimum
15 melting time of the upstream primary instantaneous and inverse-time trips. states that “Legally required standby
system(s) overcurrent devices shall be
fuse curve. In the example shown, the For more complex circuit breakers,
with solid-state trip units, trip curves selectively coordinated with all supply
knee is at 4000A 30 sec., and the 30-sec.
16 trip time should be compared to the include long- and short-time delays, side overcurrent devices.”
MMT (minimum melt time) of the fuse as well as ground-fault tripping, with a Exception: Selective coordination
curve at 4000 x 1.1547 = 4619A. In this wide range of settings and features to shall not be required between two
17 case, there is adequate clearance to provide selectivity and coordination. overcurrent devices located in series
the fuse curve. For current-limiting circuit breakers, if no loads are connected in parallel
fuses, and circuit breakers with with the downstream device.
18 In the example shown, the ANSI integral fuses, not only are time-
three-phase through fault protection current characteristic curves available, In addition, for health care facilities,
curve must be multiplied by 0.577 but also data on current-limiting Article 517.26, Application of Other
19 and replotted in order to determine performance and protection for Articles requires that “The essential
the protection given by the primary downstream devices. electrical system shall meet the
for a single line to ground fault in requirements of Article 700, except
20 the secondary. In a fully rated system, all circuit as amended by Article 517.”
breakers must have an interrupting
capacity adequate for the maximum
21
All breakers must have an interrupting Protection of Conductors (Excerpts E. Tap Conductors. Tap conductors
capacity not less than the maximum
from NFPA 70-2011, Article 240.4) shall be permitted to be protected i
available short-circuit current at their against overcurrent in accordance
point of application. A selective Conductors, other than flexible cords with the following:
system is a fully rated system with and fixture wires, shall be protected ii
tripping devices chosen and adjusted against overcurrent in accordance with 1. 210.19(A)(3) and (A)(4) Household
to provide the desired selectivity. their ampacities as specified in Section Ranges and Cooking Appliances
The tripping characteristics of each 310.15, unless otherwise permitted or and Other Loads. 1
overcurrent device should not overlap, required in (A) through (G). 2. 240.5(B)(2) Fixture Wire.
but should maintain a minimum time
interval for devices in series (to allow A. Power Loss Hazard. Conductor 3. 240.21 Location in Circuit. 2
for normal operating tolerances) at all overload protection shall not be
required where the interruption of 4. 368.17(B) Reduction in Ampacity
current values. Generally, a maximum
of four low voltage circuit breakers can the circuit would create a hazard, Size of Busway. 3
be operated selectively in series, with such as in a material handling
magnet circuit or fire pump circuit. 5. 368.17(C) Feeder or Branch Circuits
the feeder or branch breaker down- (busway taps).
stream furthest from the source. Short-circuit protection shall be 4
provided. 6. 430.53(D) Single Motor Taps.
Specify true rms sensing devices in
Note: FPN See NFPA 20-2003, standard
order to avoid false trips due to rapid for the Installation of Stationary Pumps Circuit Breaker Cable 5
currents or spikes. Specify tripping
elements with I2t or I4t feature for
for Fire Protection. Temperature Ratings
improved coordination with other B. Devices Rated 800A or Less. The UL listed circuit breakers rated 125A or 6
devices having I2t or I4t (such as next higher standard overcurrent less shall be marked as being suitable
OPTIM™ trip units) characteristics device rating (above the ampacity for 60ºC (140ºF), 75ºC (167ºF) only or
and fuses. of the conductors being protected) 60/75ºC (140/167ºF) wire. All Eaton 7
shall be permitted to be used, breakers rated 125A or less are marked
In general for systems such as shown 60/75ºC (140/167ºF). All UL listed circuit
in the example: provided all of the following
conditions are met. breakers rated over 125A are suitable 8
1. The settings or ratings of the for 75ºC conductors. Conductors rated
primary side fuse and main breaker 1. The conductors being protected for higher temperatures may be used,
must not exceed the settings are not part of a branch circuit but must not be loaded to carry more 9
allowed by NEC Article 450. supplying more than one recepta- current than the 75ºC ampacity of that
cle for cord-and-plug-connected size conductor for equipment marked
2. At 12 x IFL the minimum melting portable loads. or rated 75ºC or the 60ºC ampacity of 10
time characteristic of the fuse that size conductor for equipment
should be higher than 0.1 second. 2. The ampacity of the conductors
marked or rated 60ºC. However, when
does not correspond with the
3. The primary fuse should be to the standard ampere rating of a fuse or
applying derated factors, so long as 11
the actual load does not exceed the
left of the transformer damage a circuit breaker without overload
lower of the derated ampacity or the
curve as much as possible. The trip adjustments above its rating
correction factor for a single line- (but that shall be permitted to have
75ºC or 60ºC ampacity that applies. 12
to-ground factor must be applied other trip or rating adjustments).
to the damage curve.
Zone Selective Interlocking
3. The next higher standard rating Trip elements equipped with zone 13
4. The setting of the short-time delay selected does not exceed 800A. selective interlocking, trip without
element must be checked against intentional time delay unless a
the fuse MMT after it is corrected C. Overcurrent Devices Rated Over
restraint signal is received from 14
for line-to-line faults. 800A. Where the overcurrent
device is rated over 800A, the a protective device downstream.
Breakers equipped with this feature
5. The maximum fault current must ampacity of the conductors it
reduce the damage at the point of
15
be indicated at the load side of protects shall be equal to or
each protective device. greater than the rating of the fault if the fault occurs at a location
between the zone of protection.
6. The setting of a feeder protective
overcurrent device as defined in 16
Section 240.6. The upstream breaker upon receipt
device must comply with Article
240 and Article 430 of the NEC. D. Small Conductors. Unless of the restraint signal will not trip until
It also must allow the starting specifically permitted in 240.4(E) its time-delay setting times out. If the 17
and acceleration of the largest or 240.4(G), the overcurrent breaker immediately downstream of the
motor on the feeder while carrying protection shall not exceed 15A fault does not open, then after timing
all the other loads on the feeder. for 14 AWG, 20A for 12 AWG, and out, the upstream breaker will trip. 18
30A for 10 AWG copper; or 15A Breakers equipped with ground fault
for 12 AWG and 25A for 10 AWG trip elements should also be specified 19
aluminum and copper-clad to include zone interlocking for the
aluminum after any correction ground fault trip element.
factors for ambient temperature 20
and number of conductors have
been applied.
21
Ground Fault Protection Suggested Ground Fault Settings The Series G high performance,
i Article 230.95 of NEC requires ground-
current-limiting circuit breaker series
For the main devices: offers interrupting ratings to 200 kA.
fault protection of equipment shall be A ground fault pickup setting equal Frames are EGC, EGU, EGX, JGC,
ii provided for solidly grounded wye
electrical services of more than 150V
to 20–30% of the main breaker rating JGU, JGX, LGC, LGU and LGX.
but not to exceed 1200A, and a time
to ground, but not exceeding 600V delay equal to the delay of the short- Any of these current-limiting devices—
1 phase-to-phase for each service time element, but not to exceed fuses, fused breakers or current-limit-
disconnect rated 1000A or more. 1 second. ing breakers—cannot only clear these
large faults safely, but also will limit
The rating of the service disconnect the Ip and I2t let-through significantly
2 shall be considered to be the rating
For the feeder ground fault setting:
A setting equal to 20–30% of the feeder to prevent damage to apparatus
of the largest fuse that can be installed ampacity and a time delay to coordinate downstream, extending their zone
or the highest continuous current trip
3 setting for which the actual overcurrent
with the setting of the main (at least of protection. Without the current
6 cycles below the main). limitation of the upstream device,
device installed in a circuit breaker is the fault current could exceed the
rated or can be adjusted. If the desire to selectively coordinate
4 ground fault devices results in settings
withstand capability of the down-
The maximum allowable settings are: stream equipment. Underwriters
that do not offer adequate damage
1200A pickup, 1 second or less trip Laboratories tests and lists these
protection against arcing single line-
5 delay at currents of 3000A or greater. ground faults, the design engineer
series combinations. Application
information is available for
The characteristics of the ground-fault should decide between coordination
combinations that have been tested
and damage limitation.
6 trip elements create coordination and UL®-listed for safe operation
problems with downstream devices For low voltage systems with high- downstream from MDSL, TRI-PAC,
not equipped with ground fault magnitude available short-circuit and Current Limit-R, or Series C
7 protection. The National Electrical currents, common in urban areas and breakers of various ratings, under
Code exempts fire pumps and large industrial installations, several high available fault currents.
continuous industrial processes solutions are available. High interrupt-
Protective devices in electrical
8 from this requirement. ing Series C® molded case breakers,
distribution systems may be properly
It is recommended that in solidly current-limiting circuit breakers, or
coordinated when the systems are
grounded 480/277V systems where current-limiting fuses, limiters integral
9 designed and built, but that is no
main breakers are specified to be with molded-case circuit breakers
guarantee that they will remain
equipped with ground fault trip elements (TRI-PAC®) or mounted on power
coordinated. System changes and
that the feeder breakers be specified circuit breakers (MDSL) can be used to
10 additions, plus power source changes,
to be equipped with ground fault trip handle these large fault currents. To
frequently modify the protection
elements as well. provide current limiting, these devices
requirements, sometimes causing loss
must clear the fault completely within
11 of coordination and even increasing
the first half-cycle, limiting the peak
fault currents beyond the ratings of
current (Ip) and heat energy (I2t)
some devices. Consequently, periodic
let-through to considerably less than
12 what would have occurred without
study of protective-device settings
and ratings is as important for safety
the device. For a fully fusible system,
and preventing power outages
rule-of-thumb fuse ratios or more
13 accurate I2t curves can be used to
as is periodic maintenance of the
distribution system.
provide selectivity and coordination.
For fuse-breaker combinations, the
14 fuse should be selected (coordinated)
so as to permit the breaker to handle
those overloads and faults within its
15 capacity; the fuse should operate
before or with the breaker only on
large faults, approaching the interrupt-
16 ing capacity of the breaker, to minimize
fuse blowing. Recently, unfused, truly
current-limiting circuit breakers with
17 interrupting ratings adequate for the
largest systems (Type Series C, FDC,
JDC, KDC, LDC and NDC frames
18 or Type Current Limit-R®) have
become available.
19
20
21
Grounding above ground potential. Any person The equipment grounding system
i
coming in contact with such an object must be bonded to the grounding
Grounding encompasses several while grounded could be seriously electrode at the source or service;
different but interrelated aspects of injured or killed. In addition, current however, it may be also connected
electrical distribution system design flow from the accidental grounding of to ground at many other points. ii
and construction, all of which are an energized part of the system could This will not cause problems with
essential to the safety and proper generate sufficient heat (often with the safe operation of the electrical
operation of the system and equip- arcing) to start a fire. To prevent the distribution system. Where computers, 1
ment supplied by it. Among these establishment of such unsafe potential data processing, or microprocessor-
are equipment grounding, system difference requires that (1) the equip- based industrial process control
grounding, static and lightning ment grounding conductor provide a systems are installed, the equipment 2
protection, and connection to earth return path for ground fault currents of grounding system must be designed
as a reference (zero) potential. sufficiently low impedance to prevent to minimize interference with their
unsafe voltage drop, and (2) the equip- proper operation. Often, isolated 3
1. Equipment Grounding ment grounding conductor be large grounding of this equipment, or
enough to carry the maximum ground isolated electrical supply systems are
Equipment grounding is essential
fault current, without burning off, for required to protect microprocessors 4
to safety of personnel. Its function is
sufficient time to permit protective from power system “noise” that does
to ensure that all exposed noncurrent-
devices (ground fault relays, circuit not in any way affect motors or other
carrying metallic parts of all structures
breakers, fuses) to clear the fault. The electrical equipment. Such systems 5
and equipment in or near the electrical
grounded conductor of the system must use single-point ground concept
distribution system are at the same
(usually the neutral conductor), to minimize “noise” and still meet
potential, and that this is the zero
although grounded at the source, must the NEC requirements. Any separate 6
reference potential of the earth.
not be used for equipment grounding. isolated ground mat must be tied to
Equipment grounding is required
the rest of the facility ground mat
by both the National Electrical Code The equipment grounding conductor system for NEC compliance. 7
(Article 250) and the National Electrical may be the metallic conduit or raceway
Safety Code regardless of how the of the wiring system, or a separate 2. System Grounding
power system is grounded. Equipment equipment grounding conductor, 8
grounding also provides a return path run with the circuit conductors, as System grounding connects the
for ground fault currents, permitting permitted by NEC. If a separate electrical supply, from the utility, from
protective devices to operate. Acciden- equipment grounding conductor is transformer secondary windings, or 9
tal contact of an energized conductor used, it may be bare or insulated; if from a generator, to ground. A system
of the system with an improperly insulated, the insulation must be green, can be solidly grounded (no intentional
grounded noncurrent-carry metallic green with yellow stripe or green tape. impedance to ground), impedance 10
part of the system (such as a motor Conductors with green insulation may grounded (through a resistance or
frame or panelboard enclosure) would not be used for any purpose other than reactance), or ungrounded (with no
raise the potential of the metal object for equipment grounding. intentional connection to ground. 11
3. Medium Voltage System: Grounding
Table 1.4-1. Features of Ungrounded and Grounded Systems (from ANSI C62.92) 12
Description A B C D E
Ungrounded Solidly Grounded Reactance Grounded Resistance Grounded Resonant Grounded
13
(1) Apparatus Fully insulated Lowest Partially graded Partially graded Partially graded
insulation
(2) Fault to Usually low Maximum value rarely Cannot satisfactorily be Low Negligible except when 14
ground current higher than three-phase reduced below one-half Petersen coil is short
short circuit current or one-third of values for circuited for relay
solid grounding purposes when it may
compare with solidly 15
grounded systems
(3) Stability Usually unimportant Lower than with other Improved over solid Improved over solid Is eliminated from
methods but can be grounding particularly grounding particularly consideration during 16
made satisfactory by use if used at receiving end if used at receiving end single line-to-ground
of high-speed breakers of system of system faults unless neutralizer
is short circuited to
isolate fault by relays
17
(4) Relaying Difficult Satisfactory Satisfactory Satisfactory Requires special
provisions but can be
made satisfactory 18
(5) Arcing Likely Unlikely Possible if reactance is Unlikely Unlikely
grounds excessive
(6) Localizing Effect of fault transmitted Effect of faults localized Effect of faults localized to Effect of faults Effect of faults 19
faults as excess voltage on to system or part of system or part of system transmitted as excess transmitted as excess
sound phases to all system where they occur where they occur unless voltage on sound phases voltage on sound phases
parts of conductively
connected network
reactance is quite high to all parts of conductively
connected network
to all parts of conductively
connected network
20
(7) Double Likely Likely Unlikely unless Unlikely unless Seem to be more likely
faults reactance is quite high resistance is quite high but conclusive information
and insulation weak and insulation weak not available 21
ii (8) Lightning
protection
Ungrounded neutral Highest efficiency and
service arresters must be lowest cost
If reactance is very high
arresters for ungrounded
Arresters for ungrounded,
neutral service usually
Ungrounded neutral
service arresters must
applied at sacrifice in cost neutral service must be must be applied at be applied at sacrifice
and efficiency applied at sacrifice in cost sacrifice in cost and in cost and efficiency
1 and efficiency efficiency
(9) Telephone Will usually be low Will be greatest in Will be reduced from Will be reduced from Will be low in magnitude
interference except in cases of double magnitude due to higher solidly grounded values solidly grounded values except in cases of double
2 faults or electrostatic fault currents but can faults or series resonance
induction with neutral be quickly cleared at harmonic frequencies,
displaced but duration particularly with high but duration may be great
3 may be great speed breakers
(10) Radio May be quite high during Minimum Greater than for Greater than for May be high during faults
interference faults or when neutral solidly grounded, solidly grounded,
is displayed when faults occur when faults occur
4 (11) Line Will inherently clear Must be isolated for Must be isolated for Must be isolated for Need not be isolated but
availability themselves if total length each fault each fault each fault will inherently clear itself
of interconnected line is in about 60 to 80 percent
5 low and require isolation of faults
from system in increas-
ing percentages as length
6 becomes greater
(12) Adaptability Cannot be interconnected Satisfactory indefinitely Satisfactory indefinitely Satisfactory with solidly- Cannot be interconnected
to interconnection unless interconnecting with reactance-grounded with solidly-grounded or reactance-grounded unless interconnected
7 system is ungrounded
or isolating transformers
systems systems systems with proper
attention to relaying
system is resonant
grounded or isolating
are used transformers are used.
Requires coordination
8 between interconnected
systems in neutralizer
settings
9 (13) Circuit Interrupting capacity Same interrupting Interrupting capacity Interrupting capacity Interrupting capacity
breakers determined by three- capacity as required for determined by three- determined by three- determined by three-
phase conditions three-phase short circuit phase fault conditions phase fault conditions phase fault conditions
will practically always be
10 satisfactory
(14) Operating Ordinarily simple but Simple Simple Simple Taps on neutralizers must
procedure possibility of double be changed when major
11 faults introduces system switching is per-
complication in times formed and difficulty may
of trouble arise in interconnected
12 systems. Difficult to tell
where faults are located
(15) Total cost High, unless conditions Lowest Intermediate Intermediate Highest unless the arc
are such that arc tends suppressing characteris-
13 to extinguish itself, when tic is relied on to eliminate
transmission circuits may transmission circuits
be eliminated, reducing when it may be lowest
14 total cost for the particular types
of service
Table 1.4-2 taken from ANSI-C62.92 should not be limited to less than the Grounding Point
indicates the characteristics of the current transformers rating of the The most commonly used grounding i
various methods of grounding. source. This rule will provide sensitive point is the neutral of the system or the
differential protection for wye-connected neutral point created by means of a
Reactance Grounding generators and transformers against zigzag or a wye-broken delta grounding ii
It is generally used in the grounding line-to-ground faults near the neutral. transformer in a system that was oper-
of the neutrals of generators directly Of course, if the installation of ground ating as an ungrounded delta system.
connected to the distribution system fault differential protection is feasible, 1
bus, in order to limit the line-to-ground or ground sensor current transformers In general, it is a good practice that all
fault to somewhat less than the three- are used, sensitive differential relaying source neutrals be grounded with the
phase fault at the generator terminals. in resistance grounded system with same grounding impedance magnitude. 2
If the reactor is so sized, in all probability greater fault limitation is feasible. However, neutrals should not be tied
the system will remain effectively In general, ground sensor current together to a single resistor. Where
grounded. transformers (zero sequence) do not one of the medium voltage sources is 3
have high burden capacity. Resistance the utility, their consent for impedance
Resistance Grounded grounded systems limit the circulating grounding must be obtained.
Medium voltage systems in general currents of triple harmonics and limit 4
should be low resistance grounded. The neutral impedance must have a
the damage at the point of fault. This
The ground fault is typically limited to voltage rating at least equal to the rated
method of grounding is not suitable
about 200–400A but less than 1000A for line-to-neutral connection of loads.
line-to-neutral voltage class of the sys- 5
(a cable shield consideration). With a tem. It must have at least a 10-second
properly sized resistor and relaying On medium voltage systems, 100% rating equal to the maximum future
application, selective fault isolation cable insulation is rated for phase-to- line-to-ground fault current and a 6
is feasible. The fault limit provided neutral voltage. If continued operation continuous rating to accommodate the
has a bearing on whether residually with one phase faulted to ground is triple harmonics that may be present.
connected relays are used or ground desired, increased insulation thick- 7
sensor current transformers are used ness is required. For 100% insulation, 4. Low Voltage System: Grounding
for ground fault relaying. fault clearance is recommended within Solidly grounded three-phase systems
one minute; for 133% insulation, one (Figure 1.4-2) are usually wye- 8
In general, where residually connected hour is acceptable; for indefinite connected, with the neutral point
ground relays are used (51N), the fault operation, as long as necessary, grounded. Less common is the “red-
current at each grounded source 173% insulation is required. leg” or high-leg delta, a 240V system 9
supplied by some utilities with one
Table 1.4-2. Characteristics of Grounding winding center-tapped to provide 120V
Grounding Classes Ratios of Symmetrical Percent Fault Per Unit Transient to ground for lighting. This 240V, three- 10
and Means Component Parameters Current LG Voltage phase, four-wire system is used where
120V lighting load is small compared
A. Effectively ➃
X0/X1 R0/X1 R0/X0
to 240V power load, because the 11
1. Effective 0-3 0-1 — >60 ≤2 installation is low in cost to the utility.
2. Very effective 0-1 0-0.1 — >95 <1.5 A corner-grounded three-phase delta
B. Noneffectively system is sometimes found, with 12
1. Inductance one phase grounded to stabilize all
a. Low inductance 3-10 0-1 — >25 <2.3 voltages to ground. Better solutions
b. High inductance >10 — <2 <25 ≤2.73
are available for new installations. 13
2. Resistance
a. Low resistance 0-10 — ≥2 <25 <2.5
b. High resistance — >100 ≤(-1) <1 ≤2.73
3. Inductance and resistance >10 — >2 <10 ≤2.73
Phase A 14
4. Resonant — — <1 ≤2.73 • • • Phase B
N
5. Ungrounded/capacitance
a. Range A -∞ to -40 — — <8 ≤3 • Phase C
15
b. Range B -40 to 0 — — >8 >3 • Neutral
Values of the coefficient of grounding (expressed as a percentage of maximum phase-to-phase
Grounded Wye
voltage) corresponding to various combinations of these ratios are shown in the ANSI C62.92
Appendix figures. Coefficient of grounding affects the selection of arrester ratings.
16
Ground-fault current in percentage of the three-phase short-circuit value. • Phase B
Transient line-to-ground voltage, following the sudden initiation of a fault in per unit of the crest
of the prefault line-to-ground operating voltage for a simple, linear circuit. • • • Phase C
Phase A
17
In linear circuits, Class A1 limits the fundamental line-to-ground voltage on an unfaulted phase to
138% of the prefault voltage; Class A2 to less than 110%. • Neutral
See ANSI 62.92 para. 7.3 and precautions given in application sections. 18
Usual isolated neutral (ungrounded) system for which the zero-sequence reactance is capacitive Center-Tapped (High-Leg) Delta
(negative).
Same as NOTE (6) and refer to ANSI 62.92 para. 7.4. Each case should be treated on its own merit. • Phase A 19
Under restriking arcing ground fault conditions (e.g., vacuum breaker interrupter operation),
this value can approach 500%. • • Phase B
Under arcing ground fault conditions, this value can easily reach 700%, but is essentially unlimited. • Phase C
20
Corner-Grounded Delta
Ungrounded systems (Figure 1.4-3) Selecting the Low Voltage System used as substitutes for ungrounded
i can be either wye or delta, although Grounding Method systems where high system
the ungrounded delta system is far There is no one “best” distribution availability is required.
more common. system for all applications. In choosing
ii among solidly grounded, resistance
With one phase grounded, the voltage
to ground of the other two phases
grounded, or ungrounded power rises 73%, to full phase-to-phase
• Phase A
distribution, the characteristics of the
1 system must be weighed against the
voltage. In low voltage systems this
• • Phase B
Phase C requirements of power loads, lighting
is not important, since conductors
are insulated for 600V.
loads, continuity of service, safety
2 Ungrounded Delta
and cost. A low voltage resistance grounded
Phase A system is normally grounded so that
• • • Phase B Under ground fault conditions, each the single line-to-ground fault current
3 N system behaves very differently. A exceeds the capacitive charging
• Phase C solidly grounded system produces current of the system. If data for the
Ungrounded Wye high fault currents, usually with arcing, charging current is not available, use
4 and the faulted circuit must be cleared 40–50 ohm resistor in the neutral
Figure 1.4-3. Ungrounded Systems on the first fault within a fraction of a of the transformer.
second to minimize damage. An
5 Resistance-grounded systems ungrounded system will pass limited In commercial and institutional
(Figure 1.4-4) are simplest with a current into the first ground fault— installations, such as office buildings,
wye connection, grounding the neutral only the charging current of the system, shopping centers, schools and hospitals,
6 point directly through the resistor. caused by the distributed capacitance lighting loads are often 50% or more
Delta systems can be grounded by to ground of the system wiring and of the total load. In addition, a feeder
means of a zig-zag or other grounding equipment. In low voltage systems, outage on first ground fault is seldom
7 transformer. Wye broken delta this is rarely more than 1 or 2A. crucial—even in hospitals, that have
transformer banks may also be used. Therefore, on first ground fault, an emergency power in critical areas. For
ungrounded system can continue in these reasons, a solidly grounded wye
8 service, making it desirable where distribution, with the neutral used for
Phase A lighting circuits, is usually the most
power outages cannot be tolerated.
• • • Phase B
However, if the ground fault is economical, effective and convenient
N
9 R • Phase C intermittent, sputtering or arcing, a design. In some instances, it is an
high voltage—as much as 6 to 8 times NEC requirement.
phase voltage—can be built up across
10 Resistance-Grounded Wye the system capacitance, from the In industrial installations, the effect
phase conductors to ground. Similar of a shutdown caused by a single
high voltages can occur as a result ground fault could be disastrous.
11 • • Phase A
An interrupted process could cause
of resonance between system
the loss of all the materials involved,
• • • Phase B capacitance and the inductances
• Phase C
of transformers and motors in the often ruin the process equipment
12 • system. The phase-to-phase voltage itself, and sometimes create extremely
N • is not affected. This high transient dangerous situations for operating
R • phase-to-ground voltage can puncture personnel. On the other hand, lighting
13 insulation at weak points, such as is usually only a small fraction of the
motor windings, and is a frequent total industrial electrical load. A solidly
Delta With Derived Neutral Resistance-
cause of multiple motor failures on grounded neutral circuit conductor
14 Grounded Using Zig-Zag Transformer
ungrounded systems. Locating a first is not imperative and, when required,
fault on an ungrounded system can can be obtained from inexpensive
Figure 1.4-4. Resistance-Grounded Systems be difficult. If, before the first fault is lighting transformers.
15 cleared, a second ground fault occurs Because of the ability to continue in
This derives a neutral point, which
can be either solidly or impedance- on a different phase, even on a operation with one ground fault on
different, remote feeder, it is a high-
16 grounded. If the grounding transformer
current phase-to-ground-to-phase
the system, many existing industrial
plants use ungrounded delta distribu-
has sufficient capacity, the neutral
created can be solidly grounded and fault, usually arcing, that can cause tion. Today, new installations can have
severe damage if at least one of the
17 used as part of a three-phase, four-wire
grounds is not cleared immediately.
all the advantages of service continuity
system. Most transformer-supplied of the ungrounded delta, yet minimize
systems are either solidly grounded If the second circuit is remote, enough the problems of the system, such
current may not flow to cause
18 or resistance grounded. Generator
protection to operate. This can leave
as the difficulty of locating the first
neutrals are often grounded through ground fault, risk of damage from a
a reactor, to limit ground fault (zero high voltages and stray currents on second ground fault, and damage
structures and jeopardize personnel.
19 sequence) currents to values the transient overvoltages. A high-
generator can withstand. In general, where loads will be resistance grounded wye distribution
connected line-to-neutral, solidly can continue in operation with a
20 grounded systems are used. High ground fault on the system and will
resistance grounded systems are not develop transient overvoltages.
21
However, should any conductor become neutral. In a residual sensing scheme, levels of ground fault protection are
i grounded, the fault current will return the relationship of the polarity markings desired for added service continuity.
along the ground path—not the normal —as noted by the “X” on each sensor— Additional grounding points may be
circuit conductors—and the sensor will is critical. Because the vectorial sum of employed upstream of the residual
ii have an unbalanced magnetic flux the currents in all the conductors will sensors, but not on the load side.
condition, and a sensor output will total zero under normal, non-ground
be generated to actuate the ground faulted conditions, it is imperative Both the zero sequence and
1 fault relay. that proper polarity connections are residual sensing methods have
employed to reflect this condition. been commonly referred to as
“vectorial summation” methods.
2 Zero
Sequence
Sensor
Alternate
Sensor
Location Sensor
Most distribution systems can use
Residual
Main Polarity
Marks
Sensors either of the three sensing methods
exclusively or a combination of the
3 Main
sensing methods depending upon
Neutral the complexity of the system and
the degree of service continuity and
4 GFR
Neutral
selective coordination desired.
Typical
Feeder
Typical Different methods will be required
GFR Feeder
depending upon the number of supply
5 Typical sources, and the number and location
4W Load Typical
4W Load
of system grounding points.
6 Figure 1.4-6. Zero Sequence Sensing Method As an example, one of the more
Figure 1.4-7. Residual Sensing Method frequently used systems where
Zero sequence sensors are available continuity of service to critical loads
As with the zero sequence sensing
7 with various window openings for
method, the resultant residual sensor is a factor is the dual source system
circuits with small or large conductors, illustrated in Figure 1.4-8. This system
and even with large rectangular win- output to the ground fault relay or
integral ground fault tripping circuit uses tie-point grounding as permitted
8 dows to fit over bus bars or multiple
large size conductors in parallel. Some will be zero if all currents flow only under NEC Sec. 250.24(A)(3). The use
sensors have split cores for installation in the circuit conductors. Should a of this grounding method is limited
over existing conductors without ground fault occur, the current from to services that are dual fed (double-
9 disturbing the connections. the faulted conductor will return along ended) in a common enclosure or
the ground path, rather than on the grouped together in separate enclosures,
This method of sensing ground faults other circuit conductors, and the resid- employing a secondary tie.
10 can be employed on the main discon- ual sum of the sensor outputs will not
nect where protection per NEC (230.95) This scheme uses individual sensors
be zero. When the level of ground fault connected in ground return fashion.
is desired. It can also be easily employed
current exceeds the pre-set current
11 in multi-tier systems where additional
and time delay settings, a ground
Under tie breaker closed operating
levels of ground fault protection are conditions, either the M1 sensor or
desired for added service continuity. fault tripping action will be initiated. M2 sensor could see neutral unbalance
12 Additional grounding points may be This method of sensing ground faults currents and possibly initiate an
employed upstream of the sensor, but can be economically applied on main improper tripping operation. However,
not on the load side. with the polarity arrangements of
service disconnects where circuit break-
13 Ground fault protection employing ers with integral ground fault protection these two sensors along with the tie
ground return or zero sequence sensing are provided. It can be used in protec- breaker auxiliary switch (T/a) and
methods can be accomplished by the tion schemes per NEC (230.95) or in interconnections as shown, this
14 use of separate ground fault relays multi-tier schemes where additional possibility is eliminated.
(GFRs) and disconnects equipped with
standard shunt trip devices or by circuit
15 breakers with integral ground fault Power Power
protection with external connections Transformer Transformer
arranged for these modes of sensing. In
16 some cases, a reliable source of control
Neutral Sensor Neutral Sensor
power is needed. Main Main
Bkr. Main Bkr. 52-1 Tie Bkr. Main Bkr. 52-2 Bkr.
The third basic method of detecting 52-T 52-2
17 ground faults involves the use of
52-1
ØA, ØB, ØC ØA, ØB, ØC
multiple current sensors connected in Neutral Neutral
Neutral Sensor
a residual sensing method as illustrated
18 in Figure 1.4-7. This is a very common Typical ( )B5
Tie Bkr. 52-T
Typical
( )B5
4-Wire ( )B4
sensing method used with circuit break- ( )B4 52-T 52-T 4-Wire
M2N
M1G
M2G
M1N
Feeder
TN
TG
a a Feeder
ers equipped with electronic trip units,
19 current sensors and integral ground 33-
52-T
fault protection. The three-phase sensors 4-Wire 4-Wire
B5 B4 B4 B5 B4 B5 Load
are required for normal phase overcur- Load
Digitrip Digitrip Digitrip
20 rent protection. Ground fault sensing B4
Digitrip
B5 Main Bkr.
52-1
Main Bkr.
52-T
Main Bkr.
52-2
B4
Digitrip
B5
is obtained with the addition of an
identically rated sensor mounted on the
21 Figure 1.4-8. Dual Source System—Single Point Grounding
Note: This GF scheme requires trip units to be set to source ground sensing.
Selective ground fault tripping coordi- or a combination of all types may be GFR is an indication that any occurring
nation between the tie breaker and the employed to accomplish the desired ground fault is within the zone of the i
two main circuit breakers is achieved end results. GFR next upstream from the fault and
by pre-set current pickup and time that device will operate instantaneously
delay settings between devices GFR/1, Because the NEC (230.95) limits the to clear the fault with minimum dam- ii
GFR/2 and GFR/T. maximum setting of the ground fault age and maximum service continuity.
protection used on service equipment This operating mode permits all GFRs
The advantages of increased service to 1200A (and timed tripping at 3000A to operate instantaneously for a fault 1
continuity offered by this system can for one second), to prevent tripping within their zone and still provide
only be effectively used if additional of the main service disconnect on a complete selectivity between zones.
levels of ground fault protection are feeder ground fault, ground fault The National Electrical Manufacturers 2
added on each downstream feeder. protection must be provided on all the Association (NEMA) states, in their
Some users prefer individual grounding feeders. To maintain maximum service application guide for ground fault
of the transformer neutrals. In such continuity, more than two levels (zones) protection, that zone interlocking is 3
cases, a partial differential ground of ground fault protection will be necessary to minimize damage from
fault scheme should be used for the required, so that ground fault outages ground faults. A two-wire connection
mains and tie breaker. can be localized and service interrup- is required to carry the restraining 4
tion minimized. To obtain selectivity signal from the GFRs in one zone to
An example of a residual partial differ- between different levels of ground
ential scheme is shown in Figure 1.4-9. the GFRs in the next zone.
The scheme typically relies upon the
fault relays, time delay settings should 5
be employed with the GFR furthest Circuit breakers with integral ground
vector sum of at least two neutral downstream having the minimum fault protection and standard circuit
sensors in combination with each
breakers’ three-phase sensors. To
time delay. This will allow the GFR breakers with shunt trips activated 6
nearest the fault to operate first. by the ground fault relay are ideal for
reduce the complexity of the drawing, With several levels of protection, this ground fault protection. Many fused
each of the breakers’ three-phase
sensors have not been shown. It is
will reduce the level of protection for switches over 1200A, and Eaton Type 7
faults within the upstream GFR zones. FDP fusible switches with ratings from
absolutely critical that the sensors’ Zone interlocking was developed for 400 to 1200A, are listed by UL as suitable
polarities are supplied as shown, the GFRs to overcome this problem. for ground fault protection. Fusible 8
neutral sensor ratings of the mains and switches so listed must be equipped
tie are the same, and that there are GFRs (or circuit breakers with integral with a shunt trip, and be able to
no other grounds on the neutral bus ground fault protection) with zone open safely on faults up to 12 times 9
made downstream of points shown. interlocking are coordinated in a their rating.
system to operate in a time delayed
An infinite number of ground fault mode for ground faults occurring most Power distribution systems differ
protection schemes can be developed remote from the source. However, this widely from each other, depending
10
depending upon the number of alternate time delayed mode is only actuated upon the requirements of each user,
sources, the number of grounding points when the GFR next upstream from the and total system overcurrent protec-
and system interconnections involved. fault sends a restraining signal to the tion, including ground fault currents,
11
Depending upon the individual system upstream GFRs. The absence of a must be individually designed to meet
configuration, either mode of sensing restraining signal from a downstream these needs. Experienced and knowl-
edgeable engineers must consider the
12
power sources (utility or on-site), the
Power
Transformer
Power
Transformer
effects of outages and costs of down-
time, safety for people and equipment,
13
initial and lifecycle costs, and many
other factors. They must apply protec- 14
X X
tive devices, analyzing the time-current
X X
Neutral Neutral characteristics, fault interrupting
Sensor Main Sensor Main
Main Breaker 52-1 Breaker 52-2 Main
capacity, and selectivity and coordina- 15
Breaker Breaker tion methods to provide the most safe
52-1 52-2 and cost-effective distribution system.
Phase A, Tie Breaker Phase A, Further Information 16
Phase B, 52-T Phase B, ■ PRSC-4E—System Neutral Ground-
Phase C Phase C
Neutral X
Neutral
ing and Ground Fault Protection
(ABB Publication)
17
Neutral Sensor X
Tie Breaker 52-T ■ PB 2.2—NEMA Application Guide
Trip Unit
Trip Unit
Typical X
X
Typical X
X
for Ground Fault Protective Devices 18
Four-Wire Four-Wire for Equipment
Feeder 52-1 52-T 52-2 Feeder
a a a ■ IEEE Standard 142—Grounding of
Industrial and Commercial Power 19
Four-Wire Load Four-Wire Load
Systems (Green Book)
Trip Unit Trip Unit Trip Unit ■ IEEE Emerald Book (Standard 1100)
Main Breaker Tie Breaker Main Breaker
■ UL 96A, Installation Requirements
20
52-1 52-T 52-2
for Lightning Protection Systems
Figure 1.4-9. Dual Source System—Multiple Point Grounding 21
Lightning and Surge Protection The electrical distribution system and Surge Protection
i Physical protection of buildings
equipment ground must be connected
Eaton’s VacClad-W metal-clad switch-
to this grounding electrode system by
from direct damage from lightning a grounding electrode conductor. All gear is applied over a broad range of
ii is beyond the scope of this section.
Requirements will vary with geographic
other grounding electrodes, such as circuits, and is one of the many types
of equipment in the total system. The
those for the lightning protection sys-
location, building type and environ- tem, the telephone system, television distribution system can be subject to
1 ment, and many other factors (see antenna and cable TV system grounds, voltage transients caused by lighting
IEEE/ANSI Standard 142, Grounding and computer systems, must be bonded or switching surges.
of Industrial and Commercial Power to this grounding electrode system. Recognizing that distribution system
2 Systems). Any lightning protection
can be subject to voltage transients
system must be grounded, and the Medium Voltage Equipment Surge
lightning protection ground must be caused by lighting or switching, the
3 bonded to the electrical equipment Protection Considerations industry has developed standards to
grounding system. provide guidelines for surge protection
Transformers of electrical equipment. Those guide-
Grounding Electrodes lines should be used in design and
4 If the voltage withstand/BIL rating of
the transformer is less than that of the protection of electrical distribution
At some point, the equipment and systems independent of the circuit
switchgear feeding the transformer,
system grounds must be connected breaker interrupting medium. The
5 to the earth by means of a grounding
surge protection is recommended at
the transformer terminals, in line with industry standards are:
electrode system.
established practices. In addition, ANSI C62
6 Outdoor substations usually use a consideration should be given to using Guides and Standards for Surge
ground grid, consisting of a number of surge arresters and/or surge capacitors Protection
ground rods driven into the earth and for transformers having equal or
7 bonded together by buried copper greater withstand/BIL ratings than that IEEE 242—Buff Book
conductors. The required grounding of the switchgear feeding the trans- IEEE Recommended Practice for
electrode system for a building is former for distribution systems where Protection and Coordination of
8 spelled out in the NEC Article 250. reflected voltage waves and/or reso- Industrial and Commercial Power
nant conditions may occur. Typically Systems
The preferred grounding electrode incoming voltage surges are reflected
is a metal underground water pipe in IEEE 141—Red Book
9 direct contact with the earth for at least
at the transformer primary terminals
Recommended Practice for
(because of the change in impedance)
10 ft (3m). However, because under- resulting in voltages at the ends of the Electric Power Distribution for
ground water piping is often plastic Industrial Plants
10 outside the building, or may later be
transformer primary terminals/wind-
ings of up to two times the incoming IEEE C37.20.2
replaced by plastic piping, the NEC voltage wave. System capacitance and Standards for Metal-Clad Switchgear
11 requires this electrode to be supple- inductance values combined with the
mented by and bonded to at least one transformer impedance values can Eaton’s medium voltage metal-clad
other grounding electrode, such as cause resonant conditions resulting and metal-enclosed switchgear that
12 the effectively grounded metal frame
of the building, a concrete-encased
in amplified reflected waves. Surge uses vacuum circuit breakers is applied
arresters/capacitors when required, over a broad range of circuits. It is one
electrode, a copper conductor ground should be located as close to the trans- of the many types of equipment in the
13 ring encircling the building, or a made former primary terminals as practical. total distribution system. Whenever a
electrode such as one or more driven switching device is opened or closed,
ground rods or a buried plate. Where Motors certain interactions of the power
14 any of these electrodes are present, Surge capacitors and, where appropri- system elements with the switching
they must be bonded together into ate, surge arresters should be applied device can cause high frequency voltage
one grounding electrode system. at the motor terminals. transients in the system. Due to the
15 One of the most effective grounding Generators
wide range of applications and variety
of ratings used for different elements
electrodes is the concrete-encased Surge capacitors and station in the power systems, a given circuit
electrode, sometimes called the Ufer
16 ground, named after the man who
class surge arresters at the machine may or may not require surge protec-
terminals. tion. Therefore, Eaton does not include
developed it. It consists of at least
surge protection as standard with its
20 ft (6m) of steel reinforcing bars or
17 rods not less than 1/2 inches (12.7 mm)
metal-clad or metal-enclosed medium
voltage switchgear. The user exercises
in diameter, or at least 20 ft (6m) of
the options as to the type and extent
bare copper conductor, size No. 4 AWG
18 or larger, encased in at least 2 inches
of the surge protection necessary
depending on the individual circuit
(50.8 mm) of concrete. It must be
characteristics and cost considerations.
located within and near the bottom of
19 a concrete foundation or footing that The following are Eaton’s recommen-
is in direct contact with the earth. Tests dations for surge protection of medium
have shown this electrode to provide voltage equipment. Please note these
20 a low-resistance earth ground even in recommendations are valid when
poor soil conditions. using Eaton’s vacuum breakers only.
21
Surge Protection Recommendations RC Snubber and/or ZORC damp 6. Capacitor Switching—No surge
Note: The abbreviation ZORC® used in the internal transformer resonance: protection is required. Make sure i
text below refers to Surge Protection Device that the capacitor’s lightning
manufactured by Strike Technology (Pty) The natural frequency of transformer impulse withstand rating is equal
Ltd. An equivalent device offered by other windings can under some circumstances to that of the switchgear. ii
manufacturers, such as Type EHZ by ABB, be excited to resonate. Transformer
and Protec Z by Northern Technologies SA windings in resonance can produce 7. Shunt Reactor Switching—
can also be used. elevated internal voltages that produce Provide Surge Arrester in parallel 1
insulation damage or failure. An RC with RC Snubber, or ZORC at the
1. For circuits exposed to lightning, Snubber or a ZORC applied at the reactor terminals.
surge arresters should be applied transformer terminals as indicated 2
in line with Industry standard above can damp internal winding 8. Motor Starting Reactors or Reduced
practices. resonance and prevent the production Voltage Auto-Transformers—
Provide Surge Arrester in parallel
2. Transformers
of damaging elevated internal voltages.
with RC Snubber, or ZORC at the 3
This is typically required where rectifiers,
UPS or similar electronic equipment is reactor or RVAT terminals.
a. Close-Coupled to medium
voltage primary breaker: on the transformer secondary. 9. Switching Underground Cables— 4
Provide transients surge pro- Surge protection not needed.
3. Arc-Furnace Transformers—
tection, such as Surge Arrester
Provide Surge Arrester in parallel
in parallel with RC Snubber, or
with RC Snubber, or ZORC at the Types of Surge Protection Devices 5
ZORC. The surge protection
transformer terminals. Generally surge protective devices
device selected should be
should be located as closely as possible
located and connected at the 4. Motors—Provide Surge Arrester in to the circuit component(s) that require
6
transformer primary terminals parallel with RC Snubber, or ZORC
or it can be located inside the protection from the transients, and
at the motor terminals. For those connected directly to the terminals of
switchgear and connected on motors using VFDs, surge protec- the component with conductors that
7
the transformer side of the tion should be applied and pre-
primary breaker. are as short and flat as possible to
cede the VFD devices as well. minimize the inductance. It is also
b. Cable-Connected to medium important that surge protection devices
8
5. Generators—Provide station class
voltage primary breaker: should be properly grounded for
Surge Arrester in parallel with RC
Provide transient surge protec- effectively shunting high frequency
tion, such as Surge Arrester in
Snubber, or ZORC at the generator
transients to ground.
9
terminals.
parallel with RC Snubber, or
ZORC for transformers con-
nected by cables with lengths 10
up to 75 feet. The surge protec-
tion device should be located
and connected at the trans- 11
former terminals. No surge
protection is needed for trans-
formers with lightning impulse
12
withstand ratings equal to that
of the switchgear and connected
to the switchgear by cables at
13
least 75 feet or longer. For
transformers with lower BIL,
provide surge arrester in parallel Figure 1.4-10. Surge Protection Devices 14
with RC Snubber or ZORC.
15
16
17
18
19
20
21
18
19
20
21
Surge Protection Summary Good protection: Surge Arrester Best protection: ZORC, plus proper
Minimum protection: Surge Arrester
in parallel with Surge Capacitor for surge arrester preceding ZORC where i
protection from high overvoltage needed for protection against lightning.
for protection from high overvoltage peaks and fast rising transient. This ZORC provides protection from high
peaks, or Surge Capacitor for protec- option may not provide adequate frequency voltage transients and limits ii
tion from fast-rising transient. Please surge protection from escalating peak magnitude of the transient to
note that the surge arresters or surge voltages caused by circuit resonance. 1 to 2 PU (see ZORC description on
capacitor alone may not provide When applying surge capacitors on Page 1.4-16 for more detail). Surge 1
adequate surge protection from both sides of a circuit breaker, surge arrester provides protection from
escalating voltages caused by circuit capacitor on one side of the breaker higher voltage peaks resulting from
resonance. Note that when applying must be RC Snubber or ZORC, lightning surges. 2
surge capacitors on both sides of a to mitigate possible virtual
circuit breaker, surge capacitor on current chopping. Further Information
one side of the breaker must be ■ IEEE/ANSI Standard 142—Grounding 3
RC Snubber or ZORC, to mitigate Better protection: RC Snubber in Industrial and Commercial Power
possible virtual current chopping. parallel with Surge Arrester for Systems (Green Book)
protection from high frequency
■ IEEE Standard 241—Electric Power 4
transients and voltage peaks.
Systems in Commercial Buildings
(Gray Book)
■ IEEE Standard 141—Electric Power
5
Distribution for Industrial Plants
(Red Book)
6
Table 1.4-3. Surge Arrester Selections—Recommended Ratings
Service Distribution Class Arresters Station Class Arresters
Voltage Solidly Low Resistance High Resistance or Solidly Low Resistance High Resistance or
7
Line-to-Line Grounded System Grounded System Ungrounded System Grounded System Grounded System Ungrounded System
kV
Arrester Ratings kV
Nominal MCOV Nominal MCOV Nominal MCOV
Arrester Ratings kV
Nominal MCOV Nominal MCOV Nominal MCOV
8
2.30 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55
2.40 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10 9
3.30 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
4.00 3 2.55 6 5.10 6 5.10 3 2.55 6 5.10 6 5.10
4.16
4.76
6
6
5.10
5.10
6
6
5.10
5.10
6
9
5.10
7.65
6
6
5.10
5.10
6
6
5.10
5.10
6
9
5.10
7.65
10
4.80 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.60 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.90 6 5.10 6 5.10 9 7.65 6 5.10 9 7.65 9 7.65 11
7.20 6 5.10 6 5.10 10 8.40 6 5.10 9 7.65 10 8.40
8.32 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
8.40 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20 12
11.00 9 7.65 9 7.65 15 12.70 9 7.65 10 8.40 15 12.70
11.50 9 7.65 10 8.40 18 15.30 9 7.65 12 10.20 18 15.30
12.00 10 8.40 10 8.40 18 15.30 10 8.40 12 10.20 18 15.30
13
12.47 10 8.40 12 10.20 18 15.30 10 8.40 12 10.20 18 15.30
13.20 12 10.20 12 10.20 18 15.30 12 10.20 12 10.20 18 15.30
13.80 12 10.20 12 10.20 18 15.30 12 10.20 15 12.70 18 15.30
14.40 12 10.20 12 10.20 21 17.00 12 10.20 15 12.70 21 17.00
14
18.00 15 12.70 15 12.70 27 22.00 15 12.70 18 15.30 27 22.00
20.78 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.00 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40 15
22.86 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
23.00 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
24.94
25.80
21
21
17.00
17.00
24
24
19.50
19.50
—
—
—
—
21
21
17.00
17.00
24
24
19.50
19.50
36
36
29.00
29.00
16
26.40 21 17.00 24 19.50 — — 21 17.00 27 22.00 39 31.50
33.00
34.50
27
30
22.00
24.40
30
30
24.40
24.40
—
—
—
—
27
30
22.00
24.40
36
36
29.00
29.00
45
48
36.50
39.00 17
38.00 30 24.40 — — — — 30 24.40 36 29.00 — —
18
19
20
21
i Power Quality Terms Defining the Problem Another option is to buy power condi-
Power quality problems can be resolved tioning equipment to correct any and
Technical Overview in three ways: by reducing the variations all perceived power quality problems
in the power supply (power distur- without any on-site investigation.
ii Introduction bances), by improving the load equip- Power Quality Terms
Sensitive electronic loads deployed ment’s tolerance to those variations, or
by inserting some interface equipment Power disturbance: Any deviation
today by users require strict require-
1 ments for the quality of power delivered (known as power conditioning equip- from the nominal value (or from some
ment) between the electrical supply selected thresholds based on load
to loads.
and the sensitive load(s) to improve the tolerance) of the input AC power
2 For electronic equipment, power compatibility of the two. Practicality characteristics.
disturbances are defined in terms of and cost usually determine the extent Total harmonic distortion or distortion
amplitude and duration by the elec- to which each option is used.
3 factor: The ratio of the root-mean-
tronic equipment operating envelope.
Many methods are used to define square of the harmonic content to the
Electronic loads may be damaged
power quality problems. For example, root-mean-square of the fundamental
and disrupted, with shortened life
4 expectancy, by disturbances. one option is a thorough on-site quantity, expressed as a percentage
of the fundamental.
investigation, which includes inspecting
The proliferation of computers, variable wiring and grounding for errors, Crest factor: Ratio between the
5 frequency motor drives, UPS systems monitoring the power supply for peak value (crest) and rms value of
and other electronically controlled power disturbances, investigating a periodic waveform.
equipment is placing a greater demand equipment sensitivity to power distur-
6 on power producers for a disturbance- bances, and determining the load Apparent (total) power factor: The
free source of power. Not only do these disruption and consequential effects ratio of the total power input in watts
types of equipment require quality (costs), if any. In this way, the power to the total volt-ampere input.
7 power for proper operation; many quality problem can be defined,
Sag: An rms reduction in the AC
times, these types of equipment are alternative solutions developed,
also the sources of power disturbances voltage, at the power frequency, for
and optimal solution chosen.
8 that corrupt the quality of power in a the duration from a half-cycle to a few
seconds. An undervoltage would have
given facility. Before applying power-conditioning
equipment to solve power quality a duration greater than several seconds.
Power quality is defined according
9 to IEEE Standard 1100 as the concept
problems, the site should be checked
Interruption: The complete loss of
for wiring and grounding problems.
of powering and grounding electronic voltage for a time period.
Sometimes, correcting a relatively
10 equipment in a manner that is suitable inexpensive wiring error, such as a Transient: A sub-cycle disturbance
to the operation of that equipment. loose connection or a reversed neutral in the AC waveform that is evidenced
IEEE Standard 1159 notes that “within and ground wire, can avoid a more by a sharp brief discontinuity of the
11 the industry, alternate definitions or expensive power conditioning solution. waveform. May be of either polarity
interpretations of power quality have and may be additive to or subtractive
been used, reflecting different points Sometimes this approach is not practical
from the nominal waveform.
of view.” because of limitations in time; expense
12 is not justified for smaller installations; Surge or impulse: See transient.
In addressing power quality problems monitoring for power disturbances
at an existing site, or in the design may be needed over an extended Noise: Unwanted electrical signals
13 stages of a new building, engineers period of time to capture infrequent that produce undesirable effects
need to specify different services or disturbances; the exact sensitivities of in the circuits of control systems
mitigating technologies. The lowest the load equipment may be unknown in which they occur.
14 cost and highest value solution is and difficult to determine; and finally,
to selectively apply a combination Common-mode noise: The noise
the investigative approach tends to voltage that appears equally and in
of different products and services solve only observed problems. Thus
15 as follows: unobserved or potential problems
phase from each current-carrying
conductor to ground.
Key services/technologies in the may not be considered in the solution.
16 “power quality” industry: For instance, when planning a new Normal-mode noise: Noise signals
facility, there is no site to investigate. measurable between or among active
■ Power quality surveys, analysis Therefore, power quality solutions are circuit conductors feeding the subject
17 and studies often implemented to solve potential load, but not between the equipment
■ Power monitoring or perceived problems on a preventive grounding conductor or associated
■ Grounding products and services basis instead of a thorough on-site signal reference structure and the active
18 ■ Surge protection
investigation. circuit conductors.
■ Voltage regulation
19 ■ Harmonic solutions
■ Lightning protection (ground rods,
hardware, etc.)
20 ■ Uninterruptible power supply (UPS)
or motor-generator (M-G) set
21
Methodology for Ensuring Effective The proliferation of communication The benefit of implementing cascaded
Power Quality to Electronic Loads and computer network systems network protection is shown in i
The power quality pyramid is an has increased the need for proper Figure 1.4-12. Combined, the two
effective guide for addressing power grounding and wiring of AC and data/ stages of protection at the service
quality problems at an existing facility. communication lines. In addition to entrance and branch panel locations ii
The framework is also effective for reviewing AC grounding and bonding reduce the IEEE 62.41 recommended
specifying engineers who are design- practices, it is necessary to prevent test wave (C3–20 kV, 10 kA) to less than
ing a new facility. Power quality starts ground loops from affecting the signal 200V voltage, a harmless disturbance 1
with grounding (the base of the reference point. level for 120V rated sensitive loads.
pyramid) and then moves upward
to address the potential issues. This 2. Surge Protection If only building entrance feeder 2
protection were provided, the let-
simple, yet proven methodology, Surge protection devices (SPDs) through voltage will be approximately
will provide the most cost-effective are recommended as the next stage
approach. As we move higher up the power quality solutions. NFPA,
950V in a 277/480V system exposed 3
to induced lightning surges. This
pyramid, the cost per kVA of mitigating UL 96A, IEEE Emerald Book and level of let-through voltage can cause
potential problems increase and the equipment manufacturers recommend
quality of the power increases (refer the use of surge protectors. The
degradation or physical damage of 4
most electronic loads.
to Figure 1.4-11). SPD shunt short duration voltage
disturbances to ground, thereby Wherever possible, consultants,
preventing the surge from affecting specifiers and application engineers
5
electronic loads. When installed as should ensure similar loads are fed
part of the facility-wide design, SPDs from the same source. In this way,
are cost-effective compared to all disturbance-generating loads are
6
Cost Per kVA
19
20
21
The recommended system approach ■ Building entrance SPDs protect tion wires, the area between wires is
i for installing SPDs is summarized in the facility against large external reduced and the mutual inductance
Figure 1.4-13. transients, including lightning affect minimized.
■ SPDs are bi-directional and prevent
ii transient and noise disturbances
Increasing the diameter of the installation
1. wires is of negligible benefit. Induc-
Identify Critical Loads from feeding back within a system tance is a “skin effect” phenomenon and
when installed at distribution or
1 branch panels
a function of wire circumference. Since
2. only a marginal reduction in inductance
Identify Non-Critical Loads ■ Two levels of protection safeguard is achieved when the diameter of the
sensitive loads from physical
2 damage or operational upset
installation conductors is increased,
3.
the use of large diameter wire results
Identify Noise and in only minimal improvement (see
Side-Mounted SPD vs. Integral SPD
3 Disturbance Generating Loads
Directly connecting the surge sup-
Figure 1.4-15).
presser to the bus bar of electrical Further benefits provided by integrated
4. distribution equipment results in surge suppression designs are the
4 Review Internal Power Distribution Layout
the best possible level of protection. elimination of field installation costs and
Compared to side-mounted devices, the amount of expensive “outboard”
5. connecting the SPD unit to the bus wall space taken up by side-mounted
5 Identify Facility Exposure to bar eliminates the need for lead wires SPD devices.
Expected Levels of Disturbance
and reduces the let-through voltage
up to 50% (see Figure 1.4-14). Building Entrance Feeder Installation
6 6. Considerations
Apply Mitigating Equipment to: Given that surges are high frequency Installing an SPD device immediately
a) Service Entrance Main Panels disturbances, the inductance of the after the switchgear or switchboard
7 b) Key Sub-Panels installation wiring increases the main breaker is the optimal location
c) Critical Loads
let-through voltage of the protective for protecting against external distur-
d) Data and Communication Lines
device. Figure 1.4-15 shows that bances such as lightning. When placed
8 for every inch of lead length, the in this location, the disturbance is
Figure 1.4-13. System Approach for Installing SPDs let-through voltage is increased by “intercepted” by the SPD and reduced
There may be specific critical loads an additional 15–25V above the to a minimum before reaching the
9 within a facility that require a higher manufacturers stated suppression distribution and/or branch panel(s).
level of protection. A series SPD is best performance.
suited for protecting such loads. The use of a disconnect breaker
10 Lead length has the greatest effect on eliminates the need to de-energize
Advantages of the system approach are: the actual level of protection realized. the building entrance feeder equip-
Twisting of the installation wires is ment should the SPD fail or require
11 ■ The lowest possible investment the second most important installation
in mitigating equipment to protect isolation for Megger testing.
consideration. By twisting the installa-
a facility
12
208Y/120 Panelboard
13 (integrated versus side mounted SPD)
15 600
N 400
SPD
16 Integrated SPD
SPD (direct bus bar connection)
200
17 0
GRO UND G RO UND
Surge
Event
18 G
G
–200
–2.00 0.00 2.00 4.00 6.00 8.00 10.00
N
\
Microseconds
19
Figure 1.4-14. Performance Comparison of Side-Mounted vs. Integrated SPD
20
21
Nonlinear load currents vary widely present on the three phases add Harmonic Issues
i from a sinusoidal wave shape; often together in the neutral, as shown in
Harmonic currents perform no work
they are discontinuous pulses. This Figure 1.4-17, rather than cancel each
means that nonlinear loads are other out, as shown in Figure 1.4-16. and result in wasted electrical energy
ii that may over burden the distribution
extremely high in harmonic content. Odd non-triplen harmonics are
system. This electrical overloading
classified as “positive sequence”
Triplen harmonics are the 3rd, 9th, may contribute to preventing an
or “negative sequence” and are the
existing electrical distribution system
1 15th,...harmonics. Further, triplen 1st, 5th, 7th, 11th, 13th, etc.
from serving additional future loads.
harmonics are the most damaging
to an electrical system because these In general, as the order of a harmonic In general, harmonics present on
2 harmonics on the A-phase, B-phase gets higher, its amplitude becomes a distribution system can have the
and C-phase are in sequence with each smaller as a percentage of the funda- following detrimental effects:
other. Meaning, the triplen harmonics mental frequency.
3 1. Overheating of transformers and
rotating equipment.
60 Hz Fundamental
2. Increased hysteresis losses.
4
3. Decreased kVA capacity.
A Phase
4. Overloading of neutral.
5
5. Unacceptable neutral-to-ground
voltages.
6 120º 6. Distorted voltage and current
Lagging waveforms.
B Phase
7 7. Failed capacitor banks.
8. Breakers and fuses tripping.
8 9. Double or ever triple sized neutrals
120º
Lagging
to defy the negative effects of
C Phase triplen harmonics.
9
In transformers, generators and
uninterruptible power supplies (UPS)
10 Balance
systems, harmonics cause overheating
Neutral and failure at loads below their ratings
Current because the harmonic currents cause
11 greater heating than standard 60 Hz
current. This results from increased
Figure 1.4-16. Balanced Neutral Current Equals Zero eddy current losses, hysteresis losses
12 in the iron cores, and conductor skin
effects of the windings. In addition,
60 Hz Fundamental the harmonic currents acting on the
13 3rd Harmonic impedance of the source cause
harmonics in the source voltage, which
A Phase is then applied to other loads such as
14 motors, causing them to overheat.
The harmonics also complicate the
15 application of capacitors for power
120º factor correction. If, at a given harmonic
B Phase
Lagging
frequency, the capacitive impedance
16 equals the system reactive impedance,
the harmonic voltage and current can
reach dangerous magnitudes. At the
17 120º C Phase
same time, the harmonics create
Lagging problems in the application of power
factor correction capacitors, they
18 lower the actual power factor. The
rotating meters used by the utilities for
watthour and various measurements
19 Neutral
Triplen
do not detect the distortion component
caused by the harmonics. Rectifiers
Current
with diode front ends and large DC side
Single-phase power supplies for Total Harmonic Distortion Table 1.4-7. Current Distortion Limits for
computer and fixture ballasts are
Revised standard IEEE 519-1992
General Distribution Systems (120– 69,000V) i
rich in third harmonics and their Maximum Harmonic Current Distortion in
odd multiples. indicates the limits of current distor-
Percent of IL
tion allowed at the PCC (Point of ii
Individual Harmonic Order (Odd Harmonics)
Even with the phase currents perfectly Common Coupling) point on the
balanced, the harmonic currents in system where the current distortion ISC /IL <11 11 17 23 35 TDD
<h <h <h <h
the neutral can total 173% of the is calculated, usually the point of
connection to the utility or the main
<17 <23 <35 1
phase current. This has resulted in
overheated neutrals. The Information supply bus of the system. <20 4.0 2.0 1.5 0.6 0.3 5.0
Technology Industry Council (ITIC)
The standard also covers the harmonic
20<50
50<100
7.0
10.0
3.5
4.5
2.5
4.0
1.0
1.5
0.5
0.7
8.0
12.0
2
formerly known as CBEMA, recom-
mends that neutrals in the supply to limits of the supply voltage from the 100<1000 12.0 5.5 5.0 2.0 1.0 15.0
utility or cogenerators. >1000 15.0 7.0 6.0 2.5 1.4 20.0
electronic equipment be oversized All power generation equipment is limited 3
to at least 173% of the ampacity of Table 1.4-5. Low Voltage System Classification to these values of current distortion,
the phase conductors to prevent and Distortion Limits for 480V Systems regardless of actual ISC/IL where:
problems. ITIC also recommends Class C AN DF ISC = Maximum short-circuit current at PCC. 4
derating transformers, loading them IL = Maximum demand load current
to no more than 50% to 70% of their Special application 10 16,400 3% (fundamental frequency component) at PCC.
nameplate kVA, based on a rule-of- General system
Dedicated system
5
2
22,800
36,500
5%
10%
TDD = Total Demand Distortion. Even
harmonics are limited to 25% of the odd
5
thumb calculation, to compensate harmonic limits above. Current distortions
for harmonic heating effects. Special systems are those where the rate that result in a DC offset, e.g., half-wave
In spite of all the concerns they
of change of voltage of the notch might
mistrigger an event. AN is a measurement
converters, are not allowed. 6
cause, nonlinear loads will continue of notch characteristics measured in
volt-microseconds, C is the impedance
Harmonic Solutions
to increase. Therefore, the design of
nonlinear loads and the systems that ratio of total impedance to impedance In spite of all the concerns nonlinear 7
at common point in system. DF is loads cause, these loads will continue
supply them will have to be designed distortion factor.
so that their adverse effects are greatly to increase. Therefore, the design
reduced. Table 1.4-4 shows the typical of nonlinear loads and the systems 8
Table 1.4-6. Utility or Cogenerator Supply that supply them will need design so
harmonic orders from a variety of Voltage Harmonic Limits
harmonic generating sources. adverse harmonic effects are greatly
Voltage 2.3–69 kV 69–138 kV >138 kV reduced. Table 1.4-8 and depicts many 9
Range harmonic solutions along with their
Table 1.4-4. Source and Typical Harmonics
Source Typical Maximum 3.0% 1.5% 1.0% advantages and disadvantages.
Harmonics individual 10
harmonic Eaton’s Engineering Services &
6-pulse rectifier 5, 7, 11, 13, 17, 19… Total 5.0% 2.5% 1.5%
Systems Group (EESS) can perform
12-pulse rectifier
18-pulse rectifier
11, 13, 23, 25…
17, 19, 35, 37…
harmonic harmonic studies and recommend 11
distortion solutions for harmonic problems.
Switch-mode power
supply
Fluorescent lights
3, 5, 7, 9, 11, 13…
3, 5, 7, 9, 11, 13… V 12
Arcing devices 2, 3, 4, 5, 7…
Percentages are −−−h x 100 for each
harmonic V1
Transformer energization 2, 3, 4
Generally, magnitude decreases as harmonic and
13
order increases.
h = hmax 1/2 14
Vthd = ∑ 2
Vh
h=2 15
It is important for the system designer
to know the harmonic content of the
utility’s supply voltage because it will 16
affect the harmonic distortion of
the system.
17
18
19
20
21
18
19
20
21
5. Uninterruptible Power The normal power source supplied by Uninterruptible power supply (UPS)
Systems (UPS) the local utility or provider is not stable systems have evolved to serve the i
enough over time to continuously needs of sensitive equipment and
The advent of solid-state semiconduc- serve these loads without interruption. can supply a stable source of electrical
tors over 40 years ago, and their It is possible that a facility outside a power, or switch to backup to allow ii
subsequent evolution to transistors, major metropolitan area served by the for an orderly shutdown of the loads
and the miniaturization of electronics utility grid will experience outages of without appreciable loss of data or
into microprocessor over 25 years ago, some nature 15–20 times in one year. process. In the early days of main- 1
has created numerous computation Certain outages are caused by the frame computers, motor-generator
machines that assist us in every weather, and others by the failure sets provide isolation and clean power
conceivable manner. These machines, of the utility supply system due to to the computers. They did not have 2
and their clever configurations, equipment failures or construction deep reserves, but provided extensive
whether they take the form of interruptions. Some outages are ride-through capability while other
computers, appliance controls, fax only several cycles in duration, while sources of power (usually standby 3
machines, phone systems, computers others may be for hours at a time. emergency engine generator sets) were
of all sizes, server systems and server brought to serve the motor-generator
farms, emergency call centers, data In a broader sense, other problems sets while the normal source of power 4
processing at banks, credit companies, exist in the area of power quality, and was unstable or unavailable.
private company communication many of those issues also contribute
networks, government institutions and to the failure of the supply to provide UPS systems have evolved along the 5
defense agencies, all rely on a narrow that narrow range of power to the lines of rotary types and static types
range of nominal AC power in order sensitive loads mentioned above. of systems, and they come in many
for these devices to work properly. Power quality problems take the configurations, and even hybrid 6
Indeed, many other types of equip- form of any of the following: power designs having characteristics of
ment also require that the AC electrical failure, power sag, power surge, both types. The discussion that
power source be at or close to nominal undervoltage, overvoltage, line noise, follows attempts to compare and 7
voltage and frequency. Disturbances frequency variations, switching contrast the two types of UPS
of the power translate into failed transients and harmonic distortion. systems, and give basic guidance
processes, lost data, decreased Regardless of the reason for outages on selection criteria. This discussion 8
efficiency and lost revenue. and power quality problems, the will focus on the medium, large and
sensitive loads can not function very large UPS systems required by
normally without a backup power users who need more than 10 kVA of 9
source, and in many cases, the loads clean reliable power.
must be isolated from the instabilities
of the utility supply and power quality 10
problems and given clean reliable
power on a continuous basis, or be
able to switch over to reliable clean 11
electrical power quickly.
12
13
14
15
16
17
18
19
20
21
Power Ratings of UPS Systems types of hybrid UPS systems are not system checks are performed then
i ■ Small UPS: Typically 300 VA to 10 kVA,
the focus of this discussion, because the input contactor is closed. The static
only one or two vendors offer these disconnect switch is turned on and the
and sometimes as high as 18 kVA hybrid types of rotary UPS systems, conduction angle is rapidly increased
ii ■ Medium UPS: 10–60 kVA although admittedly they continue to from zero to an angle that causes the
■ Large UPS: 100–200 kVA units, and be used in very large-scale data center DC bus voltage between the utility
higher when units are paralleled applications. See Figure 1.4-18 for the converter and the flywheel converter
1 ■ Very Large UPS: 200–750 kVA modern high speed Rotary UPS to reach approximately 650V through
units, and higher when units systems discussed in this section the rectifying action of the freewheel-
are paralleled of the guide. These types of modern ing diodes in the utility converter.
2 rotary UPS systems are advanced, As soon as this level of DC voltage is
Each of these categories is arbitrary integrated designs using scalable reached, the static disconnect turns
because manufacturers have many configurations of high-speed fly- on fully. The next steps involved the
3 different UPS offerings for the same wheel, motor and generator in one utility converter IGBTs to start firing,
application. The choice of UPS type compact UPS package. The new rotary which allows the converter to act as
and the configuration of UPS modules technologies have the potential to a rectifier, a regulating voltage source
4 for a given application depends upon replace battery backup systems, or and an active harmonic filter. As the
many factors, including how many at least reduce the battery content IGBTs begin to operate, the DC bus
power quality problems the UPS is for certain applications. The appeal is increased to a normal operating
5 expected to solve; how much future of rotary systems is the avoidance of voltage of approximately 800V, and
capacity is to be purchased now for the purchase, maintenance and facility the output bus is transferred from
future loads; the nature of the sensi- space required by DC battery based bypass to the output of the power
6 tive loads and load wiring; which backup systems. electronics module. The transfer from
type of UPS system is favored, rotary bypass is completed when the output
or static; choices of battery or DC High-Speed Rotary contactor is closed and the bypass
7 storage technology considered; and
Concept of Operation contactor opened in a make-before-
a host of other application issues. break manner.
The modern rotary type of UPS
8 Rotary UPS Systems operation is understood by reviewing The firing of the SCRs in the static
the four topics below: startup mode, disconnect switch is now changed so
Typical Ratings normal operation mode, discharge that each SCR in each phase is only
9 300–900 kVA/720 kW maximum. mode and recharge mode. turned on during the half-cycle, which
permits real power to flow from the
Typical Rotary Configurations Startup Mode utility supply to the UPS. This firing
10 Rotary UPS systems are among the The UPS output is energized on pattern at the static disconnect switch
oldest working systems developed bypass as soon as power is applied prevents power from the flywheel
to protect sensitive loads. Many of from the source to the system input. from feeding backward into the
11 these systems are complicated engine- The UPS continues the startup utility supply and ensures that all of
generator sets coupled with high procedure automatically when the the flywheel energy is available to
inertial flywheels operated at relatively front panel controls are placed into support the load.
12 low rotational speeds. These legacy the “Online” position. Internal UPS
Ix
Filter Inductor Ig
18 Field Coil ac dc Id = Output Current
Ih = Harmonic Current
Driver dc ac Ix = Reactive Load Current
Ir = Real Load Current
19 Ih
Integrated Motor/Flywheel/
and Generator
20
Figure 1.4-18. Typical-High Speed Modern Rotary UPS
21
Immediately after the output is trans- causes a voltage boost across the line as the load power is completely
ferred from bypass to the power elec- inductor, and a lagging current causes transferred to the input source, the util- i
tronic module, the flywheel field is a bucking voltage. By controlling the ity converter and flywheel converter
excited, which also provides magnetic utility converter to maintain nominal start to recharge the flywheel and
lift to unload the flywheel bearings. output voltage, just enough reactive return to normal operation mode. The ii
The flywheel inverter is turned on current flows through the line inductor flywheel recharge power is program-
and gradually increases frequency to make up the difference between the mable between a slow and fast rate,
at a constant rate to accelerate the input voltage and the output voltage. and using the fast rate results in an 1
flywheel to approximately 60 rpm. increase of UPS input current over
Once the flywheel reaches 60 rpm, The load current consists of three nominal levels. Recharging the flywheel
the flywheel inverter controls the components: the harmonic current is accomplished by controlling the 2
acceleration to keep currents below the required by the load, the reactive load utility and flywheel converter in a
maximum charging and the maximum current, and the real current, which similar manner as is used to maintain
input settings. Once the flywheel does the work. The utility converter full charge in the normal operation 3
reaches 4000 rpm, the UPS is fully supplies both the harmonic and mode, however the IGBT gating points
functional and capable of supporting reactive currents. Because these are changed to increase current into
the load during a power quality event. currents supply no net power to the the flywheel. 4
flywheel acceleration continues until load, the flywheel supplies no energy
the Flywheel reaches “full charge” at for these currents. They circulate High-Speed Rotary Advantages
7700 rpm. The total time to complete between the utility converter and the ■ Addresses all power quality 5
startup is less than 5 minutes. load. The power stage controls analyze problems
the harmonic current requirements of
■ Battery systems are not required
Normal Operation Mode the load and set the firing angle of
or used 6
Once the UPS is started and the the inverter IGBTs to make the utility
converter a very low impedance source ■ No battery maintenance required
flywheel is operating at greater than
4000 rpm, the UPS is in the normal to any harmonic currents. Thus, ■ Unlimited discharge cycles 7
operating mode where it is regulating nonlinear load currents are supplied ■ 150-second recharge time available
output voltage and supplying reactive almost entirely from the utility ■ Wide range of operating tempera-
and harmonic currents required by the converter with little effect on the tures can be accommodated 8
load. At the same time it cancels the quality of the UPS output voltage (–20° to 40°C)
effect of load current harmonics on the waveform and with almost no
■ Small compact size and less floor
UPS output voltage. transmission of load harmonics
space required (500 kW systems
9
currents to the input of the UPS.
Input current consists of three compo- takes 20 sq ft)
nents: real load current, charging Discharge Mode ■ N+1 reliability available up to 10
current, and voltage regulation current. The UPS senses the deviation of 900 kVA maximum
Real current is current that is in phase the voltage or frequency beyond ■ No disposal issues
with the supply voltage and supplies programmed tolerances and quickly
High-Speed Rotary Disadvantages
11
real power to the load. Real current disconnects the supply source by
flowing through the line inductor causes turning off the static disconnect switch ■ Flywheel does not have deep
a slight phase shift of the current and opening the input contactor. The reserve capacity—rides through 12
lagging the voltage by 10 degrees disconnect occurs in less than one-half for up to 13 seconds at 100% load
and ensures that the UPS can quickly cycle. Then the utility converter starts ■ Some enhanced flywheel systems
transfer to bypass without causing delivering power from the DC bus to may extend the ride through to 13
unacceptable switching transients. The the load, and the flywheel converter 30 seconds at 100% load
second component is charging current changes the firing point of its IGBTs ■ Mechanical flywheel maintenance
required by the flywheel to keep the to deliver power to the DC bus. The required every 2–3 years, and oil 14
rotating mass fully charged at rated UPS maintains a clean output voltage changes required every year
rpm, or to recharge the rotating mass within 3% or nominal voltage to the
after a discharge. The power to main- load when input power is lost. ■ Recharge fast rates require the 15
tain full charge is low at 2 kW and input to be sized for 125% of
is accomplished by the IGBTs of the Recharge Mode nominal current
flywheel converter gating to provide When input power is restored to ■ Flywheels failures in field not 16
small pulses of motoring current to the acceptable limits, the UPS synchronizes understood
flywheel. This current can be much the output and input voltages, closes ■ Requires vacuum pumps for
higher if fast recharge times are the input contactor and turns on the high-speed flywheels 17
selected. The final component of input static disconnect switch. The utility ■ Limited number of vendors and
current is the voltage regulation current, converter then transfers power from experience
which is usually a reactive current that the flywheel to the input source by 18
circulates between the input and the linearly increasing the real input
utility converter to regulate the output current. The transfer time is program-
voltage. Leading reactive current mable from 1 to 15 seconds. As soon 19
20
21
12
Bypass Breaker (Optional) UPS Module
13
Bypass Static Switch
14 Source Load
Normal Rectifier/Charger Output
Inverter
Breaker Breaker
15 AC DC
DC AC
16 Battery Breaker
17 Battery
18 Figure 1.4-19. Typical Static UPS, Double Conversion Type with Battery Backup
19
20
21
Static Double Conversion Disadvantages 3. The battery stores DC energy for C. Static line interactive UPS
■ Battery systems, battery maintenance use by the inverter when input concept of operation—the basic i
and battery replacement are required power to the UPS fails. The operation of the Line Interactive
amount of power available from UPS is:
■ Large space requirement for
battery systems (higher life takes
the DC battery system and time to ii
discharge voltage is a function of 1. The Line Interactive type of UPS
more space, e.g., 500 kW takes has a different topology than the
the type of battery selected and
80–200 sq ft depending upon the static double conversion and 1
the ampere-hour sized used.
type of battery used, VRLA 10 year, standby systems. The normal
Battery systems should be sized
VRLA 20 year or flooded) input power is connected to the
for the anticipated outage.
■ Limited discharge cycles of load in parallel with a battery 2
battery system 4. The DC link connects the output of and bi-directional inverter/charger
■ Narrow temperature range the rectifier/charger to the input of assembly. The input source usu-
for application the inverter and to the battery. ally terminates at a line inductor 3
Typically the rectifier/charger and the output of the inductor is
■ Efficiencies are in the 90–94%
is sized only to supply charger connected to the load in parallel
range, which is lower than some
line interactive configurations
power to the battery, and is with the battery and inverter/ 4
rated far lower than in the charger circuit. See Figure 1.4-21
■ Bypass mode places load at risk double conversion UPS. for more details.
unless bypass has UPS backup
5. The bypass circuit provides a 2. The traditional rectifier circuit
5
■ Redundancy of UPS modules
results in higher costs direct connection of input source is eliminated and this results
to the load. The load operates in a smaller footprint and
■ Output faults are cleared by the
from unregulated power. The weight reduction. However, line
6
bypass circuit
bypass static switch can switch conditioning is compromised.
■ Output rating of the UPS is 150% to non-conducting mode in 150–
for 30 seconds 120 milliseconds. When the UPS 3. When the input power fails, the 7
■ Battery disposal and safety recognizes the loss of normal battery/inverter charger circuit
issues exist input power, it transfers to battery/ reverses power and supplies the
inverter mode by simultaneously load with regulated power. 8
B. Standby UPS concept of
turning the Inverter ON and the Static Line Interactive UPS Advantages
operation—The basic operation of
static switch OFF. 9
the Standby UPS is: ■ Slight improvement of power
Static Standby UPS Advantages conditioning over standby
1. The Standby UPS topology is UPS systems
■ Lower costs than double conversion
similar to the double conversion
■ Small footprints and weights 10
type, but the operation of the UPS ■ Rectifier and charger are
is different in significant ways. economically sized ■ Efficient design
Normal power is connected to ■ Efficient design ■ Batteries are sized for the 11
the UPS input through the facility ■ Batteries are sized for the application
electrical distribution system. This application Static Line Interactive UPS Disadvantages
usually involves two input circuits 12
that must come from the same Static Standby UPS Disadvantages ■ Impractical over 5 kVA
source. See Figure 1.4-20 for ■ Impractical over 2 kVA ■ Not as good conditioning as
details.
■ Little to no isolation of load from double conversion 13
2. The rectifier/charger function power quality disturbances ■ Standby power is from battery alone
converts the normal AC power to ■ Standby power is from battery alone ■ Battery systems, battery mainte-
DC power to charge the battery nance and battery replacement 14
■ Battery systems, battery mainte-
only, and does not simultaneously nance and battery replacement are required
power the inverter. The load is Limited discharge cycles for the
connected to the input source
are required ■
battery system
15
■ Limited discharge cycles of
through the bypass static switch. ■ Narrow temperature range for
battery system
The inverter is in the standby
mode ready to serve the load ■ Narrow temperature range for application 16
application ■ Battery disposal and safety
from battery power if the input
■ Output faults are cleared by the issues exist
power source fails. 17
bypass circuit
■ Battery disposal and safety
issues exist 18
19
20
21
i UPS Module
2 Source Load
Rectifier/
Normal Output
3 Breaker
Charger Inverter
Breaker
AC DC
4 DC AC
Battery
Breaker
5
Battery
6
7 Figure 1.4-20. Typical Static UPS, Standby Type with Battery Backup
8 UPS Module
9
Source Load
10
Inductor
11
Bidirectional
12 Inverter/Charger
DC
13 AC
14
15 Battery
16
Figure 1.4-21. Typical Static UPS, Line Interactive Type with Battery Backup
17
18
19
20
21
Secondary Voltage Selection Technical Factors supplied from a 480V system through
The choice between 208Y/120V and The principal advantage of the use of step-down transformers, voltage drop i
higher secondary voltages in buildings in the 480V supply conductors can be
480Y/277V secondary distribution for compensated for by the tap adjust-
commercial and institutional buildings is that for a given load, less current
depends on several factors. The most means smaller conductors and lower ments on the transformer, resulting ii
voltage drop. Also, a given conductor in full 120V output. Because these
important of these are size and types transformers are usually located close
size can supply a large load at the
of loads (motors, fluorescent lighting,
same voltage drop in volts, but a lower to the 120V loads, secondary voltage 1
incandescent lighting, receptacles) drop should not be a problem. If it is,
and length of feeders. In general, large percentage voltage drop because of
the higher supply voltage. Fewer or taps may be used to compensate by
motor and fluorescent lighting loads,
smaller circuits can be used to transmit raising the voltage at the transformer. 2
and long feeders, will tend to make the
higher voltages, such as 480Y/277V, the power from the service entrance The interrupting ratings of circuit
point to the final distribution points.
more economical. Very large loads
Smaller conductors can be used in many
breakers and fuses at 480V have 3
and long runs would indicate the use increased considerably in recent years,
of medium voltage distribution and branch circuits supplying power loads, and protective devices are now available
and a reduction in the number of light-
loadcenter unit substations close to
ing branch circuits is usually possible.
for any required fault duty at 480V. 4
the loads. Conversely, small loads, In addition, many of these protective
short runs and a high percentage of It is easier to keep voltage drops within devices are current limiting, and can
incandescent lighting would favor acceptable limits on 480V circuits than be used to protect downstream equip- 5
lower utilization voltages such as on 208V circuits. When 120V loads are ment against these high fault currents.
208Y/120V.
Industrial installations, with large
6
motor loads, are almost always 480V,
often ungrounded delta or resistance
grounded delta or wye systems (see Elevator
7
section on ground fault protection). Panel
Practical Factors
Typical
8
Because most low voltage distribution
Emergency
equipment available is rated for up to Typical
600V, and conductors are insulated for
HVAC
Panel
Lighting Panel 9
(Typical Every
600V, the installation of 480V systems Third Floor)
uses the same techniques and is
essentially no more difficult, costly, or 10
480Y/277 V 208Y/120 V Typical
hazardous than for 208V systems. The Panel Panel
major difference is that an arc of 120V Dry Type Transformer
20
21
Economic Factors Motors and controls are another cause and consider the cost of losses as well
i Utilization equipment suitable for of wasted energy that can be reduced. as the initial cost of the transformers
principal loads in most buildings New, energy-efficient motor designs in purchasing.
is available for either 480V or 208V are available using more and better
ii systems. Three-phase motors and core steel, and larger windings. NEMA standard TP-1 is being adopted
by many states and is another method
their controls can be obtained for either For any motor operating 10 or more of energy-efficient design. NEMA TP-1
voltage, and for a given horsepower
1 are less costly at 480V. Fluorescent and
hours per day, it is recommended to establishes minimum operating
use the energy-efficient types. These efficiencies for each distribution
HID lamps can be used with either 277V motors have a premium cost of about transformer size at a loading equal to
or 120V ballasts. However, in almost all
2 cases, the installed equipment will have
20% more than standard motors. 35% of the transformer full load kVA.
Depending on loading, hours of use The 35% loading value in the NEMA
a lower total cost at the higher voltage. and the cost of energy, the additional standard reflects field studies con-
3 Energy Conservation
initial cost could be repaid in energy ducted by the U.S. Department of
saved within a few months, and it Energy, which showed that dry-type
Because of the greatly increased cost rarely takes more than two years. transformers installed in commercial
4 of electrical power, designers must Because, over the life of a motor, the facilities are typically loaded at an
consider the efficiency of electrical cost of energy to operate it is many average of 35% of their full load
distribution systems, and design for times the cost of the motor itself, any capacity over a 24-hour time period.
5 energy conservation. In the past, motor with many hours of use should Table 1.4-9 compares losses for
especially in commercial buildings, be of the energy-efficient type. both low temperature rise and TP-1
design was for lowest first cost, transformers using a 75 kVA design.
Where a motor drives a load with
6 because energy was inexpensive.
variable output requirements such Table 1.4-9. Load Losses
Today, even in the speculative office
building, operating costs are so high as a centrifugal pump or a large fan, Temp. Load Losses in Watts
customary practice has been to run the
7 that energy-conserving designs can
motor at constant speed, and to throttle
Rise ºC No 25% 35% 50% 75% Full
justify their higher initial cost with a Loss Load Load Load Load Load
rapid payback and continuing savings. the pump output or use inlet vanes or
outlet dampers on the fan. This is highly 150 360 490 620 885 1535 2450
8 Buildings that must meet LEED certifi-
inefficient and wasteful of energy. In 115 420 480 610 805 1170 1950
cations may require energy-saving 80 500 535 615 730 945 1410
designs. There are four major sources recent years, solid-state variable-
frequency, variable-speed drives for TP-1 150 230 310 480 745 1235 2280
9 of energy conservation in a commercial
ordinary induction motors have been
building—the lighting system, the Efficiencies above TP-1. Candidates
motors and controls, the transformers available, reliable and relatively
inexpensive. Using a variable-speed Standard Level (CSL) is a DOE
10 and the HVAC system.
drive, the throttling valves, inlet vanes efficiency evaluation for transformers.
The lighting system must take or output dampers can be eliminated, CSL-1 is equivalent to TP-1. Levels
saving their initial cost and energy are from CSL-1 to CSL-5. CSL-3 is
11 advantage of the newest equipment
over the life of the system. An being promoted for higher efficiency
and techniques. New light sources,
familiar light sources with higher additional benefit of both energy- applications. A NEMA white paper
Clarifications on the Use of DOE
12 efficiencies, solid-state ballasts with efficient motors and variable-speed
drives (when operated at less than Design—Lines 6, 7 and 8 is available
dimming controls, use of daylight,
environmental design, efficient full speed) is that the motors operate from NEMA that elaborates on
the matter.
13 luminaires, computerized or at reduced temperatures, resulting in
programmed control, and the like, increased motor life. HVAC systems have traditionally been
are some of the methods that can very wasteful of energy, often being
Transformers have inherent losses.
14 increase the efficiency of lighting
Transformers, like motors, are designed designed for lowest first cost. This,
systems. They add up to providing too, is changing. For example, reheat
the necessary amount of light, with the for lower losses by using more and
better core materials, larger conductors, systems are being replaced by variable
15 desired color rendition, from the most
etc., and this results in increased initial air volume systems, resulting in equal
efficient sources, where and when it is comfort with substantial increases in
needed, and not providing light where cost. Because the 480V to 208Y/120V
stepdown transformers in an office efficiency. While the electrical engineer
16 or when it is not necessary. Using the
building are usually energized 24 hours has little influence on the design of the
best of techniques, office spaces that HVAC system, he/she can specify that
originally required as much as 3.5W a day, savings from lower losses can
be substantial, and should be consid- all motors with continuous or long duty
17 per square foot have been given
ered in all transformer specifications. cycles are specified as energy-efficient
improved lighting, with less glare types, and that the variable-air-volume
and higher visual comfort, using as One method of obtaining reduced
losses is to specify transformers with fans do not use inlet vanes or outlet
18 little as 1.0 to 2.0W per square foot.
220°C insulation systems designed for dampers, but are driven by variable-
In an office building of 200,000 square speed drives. Variable-speed drives
feet (60,960m), this could mean a 150°C average winding temperature
rise, with no more than 80°C (or can often be desirable on centrifugal
19 saving of 400 kW, which, at $0.05 per
sometimes 115°C) average winding compressor units as well. Since some
kWh, 250 days per year, 10 hours per of these requirements will be in HVAC
day, could save $50,000 per year in temperature rise at full load. A
better method would be to evaluate specifications, it is important for the
20 energy costs. Obviously, efficient
transformer losses, based on actual energy-conscious electrical engineer
lighting is a necessity. to work closely with the HVAC engineer
loading cycles throughout the day,
at the design stage.
21
Building Control Systems Because building design and control been changed by the high cost of
In order to obtain the maximum benefit
for maximum energy saving is impor- purchased energy, plus a federal law i
tant and complex, and frequently (Public Utility Regulatory Policies Act,
from these energy-saving lighting, involves many functions and several known as PURPA) that requires public
power and HVAC systems, they must systems, it is necessary for the design utilities to purchase any excess power ii
be controlled to perform their functions engineer to make a thorough building generated by the cogeneration plant.
most efficiently. Constant monitoring and environmental study, and to In many cases, practical commercial
would be required for manual operation,
so some form of automatic control
weigh the costs and advantages of cogeneration systems have been built 1
many systems. The result of good that provide some or all of the electric
is required. The simplest of these design can be economical, efficient power required, plus hot water, steam,
energy-saving controls, often very operation. Poor design can be wasteful and sometimes steam absorption-type 2
effective, is a time clock to turn various and extremely costly. air conditioning. Such cogeneration
systems on and off. Where flexible systems are now operating success-
control is required, programmable Distributed Energy Resources fully in hospitals, shopping centers, 3
controllers may be used. These range high-rise apartment buildings and
from simple devices, similar to multi- Distributed energy resources (DER)
are increasingly becoming prominent even commercial office buildings.
function time clocks, up to full micro-
sources of electric power. Distributed
4
processor-based, fully programmable Where a cogeneration system is being
devices, really small computers. For energy resources are usually small-to- considered, the electrical distribution
complete control of all building systems, medium sources of electric generation, system becomes more complex. The 5
computers with specialized software either from renewable or non-renewable interface with the utility company is
can be used. Computers can not only sources. Sources include: critical, requiring careful relaying
control lighting and HVAC systems,
■ Photovoltaic (PV) systems to protect both the utility and the 6
and provide peak demand control, to cogeneration system. Many utilities
(solar systems)
minimize the cost of energy, but they have stringent requirements that
■ Wind
can perform many other functions. must be incorporated into the system. 7
Fire detection and alarm systems can ■ Fossil-fueled (diesel, natural gas, Proper generator control and protec-
operate through the computer, which landfill gas, coal-bed methane) tion is necessary, as well. An on-site
can also perform auxiliary functions generators (reciprocating engines) electrical generating plant tied to an 8
such as elevator control and building ■ Gas-fired turbines (natural gas, electrical utility, is a sophisticated
communication in case of fire. Building landfill gas, coal-bed methane) engineering design.
security systems, such as closed-circuit ■ Water-powered (hydro) Utilities require that when the
9
television monitoring, door alarms and
■ Fuel cells protective device at their substation
intruder sensing, can be performed by
the same building computer system. ■ Microturbines opens that the device connecting a 10
■ Wave power cogenerator to the utility open also.
The time clocks, programmable
■ Coal-fired boilers One reason is that most cogenerators
controllers and computers can 11
obtain data from external sensors are connected to feeders serving other
Distributed energy resources may also
and control the lighting, motors and customers. Utilities desire to reclose
be termed alternative energy resources.
other equipment by means of hard the feeder after a transient fault is
wiring-separate wires to and from Prime Power cleared. Reclosing in most cases will 12
each piece of equipment. In the more DER can be used for generating prime damage the cogenerator if it had
complex systems, this would result in remained connected to their system.
a tremendous number of control
power or for cogeneration. Prime power
concerns a system that is electrically
13
Islanding is another reason why the
wires, so other methods are frequently separated from the electrical grid. utility insists on the disconnection of
used. A single pair of wires, with elec- Prime power is generated at remote the cogenerator. Islanding is the event 14
tronic digital multiplexing, can control sites where commercial electrical that after a fault in the utility’s system
or obtain data from many different power is not available. is cleared by the operation of the
points. Sometimes, coaxial cable is protective devices, a part of the 15
used with advanced signaling equip- Cogeneration system may continue to be supplied
ment. Some systems dispense with by cogeneration. Such a condition is
Cogeneration is another outgrowth of
control wiring completely, sending
the high cost of energy. Cogeneration dangerous to the utility’s operation 16
and receiving digital signals over the during restoration work.
is the production of electric power
power wiring. The newest systems
concurrently with the production of
may use fiber-optic cables to carry
steam, hot water and similar energy
Major cogenerators are connected to 17
tremendous quantities of data, free the subtransmission or the transmission
uses. The electric power can be the
from electromagnetic interference. system of a utility. Major cogenerators
main product, and steam or hot water
The method used will depend on
the byproduct, as in most commercial
have buy-sell agreements. In such 18
the type, number and complexity cases, utilities use a trip transfer
installations, or the steam or hot water
of functions to be performed. scheme to trip the cogenerator breaker.
can be the most required product,
and electric power a byproduct, as Guidelines that are given in ANSI 19
in many industrial installations. In Guide Standard 1001 are a good
some industries, cogeneration has starting point, but the entire design
been common practice for many should be coordinated with the utility. 20
years, but until recently it has not been
economically feasible for most
commercial installations. This has 21
PV System Design Considerations in determining the maximum number High Temperature Equation
i Successful photovoltaic (PV) design
of solar modules per string for the Once the maximum number of
open-circuit photovoltaic (PV) voltage modules per string is established,
and construction is a complex multi- rise in cold weather (Voc < 600V as per the minimum number of modules per
ii discipline endeavor. Proper planning
includes the site-layout study for
NEC). Its low 300V MPPT lower-limit string needs to be calculated. Here,
ensures that multiple configurations more site-related aspects come into
maximizing the sun’s energy harvest- are possible for solar systems hot play, as the voltage of solar modules
1 ing for solar module selection, and weather voltage drop (i.e., Vmp decreases with increasing tempera-
for updating the electrical/mechanical as a function of temperature, solar
design and construction to the latest ture. The modules’ (photovoltaic cell)
irradiance and array-conductor voltage temperature is influenced by the
2 code and local constraints, including drop). The following equations are the ambient temperature, reflected sun-
fire marshal and seismic regulations. basis of all solar system layout and
Professionally prepared bid, permit, loads from nearby structures, parapet
design. Consult professional engineer- walls, roof-coatings, etc. Air-flow
3 construction and as-build drawings ing to help when planning any solar above and behind the solar modules
shall be required and maintained. system. Engineering design firms
For installation in/on/for existing affect the cell temperature. The
offering complete solar systems accepted industry standards to add
4 structures and sites, it is advised “turn-key” calculations, drawings, to the module heating is listed below.
that, at the minimum, pre-design construction management and
and construction tests be performed Unusual mounting systems may
procurement are a good place to adjust these figures, and it is best to
5 for existing power-quality issues, start. Eaton offers professional S-Max seek assistance in establishing and
water drainage and the utility feeder/ inverter application assistance, on-site
transformer, and that electrical planning such installations.
commissioning and maintenance
6 distribution panel ratings are verified services. Eaton maintains a working ■ 20°C for ground or pole mounted
sufficient for the planned solar system, relationship with the best engineering solar systems
and the necessary arc flash studies be services firms across the country, and ■ 25°C for roof-top solar systems
7 performed. Connection to the utility helps arrange the successful implanta- mounted at inclined angles
is always a utility interconnect agree- tion of your solar system. The S-Max (offers improved air-flow behind
ment (application) process, and is 250 kW inverter and up-fit solutions the modules)
8 typically required for the available easily perform well in Mega-Watt and ■ 30°C for roof-top solar systems
solar incentives and programs offered Utility-Scale systems. Eaton also offers
by the utility, municipality, state, and mounted flat, yet at least 6.00 inches
a wide range of balance-of-system (152.4 mm) above the roof surface
9 various federal agencies and depart- (BOS) products, ranging from solar
ments. State, and IRS tax incentives module source and array combiners, Vmp_min = Vmp + (temp-differential x
require well-documented records. to DC and AC breakers, electrical and temp-coefficient-of-Vmp)
10 Solar systems, while low mainte- distribution panels and switchgear.
The temp-differential in this case
nance, do require periodic service. includes the above temperature
Low Temperature Equation
11 The solar modules need to be washed- “adders.” The Vmp and related
clean on a regular basis and electrical Voc_max = Voc + (temp-differential x
temp-coefficient-of-Voc) temperature coefficients are listed
terminations require initial and annual on the solar module’s data sheets.
12 checks. Cooling system filters are The temp-differential is the difference
periodic maintenance items, with the between the standard module rating While the code doesn’t indicate the
re-fresh rate dependent upon typical at 25°C and the low temperature. high temperature to use (i.e., because
13 and unusual circumstances. The voltage (Voc) will rise with it is an equipment application issue),
temperatures under 25°C. the industry standard is to evaluate the
Solar systems installed near other new ASHRAE 2% and 4% high temperature
construction where dust is generated Seek the solar module data sheet for
14 (e.g., grading, paving) or agricultural a list of standard test condition (STC)
figures, coupled to known location
differences. Record high temperatures
environments may require additional data, temperature coefficients, and provide an indication of system
solar-system checks and services. any special module-related informa-
15 Planning for such contingencies is tion to determine the low-temperature
performance when climatic condition
reaches these levels.
the business of solar-system design, open circuit voltage. The NEC 2011,
construction and on-going operation. Beyond the damaging temperature
16 Performance-based incentives
and industry practice, requires the
use of the site’s Extreme Annual affects on photovoltaic module Vmp
require verifiable metering, often Mean Minimum Design Dry Bulb voltage levels, voltage drop in PV
by registered/approved independent conductors under such conditions also
17 third parties. Such monitoring periods
Temperature data, available in the
ASHRAE Handbook. Code requires need to be calculated and evaluated,
are typically for 60 or more months. that the resulting maximum voltage beyond normal temperatures. The
inverter only uses (knows) the Vmp
18 The S-Max inverter offers a wide range (Voc) when added in the “string of
voltage at the inverter, not at the
of features and options to enable a modules” be under 600V. Record
low temperatures provide an PV modules.
successful and long-lived solar-energy
19 harvesting solution. The isolation step- indication of system performance Increasing grid voltages also puts a
up transformer, coupled to either a when temperatures drop to these constraint on the minimum Vmp
negative or a positive grounded solar levels. The S-Max inverter is designed voltage at the DC input stage.
20 array, ensures that the S-Max can to standards higher than 600 Vdc.
match to all (known) solar module
technologies. The S-Max follows
21 standard industry and code practices
To ensure the full MPPT range without federal or other codes, or by any nation, with a rechargeable battery,
power-clipping (reduced power governmental agency having jurisdic- a charger to keep it at full capacity i
output), prudent PV system designs tion. Optional standby systems, not when normal power is on, one or more
shall consider the PV array’s Vmp legally required, are also covered in lamps, and a relay to connect the
voltage drop to the point of the the NEC (Article 702). battery to the lamps on loss of normal ii
inverter connection, ambient power, is also permitted. Because
temperatures and the PV system Emergency systems are intended to of the critical nature of emergency
installation type’s effects on Vmp, supply power and illumination essen- power, ground fault protection is not 1
solar module miss-match and tial for safety to human life, when the required. It is considered preferable
tolerance variations, degradation of normal supply fails. NEC requirements to risk arcing damage, rather than to
solar modules over time (solar system are stringent, requiring periodic testing disconnect he emergency supply com- 2
life), etc. Typical Vmp design values, under load and automatic transfer to pletely. For emergency power, ground
based upon known and expected emergency power supply on loss of fault alarm is required by NEC 700.7(D)
conditions are 5–10% over the normal supply. See Figure 1.4-23. to indicate a ground fault in solidly 3
minimum MPPT tracking voltage. All wiring from emergency source to grounded wye emergency systems
Reference NEC 2011 Section 690, emergency loads must be kept separate of more than 150V to ground and
Solar Photovoltaic Systems. from all other wiring and equipment, circuit-protective devices rated 1000A 4
in its own distribution and raceway or more.
Emergency Power system, except in transfer equipment
9
Utility
Source
Typical Application: Three engine generator sets serve the load, plus one additional engine
generator set for redundancy to achieve N+1 level of performance. Open or Closed transition is available. 10
G1 G2 G3 G4
Paralleling Switchgear
with Distribution
11
Revenue
Metering
HMI 12
Touchscreen
52G1 52G2 52G3 52G4
Main D1 D2 D3 D4
13
Service
14
15
16
ATS1 N E ATS2 N E ATS3 N E ATS4 N E
To Normal To Emergency
Distribution Circuits 17
Circuits
Optional Remote PC 19
with Software
LP1 BP1 LP2 BP2 LP3 BP3 LP4 BP4
20
Figure 1.4-23. Typical Emergency Power System
21
NEC requirements are similar to those Industrial plants, especially in process It is important that the electrical sys-
i for emergency systems, except that industries, usually have some form tem designer providing a substantial
wiring may occupy the same distribu- of alternate power source to prevent source of emergency and standby
tion and raceway system as the extremely costly shutdowns. These power investigate the possibility of
ii normal wiring if desired. Optional standby generating systems are using it for peak shaving, and even
standby systems are those not legally critical when needed, but they are of partial utility company financing.
required, and are intended to protect needed only infrequently. They Frequently, substantial savings in
1 private business or property where represent a large capital investment. power costs can be realized for a
life safety does not depend on To be sure that their power will be small additional outlay in distribution
performance of the system. Optional available when required, they should and control equipment.
2 systems can be treated as part of the be tested periodically under load.
normal building wiring system. Both Peak shaving equipment operating in
legally required and optional standby The cost of electric energy has risen parallel with the utility are subject to the
3 systems should be installed in such to new high levels in recent years, and comments made under cogeneration
a manner that they will be fully avail- utilities bill on the basis not only of as to separation from the utility under
able on loss of normal power. It is power consumed, but also on the fault conditions.
4 preferable to isolate these systems basis of peak demand over a small
as much as possible, even though not interval. As a result, a new use for Sound Levels
required by code. in-house generating capacity has
5 developed. Utilities measure demand Sound Levels of Electrical Equipment
Where the emergency or standby charges on the basis of the maximum for Offices, Hospitals, Schools and
source, such as an engine generator demand for electricity in any given Similar Buildings
6 or separate service, has capacity to specific period (typically 15 or 30 Insurance underwriters and building
supply the entire system, the transfer minutes) during the month. Some owners desire and require that the
scheme can be either a full-capacity utilities have a demand “ratchet clause” electrical apparatus be installed
7 automatic transfer switch, or, less that will continue demand charges on for maximum safety and the least
costly but equally effective, normal a given peak demand for a full year, interference with the normal use of
and emergency main circuit breakers, unless a higher peak results in even the property. Architects should take
8 electrically interlocked such that on higher charges. One large load, coming particular care with the designs for
failure of the normal supply the on at a peak time, can create higher hospitals, schools and similar build-
emergency supply is connected to the electric demand charges for a year. ings to keep the sound perception of
9 load. However, if the emergency or
Obviously, reducing the peak demand such equipment as motors, blowers
standby source does not have capacity and transformers to a minimum.
for the full load, as is usually the can result in considerable savings in
10 case, such a scheme would require the cost of electrical energy. For those Even though transformers are
automatic disconnection of the installations with engine generators relatively quiet, resonant conditions
nonessential loads before transfer. for emergency use, modern control may exist near the equipment, which
11 Simpler and more economical in systems (computers or programmable will amplify their normal 120 Hz hum.
such a case is a separate emergency controllers) can monitor the peak Therefore, it is important that consid-
bus, supplied through an automatic demand, and start the engine-generator eration be given to the reduction of
12 transfer switch, to feed all critical to supply part of the demand as it
approaches a preset peak value. The
amplitude and to the absorption of
loads. The transfer switch connects energy at this frequency. This problem
this bus to the normal supply, in engine-generator must be selected begins in the designing stages of the
13 normal operation. On failure of the to withstand the required duty cycle. equipment and the building. There are
normal supply, the engine-generator The simplest of these schemes trans- two points worthy of consideration: 1)
is started, and when it is up to speed fer specific loads to the generator. What sound levels are desired in the
14 the automatic switch transfers the More complex schemes operate the normally occupied rooms of this build-
emergency loads to this source. On generator in parallel with the normal ing? 2) To effect this, what sound level
return of the normal source, manual or utility supply. The savings in demand in the equipment room and what type
15 automatic retransfer of the emergency charges can reduce the cost of owning of associated acoustical treatment
loads can take place. the emergency generator equipment. will give the most economical
In some instances, utilities with little installation overall?
16 Peak Shaving reserve capacity have helped finance A relatively high sound level in the
Many installations now have the cost of some larger customer- equipment room does not indicate
emergency or standby generators. owned generating equipment. In an abnormal condition within the
17 In the past, they were required for return, the customer agrees to take apparatus. However, absorption may
hospitals and similar locations, but some or all of his load off the utility be necessary if sound originating in
not common in office buildings or system and on to his own generator at
18 shopping centers. However, many the request of the utility (with varying
an unoccupied equipment room is
objectionable outside the room.
costly and unfortunate experiences limitations) when the utility load Furthermore, added absorption
during utility blackouts in recent years approaches capacity. In some cases,
19 have led to the more frequent installa- the customer’s generator is paralleled
material usually is desirable if
there is a “build-up” of sound
tion of engine generators in commer- with the utility to help supply the peak due to reflections.
utility loads, with the utility buying the
20 cial and institutional systems for safety
and for supplying important loads. supplied power. Some utilities have
been able to delay large capital expen-
ditures for additional generating
21 capacity by such arrangements.
Some reduction or attenuation takes Table 1.4-11. Maximum Average Sound Levels—Decibels
place through building walls, the kVA Liquid-Filled Transformers Dry-Type Transformers i
remainder may be reflected in various Self-Cooled Forced-Air Self-Cooled Forced-Air
directions, resulting in a build-up or Rating (OA) Cooled Rating (FA) Rating (AA) Cooled Rating (FA)
apparent higher levels, especially if ii
resonance occurs because of room 300 55 — 58 67
dimensions or material characteristics. 500 56 67 60 67
750 58 67 64 67 1
Area Consideration 1000 58 67 64 67
In determining permissible sound lev- 1500 60 67 65 68
2000 61 67 66 69
els within a building, it is necessary to
2500 62 67 68 71
2
consider how the rooms are to be used
3000 63 67 68 71
and what levels may be objectionable 3750 64 67 70 73
to occupants of the building. The
5000 65 67 71 73
3
ambient sound level values given in 6000 66 68 72 74
Table 1.4-10 are representative average 7500 67 69 73 75
values and may be used as a guide in 10,000 68 70 — 76
4
determining suitable building levels.
Because values given in Table 1.4-11 transmitted vibration is approximately
Decrease in sound level varies at an
are in general higher than those given 98%. If the floor or beams beneath 5
approximate rate of 6 dB for each
doubling of the distance from the in Table 1.4-10, the difference must be the transformer are light and flexible,
attenuated by distance and by proper the isolator must be softer or have
source of sound to the listener. For
use of materials in the design of the improved characteristics in order to 6
example, if the level 6 ft (1.8m) from
a transformer is 50 dB, the level at a building. An observer may believe keep the transmitted vibrations to a
that a transformer is noisy because minimum. (Enclosure covers and
distance of 12 ft (3.7m) would be 44 dB
the level in the room where it is ventilating louvers are often improp- 7
and at 24 ft (7.3m) the level decreases
to 38 dB, etc. However, this rule applies located is high. Two transformers of erly tightened or gasketed and
the same sound output in the same produce unnecessary noise.) The
only to equipment in large areas
room increase the sound level in the building structure will assist the 8
equivalent to an out-of-door installation,
with no nearby reflecting surfaces. room approximately 3 dB, and three dampeners if the transformer is
transformers by about 5 dB, etc. mounted above heavy floor members
Table 1.4-10. Typical Sound Levels or if mounted on a heavy floor slab. 9
Sounds due to structure-transmitted Positioning of the transformer in
Description Average vibrations originating from the trans- relation to walls and other reflecting
Decibel
Level (dB) former are lowered by mounting the surfaces has a great effect on reflected
10
transformers on vibration dampeners noise and resonances. Often, placing
Radio, recording and TV studios 25–30 or isolators. There are a number of the transformer at an angle to the wall,
Theatres and music rooms 30–35 different sound vibration isolating rather than parallel to it, will reduce
11
Hospitals, auditoriums and churches 35–40
materials that may be used with noise. Electrical connections to a
Classrooms and lecture rooms 35–40 good results. Dry-type power trans- substation transformer should
Apartments and hotels
Private offices and conference rooms
35–45
40–45
formers are often built with an isolator be made with flexible braid or
12
mounted between the transformer conductors; connections to an
Stores 45–55
support and case members. The individually mounted transformer
Residence (radio, TV off)
and small offices 53 natural period of the core and coil should be in flexible conduit.
13
Medium office (3 to 10 desks) 58 structure when mounted on vibration
Residence (radio, TV on) 60 dampeners is about 10% of the funda-
Large store (5 or more clerks) 61 mental frequency. The reduction in the 14
Factory office 61
Large office 64
Average factory 70 15
Average street 80
21
ii
10
11
12
13
14
15
16
17
18
19
20
21
2 Time-delay starting or closing relay A device that functions to give a desired amount Used for providing a time-delay for
of time delay before or after any point of operation re-transfer back to the normal source
ii
in a switching sequence or protective relay system, in an automatic transfer scheme.
except as specifically provided by device functions
48, 62 and 79 described later. 1
6 Starting circuit breaker A device whose principal function is to connect —
a machine to its source of starting voltage.
19 Starting to running transition timer A device that operates to initiate or cause the Used to transfer a reduced voltage
2
automatic transfer of a machine from the starting starter from starting to running.
to the running power connection.
21 Distance relay A device that functions when the circuit — 3
admittance, impedance or reactance increases or
decreases beyond predetermined limits.
23 Temperature control device A device that functions to raise or to lower the Used as a thermostat to control 4
temperature of a machine or other apparatus, or space heaters in outdoor equipment.
of any medium, when its temperature falls below
or rises above, a predetermined level. 5
24 Volts per hertz relay A device that operates when the ratio of voltage —
to frequency is above a preset value or is below
a different preset value. The relay may have any
combination of instantaneous or time delayed
6
characteristics.
25 Synchronizing or synchronism check device A device that operates when two AC circuits are In a closed transition breaker
within the desired limits of frequency, phase angle transfer, a 25 relay is used to ensure 7
or voltage, to permit or cause the paralleling of two-sources are synchronized before
these two circuits. paralleling. Eaton FP-5000/EDR-5000
feeder protective relays. 8
27 Undervoltage relay A device which functions on a given value of Used to initiate an automatic transfer
undervoltage. when a primary source of power is lost.
Eaton FP-5000/FP-4000/MP-4000/
EDR-5000/EDR-4000 protective relays.
9
30 Annunciator relay A non-automatically reset device that gives a Used to remotely indicate that a
number of separate visual indications upon the
functioning of protective devices, and which may
protective relay has functioned, or
that a circuit breaker has tripped.
10
also be arranged to perform a lockout function. Typically, a mechanical “drop” type
annunciator panel is used.
32 Directional power relay A relay that functions on a desired value of power Used to prevent reverse power from 11
flow in a given direction, or upon reverse power feeding an upstream fault. Often
resulting from arc back in the anode or cathode used when primary backup generation
circuits of a power rectifier. is used in a facility. Eaton FP-5000/
EDR-5000 protective relays.
12
33 Position switch A device that makes or breaks contact when the Used to indicate the position of a
main device or piece of apparatus, which has no
device function number, reaches a given point.
drawout circuit breaker (TOC switch). 13
34 Master sequence device A device such as a motor-operated multi-contact —
switch, or the equivalent, or a programmable
device, that establishes or determines the operating
14
sequence of the major devices in equipment
during starting and stopping, or during sequential
switching operations. 15
37 Undercurrent or underpower relay A relay that functions when the current or power Eaton MP-3000/MP-4000/EMR-3000
flow decreases below a predetermined value. motor protective relays.
38 Bearing protective device A device that functions on excessive bearing Eaton MP-3000/MP-4000 motor 16
temperature, or on other abnormal mechanical protective relays.
conditions, such as undue wear, which may
eventually result in excessive bearing temperature. 17
40 Field relay A device that functions on a given or abnormally —
high or low value or failure of machine field current,
or on an excessive value of the reactive component
of armature current in an AC machine indicating
18
abnormally high or low field excitation.
41 Field circuit breaker A device that functions to apply, or to remove, —
the field excitation of a machine. 19
42 Running circuit breaker A device whose function is to connect a machine —
to its source of running or operating voltage.
This function may also be used for a device, such 20
as a contactor, that is used in series with a circuit
breaker or other fault-protecting means, primarily
for frequent opening and closing of the circuit. 21
Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
i Device Function Definition Typical
Number Uses
ii 43 Manual transfer or selector device A manually operated device that transfers control
or potential circuits in order to modify the plan of
—
5 48 Incomplete sequence relay A relay that generally returns the equipment to the —
normal, or off, position and locks it out of the
normal starting, or operating or stopping sequence
is not properly completed within a predetermined
6 amount of time. If the device is used for alarm
purposes only, it should preferably be designated
as 48A (alarm).
7 49 Machine, or transformer, thermal relay A relay that functions when the temperature of a Eaton MP-3000/MP-4000/EMR-3000/
machine armature, or other load carrying winding ETR-4000 motor protective relays.
or element of a machine, or the temperature
of a power rectifier or power transformer
8 (including a power rectifier transformer) exceeds
a predetermined value.
50 Instantaneous overcurrent, A relay that functions instantaneously on an Used for tripping a circuit breaker
9 or rate-of-rise relay excessive value of current, or an excessive rate of instantaneously during a high-level
current rise, thus indicating a fault in the apparatus short circuit. Can trip on phase-
of the circuit being protected. phase (50), phase-neutral (50N),
10 phase-ground (50G) faults.
Eaton Digitrip 3000, FP-5000/
FP-4000/EDR-5000/EDR-4000/
EDR-3000 protective relays,
11 MP-3000/MP-4000/EMR-3000/
ETR-4000 motor protective relays.
51 AC time overcurrent relay A relay with either a definite or inverse time Used for tripping a circuit breaker
12 characteristic that functions when the current in an after a time delay during a sustained
AC circuit exceeds a predetermined value. overcurrent. Used for tripping a
circuit breaker instantaneously
during a high-level short circuit.
13 Can trip on phase (51), neutral (51N)
or ground (51G) overcurrents.
Eaton Digitrip 3000, FP-5000/
14 FP-4000/EDR-5000/EDR-4000/
EDR-3000 protective relays,
MP-3000/MP-4000/EMR-3000/
ETR-4000 motor protective relays.
15 52 AC circuit breaker A device that is used to close and interrupt an A term applied typically to medium
AC power circuit under normal conditions or to voltage circuit breakers, or low
interrupt this circuit under fault or emergency voltage power circuit breakers.
16 conditions. Eaton VCP-W vacuum circuit
breaker, magnum DS low voltage
power circuit breaker
17 53 Exciter or DC generator relay A device that forces the DC machine field excitation —
to build up during starting or that functions when
the machine voltage has built up to a given value.
18 55 Power factor relay A relay that operates when the power factor Eaton FP-5000/FP-4000/EDR-5000
in an AC circuit rises above or below a feeder protective relays and MP-4000
predetermined value. motor protective relay.
19 56 Field application relay A device that automatically controls the application —
of the field excitation to an AC motor at some
predetermined point in the slip cycle.
Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
Device Function Definition Typical i
Number Uses
Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
i Device Function Definition Typical
Number Uses
14
15
16
17
18
19
20
21
F Frequency/fault S Solenoid 13
I0 Zero sequence current SI Seal-in
20
21
Codes and Standards a number of other testing laboratories A design engineer should conform
i The National Electrical Code (NEC),
have been recognized and accepted. to all applicable codes, and require
The Institute of Electrical and Electronic equipment to be listed by UL or
NFPA Standard No. 70, is the most Engineers (IEEE) publishes a number another recognized testing laboratory
ii prevalent electrical code in the United
States. The NEC, which is revised every
of books (the “color book” series) on wherever possible, and to meet
recommended practices for the design ANSI or NEMA standards. ANSI/IEEE
three years, has no legal standing of of industrial buildings, commercial recommended practices should
1 its own, until it is adopted as law by buildings, emergency power systems, be followed to a great extent. In
a jurisdiction, which may be a city, grounding, and the like. Most of these many cases, standards should be
county or state. Most jurisdictions IEEE standards have been adopted as exceeded to get a system of the
2 adopt the NEC in its entirety; some ANSI standards. They are excellent quality required. The design goal
adopt it with variations, usually more guides, although they are not in any should be a safe, efficient, long-
rigid, to suit local conditions and way mandatory. lasting, flexible and economical
3 requirements. A few large cities, such electrical distribution system.
as New York and Chicago, have their
own electrical codes, basically similar Professional Organizations
4 to the NEC. The designer must deter-
American National Standards Institute National Electrical Manufacturers
mine which code applies in the area
of a specific project. (ANSI) Association (NEMA)
5 The Occupational Safety and Health Headquarters: 1300 North 17th Street
Suite 1847
Act (OSHA) of 1970 sets uniform 1819 L Street, NW Rosslyn, VA 22209
national requirements for safety in the 6th Floor
6 workplace—anywhere that people are Washington, DC 20036
703-841-3200
employed. Originally OSHA adopted 202-293-8020 www.nema.org
the 1971 NEC as rules for electrical
7 safety. As the NEC was amended every Operations: National Fire Protection Association
three years, the involved process for 25 West 43rd Street (NFPA)
modifying a federal law such as OSHA 4th Floor 1 Battery March Park
8 made it impossible for the act to adopt New York, NY 10036 Quincy, MA 02169-7471
each new code revision. To avoid this 212-642-4900 617-770-3000
problem, the OSHA administration
9 in 1981 adopted its own code, a con- www.ansi.org www.nfpa.org
densed version of the NEC containing Institute of Electrical and Electronic Underwriters Laboratories (UL)
10 only those provisions considered Engineers (IEEE) 333 Pfingsten Road
related to occupational safety. OSHA
Northbrook, IL 60062-2096
was amended to adopt this code, Headquarters:
847-272-8800
11 based on NFPA Standard 70E, Part 1, 3 Park Avenue
which is now federal law. 17th Floor www.ul.com
The NEC is a minimum safety New York, NY 10016-5997
International Code Council (ICC)
12 standard. Efficient and adequate 212-419-7900
5203 Leesburg Pike
design usually requires not just Operations: Suite 600
meeting, but often exceeding NEC
13 requirements to provide an effective,
445 Hoes Lane Falls Church, VA 22041
1-888-422-7233
Piscataway, NJ 08854-1331
reliable, economical electrical system.
732-981-0060
www.iccsafe.org
14 Many equipment standards have been
www.ieee.org
established by the National Electrical The American Institute of Architects (AIA)
Manufacturers’ Association (NEMA) International Association of Electrical 1735 New York Avenue, NW
15 and the American National Standards Inspectors (IAEI) Washington, DC 20006-5292
Institute (ANSI). Underwriters 202-626-7300
901 Waterfall Way
Laboratories (UL) has standards that
Suite 602
16 equipment must meet before UL will
Richardson, TX 75080-7702
www.aia.org
list or label it. Most jurisdictions and
972-235-1455
OSHA require that where equipment
17 listed as safe by a recognized labora- www.iaei.org
tory is available, unlisted equipment
may not be used. UL is by far the most
18 widely accepted national laboratory,
although Factory Mutual Insurance
Company lists some equipment, and
19
20
21
Motor Protection Table 1.5-2. Motor Circuit Protector (MCP), Circuit Breaker and Fusible Switch Selection Guide
Consistent with the 2011 NEC Horsepower Full Load Fuse Size NEC 430.52 Recommended Eaton i
Amperes Maximum Circuit Motor Circuit
430.6(A)(1) circuit breaker, HMCP and (NEC) FLA Amperes
fuse rating selections are based on Breaker Protector Type HMCP
full load currents for induction motors Time Delay Non-Time Delay Amperes Amperes Adj. Range
ii
running at speeds normal for belted 230V, Three-Phase
motors and motors with normal 1 3.6 10 15 15 7 21–70 1
torque characteristics using data taken 1-1/2 5.2 10 20 15 15 45–150
from NEC Table 430.250 (three-phase). 2 6.8 15 25 15 15 45–150
3 9.6 20 30 20 30 90–300
Actual motor nameplate ratings shall 2
be used for selecting motor running 5 15.2 30 50 30 30 90–300
overload protection. Motors built 7-1/2 22 40 70 50 50 150–500
10 28 50 90 60 50 150–500
special for low speeds, high torque 15 42 80 150 90 70 210–700 3
characteristics, special starting
20 54 100 175 100 100 300–1000
conditions and applications will 25 68 125 225 125 150 450–1500
require other considerations as 30 80 150 250 150 150 450–1500 4
defined in the application section 40 104 200 350 150 150 750–2500
of the NEC. 50 130 250 400 200 150 750–2500
These additional considerations may
60 154 300 500 225 250 1250–2500 5
75 192 350 600 300 400 2000–4000
require the use of a higher rated HMCP, 100 248 450 800 400 400 2000–4000
or at least one with higher magnetic
pickup settings.
125
150
312
360
600
700
1000
1200
500
600
600
600
1800–6000
1800–6000
6
200 480 1000 1600 700 600 1800–6000
Circuit breaker, HMCP and fuse
ampere rating selections are in 460V, Three-Phase 7
line with maximum rules given in 1 1.8 6 6 15 7 21–70
1-1/2 2.6 6 10 15 7 21–70
NEC 430.52 and Table 430.250. Based
on known characteristics of Eaton type
2
3
3.4
4.8
6
10
15
15
15
15
7
15
21–70
45–150
8
breakers, specific units are recom- 5 7.6 15 25 15 15 45–150
mended. The current ratings are no 7-1/2 11 20 35 25 30 90–300
more than the maximum limits set by 10 14 25 45 35 30 90–300 9
the NEC rules for motors with code 15 21 40 70 45 50 150–500
letters F to V or without code letters. 20 27 50 90 50 50 150–500
Motors with lower code letters will 25 34 60 110 70 70 210–700 10
require further considerations. 30 40 70 125 70 100 300–1000
40 52 100 175 100 100 300–1000
In general, these selections were 50 65 125 200 110 150 450–1500 11
based on: 60 77 150 150 125 150 750–2500
75 96 175 300 150 150 750–2500
1. Ambient—outside enclosure not
more than 40°C (104°F).
100 124 225 400 175 150 750–2500
12
125 156 300 500 225 250 1250–2500
150 180 350 600 250 400 2000–4000
2. Motor starting—infrequent 200 240 450 800 350 400 2000–4000
starting, stopping or reversing.
575V, Three-Phase
13
3. Motor accelerating time— 1 1.4 3 6 15 3 9–30
10 seconds or less. 1-1/2
2
2.1
2.7
6
6
10
10
15
15
7
7
21–70
21–70
14
4. Locked rotor—maximum 6 times 3 3.9 10 15 15 7 21–70
motor FLA. 5 6.1 15 20 15 15 45–150
7-1/2 9 20 30 20 15 45–150 15
Type HMCP motor circuit protector 10 11 20 35 25 30 90–300
may not set at more than 1300% of 15 17 30 60 40 30 90–300
the motor full-load current to comply 20 22 40 70 50 50 150–500 16
with NEC 430.52. (Except for NEMA 25 27 50 90 60 50 150–500
Design B energy high-efficiency 30 32 60 100 60 50 150–500
motors that can be set up to 1700%.) 40 41 80 125 80 100 300–1000 17
50 52 100 175 100 100 300–1000
Circuit breaker selections are based 60 62 110 200 125 150 750–2500
on types with standard interrupting 75
100
77
99
150
175
250
300
150
175
150
150
750–2500
750–2500
18
ratings. Higher interrupting rating types
may be required to satisfy specific 125 125 225 400 200 250 1250–2500
150 144 300 450 225 250 1250–2500
system application requirements.
200 192 350 600 300 400 2000–4000 19
For motor full load currents of
208V and 200V, increase the
corresponding 230V motor values
20
by 10 and 15% respectively.
21
10
11
12
13
14
15
16
17
18
19
20
21
20
21
10
11
12
13
14
15
16
17
18
19
20
21
Approximate Impedance Data Table 1.5-9. 600V Primary Class Three-Phase Table 1.5-10. 600V Primary Class Three-Phase
Table 1.5-6. Typical Impedances—
NEMA TP-1 Energy-Efficient Dry-Type NEMA TP-1 Energy-Efficient Dry-Type i
Distribution Transformers, Aluminum Wound Distribution Transformers, Copper Wound
Three-Phase Transformers Liquid-Filled
kVA %Z %R %X X/R kVA %Z %R %X X/R
kVA Liquid-Filled
150°C Rise Aluminum 150°C Rise Copper
ii
Network Padmount
15 4.8 4.6 1.4 0.30 15 4.8 4.0 2.6 0.65
30 4.6 3.5 3.0 0.86 30 5.2 3.1 4.1 1.33
37.5
45
—
—
—
— 45 5.1 3.8 3.4 0.91 45 4.6 3.5 3.0 0.86
1
50 — — 75 5.3 3.5 4.0 1.14 75 4.3 3.4 2.5 0.72
75 — 3.4 112.5 6.0 2.9 5.2 1.79 112.5 5.1 2.9 4.2 1.44
112.5 — 3.2 150 5.3 3.0 4.4 1.50 150 4.3 2.5 3.5 1.39 2
150 — 2.4
225 5.1 2.6 4.4 1.68 225 7.4 2.9 6.8 2.32
225 — 3.3 300 7.6 2.5 7.2 2.88 300 5.5 2.4 4.9 2.04
300 5.00 3.4 500 7.2 1.7 7.0 4.20 500 6.8 1.4 6.7 4.86 3
500 5.00 4.6
750 8.0 1.5 7.9 5.42 750 8.2 0.8 8.1 10.13
750 5.00 5.75
115°C Rise Aluminum 115°C Rise Copper
1000
1500
5.00
7.00
5.75
5.75 15 4.4 4.3 1.2 0.27 15 4.8 3.8 2.9 0.76
4
2000 7.00 5.75 30 4.8 4.4 1.8 0.41 30 4.6 3.0 3.5 1.19
2500 7.00 5.75 45 4.6 2.8 3.7 1.35 45 4.4 3.1 3.1 0.99
3000 — 6.50 75 5.9 2.8 5.1 1.82 75 4.7 2.7 3.9 1.43
5
3750 — 6.50 112.5 3.1 2.5 1.9 0.79 112.5 5.0 2.3 4.5 1.98
5000 — 6.50 150 5.2 2.2 4.7 2.16 150 4.4 1.9 4.0 2.09
Values are typical. For guaranteed values, 225 6.2 2.0 5.8 2.93 225 8.1 2.6 7.7 2.99
6
refer to transformer manufacturer. 300 5.4 2.0 4.9 2.44 300 5.2 1.7 4.9 2.80
500 6.6 1.1 6.5 6.09 500 6.8 1.3 6.6 5.16
Table 1.5-7. 15 kV Class Primary— 80°C Rise Aluminum 80°C Rise Copper 7
Oil Liquid-Filled Substation Transformers 15 3.5 2.6 2.3 0.89 15 2.1 1.7 1.3 0.75
30 3.4 2.4 2.5 1.02 30 3.0 2.0 2.1 1.05
kVA %Z %R %X X/R
45 3.3 1.6 2.9 1.76 45 3.9 2.5 3.1 1.25 8
65°C Rise
75 4.3 1.9 3.9 2.05 75 4.3 2.0 3.8 1.93
112.5 5.00 1.71 4.70 2.75 112.5 4.1 1.8 3.7 2.04 112.5 3.3 1.8 2.8 1.60
150
225
5.00
5.00
1.88
1.84
4.63
4.65
2.47
2.52
150 4.7 1.4 4.5 3.22 150 3.7 1.8 3.2 1.78 9
225 5.6 1.4 5.4 3.77 225 5.4 1.5 5.2 3.60
300 5.00 1.35 4.81 3.57
300 6.1 1.4 5.9 4.18 300 6.1 1.2 6.0 5.07
500 5.00 1.50 4.77 3.18
750 5.75 1.41 5.57 3.96 500 5.4 0.8 5.3 6.57 10
Note: Values are typical. Measurements at
1000 5.75 1.33 5.59 4.21 Note: Values are typical. Measurements at
1500 5.75 1.12 5.64 5.04
temperature rise +20ºC.
2000 5.75 0.93 5.67 6.10 temperature rise +20°C. 11
2500 5.75 0.86 5.69 6.61
Table 1.5-11. 600V Primary Class
NEMA Type TP-1 Dry-Type Transformers 12
Table 1.5-8. 15 kV Class Primary—
Dry-Type Substation Transformers kVA Temperature Rise Impedance
19
20
21
10
11
12
13
14
15
16
17
18
19
20
21
20
21
2 2
Average Characteristics of Application Notes ■ Z = X +R
i 600V Conductors— ■ Resistance and reactance are ■ For busway impedance data, see
phase-to-neutral values, based on Tab 21 of this catalog
Ohms per 1000 ft (305m)
ii The tables below are average charac-
60 Hz AC, three-phase, four-wire
distribution, in ohms per 100 ft
■ For PF (power factor) values less
than 1.0, the effective impedance Z e
teristics based on data from IEEE (30m) of circuit length (not total is calculated from
Standard 141-1993. Values from
1 different sources vary because of
conductor lengths) Z e = R × PF + X sin (arc cos PF)
■ Based upon conductivity of 100%
operating temperatures, wire ■ For copper cable data, resistance
for copper, 61% for aluminum
stranding, insulation materials based on tinned copper at 60 Hz;
2 and thicknesses, overall diameters, ■ Based on conductor temperatures
600V and 5 kV nonshielded cable
random lay of multiple conductors of 75°C. Reactance values will
based on varnished cambric insula-
in conduit, conductor spacing, and have negligible variation with
3 tion; 5 kV shielded and 15 kV cable
other divergences in materials, test temperature. Resistance of both
based on neoprene insulation
conditions and calculation methods. copper and aluminum conductors
will be approximately 5% lower ■ For aluminum cable data, cable is
These tables are for 600V 5 kV and
4 15 kV conductors, at an average at 60°C or 5% higher at 90°C. cross-linked polyethylene insulated
temperature of 75°C. Other parameters Data shown in tables may be
are listed in the notes. For medium used without significant error
5 voltage cables, differences among between 60° and 90°C
manufacturers are considerably ■ For interlocked armored cable,
greater because of the wider variations use magnetic conduit data for
6 in insulation materials and thick- steel armor and non-magnetic
nesses, shielding, jacketing, overall conduit data for aluminum armor
7 diameters, and the like. Therefore,
data for medium voltage cables should
be obtained from the manufacturer
8 of the cable to be used.
Table 1.5-16. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305m) at 75ºC (a) Three Single Conductors
9 Wire Size, In Magnetic Duct In Non-Magnetic Duct
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
10 R X Z R X Z R X Z R X Z
8 0.811 0.0754 0.814 0.811 0.0860 0.816 0.811 0.0603 0.813 0.811 0.0688 0.814
8 (solid) 0.786 0.0754 0.790 0.786 0.0860 0.791 0.786 0.0603 0.788 0.786 0.0688 0.789
11 6 0.510 0.0685 0.515 0.510 0.0796 0.516 0.510 0.0548 0.513 0.510 0.0636 0.514
6 (solid) 0.496 0.0685 0.501 0.496 0.0796 0.502 0.496 0.0548 0.499 0.496 0.0636 0.500
4 0.321 0.0632 0.327 0.321 0.0742 0.329 0.321 0.0506 0.325 0.321 0.0594 0.326
12 4 (solid)
2
0.312
0.202
0.0632
0.0585
0.318
0.210
0.312
0.202
0.0742
0.0685
0.321
0.214
0.312
0.202
0.0506
0.0467
0.316
0.207
0.312
0.202
0.0594
0.0547
0.318
0.209
1 0.160 0.0570 0.170 0.160 0.0675 0.174 0.160 0.0456 0.166 0.160 0.0540 0.169
13 1/0
2/0
0.128
0.102
0.0540
0.0533
0.139
0.115
0.128
0.103
0.0635
0.0630
0.143
0.121
0.127
0.101
0.0432
0.0426
0.134
0.110
0.128
0.102
0.0507
0.0504
0.138
0.114
3/0 0.0805 0.0519 0.0958 0.0814 0.0605 0.101 0.0766 0.0415 0.0871 0.0805 0.0484 0.0939
4/0 0.0640 0.0497 0.0810 0.0650 0.0583 0.0929 0.0633 0.0398 0.0748 0.0640 0.0466 0.0792
14 250 0.0552 0.0495 0.0742 0.0557 0.0570 0.0797 0.0541 0.0396 0.0670 0.0547 0.0456 0.0712
300 0.0464 0.0493 0.0677 0.0473 0.0564 0.0736 0.0451 0.0394 0.0599 0.0460 0.0451 0.0644
350 0.0378 0.0491 0.0617 0.0386 0.0562 0.0681 0.0368 0.0393 0.0536 0.0375 0.0450 0.0586
15 400 0.0356 0.0490 0.0606 0.0362 0.0548 0.0657 0.0342 0.0392 0.0520 0.0348 0.0438 0.0559
450 0.0322 0.0480 0.0578 0.0328 0.0538 0.0630 0.0304 0.0384 0.0490 0.0312 0.0430 0.0531
500 0.0294 0.0466 0.0551 0.0300 0.0526 0.0505 0.0276 0.0373 0.0464 0.0284 0.0421 0.0508
16 600
750
0.0257
0.0216
0.0463
0.0495
0.0530
0.0495
0.0264
0.0223
0.0516
0.0497
0.0580
0.0545
0.0237
0.0194
0.0371
0.0356
0.0440
0.0405
0.0246
0.0203
0.0412
0.0396
0.0479
0.0445
18
19
20
21
Table 1.5-17. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305m) at 75ºC (b) Three Conductor Cable
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor i
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
ii
8 0.811 0.0577 0.813 0.811 0.0658 0.814 0.811 0.0503 0.812 0.811 0.0574 0.813
8 (solid) 0.786 0.0577 0.788 0.786 0.0658 0.789 0.786 0.0503 0.787 0.786 0.0574 0.788
6
6 (solid)
0.510
0.496
0.0525
0.0525
0.513
0.499
0.510
0.496
0.0610
0.0610
0.514
0.500
0.510
0.496
0.0457
0.0457
0.512
0.498
0.510
0.496
0.0531
0.0531
0.513
0.499
1
4 0.321 0.0483 0.325 0.321 0.0568 0.326 0.321 0.0422 0.324 0.321 0.0495 0.325
4 (solid)
2
0.312
0.202
0.0483
0.0448
0.316
0.207
0.312
0.202
0.0508
0.0524
0.317
0.209
0.312
0.202
0.0422
0.0390
0.315
0.206
0.312
0.202
0.0495
0.0457
0.316
0.207
2
1 0.160 0.0436 0.166 0.160 0.0516 0.168 0.160 0.0380 0.164 0.160 0.0450 0.166
1/0 0.128 0.0414 0.135 0.128 0.0486 0.137 0.127 0.0360 0.132 0.128 0.0423 0.135
2/0 0.102 0.0407 0.110 0.103 0.0482 0.114 0.101 0.0355 0.107 0.102 0.0420 0.110 3
3/0 0.0805 0.0397 0.0898 0.0814 0.0463 0.0936 0.0766 0.0346 0.0841 0.0805 0.0403 0.090
4/0 0.0640 0.0381 0.0745 0.0650 0.0446 0.0788 0.0633 0.0332 0.0715 0.0640 0.0389 0.0749
250 0.0552 0.0379 0.0670 0.0557 0.0436 0.0707 0.0541 0.0330 0.0634 0.0547 0.0380 0.0666 4
300 0.0464 0.0377 0.0598 0.0473 0.0431 0.0640 0.0451 0.0329 0.0559 0.0460 0.0376 0.0596
350 0.0378 0.0373 0.0539 0.0386 0.0427 0.0576 0.0368 0.0328 0.0492 0.0375 0.0375 0.0530
400 0.0356 0.0371 0.0514 0.0362 0.0415 0.0551 0.0342 0.0327 0.0475 0.0348 0.0366 0.0505 5
450 0.0322 0.0361 0.0484 0.0328 0.0404 0.0520 0.0304 0.0320 0.0441 0.0312 0.0359 0.0476
500 0.0294 0.0349 0.0456 0.0300 0.0394 0.0495 0.0276 0.0311 0.0416 0.0284 0.0351 0.0453
600 0.0257 0.0343 0.0429 0.0264 0.0382 0.0464 0.0237 0.0309 0.0389 0.0246 0.0344 0.0422
750 0.0216 0.0326 0.0391 0.0223 0.0364 0.0427 0.0197 0.0297 0.0355 0.0203 0.0332 0.0389 6
Table 1.5-18. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Ft (305m) at 90ºC (a) Three Single Conductors
Wire Size, In Magnetic Duct In Non-Magnetic Duct
7
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z 8
6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —
4 0.532 0.050 0.534 0.532 0.068 0.536 0.532 0.040 0.534 0.532 0.054 0.535
2 0.335 0.046 0.338 0.335 0.063 0.341 0.335 0.037 0.337 0.335 0.050 0.339 9
1 0.265 0.048 0.269 0.265 0.059 0.271 0.265 0.035 0.267 0.265 0.047 0.269
1/0 0.210 0.043 0.214 0.210 0.056 0.217 0.210 0.034 0.213 0.210 0.045 0.215
2/0
3/0
0.167
0.133
0.041
0.040
0.172
0.139
0.167
0.132
0.055
0.053
0.176
0.142
0.167
0.133
0.033
0.037
0.170
0.137
0.167
0.132
0.044
0.042
0.173
0.139
10
4/0 0.106 0.039 0.113 0.105 0.051 0.117 0.105 0.031 0.109 0.105 0.041 0.113
250
300
0.0896
0.0750
0.0384
0.0375
0.0975
0.0839
0.0892
0.0746
0.0495
0.0479
0.102
0.0887
0.0894
0.0746
0.0307
0.0300
0.0945
0.0804
0.0891
0.0744
0.0396
0.0383
0.0975
0.0837
11
350 0.0644 0.0369 0.0742 0.0640 0.0468 0.0793 0.0640 0.0245 0.0705 0.0638 0.0374 0.0740
400 0.0568 0.0364 0.0675 0.0563 0.0459 0.0726 0.0563 0.0291 0.0634 0.0560 0.0367 0.0700
500 0.0459 0.0355 0.0580 0.0453 0.0444 0.0634 0.0453 0.0284 0.0535 0.0450 0.0355 0.0573 12
600 0.0388 0.0359 0.0529 0.0381 0.0431 0.0575 0.0381 0.0287 0.0477 0.0377 0.0345 0.0511
700 0.0338 0.0350 0.0487 0.0332 0.0423 0.0538 0.0330 0.0280 0.0433 0.0326 0.0338 0.0470
750 0.0318 0.0341 0.0466 0.0310 0.0419 0.0521 0.0309 0.0273 0.0412 0.0304 0.0335 0.0452 13
1000 0.0252 0.0341 0.0424 0.0243 0.0414 0.0480 0.0239 0.0273 0.0363 0.0234 0.0331 0.0405
Table 1.5-19. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 ft (30m) at 90ºC (b) Three Conductor Cable 14
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z 15
6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —
4
2
0.532
0.335
0.050
0.046
0.534
0.338
—
0.335
—
0.056
—
0.340
0.532
0.335
0.040
0.037
0.534
0.337
—
0.335
—
0.045
—
0.338
16
1 0.265 0.048 0.269 0.265 0.053 0.270 0.265 0.035 0.267 0.265 0.042 0.268
1/0 0.210 0.043 0.214 0.210 0.050 0.216 0.210 0.034 0.213 0.210 0.040 0.214
2/0 0.167 0.041 0.172 0.167 0.049 0.174 0.167 0.033 0.170 0.167 0.039 0.171 17
3/0 0.133 0.040 0.139 0.133 0.048 0.141 0.133 0.037 0.137 0.132 0.038 0.138
4/0 0.106 0.039 0.113 0.105 0.045 0.114 0.105 0.031 0.109 0.105 0.036 0.111
250 0.0896 0.0384 0.0975 0.0895 0.0436 0.100 0.0894 0.0307 0.0945 0.0893 0.0349 0.0959 18
300 0.0750 0.0375 0.0839 0.0748 0.0424 0.0860 0.0746 0.0300 0.0804 0.0745 0.0340 0.0819
350 0.0644 0.0369 0.0742 0.0643 0.0418 0.0767 0.0640 0.0245 0.0705 0.0640 0.0334 0.0722
400 0.0568 0.0364 0.0675 0.0564 0.0411 0.0700 0.0563 0.0291 0.0634 0.0561 0.0329 0.0650
19
500 0.0459 0.0355 0.0580 0.0457 0.0399 0.0607 0.0453 0.0284 0.0535 0.0452 0.0319 0.0553
600 0.0388 0.0359 0.0529 0.0386 0.0390 0.0549 0.0381 0.0287 0.0477 0.0380 0.0312 0.0492
700 0.0338 0.0350 0.0487 0.0335 0.0381 0.0507 0.0330 0.0280 0.0433 0.0328 0.0305 0.0448
750 0.0318 0.0341 0.0466 0.0315 0.0379 0.0493 0.0309 0.0273 0.0412 0.0307 0.0303 0.0431 20
1000 0.0252 0.0341 0.0424 0.0248 0.0368 0.0444 0.0239 0.0273 0.0363 0.0237 0.0294 0.0378
21
Current Carrying Capacities of Copper and Aluminum and Copper-Clad Aluminum Conductors
i From National Electrical Code (NEC), 2011 Edition (NFPA 70-2011)
Table 1.5-20. Allowable Ampacities of Insulated Conductors Rated 0–2000V, 60° to 90°C (140° to 194°F).
ii Not more than three current-carrying conductors in raceway, cable or earth (directly buried), based on ambient temperature of 30°C (86°F).
Size Temperature Rating of Conductor (See Table 310.15 [B][16]) Size
AWG or 60°C (140°F) 75°C (167°F) 90°C (194°F) 60°C (140°F) 75°C (167°F) 90°C (194°F) AWG or
1 kcmil Types Types kcmil
TW, UF RHW, THHW, TBS, SA, SIS, TW, UF RHW, THHW, TBS, SA, SIS,
2 THW, THWN,
XHHW, USE, ZW
FEP, FEPB, MI,
RHH, RHW-2,
THW, THWN,
XHHW, USE
THHN, THHW,
THW-2, THWN-2,
THHN, THHW, RHH, RHW-2,
THW-2, THWN-2, USE-2, XHH,
3 USE-2, XHH, XHHW, XHHW-2,
XHHW, XHHW-2, ZW-2
ZW-2
4 Copper Aluminum or Copper-Clad Aluminum
18 — — 14 — — — —
16 — — 18 — — — —
5 14 15 20 25 — — — —
12 20 25 30 20 20 25 12
10 30 35 40 25 30 35 10
6 8 40 50 55 30 40 45 8
6 55 65 75 40 50 60 6
4 70 85 95 55 65 75 4
7 3 85 100 110 65 75 85 3
2 95 115 130 75 90 100 2
1 110 130 150 85 100 115 1
8 1/0 125 150 170 100 120 135 1/0
2/0 145 175 195 115 135 150 2/0
3/0 165 200 225 130 155 175 3/0
9 4/0 195 230 260 150 180 205 4/0
250 215 255 290 170 205 230 250
300 240 285 320 190 230 255 300
10 350 260 310 350 210 250 280 350
400 280 335 380 225 270 305 400
500 320 380 430 260 310 350 500
600 355 420 475 285 340 385 600
11 700 385 460 520 310 375 420 700
750 400 475 535 320 385 435 750
800 410 490 555 330 395 450 800
12 900 435 520 585 355 425 480 900
1000 455 545 615 375 445 500 1000
1250 495 590 665 405 485 545 1250
13 1500 520 625 705 435 520 585 1500
1750 545 650 735 455 545 615 1750
2000 560 665 750 470 560 630 2000
14 See NEC Section 240.4 (D).
Note: For complete details of using Table 1.5-20, see NEC Article 310 in its entirety.
15 Table 1.5-21. Correction Factors From NFPA 70-2011 (See Table 310.15 [B][2][a])
Ambient For ambient temperatures other than 30°C (86°F), multiply the allowable ampacities shown Ambient
Temperature °C above by the appropriate factor shown below. Temperature °F
16
21–25 1.08 1.05 1.04 1.08 1.05 1.04 070–77
26–30 1.00 1.00 1.00 1.00 1.00 1.00 078–86
17 31–35 0.91 0.94 0.96 0.91 0.94 0.96 087–95
36–40 0.82 0.88 0.91 0.82 0.88 0.91 096–104
41–45 0.71 0.82 0.87 0.71 0.82 0.87 105–113
18 46–50 0.58 0.75 0.82 0.58 0.75 0.82 114–122
51–55 0.41 0.67 0.76 0.41 0.67 0.76 123–131
56–60 — 0.58 0.71 — 0.58 0.71 132–140
61–70 — 0.33 0.58 — 0.33 0.58 141–158
19 71–80 — — 0.41 — — 0.41 159–176
20
21
Ampacities for Conductors (4) Preservation of the safety benefits (4) Adjustment factors shall not
i
of established industry practices apply to Type AC cable or to
Rated 0–2000V (Excerpted and standardized procedures. Type MC cable under the following
from NFPA 70-2011, 310.15) (1) General. For explanation of type
conditions:
ii
Note: Fine Print Note (FPN) was changed letters used in tables and for a. The cables do not have an overall
to Informational Note in the 2011 NEC. recognized sizes of conductors for outer jacket.
(A) General.
the various conductor insulations,
b. Each cable has not more than three 1
see Table 310.104(A) and Table
310.104(B). For installation current-carrying conductors.
(1) Tables or Engineering Supervision.
Ampacities for conductors shall requirements, see 310.1 through c. The conductors are 12 AWG copper. 2
be permitted to be determined by 310.15(A)(3) and the various
tables as provided in 310.15(B) or articles of this Code. For flexible d. Not more than 20 current-carrying
under engineering supervision, cords, see Table 400.4, Table conductors are installed without 3
as provided in 310.15(C). 400.5(A)(1) and Table 400.5(A)(2). maintaining spacing, are stacked,
or are supported on”bridle rings.”
Note: Informational Note No. 1: Ampacities (3) Adjustment Factors.
provided by this section do not take voltage (5) An adjustment factor of 60 percent 4
drop into consideration. See 210.19(A), (a) More Than Three Current- shall be applied to Type AC cable or
Informational Note No. 4, for branch circuits Carrying Conductors in a Raceway Type MC cable under the following
and 215.2(A), Informational No. 2, for feeders. or Cable. Where the number of conditions: 5
Note: Informational Note No. 2: For the current-carrying conductors in a
allowable ampacities of Type MTW wire, raceway or cable exceeds three, or a. The cables do not have an overall
see Table 13.5.1 in NFPA 79-2007, Electrical where single conductors or multi- outer jacket. 6
Standard for Industrial Machinery. conductor cables are installed
b. The number of current carrying
without maintaining spacing for
(2) Selection of Ampacity. Where a continuous length longer than
conductors exceeds 20. 7
more than one ampacity applies 24.00-inch (600 mm) and are not c. The cables are stacked or bundled
for a given circuit length, the installed in raceways, the allowable longer that 24.00-inch (600 mm)
lowest value shall be used. ampacity of each conductor shall without spacing being maintained. 8
Exception: Where two different be reduced as shown in Table
ampacities apply to adjacent 310.15(B)(3)(a). Each current-carrying (b) More Than One Conduit, Tube,
portions of a circuit, the higher conductor of a paralleled set of or Raceway. Spacing between 9
ampacity shall be permitted to conductors shall be counted as a conduits, tubing, or raceways
be used beyond the point of current-carrying conductor. shall be maintained.
transition, a distance equal to 10 ft
(c) Circular Raceways Exposed to
10
(3.0m) or 10 percent of the circuit Note: Informational Note No. 1: See Annex
length figured at the higher B, Table B.310.15(B)(2)(11), for adjustment Sunlight on Rooftops.
ampacity, whichever is less. factors for more than three current-carrying
conductors in a raceway or cable with Where conductors or cables are 11
Note: Informational Note: See 110.14(C) for load diversity. installed in circular raceways exposed
conductor temperature limitations due to to direct sunlight on or above rooftops,
termination provisions. Note: Informational Note No. 2: See 366.23(A) the adjustments shown in Table 1.5-22 12
for adjustment factors for conductors in shall be added to the outdoor
(B) Tables. Ampacities for conductors sheet metal auxiliary gutters and 376.22(B) temperature to determine the
rated 0–2000V shall be as specified for adjustment factors for conductors in applicable ambient temperature 13
metal wireways.
in the Allowable Ampacity for application of the correction
Table 310.15(B)(16) through factors in Table 310.15(B)(2)(a) or
Table 310.15(B)(19), and
(1) Where conductors are installed in
Table 310.15(B)(2)(b). 14
cable trays, the provisions of
Ampacity Table 310.15(B)(20) and 392.80 shall apply. Note: Informational Note: One source for
Table 310.15(B)(21) as modified
by 310.15(B)(1) through (B)(7). (2) Adjustment factors shall not apply
the average ambient temperatures in various 15
locations is the ASHRAE Handbook
to conductors in raceways having —Fundamentals.
Note: Informational Note: Table
a length not exceeding 24.00-inch
310.15(B)(16) through Table 310.15(B)(19)
(600 mm). Table 1.5-22. NEC (2011) Table 310.15(B)(3)(c)
16
are application tables for use in determining
conductor sizes on loads calculated in Ambient Temperature Adjustment for Circular
(3) Adjustment factors shall not apply Raceways Exposed to Sunlight On or
accordance with Article 220. Allowable
ampacities result from consideration of one to underground conductors enter- Above Rooftops
17
or more of the following: ing or leaving an outdoor trench
Distance Above Roof to Temperature
if those conductors have physical
(1) Temperature compatibility with protection in the form of rigid
Bottom of Conduit Adder ºF (ºC) 18
connected equipment, especially metal conduit, intermediate metal 0–0.51-inch (0–13.0 mm) 60 (33)
the connection points. conduit, rigid polyvinyl chloride Above 0.51-inch (13.0 mm)– 40 (22)
conduit (PVC), or reinforced 3.54-inch (90.0 mm) 19
(2) Coordination with circuit and thermosetting resin conduit (RTRC) Above 3.54-inch (90.0 mm)– 30 (17)
system overcurrent protection. having a length not exceeding 11.81-inch (300.0 mm)
(3) Compliance with the requirements 10 ft (3.05m), and if the number of Above 12.00-inch (300.0 mm)– 25 (14)
20
of product listings or certifications. conductors does not exceed four. 36.00-inch (900.0 mm)
See 110.3(B). 21
(4) Bare or Covered Conductors. (b) In a three-wire circuit consisting (6) Grounding or Bonding Conductor.
i Where bare or covered conductors of two phase conductors and the A grounding or bonding conductor
are installed with insulated neutral conductor of a four-wire, shall not be counted when applying
conductors, the temperature three-phase, wye-connected the provisions of 310.15(B)(3)(a).
ii rating of the bare or covered system, a common conductor
conductor shall be equal to the carries approximately the same
lowest temperature rating of the current as the line-to-neutral load
1 insulated conductors for the currents of the other conductors
purpose of determining ampacity. and shall be counted when applying
the provisions of 310.15(B)(3)(a).
2 (5) Neutral Conductor.
(c) On a four-wire, three-phase wye
(a) A neutral conductor that carries circuit where the major portion of
only the unbalanced current from
3 other conductors of the same
the load consists of nonlinear
loads, harmonic currents are
circuit shall not be required to present in the neutral conductor;
be counted when applying the
4 provisions of 310.15(B)(3)(a).
the neutral conductor shall there-
fore be considered a current-
carrying conductor.
5
10
11
12
13
14
15
16
17
18
19
20
21
20
21
i Seismic Requirements
ii
1
General
2 In the 1980s, Eaton embarked on a
comprehensive program centered
around designing and building
3 electrical distribution and control
equipment capable of meeting and
exceeding the seismic load require-
4 ments of the Uniform Building Code
(UBC) and California Building Code
(CBC). These codes emphasize build-
5 ing design requirements. Electrical
equipment and distribution system
components are considered attach-
6 ments to the building. The entire
program has been updated to show
compliance with the 2009 International
7 Building Code (IBC) and the 2010 CBC
seismic requirements. A cooperative Figure 1.5-1. Typical Earthquake Ground Motion Map for the United States
effort with the equipment user, the
8 building designer and the equipment International Building Code (IBC) California Building Code
installer ensures that the equipment On December 9, 1994, the International The 2001 CBC was based upon the
is correctly anchored such that it can Code Council (ICC) was established 1997 UBC. In August of 2006, it was
9 withstand the effects of an earthquake. as a nonprofit organization dedicated repealed by the California Building
Eaton’s electrical distribution and to developing a single set of compre- Standards Commission (CBSC) and
control equipment has been tested hensive and coordinated codes. The replaced by the 2007 CBC, California
10 and seismically proven for require- ICC founders—the Building Officials Code of Regulations (CCR), Title 24,
ments exceeding the IBC and CBC. and Code Administrators (BOCA), the Part 2 and used the 2006 IBC as the
Over 100 different assemblies International Conference of Building basis for the code. The 2010 CBC
11 representing essentially all product Officials (ICBO), and the Southern is based upon the 2009 IBC, with
lines have been successfully tested Building Code Congress International amendments as deemed appropriate
and verified to seismic levels higher (SBCCI)—created the ICC in response by the CBSC. Eaton’s seismic
12 than the maximum seismic require- to technical disparities among the qualification program fully envelopes
ments specified in the IBC and CBC. three nationally recognized model the requirements of the 2010 CBC.
The equipment maintained structural codes now in use in the U.S. The
13 integrity and demonstrated the ability ICC offers a single, complete set of Process
to function immediately after the construction codes without regional
seismic tests. A technical paper, According to Chapter 16 of the 2009
limitations—the International
14 Earthquake Requirements and Eaton Building Code.
IBC, structure design, the seismic
Distribution and Control Equipment requirements of electrical equipment
in buildings may be computed in two
Seismic Capabilities (SA12501SE), Uniform Building Code (UBC)
15 provides a detailed explanation steps. The first step is to determine
of the applicable seismic codes 1997 was the final year in which the the maximum ground motion to be
and Eaton’s equipment qualification UBC was published. It has since been considered at the site. The second step
16 program. The paper may be found replaced by the IBC. is to evaluate the equipment mounting
at www.eaton.com/seismic. Type and attachments inside the building
in SA12501SE in the document or structure. These are then evaluated
17 search field. to determine appropriate seismic test
requirements. The ground motion,
seismic requirements of the equipment,
18 and the seismic response spectrum
requirements are discussed on
Page 1.5-22, see Figure 1.5-3.
19
20
21
Ground Motion If the latitude and longitude of the SDS, the peak spectral acceleration,
According to the code, the first and
building location is not known, extends between the values of T 0 and i
another convenient Web site is TS. T0 and TS are defined in the codes
most important step in the process available that will provide this as follows:
is to determine the maximum information based upon a street ii
considered earthquake spectral address: http://geocoder.us/ T0 = 0.2 SD1/SDS = 0.2 x 1.24/1.90 =
response acceleration at short 0.131 seconds (7.63 Hz)
periods of 0.2 seconds (SS) and at
a period of 1.0 second (S1). These
To determine the maximum consid-
TS = SD1/SDS = 1.24/1.90 = 1
ered earthquake ground motion for
values are determined from a set most site classes (A through D), the 0.653 seconds (1.53 Hz)
of 24 spectral acceleration maps code introduces site coefficients, According to the IBC and ASCE 7, the 2
(Figure 1.5-1) and include numerous which when applied against the spectral acceleration (Sa) at periods
contour lines indicating the severity location-specific site class, produces less than 1.45 seconds may be com-
of the earthquake requirements at a the adjusted maximum considered puted by using the following formula: 3
particular location in the country. earthquake spectral response
acceleration for the required site. Sa = SDS (0.6 T/T0 + 0.4)
The spectral acceleration maps
indicate low to moderate seismic
The site coefficients are defined as Where T is the period where Sa is 4
Fa at 0.2 seconds short period and being calculated:
requirements for the entire country, FV at 1.0 second period. From the
with the exception of two particular
areas; the West Coast and the Midwest
tables in the code, the highest adjust- Therefore, the acceleration at 5
ing factor for SS is equal to 1.0 and the 0.0417 seconds (24 Hz), for example,
(the New Madrid area). The seismic highest adjusting factor for S1 is 1.50. is equal to:
requirements at the New Madrid area
are approximately 30% higher than the As a result, the adjusted maximum Sa = 1.90 (0.6 (0.0417/0.131) + 0.4) = 1.12g
6
maximum requirements of the West considered earthquake spectral
Coast. The maps also suggest that the response for 0.2 second short period The acceleration at 0.03 seconds
high seismic requirements in both (SMS) and at 1.0 second (SM1), adjusted (33 Hz) is equal to: 7
regions, West Coast and Midwest, for site class effects, are determined Sa = 1.90 (0.6 (0.03/0.131) + 0.4) = 1.02g
quickly decrease as one moves away from the following equations:
from the fault area. Therefore, the high At zero period (infinite frequency), 8
requirements are only limited to a SMS = Fa SS = 1.0 x 2.85g = 2.85g T = 0.0, the acceleration (ZPA) is
relatively narrow strip along the fault equal to:
lines. Just a few miles away from this
SM1 = Fv S1 = 1.5 x 1.24g = 1.86g 9
Sa = 1.90 (0.6 (0.0/0.131) + 0.4) =
strip, only a small percentage of the ASCE 7 (American Society of Civil
0.76g (ZPA)
maximum requirements are indicated. Engineers), Section 11.4, provides a
plot of the final shape of the design The acceleration to frequency
10
Assuming the worse condition, which response spectra of the seismic relationship in the frequency range
is a site directly located near a fault, ground motion. The plot is shown in
the maximum considered earthquake Figure 1.5-2. ASCE 7 is referenced
of 1.0 Hz to TS is stated equal to: 11
spectral response acceleration at short throughout the IBC as the source for Sa = SD1/T
periods of 0.2 seconds (SS) is equal to numerous structural design criteria.
285% gravity and at 1.0 second period Where Sa is the acceleration at the 12
(S1) is 124% gravity. These numbers The design spectral acceleration curve T period.
are the maximum numbers for the can now be computed. The peak spec- At 1.0 Hz (T=1.0) this equation yields
entire country except for the New tral acceleration (SDS) and the spectral the following acceleration:
13
Madrid area. These particular sites are acceleration at 1.0 second (SD1) may
on the border of California and Mexico now be computed from the following Sa = 1.24/1 = 1.24g
(S1) and in Northern California (SS). formulas in the code: 14
To help understand the 2009 IBC (and SDS = 2/3 x SMS = 2/3 x 2.85g = 1.90g
2010 CBC) seismic parameters for a
SD1 = 2/3 x SM1 = 2/3 x 1.8g = 1.24g
15
specific building location, the link to
the US Geological Society is extremely
helpful: http://earthquake.usgs.gov/ 16
Spectural Response Acceleration Sa(g)
research/hazmaps/design/
SDS
Download the file “Java Ground 17
Motion Parameter Calculator”—and SD1
Sa =
save it to your hard drive, then run the T
executable that was downloaded. 18
The program will allow one to enter SD1 S T
Sa = D12 L
the latitude and longitude of a T
location. (One must be connected 19
to the Internet to run this application,
even after downloading the program.)
The IBC (CBC) seismic parameters for 20
T0 TS 1.0 TL
that location will then be displayed. Period T (sec)
21
Figure 1.5-2. Design Response Spectrum
Testing has demonstrated that the It can be seen that Eaton has elected to This completes the ground motion
i lowest dominant natural frequency of develop generic seismic requirements design response spectrum. The
Eaton’s electrical equipment is above that envelop two criteria: spectral accelerations are equal to
3.2 Hz. This indicates that testing at 0.76g at ZPA, or 33 Hz, and increases
ii 1.24g at 1 Hz is not necessary. In ■ The highest possible spectral peak linearly to a peak acceleration of 1.90g
addition, having the low end of the accelerations and ZPA at 0.09 seconds (or 11.49 Hz) and stays
spectra higher than realistically ■ The maximum frequency range constant to 0.653 seconds (1.53 Hz),
1 required forces the shake table to required for many different sites then gradually decreases to 1.24g at
move at extremely high displacements 1 second (or 1.0 Hz). This curve is
to meet the spectral acceleration at shown in Figure 1.5-3.
2 the low frequencies.
Testing to accommodate the low end
3 of the spectra using this acceleration 10
9
component can result in testing to a 8
7 Test Response Spectrum Zero Period
factor 2 to 3 times greater than that Acceleration (g peak) 6 (TRS) Acceleration = Maximum
4 realistically required. 5
4
Table Test Motion
Acceleration (g)
The seismic response at the middle of
base mounted equipment close to its 1 2
C.G. is at least 50% higher than the
Eaton Seismic
floor input at the equipment natural
frequency. The base accelerations 3
associated with the accelerations of
FP/WP at the C.G. of the equipment
could then be computed as 3.42 /1.5 4
= 2.28g. It is the equipment base input
acceleration that is measured and
documented during seismic testing
0.1 5
1 10 100
and is the acceleration value shown
on Eaton’s seismic certificates. Frequency (Hz)
6
Final Combined Requirements Figure 1.5-4. Required Response Spectrum Curve
To better compare all seismic levels 7
and determine the final envelope
10
seismic requirements, the 2010 CBC,
2009 IBC for California, and 2009 IBC 8
for New Madrid area seismic require-
ments are plotted in Figure 1.5-4. All Eaton 120% Seismic Envelope
curves are plotted at 5% damping. An 9
envelopment of the seismic levels in
the frequency range of 3.2 Hz to 100 Hz
10
Acceleration (g)
16
17
18
19
20
21
16
17
18
19
20
21
Additional Design and If steel, factors such as thickness or Stand-Alone or Free-Standing Equipment
Installation Considerations gauge, attachment via bolts or welding, If stand-alone or free-standing, then i
and the size and type of hardware this may require that additional width
When installing electrical distribution must be considered. space be allowed at each end of the
and control equipment, consideration equipment for additional seismic ii
must be given as to how the methods If concrete, the depth, the PSI, the type
of re-enforcing bars used, as well as bracing supplied by the manufacturer.
employed will affect seismic forces
imposed on the equipment, equipment the diameter and embedment of Additional thought must be given to 1
mounting surface, and conduits anchorage all must be considered. the clearances around the equipment
entering the equipment. The designer must also give consider- to rigid structural edifices. Space must
ation if the equipment will be secured be allowed for the differing motions of 2
Eaton recommends that when specify- the equipment and the structure, so
ing a brand of electrical distribution to the wall, versus stand-alone or free-
standing, which requires the equip- that they do not collide during a seis-
and control equipment, the designer
ment to withstand the highest level of mic event and damage one another. 3
references the installation manuals of
that manufacturer to ascertain that the seismic forces. Top cable entry should Note: If the equipment is installed as stand-
be avoided for large enclosures, as alone or free-standing, with additional
requirements can be met through the
accommodation for cable/conduit seismic bracing at each end and not
4
design and construction process.
flexibility will need to be designed attached to the structure as tested, and yet,
For Eaton electrical distribution and into the system. it is fitted tightly against a structural wall,
control products, the seismic installa- then this would be an incorrect installation 5
tion guides for essentially all product For a manufacturer to simply state for the application of the seismic certificate.
lines can be found at our Web site: “Seismic Certified” or “Seismic
http://www.eaton.com/seismic. Qualified” does not tell the designer Furthermore, if conduits are to be 6
if the equipment is appropriate for installed overhead into the equipment,
Electrical designers must work closely the intended installation. does the design call for flexible conduits
with the structural or civil engineers of sufficient length to allow for the 7
for a seismic qualified installation. Note: Eaton recommends that designers conflicting motion of the equipment
confirm with the manufacturer if the and the structure during a seismic event
seismic certification supplied with the
Consideration must be given to the
equipment is based on:
so as to not damage the conductors 8
type of material providing anchorage contained therein, and the terminations
for the electrical equipment. points within the equipment.
1. ACTUAL shaker table test as
required by the IBC and CBC. 9
Structure Attached Equipment
2. The seismic certificate and test The designer must work closely
data clearly state if the equipment with the structural engineer if the 10
was tested as free-standing— equipment is to be attached to the
anchored at the bottom of the structure to ascertain that the internal
equipment to the shaker table. wall re-enforcement of the structure, 11
type of anchor, and depth of embed-
3. Structure attached, that is, ment is sufficient to secure the
anchored at the center of gravity equipment so that the equipment, 12
(C.G.) or at the TOP of the equip- conduits and structure move at or
ment to a simulated wall on the near the same frequency.
shaker table. 13
14
15
16
17
18
19
20
21
ii
10
11
12
13
14
15
16
17
18
19
20
21