You are on page 1of 120

Power Distribution Systems 1.

0-1
August 2013
Sheet 01 001

Power Distribution
Systems
Contents i
Power Distribution Systems Suggested Ground
System Design Fault Settings . . . . . . . . . . . . . 1.4-6 ii
Basic Principles. . . . . . . . . . . 1.1-1 Grounding/Ground Fault Protection
Modern Electric Power Grounding—Equipment,
Technologies . . . . . . . . . . . 1.1-1 System, MV System, 1
Goals of System Design . . . 1.1-2 LV System . . . . . . . . . . . . . . 1.4-9
Voltage Classifications; BILs— Ground Fault Protection . . . . 1.4-11
Basic Impulse Levels . . . . . 1.1-4 Lightning and Surge 2
Three-Phase Transformer Protection . . . . . . . . . . . . . . 1.4-14
Winding Connections . . . . 1.1-5 Grounding Electrodes. . . . . . 1.4-14
Types of Systems—Radial, MV Equipment Surge 3
Loop, Selective, Two-Source, Protection Considerations . 1.4-14
Sparing Transformer, Spot Surge Protection . . . . . . . . . . 1.4-14
Network, Distribution . . . . 1.1-6 Types of Surge
4
Health Care Facility Protection Devices . . . . . . . 1.4-15
Design Considerations . . . 1.1-14 Power Quality 5
Generator Systems . . . . . . 1.1-17 Terms, Technical Overview . . 1.4-18
Generator System Design SPD. . . . . . . . . . . . . . . . . . . . . 1.4-19
Types of Generators . . . . . . . 1.2-1 Harmonics and 6
Generator Systems . . . . . . . 1.2-2 Nonlinear Loads . . . . . . . . . 1.4-21
Generator Grounding. . . . . . 1.2-3 UPS . . . . . . . . . . . . . . . . . . . . 1.4-25
Generator Controls. . . . . . . . 1.2-4 Other Application Considerations
7
Generator Short-Circuit Secondary Voltage . . . . . . . . 1.4-31
Characteristics . . . . . . . . . . 1.2-4
Generator Protection . . . . . . 1.2-5
Energy Conservation . . . . . . 1.4-32 8
Building Control Systems . . 1.4-33
System Analysis Distributed Energy
Systems Analysis . . . . . . . . . 1.3-1 Resources . . . . . . . . . . . . . . 1.4-33 9
Short-Circuit Currents . . . . . 1.3-2 Cogeneration. . . . . . . . . . . . . 1.4-33
Fault Current Waveform PV System Design
Relationships . . . . . . . . . . . 1.3-3 Considerations . . . . . . . . . . 1.4-34 10
Fault Current Calculations Emergency Power. . . . . . . . . 1.4-35
and Methods Index . . . . . . 1.3-4 Peak Shaving. . . . . . . . . . . . . 1.4-36
Determine X and R from 11
Sound Levels. . . . . . . . . . . . . 1.4-36
Transformer Loss Data . . . 1.3-19
Reference Data
Voltage Drop
Considerations . . . . . . . . . . 1.3-20
IEEE Protective Relay 12
Numbers . . . . . . . . . . . . . . . 1.5-1
System Application Considerations
Codes and Standards . . . . . . 1.5-6
Capacitors and
Motor Protective 13
Power Factor . . . . . . . . . . . 1.4-1
Device Data . . . . . . . . . . . . . 1.5-7
Overcurrent Protection Chart of Short-Circuit
and Coordination . . . . . . . . 1.4-3 Currents for Transformers . . 1.5-9 14
Protection of Conductors . . . 1.4-5 Transformer Full Load
Circuit Breaker Cable Amperes . . . . . . . . . . . . . . . 1.5-10
Temperature Ratings . . . . . 1.4-5 Impedances Data . . . . . . . . . 1.5-11
15
Zone Selective Interlocking . 1.4-5 Transformer Losses,
Ground Fault Protection . . . 1.4-6 TP-1 Losses . . . . . . . . . . . . . 1.5-12 16
Power Equipment Losses . . . 1.5-13
NEMA Enclosure Definitions . . 1.5-13
Cable R, X, Z Data . . . . . . . . . 1.5-14 17
Conductor Ampacities . . . . . 1.5-16
Conductor Temperature
Ratings . . . . . . . . . . . . . . . . 1.5-16
18
Formulas and Terms . . . . . . . 1.5-19
Seismic Requirements . . . . . 1.5-20 19

20
Designing a Distribution System
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.0-2 Power Distribution Systems
August 2013
Sheet 01 002

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-1
August 2013 System Design
Sheet 01 003

Basic Principles The basic principles or factors requir- Modern Electric Power i
ing consideration during design of
The best distribution system is one the power distribution system include: Technologies
that will, cost-effectively and safely,
■ Functions of structure, present Several new factors to consider in ii
supply adequate electric service to
and future modern power distribution systems
both present and future probable
■ Life and flexibility of structure result from two relatively recent
loads—this section is included to aid
in selecting, designing and installing ■ Locations of service entrance and
changes. The first recent change is 1
utility deregulation. The traditional
such a system. distribution equipment, locations
dependence on the utility for problem
and characteristics of loads,
The function of the electric power locations of unit substations
analysis, energy conservation mea- 2
distribution system in a building or surements and techniques, and a
■ Demand and diversity factors simplified cost structure for electricity
an installation site is to receive power
of loads
at one or more supply points and
■ Sources of power; including
has changed. The second change is less 3
to deliver it to the individual lamps, obvious to the designer yet will have
motors and all other electrically normal, standby and emergency an impact on the types of equipment
operated devices. The importance (see Tab 40) and systems being designed. It is the 4
of the distribution system to the ■ Continuity and quality of diminishing quantity of qualified build-
function of a building makes it almost power available and required ing electrical operators, maintenance
imperative that the best system be (see Tab 33) departments and facility engineers. 5
designed and installed. ■ Energy efficiency and management Modern electric power technologies
In order to design the best distribution ■ Distribution and utilization voltages may be of use to the designer and
system, the system design engineer ■ Bus and/or cable feeders building owner in addressing these
6
must have information concerning the ■ Distribution equipment and new challenges. The advent of micro-
loads and a knowledge of the various processor devices (smart devices)
types of distribution systems that are
motor control
into power distribution equipment has
7
■ Power and lighting panelboards
applicable. The various categories of expanded facility owners’ options and
and motor control centers
buildings have many specific design capabilities, allowing for automated
challenges, but certain basic principles ■ Types of lighting systems communication of vital power system
8
are common to all. Such principles, ■ Installation methods information (both energy data and
system operation information) and
if followed, will provide a soundly ■ Power monitoring systems
electrical equipment control.
9
executed design. ■ Electric utility requirements
These technologies may be grouped as:
10
■ Power monitoring and control
■ Building management systems
interfaces 11
■ Lighting control
■ Automated energy management
12
■ Predictive diagnostics
Various sections of this guide cover
the application and selection of such 13
systems and components that may be
incorporated into the power equip-
ment being designed. See Tabs 2, 3, 4, 14
23 and 41.
15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-2 Power Distribution Systems
System Design August 2013
Sheet 01 004

i Goals of System Design 2. Minimum Initial Investment: 4. Maximum Flexibility and


The owner’s overall budget for Expendability: In many industrial
When considering the design of an first cost purchase and installa- manufacturing plants, electrical
electrical distribution system for tion of the electrical distribution utilization loads are periodically
ii a given customer and facility, the system and electrical utilization relocated or changed requiring
electrical engineer must consider equipment will be a key factor changes in the electrical distribu-
alternate design approaches that in determining which of various tion system. Consideration of
1 best fit the following overall goals. alternate system designs are to be the layout and design of the
selected. When trying to minimize electrical distribution system to
1. Safety: The No. 1 goal is to design initial investment for electrical accommodate these changes
2 a power system that will not equipment, consideration should must be considered. For example,
present any electrical hazard to be given to the cost of installation, providing many smaller trans-
the people who use the facility, floor space requirements and formers or loadcenters associated
3 and/or the utilization equipment possible extra cooling require- with a given area or specific
fed from the electrical system. ments as well as the initial groups of machinery may lend
It is also important to design a purchase price. more flexibility for future changes
4 system that is inherently safe for than one large transformer; the
the people who are responsible 3. Maximum Service Continuity: use of plug-in busways to feed
for electrical equipment The degree of service continuity selected equipment in lieu of
5 maintenance and upkeep. and reliability needed will vary conduit and wire may facilitate
depending on the type and use future revised equipment layouts.
The National Electrical Code® of the facility as well as the loads
6 (NEC®), NFPA® 70 and NFPA 70E, or processes being supplied by In addition, consideration must be
as well as local electrical codes, the electrical distribution system. given to future building expansion,
provide minimum standards and For example, for a smaller and/or increased load require-
7 requirements in the area of wiring commercial office building, a ments due to added utilization
design and protection, wiring power outage of considerable equipment when designing the
methods and materials, as well time, say several hours, may be electrical distribution system.
8 as equipment for general use with
the overall goal of providing safe
acceptable, whereas in a larger In many cases considering trans-
commercial building or industrial formers with increased capacity
electrical distribution systems plant only a few minutes may be or fan cooling to serve unexpected
9 and equipment. acceptable. In other facilities such loads as well as including spare
The NEC also covers minimum as hospitals, many critical loads additional protective devices and/
requirements for special permit a maximum of 10 seconds or provision for future addition of
10 occupancies including hazardous outage and certain loads, such these devices may be desirable.
locations and special use type as real-time computers, cannot Also to be considered is increasing
facilities such as health care tolerate a loss of power for even appropriate circuit capacities or
11 facilities, places of assembly, a few cycles. quantities for future growth.
theaters and the like, and the Typically, service continuity and Power monitoring communication
equipment and systems located in
12 these facilities. Special equipment
reliability can be increased by: systems connected to electronic
metering can provide the trending
and special conditions such as A. Supplying multiple utility power and historical data necessary for
emergency systems, standby sources or services.
13 systems and communication
future capacity growth.
B. Supplying multiple connection
systems are also covered in
paths to the loads served.
the code.
14 C. Using short-time rated power
It is the responsibility of the design
circuit breakers.
engineer to be familiar with the
15 NFPA and NEC code requirements D. Providing alternate customer-
as well as the customer’s facility, owned power sources such as
process and operating procedures; generators or batteries supplying
16 to design a system that protects uninterruptable power supplies.
personnel from live electrical
conductors and uses adequate E. Selecting the highest quality elec-
17 circuit protective devices that will trical equipment and conductors.
selectively isolate overloaded or F. Using the best installation methods.
faulted circuits or equipment as
18 quickly as possible. G. Designing appropriate system
alarms, monitoring and diagnostics.
19 H. Selecting preventative mainte-
nance systems or equipment to
alarm before an outage occurs.
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-3
August 2013 System Design
Sheet 01 005

5. Maximum Electrical Efficiency 7. Maximum Power Quality: Summary


(Minimum Operating Costs): The power input requirements
It is to be expected that the engineer
i
Electrical efficiency can generally of all utilization equipment has
be maximized by designing to be considered including the will never have complete load infor-
systems that minimize the losses acceptable operating range of mation available when the system is ii
in conductors, transformers and the equipment and the electrical designed. The engineer will have to
utilization equipment. Proper distribution system has to be expand the information made avail-
voltage level selection plays a designed to meet these needs. able to him on the basis of experience 1
key factor in this area and will For example, what is the required with similar problems. Of course, it
be discussed later. Selecting input voltage, current, power is desirable that the engineer has as
equipment, such as transformers, factor requirement? Consider- much definite information as possible 2
with lower operating losses, ation to whether the loads are concerning the function, requirements,
generally means higher first cost affected by harmonics (multiples and characteristics of the utilization
and increased floor space require- of the basic 60 Hz sine wave) or devices. The engineer should know 3
ments; thus, there is a balance generate harmonics must be taken whether certain loads function
to be considered between the into account as well as transient separately or together as a unit, the
owner’s utility energy change voltage phenomena. magnitude of the demand of the loads 4
for the losses in the transformer viewed separately and as units, the rated
or other equipment versus the The above goals are interrelated voltage and frequency of the devices,
owner’s first cost budget and and in some ways contradictory. their physical location with respect 5
cost of money. As more redundancy is added to to each other and with respect to the
the electrical system design along source and the probability and possi-
6. Minimum Maintenance Cost: with the best quality equipment bility of the relocation of load devices 6
Usually the simpler the electrical to maximize service continuity, and addition of loads in the future.
system design and the simpler flexibility and expandability, and
Coupled with this information, a
the electrical equipment, the less power quality, the more initial
knowledge of the major types of electric
7
the associated maintenance costs investment and maintenance
and operator errors. As electrical are increased. Thus, the designer power distribution systems equips the
engineers to arrive at the best system
systems and equipment become must weigh each factor based
design for the particular building.
8
more complicated to provide on the type of facility, the loads
greater service continuity or to be served, the owner’s past It is beyond the scope of this guide to
flexibility, the maintenance costs experience and criteria. present a detailed discussion of loads 9
and chance for operator error that might be found in each of several
increases. The systems should be types of buildings. Assuming that the
designed with an alternate power design engineer has assembled the 10
circuit to take electrical equipment necessary load data, the following
(requiring periodic maintenance) pages discuss some of the various
out of service without dropping types of electrical distribution systems 11
essential loads. Use of drawout that can be used. The description of
type protective devices such as types of systems, and the diagrams
breakers and combination starters used to explain the types of systems 12
can also minimize maintenance on the following pages omits the
cost and out-of-service time. location of utility revenue metering
equipment for clarity. A discussion of 13
short-circuit calculations, coordination,
voltage selection, voltage drop, ground
fault protection, motor protection and 14
other specific equipment protection
is also presented.
15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-4 Power Distribution Systems
System Design August 2013
Sheet 01 006

i Voltage Classifications Table 1.1-2. Metal-Clad Switchgear Voltage


and Insulation Levels (From ANSI/IEEE
Table 1.1-5. Dry-Type Transformers Voltage
and Basic Lightning Impulse Insulation
ANSI and IEEE® standards define C37.20.2-1999) Levels (BIL)—From ANSI/IEEE C57.12.01-1998)
various voltage classifications for Rated Maximum Impulse Nominal BIL (kV Crest) 
ii single-phase and three-phase systems. Voltage (kV rms) Withstand (kV) System
The terminology used divides voltage Voltage
4.76 60 (kV rms)
classes into: 8.25 95
1 15.0 95 1.2 — 10 20 30
■ Low voltage 2.5 — 20 30 45
27.0 125
■ Medium voltage 38.0 150 5.0 — 30 45 60
2 ■ High voltage 8.7 — 45 60 95
Table 1.1-3. Metal-Enclosed Switchgear 15.0 — 60 95 110
■ Extra-high voltage 25.0 95  110 125 150
Voltage and Insulation Levels
3 ■ Ultra-high voltage
(From ANSI C37.20.3-1987)
34.5 — 125  150 200
 BIL values in bold typeface are listed as
Table 1.1-1 presents the nominal sys- Rated Maximum Impulse standard. Others listed are in common use.
tem voltages for these classifications. Voltage (kV rms) Withstand (kV)
4 Optional higher levels used where exposure
to overvoltage occurs and higher protection
Table 1.1-1. Standard Nominal System 4.76 60
margins are required.
Voltages and Voltage Ranges 8.25 75  Lower levels where surge arrester
5 (From IEEE Standard 141-1993) 15.0 95
protective devices can be applied with
Voltage Nominal System Voltage 15.5 110 lower spark-over levels.
Class 25.8 125
Three-Wire Four-Wire
6 38.0 150
Voltage Recommendations by
Low 240/120 208Y/120
voltage 240 240/120 Table 1.1-4. Liquid-Immersed Motor Horsepower
Transformers Voltage and Basic
7 480
600 —
480Y/277
Lightning Impulse Insulation Levels (BIL)
Some factors affecting the selection
of motor operating voltage include:
Medium 2400 4160Y/2400 (From ANSI/IEEE C57.12.00-2000)
■ Motor, motor starter and cable
8 voltage 4160
4800
8320Y/4800
12000Y/6930
Applica-
tion
Nominal BIL
System (kV Crest)  first cost
6900 12470Y/7200 Voltage
13,200 13200Y/7620
■ Motor, motor starter and cable
(kV rms)
9 13,800 13800Y/7970 installation cost
23,000 20780Y/12000 Distribu- 1.2 30 — — — ■ Motor and cable losses
34,500 22860Y/13200 tion 2.5 45 — — —
46,000 24940Y/14400 5.0 60 — — — ■ Motor availability
10 69,000 34500Y/19920 8.7 75 — — — ■ Voltage drop
High 115,000 — 15.0 95 — — — ■ Qualifications of the building
voltage 138,000 — 25.0 150 125 — — operating staff; and many more
11 161,000 — 34.5 200 150 125 —
230,000 — 46.0 250 200 — — The following table is based in part
Extra-high 345,000 — 69.0 350 250 — — on the above factors and experience.
12 voltage 500,000 — Power 1.2 45 30 — — Because all the factors affecting the
765,000 — 2.5 60 45 — — selection are rarely known, it is only
Ultra-high 1,100,000 — 5.0 75 60 — — an approximate guideline.
13 voltage 8.7 95 75 — —
15.0 110 95 — — Table 1.1-6. Selection of Motor Horsepower
BIL—Basic Impulse Levels 25.0 150 — — — Ratings as a Function of System Voltage
14 ANSI standards define recommended 34.5 200 — — — Motor Voltage Motor System
46.0 250 200 — — (Volts) hp Range Voltage
and required BIL levels for: 69.0 350 250 — —
15 ■ Metal-clad switchgear 115.0 550 450 350 —
460
2300
up to 500
250 to 2000
480
2400
(typically vacuum breakers) 138.0 650 550 450 —
4000 250 to 3000 4160
161.0 750 650 550 —
■ Metal-enclosed switchgear (typically 4600 250 to 3000 4800
16 load interrupters, switches)
230.0 900 825 750 650
13,200 above 2000 13,800
345.0 1175 1050 900 —
■ Liquid immersed transformers 500.0 1675 1550 1425 1300
765.0 2050 1925 1800 —
17 ■ Dry-type transformers
 BIL values in bold typeface are listed as
Table 1.1-2 through Table 1.1-5 contain standard. Others listed are in common use.
those values.
18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-5
August 2013 System Design
Sheet 01 007

Table 1.1-7. Three-Phase Transformer Winding Connections


Phasor Notes i
Diagram

DELTA-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources. ii
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor H2 X2
Diagram:
1

H1 H3 X1 X3 2
Angular Displacement (Degrees): 0

DELTA-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources. 3
2. Suitable for a three-wire service or a four-wire grounded service with
Phasor H2 X2 XO grounded.
Diagram:
3. With XO grounded, the transformer acts as a ground source for the 4
secondary system.
X1 X0
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
lines supplied by the transformer do not flow in the primary lines. Instead the 5
H1 H3 X3 zero sequence currents circulate in the closed delta primary windings.
5. When supplied from an effectively grounded primary system does not see load
Angular Displacement (Degrees): 30 unbalances and ground faults in the secondary system. 6
WYE-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire delta service with a mid-tap ground.
Phasor
Diagram:
H2 X2 3. Grounding the primary neutral of this connection would create a ground source 7
for the primary system. This could subject the transformer to severe overloading
during a primary system disturbance or load unbalance.
X1
4. Frequently installed with mid-tap ground on one leg when supplying 8
combination three-phase and single-phase load where the three-phase
H1 H3 load is much larger than single-phase load.
X3
Angular Displacement (Degrees): 30
5. When used in 25 kV and 35 kV three-phase four-wire primary systems,
ferroresonance can occur when energizing or de-energizing the transformer
9
using single-pole switches located at the primary terminals. With smaller kVA
transformers the probability of ferroresonance is higher.
WYE-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
10
2. Suitable for a three-wire service only, even if XO is grounded.
Phasor H2 X2 3. This connection is incapable of furnishing a stabilized neutral and its use may
Diagram:
result in phase-to-neutral overvoltage (neutral shift) as a result of unbalanced 11
phase-to-neutral load.
X0 4. If a three-phase unit is built on a three-legged core, the neutral point of the
primary windings is practically locked at ground potential. 12
H1 H3 X1 X3

Angular Displacement (Degrees): 0


13
GROUNDED WYE-WYE Connection 1. Suitable for four-wire effectively grounded source only.
2. Suitable for a three-wire service or for four-wire grounded service with
Phasor
Diagram:
H2 X2 XO grounded. 14
3. Three-phase transformers with this connection may experience stray flux tank
heating during certain external system unbalances unless the core configuration
H0 X0 (four or five legged) used provides a return path for the flux.
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
15
H1 H3 X1 X3 lines supplied by the transformer also flow in the primary lines (and primary
neutral conductor).
Angular Displacement (Degrees): 0 5. Ground relay for the primary system may see load unbalances and ground
16
faults in the secondary system. This must be considered when coordinating
overcurrent protective devices.
6. Three-phase transformers with the neutral points of the high voltage and low 17
voltage windings connected together internally and brought out through an
HOXO bushing should not be operated with the HOXO bushing ungrounded
(floating). To do so can result in very high voltages in the secondary systems. 18
DELTA-DELTA Connection with Tap 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor
Diagram:
H2 X2 3. When using the tap for single-phase circuits, the single-phase load kVA should 19
X4 not exceed 5% of the three-phase kVA rating of the transformer. The three-phase
rating of the transformer is also substantially reduced.
20
H1 H3 X1 X3

Angular Displacement (Degrees): 0 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-6 Power Distribution Systems
System Design August 2013
Sheet 01 008

i Types of Systems Low voltage feeder circuits run from A fault on the secondary low voltage
the switchgear or switchboard assem- bus or in the source transformer will
In many cases, power is supplied by blies to panelboards that are located interrupt service to all loads. Service
the utility to a building at the utilization closer to their respective loads as cannot be restored until the necessary
ii voltage. In these cases, the distribution shown in Figure 1.1-1. repairs have been made. A low voltage
of power within the building is achieved feeder circuit fault will interrupt service
Each feeder is connected to the switch- to all loads supplied over that feeder.
through the use of a simple radial
1 distribution system.
gear or switchboard bus through a
circuit breaker or other overcurrent A modern and improved form of the
In cases where the utility service voltage protective device. A relatively small conventional simple radial system
2 is at some voltage higher than the number of circuits are used to distribute distributes power at a primary voltage.
utilization voltage within the building, power to the loads from the switch- The voltage is stepped down to
the system design engineer has a choice gear or switchboard assemblies and utilization level in the several load
3 of a number of types of systems that panelboards. areas within the building typically
may be used. This discussion covers through secondary unit substation
Because the entire load is served from transformers. The transformers are
several major types of distribution
a single source, full advantage can be
4 systems and practical modifications
taken of the diversity among the loads.
usually connected to their associated
of them. load bus through a circuit breaker, as
This makes it possible to minimize the shown in Figure 1.1-2. Each secondary
1. Simple radial installed transformer capacity. However,
5 the voltage regulation and efficiency
unit substation is an assembled unit
2. Loop-primary system— consisting of a three-phase, liquid-
of this system may be poor because filled or air-cooled transformer, an
radial secondary system of the low voltage feeders and single
6 3. Primary selective system— source. The cost of the low voltage-
integrally connected primary fused
switch, and low voltage switchgear or
secondary radial system feeder circuits and their associated circuit switchboard with circuit breakers or
breakers are high when the feeders are
7 4. Two-source primary— long and the peak demand is above
fused switches. Circuits are run to
secondary selective system the loads from these low voltage
1000 kVA. protective devices.
8 5. Sparing transformer system
6. Simple spot network
Primary Fused Switch
9 7. Medium voltage distribution
system design Transformer

10 1. Simple Radial System 600V Class


The conventional simple radial system Switchboard
receives power at the utility supply
11 voltage at a single substation and steps
the voltage down to the utilization level. Distribution
In those cases where the customer Dry-Type
12 receives his supply from the primary Transformer
system and owns the primary switch Distribution MCC Distribution Lighting
and transformer along with the second- Panel Panel Panelboard
13 ary low voltage switchboard or switch-
gear, the equipment may take the form
of a separate primary switch, separate
14 transformer, and separate low voltage
Figure 1.1-1. Simple Radial System
switchgear or switchboard. This equip-
ment may be combined in the form of
15 an outdoor pad-mounted transformer 52 Primary Main Breaker
with internal primary fused switch
and secondary main breaker feeding
16 an indoor switchboard. 52 52 52 52 52 52 Primary Feeder Breakers
Another alternative would be a
17 secondary unit substation where
the primary fused switch, transformer
and secondary switchgear or switch-
18 board are designed and installed as
a close-coupled single assembly.

19 In those cases where the utility owns


the primary equipment and transformer,
Secondary Unit
the supply to the customer is at the Substation
Primary
20 utilization voltage, and the service
Cables
equipment then becomes low voltage
main distribution switchgear or
21 a switchboard.
Figure 1.1-2. Primary and Secondary Simple Radial System

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-7
August 2013 System Design
Sheet 01 009

Because each transformer is located In addition, if only one primary fuse on break switches with load side bus
within a specific load area, it must a circuit opens, the secondary loads are connection) sectionalizing switches i
have sufficient capacity to carry the then single phased, causing damage to and primary load break fused switch
peak load of that area. Consequently, low voltage motors. as shown in Figure 1.1-4.
if any diversity exists among the load ii
area, this modified primary radial Another approach to reducing costs When pad-mounted compartmental-
system requires more transformer is to eliminate the primary feeder ized transformers are used, they are
capacity than the basic form of the breakers completely, and use a single furnished with loop-feed oil-immersed 1
simple radial system. However, primary main breaker or fused switch gang-operated load break sectionalizing
because power is distributed to the for protection of a single primary switches and drawout current limiting
load areas at a primary voltage, losses feeder circuit with all secondary unit fuses in dry wells as shown in Figure 2
are reduced, voltage regulation is substations supplied from this circuit. 1.1-5. By operating the appropriate
improved, feeder circuit costs are Although this system results in less sectionalizing switches, it is possible
reduced substantially, and large initial equipment cost, system reliability to disconnect any section of the loop 3
low voltage feeder circuit breakers is reduced drastically because a single conductors from the rest of the system.
are eliminated. In many cases the fault in any part of the primary conductor In addition, by opening the transformer
interrupting duty imposed on the would cause an outage to all loads primary switch (or removing the load 4
load circuit breakers is reduced. within the facility. break drawout fuses in the pad-mounted
transformer) it is possible to disconnect
This modern form of the simple radial 2. Loop Primary System— any transformer from the loop. 5
system will usually be lower in initial Radial Secondary System
investment than most other types of A key interlocking scheme is normally
This system consists of one or more recommended to prevent closing all
primary distribution systems for build-
“PRIMARY LOOPS” with two or more sectionalizing devices in the loop. Each
6
ings in which the peak load is above
1000 kVA. A fault on a primary feeder transformers connected on the loop. primary loop sectionalizing switch and
the feeder breakers to the loop are
circuit or in one transformer will cause This system is typically most effective
when two services are available from interlocked such that to be closed they
7
an outage to only those secondary
loads served by that feeder or trans- the utility as shown in Figure 1.1-3. Each require a key (which is held captive
until the switch or breaker is opened)
former. In the case of a primary main primary loop is operated such that one
and one less key than the number of
8
bus fault or a utility service outage, of the loop sectionalizing switches is
service is interrupted to all loads until kept open to prevent parallel operation key interlock cylinders is furnished.
the trouble is eliminated. of the sources. When secondary unit An extra key is provided to defeat the 9
substations are used, each trans- interlock under qualified supervision.
Reducing the number of transformers former has its own duplex (2-load
per primary feeder by adding more 10
primary feeder circuits will improve
the flexibility and service continuity
of this system; the ultimate being one 11
Primary Main Breaker 1 52 52 Primary Main Breaker 2
secondary unit substation per primary
feeder circuit. This of course increases 52
the investment in the system but Tie 12
minimizes the extent of an outage 52 52 Breaker 52 52 Loop Feeder Breaker
resulting from a transformer or
primary feeder fault. Loop A
Loop B
13
Primary connections from one secondary
unit substation to the next secondary
unit substation can be made with
NC NO NC NC
Fault Sensors
14
“double” lugs on the unit substation
primary switch as shown, or with
separable connectors made in 15
manholes or other locations.
Depending on the load kVA connected 16
to each primary circuit and if no ground
fault protection is desired for either the
primary feeder conductors and trans- NC NC NO NC NC NC 17
formers connected to that feeder or
the main bus, the primary main and/or
feeder breakers may be changed to 18
primary fused switches. This will sig-
nificantly reduce the first cost, but also
decrease the level of conductor and 19
equipment protection. Thus, should
a fault or overload condition occur,
downtime increases significantly and Secondary Unit Substations Consisting of:
20
higher costs associated with increased Duplex Primary Switches/Fused Primary Switches/
Transformer and Secondary Main Feeder Breakers
damage levels and the need for fuse
replacement is typically encountered. 21
Figure 1.1-3. Loop Primary—Radial Secondary System

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-8 Power Distribution Systems
System Design August 2013
Sheet 01 010

When a primary feeder conductor fault


i Loop
Feeder
Loop
Feeder occurs, the associated loop feeder
breaker opens and interrupts service
Load Break to all loads up to the normally open 52
ii Loop Switches
primary loop load break switch
(typically half of the loads). Once it is Loop A Loop A
determined which section of primary
1 cable has been faulted, the loop sec-
tionalizing switches on each side of In cases where only one primary line
Fused is available, the use of a single primary
Disconnect the faulted conductor can be opened, breaker provides the loop connections
2 Switch the loop sectionalizing switch that had to the loads as shown here.
been previously left open then closed
and service restored to all secondary Figure 1.1-6. Single Primary Feeder—
3 unit substations while the faulted Loop System
conductor is replaced. If the fault
should occur in a conductor directly A basic primary loop system that
4 on the load side of one of the loop uses a single primary feeder breaker
feeder breakers, the loop feeder connected directly to two loop feeder
breaker is kept open after tripping and switches which in turn then feed the
Figure 1.1-4. Secondary Unit Substation
5 Loop Switching the next load side loop sectionalizing loop is shown in Figure 1.1-6. In this
switch manually opened so that the basic system, the loop may be normally
faulted conductor can be sectionalized operated with one of the loop section-
6 Loop
Feeder
Loop
Feeder and replaced. alizing switches open as described
above or with all loop sectionalizing
Load Break Note: Under this condition, all secondary switches closed. If a fault occurs in the
7 Loop Switches unit substations are supplied through the
other loop feeder circuit breaker, and thus
basic primary loop system, the single
loop feeder breaker trips, and secondary
all conductors around the loop should be
loads are lost until the faulted conductor
sized to carry the entire load connected to
8 the loop. Increasing the number of primary is found and eliminated from the loop
loops (two loops shown in Figure 1.1-6) by opening the appropriate loop
Load Break will reduce the extent of the outage from a sectionalizing switches and then
Drawout Fuses
9 conductor fault, but will also increase the reclosing the breaker.
system investment.
3. Primary Selective System—
10 When a transformer fault or overload
Secondary Radial System
occurs, the transformer primary fuses
open, and the transformer primary The primary selective—secondary
11 switch manually opened, disconnecting radial system, as shown in Figure 1.1-7,
the transformer from the loop, and differs from those previously described
leaving all other secondary unit in that it employs at least two primary
12 Figure 1.1-5. Pad-Mounted Transformer substation loads unaffected. feeder circuits in each load area. It is
Loop Switching
In addition, the two primary main
13 breakers, which are normally closed,
Primary Metal-Clad

Switchgear Lineup
and primary tie breaker, which is 52 52 Primary Main Breaker
normally open, are either mechanically
14 or electrically interlocked to prevent Bus A 52 Bus B
paralleling the incoming source lines.
For slightly added cost, an automatic 52 52 52 52 Primary Feeder Breaker
15 throw-over scheme can be added
between the two main breakers and Feeder A1 Feeder B1 Feeder B2
tie breaker. During the more common To Other
16 event of a utility outage, the automatic
Feeder A2 Substations

transfer scheme provides significantly NO

17 reduced power outage time.


The system in Figure 1.1-3 has higher NC
costs than in Figure 1.1-2, but offers
18 increased reliability and quick restora- NO Typical Secondary Unit
tion of service when 1) a utility outage Substation Duplex Primary
Switch/Fuses
occurs, 2) a primary feeder conductor Transformer/600V Class
19 fault occurs, or 3) a transformer fault
NC
Secondary Switchgear
or overload occurs.
NO
20 Should a utility outage occur on one of
the incoming lines, the associated pri- NC
mary main breaker is opened and the
21 tie breaker closed either manually or
through an automatic transfer scheme. Figure 1.1-7. Basic Primary Selective—Radial Secondary System

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-9
August 2013 System Design
Sheet 01 011

designed so that when one primary or most of the loads, may more than
circuit is out of service, the remaining Primary offset the greater cost. Having two i
feeder or feeders have sufficient Feeders sources allows for either manual or
capacity to carry the total load. Half automatic transfer of the two primary
of the transformers are normally Non-Load Break main breakers and tie breaker should ii
connected to each of the two feeders. Selector Switches one of the sources become unavailable.
When a fault occurs on one of the Inter-
primary feeders, only half of the
lock Load Break
Disconnect
The primary selective-secondary radial 1
load in the building is dropped. system, however, may be less costly or
Fuses
more costly than a primary loop—
Duplex fused switches as shown in secondary radial system of Figure 1.1-3 2
Figure 1.1-7 and detailed in Figure 1.1-8 depending on the physical location
are the normal choice for this type of of the transformers while offering
system. Each duplex fused switch comparable downtime and reliability. 3
consists of two (2) load break three- The cost of conductors for the two
pole switches each in their own types of systems may vary greatly
separate structure, connected together depending on the location of the 4
by bus bars on the load side. Typically, transformers and loads within the
the load break switch closest to the facility and greatly override primary
Figure 1.1-9. Fused Selector Switch in
transformer includes a fuse assembly
One Structure
switching equipment cost differences 5
with fuses. Mechanical and/or key between the two systems.
interlocking is furnished such that This means limited cable space espe-
both switches cannot be closed at cially if double lugs are furnished for 4. Two-Source Primary— 6
the same time (to prevent parallel each line as shown in Figure 1.1-7 and Secondary Selective System
operation) and interlocking such should a faulted primary conductor
that access to either switch or fuse have to be changed, both lines would This system uses the same principle
of duplicate sources from the power
7
assembly cannot be obtained unless have to be de-energized for safe
both switches are opened. changing of the faulted conductors. supply point using two primary main
breakers and a primary tie breaker. 8
In Figure 1.1-7 when a primary feeder The two primary main breakers and
Primary fault occurs, the associated feeder primary tie breaker being either
Feeders breaker opens and the transformers manually or electrically interlocked 9
normally supplied from the faulted to prevent closing all three at the same
Load Break feeder are out of service. Then manu- time and paralleling the sources. Upon
Switches ally, each primary switch connected to loss of voltage on one source, a manual 10
the faulted line must be opened and or automatic transfer to the alternate
then the alternate line primary switch source line may be used to restore
can be closed connecting the trans- power to all primary loads. 11
Fuses former to the live feeder, thus restoring
service to all loads. Note that each of the Each transformer secondary is
arranged in a typical double-ended
primary circuit conductors for Feeder
unit substation arrangement as shown
12
A1 and B1 must be sized to handle the
sum of the loads normally connected in Figure 1.1-10. The two secondary
main breakers and secondary tie
to both A1 and B1. Similar sizing of
breaker of each unit substation are
13
Feeders A2 and B2, etc., is required.
again either mechanically or electrically
If a fault occurs in one transformer, interlocked to prevent parallel operation.
the associated primary fuses blow Upon loss of secondary source voltage
14
Figure 1.1-8. Duplex Fused Switch in
Two Structures and interrupt the service to just on one side, manual or automatic
the load served by that transformer. transfer may be used to transfer the
As an alternate to the duplex switch Service cannot be restored to the loads to the other side, thus restoring
15
arrangement, a non-load break selector loads normally served by the faulted power to all secondary loads.
switch mechanically interlocked with a transformer until the transformer 16
load break fused switch can be used as is repaired or replaced. This arrangement permits quick
shown in Figure 1.1-9. The non-load restoration of service to all loads when
break selector switch is physically Cost of the primary selective— a primary feeder or transformer fault
located in the rear of the load break secondary radial system is greater occurs by opening the associated 17
fused switch, thus only requiring one than that of the simple primary radial secondary main and closing the
structure and a lower cost and floor system of Figure 1.1-1 because of the secondary tie breaker. If the loss of
space savings over the duplex additional primary main breakers, tie secondary voltage has occurred 18
arrangement. The non-load break breaker, two-sources, increased number because of a primary feeder fault
switch is mechanically interlocked to of feeder breakers, the use of primary- with the associated primary feeder
prevent its operation unless the load duplex or selector switches, and the breaker opening, then all secondary 19
break switch is opened. The main greater amount of primary feeder loads normally served by the faulted
cable required. The benefits from the feeder would have to be transferred
disadvantage of the selector switch is
that conductors from both circuits are reduction in the amount of load lost to the opposite primary feeder. This 20
terminated in the same structure. when a primary feeder is faulted, plus means each primary feeder conductor
the quick restoration of service to all must be sized to carry the load on both
sides of all the secondary buses it is 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-10 Power Distribution Systems
System Design August 2013
Sheet 01 012

serving under secondary emergency emergency conditions, the in-service transformers are furnished with
i transfer. If the loss of voltage was due transformer of a double-ended unit fan-cooling and/or lower than normal
to a failure of one of the transformers in substation would have to have the temperature rise such that under
the double-ended unit substation, then capability of serving the loads on emergency conditions they can carry
ii the associated primary fuses would both sides of the tie breaker. For this on a continuous basis the maximum
open taking only the failed transformer reason, transformers used in this load on both sides of the secondary tie
out of service, and then only the application have equal kVA rating breaker. Because of this spare trans-
1 secondary loads normally served by on each side of the double-ended former capacity, the voltage regulation
the faulted transformer would have unit substation and the normal provided by the double-ended unit
to be transferred to the opposite operating maximum load on each substation system under normal
2 transformer. In either of the above transformer is typically about 2/3 base conditions is better than that of the
nameplate kVA rating. Typically these systems previously discussed.

3 The double-ended unit substation


arrangement can be used in conjunction
with any of the previous systems
4 52 52 Primary Main Breakers discussed, which involve two primary
sources. Although not recommended,
52 if allowed by the utility, momentary
5 52 52 52 52 Primary Feeder Breakers
re-transfer of loads to the restored
source may be made closed transition
(anti-parallel interlock schemes would
6 To Other Substations To Other Substations have to be defeated) for either the
primary or secondary systems. Under
Typical this condition, all equipment interrupt-
7 Double-Ended
Unit
ing and momentary ratings should be
suitable for the fault current available
Substation
from both sources.
8 For double-ended unit substations
equipped with ground fault systems
special consideration to transformer
9 neutral grounding and equipment
operation should be made—see
10 “Grounding” and “Ground Fault
Protection” in Section 1.4. Where
Primary Fused Switch Transformer Tie Breaker Secondary Main Breaker two single-ended unit substations are
11 connected together by external tie
Figure 1.1-10. Two-Source Primary—Secondary Selective System conductors, it is recommended that
a tie breaker be furnished at each end
12 of the tie conductors.

5. Sparing Transformer System


13 The sparing transformer system concept
came into use as an alternative to the
K K K
capital cost intensive double-ended
14 secondary unit substation distribution
system (see Two-Source Primary—
Secondary Selective System). It essen-
15 tially replaces double-ended substations
Sparing Transformer with single-ended substations and one
or more “sparing” transformer substa-
16 tions all interconnected on a common
K K secondary bus (see Figure 1.1-11).

17 Generally no more than three to five


single-ended substations are on a
sparing loop.
18 Typical Secondary Busway Loop
The essence of this design philosophy
is that conservatively designed and
loaded transformers are highly reliable
19 electrical devices and rarely fail. There-
K K fore, this design provides a single com-
Typical Single-Ended Substation mon backup transformer for a group of
20 transformers in lieu of a backup trans-
former for each and every transformer.
This system design still maintains a
21 Figure 1.1-11. Sparing Transformer System high degree of continuity of service.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-11
August 2013 System Design
Sheet 01 013

Referring to Figure 1.1-11, it is appar- In facilities without qualified electrical The major advantage of the secondary
ent that the sparing concept backs up power operators, an open transition network system is continuity of i
primary switch and primary cable fail- with key interlocking is often a service. No single fault anywhere
ure as well. Restoration of lost or failed prudent design. on the primary system will interrupt
utility power is accomplished similarly
Note: Each pair of “main breaker/tie breaker”
service to any of the system’s loads. ii
to primary selective scheme previously Most faults will be cleared without
key cylinders should be uniquely keyed to
discussed. It is therefore important to prevent any paralleled source operations. interrupting service to any load.
use an automatic throwover system Another outstanding advantage that 1
in a two source lineup of primary Careful sizing of these transformers the network system offers is its flexi-
switchgear to restore utility power as well as careful specification of the bility to meet changing and growing
as discussed in the “Two-Source transformers is required for reliability. load conditions at minimum cost and 2
Primary” scheme—see Figure 1.1-10. Low temperature rise specified with minimum interruption in service to
continuous overload capacity or other loads on the network. In addition
A major advantage of the sparing
transformer system is the typically upgraded types of transformers to flexibility and service reliability, the 3
should be considered. secondary network system provides
lower total base kVA of transformation.
exceptionally uniform and good
In a double-ended substation design, One disadvantage to this system is 4
voltage regulation, and its high
each transformer must be rated to the external secondary tie system, efficiency materially reduces the
carry the sum of the loads of two busses see Figure 1.1-11. As shown, all single-
and usually requires the addition of costs of system losses.
cooling fans to accomplish this rating.
ended substations are tied together on 5
the secondary with a tie busway or Three major differences between the
In the “sparing” concept, each trans- cable system. Location of substations network system and the simple radial
former carries only its own load, which is therefore limited because of voltage system account for the outstanding 6
is typically not a fan-cooled rating. Major advantages of the network. First,
drop and cost considerations.
space savings is also a benefit of this a network protector is connected in
system in addition to first cost savings. Routing of busway, if used, must be the secondary leads of each network 7
carefully layed out. It should also be transformer in place of, or in addition
The sparing transformer system
noted, that a tie busway or cable fault to, the secondary main breaker, as
operates as follows:
will essentially prevent the use of the shown in Figure 1.1-12. Also, the 8
■ All main breakers, including sparing transformer until it is repaired. secondaries of each transformer in
the sparing main breaker, are Commonly, the single-ended substa- a given location (spot) are connected
normally closed; the tie breakers tions and the sparing transformer together by a switchgear or ring bus 9
are normally open must be clustered. This can also be from which the loads are served over
■ Once a transformer (or primary an advantage, as more kVA can be short radial feeder circuits. Finally, the
cable or primary switch/fuse) fails, supported from a more compact primary supply has sufficient capacity 10
the associated secondary main space layout. to carry the entire building load with-
breaker is opened. The associated out overloading when any one primary
tie breaker is then closed, which 6. Simple Spot Network Systems feeder is out of service. 11
restores power to the single-ended The AC secondary network system A network protector is a specially
substation bus is the system that has been used for designed heavy-duty air power breaker, 12
■ Schemes that require the main to many years to distribute electric power spring close with electrical motor-charged
be opened before the tie is closed in the high-density, downtown areas mechanism, with a network relay to
(“open transition”), and that allow of cities, usually in the form of utility
any tie to be closed before the grids. Modifications of this type of
control the status of the protector
(tripped or closed). The network relay
13
substation main is opened, (“closed system make it applicable to serve is usually a solid-state microprocessor-
transition”) are possible loads within buildings. based component integrated 14
With a closed transition scheme, it is
common to add a timer function that
opens the tie breaker unless either Typical Feeder 15
main breaker is opened within a time Primary Circuit
interval. This closed transition allows To Other
power to be transferred to the sparing Network Transformer
Networks
16
transformer without interruption, such
as for routine maintenance, and then Network Protector
back to the substation. This closed Fuses 17
transition transfer has an advantage in Optional Main, 50/51
some facilities; however, appropriate Relaying and/or
Network Disconnect
interrupting capacities and bus bracing Tie Tie
Drawout
18
must be specified suitable for the Low Voltage
momentary parallel operation. LV Feeder NC NC Switchgear
19
Customer Customer Customer
Loads Loads Loads
20
Figure 1.1-12. Three-Source Spot Network
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-12 Power Distribution Systems
System Design August 2013
Sheet 01 014

into the protector enclosure that with that feeder circuit. This operation They are also economical when
i functions to automatically close the does not interrupt service to any loads. compared to two transformer double-
protector only when the voltage After the necessary repairs have been ended substations with normally
conditions are such that its associated made, the system can be restored to opened tie breakers.
ii transformer will supply power to the normal operating conditions by closing
secondary network loads, and to auto- the primary feeder breaker. All network Emergency power should be connected
matically open the protector when protectors associated with that feeder to network loads downstream from
1 power flows from the secondary to the will close automatically. the network, or upstream at primary
network transformer. The purpose of voltage, not at the network bus itself.
the network protector is to protect the The chief purpose of the network bus
2 integrity of the network bus voltage normally closed ties is to provide for 7. Medium Voltage Distribution
and the loads served from it against the sharing of loads and a balancing System Design
transformer and primary feeder faults of load currents for each primary ser-
3 by quickly disconnecting the defective vice and transformer regardless of A. Single Bus, Figure 1.1-13
feeder-transformer pair from the the condition of the primary services.
The sources (utility and/or generator(s))
network when backfeed occurs. Also, the ties provide a means for are connected to a single bus. All feeders
4 isolating and sectionalizing ground are connected to the same bus.
The simple spot network system
resembles the secondary-selective fault events within the switchgear
network bus, thereby saving a portion
5 radial system in that each load area
of the loads from service interruptions, Utility
is supplied over two or more primary
feeders through two or more trans- yet isolating the faulted portion for
G
corrective action.
6 formers. In network systems, the
transformers are connected through The use of spot network systems
network protectors to a common provides users with several important
7 bus, as shown in Figure 1.1-12, from advantages. First, they save trans-
which loads are served. Because the former capacity. Spot networks permit
transformers are connected in parallel, equal loading of transformers under 52 52
8 a primary feeder or transformer fault all conditions. Also, networks yield
does not cause any service interrup- lower system losses and greatly Main Bus
tion to the loads. The paralleled improve voltage conditions. The
9 transformers supplying each load voltage regulation on a network
bus will normally carry equal load system is such that both lights and
currents, whereas equal loading of power can be fed from the same
10 the two separate transformers supply- load bus. Much larger motors can
52
ing a substation in the secondary- be started across-the-line than on a
selective radial system is difficult to simple radial system. This can result in One of Several Feeders
11 obtain. The interrupting duty imposed simplified motor control and permits
on the outgoing feeder breakers in the the use of relatively large low voltage
network will be greater with the spot Figure 1.1-13. Single Bus
motors with their less expensive
12 network system. control. Finally, network systems This configuration is the simplest
The optimum size and number of provide a greater degree of flexibility system; however, outage of the utility
in adding future loads; they can be results in total outage.
13 primary feeders can be used in the
connected to the closest spot
spot network system because the Normally the generator does not have
loss of any primary feeder and its network bus.
adequate capacity for the entire load.
14 associated transformers does not Spot network systems are economical A properly relayed system equipped
result in the loss of any load even for buildings that have heavy concen- with load shedding, automatic voltage/
for an instant. In spite of the spare trations of loads covering small areas, frequency control may be able to
15 capacity usually supplied in network with considerable distance between maintain partial system operation.
systems, savings in primary switch- areas, and light loads within the
gear and secondary switchgear costs distances separating the concentrated Any future addition of breaker sections
16 often result when compared to a radial loads. They are commonly used in to the bus will require a shutdown of
system design with similar spare hospitals, high rise office buildings, the bus, because there is no tie breaker.
capacity. This occurs in many radial and institutional buildings where a B. Single Bus with Two Sources from the
17 systems because more and smaller high degree of service reliability is Utility, Figure 1.1-14
feeders are often used in order to required from the utility sources.
minimize the extent of any outage Spot network systems are especially Same as the single bus, except that
18 when a primary fault event occurs. economical where three or more two utility sources are available.
primary feeders are available. This system is operated normally with
In spot networks, when a fault occurs the main breaker to one source open.
on a primary feeder or in a transformer, Principally, this is due to supplying
19 the fault is isolated from the system each load bus through three or Upon loss of the normal service, the
more transformers and the reduction transfer to the standby normally
through the automatic tripping of the open (NO) breaker can be automatic
primary feeder circuit breaker and all in spare cable and transformer
20 of the network protectors associated capacity required. or manual. Automatic transfer is
preferred for rapid service restoration
especially in unattended stations.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-13
August 2013 System Design
Sheet 01 015

Again, the closing of the tie breaker can The third tie breaker allows any bus
Utility #1 Utility #2 be manual or automatic. The statements to be fed from any utility source. i
made for the retransfer of scheme B
apply to this scheme also. Caution for Figures 1.1-14, 1.1-15 and
Normal Standby
1.1-16: If continuous paralleling of ii
Utility #1 Utility #2 sources is planned, reverse current,
reverse power and other appropriate
relaying protection should be added. 1
When both sources are paralleled for
any amount of time, the fault current
52 NC 52 NO available on the load side of the main 2
device is the sum of the available
52 NC 52 NC fault current from each source plus
the motor fault contribution. It is 3
Loads required that bus bracing, feeder
NO
Bus #1 Bus #2 breakers and all load side equipment
Figure 1.1-14. Single Bus with Two-Sources
52
is rated for the increased available 4
fault current.
Retransfer to the “Normal” can be
closed transition subject to the approval 52 52
Summary
5
of the utility. Closed transition momen-
tarily (5–10 cycles) parallels both The medium voltage system configura-
utility sources. Caution: when both Load Load
tions shown are based on using metal- 6
sources are paralleled, the fault current clad drawout switchgear. The service
available on the load side of the main Figure 1.1-15. Two-Source Utility with continuity required from electrical
device is the sum of the available fault Tie Breaker systems makes the use of single-source 7
current from each source plus the motor systems impractical.
fault contribution. It is recommended If looped or primary selective distribu-
tion system for the loads is used, the In the design of a modern medium 8
that the short-circuit ratings of the voltage system, the engineer should:
bus, feeder breakers and all load side buses can be extended without a shut-
equipment are rated for the increased down by closing the tie breaker and 1. Design a system as simple as
available fault current. If the utility transferring the loads to the other bus. possible. 9
requires open transfer, the disconnec- This configuration is more expensive
tion of motors from the bus must be 2. Limit an outage to as small a
than B. The system is not limited to two portion of the system as possible. 10
ensured by means of suitable time delay buses only. Another advantage is that
on reclosing as well as supervision the design may incorporate momentary 3. Provide means for expanding the
of the bus voltage and its phase with paralleling of buses on retransfer after system without major shutdowns.
respect to the incoming source voltage. the failed line has been restored to pre-
11
vent another outage. See the Caution 4. Relay the system so that only the
This busing scheme does not preclude faulted part is removed from
the use of cogeneration, but requires for Figures 1.1-14, 1.1-15 and 1.1-16. 12
service, and damage to it is mini-
the use of sophisticated automatic syn- In Figure 1.1-16, closing of the tie mized consistent with selectivity.
chronizing and synchronism checking breaker following the opening of a
controls, in addition to the previously main breaker can be manual or auto- 5. Specify and apply all equipment 13
mentioned load shedding, automatic matic. However, because a bus can within its published ratings and
frequency and voltage controls. be fed through two tie breakers, the national standards pertaining to
This configuration is more expensive control scheme should be designed the equipment and its installation. 14
than the scheme shown in Figure 1.1-13, to make the selection.
but service restoration is quicker. Again,
a utility outage results in total outage to
15
Utility #1 Utility #2 Utility #3
the load until transfer occurs. Extension
of the bus or adding breakers requires 16
a shutdown of the bus.
If paralleling sources, reverse current,
reverse power and other appropriate 17
relaying protection should be added
as requested by the utility. 52 NC 52 NC 52 NC
18
C. Multiple Sources with Tie Breaker, NO NO
Bus #1 Bus #2 Bus #3
Figure 1.1-15 and Figure 1.1-16 52 52
This configuration is similar to configu- 19
ration B. It differs significantly in that
both utility sources normally carry the 52 NO 52 Typical Feeder 52 52 52 NO
loads and also by the incorporation 20
of a normally open tie breaker. The Tie Busway
outage to the system load for a utility
outage is limited to half of the system. 21
Figure 1.1-16. Triple-Ended Arrangement

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-14 Power Distribution Systems
System Design August 2013
Sheet 01 016

i Health Care Facilities ■ NFPA 101-2009—Life Safety Code The electrical system requirements for
■ NFPA 110-2010—Standard for Emer- the essential electrical system (EES)
Health care facilities are defined by gency and Standby Power Systems vary according to the type of health
NFPA (National Fire Protection Agency) ■ NFPA 111-2010—Standard on
care facility. Health care facilities are
ii as “Buildings or portions of buildings Stored Electrical Energy Emergency categorized by NFPA 99 as Type 1,
in which medical, dental, psychiatric, and Standby Power Systems Type 2 or Type 3 facilities. Some
nursing, obstetrical, or surgical care example health care facilities, classified
1 are provided.” Due to the critical These NFPA guidelines represent the by type, are summarized in the
nature of the care being provided at most industry recognized standard following Table 1.1-8.
these facilities and their increasing requirements for health care electrical
2 dependence on electrical equipment design. However, the electrical design Table 1.1-8. Health Care Facilities
for preservation of life, health care engineer should consult with the Description Definition EES Type
facilities have special requirements for authorities having jurisdiction over
3 the design of their electrical distribu- the local region for specific electrical
Hospitals NFPA 99 Chap. 13 Type 1
Nursing homes NFPA 99 Chap. 17 Type 2
tion systems. These requirements are distribution requirements. Limited care
typically much more stringent than facilities NFPA 99 Chap. 18 Type 2
4 commercial or industrial facilities. Health Care Electrical System Ambulatory
The following section summarizes Requirements surgical
some of the unique requirements facilities NFPA 99 Chap. 14 Type 3 
5 of health care facility design. Health care electrical systems usually Other health
consist of two parts: care facilities NFPA 99 Chap. 14 Type 3 
There are several agencies and organi-  If electrical life support or critical care areas
6 zations that develop requirements 1. Non-essential or normal are present, then facility is classified as Type 1.
for health care electrical distribution electrical system.
system design. The following is a 2. Essential electrical system.
Type 1 Essential Electrical
7 listing of some of the specific NFPA Systems (EES)
(National Fire Protection Agency) All electrical power in a health care
standards that affect health care facility is important, though some Type 1 essential electrical systems
8 facility design and implementation: loads are not critical to the safe opera- (EES) have the most stringent require-
tion of the facility. These “non-essential” ments for providing continuity of
■ NFPA 37-2010—Standard for or “normal” loads include things such electrical service and will, therefore,
9 Stationary Combustion Engines as general lighting, general lab equip- be the focus of this section. Type 1
and Gas Turbines ment, non-critical service equipment, EES requirements meet or exceed
■ NFPA 70-2011—National patient care areas, etc. These loads are the requirements for Type 2 and
10 Electrical Code not required to be fed from an alternate Type 3 facilities.
■ NFPA 99-2005—Health Care Facilities source of power.

11
Normal Source Normal Source Normal Source Emergency Power Supply

12 G

13

14

15

16
Non-Essential Loads Non-Essential Loads

17

18 Manual Transfer Switch

Equipment Life Safety Critical


Delayed Automatic Transfer Switch System Branch Branch
19 Emergency System
Automatic (Non-Delaying)
Transfer Switch Essential Electrical System
20
Figure 1.1-17. Typical Large Hospital Electrical System—Type 1 Facility
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-15
August 2013 System Design
Sheet 01 017

Sources: Type 1 systems are required Table 1.1-9. Type 1 EES Applicable Codes B. Critical branch—supplies power
to have a minimum of two independent Description Standard Section for task illumination, fixed equip- i
sources of electrical power—a normal ment, selected receptacles and
source that generally supplies the Design NFPA 99 4.4.1.1.1 selected power circuits for areas
entire facility and one or more alter- Sources NFPA 99 4.4.1.1.4 thru
4.4.4.1.1.7.2
related to patient care. The ii
nate sources that supply power when Uses NFPA 99 4.4.1.1.8 (1-3)
purpose of the critical branch
the normal source is interrupted. The Emergency is to provide power to a limited
alternate source(s) must be an on-site Power Supply number of receptacles and loca- 1
generator driven by a prime mover Classification NFPA 110 4 tions to reduce load and minimize
unless a generator(s) exists as the Distribution NFPA 99 4.4.2 the chances of fault conditions.
normal power source. In the case NEC 517.30 The transfer switch(es) feeding the 2
where a generator(s) is used as the critical branch must be automatic
normal source, it is permissible for the Systems and Branches of Service: The type. They are permitted to have
alternate source to be a utility feed. Type 1 EES consists of two separate appropriate time delays that will 3
Alternate source generators must be power systems capable of supplying follow the restoration of the life
classified as Type 10, Class X, Level 1 power considered essential for life safety branch, but should have
gensets per NFPA 110 Tables 4.1(a) safety and effective facility operation power restored within 10 seconds 4
and 4.2(b) that are capable of providing during an interruption of the normal of normal source power loss.
power to the load in a maximum of power source. They are the emergency The critical branch provides power
10 seconds. Typically, the alternate system and the equipment system. to circuits serving the following 5
sources of power are supplied to the areas and functions:
1. Emergency system—consists of
loads through a series of automatic
and/or manual transfer switches (see
circuits essential to life safety and 1. Critical care areas. 6
critical patient care.
Tab 25). The transfer switches can 2. Isolated power systems in
be non-delayed automatic, delayed The emergency system is an electrical special environments.
automatic or manual transfer depending sub-system that must be fed from an 3. Task illumination and selected
7
on the requirements of the specific automatic transfer switch or series of receptacles in the following
branch of the EES that they are feeding. automatic transfer switches. This patient care areas: infant
It is permissible to feed multiple emergency system consists of two nurseries, medication prep
8
branches or systems of the EES from mandatory branches that provide power areas, pharmacy, selected
a single automatic transfer switch to systems and functions essential to acute nursing areas, psychiatric
provided that the maximum demand life safety and critical patient care. bed areas, ward treatment
9
on the EES does not exceed 150 kVA. rooms, nurses’ stations.
This configuration is typically seen A. Life safety branch—supplies
in smaller health care facilities that power for lighting, receptacles 4. Specialized patient care task 10
must meet Type 1 EES requirements and equipment to perform the illumination, where needed.
(see Figure 1.1-18). following functions: 5. Nurse call systems.
6. Blood, bone and tissue banks.
11
1. Illumination of means of egress.
Normal Source 2. Exit signs and exit direction signs. 7. Telephone equipment rooms
3. Alarms and alerting systems.
and closets. 12
Alternate 8. Task illumination, selected
4. Emergency communications
Source receptacles and selected power
systems.
circuits for the following: general 13
G 5. Task illumination, battery care beds (at least one duplex
chargers for battery powered receptacle), angiographic labs,
lighting, and select receptacles cardiac catheterization labs, 14
at the generator. coronary care units, hemodialysis
6. Elevator lighting control, com- rooms, selected emergency
munication and signal systems. room treatment areas, human 15
7. Automatic doors used for egress. physiology labs, intensive care
units, selected postoperative
Non-Essential
Loads These are the only functions recovery rooms. 16
permitted to be on the life safety 9. Additional circuits and single-
Entire Essential branch. Life safety branch equip-
Electric System ment and wiring must be entirely
phase fraction motors as needed
for effective facility operation.
17
(150 kVA or Less) independent of all other loads
and branches of service. This
Figure 1.1-18. Small Hospital Electrical includes separation of raceways, 18
System—Single EES Transfer Switch boxes or cabinets. Power must be
supplied to the life safety branch
from a non-delayed automatic
19
transfer switch.
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-16 Power Distribution Systems
System Design August 2013
Sheet 01 018

Table 1.1-10. Type 1—Emergency System The following equipment must be and must be shed in the event the
i Applicable Codes arranged for delayed automatic or generator enters an overload condition.
Description Standard Section manual transfer to the emergency
power supply: Ground fault protection—per NFPA 70
ii General NFPA 99 4.4.2.2.2 NEC Article 230.95, ground fault
NEC 517.31 1. Select heating equipment. protection is required on any feeder or
Life safety NFPA 99 4.4.2.2.2.2 2. Select elevators. service disconnect 1000A or larger on
1 branch NEC 517.32
3. Supply, return and exhaust
systems with line to ground voltages
Critical branch NFPA 99 4.4.2.2.2.3 of 150V or greater and phase-to-phase
NEC 517.33 ventilating systems for surgical, voltages of 600V or less. For health care
obstetrical, intensive care,
2 Wiring NFPA 99 4.4.2.2.4
coronary care, nurseries and
facilities (of any type), a second level of
NEC 517.30(C) ground fault protection is required to
emergency treatment areas. be on the next level of feeder down-
3 2. Equipment system—consists of 4. Supply, return and exhaust stream. This second level of ground
major electrical equipment necessary ventilating systems for airborne fault is only required for feeders that
for patient care and Type 1 operation. infectious/isolation rooms, labs and serve patient care areas and equipment
4 The equipment system is a subsystem
medical areas where hazardous intended to support life. 100% selective
materials are used. coordination of the two levels of ground
of the EES that consists of large electrical fault protection must be achieved with a
equipment loads needed for patient 5. Hyperbaric facilities.
5 care and basic hospital operation. 6. Hypobaric facilities.
minimum six-cycle separation between
the upstream and downstream device.
Loads on the equipment system that 7. Autoclaving equipment.
are essential to generator operation are New in the 2011 NEC, ground fault
6 required to be fed by a non-delayed 8. Controls for equipment listed above. protection is now allowed between
automatic transfer switch. 9. Other selected equipment in the generator(s) and the EES transfer
kitchens, laundries, radiology switch(es). However, NEC 517.17(B)
7 The following equipment must be rooms and central refrigeration prohibits the installation of ground fault
arranged for delayed automatic transfer as selected. protection on the load side of a transfer
to the emergency power supply: switch feeding EES circuits (see Figure
8 Table 1.1-11. Type 1—Equipment System
1.1-19—additional level of ground fault).
1. Central suction systems for medical Applicable Codes
and surgical functions. Careful consideration should be used in
Description Standard Section applying ground fault protection on the
9 2. Sump pumps and other equipment
essential electrical system to prevent
required for the safe operation of General NFPA 99 4.4.2.2.3
NEC 517.34 a ground fault that causes a trip of the
a major apparatus.
10 Equipment NFPA 99 4.4.2.2.3 (3-5) normal source to also cause a trip on
3. Compressed air systems for NEC 517.34(A)-(B) the emergency source. Such an event
medical and surgical functions. could result in complete power loss of
11 4. Smoke control and stair Any loads served by the generator that both normal and emergency power
pressurization systems. are not approved as outlined above as sources and could not be recovered
part of the essential electrical system until the source of the ground fault
5. Kitchen hood supply and exhaust
12 systems, if required to operate must be connected through a separate was located and isolated from the
system. To prevent this condition,
during a fire. transfer switch. These transfer switches
must be configured such that the loads NEC 700.26 removes the ground fault
13 will not cause the generator to overload protection requirement for the

Normal Source Normal Source(s)


14 G
Generator Breakers are
Supplied with
15 480/277V ➀ 480/277V ➀ 480/277 V ➀ Ground Fault Alarm
1000 A Service 1000 A Service 1000 A Service Only. (NEC 700.26)
GF GF GF
or Larger Entrance or Larger Entrance or Larger Entrance
16 Ground Fault
is Permitted
Additional Level
17 GF GF GF GF GF of Ground Fault
Protection
GF GF GF GF GF GF and EES Transfer
Switches.
(NEC 517.17(B))

18 Non-Essential Loads Non-Essential Loads

19
GF = Ground Fault Protection Required Additional Level of Ground Fault is
not
20 Essential Electrical System Transfer Switches. (NEC 517.17a(2))

Figure 1.1-19. Additional Level of Ground Fault Protection


21  Ground fault protection is required for service disconnects 1000A and larger or systems with less than 600V phase-to-phase and greater than 150V to
ground per NEC 230.95.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-17
August 2013 System Design
Sheet 01 019

emergency system source. Typically, Maintenance and Testing trained in development and execution
the emergency system generator(s) Regular maintenance and testing of of annual preventative maintenance i
are equipped with ground fault alarms the electrical distribution system in procedures of health care facility
that do not automatically disconnect a health care facility is necessary to electrical distribution systems.
power during a ground fault. ensure proper operation in an emer- ii
gency and, in some cases, to maintain Paralleling Emergency Generators
Table 1.1-12. Ground Fault Protection
government accreditation. Any health
Applicable Codes
care facility receiving Medicare or Without Utility Paralleling 1
Description Standard Section In many health care facilities (and
Medicaid reimbursement from the
government must be accredited by the other large facilities with critical
Services
Feeders
NEC
NEC
230.95
215.10 Joint Commission on Accreditation of loads), the demand for standby 2
Additional level NEC 517.17 Health Care Organizations (JCAHO). emergency power is large enough
NFPA 99 4.3.2.5 JCAHO has established a group of to require multiple generator sets to
Alternate source NEC 700.26 standards called the Environment of power all of the required essential 3
NEC 701.26 Care, which must be met for health electrical system (EES) loads. In many
care facility accreditation. Included in cases, it becomes more flexible and
Wet procedure locations—A wet these standards is the regular testing easier to operate the required multiple 4
procedure location in a health care of the emergency (alternate) power generators from a single location using
facility is any patient care area that system(s). Diesel-powered EPS instal- generator paralleling switchgear.
is normally subject to wet conditions lations must be tested monthly in Figure 1.1-20 on Page 1.1-18 shows 5
while patients are present. Typical wet accordance with NFPA 110 Standard an example of a typical one-line for a
procedure locations can include oper- for Emergency and Standby Power paralleling switchgear lineup feeding
ating rooms, anesthetizing locations, Systems. Generators must be tested the EES. 6
dialysis locations, etc. (Patient beds, for a minimum of 30 minutes under
A typical abbreviated sequence of
toilets and sinks are not considered the criteria defined in NFPA 110.
wet locations.) These wet procedure
operation for a multiple emergency 7
One method to automate the task of generator and ATS system follows.
locations require special protection
monthly generator tests is through the Note that other modes of operation
to guard against electric shock. The
ground fault current in these areas use of Power Xpert® communications. such as generator demand priority and 8
With the Power Xpert integrated meter- automated testing modes are available
must be limited to not exceed 6 mA.
ing, monitoring and control system, a but are not included below. (Reference
In areas where the interruption of power facility maintenance director can ini- Tab 41 for complete detailed 9
is permissible, ground fault circuit tiate a generator test, control/monitor sequences of operation.)
interrupters (GFCI) can be employed. loads, meter/monitor generator test
GFCIs will interrupt a circuit when points and create a JCAHO compliant
1. Entering emergency mode 10
ground fault current exceeds 5 mA report automatically from a central PC. a. Upon loss of normal source,
(±1 mA). The report contains all metered values, automatic transfer switches
test results, date/time information, etc. send generator control system 11
In areas where the interruption of necessary to satisfy JCAHO require- a run request.
power cannot be tolerated, protection ments. This automated generator testing
from ground fault currents is accom- procedure reduces the labor, training
b. All available generators are 12
plished through the use of an isolated started. The first generator up
and inaccuracies that occur during to voltage and frequency is
power system. Isolated power systems manual emergency power system tests.
provide power to an area that is iso- (See Power Monitoring Tab 2.)
closed to the bus. 13
lated from ground (or ungrounded). c. Unsheddable loads and load
This type of system limits the amount Table 1.1-14. Maintenance and Testing shed Priority 1 loads are pow-
of current that flows to ground in Applicable Codes ered in less than 10 seconds. 14
the event of a single line-to-ground Description Standard Section d. The remaining generators are
fault and maintains circuit continuity.
synchronized and paralleled
Electronic line isolation monitors (LIM) Grounding NFPA 99 4.3.3.1
to the bus as they come up to 15
are used to monitor and display leakage Emergency power NFPA 99 4.4.4.1.1
system JCAHO EC.2.14(d) voltage and frequency.
currents to ground. When leakage
current thresholds are exceeded, visible Generator NFPA 110 8.4 e. As additional generators are 16
and/or audible alarms are initiated to Transfer switches NFPA 110 8.3.5, 8.4.6 paralleled to the emergency
alert occupants of a possible hazardous bus, load shed priority levels
Breakers NFPA 99 4.4.4.1.2
condition. This alarm occurs without NFPA 110 8.4.7 are added, powering their 17
interrupting power to allow for the associated loads.
safe conclusion of critical procedures. Routine maintenance should be per- f. The system is now in
Table 1.1-13. Wet Procedure Location
formed on circuit breakers, transfer emergency mode. 18
switches, switchgear, generator equip- 2. Exit from emergency mode
Applicable Codes
ment, etc. by trained professionals
Description Standard Section to ensure the most reliable electrical a. Automatic transfer switches 19
General NFPA 99 4.3.2.2.9 system possible. See Tab 41 for sense the utility source is
NEC 517.20 Eaton’s Electrical Services & Systems within acceptable operational
Isolated power NFPA 99 4.3.2.6 (EESS), which provides engineers, tolerances for a time duration 20
systems NEC 517.160 set at the automatic transfer
switch.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-18 Power Distribution Systems
System Design August 2013
Sheet 01 020

b. As each automatic transfer With Utility Paralleling Many health care facilities are taking
i switch transfers back to utility Today, many utilities are offering their advantage of these utility incentives
power, it removes its run customers excellent financial incen- by adding generator capacity over
request from the generator tives to use their on-site generation and above the NFPA requirements.
ii plant. capacity to remove load from the utility Figure 1.1-21 on Page 1.1-19 shows
c. When the last automatic trans- grid. These incentives are sometimes an example one-line of a health care
fer switch has retransferred to referred to as limited interruptible facility with complete generator
1 the utility and all run requests rates (LIP). Under these incentives, backup and utility interconnect.
have been removed from the utilities will greatly reduce or eliminate NFPA 110 requirements state that the
generator plant, all generator kWhr or kW demand charges to their
2 circuit breakers are opened. customers with on-site generation
normal and emergency sources must
be separated by a fire-rated wall.
d. The generators are allowed capabilities. In exchange, during times
of peak loading of the utility grid, the The intent of this requirement is so that
3 to run for their programmed
utility can ask their LIP rate customers a fire in one location cannot take out
cool-down period.
to drop load from the grid by using both sources of power. To meet this
e. The system is now back in their on-site generation capabilities. requirement, the paralleling switchgear
4 automatic/standby mode. must be split into separate sections
Health care facilities are ideally suited with a tie bus through a fire-rated wall.
to take advantage of these programs For more information on generator
5 because they already have significant paralleling switchgear, see Tab 40.
on-site generation capabilities due to
the code requirements described.
6
Utility
7
Transformer Generators X = Number of Units
8
Utility G1 G2 Gx
Metering
9
Typical
Generator
Breaker
10 Service Main

11 Normal Bus Emergency Bus

Optional Optional Electrically


12 Electrically Operated Stored
Energy Breakers
Operated
Stored EF1 EF2 EFx
F1 F2 Fx
Energy
13 Breakers

14
Equipment Life Safety Critical Load Shed/Load
ATS # 1 ATS # 2 ATS # X Add ATS Units
15 Non-Essential
Loads

Optional Closed
16 EP1 EP2 Typical
Panelboards
EPX Transition
Paralleling of
Generators and
Utility
17
Figure 1.1-20. Typical One-Line for a Paralleling Switchgear Lineup Feeding the Essential Electrical System (EES)
18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-19
August 2013 System Design
Sheet 01 021

Utility Fire-Rated Wall i


or Separation Barrier

Transformer
Generators X = Number of Units ii
Utility G1 G2 Gx
Metering 1
Utility
Closed
Protective Typical
Relay Transition
Paralleling of Generator
2
Generators and Breaker
Service Main Utility, Plus
Soft Loading/ 3
Unloading
Normal Bus Emergency Bus
TIE Optional TIE 4
Optional Electrically Operated
Electrically Stored Energy
Operated
Field Installed
Cable or Busway
Breakers 5
Stored F1 F2 Fx EF1 EF2 EFx
Energy
Breakers 6

Equipment Life Safety Critical Load Shed/


7
ATS # 1 ATS # 2 ATS # X Load Add
Non-Essential ATS Units
Loads 8
EP1 EP2 EPX Typical
Panelboards 9
Figure 1.1-21. Typical One-Line Health Care Facility with Complete Generator Backup and Utility Interconnect
10

11

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-20 Power Distribution Systems
August 2013
Sheet 01022

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-1
August 2013 Generator System Design
Sheet 01 023

Generators and a supply-side bonding jumper to Types of Generators


i
be installed from the source of a
Generator Systems separately derived system to the first Generators can be either synchronous
disconnecting means in accordance or asynchronous. Asynchronous
with 250.30(A)(2). Another new generators are also referred to as ii
requirement, 250.30(C)—Outdoor induction generators. The construction
Source—has been added, and requires is essentially the same as an induction
a grounding electrode connection at motor. It has a squirrel-cage rotor and 1
the source location when the separately wound stator. An induction generator
derived system is located outside is a motor driven above its designed
of the building or the structure synchronous speed thus generating 2
being supplied. power. It will operate as a motor if it
is running below synchronous speed.
Typical Diesel Genset—Caterpillar Article 445.19—Generators Supplying The induction generator does not have 3
Multiple Loads—has been revised an exciter and must operate in parallel
Introduction to require that the generator have with the utility or another source. The
The selection and application overcurrent protection per 240.15(A) induction generator requires VARs from 4
when using individual enclosures an external source for it to generate
of generators into the electrical
tapped from a single feeder. power. The induction generator
distribution system will depend on
the particular application. There are Article 517.17(B)—Feeder GFP (Health
operates at a slip frequency so its 5
output frequency is automatically
many factors to consider, including Care Facilities)—now allows, but does locked in with the utility's frequency.
code requirements, environmental not require, multiple levels of GFPE
constraints, fuel sources, control upstream of the transfer switch when An induction generator is a popular
6
complexity, utility requirements and the choice is made to provide GFPE choice for use when designing
load requirements. The health care on the alternate power source cogeneration systems, where it will
requirements for legally required (i.e., generator). operate in parallel with the utility.
7
emergency standby generation This type of generator offers certain
systems are described starting on Article 701.6(D)—Signals (Legally advantages over a synchronous
Page 1.1-14. Systems described in Required Standby Systems)—now generator. For example, voltage and
8
this section are applicable to health requires ground fault indication for frequency are controlled by the utility;
care requirements, as well as other legally required standby systems of thus voltage and frequency regulators
facilities that may require a high more than 150V to ground and OCPDs are not required. In addition, the
9
degree of reliability. The electrical rated 1000A or more. generator construction offers high
supply for data centers, financial reliability and little maintenance.
institutions, telecommunications, Types of Engines Also, a minimum of protective relays
10
government and public utilities Many generator sets are relatively and controls are required. Its major
also require high reliability. Threats disadvantages are that it requires
of disaster or terror attacks have
small in size, typically ranging from
several kilowatts to several mega- VARs from the system and it normally
11
prompted many facilities to require watts. These units are often required cannot operate as a standby/
complete self-sufficiency for emergency generator.
continuous operation.
to come online and operate quickly. 12
They need to have the capacity to
Synchronous generators, however,
run for an extended period of time.
2011 NEC Changes Related to are the most common. Their output is
The internal combustion engine is
determined by their field and governor 13
Generator Systems an excellent choice as the prime
controls. Varying the current in the
mover for the majority of these
Article 250.30—Grounding Separately DC field windings controls the voltage
Derived AC Systems—has been
applications. Turbines may also be
output. The frequency is controlled 14
used. Diesel-fueled engines are the
completely rewritten for clarity and by the speed of rotation. The torque
most common, but other fuels used
for usability. Most notably, the term applied to the generator shaft by
equipment bonding jumper was
include natural gas, digester gas,
the driving engine controls the power 15
landfill gas, propane, biodiesel,
changed to supply-side bonding output. In this manner, the synchro-
crude oil, steam and others.
jumper (see 250.30(A)(2)). This was nous generator offers precise control
necessary to ensure proper identifica- Some campuses and industrial over the power it can generate. In 16
tion and installation of bonding facilities use and produce steam cogeneration applications, it can be
conductors within or on the supply for heating and other processes. used to improve the power factor of
side of service equipment and These facilities may find it economi- the system. 17
between the source of a separately cally feasible to produce electricity as
derived system and the first discon- a byproduct of the steam production.
necting means. The other require- These installations would typically be
18
ments for grounded systems were classified as a cogeneration facility
renumbered to accommodate the producing a fairly constant power
250.30(A)(2) change. 250.30(B)(3)— output and operating in parallel with
19
Ungrounded Systems—has been the electric utility system.
added, and this language requires
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-2 Power Distribution Systems
Generator System Design August 2013
Sheet 01 024

Generator Systems Multiple Isolated Standby Generators Multiple generator systems have a
i The second type of generator system more complex control and protection
Emergency Standby Generator System is a multiple isolated set of standby requirement as the units have to be
There are primarily three types of generators. Figure 1.2-2 shows synchronized and paralleled together.
ii generator systems. The first and multiple generators connected to The generators are required to share
simplest type is a single generator a paralleling bus feeding multiple the load proportionally without swings
that operates independently from transfer switches. The utility is the or prolonged hunting in voltage or
1 the electric utility power grid. normal source for the transfer switches. frequency for load sharing. They may
This is typically referred to as an The generators and the utility are never also require multiple levels of load
emergency standby generator continuously connected together in this shedding and/or load restoration
2 system. Figure 1.2-1 shows a single scheme. Multiple generators may be schemes to match generation capacity.
standby generator, utility source required to meet the load requirements Multiple Generators Operating in
and a transfer switch. In this case, the (N system). Generators may be applied
3 load is either supplied from the utility in an N+1 or a 2N system for improved
Parallel with Utility System
or the generator. The generator and system reliability. The third type of system is either one
the utility are never continuously with a single or multiple generators
4 connected together. This simple radial that operate in parallel with the utility
system has few requirements for Utility system. Figure 1.2-3 shows two
protection and control. It also has the G1 G2 generators and a utility source feeding
5 least impact on the complete electric a switchgear lineup feeding multiple
power distribution system. It should Switchgear
loads. This system typically requires
be noted that this type of generator generator capacity sufficient to carry
6 system improves overall electrical the entire load or sophisticated load
reliability but does not provide the shedding schemes. This system will
ATS-1 ATS-2
redundancy that some facilities require a complete and complex
7 require if the generator fails to protection and control scheme. The
start or is out for maintenance. electric utility may have very stringent
Load 1 Load 2 and costly protection requirements
8 for the system. IEEE standard 1547
Utility describes the interconnection require-
Figure 1.2-2. Multiple Isolated Set of ments for paralleling to the utility.
G1
9 Standby Generators
In an N system, where N is the number
Utility
of generators required to carry the
10 load; if a generator fails or is out for
G1 G2

maintenance, then the load may be


dropped. This is unacceptable for most Switchgear
11 critical 24/7 operations. In an N + 1
ATS
system, N is the number of generators
12 needed to carry the load and 1 is
an extra generator for redundancy.
If one generator fails to start or is out
13 Load
for maintenance, it will not affect the
Load 1 Load 2 Load 3
load. In a 2N system, there is complete
100% redundancy in the standby
14 Figure 1.2-1. Emergency Standby generation system such that the failure Figure 1.2-3. Multiple Generators Operating
Generator System of one complete set of generators in Parallel with Utility System
will not affect the load.
15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-3
August 2013 Generator System Design
Sheet 01 025

Generator Fundamentals The application of generators requires derived system and a four-pole transfer
A generator consists of two primary
special protection requirements. switch is required or ground fault relays i
The size, voltage class, importance could misoperate and unbalanced
components, a prime mover and an and dollar investment will influence neutral current may be carried on
alternator. The prime mover is the the protection scheme associated with ground conductors. ii
energy source used to turn the rotor the generator(s). Mode of operation
of the alternator. It is typically a An IEEE working group has studied the
will influence the utility company’s practice of low resistance grounding
diesel combustion engine for most interface protection requirements. 1
emergency or standby systems. of medium voltage generators within
Paralleling with the electric utility is the general industry. This “working
In cogeneration applications, the the most complicated of the utility
prime mover may come from a steam group” found that, for internal generator
driven turbine or other source. On
inter-tie requirements. IEEE ANSI 1547 ground faults, the vast majority of the 2
provides recommended practices. damage is done after the generator
diesel units, a governor and voltage
regulator are used to control the speed breaker is tripped offline, and the field
and power output.
Generator Grounding and Bonding and turbine are tripped. This is due to 3
(Ref. NEC 2011, Article 250.30(A)(1) the stored energy in the generator flux
The alternator is typically a synchro- that takes several seconds to dissipate
nous machine driven by the prime and (2)) 4
after the generator is tripped offline.
mover. A voltage regulator controls its Generator grounding methods need It is during this time that the low
voltage output by adjusting the field. to be considered and may affect the resistance ground allows significant
The output of a single generator or distribution equipment and ratings. amounts of fault current to flow into 5
multiple paralleled generator sets is Generators may be connected in delta the ground fault. Because the large fault
controlled by these two inputs. The or wye, but wye is the most typical currents can damage the generator’s
alternator is designed to operate at a connection. A wye-connected generator winding, application of an alternate 6
specified speed for the required output can be solidly grounded, low impedance protection method is desirable during
frequency, typically 60 or 50 Hz. The grounded, high impedance grounded this time period. One of the solutions
voltage regulator and engine governor or ungrounded. Section 1.4 discusses set forth by this “working group” is 7
along with other systems define the general grounding schemes, benefits a hybrid high resistance grounding
generator’s response to dynamic of each and protection considerations. (HHRG) scheme as shown in
load changes and motor starting A solidly grounded generator may have Figure 1.2-4. In the HHRG scheme, 8
characteristics. a lower zero sequence impedance than the low resistance ground (LRG)
its positive sequence impedance. In this is quickly tripped offline when the
Generators are rated in power and
case, the equipment will need to be rated generator protection senses the 9
voltage output. Most generators are
for the larger available ground fault ground fault. The LRG is cleared
designed to operate at a 0.8 power
current. The generator’s neutral may at the same time that the generator
factor. For example, a 2000 kW
generator at 277/480V would have a be connected to the system-neutral; if breaker clears, leaving the high 10
it is, the generator is not a separately resistance ground portion connected
kVA rating of 2500 kVA (2000 kW/ 08 pf)
derived system and a three-pole transfer to control the transient overvoltages
and a continuous current rating
˙˙˙
of 3007A ( 2500 kVA ⁄ 480V 3 ) . switch is used. If the generator’s neutral during the coast-down phase of the 11
is bonded to ground separate from the generator, thereby all but eliminating
Typical synchronous generators system-neutral, it is a separately generator damage.
for industrial and commercial 12
power systems range in size from
100–3000 kVA and from 208V–13,800V.
Other ratings are available and these
HRG 13
discussions are applicable to those 51G
ratings as well. Gen R 59G
86
R LRG
14
Generators must be considered in the Phase 87GN
short-circuit and coordination study Relays
as they may greatly impact the rating 15
of the electrical distribution system.
This is especially common on large
installations with multiple generators 16
and systems that parallel with the
utility source. Short-circuit current
contribution from a generator 17
typically ranges from 8 to 12 times
Figure 1.2-4. Hybrid High Resistance Grounding Scheme
full load amperes.
18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-4 Power Distribution Systems
Generator System Design August 2013
Sheet 01 026

Generator Controls A synch-scope is typically supplied The subtransient reactance Xd” will
i The engine generator set has controls
on paralleling gear. The synch-scope range from a minimum of approxi-
displays the relative relationship mately 9% for a two-pole, wound-rotor
to maintain the output frequency between voltage phasors on the machine to approximately 32% for a
ii (speed) and voltage. These controls
consist of a governor and voltage
generator to be paralleled and the low-speed, salient-pole, hydro-generator.
bus. If the generator is running slower The initial symmetrical fault current can
regulator. As loads change on the than the bus (less than 60 Hz) then the be as much as 12 times full load current.
1 system, the frequency and voltage needle on the scope will spin in the
will change. The speed control will counterclockwise direction. If it is Depending on the generator type,
then adjust the governor to correct running faster, then it will rotate in the zero sequence impedance may be
2 for the load (kW) change. The the clockwise direction. The greater less than the subtransient reactance
voltage regulator will change the the frequency difference, the faster and the ground fault current substan-
field current to adjust the voltage is the rotation. It is important that the tially higher than the three-phase
3 to the desired voltage value. These generators are in phase before they short-circuit current. For example, a
are the basic controls found on all are paralleled. Severe damage will 2500 kVA, 480/277V, four-pole, 2/3 pitch
synchronous generators. occur if generators are paralleled standby generator has a 0.1411 per
4 Multiple generator systems require out-of-phase. unit subtransient reactance Xd” and
a 0.033 per unit zero sequence X o
more sophisticated controls. reactance. The ground current is
Generators are paralleled in a multi- Generator Short-Circuit
5 generator system and they must share
approximately a third larger than the
Characteristics three-phase fault current. The ground
the load. These systems often have fault current can be reduced to the
a load shed scheme, which adds to
6 the complexity. If a short circuit is applied directly to three-phase level by simply adding a
the output terminals of a synchronous small reactance between the generator
Multiple generator schemes need a generator, it will produce an extremely neutral and ground while still being
7 master controller to prevent units from high current initially, gradually decaying considered solidly grounded.
being connected out-of-phase. The to a steady-state value. This change The electric power system analysis
sequence of operation is to send a is represented by a varying reactive must be performed based on the worst-
8 start signal to all generators simulta- impedance. Three specific reactances case operating conditions. Typically
neously. The first unit up to frequency are used for short-circuit fault currents. this is when all sources are paralleled.
and voltage will be permitted to close They are: If the system can operate with both
9 its respective breaker and energize the the utility supply and generators in
paralleling bus. Breakers for the other ■ Subtransient reactance Xd”, which
is used to determine the fault parallel, then the equipment must be
generators are held open, not permit- rated for the combined fault current
10 ted to close, until certain conditions current during the first 1 to 5 cycles
plus motor contribution. If the generator
are met. Once the paralleling bus is ■ Transient reactance Xd’, which is
used to determine the fault current and utility will not be paralleled, then
energized, the remaining generators both cases will need to be looked at
11 must be synchronized to it before during the next 5 to 200 cycles
independently and the worst case used
the generators can be paralleled. ■ Synchronous reactance Xd”, which
for selecting the equipment ratings.
Synchronization compares the voltage is used to determine the steady-
12 phasor’s angle and magnitude. Both state fault current
generators must be operating at the
same frequency and phase-matched
13 within typically 5 to 10 degrees with
each other. The voltage magnitude
typically must be within 20 to 24%.
14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-5
August 2013 Generator System Design
Sheet 01 027

Generator Protection
Generator protection will vary and
Generator Protection ANSI/IEEE i
Std 242-1986
depend on the size of the generator,
type of system and importance of the ii
generator. Generator sizes are defined
1 1 1 1
as: small—1000 kVA maximum up
Alternate
to 600V (500 kVA maximum when 51
Location
51V 32 40
1
above 600V); medium over 1000 kVA
to 12,500 kVA maximum regardless
of voltage; large—from 12,500– 2
50,000 kVA. The simplest is a single
generator system used to feed emer- 1 3
gency and/or standby loads. In this
Gen 51G 87 3
case, the generator is the only source
available when it is operating and 1
it must keep operating until the
51 Preferred 4
normal source returns. Location Gen

Figure 1.2-5 Part (A) shows minimum 1


recommended protection for a single 51G
5
generator used as an emergency or
standby system. Phase and ground
time overcurrent protection (Device
(A) (A) Single Isolated Generator on Low Voltage System (B) 6
(B) Multiple Isolated Generator on Medium Voltage System
51 and 51G) will provide protection for
external faults. For medium voltage
generators, a voltage controlled time
Figure 1.2-5. Typical Protective Relaying Scheme for Small Generators 7
overcurrent relay (Device 51V) is
recommended for the phase protec-
tion as it can be set more sensitive
8
R
than standard overcurrent relays and
is less likely to false operate on normal
overloads. This scheme may not
9
provide adequate protection for
50/5A 87-1
internal generator faults when no 10
other power source exists. Local
generator controllers may offer 50/5A 87-2
additional protection for voltage 11
and frequency conditions outside
the generator’s capabilities.
50/5A 87-3
Figure 1.2-5 Part (B) shows the 12
recommended protection for multiple,
isolated, medium voltage, small
generators. Additional protection 13
may be desired and could include
generator differential, reverse power,
and loss of field protection. Differential Gen 14
protection (Device 87) can be accom-
plished with either a self-balancing
set of CTs as in Figure 1.2-6 or with 15
a percentage differential scheme as
in Figure 1.2-7 on Page 1.2-6. The
percentage differential scheme 16
offers the advantage of reducing the
Figure 1.2-6. Self-Balancing Generator
possibility for false tripping due to
CT saturation. The self-balancing
Differential Relay Scheme 17
scheme offers the advantages of
increased sensitivity, needing three
current transformers in lieu of six, 18
and the elimination of current
transformer external wiring from
the generator location to the generator 19
switchgear location.
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-6 Power Distribution Systems
Generator System Design August 2013
Sheet 01 028

Reverse power protection (Device 32)


i is used to prevent the generator
from being motored. Motoring could Grounding
Resistor
damage (with other hazards) the prime
ii mover. A steam turbine could overheat 51G

and fail. A diesel or gas engine could


either catch fire or explode. A steam
1 turbine can typically withstand
approximately 3% reverse power
where a diesel engine can withstand
2 up to 25% reverse power.
Loss of field protection (Device 40) is 87

3 needed when generators are operating


01
in parallel with one another or the R1
PC
power grid. When a synchronous R1

4 generator loses its field, it will continue 02 R2


to generate power as an induction Gen
generator obtaining its excitation from OC
R2

5 the other machines on the system. 03 R3


During this condition, the rotor will 87G R3
quickly overheat due to the slip
6 frequency currents induced in it. Loss
of excitation in one machine could
jeopardize the operation of the other
7 machines beyond their capability and 52

the entire system.

9
To Main Bus OC = Operating coil
PC = Permissive coil
10
Figure 1.2-7. Generator Percentage Differential Relay (Phase Scheme)
and Ground Differential Scheme Using a Directional Relay
11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-7
August 2013 Generator System Design
Sheet 01 029

Typical protection for larger generators


is shown in Figure 1.2-8. It adds i
phase unbalance and field ground
fault protection. Phase unbalance 3
(Device 46) or negative sequence
87B
ii
overcurrent protection prevents the 81U/O
generator’s rotor from overheating
damage. Unbalanced loads, fault 1
conditions or open phasing will
27/59
produce a negative sequence current
to flow. The unbalanced currents 2
induce double system frequency
currents in the rotor, which quickly
causes rotor overheating. Serious 3 1 1 1 3
damage will occur to the generator if 51V 40 32 46
the unbalance is allowed to persist.
3 1 4
Other protection functions such as 87G
87
under/overvoltage (Device 27/59) 60
could be applied to any size generator. Voltage Regulator and 5
The voltage regulator typically main- Metering Circuits
tains the output voltage within its 1
desired output range. This protection 1 64 6
can provide backup protection in case 49
the voltage regulator fails. Under/over
frequency protection (Device 81U/81O) 7
could be used for backup protection Gen
for the speed control. Sync check E

relays (Device 25) are typically applied 8


as a breaker permissive close function
where generators are paralleled.
Many modern protective relays are 51G
9
microprocessor-based and provide a
full complement of generator protection 10
functions in a single package. The cost
per protection function has been
drastically reduced such that it is 11
feasible to provide more complete Figure 1.2-8. Typical Protective Relaying Scheme for Large Generator
protection even to smaller generators.
IEEE ANSI 1547 provides recom- 12
mended practices for utility inter-tie
protection. If the system has closed-
transition or paralleling capability, 13
additional protection may be required
by the utility. Typically, no additional
protection is required if the generator 14
is paralleled to the utility for a maximum
of 100 msec or less. Systems that
offer soft transfer, peak shaving or 15
co-generation will require additional
utility inter-tie protection. The protection
could include directional overcurrent 16
and power relays and even transfer
trip schemes. Please consult your local
utility for specific requirements. 17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-8 Power Distribution Systems
Generator System Design August 2013
Sheet 01 030

i Generator Set Sizing Typical rating definitions for diesel Electrical rating definitions for natural
gensets are: standby, prime plus 10, gas powered gensets are typically
and Ratings continuous and load management defined as standby or continuous with
(paralleled with or isolated from definitions similar to those mentioned
ii Many factors must be considered utility). Any diesel genset can have above for diesels. Natural gas gensets
when determining the proper size or several electrical ratings depending recover more slowly than diesel
electrical rating of an electrical power on the number of hours of operation gensets when subjected to block
1 generator set. The engine or prime per year and the ratio of electrical loads. Diesel engines have a much
mover is sized to provide the actual load/genset rating when in operation. more direct path from the engine gov-
or real power in kW, as well as speed The same diesel genset can have a ernor and fuel delivery system to the
2 (frequency) control through the use
of an engine governor. The generator
standby rating of 2000 kW at 0.8 power combustion chamber and this results
factor (pf) and a continuous rating of in a very responsive engine-generator.
is sized to supply the kVA needed at 1825 kW at 0.8 pf. The lower continu- A natural gas engine is challenged
3 startup and during normal running ous rating is due to the additional with air-fuel flow dynamics and a
operation and it also provides voltage hours of operation and higher load much more indirect path from the
control using a brushless exciter and that the continuous genset must engine governor (throttle actuator)
4 voltage regulator. Together the engine carry. These additional requirements and fuel delivery system (natural
and generator provide the energy put more stress on the engine and gas pressure regulator, fuel valve and
necessary to supply electrical loads generator and therefore the rating actuator, carburetor mixer, aftercooler,
5 in many different applications is decreased to maintain longevity intake manifold) to the combustion
encountered in today’s society. of the equipment. chamber and this results in a
The generator set must be able to less responsive engine-generator.
6 supply the starting and running
Different generator set manufacturers Diesel gensets recover about twice
use basically the same diesel genset as fast as natural gas gensets.
electrical load. It must be able to electrical rating definitions and these
pick up and start all motor loads and
7 low power factor loads, and recover
are based on international diesel For the actual calculations involved
fuel stop power standards from for sizing a genset, there are readily
without excessive voltage dip or organizations like ISO, DIN and others. accessible computer software programs
extended recovery time. Nonlinear
8 loads like variable frequency drives,
A standby diesel genset rating is that are available on the genset manu-
typically defined as supplying varying facturer’s Internet sites or from the
uninterruptible power supply (UPS) electrical loads for the duration of a manufacturer’s dealers or distributors.
systems and switching power supplies
9 also require attention because the SCR
power outage with the load normally These programs are used to quickly
connected to utility, genset operating and accurately size generator sets for
switching causes voltage and current <100 hours per year and no overload their application. The programs take
waveform distortion and harmonics.
10 The harmonics generate additional
capability. A prime plus 10 rating is into consideration the many different
typically defined as supplying varying parameters discussed above, including
heat in the generator windings, and electrical loads for the duration of a the size and type of the electrical loads
the generator may need to be upsized
11 to accommodate this. The type of
power outage with the load normally (resistive, inductive, SCR, etc.), reduced
connected to utility, genset operating voltage soft starting devices (RVSS),
fuel (diesel, natural gas, propane, etc.) ≤500 hours per year and overload motor types, voltage, fuel type, site
12 used is important as it is a factor in capability of 10% above its rating for conditions, ambient conditions and
determining generator set transient 1 hour out of 12. A continuous rating other variables. The software will
response. It is also necessary to is typically defined as supplying optimize the starting sequences of the
13 determine the load factor or average unvarying electrical loads (i.e., base motors for the least amount of voltage
power consumption of the generator loaded) for an unlimited time. The load dip and determine the starting kVA
set. This is typically defined as the load management ratings apply to gensets needed from the genset. It also provides
14 (kW) x time (hrs. while under that in parallel operation with the utility transient response data, including
particular load) / total running time. or isolated/islanded from utility and voltage dip magnitude and recovery
When this load factor or average these ratings vary in usability from duration. If the transient response is
15 power is taken into consideration <200 hours per year to unlimited unacceptable, then design changes can
with peak demand requirements usage. Refer to generator set manufac- be considered, including oversizing
and the other operating parameters turers for further definitions on load the generator to handle the additional
16 mentioned above, the overall electrical
rating of the genset can be deter-
management ratings, load factor or kVAR load, adding RVSS devices to
average power consumption, peak reduce the inrush current, improving
mined. Other items to consider include demand and how these ratings are system power factor and other methods.
17 the unique installation, ambient, and typically applied. Even though there is The computer software programs are
site requirements of the project. These some standardization of these ratings quite flexible in that they allow changes
will help to determine the physical across the manufacturers, there also to the many different variables and
18 configuration of the overall system. exists some uniqueness with regard to parameters to achieve an optimum
how each manufacturer applies their design. The software allows, for
generator sets. example, minimizing voltage dips
19 or using paralleled gensets vs. a
single genset.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-9
August 2013 Generator System Design
Sheet 01 031

Genset Sizing Guidelines Generator Set Installation ■ Hazardous waste considerations


i
for fuel, antifreeze, engine oil
Some conservative rules of thumb and Site Considerations ■ Meeting local building and
for genset sizing include:
There are many different installation electrical codes
1. Oversize genset 20–25% parameters and site conditions ■ Genset exposure (coastal
ii
for reserve capacity and for that must be considered to have a conditions, dust, chemicals, etc.)
motor starting. successful generator set installation. ■ Properly sized starting systems 1
2. Oversize gensets for unbalanced The following is a partial list of areas (compressed air, batteries
loading or low power factor to consider when conducting this and charger)
running loads. design. Some of these installation ■ Allowing adequate space for 2
parameters include: installation of the genset and for
3. Use 1/2 hp per kW for motor loads. maintenance (i.e., air filter removal,
■ Foundation type (crushed rock,
4. For variable frequency drives, concrete, dirt, wood, separate oil changing, general genset 3
oversize the genset by at concrete inertia pad, etc.) inspection, etc…)
least 40%. ■ Foundation to genset vibration ■ Flex connections on all systems that
dampening (spring type, cork are attached to the genset and a 4
5. For UPS systems, oversize the rigid structure (fuel piping, founda-
genset by 40% for 6 pulse and and rubber, etc.)
tion vibration isolators, exhaust, air
15% for 6 pulse with input filters ■ Noise attenuation (radiator fan intake, control wiring, power cables, 5
or 12 pulse. mechanical noise, exhaust noise, radiator flanges/duct work, etc.)
air intake noise)
6. Always start the largest motor ■ Diesel fuel day tank systems
first when stepping loads.
■ Combustion and cooling air (pumps, return piping)
6
requirements
■ Fuel storage tank (double walled,
For basic sizing of a generator system, ■ Exhaust backpressure requirements
the following example could be used: ■ Emissions permitting
fire codes) and other parameters 7
■ Delivery and rigging requirements Please see the generator set manufac-
Step 1: Calculate Running Amperes turer’s application and installation
■ Motor loads: ■ Genset derating due to high guidelines for proper application 8
❑ 200 hp motor . . . . . . . . . . . . . 156A
altitudes or excessive ambient and operation of their equipment.
temperatures
❑ 100 hp motor . . . . . . . . . . . . . . 78A 9
❑ 60 hp motor . . . . . . . . . . . . . . . 48A
■ Lighting load . . . . . . . . . . . . . . . . 68A
■ Miscellaneous loads . . . . . . . . . . 95A
10
■ Running amperes . . . . . . . . . . . 445A

Step 2: Calculating Starting Amperes


11
Using 1.25 Multiplier
■ Motor loads: 12
❑ . . . . . . . . . . . . . . . . . . . . . . . . 195A
❑ . . . . . . . . . . . . . . . . . . . . . . . . . 98A
❑ . . . . . . . . . . . . . . . . . . . . . . . . . 60A
13
■ Lighting load . . . . . . . . . . . . . . . . 68A
■ Miscellaneous loads . . . . . . . . . . 95A 14
■ Starting amperes . . . . . . . . . . . 516A

Step 3: Selecting kVA of Generator 15


■ Running kVA =
(445A x 480V x 1.732)/
1000 = 370 kVA 16
■ Starting kVA =
(516A x 480V x 1.732)/ 17
1000 = 428 kVA
Solution
Generator must have a minimum
18
starting capability of 428 kVA and Figure 1.2-9. Typical Genset Installation
minimum running capability of 370 kVA. 19
Note: Courtesy of Caterpillar, Inc.
Also, please see section “Factors
Governing Voltage Drop” on
Page 1.3-21 for further discussion 20
on generator loading and reduced
voltage starting techniques for motors.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-10 Power Distribution Systems
August 2013
Sheet 01032

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-1
August 2013 System Analysis
Sheet 01 033

Systems Analysis The principal types of computer Short-circuit calculations define


i
programs used to provide system momentary and steady-state fault
A major consideration in the studies include: currents for LV and MV breaker and
design of a distribution system is to fuse duty and bus bracings at any
ensure that it provides the required
■ Short circuit—identify three-phase selected location in the system, and also ii
and line-to-ground fault currents determine the effect on the system
quality of service to the various
and system impedances after removal of utility power due to
loads. This includes serving each
load under normal conditions and, ■ Arc flash—calculates arc flash breaker operation or scheduled power 1
under abnormal conditions, providing energy levels, which leads to the outages. Computer software programs
the desired protection to service selection of personal protective can identify the fault current at any
and system apparatus so that equipment (PPE) bus, in every line or source connected 2
interruptions of service are minimized ■ Circuit breaker duty—identify to the faulted bus, or to it and every
consistent with good economic and asymmetrical fault current based adjacent bus, or to it and every bus
mechanical design. on X/R ratio that is one and two buses away, or 3
■ Protective device coordination— currents in every line or source in the
Under normal conditions, the impor- system. The results of these calculations
determine characteristics and set-
tant technical factors include voltage
tings of medium voltage protective permit optimizing service to the loads 4
profile, losses, load flow, effects of while properly applying distribution
relays and fuses, and entire low
motor starting, service continuity and apparatus within their intended limits.
voltage circuit breaker and fuse
reliability. The prime considerations
coordination
5
under faulted conditions are apparatus The following additional studies
protection, fault isolation and service ■ Load flow—simulate normal should be considered depending
continuity. During the system prelimi- load conditions of system upon the type and complexity of the 6
nary planning stage, before selection voltages, power factor, line distribution system, the type of facility
of the distribution apparatus, several and transformer loadings and the type of loads to be connected
distribution systems should be analyzed ■ Motor starting—identify system to the system: 7
and evaluated, including both economic voltages, motor terminal voltage,
motor accelerating torque, and ■ Harmonic analysis
and technical factors. During this stage,
if system size or complexity warrant, motor accelerating time when ■ Transient stability 8
it may be appropriate to provide a starting large motors ■ Insulation coordination
thorough review of each system under ■ Grounding study
both normal and abnormal conditions. ■ Switching transient 9
Eaton’s Electrical Services & Systems
division can provide the studies 10
enumerated above.

11

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-2 Power Distribution Systems
System Analysis August 2013
Sheet 01 034

i Short-Circuit Currents— The AC component is not constant rated secondary current. Limiting the
if rotating machines are connected power source fault capacity will thereby
General to the system because the impedance reduce the maximum fault current from
of this apparatus is not constant. The the transformer.
ii The amount of current available in a
short-circuit fault is determined by the
rapid variation of motor and generator
impedance is due to these factors: The electric network that determines
capacity of the system voltage sources the short-circuit current consists of an
1 and the impedances of the system, Subtransient reactance (x d" ), deter- AC driving voltage equal to the pre-fault
including the fault. Voltage sources mines fault current during the first system voltage and an impedance
include the power supply (utility or cycle, and after about 6 cycles this corresponding to that observed when
2 on-site generation) plus all rotating value increases to the transient reac- looking back into the system from the
machines connected to the system at tance. It is used for the calculation fault location. In medium and high
the time of the fault. A fault may be of the momentary interrupting and/or voltage work, it is generally satisfactory
3 either an arcing or bolted fault. In an momentary withstand duties of to regard reactance as the entire
arcing fault, part of the circuit voltage is equipment and/or system. impedance; resistance may be
consumed across the fault and the total neglected. However, this is normally
Transient reactance (x d' ), which deter-
4 fault current is somewhat smaller than
mines fault current after about 6 cycles
permissible only if the X/R ratio of the
for a bolted fault, so the latter is the medium voltage system is equal to or
worst condition, and therefore is the and this value in 1/2 to 2 seconds more than 25. In low voltage (1000V
increases to the value of the synchro-
5 value sought in the fault calculations.
nous reactance. It is used in the setting
and below) calculations, it is usually
worthwhile to attempt greater accuracy
Basically, the short-circuit current is of the phase OC relays of generators by including resistance with reactance
determined by applying Ohm’s Law and medium voltage circuit breakers.
6 to an equivalent circuit consisting of
in dealing with impedance. It is for this
Synchronous reactance (xd ), which reason, plus ease of manipulating the
a constant voltage source and a time- various impedances of cables and
varying impedance. A time-varying determines fault current after steady-
7 impedance is used in order to account state condition is reached. It has no buses and transformers of the low
effect as far as short-circuit calculations voltage circuits, that computer studies
for the changes in the effective voltages are recommended before final selection
of the rotating machines during the are concerned, but is useful in the
8 fault. In an AC system, the resulting determination of relay settings. of apparatus and system arrangements.
short-circuit current starts out higher Transformer impedance, in percent, is When evaluating the adequacy
in magnitude than the final steady- of short-circuit ratings of medium
9 state value and asymmetrical (due
defined as that percent of rated primary
voltage circuit breakers and fuses,
voltage that must be applied to the
to the DC offset) about the X-axis. transformer to produce rated current both the rms symmetrical value and
10 The current then decays toward a flowing in the secondary, with second- asymmetrical value of the short-circuit
lower symmetrical steady-state value. ary shorted through zero resistance. current should be determined.
The time-varying characteristic of the Therefore, assuming the primary
impedance accounts for the symmetri- For low voltage circuit breakers and
11 cal decay in current. The ratio of the
voltage can be sustained (generally fuses, the rms symmetrical value
referred to as an infinite or unlimited should be determined along with
reactive and resistive components (X/R supply), the maximum current a trans-
ratio) accounts for the DC decay, see either: the X/R ratio of the fault
12 Figure 1.3-1. The fault current consists
former can deliver to a fault condition is at the device or the asymmetrical
the quantity of (100 divided by percent short- circuit current.
of an exponentially decreasing direct- impedance) times the transformer
13 current component superimposed
upon a decaying alternating-current.
The rate of decay of both the DC and Total Current—A Wholly Offset
Asymmetrical Alternating Wave
14 AC components depends upon the
ratio of reactance to resistance (X/R) 3.0
rms Value of Total Current
of the circuit. The greater this ratio, Alternating Component -
2.5
15 the longer the current remains higher Symmetrical Wave
than the steady-state value that it rms Value of
2.0
would eventually reach. Alternating Component
16 The total fault current is not symmetrical 1.5
Scale of Curent Values

with respect to the time-axis because


of the direct-current component, 1.0
17 hence it is called asymmetrical current.
The DC component depends on the 0.5
point on the voltage wave at which 1 2 3 4
18 the fault is initiated.
0

See Table 1.3-2 for multiplying factors 0.5


19 that relate the rms asymmetrical value
of total current to the rms symmetrical –1.0
value, and the peak asymmetrical Direct Component—The Axis
20 value of total current to the rms –1.5 of Symmetrical Wave Time in Cycles of
a 60 Hz Wave
symmetrical value.
–2.0
21
Figure 1.3-1. Structure of an Asymmetrical Current Wave

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-3
August 2013 System Analysis
Sheet 01 035

Fault Current Waveform Relationships i


The following Figure 1.3-2 describes Based on a 60 Hz system and t = 1/2 cycle
the relationship between fault (ANSI/IEEE C37.13.1990/10.1.4)
current peak values, rms symmetrical – 2 π 60
----------------
ii
values and rms asymmetrical values 120 –π
Ip  ---------------- ----------
depending on the calculated X/R ratio. Peak multiplication factor = ----- = 2 1 + e X ⁄ R  = 2  1 + e
X⁄R
I    1
The table is based on the following  
general formulas:


– ωt
------------
( – 2 ) ( 2 π 60 )
-------------------------------
120 –2 π
2
1. Ip = I 2  1 + e X ⁄ R I rms asym -------------------------------
X⁄R
------------
X⁄R
  rms multiplication factor = ------------------------------ = 1 + 2e = 1 + 2e
  I 3
– 2ωt Example for X/R =15
---------------
X⁄R
2. I rms asym = I 1 + 2e –π 4
 ------- 
15 
Peak mf = 2  1 + e 
= 2.5612
Where:   5
I = Symmetrical rms current
–2 π
Ip = Peak current ----------
rms mf = 1 + 2e
15
= 1.5217 6
e = 2.718
ω=2πf 7
f = Frequency in Hz
t = Time in seconds 8

2.8
9
2.7 10
PEAK MAXIMUM ASYMMETRICAL

RMS MAXIMUM ASYMMETRICAL


Based Upon: rms Asym = DC 2 + rms Sym2
2.6 with DC Value
RMS SYMMETRICAL

Taken at Current Peak 11

RMS SYMMETRICAL
2.5

2.4 12
2.3
13
2.2 1.8
R
O
CT

14
FA

2.1 1.7
N
PEAK MULTIPLICATION FACTOR =

O
TI

RMS MULTIPLICATION FACTOR =


CA

2.0 1.6
15
LI
IP
LT

1.9 1.5
U
M

OR
AK

CT 16
PE

1.8 FA 1.4
TION
1.7 LICA 1.3
UL
TIP 17
M
1.6 RMS 1.2

1.5 1.1
18
1.4
1 1.5 2 2.5 3 4 5 6 7 8 9 10 15 20 25 30 40 50 60 70 80 90 100 19
CIRCUIT X/R RATIO (TAN PHASE)
20
Figure 1.3-2. Relation of X/R Ratio to Multiplication Factor
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-4 Power Distribution Systems
System Analysis August 2013
Sheet 01 036

i Fault Current Calculations Synchronous motors—use 5.0 times Medium Voltage Motors
motor full load current (impedance
value of 20%). If known, use actual values otherwise
The calculation of asymmetrical
use the values indicated for the same
currents is a laborious procedure since
ii the degree of asymmetry is not the
When the motor load is not known, type of motor.
the following assumptions generally
same on all three phases. It is common
practice for medium voltage systems,
are made: Calculation Methods
1 to calculate the rms symmetrical fault 208Y/120V Systems The following pages describe various
current, with the assumption being methods of calculating short-circuit
■ Assume 50% lighting and 50%
made that the DC component has currents for both medium and low
2 decayed to zero, and then apply
motor load
voltage systems. A summary of
a multiplying factor to obtain the first or the types of methods and types of
half-cycle rms asymmetrical current, calculations is as follows:
3 which is called the “momentary ■ Assume motor feedback contribu-
tion of twice full load current of ■ Medium voltage
current.” For medium voltage systems
transformer switchgear—exact
(defined by IEEE as greater than 1000V
4 up to 69,000V) the multiplying factor or
method . . . . . . . . . . . . . . Page 1.3-5
is established by NEMA® and ANSI ■ Medium voltage
standards depending upon the 240/480/600V Three-Phase, Three-Wire or switchgear—quick
5 operating speed of the breaker. For Four-Wire Systems check table . . . . . . . . . . . Page 1.3-7
low voltage systems, short-circuit ■ Assume 100% motor load ■ Medium voltage
study software usually calculates the switchgear
6 symmetrical fault current and the or Example 1—verify
faulted system X/R ratio using ANSI ratings of breakers. . . . . Page 1.3-8
■ Assume motors 25% synchronous
guidelines. If the X/R ratio is within the ■ Medium voltage
7 standard, and the breaker interrupting
and 75% induction
switchgear
current is under the symmetrical fault or Example 2—verify
value, the breaker is properly rated. ratings of breakers
8 If the X/R ratio is higher than ANSI ■ Assume motor feedback contribu- with rotating
standards, the study applies a multi- tion of four times full load current loads . . . . . . . . . . . . . . . . Page 1.3-9
plying factor to the symmetrical of transformer
9 calculated value (based on the
■ Medium voltage
480Y/277V Systems in Commercial Buildings switchgear Example 3
X/R value of the system fault) and —verify ratings of
compares that value to the breaker ■ Assume 50% induction motor load
10 symmetrical value to assess if it is
breakers with
or generators . . . . . . . . . . . Page 1.3-10
properly rated. In the past, especially
using manual calculations, a multiply- ■ Assume motor feedback contribu- ■ Medium voltage
11 ing factor of 1.17 (based on the use tion of two times full load current fuses—exact method. . . Page 1.3-11
of an X/R ratio of 6.6 representing of transformer or source ■ Power breakers—
a source short-circuit power factor asymmetry
12 of 15%) was used to calculate the derating factors . . . . . . . Page 1.3-11
asymmetrical current. These values ■ Molded-case
take into account that medium voltage breakers—asymmetry
13 breakers are rated on maximum derating factors . . . . . . . Page 1.3-12
asymmetry and low voltage breakers ■ Short-circuit
are rated average asymmetry.
14 calculations—
To determine the motor contribution short cut method
during the first half-cycle fault current, for a system . . . . . . . . . . Page 1.3-13
15 when individual motor horsepower ■ Short-circuit
load is known, the subtransient calculations—short
reactances found in the IEEE Red Book cut method for
16 should be used in the calculations. end of cable . . . . . . . . . . Page 1.3-15
When the system motor load is ■ Short-circuit
unknown, the following assumptions calculations—
17 generally are made: short cut method
for end of cable
Induction motors—use 4.0 times chart method . . . . . . . . . Page 1.3-16
18 motor full load current (impedance
■ Short-circuit currents—
value of 25%).
chart of transformers
Note: For motors fed through adjustable 300–3750 kVA . . . . . . . . . Page 1.5-9
19 frequency drives or solid-state soft starters,
there is no contribution to fault current, unless
1) they have an internal run contactor or
20 2) they have a bypass contactor.

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-5
August 2013 System Analysis
Sheet 01 037

Fault Current Calculations a voltage = maximum rated voltage


divided by K (for example, 4.76/1.24 =
current of 20,000A, the breaker is
acceptable (assumes the breaker’s i
for Specific Equipment— 3.85). If this breaker is applied in a momentary and fault close rating is
Exact Method system rated at 2.4 kV, the calculated also acceptable).
fault current must be less than 36 kA.
Note: If the system available fault current
ii
The purpose of the fault current calcu- For example, consider the following case: were 22,000A symmetrical, this breaker
lations is to determine the fault current could not be used even though the
at the location of a circuit breaker, fuse Assume a 12.47 kV system with 20,000A “Maximum Symmetrical Interrupting 1
or other fault interrupting device in symmetrical available. In order to Capability” is greater than 22,000 because
order to select a device adequate for the determine if an Eaton Type 150 VCP-W Test 1 calculation is not satisfied.
calculated fault current or to check the 500 vacuum breaker is suitable for this 2
thermal and momentary ratings of non- application, check the following: For approximate calculations, Table 1.3-1
interrupting devices. When the devices provides typical values of % reactance
to be used are ANSI-rated devices, the From Table 5.4-1B in Tab 5, Section 5.4 (X) and X/R values for various rotating 3
fault current must be calculated and the under column “Rated Maximum equipment and transformers. For sim-
device selected as per ANSI standards. Voltage” V = 15 kV, under column plification purposes, the transformer
The calculation of available fault current
“Rated short-circuit Current” I = 18 kA, impedance (Z) has been assumed to be 4
“Rated Voltage Range Factor” K = 1.3. primarily reactance (X). In addition, the
and system X/R rating is also used to resistance (R) for these simplified cal-
verify adequate bus bar bracing and Test 1 for V/Vo x I or 15 kV/12.47 kV x
momentary withstand ratings of 18 kA = 21.65; also check K x I (which culations has been ignored. For detailed 5
is shown in the column headed calculations, the values from the IEEE
devices such as contactors. Red Book Standard 141, for rotating
“Maximum Symmetrical Interrupting
Medium Voltage VCP-W Capability”) or 1.3 x 18 kA = 23.4 kA. machines, and ANSI C57 and/or C37 6
Because both of these numbers are for transformers should be used.
Metal-Clad Switchgear greater than the available system fault
The applicable ANSI Standards, C37 7
is the latest applicable edition. The Table 1.3-1. Reactance X
following is a review of the meaning System Reactance X Used for Typical Values and Range
of the ratings. (See Tab 5, Section 5.4.) Component Short-Circuit Close and Latch on Component Base 8
Duty (Momentary) % Reactance X/R Ratio
The Rated Maximum Voltage
This designates the upper limit of Two-pole turbo generator
Four-pole turbo generator
X
X
X
X
9 (7–14)
15 (12–17)
80 (40–120)
80 (40–120)
9
design and operation of a circuit
breaker. For example, a circuit breaker Hydro generator with damper wedges X X 20 (13–32) 30 (10–60)
with a 4.76 kV rated maximum voltage and synchronous condensers
10
cannot be used in a 4.8 kV system. Hydro generator without damper windings 0.75X 0.75X 16 (16–50) 30 (10–60)
All synchronous motors 1.5X 1.0X 20 (13–35) 30 (10–60)
K-Rated Voltage Factor Induction motors above 1000 hp, 1800 rpm 1.5X 1.0X 17 (15–25) 30 (15–40) 11
The rated voltage divided by this factor and above 250 hp, 3600 rpm
determines the system kV a breaker can All other induction motors 50 hp and above 3.0X 1.2X 17 (15–25) 15 (2–40)
be applied up to the short-circuit kVA Induction motors below 50 hp and Neglect Neglect — — 12
rating calculated by the formula all single-phase motors
Distribution system from remote X X As specified 15 (5–15)
3 × Rated SC Current × Rated Max. Voltage transformers or calculated 13
Note: Interrupting capabilities of some of Current limiting reactors X X As specified 80 (40–120)
today’s vacuum breakers may have K = 1, or calculated
whereby the interrupting current is constant Transformers 14
across its entire operating range. OA to 10 MVA, 69 kV X X 8.0 18 (7–24)

Rated Short-Circuit Current


OA to 10 MVA, above 69 kV X X 8.0 to 10.5
Depends on
18 (7–24)
15
FOA 12–30 MVA X X 20 (7–30)
This is the symmetrical rms value of primary
FOA 40–100 MVA X X windings BIL 38 (32–44)
current that the breaker can interrupt
at rated maximum voltage. It should
rating 16
be noted that the product 3 x 4.76 x Table 1.3-2. Typical System X/R Ratio Range (for Estimating Purposes)
29,000 = 239,092 kVA is less than the
nominal 250,000 kVA listed. This rating Type of Circuit X/R Range 17
(29,000A) is also the base quantity Remote generation through other types of circuits such as transformers rated 10 MVA 15 or less
that all the “related” capabilities are or smaller for each three-phase bank, transmission lines, distribution feeders, etc.
referred to. Remote generation connected through transformer rated 10 MVA to 100 MVA 15–40
18
for each three-phase bank, where the transformers provide 90% or more
Maximum Symmetrical Interrupting of the total equivalent impedance to the fault point
Capability Remote generation connected through transformers rated 100 MVA or larger 30–50 19
This is expressed in rms symmetrical for each three-phase bank where the transformers provide 90% or more
amperes or kiloamperes and is K x I of the total equivalent impedance to the fault point
rated; 29,000 x 1.24 = 35,960 rounded Synchronous machines connected through transformers rated 25–100 MVA 30–50 20
to 36 kA. for each three-phase bank
Synchronous machines connected through transformers rated 100 MVA and larger 40–60
This is the rms symmetrical current
that the breaker can interrupt down to
Synchronous machines connected directly to the bus or through reactors 40–120 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-6 Power Distribution Systems
System Analysis August 2013
Sheet 01 038

The Close and Latch Capability The ANSI Standard C37.010 allows the Step 3: Reduce the reactance network
i This is also a related quantity use of the X values only in determin- to an equivalent reactance. Call this
expressed in rms asymmetrical ing the E/X value of a fault current. The reactance XI.
amperes by 1.6 x maximum R values are used to determine the X/R
ii symmetrical interrupting capability. ratio, in order to apply the proper Step 4: Set up the same network for
multiplying factor, to account for the resistance values.
For example, 1.6 x 36 = 57.6 or 58 kA,
or 1.6 K x rated short-circuit current. total fault clearing time, asymmetry, Step 5: Reduce the resistance network
1 and decrement of the fault current. to an equivalent resistance. Call this
Another way of expressing the close resistance RI. The above calculations
and latch rating is in terms of the peak The steps in the calculation of fault
of XI and RI may be calculated by
2 current, which is the instantaneous currents and breaker selection are
several computer programs.
value of the current at the crest. ANSI described hereinafter:
Standard C37.09 indicates that the Step 1: Collect the X and R data of the Step 6: Calculate the E/XI value, where
3 ratio of the peak to rms asymmetrical circuit elements. Convert to a common E is the prefault value of the voltage at
value for any asymmetry of 100% to kVA and voltage base. If the reactances the point of fault nominally assumed
20% (percent asymmetry is defined as and resistances are given either in 1.0 pu.
4 the ratio of DC component of the fault ohms or per unit on a different voltage X
in per unit to 2 ) varies not more than Step 7: Determine X/R = ------I as
or kVA base, all should be changed previously calculated. RI
±2% from a ratio of 1.69. Therefore, to the same kVA and voltage base.
5 the close and latch current expressed This caution does not apply where Step 8: Go to the proper curve for
in terms of the peak amperes is = 1.6 x the base voltages are the same as the type of fault under consideration
1.69 x K x rated short-circuit current. the transformation ratio. (three-phase, phase-to-phase, phase-
6 to-ground), type of breaker at the loca-
In the calculation of faults for the pur- Step 2: Construct the sequence
poses of breaker selection, the rotating tion (2, 3, 5 or 8 cycles), and contact
networks and connect properly for parting time to determine the multi-
7 machine impedances specified in ANSI the type of fault under consideration. plier to the calculated E/XI.
Standard C37.010 Article 5.4.1 should Use the X values required by ANSI
be used. The value of the impedances Standard C37.010 for the “interrupting” See Figures 1.3-3, 1.3-4 and 1.3-5 for
8 and their X/R ratios should be obtained duty value of the short-circuit current. 5-cycle breaker multiplying factors.
from the equipment manufacturer. At Use Figure 1.3-5 if the short circuit is
initial short-circuit studies, data from fed predominantly from generators
9 manufacturers is not available. Typical removed from the fault by two or more
values of impedances and their X/R
ratios are given in Table 1.3-1.
10
130 130 130

11 120 120 120


8

7
5

110 110
12 110
4
6

12
10
5

8
6
100 100 100
4

13 4
3

90 90 90 3

14 80 80 80
TIME
Ratio X/R

Ratio X/R
Ratio X/R

TIME

70 70 70
ING

15
RT
ING

60 60 60
PA
T
PAR

16
AC

50 50 50
NT
T
AC

CO

40
NT

40 40
17
CO

30 30 30
5-CYCLE 5-CYCLE 5-CYCLE
BREAKER BREAKER BREAKER
18 20 20 20

10 10 10
19
1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4

20 Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes

Figure 1.3-3. Three-phase Fault Multiplying Figure 1.3-4. Line-to-Ground Fault Multiplying Figure 1.3-5. Three-phase and Line-to-Ground
21 Factors that Include Effects of AC and Factors that Include Effects of AC and Fault Multiplying Factors that Include Effects
DC Decrement DC Decrement of DC Decrement Only

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-7
August 2013 System Analysis
Sheet 01 039

transformations or the per unit reac- The ANSI standards do not require the Application Quick Check Table i
tance external to the generation is 1.5 inclusion of resistances in the calcula-
times or more than the subtransient tion of the required interrupting and For application of circuit breakers in a
reactance of the generation on a com- close and latch capabilities. Thus the radial system supplied from a single
mon base. Also use Figure 1.3-5 where calculated values are conservative. source transformer. Short-circuit duty ii
the fault is supplied by a utility only. However, when the capabilities of was determined using E/X amperes
existing switchgears are investigated, and 1.0 multiplying factor for X/R ratio
Step 9: Interrupting duty short-circuit the resistances should be included. of 15 or less and 1.25 multiplying 1
current = E/XI x MFx = E/X2.
factor for X/R ratios in the range of
For single line-to-ground faults, the
Step 10: Construct the sequence 15 to 40.
(positive, negative and zero) networks
symmetrical interrupting capability 2
is 1.15 x the symmetrical interrupting Application Above 3,300 ft (1,000m)
properly connected for the type of capability at any operating voltage,
fault under consideration. Use the The rated one-minute power frequency
X values required by ANSI Standard
but not to exceed the maximum withstand voltage, the impulse with- 3
symmetrical capability of the breaker. stand voltage, the continuous current
C37.010 for the “Close and Latch”
duty value of the short-circuit current. Section 5 of ANSI C37 provides rating, and the maximum voltage rating
further guidance for medium voltage must be multiplied by the appropriate 4
Step 11: Reduce the network to an breaker application. correction factors below to obtain
equivalent reactance. Call the reac- modified ratings that must equal or
tance X. Calculate E/X x 1.6 if the Reclosing Duty exceed the application requirements. 5
breaker close and latch capability is ANSI Standard C37.010 indicates the
given in rms amperes or E/X x 2.7 if Note: Intermediate values may be obtained
reduction factors to use when circuit
the breaker close and latch capability breakers are used as reclosers. Eaton
by interpolation. 6
is given in peak or crest amperes. VCP-W breakers are listed at 100% Table 1.3-3. Altitude Derating
rating factor for reclosing.
Step 12: Select a breaker whose: Altitude in Correction Factor 7
Feet (Meters) Current Voltage
a. Maximum voltage rating exceeds
the operating voltage of the system: 3300 (1006) (and below)
5000 (1524)
1.00
0.99
1.00
0.95
8
E V max 10,000 (3048) 0.96 0.80
b. ------- ≤ I × -------------- ≤ KI
X2 Vo
Table 1.3-4. Application Quick Check Table 9
See Table 6.0-1, Tab 6. Source Operating Voltage
Transformer kV
Where: MVA Rating 10
I = Rated short-circuit current Motor Load 2.4 4.16 6.6 12 13.8

Vmax = Rated maximum voltage


100% 0%
11
of the breaker 1 1.5
1.5 2 50 VCP-W 250
VD = Actual system voltage 2 2.5 12 kA 50 VCP-W 250 150 VCP-W 500 150 VCP-W 500 150 VCP-W 500 12
2.5 3 10.1 kA 23 kA 22.5 kA 19.6 kA
KI = Maximum symmetrical 3 3.75
interrupting capacity
3.75 5 50 VCP-W 250 13
c. E/X x 1.6 ≤ rms closing and 5 7.5 36 kA 50 VCP-W 250
33.2 kA
latching capability of the breaker 7.5 10 50 VCP-W 350
10  10 49 kA 14
and/or 10 12 
E/X x 2.7 ≤ Crest closing and 12 15 50 VCP-W 350 75 VCP-W 500
latching capability of the breaker. 46.9 kA 41.3 kA 15
15 20
20  20 Breaker Type and 150 VCP-W 750 150 VCP-W 750
25 symmetrical interrupting capacity 35 kA 30.4 kA 16
30 at the operating voltage

50  150 VCP-W 1000


46.3 kA
150 VCP-W 1000
40.2 kA
17
 Transformer impedance 6.5% or more, all other transformer impedances are 5.5% or more.
18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-8 Power Distribution Systems
System Analysis August 2013
Sheet 01 040

Application on Symmetrical Current Rating Basis For Three-Phase Fault


i E-
I 3-Phase = ----
Example 1—Fault Calculations X
Given a circuit breaker interrupting and momentary rating in the table below,
ii verify the adequacy of the ratings for a system without motor loads, as shown.
where X is ohms per phase and E is
the highest typical line-to-neutral
Table 1.3-5. Short-Circuit Duty operating voltage or
1 Type V Max. Three-Phase Symmetrical Interrupting Capability Close and Latch or
I
Breaker at V Max. Max. KI at 4.16 kV Oper. Voltage Momentary I 3-Phase = ----B-
X
2 50VCP–W250 4.76 kV 29 kA 36 kA 4.76
----------- (29) = 33.2 kA I1
58 kA I3
where X is per unit reactance
4.16
LG symmetrical interrupting capability IB is base current
3 — 36 kA 1.15 (33.2) = 38.2 kA I2
Base current I B = −−3.75 MVA
−−−−−−−−−−−−−−−−− = 0.52kA
Note: Interrupting capabilities I1 and I2 at operating voltage must not exceed maximum 3 ( 4.16 kV )
4 symmetrical interrupting capability Kl.
I 0.52 = 8.6 kA Sym.
Check capabilities I1, I2 and I3 on the following utility system where there is no I 3-Phase = ----1- = ----------------------
X 0.0604
5 motor contribution to short circuit.
System X
−− = 9 (is less than 15)
On 13.8 kV System, 3.75 MVA Base R
6 13.8 kV
would use 1.0 multiplying factor for
3.75 MVA- = 0.01 pu or 1%
Z = --------------------------------
375 MVA short-circuit duty, therefore, short-
X circuit duty is 8.6 kA sym. for three-
7 R
= 15
phase fault I1 and momentary duty is
2X 
2
2 2 2
Z = X + R = R  -------2- + 1 8.6 x 1.6 = 13.7 kA I3.
8
375 MVA
V R 
A
Available For Line-to-Ground Fault
Z - = ---------------
R = ---------------------- 1 - = -----------------
1 - = 0.066%
3I B
3E - = --------------------------
9 X
2 266 15.03 I LG = -------------------------- -
-------- + 1 2X 1 + X 0 2X 1 + X 0
2
R
13.8 kV For this system, X0 is the zero sequence
10 reactance of the transformer, which
3750 kVA
V X = X
----- ( R ) = 15 (0.066) = .99% is equal to the transformer positive
R sequence reactance and X1 is the posi-
11 tive sequence reactance of the system.
Transformer Standard 5.5% Impedance
has a ±7.5% Manufacturing Tolerance Therefore,
12 4.16 kV
5.50 Standard Impedance 3(0.52)
I LG = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−− = 9.1 kA Sym.
–0.41 (–7.5% Tolerance) 2(0.0604) + 0.0505
Transformer Z =
13 50VPC-W250 5.09%
Using 1.0 multiplying factor (see
Table 1.3-6), short-circuit duty = 9.1 kA
Sym. LG (I2)
14
Answer

15 The 50VCP-W250 breaker capabilities


Figure 1.3-6. Example 1—One-Line Diagram exceed the duty requirements and
From transformer losses per unit or percent may be applied.
16 R is calculated
With this application, shortcuts could
31,000 Watts Full Load have been taken for a quicker check of
24.2 kW - = 0.0065 pu or 0.65%
R = -------------------------------
17 – 6,800 Watts No Load
3750 kVA
the application. If we assume unlimited
24,200 Watts Load Losses short circuit available at 13.8 kV and
that Trans. Z = X
18 Transformer X = Z –R
2 2 2
(5.09) – (0.65) =
2
25.91 – 0.42 = 25.48 I 0.52 = 9.5 kA Sym.
Then I 3-Phase = ----B- = ------------------
X 0.055
X = 5.05%
19 X/R ratio 15 or less multiplying factor
X R X/R is 1.0 for short-circuit duty.
20 13.8 kV System 0.99% 0.066% 15 The short-circuit duty is then 9.5 kA
Transformer 5.05% 0.65% 8 Sym. (I1, I2) and momentary duty is
System Total 6.04% 0.716% 9 9.5 x 1.6 kA = 15.2 kA (I3).
21 or 0.0604 pu 0.00716 pu

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-9
August 2013 System Analysis
Sheet 01 041

Example 2—Fault Calculations


Given the system shown with motor 13.8 kV System i
loads, calculate the fault currents X = 15
and determine proper circuit breaker 21 kA Sym. Available
selection.
13.8 kV R ii
X = 5.5% X
All calculations on per unit basis. 7500 kVA Z = 5.53% = 10
R = 0.55% R
7.5 MVA base 1
7.5 MVA- = 0.628 kA
Base Current I B = ------------------------------ 6.9 kV
3 6.9 kV 1 2
X R X/R
13.8 kV System 3
X = 0.628 (6.9) = 0.015 0.015 0.001 15 X X
21 (13.8) = 25 = 35
Transformer 0.055 0.0055 10 2 R 3
R 4
197A FL 173A FL
Total Source Transformer 0.070 pu 0.0065 pu 11 X''d = 20% X''d = 25%

3000 hp Synchronous Motor


5
X = 0.20 (0.628) = 0.638 pu at 7.5 MVA Base 3000 hp
0.197 1.0 PF 2500 hp
Ind.
6
Syn.
2500 hp Ind. Motor
7
X = 0.25 (0.628) = 0.908 pu at 7.5 MVA Base Figure 1.3-7. Example 2—One-Line Diagram
0.173

E- = I----B- where X on per unit base Source of Interrupting Momentary X X (1) 1 8


I 3-Ph = ---- Short-Circuit Current E/X Amperes E/X Amperes R R (X) R
X X
I3 Source Transformer 0.628 0.628 11 11 = 157
= 8.971 = 8.971
Table 1.3-6. Multiplying Factor for E/X 0.070 0.070 0.070 9
Amperes (ANSI C37.010, 1979, Figures 1.1-8, I1 3000 hp Syn. Motor 0.628 0.628 25 = 39
= 0.656 = 0.984 25
1.1-9 and 1.1-10) (1.5) 0.638 0.638 0.638

System Type VCP-W Vacuum I1 2500 hp Syn. Motor 0.628


= 0.461
0.628
= 0.691 35 35 = 39
10
X/R Circuit Breaker (1.5) 0.908 0.908 0.908
Rated Interrupting Time, 5-Cycle I3F = 10.088 10.647 Total 1/R = 235
Type of Fault or 10.1 kA x 1.6 11
17.0 kA Momentary Duty
Ratio Three- LG Three-Phase
Phase and LG
Source of Short Circuit
I B = 0.628 = 0.062
Total X = -------
- ------------------
12
I 3F 10.1
Local Remote

1 1.00 1.00 1.00


System X
----- = 0.062 (235) = 14.5 is a Multiplying Factor of 1.0 from Table 1.3-6
13
15  1.00 1.00 1.00 R
20 1.00 1.02 1.05
25
30
1.00
1.04
1.06
1.10
1.10
1.13
Table 1.3-7. Short-Circuit Duty = 10.1 kA 14
36 1.06 1.14 1.17 Breaker V Three-Phase Symmetrical Interrupting Capability Close and Latch
Type Max. or Momentary
40
45
1.08
1.12
1.16
1.19
1.22
1.25
at V Max. Max. KI at 6.9 kV Oper. Voltage
15
50 1.13 1.22 1.27 75VCP-W500 8.25 kV 33 kA 41 kA 8.25 (33) = 39.5 kA 66 kA
55 1.14 1.25 1.30 6.9
60 1.16 1.26 1.32 150VCP-W500 15 kV 18 kA 23 kA 15 (18) (39.1) = 23 kA 37 kA 16
65 1.17 1.28 1.33 6.9
70 1.19 1.29 1.35 (But not to exceed KI)
75 1.20 1.30 1.36 17
80 1.21 1.31 1.37 Answer
85 — — 1.38
Either breaker could be properly
90
95
1.22

1.32

1.39
1.40 applied, but price will make the type 18
100 1.23 1.33 1.41 150VCP-W500 the more economical
selection.
100
120
1.24
1.24
1.34
1.35
1.42
1.43
19
130 1.24 1.35 1.43
 Where system X/R ratio is 15 or less, the
multiplying factor is 1.0.
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-10 Power Distribution Systems
System Analysis August 2013
Sheet 01 042

Example 3—Fault Calculations Answer


i Check breaker application or generator bus for the system of generators shown. The 50VCP-W250 breaker could be
Each generator is 7.5 MVA, 4.16 kV 1040A full load, IB = 1.04 kA applied.
ii Sub transient reactance Xd” = 11% or, X = 0.11 pu
X- ratio is 30
1 Gen ----
R

2 1 1 1 1 3 1 1 1 1 3
−−−− = −− + −− + −− = −− and −−− = −− + −− + −− = −−
XS X X X X RS R R R R

3 XS = X
G1 G2 G3
or X S = X R
----- and R S = ---- Therefore, System --------
X- = 30
----- = Gen ----
3 3 RS R R
4
Since generator neutral grounding reactors are used to limit the I LG to I3-phase or
below, we need only check the I3 short-circuit duty.
5
I I I 31
I B Phase = ----B- + ----B- + ----B- + ----------B- = 3(1.04)
4.16 kV
----------------------- = 28.4 kA Symmetrical E/X amperes
X X X X 0.11
6
System X
----- of 30 is a Multiplying Factor of 1.04 from Table 1.3-6.
7 R
Short-circuit duty is 28.4 (1.04) = 29.5 kA Symmetrical
8 Three-Phase Symmetrical Interrupting Capability Figure 1.3-8. Example 3—One-Line Diagram
Breaker Type V Max. at V Max. Max. KI at 4.16 kV Oper. Voltage
50VCP-W250 4.76 kV 29 kA 36 kA 4.76
9 4.16
(29) = 33.2 kA

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-11
August 2013 System Analysis
Sheet 01 043

Medium Voltage Fuses— Step 4—Construct the sequence includes induction and synchronous
motor loads. The assumption is made i
networks using resistances and
Fault Calculations connect properly for the type of that in 208Y/120V systems the contri-
fault under consideration and reduce bution from motors is two times the full
There are two basic types of medium to a single equivalent resistance. load current of step-down transformer. ii
voltage fuses. The following definitions This corresponds to an assumed 50%
are taken from ANSI Standard C37.40. Step 5—Calculate the E/XI value, motor aggregate impedance on a kVA
Expulsion Fuse (Unit)
where E is the prefault value of the base equal to the transformer kVA 1
voltage at the point of fault normally rating or 50% motor load. For 480V,
A vented fuse (unit) in which the assumed 1.0 in pu. For three-phase 480Y/277V and 600V systems, the
expulsion effect of the gases produced faults E/XI is the fault current to be assumption is made that the contribution 2
by internal arcing, either alone or aided used in determining the required inter- from the motors is four times the full
by other mechanisms, results in current rupting capability of the fuse. load current of the step-down trans-
interruption. former, which corresponds to an assumed 3
Note: It is not necessary to calculate a
Current-Limiting Fuse (Unit) single phase-to-phase fault current. This 25% aggregate motor impedance on a
current is very nearly 3 /2 x three-phase kVA base equal to the transformer kVA
A fuse unit that, when its current-
responsive element is melted by a
fault. The line-to-ground fault may exceed rating or 100% motor load. 4
the three-phase fault for fuses located in
current within the fuse’s specified generating stations with solidly grounded In low voltage systems that contain
current-limiting range, abruptly neutral generators, or in delta-wye trans- generators, the subtransient reactance 5
introduces a high resistance to formers with the wye solidly grounded, should be used.
reduce current magnitude and where the sum of the positive and negative
duration, resulting in subsequent sequence impedances on the high voltage If the X/R to the point of fault is greater
current interruption. side (delta) is smaller than the impedance of than 6.6, a derating multiplying factor 6
the transformer. (MF) must be applied. The X/R ratio is
There are two classes of fuses; calculated in the same manner as that
power and distribution. They are For single line-to-ground fault: for medium voltage circuit breakers. 7
distinguished from each other by X I = X I (+) + X I (–) + X I (0) Calculated symmetrical amperes x
the current ratings and minimum
MF ≤ breaker interrupting rating. 8
melting type characteristics.
E ×3
I f = ------ The multiplying factor MF can be
The current-limiting ability of a XI calculated by the formula:
current-limiting fuse is specified by 9
its threshold ratio, peak let-through – ( π ) ⁄ ( X/R )
current and I2t characteristics.
Step 6—Select a fuse whose 2 [ 1 + 2.718 ]
published interrupting rating MF = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
Interrupting Ratings of Fuses exceeds the calculated fault current.
2.29 10
If the X/R of system feeding the
Modern fuses are rated in amperes Figure 1.3-2 should be used where breaker is not known, use X/R = 15.
rms symmetrical. They also have a older fuses asymmetrically rated are 11
listed asymmetrical rms rating that involved. For fused breakers by the formula:
is 1.6 x the symmetrical rating.
The voltage rating of power fuses used
1 + 2 × ( 2.718 )
– ( 2π ) ⁄ ( X/R ) 12
Refer to ANSI/IEEE C37.48 for fuse on three-phase systems should equal MF = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
interrupting duty guidelines. or exceed the maximum line-to-line 1.25

Calculation of the Fuse Required


voltage rating of the system. Current If the X/R of the system feeding the 13
limiting fuses for three-phase systems breaker is not known, use X/R = 20.
Interrupting Rating: should be so applied that the fuse
Step 1—Convert the fault from Refer to Table 1.3-8 for the standard
the utility to percent or per unit on
voltage rating is equal to or less than
ranges of X/R and power factors used in
14
1.41 x nominal system voltage.
a convenient voltage and kVA base. testing and rating low voltage breakers.
Refer to Table 1.3-9 for the circuit 15
Step 2—Collect the X and R data of all Low Voltage Power Circuit breaker interrupting rating multiplying
the other circuit elements and convert
to a percent or per unit on a conve- Breakers—Fault Calculations factors to be used when the calculated
X/R ratio or power factor at the point 16
nient kVA and voltage base same as The steps for calculating the fault cur- the breaker is to be applied in the
that used in Step 1. Use the substran- rent for the selection of a low voltage power distribution system falls outside
sient X and R for all generators and of the Table 1.3-8 X/R or power factors
motors.
power circuit breaker are the same as
those used for medium voltage circuit used in testing and rating the circuit
17
Step 3—Construct the sequence breakers except that where the con- breakers. MF is always greater than 1.0.
networks using reactances and connect nected loads to the low voltage bus 18
properly for the type of fault under
consideration and reduce to a single
equivalent reactance. 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-12 Power Distribution Systems
System Analysis August 2013
Sheet 01 044

i Molded-Case Breakers and Low Voltage Circuit Breaker


Insulated Case Circuit Interrupting Derating Factors
ii Breakers—Fault Calculations Refer to Table 1.3-8 for the standard Established standard values include
ranges of X/R and power factors used the following:
The method of fault calculation is the
in testing and rating low voltage
same as that for low voltage power Table 1.3-8. Standard Test Power Factors
1 circuit breakers. Again, the calculated
breakers. Refer to Table 1.3-9 for
the circuit breaker interrupting rating Interrupting Power Factor X/R Test
fault current x MF ≤ breaker interrupting Rating in kA Test Range Range
de-rating factors to be used when the
capacity. Because molded case breakers
2 are tested at lower X/R ratios, the MFs
calculated X/R ratio or power factor Molded Case Circuit Breaker
at the point the breaker is to be applied 10 or Less 0.45–0.50 1.98–1.73
are different than those for low voltage
in the power distribution system falls Over 10 to 20 0.25–0.030 3.87–3.18
power circuit breakers. Over 20 0.15–0.20 6.6–4.9
3 outside of the Table 1.3-8 X/R or power
factors used in testing and rating the Low Voltage Power Circuit Breaker
– π ⁄ −
X 2

1 + 2.718  R 2 circuit breakers. All 0.15 Maximum 6.6 Minimum
4 MF = ----------------------------------------------------
Normally the short-circuit power factor
– π ⁄ −
X 1
− For distribution systems where the
1 + 2.718  R 1 or X/R ratio of a distribution system
calculated short-circuit current X/R
need not be considered in applying
5 X1 ⁄ R1 = test X/R value low voltage circuit breakers. This is
ratio differs from the standard values
given in the above table, circuit breaker
because the ratings established in
interrupting rating derating factors from
the applicable standard are based
6 X2 ⁄ R2 = X/R at point where breaker Table 1.3-9 table should be applied.
is applied on power factor values that amply
cover most applications.
7
Table 1.3-9. Circuit Breaker Interrupting Rating Derating Factors
% P.F. X/R Interrupting Rating
8 Molded Case or Insulated Case Power Circuit Breaker
>10 kA
< / = 10 kA < / = 20 kA >20 kA Unfused Fused
9
50 1.73 1.000 1.000 1.000 1.000 1.000
30 3.18 0.847 1.000 1.000 1.000 1.000
10 25 3.87 0.805 0.950 1.000 1.000 1.000
20 4.90 0.762 0.899 1.000 1.000 1.000
15 6.59 0.718 0.847 0.942 1.000 0.939
12 8.27 0.691 0.815 0.907 0.962 0.898
11 10 9.95 0.673 0.794 0.883 0.937 0.870
8.5 11.72 0.659 0.778 0.865 0.918 0.849
7 14.25 0.645 0.761 0.847 0.899 0.827
12 5 19.97 0.627 0.740 0.823 0.874 0.797

Note: These are derating factors applied to the breaker and are the inverse of MF.
13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-13
August 2013 System Analysis
Sheet 01 045

Short-Circuit Calculations—Shortcut Method i


Determination of Short-Circuit Current
Note 1: Transformer impedance generally relates to self-ventilated rating (e.g., with OA/FA/FOA transformer use OA base). ii
Note 2: kV refers to line-to-line voltage in kilovolts.
Note 3: Z refers to line-to-neutral impedance of system to fault where R + jX = Z.
Note 4: When totaling the components of system Z, arithmetic combining of impedances as “ohms Z”. “per unit Z”. etc., is considered a 1
shortcut or approximate method; proper combining of impedances (e.g., source, cables transformers, conductors, etc.). should use
individual R and X components. This Total Z = Total R + j Total X (see IEEE “Red Book” Standard No. 141).

1. Select convenient kVA base for system to


2
be studied.
kVA base 2
(a) Per unit = pu impedance kVA base 2 = −−−−−−−−−−−−−−− × (pu impedance on kVA base 1)
2. Change per unit, or percent, impedance from
one kVA base to another:
kVA base 1 3
kVA base 2
(b) Percent = % impedance kVA base 2 = −−−−−−−−−−−−−−− × (% impedance on kVA base 1)
kVA base 1
(ohms impedance) (kVA base)
4
3. Change ohms, or percent or per unit, etc.: (a) Per unit impedance = pu Z = percent −−−−−−−−−−−−−− = −−−−−−−−−−(−kV
−−−−−−−−−−−−impedance −−−−−2−−−−−−−−−− −−−−−−−−−−−−−−
) ( 1000 )
100

(b) % impedance = % Z =
(ohms impedance) (kVA base)
−−−−−−−−−−−−−−−−2−−−−−−−−−− −−−−−−−−−−−−−−
( kV ) ( 10 )
5
(% impedance) ( kV )2
(c) Ohms impedance = −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−(10)
−−−−
kVA base 6
4. Change power-source impedance to per unit (a) —if utility fault capacity given in kVA
or percent impedance on kVA base as selected
for this study: kVA base in study
7
Per-unit impedance = pu Z = ------------------------------------------------------------------------------------------
-
power-source kVA fault capacity

(b) —if utility fault capacity given in rms symmetrical short circuit amperes 8
kVA base in study
Per-unit impedance = pu Z = ---------------------------------------------------------------------------------------------------------------
-
(short-circuit current) ( 3 )(kV of source) 9
5. Change motor rating to kVA: (a) —motor kVA — ( 3 ) (kV) (I) where I = motor nameplate full-load amperes
(b) —if 1.0 power factor synchronous motor kVA = (0.8) (hp)
10
(c) —if 0.8 power factor synchronous motor kVA = (1.0) (hp)
(d) —if induction motor kVA = (1.0) (hp)

Three-phase kVA Single-phase kVA


11
6. Determine symmetrical short-circuit current: (a) Base current = I Base = −−−−−−−−−−−−−−−−−−−−−−− or −−−−−−−−−−−−−−−−−−−−−−−−
( 3 ) ( kV ) kV line-to-neutral
1.0
(b) Per unit I SC = −−−−− 12
puZ

(c) rms Symmetrical current = ISC = (pu ISC) (IBase Amperes)


13
Three-phase KVA base Single-phase kVA base
(d) rms Symmetrical current = Amperes = ---------------------------------------------------------------- or -----------------------------------------------------------------
( puZ ) ( 3 ) ( kV ) ( puZ ) ( kV )
(Three-phase kVA base) (100) Single-phase kVA base (100)
14
(e) = ----------------------------------------------------------------------------------- or --------------------------------------------------------------------------------
(%Z) ( 3 ) ( kV ) (%Z) ( kV )

(g)
(kV) (1000)
= ----------------------------------- 15
3 (ohms Z)

(a) Symmetrical short-circuit kVA = kVA base (kVA base) (100) ( kV )2 ( 1000 )
-------------------------- = ---------------------------------------------- = ----------------------------------
7. Determine symmetrical short-circuit kVA: ( puZ ) %Z ohms Z 16
3(line-to-neutral kV) 2 ( 1000 )
(b) = -----------------------------------------------------------------------------
(ohms Z)
17
8. Determine line-to-line short-circuit current: (a) —from three-phase transformer—approx. 86% of three-phase current
(b) —three single-phase transformers (e.g., 75 kVA, Z = 2%) calculate same as one three-phase
unit (i.e., 3 x 75 kVA = 225 kVA, Z = 2%). 18
(c) —from single-phase transformer—see Page 1.3-15.

19
9. Determine motor contribution (or feedback) as
source of fault current:
(a) —synchronous motor—5 times motor full load current (impedance 20%)
(b) —induction motor—4 times motor full-load current (impedance 25%)
See IEEE
Standard No. 141 
(c) —motor loads not individually identified, use contribution from group of motors as follows:
—on 208Y/120V systems—2.0 times transformer full-load current 20
—on 240-480-600V three-phase, three-wire systems—4.0 times transformer full-load current
—on 480Y/277V three-phase, four-wire systems
—In commercial buildings, 2.0 times transformers full-load current (50% motor load)
—In industrial plants, 4.0 times transformer full-load current (100% motor load) 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-14 Power Distribution Systems
System Analysis August 2013
Sheet 01 046

Example Number 1
i
How to Calculate Short-Circuit Currents at Ends of Conductors
ii A. System Diagram B. Impedance Diagram (Using “Short Cut” Method for Combining Impedances
and Sources).
1 A B C
Utility Source 500 MVA
Major Contribution
Utility
2
Cables
Transformer
3 1000 kV A
Switchboard Fault
5.75%
480V Cables
4
Cable Fault
Switchboard Fault

5 0.002 pu 1.00 pu 1.00 pu 1.00 pu


100 ft (30m)
3–350 kcmil Cable
6 A B C
in Steel Conduit
0.0575 pu 0.027 pu 0.027 pu 0.027 pu
Switchboard Fault
Mixed Load—Motors and Lighting
7 Each Feeder—100 ft (30m) of 3–350 kcmil
0.027 pu
Cable in Steel Conduit Feeding Lighting and
250 kVA of Motors
Cable Fault
8 Cable Fault
Combining Series Impedances: ZTOTAL = Z1 + Z2 + ... +Zn

9 C. Conductor impedance from Table 1.5-16, Combining Parallel Impedances:


1 = 1 + 1 + ... 1
ZTOTAL Z1 Z2 Zn
Page 1.5-14. Conductors: 3–350 kcmil copper,
single conductors Circuit length: 100 ft (30m),
10 in steel (magnetic) conduit Impedance
0.0595 pu 0.342 pu 0.0507 pu
Z = 0.00619 ohms/100 ft (30m).
ZTOT = 0.00619 ohms (100 circuit feet) E 0.0777 pu
11 0.027 pu 0.027 pu
D. Fault current calculations (combining imped-
ances arithmetically, using approximate
12 “Short Cut” method—see Note 4,
Page 1.3-13)

13 Equation
Step (See) Calculation
1 – Select 1000 kVA as most convenient base, since all data except utility source is on
secondary of 1000 kVA transformer.
14
2 4(a) kVA base
Utility per unit impedance = Z pu = ------------------------------------------ 1000
- = --------------------- = 0.002 pu
utility fault kVA 500.000
15 %Z = 5.75 = 0.0575 pu
3 3(a) Transformer per unit impedance = Z pu = ---------
- -----------
100 100

16 4 4(a) and kVA base


Motor contribution per unit impedance = Z pu = --------------------------------------- 1000
- = -------------------- = 1.00 pu
9(c) 4 x motor kVA 4 x 250

17 5 3(a) Cable impedance in ohms (see above) = 0.00619 ohms


(ohms)(kVA base) = (0.00619)(1000) = 0.027pu
Cable impedance per unit = Z pu = -------------------------------------------------
- -------------------------------------------
2 2
(kV) (1000) (0.480) (1000)
18
6 6(d) Total impedance to switchboard fault = 0.0507 pu (see diagram above)

19 Symmetrical short circuit current at switchboard fault = 3-phase


−−−−−−−−−−−−−−−−−−−−−−−− −−−−−−−−−−−1000
kVA base =
−−−−−−−−−−−−−−−− = 23,720 amperes rms
( Z pu ) ( 3 ) ( kV ) ( 0.0507 ) ( 3 ) ( 0.480 )

7 6(d) Total impedance to cable fault = 0.0777 pu (see diagram above)


20
Symmetrical short circuit current at cable fault = 3-phase kVA base =
−−−−−−−−−−−−−−−−−−−−−−−− −−−−−−−−−−−1000
−−−−−−−−−−−−−−−− = 15, 480 amperes rms
( Z pu ) ( 3 ) ( kV ) ( 0.0777 ) ( 3 ) ( 0.480 )
21
Figure 1.3-9. Example Number 1

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-15
August 2013 System Analysis
Sheet 01 047

Example Number 2
i
Fault Calculation—Secondary Side of Single-Phase Transformer

A. System Diagram Deriving Transformer R and X:


ii
480V Three-Phase Switchboard Bus at 50,000A Symmetrical, X/R = 6.6 { RX == 0.1498 Z
0.9887 Z
X
− = 6.6 X = 6.6 R
R 1
2 2 2 2 2 2 2
Z= X +R = ( 6.6R ) + R = 43.56R + R = 44.56R = 6.6753R
100 Ft. Two #2/0 Copper Conductors, Magnetic Conduit R = 0.0104 Ohms
{
X = 0.0051 Ohms 2
R= −−−−Z−−−− R = 0.1498Z
6.6753
75 kVA Single-Phase 480-120/240V; Z = 2.8%, R = 1.64%, X = 2.27%
X = 6.6R X = 0.9887Z 3
120V
F2 Half-winding of Transformer
{ Multiply % R by 1.5
Multiply % X by 1.2 } Reference: IEEE Standard No. 141 4
240V
F1 Full-winding of Transformer

B. Impedance Diagram—Fault F1 C. Impedance Diagram—Fault F2 5

RSyst = 0.00054 RSyst = 0.00356 RSyst = 0.00054 XSyst = 0.00356 6


RCond = 0.00677 RCond = 0.00332 RCond = 0.00677 XCond = 0.00332

RTfmr = 0.0164 RTfmr = 0.0227 RTfmr = 0.0246 XTfmr = 0.0272 7


RTotal = 0.02371 RTotal = 0.02958 RTotal = 0.03191 XTotal = 0.03408
F1 F1 F2 F2
8
D. Impedance and Fault Current Calculations—75 kVA Base
Note: To account for the outgoing and return paths of single-phase circuits (conductors,
systems, etc.) use twice the three-phase values of R and X. 9
75
ZSyst = −−−−−−−−−−−−−−−−−−−−−−−−−−− = 0.0018 pu (From Page 1.3-13 RSyst = 2 (0.1498 x Z) = 0.00054 pu
3 × 0.480 × 50,000 Formula 4(b) )
XSyst = 2 (0.9887 x Z) = 0.00356 pu 10
×−−kVA 0.0104 × 75
RCond = 2  −−−−−−2−−−−−−−−−−−
ohms Base
ZCond = −−−−−−−−−−− −−−−−−−−−−−− (From Page 1.3-13 = 0.00677 pu
( kV ) × 1000
2  0.48 × 1000
Formula 3(a) )
0.0051 × 75 
11
XCond = 2  −−−−−−−−− −−−−−−−−−− = 0.00332 pu
 ( 0.48 ) 2 × 1000
Full-winding of Transformer (75 kVA Base)
1.64
RTfmr = −−−−− = 0.0164 pu 12
100
2.27
XTfmr = −−−−− = 0.0277 pu
100 13
1.64
Half-winding of Transformer (75 kVA Base) RTfmr = 1.5 ( −−−−− ) = 0.0246 pu
100
14
XTfmr = 1.2 ( 2.27
−−−−− ) = 0.0272 pu
100

Impedance to Fault F1—Full Winding Z= 2


( 0.02371 ) + ( 0.02958 )
2 = 0.03791 pu 15
Impedance to Fault F2—Half Winding
Z= 2 2 = 0.04669 pu
Short circuit current F1 = 75 ÷ (0.03791 x 0.240 kV) = 8,243A Symmetrical ( 0.03191 ) + ( 0.03408 )
Short circuit current F2 = 75 ÷ (0.04669 x 0.120 kV) = 13,386A Symmetrical 16
Figure 1.3-10. Example Number 2
17
Method 1: Shortcut Methods— at the load side end of the conductors Add source and conductor impedance or
can be calculated as follows. 0.00923 + 0.00273 = 0.01196 total ohms
End of Cable
This method uses the approximation 277V/30,000A = 0.00923 ohms (source Next, 277V/0.01196 ohms = 23,160A 18
of adding Zs instead of the accurate impedance) rms at load side of conductors
method of Rs and Xs. Conductor ohms for 500 kcmil conductor 19
from reference data in this section in X 30,000A available
For Example: For a 480/277V system
with 30,000A symmetrical available magnetic conduit is 0.00551 ohms per 100 ft (30m)
at the line side of a conductor run of 100 ft (30m). For 100 ft (30m) and two 2–500 kcmil per phase 20
100 ft (30m) of 2–500 kcmil per phase conductors per phase we have:
X If = 23,160A
and neutral, the approximate fault current 0.00551/2 = 0.00273 ohms (conductor
impedance)
21
Figure 1.3-11. Short-Circuit Diagram

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-16 Power Distribution Systems
System Analysis August 2013
Sheet 01 048

Method 2: Chart Approximate Method Step Five


i The chart method is based on the following: Enter the chart along the bottom horizontal scale with the
distance (in feet) from the transformer to the fault point.
Motor Contribution Draw a vertical line up the chart to the point where it inter-
ii For system voltages of 120/208V, it is reasonable to assume sects the selected curve. Then draw a horizontal line to the
that the connected load consists of 50% motor load, and that left from this point to the scale along the left side of the chart.
the motors will contribute four times their full load current
1 into a fault. For system voltages of 240 and 480V, it is rea- Step Six
sonable to assume that the connected load consists of 100% The value obtained from the left-hand vertical scale is the fault
motor load, and that the motors will contribute four times current (in thousands of amperes) available at the fault point.
2 their full load current into a fault. These motor contributions
have been factored into each curve as if all motors were For a more exact determination, see the formula method.
connected to the transformer terminals. It should be noted that even the most exact methods for
3 calculating fault energy use some approximations and some
Feeder Conductors assumptions. Therefore, it is appropriate to select a method
The conductor sizes most commonly used for feeders which is sufficiently accurate for the purpose, but not more
4 from molded case circuit breakers are shown. For conductor burdensome than is justified. The charts that follow make
sizes not shown, the following table has been included for use of simplifications that are reasonable under most cir-
conversion to equivalent arrangements. In some cases it cumstances and will almost certainly yield answers that are
5 may be necessary to interpolate for unusual feeder ratings. on the safe side. This may, in some cases, lead to application
Table 1.3-10 is based on using copper conductor. of circuit breakers having interrupting ratings higher than
necessary, but should eliminate the possibility of applying
Table 1.3-10. Conductor Conversion (Based on Using Copper Conductor)
6 units which will not be safe for the possible fault duty.
If Your Conductor is: Use Equivalent Arrangement

3–No. 4/0 cables 2–500 kcmil


7 4–No. 2/0 cables 2–500 kcmil
UTILITY KVA
V
3–2000 kcmil cables 4–750 kcmil
5–400 kcmil cables 4–750 kcmil
8 6–300 kcmil cables 4–750 kcmil
800A busway 2–500 kcmil 12.5
1000A busway 2–500 kcmil
9 1600A busway 4–750 kcmil
10.0

Short-Circuit Current Readout 250 kcmil


W
WG
10 The readout obtained from the charts is the rms symmetrical
7.5 W
WG

amperes available at the given distance from the trans-


5.0
former. The circuit breaker should have an interrupting
11 capacity at least as large as this value.
2.5
How to Use the Short-Circuit Charts
12
Step One 0
0 2 5 10 20 50 100 200 500 1000 2000 5000
Obtain the following data: Distance in Feet from T
13
1. System voltage Figure 1.3-12. 225 kVA Transformer/4.5% Impedance/208V
2. Transformer kVA rating (from transformer nameplate)
14 3. Transformer impedance (from transformer nameplate)
4. Primary source fault energy available in kVA KV
15 (from electric utility or distribution system engineers)
Fault Current in Thousands of Amperes (Sym.)

30
kcmil
Step Two
25
Select the applicable chart from the following pages. The
16 charts are grouped by secondary system voltage, which is #4 A F 50,000

listed with each transformer. Within each group, the chart 20 B


for the lowest kVA transformer is shown first, followed in
17 ascending order to the highest rated transformer.
F

15

Step Three
18 Select the family of curves that is closest to the “available 10
source kVA.” The black line family of curves is for a source of
500,000 kVA. The lower value line (in red) family of curves is
19 for a source of 50,000 kVA. You may interpolate between
5

curves if necessary, but for values above 100,000 kVA it is


appropriate to use the 500,000 kVA curves. 0
20 Step Four
0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000

Select the specific curve for the conductor size being used. If Figure 1.3-13. 300 kVA Transformer/4.5% Impedance/208V
21 your conductor size is something other than the sizes shown
on the chart, refer to the conductor conversion Table 1.3-10.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-17
August 2013 System Analysis
Sheet 01 049

B i
KV A
Fault Current in Thousands of Amperes (Sym.)

30 120
F
ii
25 100
F 50,000
W
WG

20 80 B
1

15 60 F 2
4
2
10 40
3
5 20 #4 AWG
A

4
0 0
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T
5
Figure 1.3-14. 500 kVA Transformer/4.5% Impedance/208V Figure 1.3-17. 1500 kVA Transformer/5.5% Impedance/208V
6
A A
7
Fault Current in Thousands of Amperes (Sym.)

60 120 –

– B
50 100 W
WG

W
WG
F 50,000 F 50,000 8
40 B 80

F
F 9
30 60

20 40
10
4– kcmil

10 20 11
0 0
0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000
12
Figure 1.3-15. 750 kVA Transformer/5.5% Impedance/208V Figure 1.3-18. 2000 kVA Transformer/5.5% Impedance/208V
13

kcmil A A
14
kcmil
Fault Current in Thousands of Amperes (Sym.)

Fault Current in Thousands of Amperes (Sym.)

60 12

50
B
10
15
F 50,000 B F 50,000
F
40 8 16
30 6 4
2 17
20 W
WG 4

18
10 2

0 0
19
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T

Figure 1.3-16. 1000 kVA Transformer/5.5% Impedance/208V Figure 1.3-19. 300 kVA Transformer/4.5% Impedance/480V
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-18 Power Distribution Systems
System Analysis August 2013
Sheet 01 050

i
A A
Fault Current in Thousands of Amperes (Sym.)

Fault Current in Thousands of Amperes (Sym.)


30 60
ii
25 50 kcmil
F 50,000 F 50,000
1 20 40
#4 AWG
A
– B

2 15 B #1/0 AWG
#4 A
A
AWG
30
F

10 20
3 4 750 kcmil

5 10

4
0 0
0 2 5 10 20 50 100 200 500 1000 2000 5000 0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T Distance in Feet from T
5
Figure 1.3-20. 500 kVA Transformer/4.5% Impedance/480V Figure 1.3-23. 1500 kVA Transformer/5.5% Impedance/480V
6
A A
7
Fault Current in Thousands of Amperes (Sym.)

Fault Current in Thousands of Amperes (Sym.)

30 60 4– kcmil

750
25 50 B W
WG
8 500
F 50,000 F 50,000

20 B 40

9 F
F
15 30

10 10
4– kcmil
20

#4 A
11 5 10

0 0
12 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000 0 2 5 10 20
Distance in Feet from T
50 100 200 500 1000 2000 5000

Figure 1.3-21. 750 kVA Transformer/5.5% Impedance/480V Figure 1.3-24. 2000 kVA Transformer/5.5% Impedance/480V
13

14 A
Fault Current in Thousands of Amperes (Sym.)

30
W
WG
15 25
B

F 50,000

F
16 20

15
17 4 – 750 kcmil
2

10

18
5

19 0
0 2 5 10 20 50 100 200 500 1000 2000 5000
Distance in Feet from T

20 Figure 1.3-22. 1000 kVA Transformer/5.5% Impedance/480V

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-19
August 2013 System Analysis
Sheet 01 051

Determining X and R Values How to Estimate Short-Circuit Method 2:


i
Currents at Transformer Refer to Page 1.5-9 in the Reference
from Transformer Loss Data section, and use appropriate row of
Secondaries: data based on transformer kVA and
Method 1: ii
primary short-circuit current available.
Given a 500 kVA, 5.5% Z transformer Method 1:
This will yield more accurate results
with 9000W total loss; 1700W no-load To obtain three-phase rms symmetrical and allow for including motor short-
loss; 7300W load loss and primary short-circuit current available at circuit contribution. 1
voltage of 480V. transformer secondary terminals,
use the formula:
3 ×  −−−−−−500
2
−−−−−−−−−−− × R = 7300W
2
 3 × 0.480 I SC 100
= I FLC × ------------
%Z
%R = 0.0067 ohms 3
where %Z is the transformer impedance
0.0067 × 500 in percent, from Tables 1.5-6 through
%R = −−−−−−−−−−−−−−−−−−2−− = 1.46%
10 × 0.48
1.5-10, Page 1.5-11. 4
This is the maximum three-phase sym-
2 2
%X = 5.5 – 1.46 = 5.30% metrical bolted-fault current, assuming
sustained primary voltage during fault, 5
Method 2: i.e., an infinite or unlimited primary
Using same values above. power source (zero source impedance).
Because the power source must 6
2
I R Losses always have some impedance, this
%R = −−−−−−−−−−−−−−−−−
10 × kVA is a conservative value; actual fault
7
current will be somewhat less.
7300
−−−−−−−−−−−−− = 1.46 Note: This will not include motor short-
10 × 500
circuit contribution. 8
2 2
%X = 5.5 – 1.46 = 5.30%
9

10

11

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-20 Power Distribution Systems
System Analysis August 2013
Sheet 01 052

Voltage Drop Considerations Computer Equipment: With the Motor Starting


i The first consideration for voltage
proliferation of data-processing and
Motor inrush on starting must be limited
computer- or microprocessor-controlled
drop is that under the steady-state manufacturing, the sensitivity of to minimize voltage dips. Table 1.3-11
ii conditions of normal load, the voltage
at the utilization equipment must be
computers to voltage has become an on the next page will help select the
proper type of motor starter for various
important consideration. Severe dips of
adequate. Fine-print notes in the NEC short duration can cause a computer motors, and to select generators of
1 recommend sizing feeders and branch to “crash”—shut down completely, adequate size to limit voltage dip.
circuits so that the maximum voltage and other voltage transients caused See Tab 29 for additional data on
drop in either does not exceed 3%, by starting and stopping motors can reduced voltage motor starting.
2 with the total voltage drop for feeders cause data-processing errors. While Utility Systems
and branch circuits not to exceed 5%, voltage drops must be held to a mini-
for efficiency of operation. (Fine print Where the power is supplied by a
mum, in many cases computers will
3 notes in the NEC are not mandatory.) utility network, the motor inrush can
require special power-conditioning
be assumed to be small compared
In addition to steady-state conditions, equipment to operate properly.
to the system capacity, and voltage
voltage drop under transient condi-
4 tions, with sudden high-current, short-
Industrial Plants: Where large motors at the source can be assumed to
be constant during motor starting.
exist, and unit substation transformers
time loads, must be considered. The are relatively limited in size, voltage Voltage dip resulting from motor
most common loads of this type are
5 motor inrush currents during starting.
dips of as much as 20% may be per- starting can be calculated on the basis
of the voltage drop in the conductors
missible in some cases, if they do not
These loads cause a voltage dip on occur too frequently. Lighting is often between the power source and
the system as a result of the voltage
6 drop in conductors, transformers and
supplied from separate transformers, the motor resulting from the inrush
and is minimally affected by voltage current. Where the utility system is
generators under the high current. dips in the power systems. However, it limited, the utility will often specify the
This voltage dip can have numerous
7 adverse effects on equipment in the
is usually best to limit dips to between maximum permissible inrush current
5 and 10% at most. One critical consid- or the maximum hp motor they will
system, and equipment and conduc- eration is that a large voltage dip can permit to be started across-the-line.
tors must be designed and sized to
8 minimize these problems. In many
cause a dropout (opening) of magnetic
Transformer Considerations
motor contactors and control relays.
cases, reduced-voltage starting of The actual dropout voltage varies con- If the power source is a transformer,
motors to reduce inrush current
9 will be necessary.
siderably among starters of different and the inrush kVA or current of the
motor being started is small compared
manufacturers. The only standard that
exists is that of NEMA, which states to the full-rated kVA or current of the
10 Recommended Limits of that a starter must not drop out at 85% transformer, the transformer voltage
Voltage Variation of its nominal coil voltage, allowing dip will be small and may be ignored.
only a 15% dip. While most starters As the motor inrush becomes a signifi-
General Illumination: Flicker in
11 incandescent lighting from voltage will tolerate considerably more volt- cant percentage of the transformer
age dip before dropping out, limiting full-load rating, an estimate of the
dip can be severe; lumen output drops transformer voltage drop must be
about three times as much as the dip to 15% is the only way to ensure
12 voltage dips. That is, a 10% drop in continuity of operation in all cases. added to the conductor voltage drop
to obtain the total voltage drop to the
voltage will result in a 30% drop in X-Ray Equipment: Medical x-ray and motor. Accurate voltage drop calcula-
light output. While the lumen output
13 drop in fluorescent lamps is roughly
similar diagnostic equipment, such as tion would be complex and depend
CAT-scanners, are extremely sensitive upon transformer and conductor
proportional to voltage drop, if the to low voltage. They present a small, resistance, reactance and impedance,
voltage dips about 25%, the lamp will
14 go out momentarily and then restrike.
steady load to the system until the as well as motor inrush current and
instant the x-ray tube is “fired.” This power factor. However, an approxima-
For high-intensity discharge (HID) presents a brief but extremely high tion can be made on the basis of the
lamps such as mercury vapor, high-
15 pressure sodium or metal halide, if the
instantaneous momentary load. In low power-factor motor inrush current
some modern x-ray equipment, the (30–40%) and impedance of the trans-
lamp goes out because of an excessive firing is repeated rapidly to create former.
voltage dip, it will not restrike until it
16 has cooled. This will require several
multiple images. The voltage regula-
tion must be maintained within the
minutes. These lighting flicker effects For example, if a 480V transformer
manufacturer’s limits, usually 2 to 3%,
can be annoying, and in the case of has an impedance of 5%, and the
17 HID lamps, sometimes serious. In
under these momentary loads, to
motor inrush current is 25% of the
ensure proper x-ray exposure.
areas where close work is being done, transformer full-load current (FLC),
such as drafting rooms, precision then the worst case voltage drop will
18 assembly plants, and the like, even be 0.25 x 5%, or 1.25%.
a slight variation, if repeated, can be
19 very annoying, and reduce efficiency. The allowable motor inrush current is
Voltage variation in such areas should determined by the total permissible
be held to 2 or 3% under motor-starting voltage drop in transformer and
20 or other transient conditions. conductors.

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-21
August 2013 System Analysis
Sheet 01 053

Table 1.3-11. Factors Governing Voltage Drop


Type of Starting Starting How Starting Starting Torque per Unit of Full-Load Amperes i
Motor  Torque Current  Started Current Full Load Torque per kVA Generator
% Full-Load  Motor Rpm Capacity for Each

1750 1150  850


1% Voltage Drop ii
Design A Normal Normal Across-the-line 600–700 1.5 1.35 1.25 0.0109–.00936
resistance 480–560 ➁ 0.96 0.87 0.80 0.0136–.0117 1
autotransformer 375–450 ➁ 0.96 0.87 0.80 0.0170–.0146
Design B Normal Low Across-the-line 500–600 1.5 1.35 1.25 0.0131–.0109
resistance
autotransformer
400–480 ➁
320–400 ➁
0.96
0.96
0.87
0.87
0.80
0.80
0.0164–.01365
0.0205–.0170
2
Design C High Low Across-the-line 500–600 — 0.2 to 2.5 — 0.0131–.0109
resistance
autotransformer
400–480 ➁
320–400 ➁


1.28 to 1.6
1.28 to 1.6


0.0164–.01365
0.0205–.0170
3
Wound Rotor High Low Secondary controller 100% current — — — —
for 100%
torque







0.0655
4
Synchronous (for compressors) Low — Across-the-line 300 40% Starting, 40% Pull-In 0.0218
Synchronous (for centrifugal pumps) Low — Across-the-line 450–550 60% Starting, 110% Pull-In 0.0145–.0118
Autotransformer 288–350  38% Starting, 110% Pull-In 0.0228–.0197 5
 Consult NEMA MG-1 sections 1 and 12 for the exact definition of the design letter.
 In each case, a solid-state reduced voltage starter can be adjusted and controlled to provide the required inrush current and torque characteristics.
 Where accuracy is important, request the code letter of the the motor and starting and breakdown torques from the motor vendor.
6
 Using 80% taps.

Engine Generator Systems From the nameplate data on the motor, Example: 7
With an engine generator as the the full-load amperes of a 7-1/2 hp. Assuming a project having a
source of power, the type of starter 220V, 1750 rpm, three-phase, squirrel- 1000 kVA generator, where the
that will limit the inrush depends on cage motor is 19.0A. Therefore: voltage variation must not exceed
8
the characteristics of the generator. Starting current (%F.L.) = 10%. Can a 75 hp, 1750 rpm, 220V,
Although automatic voltage regulators three-phase, squirrel-cage motor be 9
are usually used with all AC engine- 10 × 100 × 1000 started without objectionable lamp
−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−− = 3.45 or 345%.
generators, the initial dip in voltage is 19.0 × 220 × 3 × 0.40 flicker (or 10% voltage drop)?
caused by the inherent regulation of 10
the generator and occurs too rapidly From tables in the circuit protective
From Table 1.3-11, a NEMA design C or
for the voltage regulator to respond. devices reference section, the full-load
NEMA design D motor with an autotrans-
It will occur whether or not a regulator amperes of this size and type of motor
is installed. Consequently, the percent
former starter gives approximately this
is 158A. To convert to same basis as 11
starting ratio. It could also be obtained
of initial voltage drop depends on the column 7, 158A must be divided by
from a properly set solid-state adjust-
ratio of the starting kVA taken by the the generator capacity and % voltage
motor to the generator capacity, the
able reduced voltage starter.
drop, or: 12
inherent regulation of the generator, The choice will depend upon the
158 = 0.0158A per kVA
torque requirements of the load since
the power-factor of the load thrown
on the generator, and the percentage the use of an autotransformer starter
1000 x 10 per 1% voltage drop 13
load carried by the generator. reduces the starting torque in direct Checking against the table, 0.0158 falls
proportion to the reduction in starting within the 0.0170–0.0146 range. This
A standard 80% power-factor engine- current. In other words, a NEMA indicates that a general-purpose motor
14
type generator (which would be design C motor with an autotrans- with autotransformer starting can
used where power is to be supplied former would have a starting torque be used.
to motor loads) has an inherent of approximately full-load (see Table
15
regulation of approximately 40% 1.3-11) whereas the NEMA design D Note: Designers may obtain calculated
from no-load to full-load. This means information from engine generator
motor under the same conditions
that a 50% variation in load would would have a starting torque of
manufacturers. 16
cause approximately 20% variation approximately 1-1/2 times full-load. The calculation results in conservative
in voltage (50% x 40% = 20%).
Note: If a resistance starter were used for results. The engineer should provide 17
Assume that a 100 kVA, 80% PF the same motor terminal voltage, the start- to the engine-generator vendor the
engine-type generator is supplying ing torque would be the same as that starting kVA of all motors connected to
the power and that the voltage drop obtained with autotransformer type, but the the generator and their starting sequence. 18
should not exceed 10%. Can a 7-1/2 hp, starting current would be higher, as shown. The engineer should also specify the
220V, 1750 rpm, three-phase, squirrel- maximum allowable drop. The engineer
cage motor be started without Shortcut Method should request that the engine-generator 19
exceeding this voltage drop? Column 7 in Table 1.3-11 has been vendor consider the proper generator
worked out to simplify checking. size when closed-transition autotrans-
Starting ratio =
The figures were obtained by using former reduced voltage starters, and 20
the formula above and assuming soft-start solid-state starter are used;
Percent voltage drop × gen. kVA × 1000
−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−− 1 kVA generator capacity and 1% so the most economical method of
F.L. amperes × volts × 3 × reg. of gen. voltage drop. installation is obtained. 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-22 Power Distribution Systems
System Analysis August 2013
Sheet 01 054

Voltage Drop Formulas If the receiving end voltage, load current and power factor
i (PF) are known.
Approximate Method
2 2
Voltage Drop E VD = ( E R cosθ + I R ) + ( E R sinθ + I X ) – E R
ii
E VD = IR cosθ + IX sinθ
ER is the receiving end voltage.
1 where abbreviations are same as below “Exact Method.” Exact Method 2—If receiving or sending mVA and its power
factor are known at a known sending or receiving voltage.
Exact Methods
2 Voltage drop
2 2 ( ZMVA R )
2
- + 2ZMVA R cos ( γ – θ R )
E S = E R + ---------------------------------
Exact Method 1—If sending end voltage and load PF 2
ER
3 are known.
or
2 2
E VD = E S + IR cosθ + IX sinθ – E S – ( IX cosθ – IR sinθ )
4 2 2 ( ZMVA R )
2
- – 2ZMVA S cos ( γ – θ S )
E R = E S + ---------------------------------
where: 2
ES
5 EVD = Voltage drop, line-to-neutral, volts
where:
ES = Source voltage, line-to-neutral, volts
ER = Receiving line-line voltage in kV
6 I = Line (Load) current, amperes
ES = Sending line-line voltage in kV
R = Circuit (branch, feeder) resistance, ohms
7 X = Circuit (branch, feeder) reactance, ohms
MVAR = Receiving three-phase mVA
MVAS = Sending three-phase mVA
cosθ = Power factor of load, decimal
8 Z = Impedance between and receiving ends
sinθ = Reactive factor of load, decimal
γ = The angle of impedance Z
9 θR = Receiving end PF
θS = Sending end PF, positive when lagging
10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-23
August 2013 System Analysis
Sheet 01 055

Voltage Drop Table 1.3-12. Temperature Correction Factors


for Voltage Drop
To select minimum conductor size:
i
1. Determine maximum desired
Voltage Drop Tables Conductor Percent Correction voltage drop, in volts.
Size Power Factors %
Note: Busway voltage drop tables are
100 90 80 70 60
2. Divide voltage drop by ii
shown in Tab 24 of this catalog. (amperes x circuit feet).
No. 14 to No. 4 5.0 4.7 4.7 4.6 4.6
Tables for calculating voltage drop for No. 2 to 3/0 5.0 4.2 3.7 3.5 3.2
3. Multiply by 100. 1
copper and aluminum conductors, in 4/0 to 500 kcmil 5.0 3.1 2.6 2.3 1.9 4. Find nearest lower voltage drop
either magnetic (steel) or nonmagnetic 600 to 1000 kcmil 5.0 2.6 2.1 1.5 1.3
value in tables, in correct column
(aluminum or non-metallic) conduit,
for type of conductor, conduit and 2
appear on Page 1.3-24. These tables Calculations power factor. Read conductor size
give voltage drop per ampere per
for that value.
100 ft (30m) of circuit length. The To calculate voltage drop: 3
circuit length is from the beginning 1. Multiply current in amperes by 5. Where this results in an oversized
point to the end point of the circuit the length of the circuit in feet to cable, verify cable lug sizes for
regardless of the number of conductors. get ampere-feet. Circuit length is molded case breakers and fusible 4
the distance from the point of switches. Where lug size available
Tables are based on the following
origin to the load end of the circuit. is exceeded, go to next higher
conditions: rating. 5
1. Three or four single conductors in 2. Divide by 100.
a conduit, random lay. For three- Example:
3. Multiply by proper voltage drop
conductor cable, actual voltage
value in tables. Result is voltage A three-phase, four-wire lighting 6
drop will be approximately the feeder on a 208V circuit is 250 ft
drop.
same for small conductor sizes (76.2m) long. The load is 175A at
and high power factors. Actual Example: 90% PF. It is desired to use aluminum 7
voltage drop will be from 10 to A 460V, 100 hp motor, running at 80% conductors in aluminum conduit. What
15% lower for larger conductor PF, draws 124A full-load current. It is size conductor is required to limit the
sizes and lower power factors. fed by three 2/0 copper conductors in voltage drop to 2% phase-to-phase? 8
2. Voltage drops are phase-to-phase, steel conduit. The feeder length is 1. VD = −−− 2−− × 208 = 4.16V
for three-phase, three-wire or 150 ft (46m). What is the voltage drop 100
three-phase, four-wire 60 Hz in the feeder? What is the percentage 9
circuits. For other circuits, multiply voltage drop? 2. −−−−−4.16
−−−−−−−−−− = 0.0000951
175 × 250
voltage drop given in the tables by
the following correction factors:
1. 124A x 150 ft (46m) = 18,600A-ft 10
3. 0.0000951 × 100 = 0.00951
2. Divided by 100 = 186
Three-phase, four-wire, 4. In table, under aluminum conduc-
phase-to-neutral x 0.577 3. Table: 2/0 copper, magnetic conduit, tors, nonmagnetic conduit, 90%
11
Single-phase, two-wire x 1.155 80% PF = 0.0187 PF, the nearest lower value is
Single-phase, three-wire, 186 x 0.0187 = 3.48V drop 0.0091. Conductor required is
phase-to-phase x 1.155 3.48 x 100 = 0.76% drop 500 kcmil. (Size 4/0 THW would
12
Single-phase, three-wire, 460 have adequate ampacity, but the
phase-to-neutral x 0.577 voltage drop would be excessive.)
4. Conclusion: 0.76% voltage drop 13
3. Voltage drops are for a conductor is very acceptable. (See NEC 2005
temperature of 75°C. They may be Article 215, which suggests that a
used for conductor temperatures voltage drop of 3% or less on a 14
between 60°C and 90°C with feeder is acceptable.)
reasonable accuracy (within ±5%).
However, correction factors in 15
Table 1.3-12 can be applied if
desired. The values in the table are
in percent of total voltage drop. 16
For conductor temperature of 60°C–
SUBTRACT the percentage from 17
Table 1.3-12.
For conductor temperature of 90°C–
ADD the percentage from Table 1.3-12. 18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-24 Power Distribution Systems
System Analysis August 2013
Sheet 01 056

Table 1.3-13. Voltage Drop—Volts per Ampere per 100 Feet (30 m); Three-Phase, Phase-to-Phase
i Conductor Size Magnetic Conduit (Steel) Nonmagnetic Conduit (Aluminum or Nonmetallic)
AWG Load Power Factor, % Load Power Factor, %
or kcmil
ii 60 70 80 90 100 60 70 80 90 100
Copper Conductors
14 0.3390 0.3910 0.4430 0.4940 0.5410 0.3370 0.3900 0.4410 0.4930 0.5410
1 12 0.2170 0.2490 0.2810 0.3130 0.3410 0.2150 0.2480 0.2800 0.3120 0.3410
10 0.1390 0.1590 0.1790 0.1980 0.2150 0.1370 0.1580 0.1780 0.1970 0.2150
8 0.0905 0.1030 0.1150 0.1260 0.1350 0.0888 0.1010 0.1140 0.1250 0.1350
2 6
4
0.0595
0.0399
0.0670
0.0443
0.0742
0.0485
0.0809
0.0522
0.0850
0.0534
0.0579
0.0384
0.0656
0.0430
0.0730
0.0473
0.0800
0.0513
0.0849
0.0533
2 0.0275 0.0300 0.0323 0.0342 0.0336 0.0260 0.0287 0.0312 0.0333 0.0335
1 0.0233 0.0251 0.0267 0.0279 0.0267 0.0218 0.0238 0.0256 0.0270 0.0266
3 1/0 0.0198 0.0211 0.0222 0.0229 0.0213 0.0183 0.0198 0.0211 0.0220 0.0211
2/0 0.0171 0.0180 0.0187 0.0190 0.0170 0.0156 0.0167 0.0176 0.0181 0.0169
3/0 0.0148 0.0154 0.0158 0.0158 0.0136 0.0134 0.0141 0.0147 0.0149 0.0134
4 4/0 0.0130 0.0134 0.0136 0.0133 0.0109 0.0116 0.0121 0.0124 0.0124 0.0107
250 0.0122 0.0124 0.0124 0.0120 0.0094 0.0107 0.0111 0.0112 0.0110 0.0091
300 0.0111 0.0112 0.0111 0.0106 0.0080 0.0097 0.0099 0.0099 0.0096 0.0077
5 350 0.0104 0.0104 0.0102 0.0096 0.0069 0.0090 0.0091 0.0091 0.0087 0.0066
500 0.0100 0.0091 0.0087 0.0080 0.0053 0.0078 0.0077 0.0075 0.0070 0.0049
600 0.0088 0.0086 0.0082 0.0074 0.0046 0.0074 0.0072 0.0070 0.0064 0.0042
6 750
1000
0.0084
0.0080
0.0081
0.0077
0.0077
0.0072
0.0069
0.0063
0.0040
0.0035
0.0069
0.0064
0.0067
0.0062
0.0064
0.0058
0.0058
0.0052
0.0035
0.0029
Aluminum Conductors
7 12 0.3296 0.3811 0.4349 0.4848 0.5330 0.3312 0.3802 0.4328 0.4848 0.5331
10 0.2133 0.2429 0.2741 0.3180 0.3363 0.2090 0.2410 0.2740 0.3052 0.3363
8 0.1305 0.1552 0.1758 0.1951 0.2106 0.1286 0.1534 0.1745 0.1933 0.2115
8 6 0.0898 0.1018 0.1142 0.1254 0.1349 0.0887 0.1011 0.1127 0.1249 0.1361
4 0.0595 0.0660 0.0747 0.0809 0.0862 0.0583 0.0654 0.0719 0.0800 0.0849
2 0.0403 0.0443 0.0483 0.0523 0.0535 0.0389 0.0435 0.0473 0.0514 0.0544
1 0.0332 0.0357 0.0396 0.0423 0.0428 0.0318 0.0349 0.0391 0.0411 0.0428
9 1/0 0.0286 0.0305 0.0334 0.0350 0.0341 0.0263 0.0287 0.0322 0.0337 0.0339
2/0 0.0234 0.0246 0.0275 0.0284 0.0274 0.0227 0.0244 0.0264 0.0274 0.0273
3/0 0.0209 0.0220 0.0231 0.0241 0.0217 0.0160 0.0171 0.0218 0.0233 0.0222
10 4/0 0.0172 0.0174 0.0179 0.0177 0.0170 0.0152 0.0159 0.0171 0.0179 0.0172
250 0.0158 0.0163 0.0162 0.0159 0.0145 0.0138 0.0144 0.0147 0.0155 0.0138
300 0.0137 0.0139 0.0143 0.0144 0.0122 0.0126 0.0128 0.0133 0.0132 0.0125
11 350 0.0130 0.0133 0.0128 0.0131 0.0100 0.0122 0.0123 0.0119 0.0120 0.0101
500 0.0112 0.0111 0.0114 0.0099 0.0076 0.0093 0.0094 0.0094 0.0091 0.0072
600 0.0101 0.0106 0.0097 0.0090 0.0063 0.0084 0.0085 0.0085 0.0081 0.0060
12 750 0.0095 0.0094 0.0090 0.0084 0.0056 0.0081 0.0080 0.0078 0.0072 0.0051
1000 0.0085 0.0082 0.0078 0.0071 0.0043 0.0069 0.0068 0.0065 0.0058 0.0038

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-1
August 2013 System Application Considerations
Sheet 01 057
Capacitors

Capacitors and Power Factor ANSI Standard C37.06 (indoor oilless Low Voltage Capacitor Switching
i
circuit breakers) indicates the preferred
ratings of Eaton’s Type VCP-W vacuum Circuit breakers and switches for use
Capacitor General Application breaker. For capacitor switching, with a capacitor must have a current
Considerations careful attention should be paid to rating in excess of rated capacitor ii
the notes accompanying the table. current to provide for overcurrent from
Additional application information overvoltages at fundamental frequency
is available in Tab 35 regarding The definition of the terms are in ANSI
capacitors and harmonic filters Standard C37.04 Article 5.13 (for the and harmonic currents. The following 1
latest edition). The application guide percent of the capacitor-rated current
as follows: should be used as a general guideline:
ANSI/IEEE Standard C37.012 covers
■ Capacitor selection the method of calculation of the Fused and unfused switches. . . . 165% 2
■ Where to install capacitors in a plant quantities covered by C37.06 Standard.
distribution system Molded case breaker or
■ Locating capacitors on reduced
Note that the definitions in C37.04 equivalent . . . . . . . . . . . . . . . . . 150% 3
make the switching of two capacitors
voltage and multi-speed starters banks in close proximity to the switch- DSII power circuit breakers. . . . . 135%
■ Harmonic considerations gear bus a back-to-back mode of
Magnum DS power 4
■ Eliminating harmonic problems switching. This classification requires
circuit breaker . . . . . . . . . . . . . . 135%
■ National Electrical Code a definite purpose circuit breaker
requirements (breakers specifically designed for Contactors: 5
capacitance switching). Open type . . . . . . . . . . . . . . . . . . . 135%
Medium Voltage We recommend that such application
Capacitor Switching be referred to Eaton.
Enclosed type . . . . . . . . . . . . . . . . 150% 6
Capacitance switching constitutes The NEC, Section 460.8(C), requires
A breaker specified for capacitor the disconnecting means to be rated not
severe operating duty for a circuit switching should include as applicable: less than 135% of the rated capacitor
7
breaker. At the time the breaker opens
at near current zero, the capacitor is 1. Rated maximum voltage. current (for 600V and below).
fully charged. After interruption, when 2. Rated frequency. See Tab 35 for switching device 8
the alternating voltage on the source ampere ratings. They are based on
side of the breaker reaches its opposite 3. Rated open wire line charging percentage of capacitor-rated current
maximum, the voltage that appears switching current. as indicated (above). The interrupting 9
across the contacts of the open breaker rating of the switch must be selected
is at least twice the normal peak line- 4. Rated isolated cable charging and
to match the system fault current
to-neutral voltage of the circuit. If a shunt capacitor switching current.
available at the point of capacitor 10
breakdown occurs across the open 5. Rated back-to-back cable application. Whenever a capacitor
contact, the arc is re-established. Due charging and back-to-back bank is purchased with less than the
to the circuit constants on the supply capacitor switching current. ultimate kVAR capacity of the rack 11
side of the breaker, the voltage across or enclosure, the switch rating should
the open contact can reach three times 6. Rated transient overvoltage factor. be selected based on the ultimate
the normal line-to-neutral voltage. kVAR capacity—not the initial 12
After it is interrupted and with 7. Rated transient inrush current and
its frequency. installed capacity.
subsequent alternation of the supply
side voltage, the voltage across the 8. Rated interrupting time. Refer to Tab 35 for recommended 13
open contact is even higher. selection of capacitor switching
9. Rated capacitive current devices; recommended maximum
switching life. capacitor ratings for various motor 14
types and voltages; and for required
10. Grounding of system and multipliers to determine capacitor
capacitor bank. kVARs required for power factor 15
Load break interrupter switches correction.
are permitted by ANSI/IEEE Standard
C37.30 to switch capacitance, but they 16
must have tested ratings for the purpose.
Refer to Eaton Type MVS ratings.
17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-2 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 058
Capacitors

i Motor Power Factor % AR—percent reduction in line To derate a capacitor used on a system
current due to the capacitor. A voltage lower than the capacitor
Correction capacitor located on the motor side voltage rating, such as a 240V
of the overload relay reduces line capacitor used on a 208V system,
ii See Tab 35 containing suggested
maximum capacitor ratings for
current through the relay. Therefore, a use the following formula:
different overload relay and/or setting
induction motors switched with the may be necessary. The reduction in Actual kVAR =
1 capacitor. The data is general in nature line current may be determined by
( Applied Voltage )
2
and representative of general purpose measuring line current with and Nameplate kVAR × ---------------------------------------------------------------------
-
induction motors of standard design. 2
without the capacitor or by calculation ( Nameplate Voltage )
2 The preferable means to select capacitor as follows:
ratings is based on the “maximum For the kVAC required to correct the
recommended kVAR” information (Original PF) power factor from a given value of
% AR = 100 – 100 × −−−−−−−−−−−−−−−−−−−−−−− COS φ1 to COS φ2, the formula is:
3 available from the motor manufacturer. (Improved PF)
If this is not possible or feasible, the
tables can be used. kVAC = kW (tan phase1–tan phase2)
If a capacitor is used with a lower kVAR
4 An important point to remember
rating than listed in tables, the % AR Capacitors cause a voltage rise.
can be calculated as follows: At light load periods the capacitive
is that if the capacitor used with the
motor is too large, self-excitation Actual kVAR voltage rise can raise the voltage at
5 may cause a motor-damaging over-
% AR = Listed % AR × −−−−−−−−−−−−−−−−−−−−−−−−
kVAR in Table
the location of the capacitors to an
voltage when the motor and capacitor unacceptable level. This voltage rise
combination is disconnected from the The tables can also be used for other can be calculated approximately by
6 line. In addition, high transient torques motor ratings as follows: the formula:
capable of damaging the motor shaft A. For standard 60 Hz motors MVA r
or coupling can occur if the motor is % VR = −−−−−−−−−−−

7 reconnected to the line while rotating
operating at 50 Hz: MVA SC
kVAR = 1.7–1.4 of kVAR listed
and still generating a voltage of % AR = 1.8–1.35 of % AR listed
self-excitation. MVAR is the capacitor rating and MVASC
8 B. For standard 50 Hz motors is the system short-circuit capacity.
Definitions operating at 50 Hz: With the introduction of variable speed
kVAR—rating of the capacitor in kVAR = 1.4–1.1 of kVAR listed
9 reactive kilovolt-amperes. This value % AR = 1.4–1.05 of % AR listed
drives and other harmonic current
generating loads, the capacitor
is approximately equal to the motor
C. For standard 60 Hz wound-rotor impedance value determined must
no-load magnetizing kilovars.
10 motors: not be resonant with the inductive
kVAR = 1.1 of kVAR listed reactances of the system.
% AR= 1.05 of % AR listed
11
Note: For A, B, C, the larger multipliers
apply for motors of higher speeds; i.e.,
12 3600 rpm = 1.7 mult., 1800 rpm = 1.65
mult., etc.

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-3
August 2013 System Application Considerations
Sheet 01 059
Protection and Coordination

Overcurrent Protection damage or withstand characteristics, substation transformer can be coordi-


i
(e) calculation of maximum short- nated with the low voltage breakers.
and Coordination circuit currents (and ground fault Transformer damage points, based on
currents if ground fault protection is ANSI standards, and low voltage cable
Overcurrents in a power distribution included) available at each protective heating limits can be plotted on this ii
system can occur as a result of both device location, (f) understanding of set of curves to ensure that apparatus
normal (motor starting, transformer operating characteristics and available limitations are not exceeded.
inrush, etc.) and abnormal (overloads, adjustments of each protective device, 1
ground fault, line-to-line fault, etc.) (g) any special overcurrent protection Ground-fault curves may also be
conditions. In either case, the funda- requirements including utility limita- included in the coordination study
mental purposes of current-sensing tions. Refer to Figure 1.4-1. if ground-fault protection is provided, 2
protective devices are to detect the but care must be used in interpreting
abnormal overcurrent and with proper To ensure complete coordination, the their meaning.
coordination, to operate selectively time-trip characteristics of all devices
Standard definitions have been 3
to protect equipment, property in series should be plotted on a single
and personnel while minimizing the sheet of standard log-log paper. established for overcurrent protective
devices covering ratings, operation
outage of the remainder of the system. Devices of different-voltage systems
and application systems.
4
With the increase in electric power can be plotted on the same sheet by
consumption over the past few converting their current scales, using M—Motor (100 hp). Dashed line shows
decades, dependence on the contin- the voltage ratios, to the same voltage- initial inrush current, starting current 5
ued supply of this power has also basis. Such a coordination plot is during 9-sec. acceleration, and drop to
increased so that the direct costs shown in Figure 1.4-1. In this manner, 124A normal running current, all well
of power outages have risen signifi- primary fuses and circuit breaker below CBA trip curve. 6
cantly. Power outages can create relays on the primary side of a
dangerous and unsafe conditions as
a result of failure of lighting, elevators, 7
ventilation, fire pumps, security SCALE X 100 = CURRENT IN AMPERES AT 480V

10,000
systems, communications systems,

1000

2000

3000

4000
5000
6000
7000
8000
9000
100

200

300

400

500
600
700
800
900
70
80
90
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
1000 1000
and the like. In addition, economic loss 900
800
700
4.16 kV 250 MVA
900
800
700
8
from outages can be extremely high 600
500
600
500
as a result of computer downtime, 400 400

or, especially in industrial process 300 B 300 9


plants, interruption of production. 200
A D
200
C
Protective equipment must be adjusted D 10
and maintained in order to function 100
90
80
250A 100
90
1000 80
properly when an overcurrent occurs, 70
60
kVA 4,160V ∆
70
60
5.75%
but coordination begins during power 50 480/277V 50
11
40 19,600A 40
system design with the knowledgeable ANSI Three-Phase
30 Thru Fault 30
analysis and selection and application Protection Curve
20 (More Than 10 in C 1,600A 20
of each overcurrent protective device Lifetime) 12
in the series circuit from the power 24,400A
B
source(s) to each load apparatus. The 10
9
600A
10
9
8 8
objective of coordination is to localize 7
M 7
13

TIME IN SECONDS
TIME IN SECONDS

6 6
the overcurrent disturbance so that the 5
20,000A
5
4 4
protective device closest to the fault
3 3
on the power-source side has the first A 175A
14
chance to operate; but each preceding 2 B C 2

protective device upstream toward the


power source should be capable, within 1
.9
.8 100 hp –
1
.9
.8
15
its designed settings of current and .7
.6
M 124A FLC .7
.6
time, to provide backup and de-energize .5 .5
X = Available fault current
the circuit if the fault persists. Sensitivity .4

.3
including motor
contribution.
.4

.3
16
of coordination is the degree to which Ground
the protective devices can minimize .2 Fault Trip .2

C
the damage to the faulted equipment.
.1 .1
17
.09 .09
To study and accomplish coordination .08
.07
.08
.07
requires (a) a one-line diagram, the .06 Transformer .06
.05
B Inrush .05
18
Max. Three-Phase

roadmap of the power distribution .04 .04

system, showing all protective devices


4.16 kV Fault

.03 .03

A
480V Fault

and the major or important distribution


and utilization apparatus, (b) identifi-
.02 .02
19
Max.

cation of desired degrees of power .01 .01


continuity or criticality of loads
70
80
90
100

200

300

400

500
600
700
800
900
1000

2000

3000

4000
5000
6000
7000
8000
9000
10,000

.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60

throughout system, (c) definition SCALE X 100 = CURRENT IN AMPERES AT 480V


20
of operating-current characteristics
(normal, peak, starting) of each Figure 1.4-1. Time-Current Characteristic Curves for Typical Power Distribution System
utilization circuit, (d) equipment Protective Devices Coordination Analysis 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-4 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 060
Protection and Coordination

A—CB (175A) coordinates selectively Maximum 480V three-phase fault available fault current at their point of
i with motor M on starting and running indicated on the horizontal current axis. application. All breakers are equipped
and with all upstream devices, except with long-time-delay (and possibly
that CB B will trip first on low level Maximum 4160V three-phase fault short delay) and instantaneous over-
ii ground faults. indicated, converted to 480V basis. current trip devices. A main breaker
4160 may have short time-delay tripping to
B—CB (600A) coordinates selectively I 480 V = I 4160 V × −−−−−−− allow a feeder breaker to isolate the
1 with all upstream and downstream 480
fault while power is maintained to all
devices, except will trip before A on the remaining feeders.
The ANSI protection curves are
limited ground faults, since A has no
specified in ANSI C57.109 for liquid-
2 ground fault trips.
filled transformers and C57.12.59 for
A selective or fully coordinated system
permits maximum service continuity.
C—Main CB (1600A) coordinates dry-type transformers.
The tripping characteristics of each
selectively with all downstream
3 devices and with primary fuse D,
Illustrative examples such as shown overcurrent device in the system must
here start the coordination study from be selected and set so that the breaker
for all faults on load side of CB. nearest the fault opens to isolate the
the lowest rated device proceeding
4 D—Primary fuse (250A, 4160V) coordi- upstream. In practice, the setting or faulted circuit, while all other breakers
nates selectively with all secondary rating of the utility’s protective device remain closed, continuing power to
protective devices. Curve converted to sets the upper limit. Even in cases the entire unfaulted part of the system.
5 480V basis. Clears transformer inrush where the customer owns the medium
The National Electrical Code 
point (12 x FLC for 0.1 sec.), indicating voltage or higher distribution system,
contains specific requirements for
that fuse will not blow on inrush. the setting or rating of the lowest set
designing certain circuits with selective
6 Fuse is underneath right-half of ANSI protective device at the source deter-
coordination. Article 100 defines
three-phase withstand curve, indicating mines the settings of the downstream
selective coordination: Coordination
fuse will protect transformer for high- devices and the coordination.
(Selective), the following definition:
7 magnitude faults up to ANSI rating.
Therefore the coordination study “Localization of an overcurrent condi-
Delta-wye secondary side short should start at the present setting tion to restrict outages to the circuit or
equipment affected, accomplished by
8 circuit is not reflected to the primary or rating of the upstream device and
work toward the lowest rated device. If the choice of overcurrent protective
by the relation
this procedure results in unacceptable devices and their ratings or settings.”
9 V
I P = −−−S × I S
settings, the setting or rating of the  NEC 2011 NFPA 70: National Electrical Code
VP upstream device should be reviewed. International Electrical Code Series.
Where the utility is the sole source,
Article 620.62 (elevators, dumbwaiters,
10 for L-L and L-G faults. For line-to-line they should be consulted. Where the
escalators, moving walks, wheelchair
fault, the secondary (low voltage) side owner has its own medium or higher
voltage distribution, the settings or lifts, and stairway chair lifts) requires
fault current is 0.866 x I three-phase
11 ratings of all upstream devices should “Where more than one driving machine
fault current.
be checked. disconnecting means is supplied by a
However, the primary (high voltage) single feeder, the overcurrent protective
If perfect coordination is not feasible, devices in each disconnecting means
12 side fault is the same as if the secondary
then lack of coordination should be shall be selectively coordinated with
fault was a three-phase fault. Therefore
in coordination studies, the knee of the limited to the smallest part of the system. any other supply side overcurrent
13 short-time pickup setting on the sec- Application data is available for all protective device.” A similar require-
ondary breaker should be multiplied by protective equipment to permit ment under Article 700.27 is as follows;
systems to be designed for adequate “Emergency system(s) overcurrent
14 −−−−1−−−− or 1.1547 overcurrent protection and coordina- devices shall be selectively coordinated
0.866 with all supply side overcurrent
tion. For circuit breakers of all types,
time-current curves permit selection of protective devices.” Article 701.27
before it is compared to the minimum
15 melting time of the upstream primary instantaneous and inverse-time trips. states that “Legally required standby
system(s) overcurrent devices shall be
fuse curve. In the example shown, the For more complex circuit breakers,
with solid-state trip units, trip curves selectively coordinated with all supply
knee is at 4000A 30 sec., and the 30-sec.
16 trip time should be compared to the include long- and short-time delays, side overcurrent devices.”
MMT (minimum melt time) of the fuse as well as ground-fault tripping, with a Exception: Selective coordination
curve at 4000 x 1.1547 = 4619A. In this wide range of settings and features to shall not be required between two
17 case, there is adequate clearance to provide selectivity and coordination. overcurrent devices located in series
the fuse curve. For current-limiting circuit breakers, if no loads are connected in parallel
fuses, and circuit breakers with with the downstream device.
18 In the example shown, the ANSI integral fuses, not only are time-
three-phase through fault protection current characteristic curves available, In addition, for health care facilities,
curve must be multiplied by 0.577 but also data on current-limiting Article 517.26, Application of Other
19 and replotted in order to determine performance and protection for Articles requires that “The essential
the protection given by the primary downstream devices. electrical system shall meet the
for a single line to ground fault in requirements of Article 700, except
20 the secondary. In a fully rated system, all circuit as amended by Article 517.”
breakers must have an interrupting
capacity adequate for the maximum
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-5
August 2013 System Application Considerations
Sheet 01 061
Protection and Coordination

All breakers must have an interrupting Protection of Conductors (Excerpts E. Tap Conductors. Tap conductors
capacity not less than the maximum
from NFPA 70-2011, Article 240.4) shall be permitted to be protected i
available short-circuit current at their against overcurrent in accordance
point of application. A selective Conductors, other than flexible cords with the following:
system is a fully rated system with and fixture wires, shall be protected ii
tripping devices chosen and adjusted against overcurrent in accordance with 1. 210.19(A)(3) and (A)(4) Household
to provide the desired selectivity. their ampacities as specified in Section Ranges and Cooking Appliances
The tripping characteristics of each 310.15, unless otherwise permitted or and Other Loads. 1
overcurrent device should not overlap, required in (A) through (G). 2. 240.5(B)(2) Fixture Wire.
but should maintain a minimum time
interval for devices in series (to allow A. Power Loss Hazard. Conductor 3. 240.21 Location in Circuit. 2
for normal operating tolerances) at all overload protection shall not be
required where the interruption of 4. 368.17(B) Reduction in Ampacity
current values. Generally, a maximum
of four low voltage circuit breakers can the circuit would create a hazard, Size of Busway. 3
be operated selectively in series, with such as in a material handling
magnet circuit or fire pump circuit. 5. 368.17(C) Feeder or Branch Circuits
the feeder or branch breaker down- (busway taps).
stream furthest from the source. Short-circuit protection shall be 4
provided. 6. 430.53(D) Single Motor Taps.
Specify true rms sensing devices in
Note: FPN See NFPA 20-2003, standard
order to avoid false trips due to rapid for the Installation of Stationary Pumps Circuit Breaker Cable 5
currents or spikes. Specify tripping
elements with I2t or I4t feature for
for Fire Protection. Temperature Ratings
improved coordination with other B. Devices Rated 800A or Less. The UL listed circuit breakers rated 125A or 6
devices having I2t or I4t (such as next higher standard overcurrent less shall be marked as being suitable
OPTIM™ trip units) characteristics device rating (above the ampacity for 60ºC (140ºF), 75ºC (167ºF) only or
and fuses. of the conductors being protected) 60/75ºC (140/167ºF) wire. All Eaton 7
shall be permitted to be used, breakers rated 125A or less are marked
In general for systems such as shown 60/75ºC (140/167ºF). All UL listed circuit
in the example: provided all of the following
conditions are met. breakers rated over 125A are suitable 8
1. The settings or ratings of the for 75ºC conductors. Conductors rated
primary side fuse and main breaker 1. The conductors being protected for higher temperatures may be used,
must not exceed the settings are not part of a branch circuit but must not be loaded to carry more 9
allowed by NEC Article 450. supplying more than one recepta- current than the 75ºC ampacity of that
cle for cord-and-plug-connected size conductor for equipment marked
2. At 12 x IFL the minimum melting portable loads. or rated 75ºC or the 60ºC ampacity of 10
time characteristic of the fuse that size conductor for equipment
should be higher than 0.1 second. 2. The ampacity of the conductors
marked or rated 60ºC. However, when
does not correspond with the
3. The primary fuse should be to the standard ampere rating of a fuse or
applying derated factors, so long as 11
the actual load does not exceed the
left of the transformer damage a circuit breaker without overload
lower of the derated ampacity or the
curve as much as possible. The trip adjustments above its rating
correction factor for a single line- (but that shall be permitted to have
75ºC or 60ºC ampacity that applies. 12
to-ground factor must be applied other trip or rating adjustments).
to the damage curve.
Zone Selective Interlocking
3. The next higher standard rating Trip elements equipped with zone 13
4. The setting of the short-time delay selected does not exceed 800A. selective interlocking, trip without
element must be checked against intentional time delay unless a
the fuse MMT after it is corrected C. Overcurrent Devices Rated Over
restraint signal is received from 14
for line-to-line faults. 800A. Where the overcurrent
device is rated over 800A, the a protective device downstream.
Breakers equipped with this feature
5. The maximum fault current must ampacity of the conductors it
reduce the damage at the point of
15
be indicated at the load side of protects shall be equal to or
each protective device. greater than the rating of the fault if the fault occurs at a location
between the zone of protection.
6. The setting of a feeder protective
overcurrent device as defined in 16
Section 240.6. The upstream breaker upon receipt
device must comply with Article
240 and Article 430 of the NEC. D. Small Conductors. Unless of the restraint signal will not trip until
It also must allow the starting specifically permitted in 240.4(E) its time-delay setting times out. If the 17
and acceleration of the largest or 240.4(G), the overcurrent breaker immediately downstream of the
motor on the feeder while carrying protection shall not exceed 15A fault does not open, then after timing
all the other loads on the feeder. for 14 AWG, 20A for 12 AWG, and out, the upstream breaker will trip. 18
30A for 10 AWG copper; or 15A Breakers equipped with ground fault
for 12 AWG and 25A for 10 AWG trip elements should also be specified 19
aluminum and copper-clad to include zone interlocking for the
aluminum after any correction ground fault trip element.
factors for ambient temperature 20
and number of conductors have
been applied.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-6 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 062
Protection and Coordination

Ground Fault Protection Suggested Ground Fault Settings The Series G high performance,
i Article 230.95 of NEC requires ground-
current-limiting circuit breaker series
For the main devices: offers interrupting ratings to 200 kA.
fault protection of equipment shall be A ground fault pickup setting equal Frames are EGC, EGU, EGX, JGC,
ii provided for solidly grounded wye
electrical services of more than 150V
to 20–30% of the main breaker rating JGU, JGX, LGC, LGU and LGX.
but not to exceed 1200A, and a time
to ground, but not exceeding 600V delay equal to the delay of the short- Any of these current-limiting devices—
1 phase-to-phase for each service time element, but not to exceed fuses, fused breakers or current-limit-
disconnect rated 1000A or more. 1 second. ing breakers—cannot only clear these
large faults safely, but also will limit
The rating of the service disconnect the Ip and I2t let-through significantly
2 shall be considered to be the rating
For the feeder ground fault setting:
A setting equal to 20–30% of the feeder to prevent damage to apparatus
of the largest fuse that can be installed ampacity and a time delay to coordinate downstream, extending their zone
or the highest continuous current trip
3 setting for which the actual overcurrent
with the setting of the main (at least of protection. Without the current
6 cycles below the main). limitation of the upstream device,
device installed in a circuit breaker is the fault current could exceed the
rated or can be adjusted. If the desire to selectively coordinate
4 ground fault devices results in settings
withstand capability of the down-
The maximum allowable settings are: stream equipment. Underwriters
that do not offer adequate damage
1200A pickup, 1 second or less trip Laboratories tests and lists these
protection against arcing single line-
5 delay at currents of 3000A or greater. ground faults, the design engineer
series combinations. Application
information is available for
The characteristics of the ground-fault should decide between coordination
combinations that have been tested
and damage limitation.
6 trip elements create coordination and UL®-listed for safe operation
problems with downstream devices For low voltage systems with high- downstream from MDSL, TRI-PAC,
not equipped with ground fault magnitude available short-circuit and Current Limit-R, or Series C
7 protection. The National Electrical currents, common in urban areas and breakers of various ratings, under
Code exempts fire pumps and large industrial installations, several high available fault currents.
continuous industrial processes solutions are available. High interrupt-
Protective devices in electrical
8 from this requirement. ing Series C® molded case breakers,
distribution systems may be properly
It is recommended that in solidly current-limiting circuit breakers, or
coordinated when the systems are
grounded 480/277V systems where current-limiting fuses, limiters integral
9 designed and built, but that is no
main breakers are specified to be with molded-case circuit breakers
guarantee that they will remain
equipped with ground fault trip elements (TRI-PAC®) or mounted on power
coordinated. System changes and
that the feeder breakers be specified circuit breakers (MDSL) can be used to
10 additions, plus power source changes,
to be equipped with ground fault trip handle these large fault currents. To
frequently modify the protection
elements as well. provide current limiting, these devices
requirements, sometimes causing loss
must clear the fault completely within
11 of coordination and even increasing
the first half-cycle, limiting the peak
fault currents beyond the ratings of
current (Ip) and heat energy (I2t)
some devices. Consequently, periodic
let-through to considerably less than
12 what would have occurred without
study of protective-device settings
and ratings is as important for safety
the device. For a fully fusible system,
and preventing power outages
rule-of-thumb fuse ratios or more
13 accurate I2t curves can be used to
as is periodic maintenance of the
distribution system.
provide selectivity and coordination.
For fuse-breaker combinations, the
14 fuse should be selected (coordinated)
so as to permit the breaker to handle
those overloads and faults within its
15 capacity; the fuse should operate
before or with the breaker only on
large faults, approaching the interrupt-
16 ing capacity of the breaker, to minimize
fuse blowing. Recently, unfused, truly
current-limiting circuit breakers with
17 interrupting ratings adequate for the
largest systems (Type Series C, FDC,
JDC, KDC, LDC and NDC frames
18 or Type Current Limit-R®) have
become available.
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-7
August 2013 System Application Considerations
Sheet 01 063
Grounding/Ground Fault Protection

Grounding above ground potential. Any person The equipment grounding system
i
coming in contact with such an object must be bonded to the grounding
Grounding encompasses several while grounded could be seriously electrode at the source or service;
different but interrelated aspects of injured or killed. In addition, current however, it may be also connected
electrical distribution system design flow from the accidental grounding of to ground at many other points. ii
and construction, all of which are an energized part of the system could This will not cause problems with
essential to the safety and proper generate sufficient heat (often with the safe operation of the electrical
operation of the system and equip- arcing) to start a fire. To prevent the distribution system. Where computers, 1
ment supplied by it. Among these establishment of such unsafe potential data processing, or microprocessor-
are equipment grounding, system difference requires that (1) the equip- based industrial process control
grounding, static and lightning ment grounding conductor provide a systems are installed, the equipment 2
protection, and connection to earth return path for ground fault currents of grounding system must be designed
as a reference (zero) potential. sufficiently low impedance to prevent to minimize interference with their
unsafe voltage drop, and (2) the equip- proper operation. Often, isolated 3
1. Equipment Grounding ment grounding conductor be large grounding of this equipment, or
enough to carry the maximum ground isolated electrical supply systems are
Equipment grounding is essential
fault current, without burning off, for required to protect microprocessors 4
to safety of personnel. Its function is
sufficient time to permit protective from power system “noise” that does
to ensure that all exposed noncurrent-
devices (ground fault relays, circuit not in any way affect motors or other
carrying metallic parts of all structures
breakers, fuses) to clear the fault. The electrical equipment. Such systems 5
and equipment in or near the electrical
grounded conductor of the system must use single-point ground concept
distribution system are at the same
(usually the neutral conductor), to minimize “noise” and still meet
potential, and that this is the zero
although grounded at the source, must the NEC requirements. Any separate 6
reference potential of the earth.
not be used for equipment grounding. isolated ground mat must be tied to
Equipment grounding is required
the rest of the facility ground mat
by both the National Electrical Code The equipment grounding conductor system for NEC compliance. 7
(Article 250) and the National Electrical may be the metallic conduit or raceway
Safety Code regardless of how the of the wiring system, or a separate 2. System Grounding
power system is grounded. Equipment equipment grounding conductor, 8
grounding also provides a return path run with the circuit conductors, as System grounding connects the
for ground fault currents, permitting permitted by NEC. If a separate electrical supply, from the utility, from
protective devices to operate. Acciden- equipment grounding conductor is transformer secondary windings, or 9
tal contact of an energized conductor used, it may be bare or insulated; if from a generator, to ground. A system
of the system with an improperly insulated, the insulation must be green, can be solidly grounded (no intentional
grounded noncurrent-carry metallic green with yellow stripe or green tape. impedance to ground), impedance 10
part of the system (such as a motor Conductors with green insulation may grounded (through a resistance or
frame or panelboard enclosure) would not be used for any purpose other than reactance), or ungrounded (with no
raise the potential of the metal object for equipment grounding. intentional connection to ground. 11
3. Medium Voltage System: Grounding
Table 1.4-1. Features of Ungrounded and Grounded Systems (from ANSI C62.92) 12
Description A B C D E
Ungrounded Solidly Grounded Reactance Grounded Resistance Grounded Resonant Grounded
13
(1) Apparatus Fully insulated Lowest Partially graded Partially graded Partially graded
insulation
(2) Fault to Usually low Maximum value rarely Cannot satisfactorily be Low Negligible except when 14
ground current higher than three-phase reduced below one-half Petersen coil is short
short circuit current or one-third of values for circuited for relay
solid grounding purposes when it may
compare with solidly 15
grounded systems
(3) Stability Usually unimportant Lower than with other Improved over solid Improved over solid Is eliminated from
methods but can be grounding particularly grounding particularly consideration during 16
made satisfactory by use if used at receiving end if used at receiving end single line-to-ground
of high-speed breakers of system of system faults unless neutralizer
is short circuited to
isolate fault by relays
17
(4) Relaying Difficult Satisfactory Satisfactory Satisfactory Requires special
provisions but can be
made satisfactory 18
(5) Arcing Likely Unlikely Possible if reactance is Unlikely Unlikely
grounds excessive
(6) Localizing Effect of fault transmitted Effect of faults localized Effect of faults localized to Effect of faults Effect of faults 19
faults as excess voltage on to system or part of system or part of system transmitted as excess transmitted as excess
sound phases to all system where they occur where they occur unless voltage on sound phases voltage on sound phases
parts of conductively
connected network
reactance is quite high to all parts of conductively
connected network
to all parts of conductively
connected network
20
(7) Double Likely Likely Unlikely unless Unlikely unless Seem to be more likely
faults reactance is quite high resistance is quite high but conclusive information
and insulation weak and insulation weak not available 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-8 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 064
Grounding/Ground Fault Protection

Table 1.4-1. Features of Ungrounded and Grounded Systems (Continued)


i Description A B C D E
Ungrounded Solidly Grounded Reactance Grounded Resistance Grounded Resonant Grounded

ii (8) Lightning
protection
Ungrounded neutral Highest efficiency and
service arresters must be lowest cost
If reactance is very high
arresters for ungrounded
Arresters for ungrounded,
neutral service usually
Ungrounded neutral
service arresters must
applied at sacrifice in cost neutral service must be must be applied at be applied at sacrifice
and efficiency applied at sacrifice in cost sacrifice in cost and in cost and efficiency
1 and efficiency efficiency
(9) Telephone Will usually be low Will be greatest in Will be reduced from Will be reduced from Will be low in magnitude
interference except in cases of double magnitude due to higher solidly grounded values solidly grounded values except in cases of double
2 faults or electrostatic fault currents but can faults or series resonance
induction with neutral be quickly cleared at harmonic frequencies,
displaced but duration particularly with high but duration may be great
3 may be great speed breakers
(10) Radio May be quite high during Minimum Greater than for Greater than for May be high during faults
interference faults or when neutral solidly grounded, solidly grounded,
is displayed when faults occur when faults occur
4 (11) Line Will inherently clear Must be isolated for Must be isolated for Must be isolated for Need not be isolated but
availability themselves if total length each fault each fault each fault will inherently clear itself
of interconnected line is in about 60 to 80 percent
5 low and require isolation of faults
from system in increas-
ing percentages as length
6 becomes greater
(12) Adaptability Cannot be interconnected Satisfactory indefinitely Satisfactory indefinitely Satisfactory with solidly- Cannot be interconnected
to interconnection unless interconnecting with reactance-grounded with solidly-grounded or reactance-grounded unless interconnected
7 system is ungrounded
or isolating transformers
systems systems systems with proper
attention to relaying
system is resonant
grounded or isolating
are used transformers are used.
Requires coordination
8 between interconnected
systems in neutralizer
settings
9 (13) Circuit Interrupting capacity Same interrupting Interrupting capacity Interrupting capacity Interrupting capacity
breakers determined by three- capacity as required for determined by three- determined by three- determined by three-
phase conditions three-phase short circuit phase fault conditions phase fault conditions phase fault conditions
will practically always be
10 satisfactory
(14) Operating Ordinarily simple but Simple Simple Simple Taps on neutralizers must
procedure possibility of double be changed when major
11 faults introduces system switching is per-
complication in times formed and difficulty may
of trouble arise in interconnected
12 systems. Difficult to tell
where faults are located
(15) Total cost High, unless conditions Lowest Intermediate Intermediate Highest unless the arc
are such that arc tends suppressing characteris-
13 to extinguish itself, when tic is relied on to eliminate
transmission circuits may transmission circuits
be eliminated, reducing when it may be lowest
14 total cost for the particular types
of service

15 Because the method of grounding


affects the voltage rise of the unfaulted
The aforementioned definition is
of significance in medium voltage
of the three-phase current at the point
of fault. Damage to cable shields must
phases above ground, ANSI C62.92 distribution systems with long lines be checked. Although this fact is not
16 classifies systems from the point of and with grounded sources removed a problem except in small cables, it is
view of grounding in terms of a during light load periods so that in a good idea to supplement the cable
coefficient of grounding some locations in the system the shields returns of ground fault current
17 Highest Power Frequency
X0 /X1, R0 /X1 may exceed the defining to prevent damage, by installing an
limits. Other standards (cable and equipment grounding conductor.
rms Line – Ground Voltage
COG = --------------------------------------------------------------------------------------------- lightning arrester) allow the use of
The burdens on the current transformers
18 rms Line – Line Voltage at Fault
Location with the Fault Removed
100% rated cables and arresters
must be checked also (for saturation
selected on the basis of an effectively
grounded system only where the considerations), where residually
This same standard also defines connected ground relays are used
19 systems as effectively grounded when
criteria in the above are met. In
and the current transformers supply
effectively grounded system the line-
COG ≤ .8 such a system would have current to phase relays and meters.
to-ground fault current is high and
X0 /X1 ≤ 3.0 and R0 /X1 ≤ 1.0. Any other
20 grounding means that does not satisfy
there is no significant voltage rise in If ground sensor current transformers
the unfaulted phases. (zero sequence type) are used they
these conditions at any point in a
system is not effectively grounded. With selective ground fault isolation must be of high burden capacity.
21 the fault current should be at least 60%

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-9
August 2013 System Application Considerations
Sheet 01 065
Grounding/Ground Fault Protection

Table 1.4-2 taken from ANSI-C62.92 should not be limited to less than the Grounding Point
indicates the characteristics of the current transformers rating of the The most commonly used grounding i
various methods of grounding. source. This rule will provide sensitive point is the neutral of the system or the
differential protection for wye-connected neutral point created by means of a
Reactance Grounding generators and transformers against zigzag or a wye-broken delta grounding ii
It is generally used in the grounding line-to-ground faults near the neutral. transformer in a system that was oper-
of the neutrals of generators directly Of course, if the installation of ground ating as an ungrounded delta system.
connected to the distribution system fault differential protection is feasible, 1
bus, in order to limit the line-to-ground or ground sensor current transformers In general, it is a good practice that all
fault to somewhat less than the three- are used, sensitive differential relaying source neutrals be grounded with the
phase fault at the generator terminals. in resistance grounded system with same grounding impedance magnitude. 2
If the reactor is so sized, in all probability greater fault limitation is feasible. However, neutrals should not be tied
the system will remain effectively In general, ground sensor current together to a single resistor. Where
grounded. transformers (zero sequence) do not one of the medium voltage sources is 3
have high burden capacity. Resistance the utility, their consent for impedance
Resistance Grounded grounded systems limit the circulating grounding must be obtained.
Medium voltage systems in general currents of triple harmonics and limit 4
should be low resistance grounded. The neutral impedance must have a
the damage at the point of fault. This
The ground fault is typically limited to voltage rating at least equal to the rated
method of grounding is not suitable
about 200–400A but less than 1000A for line-to-neutral connection of loads.
line-to-neutral voltage class of the sys- 5
(a cable shield consideration). With a tem. It must have at least a 10-second
properly sized resistor and relaying On medium voltage systems, 100% rating equal to the maximum future
application, selective fault isolation cable insulation is rated for phase-to- line-to-ground fault current and a 6
is feasible. The fault limit provided neutral voltage. If continued operation continuous rating to accommodate the
has a bearing on whether residually with one phase faulted to ground is triple harmonics that may be present.
connected relays are used or ground desired, increased insulation thick- 7
sensor current transformers are used ness is required. For 100% insulation, 4. Low Voltage System: Grounding
for ground fault relaying. fault clearance is recommended within Solidly grounded three-phase systems
one minute; for 133% insulation, one (Figure 1.4-2) are usually wye- 8
In general, where residually connected hour is acceptable; for indefinite connected, with the neutral point
ground relays are used (51N), the fault operation, as long as necessary, grounded. Less common is the “red-
current at each grounded source 173% insulation is required. leg” or high-leg delta, a 240V system 9
supplied by some utilities with one
Table 1.4-2. Characteristics of Grounding winding center-tapped to provide 120V
Grounding Classes Ratios of Symmetrical Percent Fault Per Unit Transient to ground for lighting. This 240V, three- 10
and Means Component Parameters  Current LG Voltage phase, four-wire system is used where
  120V lighting load is small compared
A. Effectively ➃
X0/X1 R0/X1 R0/X0
to 240V power load, because the 11
1. Effective 0-3 0-1 — >60 ≤2 installation is low in cost to the utility.
2. Very effective 0-1 0-0.1 — >95 <1.5 A corner-grounded three-phase delta
B. Noneffectively system is sometimes found, with 12
1. Inductance one phase grounded to stabilize all
a. Low inductance 3-10 0-1 — >25 <2.3 voltages to ground. Better solutions
b. High inductance >10 — <2 <25 ≤2.73 
are available for new installations. 13
2. Resistance
a. Low resistance 0-10 — ≥2 <25 <2.5
b. High resistance — >100 ≤(-1) <1 ≤2.73
3. Inductance and resistance >10 — >2 <10 ≤2.73
Phase A 14
4. Resonant  — — <1 ≤2.73 • • • Phase B
N
5. Ungrounded/capacitance
a. Range A -∞ to -40  — — <8 ≤3 • Phase C
15
b. Range B -40 to 0 — — >8 >3  • Neutral
 Values of the coefficient of grounding (expressed as a percentage of maximum phase-to-phase
Grounded Wye
voltage) corresponding to various combinations of these ratios are shown in the ANSI C62.92
Appendix figures. Coefficient of grounding affects the selection of arrester ratings.
16
 Ground-fault current in percentage of the three-phase short-circuit value. • Phase B
 Transient line-to-ground voltage, following the sudden initiation of a fault in per unit of the crest
of the prefault line-to-ground operating voltage for a simple, linear circuit. • • • Phase C
Phase A
17
 In linear circuits, Class A1 limits the fundamental line-to-ground voltage on an unfaulted phase to
138% of the prefault voltage; Class A2 to less than 110%. • Neutral
 See ANSI 62.92 para. 7.3 and precautions given in application sections. 18
 Usual isolated neutral (ungrounded) system for which the zero-sequence reactance is capacitive Center-Tapped (High-Leg) Delta
(negative).
 Same as NOTE (6) and refer to ANSI 62.92 para. 7.4. Each case should be treated on its own merit. • Phase A 19
 Under restriking arcing ground fault conditions (e.g., vacuum breaker interrupter operation),
this value can approach 500%. • • Phase B
Under arcing ground fault conditions, this value can easily reach 700%, but is essentially unlimited. • Phase C
20
Corner-Grounded Delta

Figure 1.4-2. Solidly Grounded Systems


21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-10 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 066
Grounding/Ground Fault Protection

Ungrounded systems (Figure 1.4-3) Selecting the Low Voltage System used as substitutes for ungrounded
i can be either wye or delta, although Grounding Method systems where high system
the ungrounded delta system is far There is no one “best” distribution availability is required.
more common. system for all applications. In choosing
ii among solidly grounded, resistance
With one phase grounded, the voltage
to ground of the other two phases
grounded, or ungrounded power rises 73%, to full phase-to-phase
• Phase A
distribution, the characteristics of the
1 system must be weighed against the
voltage. In low voltage systems this
• • Phase B
Phase C requirements of power loads, lighting
is not important, since conductors
are insulated for 600V.
loads, continuity of service, safety
2 Ungrounded Delta
and cost. A low voltage resistance grounded
Phase A system is normally grounded so that
• • • Phase B Under ground fault conditions, each the single line-to-ground fault current
3 N system behaves very differently. A exceeds the capacitive charging
• Phase C solidly grounded system produces current of the system. If data for the
Ungrounded Wye high fault currents, usually with arcing, charging current is not available, use
4 and the faulted circuit must be cleared 40–50 ohm resistor in the neutral
Figure 1.4-3. Ungrounded Systems on the first fault within a fraction of a of the transformer.
second to minimize damage. An
5 Resistance-grounded systems ungrounded system will pass limited In commercial and institutional
(Figure 1.4-4) are simplest with a current into the first ground fault— installations, such as office buildings,
wye connection, grounding the neutral only the charging current of the system, shopping centers, schools and hospitals,
6 point directly through the resistor. caused by the distributed capacitance lighting loads are often 50% or more
Delta systems can be grounded by to ground of the system wiring and of the total load. In addition, a feeder
means of a zig-zag or other grounding equipment. In low voltage systems, outage on first ground fault is seldom
7 transformer. Wye broken delta this is rarely more than 1 or 2A. crucial—even in hospitals, that have
transformer banks may also be used. Therefore, on first ground fault, an emergency power in critical areas. For
ungrounded system can continue in these reasons, a solidly grounded wye
8 service, making it desirable where distribution, with the neutral used for
Phase A lighting circuits, is usually the most
power outages cannot be tolerated.
• • • Phase B
However, if the ground fault is economical, effective and convenient
N
9 R • Phase C intermittent, sputtering or arcing, a design. In some instances, it is an
high voltage—as much as 6 to 8 times NEC requirement.
phase voltage—can be built up across
10 Resistance-Grounded Wye the system capacitance, from the In industrial installations, the effect
phase conductors to ground. Similar of a shutdown caused by a single
high voltages can occur as a result ground fault could be disastrous.
11 • • Phase A
An interrupted process could cause
of resonance between system
the loss of all the materials involved,
• • • Phase B capacitance and the inductances
• Phase C
of transformers and motors in the often ruin the process equipment
12 • system. The phase-to-phase voltage itself, and sometimes create extremely
N • is not affected. This high transient dangerous situations for operating
R • phase-to-ground voltage can puncture personnel. On the other hand, lighting
13 insulation at weak points, such as is usually only a small fraction of the
motor windings, and is a frequent total industrial electrical load. A solidly
Delta With Derived Neutral Resistance-
cause of multiple motor failures on grounded neutral circuit conductor
14 Grounded Using Zig-Zag Transformer
ungrounded systems. Locating a first is not imperative and, when required,
fault on an ungrounded system can can be obtained from inexpensive
Figure 1.4-4. Resistance-Grounded Systems be difficult. If, before the first fault is lighting transformers.
15 cleared, a second ground fault occurs Because of the ability to continue in
This derives a neutral point, which
can be either solidly or impedance- on a different phase, even on a operation with one ground fault on
different, remote feeder, it is a high-
16 grounded. If the grounding transformer
current phase-to-ground-to-phase
the system, many existing industrial
plants use ungrounded delta distribu-
has sufficient capacity, the neutral
created can be solidly grounded and fault, usually arcing, that can cause tion. Today, new installations can have
severe damage if at least one of the
17 used as part of a three-phase, four-wire
grounds is not cleared immediately.
all the advantages of service continuity
system. Most transformer-supplied of the ungrounded delta, yet minimize
systems are either solidly grounded If the second circuit is remote, enough the problems of the system, such
current may not flow to cause
18 or resistance grounded. Generator
protection to operate. This can leave
as the difficulty of locating the first
neutrals are often grounded through ground fault, risk of damage from a
a reactor, to limit ground fault (zero high voltages and stray currents on second ground fault, and damage
structures and jeopardize personnel.
19 sequence) currents to values the transient overvoltages. A high-
generator can withstand. In general, where loads will be resistance grounded wye distribution
connected line-to-neutral, solidly can continue in operation with a
20 grounded systems are used. High ground fault on the system and will
resistance grounded systems are not develop transient overvoltages.

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-11
August 2013 System Application Considerations
Sheet 01 067
Grounding/Ground Fault Protection

And, because the ground point is disconnecting means rated 1000A or


established, locating a ground fault is more on solidly grounded wye services Main i
less difficult than on an ungrounded of more than 150V to ground, but
system especially when a “pulsing not exceeding 600V phase-to-phase. Neutral

contactor” design is applied. When Practically, this makes ground fault


Service
Transformer
GFR
ii
combined with sensitive ground-fault protection mandatory on 480Y/277V Sensor
Typical
Feeder
protection, damage from a second services, but not on 208Y/120V services. Ground Bus

ground fault can be nearly eliminated. On a 208V system, the voltage to


Main Bonding
1
Ungrounded delta systems can be ground is 120V. If a ground fault Jumper
Typical
converted to high-resistance grounded occurs, the arc goes out at current Grounding Equipment
systems, using a zig-zag or other zero, and the voltage to ground is Electrode
Conductor
Grounding
Conductor
4W Load
2
grounding transformer to derive a often too low to cause it to restrike.
neutral, with similar benefits, see Therefore, arcing ground faults on
Tab 36. While the majority of 208V systems tend to be self-extin- Figure 1.4-5. Ground Return Sensing Method 3
manufacturing plants use solidly guishing. On a 480V system, with 277V When an energized conductor faults
grounded systems, in many instances, to ground, restrike usually takes place to grounded metal, the fault current
the high-resistance grounded distribu- after current zero, and the arc tends to returns along the ground return path to
4
tion will be the most advantageous. be self-sustaining, causing severe and the neutral of the source transformer.
increasing damage, until the fault is This path includes the main bonding
Ground Fault Protection cleared by a protective device. jumper as shown in Figure 1.4-5.
5
A ground fault normally occurs in one The NEC requires ground fault A current sensor on this conductor
of two ways: by accidental contact of protection on the service disconnecting (which can be a conventional bar-type 6
an energized conductor with normally means. This protection works so fast or window type CT) will respond to
grounded metal, or as a result of that for ground faults on feeders, or ground fault currents only. Normal
an insulation failure of an energized even branch circuits, it will often open neutral currents resulting from 7
conductor. When an insulation failure the service disconnect before the unbalanced loads will return along
occurs, the energized conductor feeder or branch circuit overcurrent the neutral conductor and will not be
contacts normally noncurrent-carrying device can operate. This is highly detected by the ground return sensor. 8
grounded metal, which is bonded to undesirable, and in the NEC (230.95)
or part of the equipment grounding This is an inexpensive method of sensing
a Fine Print Note (FPN) states that ground faults where protection per
conductor. In a solidly grounded additional ground fault protective NEC (230.95) is desired. For it to 9
system, the fault current returns to the equipment will be needed on feeders
source primarily along the equipment operate properly, the neutral must be
and branch circuits where maximum grounded in only one place as indicated
grounding conductors, with a small continuity of electric service is neces- in Figure 1.4-5. In many installations, 10
part using parallel paths such as build- sary. Unless it is acceptable to discon-
ing steel or piping. If the ground return the servicing utility grounds the neutral
nect the entire service on a ground at the transformer and additional
impedance was as low as that of the fault almost anywhere in the system, grounding is required in the service 11
circuit conductors, ground fault currents such additional stages of ground
would be high, and the normal phase equipment per NEC (250.24(A)(2)).
fault protection must be provided. In such cases, and others including
overcurrent protection would clear At least two stages of protection are multiple source with multiple, inter- 12
them with little damage. Unfortunately, mandatory in health care facilities
the impedance of the ground return connected neutral ground points,
(NEC Sec. 517.17). residual or zero sequence ground
path is usually higher, the fault itself
sensing methods should be employed. 13
is usually arcing and the impedance Overcurrent protection is designed to
of the arc further reduces the fault protect conductors and equipment A second method of detecting ground
current. In a 480Y/277V system, the against currents that exceed their faults involves the use of a zero 14
voltage drop across the arc can be ampacity or rating under prescribed sequence sensing method, as illus-
from 70 to 140V. The resulting ground time values. An overcurrent can result trated in Figure 1.4-6. This sensing
fault current is rarely enough to cause from an overload, short circuit or (high method requires a single, specially 15
the phase overcurrent protection level) ground fault condition. When designed sensor either of a toroidal
device to open instantaneously and currents flow outside the normal or rectangular shaped configuration.
prevent damage. Sometimes, the current path to ground, supplementary This core balance current transformer 16
ground fault is below the trip setting of ground fault protection equipment will surrounds all the phase and neutral
the protective device and it does not be required to sense low-level ground conductors in a typical three-phase,
trip at all until the fault escalates and fault currents and initiate the protection four-wire distribution system. The 17
extensive damage is done. For these required. Normal phase overcurrent sensing method is based on the fact
reasons, low level ground protection protection devices provide no protection that the vectorial sum of the phase and
devices with minimum time delay against low-level ground faults. neutral currents in any distribution 18
settings are required to rapidly clear circuit will equal zero unless a ground
There are three basic means of sensing
ground faults. This is emphasized by fault condition exists downstream from
ground faults. The most simple and
the NEC requirement that a ground
direct method is the ground return the sensor. All currents that flow only 19
fault relay on a service shall have a in the circuit conductors, including
method as illustrated in Figure 1.4-5.
maximum delay of one second for balanced or unbalanced phase-to-phase
This sensing method is based on the fact
faults of 3000A or more.
that all currents supplied by a trans- and phase-to-neutral normal or fault 20
The NEC (Sec. 230.95) requires that former must return to that transformer. currents, and harmonic currents, will
result in zero sensor output.
ground fault protection, set at no more
than 1200A, be provided for each service
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-12 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 068
Grounding/Ground Fault Protection

However, should any conductor become neutral. In a residual sensing scheme, levels of ground fault protection are
i grounded, the fault current will return the relationship of the polarity markings desired for added service continuity.
along the ground path—not the normal —as noted by the “X” on each sensor— Additional grounding points may be
circuit conductors—and the sensor will is critical. Because the vectorial sum of employed upstream of the residual
ii have an unbalanced magnetic flux the currents in all the conductors will sensors, but not on the load side.
condition, and a sensor output will total zero under normal, non-ground
be generated to actuate the ground faulted conditions, it is imperative Both the zero sequence and
1 fault relay. that proper polarity connections are residual sensing methods have
employed to reflect this condition. been commonly referred to as
“vectorial summation” methods.
2 Zero
Sequence
Sensor
Alternate
Sensor
Location Sensor
Most distribution systems can use
Residual
Main Polarity
Marks
Sensors either of the three sensing methods
exclusively or a combination of the
3 Main
sensing methods depending upon
Neutral the complexity of the system and
the degree of service continuity and
4 GFR
Neutral
selective coordination desired.
Typical
Feeder
Typical Different methods will be required
GFR Feeder
depending upon the number of supply
5 Typical sources, and the number and location
4W Load Typical
4W Load
of system grounding points.
6 Figure 1.4-6. Zero Sequence Sensing Method As an example, one of the more
Figure 1.4-7. Residual Sensing Method frequently used systems where
Zero sequence sensors are available continuity of service to critical loads
As with the zero sequence sensing
7 with various window openings for
method, the resultant residual sensor is a factor is the dual source system
circuits with small or large conductors, illustrated in Figure 1.4-8. This system
and even with large rectangular win- output to the ground fault relay or
integral ground fault tripping circuit uses tie-point grounding as permitted
8 dows to fit over bus bars or multiple
large size conductors in parallel. Some will be zero if all currents flow only under NEC Sec. 250.24(A)(3). The use
sensors have split cores for installation in the circuit conductors. Should a of this grounding method is limited
over existing conductors without ground fault occur, the current from to services that are dual fed (double-
9 disturbing the connections. the faulted conductor will return along ended) in a common enclosure or
the ground path, rather than on the grouped together in separate enclosures,
This method of sensing ground faults other circuit conductors, and the resid- employing a secondary tie.
10 can be employed on the main discon- ual sum of the sensor outputs will not
nect where protection per NEC (230.95) This scheme uses individual sensors
be zero. When the level of ground fault connected in ground return fashion.
is desired. It can also be easily employed
current exceeds the pre-set current
11 in multi-tier systems where additional
and time delay settings, a ground
Under tie breaker closed operating
levels of ground fault protection are conditions, either the M1 sensor or
desired for added service continuity. fault tripping action will be initiated. M2 sensor could see neutral unbalance
12 Additional grounding points may be This method of sensing ground faults currents and possibly initiate an
employed upstream of the sensor, but can be economically applied on main improper tripping operation. However,
not on the load side. with the polarity arrangements of
service disconnects where circuit break-
13 Ground fault protection employing ers with integral ground fault protection these two sensors along with the tie
ground return or zero sequence sensing are provided. It can be used in protec- breaker auxiliary switch (T/a) and
methods can be accomplished by the tion schemes per NEC (230.95) or in interconnections as shown, this
14 use of separate ground fault relays multi-tier schemes where additional possibility is eliminated.
(GFRs) and disconnects equipped with
standard shunt trip devices or by circuit
15 breakers with integral ground fault Power Power
protection with external connections Transformer Transformer
arranged for these modes of sensing. In
16 some cases, a reliable source of control
Neutral Sensor Neutral Sensor
power is needed. Main Main
Bkr. Main Bkr. 52-1 Tie Bkr. Main Bkr. 52-2 Bkr.
The third basic method of detecting 52-T 52-2
17 ground faults involves the use of
52-1
ØA, ØB, ØC ØA, ØB, ØC
multiple current sensors connected in Neutral Neutral
Neutral Sensor
a residual sensing method as illustrated
18 in Figure 1.4-7. This is a very common Typical ( )B5
Tie Bkr. 52-T
Typical
( )B5
4-Wire ( )B4
sensing method used with circuit break- ( )B4 52-T 52-T 4-Wire
M2N
M1G

M2G
M1N

Feeder
TN
TG

a a Feeder
ers equipped with electronic trip units,
19 current sensors and integral ground 33-
52-T
fault protection. The three-phase sensors 4-Wire 4-Wire
B5 B4 B4 B5 B4 B5 Load
are required for normal phase overcur- Load
Digitrip Digitrip Digitrip
20 rent protection. Ground fault sensing B4
Digitrip
B5 Main Bkr.
52-1
Main Bkr.
52-T
Main Bkr.
52-2
B4
Digitrip
B5
is obtained with the addition of an
identically rated sensor mounted on the
21 Figure 1.4-8. Dual Source System—Single Point Grounding
Note: This GF scheme requires trip units to be set to source ground sensing.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-13
August 2013 System Application Considerations
Sheet 01 069
Grounding/Ground Fault Protection

Selective ground fault tripping coordi- or a combination of all types may be GFR is an indication that any occurring
nation between the tie breaker and the employed to accomplish the desired ground fault is within the zone of the i
two main circuit breakers is achieved end results. GFR next upstream from the fault and
by pre-set current pickup and time that device will operate instantaneously
delay settings between devices GFR/1, Because the NEC (230.95) limits the to clear the fault with minimum dam- ii
GFR/2 and GFR/T. maximum setting of the ground fault age and maximum service continuity.
protection used on service equipment This operating mode permits all GFRs
The advantages of increased service to 1200A (and timed tripping at 3000A to operate instantaneously for a fault 1
continuity offered by this system can for one second), to prevent tripping within their zone and still provide
only be effectively used if additional of the main service disconnect on a complete selectivity between zones.
levels of ground fault protection are feeder ground fault, ground fault The National Electrical Manufacturers 2
added on each downstream feeder. protection must be provided on all the Association (NEMA) states, in their
Some users prefer individual grounding feeders. To maintain maximum service application guide for ground fault
of the transformer neutrals. In such continuity, more than two levels (zones) protection, that zone interlocking is 3
cases, a partial differential ground of ground fault protection will be necessary to minimize damage from
fault scheme should be used for the required, so that ground fault outages ground faults. A two-wire connection
mains and tie breaker. can be localized and service interrup- is required to carry the restraining 4
tion minimized. To obtain selectivity signal from the GFRs in one zone to
An example of a residual partial differ- between different levels of ground
ential scheme is shown in Figure 1.4-9. the GFRs in the next zone.
The scheme typically relies upon the
fault relays, time delay settings should 5
be employed with the GFR furthest Circuit breakers with integral ground
vector sum of at least two neutral downstream having the minimum fault protection and standard circuit
sensors in combination with each
breakers’ three-phase sensors. To
time delay. This will allow the GFR breakers with shunt trips activated 6
nearest the fault to operate first. by the ground fault relay are ideal for
reduce the complexity of the drawing, With several levels of protection, this ground fault protection. Many fused
each of the breakers’ three-phase
sensors have not been shown. It is
will reduce the level of protection for switches over 1200A, and Eaton Type 7
faults within the upstream GFR zones. FDP fusible switches with ratings from
absolutely critical that the sensors’ Zone interlocking was developed for 400 to 1200A, are listed by UL as suitable
polarities are supplied as shown, the GFRs to overcome this problem. for ground fault protection. Fusible 8
neutral sensor ratings of the mains and switches so listed must be equipped
tie are the same, and that there are GFRs (or circuit breakers with integral with a shunt trip, and be able to
no other grounds on the neutral bus ground fault protection) with zone open safely on faults up to 12 times 9
made downstream of points shown. interlocking are coordinated in a their rating.
system to operate in a time delayed
An infinite number of ground fault mode for ground faults occurring most Power distribution systems differ
protection schemes can be developed remote from the source. However, this widely from each other, depending
10
depending upon the number of alternate time delayed mode is only actuated upon the requirements of each user,
sources, the number of grounding points when the GFR next upstream from the and total system overcurrent protec-
and system interconnections involved. fault sends a restraining signal to the tion, including ground fault currents,
11
Depending upon the individual system upstream GFRs. The absence of a must be individually designed to meet
configuration, either mode of sensing restraining signal from a downstream these needs. Experienced and knowl-
edgeable engineers must consider the
12
power sources (utility or on-site), the
Power
Transformer
Power
Transformer
effects of outages and costs of down-
time, safety for people and equipment,
13
initial and lifecycle costs, and many
other factors. They must apply protec- 14
X X
tive devices, analyzing the time-current
X X
Neutral Neutral characteristics, fault interrupting
Sensor Main Sensor Main
Main Breaker 52-1 Breaker 52-2 Main
capacity, and selectivity and coordina- 15
Breaker Breaker tion methods to provide the most safe
52-1 52-2 and cost-effective distribution system.
Phase A, Tie Breaker Phase A, Further Information 16
Phase B, 52-T Phase B, ■ PRSC-4E—System Neutral Ground-
Phase C Phase C
Neutral X
Neutral
ing and Ground Fault Protection
(ABB Publication)
17
Neutral Sensor X
Tie Breaker 52-T ■ PB 2.2—NEMA Application Guide
Trip Unit
Trip Unit

Typical X
X
Typical X
X
for Ground Fault Protective Devices 18
Four-Wire Four-Wire for Equipment
Feeder 52-1 52-T 52-2 Feeder
a a a ■ IEEE Standard 142—Grounding of
Industrial and Commercial Power 19
Four-Wire Load Four-Wire Load
Systems (Green Book)
Trip Unit Trip Unit Trip Unit ■ IEEE Emerald Book (Standard 1100)
Main Breaker Tie Breaker Main Breaker
■ UL 96A, Installation Requirements
20
52-1 52-T 52-2
for Lightning Protection Systems
Figure 1.4-9. Dual Source System—Multiple Point Grounding 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-14 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 070
Grounding/Ground Fault Protection

Lightning and Surge Protection The electrical distribution system and Surge Protection
i Physical protection of buildings
equipment ground must be connected
Eaton’s VacClad-W metal-clad switch-
to this grounding electrode system by
from direct damage from lightning a grounding electrode conductor. All gear is applied over a broad range of
ii is beyond the scope of this section.
Requirements will vary with geographic
other grounding electrodes, such as circuits, and is one of the many types
of equipment in the total system. The
those for the lightning protection sys-
location, building type and environ- tem, the telephone system, television distribution system can be subject to
1 ment, and many other factors (see antenna and cable TV system grounds, voltage transients caused by lighting
IEEE/ANSI Standard 142, Grounding and computer systems, must be bonded or switching surges.
of Industrial and Commercial Power to this grounding electrode system. Recognizing that distribution system
2 Systems). Any lightning protection
can be subject to voltage transients
system must be grounded, and the Medium Voltage Equipment Surge
lightning protection ground must be caused by lighting or switching, the
3 bonded to the electrical equipment Protection Considerations industry has developed standards to
grounding system. provide guidelines for surge protection
Transformers of electrical equipment. Those guide-
Grounding Electrodes lines should be used in design and
4 If the voltage withstand/BIL rating of
the transformer is less than that of the protection of electrical distribution
At some point, the equipment and systems independent of the circuit
switchgear feeding the transformer,
system grounds must be connected breaker interrupting medium. The
5 to the earth by means of a grounding
surge protection is recommended at
the transformer terminals, in line with industry standards are:
electrode system.
established practices. In addition, ANSI C62
6 Outdoor substations usually use a consideration should be given to using Guides and Standards for Surge
ground grid, consisting of a number of surge arresters and/or surge capacitors Protection
ground rods driven into the earth and for transformers having equal or
7 bonded together by buried copper greater withstand/BIL ratings than that IEEE 242—Buff Book
conductors. The required grounding of the switchgear feeding the trans- IEEE Recommended Practice for
electrode system for a building is former for distribution systems where Protection and Coordination of
8 spelled out in the NEC Article 250. reflected voltage waves and/or reso- Industrial and Commercial Power
nant conditions may occur. Typically Systems
The preferred grounding electrode incoming voltage surges are reflected
is a metal underground water pipe in IEEE 141—Red Book
9 direct contact with the earth for at least
at the transformer primary terminals
Recommended Practice for
(because of the change in impedance)
10 ft (3m). However, because under- resulting in voltages at the ends of the Electric Power Distribution for
ground water piping is often plastic Industrial Plants
10 outside the building, or may later be
transformer primary terminals/wind-
ings of up to two times the incoming IEEE C37.20.2
replaced by plastic piping, the NEC voltage wave. System capacitance and Standards for Metal-Clad Switchgear
11 requires this electrode to be supple- inductance values combined with the
mented by and bonded to at least one transformer impedance values can Eaton’s medium voltage metal-clad
other grounding electrode, such as cause resonant conditions resulting and metal-enclosed switchgear that
12 the effectively grounded metal frame
of the building, a concrete-encased
in amplified reflected waves. Surge uses vacuum circuit breakers is applied
arresters/capacitors when required, over a broad range of circuits. It is one
electrode, a copper conductor ground should be located as close to the trans- of the many types of equipment in the
13 ring encircling the building, or a made former primary terminals as practical. total distribution system. Whenever a
electrode such as one or more driven switching device is opened or closed,
ground rods or a buried plate. Where Motors certain interactions of the power
14 any of these electrodes are present, Surge capacitors and, where appropri- system elements with the switching
they must be bonded together into ate, surge arresters should be applied device can cause high frequency voltage
one grounding electrode system. at the motor terminals. transients in the system. Due to the
15 One of the most effective grounding Generators
wide range of applications and variety
of ratings used for different elements
electrodes is the concrete-encased Surge capacitors and station in the power systems, a given circuit
electrode, sometimes called the Ufer
16 ground, named after the man who
class surge arresters at the machine may or may not require surge protec-
terminals. tion. Therefore, Eaton does not include
developed it. It consists of at least
surge protection as standard with its
20 ft (6m) of steel reinforcing bars or
17 rods not less than 1/2 inches (12.7 mm)
metal-clad or metal-enclosed medium
voltage switchgear. The user exercises
in diameter, or at least 20 ft (6m) of
the options as to the type and extent
bare copper conductor, size No. 4 AWG
18 or larger, encased in at least 2 inches
of the surge protection necessary
depending on the individual circuit
(50.8 mm) of concrete. It must be
characteristics and cost considerations.
located within and near the bottom of
19 a concrete foundation or footing that The following are Eaton’s recommen-
is in direct contact with the earth. Tests dations for surge protection of medium
have shown this electrode to provide voltage equipment. Please note these
20 a low-resistance earth ground even in recommendations are valid when
poor soil conditions. using Eaton’s vacuum breakers only.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-15
August 2013 System Application Considerations
Sheet 01 071
Grounding/Ground Fault Protection

Surge Protection Recommendations RC Snubber and/or ZORC damp 6. Capacitor Switching—No surge
Note: The abbreviation ZORC® used in the internal transformer resonance: protection is required. Make sure i
text below refers to Surge Protection Device that the capacitor’s lightning
manufactured by Strike Technology (Pty) The natural frequency of transformer impulse withstand rating is equal
Ltd. An equivalent device offered by other windings can under some circumstances to that of the switchgear. ii
manufacturers, such as Type EHZ by ABB, be excited to resonate. Transformer
and Protec Z by Northern Technologies SA windings in resonance can produce 7. Shunt Reactor Switching—
can also be used. elevated internal voltages that produce Provide Surge Arrester in parallel 1
insulation damage or failure. An RC with RC Snubber, or ZORC at the
1. For circuits exposed to lightning, Snubber or a ZORC applied at the reactor terminals.
surge arresters should be applied transformer terminals as indicated 2
in line with Industry standard above can damp internal winding 8. Motor Starting Reactors or Reduced
practices. resonance and prevent the production Voltage Auto-Transformers—
Provide Surge Arrester in parallel
2. Transformers
of damaging elevated internal voltages.
with RC Snubber, or ZORC at the 3
This is typically required where rectifiers,
UPS or similar electronic equipment is reactor or RVAT terminals.
a. Close-Coupled to medium
voltage primary breaker: on the transformer secondary. 9. Switching Underground Cables— 4
Provide transients surge pro- Surge protection not needed.
3. Arc-Furnace Transformers—
tection, such as Surge Arrester
Provide Surge Arrester in parallel
in parallel with RC Snubber, or
with RC Snubber, or ZORC at the Types of Surge Protection Devices 5
ZORC. The surge protection
transformer terminals. Generally surge protective devices
device selected should be
should be located as closely as possible
located and connected at the 4. Motors—Provide Surge Arrester in to the circuit component(s) that require
6
transformer primary terminals parallel with RC Snubber, or ZORC
or it can be located inside the protection from the transients, and
at the motor terminals. For those connected directly to the terminals of
switchgear and connected on motors using VFDs, surge protec- the component with conductors that
7
the transformer side of the tion should be applied and pre-
primary breaker. are as short and flat as possible to
cede the VFD devices as well. minimize the inductance. It is also
b. Cable-Connected to medium important that surge protection devices
8
5. Generators—Provide station class
voltage primary breaker: should be properly grounded for
Surge Arrester in parallel with RC
Provide transient surge protec- effectively shunting high frequency
tion, such as Surge Arrester in
Snubber, or ZORC at the generator
transients to ground.
9
terminals.
parallel with RC Snubber, or
ZORC for transformers con-
nected by cables with lengths 10
up to 75 feet. The surge protec-
tion device should be located
and connected at the trans- 11
former terminals. No surge
protection is needed for trans-
formers with lightning impulse
12
withstand ratings equal to that
of the switchgear and connected
to the switchgear by cables at
13
least 75 feet or longer. For
transformers with lower BIL,
provide surge arrester in parallel Figure 1.4-10. Surge Protection Devices 14
with RC Snubber or ZORC.
15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-16 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 072
Grounding/Ground Fault Protection

Surge Arresters Surge Capacitors ZORC


i The modern metal-oxide surge Metal-oxide surge arresters limit the A ZORC device consists of parallel
arresters are recommended because magnitude of prospective surge over- combination of Resistor (R) and Zinc
this latest advance in arrester design voltage, but are ineffective in control- Oxide Voltage Suppressor (ZnO), con-
ii ensures better performance and high ling its rate of rise. Specially designed nected in series with a Surge Capacitor.
reliability of surge protection schemes. surge capacitors with low internal The resistor R is sized to match surge
Manufacturer’s technical data must inductance are used to limit the rate of impedance of the load cables, typically
1 be consulted for correct application rise of this surge overvoltage to protect 20 to 30 ohms. The ZnO is a gapless
of a given type of surge arrester. turn-to-turn insulation. Recommended metal-oxide nonlinear arrester, set
Notice that published arrester MCOV values for surge capacitors are: 0.5 µf to trigger at 1 to 2 PU voltage, where
2 (Maximum Continuous Operating on 5 and 7.5 kV, 0.25 µf on 15 kV, and 1 PU = 1.412*(VL-L/1.732). The Surge
Voltage) ratings are based on 40º or 0.13 µf on systems operating at 24 kV Capacitor is typically sized to be 0.15
45ºC ambient temperature. In general, and higher. to 0.25 microfarad. As with RC Snubber,
3 the following guidelines are recom- under normal operating conditions,
mended for arrester selections, when RC Snubber impedance of the capacitor is very
installed inside Eaton’s medium A RC Snubber device consists of a high, effectively “isolating” the resistor
4 voltage switchgear: non-inductive resistor R sized to match R and ZnO from the system at normal
surge impedance of the load cables, power frequencies, and minimizing
A. Solidly Grounded Systems: typically 20 to 30 ohms, and connected heat dissipation during normal opera-
5 Arrester MCOV rating should be in series with a Surge Capacitor C. The tion. Under high frequency transient
equal to 1.05 x VLL/(1.732 x T), Surge Capacitor is typically sized to be conditions, the capacitor offers very
where VLL is nominal line-to-line 0.15 to 0.25 microfarad. Under normal low impedance, thus effectively
6 service voltage, 1.05 factor allows operating conditions, impedance of “inserting” the resistor R and ZnO in
for +5% voltage variation above the capacitor is very high, effectively the power system as cable terminating
the nominal voltage according “isolating” the resistor R from the network, thus minimizing reflection of
7 to ANSI C84.1, and T is derating system at normal power frequencies, the steep wave-fronts of the voltage
factor to allow for operation at and minimizing heat dissipation during transients and prevents voltage dou-
55ºC switchgear ambient, which normal operation. Under high frequency bling of the traveling wave. The ZnO
8 should be obtained from the transient conditions, the capacitor element limits the peak voltage magni-
arrester manufacturer for the type offers very low impedance, thus effec- tudes. The combined effects of R, ZnO,
of arrester under consideration. tively “inserting” the resistor R in the and Capacitor of the ZORC device
9 Typical values of T are: 0.946 to 1.0. power system as cable terminating provides optimum protection against
B. Low Resistant Grounded Systems resistor, thus minimizing reflection of high frequency transients by absorbing,
the steep wave-fronts of the voltage damping, and by limiting the peak
10 (systems grounded through
transients and prevents voltage dou- amplitude of the voltage wave-fronts.
resistor rated for 10 seconds):
Arrester 10-second MCOV capability bling of the traveling wave. The RC Please note that the ZORC is not a
Snubber provides protection against lightning protection device. If lightning
11 at 60ºC, which is obtained from
high frequency transients by absorb- can occur or be induced in the electrical
manufacturer’s data, should be
equal to 1.05 x VLL, where VLL is ing and damping and the transients. system, a properly rated and applied
Please note RC Snubber is most effec-
12 nominal line-to-line service voltage,
tive in mitigating fast-rising transient
surge arrester must precede the ZORC.
and 1.05 factor allows for +5%
voltage variation above the voltages, and in attenuating reflections
13 nominal voltage. and resonances before they have a
chance to build up, but does not limit
C. Ungrounded or Systems the peak magnitude of the transient.
14 Grounded through impedance Therefore, the RC Snubber alone may
other than 10-second resistor: not provide adequate protection. To
Arrester MCOV rating should be limit peak magnitude of the transient,
15 equal to 1.05 x VLL/T, where VLL application of surge arrester should
and T are as defined above. also be considered.
Refer to Table 1.4-3 for recommended
16 ratings for metal-oxide surge arresters
that are sized in accordance with the
above guidelines, when located in
17 Eaton’s switchgear.

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-17
August 2013 System Application Considerations
Sheet 01 073
Grounding/Ground Fault Protection

Surge Protection Summary Good protection: Surge Arrester Best protection: ZORC, plus proper
Minimum protection: Surge Arrester
in parallel with Surge Capacitor for surge arrester preceding ZORC where i
protection from high overvoltage needed for protection against lightning.
for protection from high overvoltage peaks and fast rising transient. This ZORC provides protection from high
peaks, or Surge Capacitor for protec- option may not provide adequate frequency voltage transients and limits ii
tion from fast-rising transient. Please surge protection from escalating peak magnitude of the transient to
note that the surge arresters or surge voltages caused by circuit resonance. 1 to 2 PU (see ZORC description on
capacitor alone may not provide When applying surge capacitors on Page 1.4-16 for more detail). Surge 1
adequate surge protection from both sides of a circuit breaker, surge arrester provides protection from
escalating voltages caused by circuit capacitor on one side of the breaker higher voltage peaks resulting from
resonance. Note that when applying must be RC Snubber or ZORC, lightning surges. 2
surge capacitors on both sides of a to mitigate possible virtual
circuit breaker, surge capacitor on current chopping. Further Information
one side of the breaker must be ■ IEEE/ANSI Standard 142—Grounding 3
RC Snubber or ZORC, to mitigate Better protection: RC Snubber in Industrial and Commercial Power
possible virtual current chopping. parallel with Surge Arrester for Systems (Green Book)
protection from high frequency
■ IEEE Standard 241—Electric Power 4
transients and voltage peaks.
Systems in Commercial Buildings
(Gray Book)
■ IEEE Standard 141—Electric Power
5
Distribution for Industrial Plants
(Red Book)
6
Table 1.4-3. Surge Arrester Selections—Recommended Ratings
Service Distribution Class Arresters Station Class Arresters
Voltage Solidly Low Resistance High Resistance or Solidly Low Resistance High Resistance or
7
Line-to-Line Grounded System Grounded System Ungrounded System Grounded System Grounded System Ungrounded System
kV
Arrester Ratings kV
Nominal MCOV Nominal MCOV Nominal MCOV
Arrester Ratings kV
Nominal MCOV Nominal MCOV Nominal MCOV
8
2.30 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55
2.40 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10 9
3.30 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
4.00 3 2.55 6 5.10 6 5.10 3 2.55 6 5.10 6 5.10
4.16
4.76
6
6
5.10
5.10
6
6
5.10
5.10
6
9
5.10
7.65
6
6
5.10
5.10
6
6
5.10
5.10
6
9
5.10
7.65
10
4.80 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.60 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.90 6 5.10 6 5.10 9 7.65 6 5.10 9 7.65 9 7.65 11
7.20 6 5.10 6 5.10 10 8.40 6 5.10 9 7.65 10 8.40
8.32 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
8.40 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20 12
11.00 9 7.65 9 7.65 15 12.70 9 7.65 10 8.40 15 12.70
11.50 9 7.65 10 8.40 18 15.30 9 7.65 12 10.20 18 15.30
12.00 10 8.40 10 8.40 18 15.30 10 8.40 12 10.20 18 15.30
13
12.47 10 8.40 12 10.20 18 15.30 10 8.40 12 10.20 18 15.30
13.20 12 10.20 12 10.20 18 15.30 12 10.20 12 10.20 18 15.30
13.80 12 10.20 12 10.20 18 15.30 12 10.20 15 12.70 18 15.30
14.40 12 10.20 12 10.20 21 17.00 12 10.20 15 12.70 21 17.00
14
18.00 15 12.70 15 12.70 27 22.00 15 12.70 18 15.30 27 22.00
20.78 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.00 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40 15
22.86 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
23.00 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
24.94
25.80
21
21
17.00
17.00
24
24
19.50
19.50




21
21
17.00
17.00
24
24
19.50
19.50
36
36
29.00
29.00
16
26.40 21 17.00 24 19.50 — — 21 17.00 27 22.00 39 31.50
33.00
34.50
27
30
22.00
24.40
30
30
24.40
24.40




27
30
22.00
24.40
36
36
29.00
29.00
45
48
36.50
39.00 17
38.00 30 24.40 — — — — 30 24.40 36 29.00 — —

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-18 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 074
Power Quality

i Power Quality Terms Defining the Problem Another option is to buy power condi-
Power quality problems can be resolved tioning equipment to correct any and
Technical Overview in three ways: by reducing the variations all perceived power quality problems
in the power supply (power distur- without any on-site investigation.
ii Introduction bances), by improving the load equip- Power Quality Terms
Sensitive electronic loads deployed ment’s tolerance to those variations, or
by inserting some interface equipment Power disturbance: Any deviation
today by users require strict require-
1 ments for the quality of power delivered (known as power conditioning equip- from the nominal value (or from some
ment) between the electrical supply selected thresholds based on load
to loads.
and the sensitive load(s) to improve the tolerance) of the input AC power
2 For electronic equipment, power compatibility of the two. Practicality characteristics.
disturbances are defined in terms of and cost usually determine the extent Total harmonic distortion or distortion
amplitude and duration by the elec- to which each option is used.
3 factor: The ratio of the root-mean-
tronic equipment operating envelope.
Many methods are used to define square of the harmonic content to the
Electronic loads may be damaged
power quality problems. For example, root-mean-square of the fundamental
and disrupted, with shortened life
4 expectancy, by disturbances. one option is a thorough on-site quantity, expressed as a percentage
of the fundamental.
investigation, which includes inspecting
The proliferation of computers, variable wiring and grounding for errors, Crest factor: Ratio between the
5 frequency motor drives, UPS systems monitoring the power supply for peak value (crest) and rms value of
and other electronically controlled power disturbances, investigating a periodic waveform.
equipment is placing a greater demand equipment sensitivity to power distur-
6 on power producers for a disturbance- bances, and determining the load Apparent (total) power factor: The
free source of power. Not only do these disruption and consequential effects ratio of the total power input in watts
types of equipment require quality (costs), if any. In this way, the power to the total volt-ampere input.
7 power for proper operation; many quality problem can be defined,
Sag: An rms reduction in the AC
times, these types of equipment are alternative solutions developed,
also the sources of power disturbances voltage, at the power frequency, for
and optimal solution chosen.
8 that corrupt the quality of power in a the duration from a half-cycle to a few
seconds. An undervoltage would have
given facility. Before applying power-conditioning
equipment to solve power quality a duration greater than several seconds.
Power quality is defined according
9 to IEEE Standard 1100 as the concept
problems, the site should be checked
Interruption: The complete loss of
for wiring and grounding problems.
of powering and grounding electronic voltage for a time period.
Sometimes, correcting a relatively
10 equipment in a manner that is suitable inexpensive wiring error, such as a Transient: A sub-cycle disturbance
to the operation of that equipment. loose connection or a reversed neutral in the AC waveform that is evidenced
IEEE Standard 1159 notes that “within and ground wire, can avoid a more by a sharp brief discontinuity of the
11 the industry, alternate definitions or expensive power conditioning solution. waveform. May be of either polarity
interpretations of power quality have and may be additive to or subtractive
been used, reflecting different points Sometimes this approach is not practical
from the nominal waveform.
of view.” because of limitations in time; expense
12 is not justified for smaller installations; Surge or impulse: See transient.
In addressing power quality problems monitoring for power disturbances
at an existing site, or in the design may be needed over an extended Noise: Unwanted electrical signals
13 stages of a new building, engineers period of time to capture infrequent that produce undesirable effects
need to specify different services or disturbances; the exact sensitivities of in the circuits of control systems
mitigating technologies. The lowest the load equipment may be unknown in which they occur.
14 cost and highest value solution is and difficult to determine; and finally,
to selectively apply a combination Common-mode noise: The noise
the investigative approach tends to voltage that appears equally and in
of different products and services solve only observed problems. Thus
15 as follows: unobserved or potential problems
phase from each current-carrying
conductor to ground.
Key services/technologies in the may not be considered in the solution.
16 “power quality” industry: For instance, when planning a new Normal-mode noise: Noise signals
facility, there is no site to investigate. measurable between or among active
■ Power quality surveys, analysis Therefore, power quality solutions are circuit conductors feeding the subject
17 and studies often implemented to solve potential load, but not between the equipment
■ Power monitoring or perceived problems on a preventive grounding conductor or associated
■ Grounding products and services basis instead of a thorough on-site signal reference structure and the active
18 ■ Surge protection
investigation. circuit conductors.
■ Voltage regulation
19 ■ Harmonic solutions
■ Lightning protection (ground rods,
hardware, etc.)
20 ■ Uninterruptible power supply (UPS)
or motor-generator (M-G) set
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-19
August 2013 System Application Considerations
Sheet 01 075
Power Quality

Methodology for Ensuring Effective The proliferation of communication The benefit of implementing cascaded
Power Quality to Electronic Loads and computer network systems network protection is shown in i
The power quality pyramid is an has increased the need for proper Figure 1.4-12. Combined, the two
effective guide for addressing power grounding and wiring of AC and data/ stages of protection at the service
quality problems at an existing facility. communication lines. In addition to entrance and branch panel locations ii
The framework is also effective for reviewing AC grounding and bonding reduce the IEEE 62.41 recommended
specifying engineers who are design- practices, it is necessary to prevent test wave (C3–20 kV, 10 kA) to less than
ing a new facility. Power quality starts ground loops from affecting the signal 200V voltage, a harmless disturbance 1
with grounding (the base of the reference point. level for 120V rated sensitive loads.
pyramid) and then moves upward
to address the potential issues. This 2. Surge Protection If only building entrance feeder 2
protection were provided, the let-
simple, yet proven methodology, Surge protection devices (SPDs) through voltage will be approximately
will provide the most cost-effective are recommended as the next stage
approach. As we move higher up the power quality solutions. NFPA,
950V in a 277/480V system exposed 3
to induced lightning surges. This
pyramid, the cost per kVA of mitigating UL 96A, IEEE Emerald Book and level of let-through voltage can cause
potential problems increase and the equipment manufacturers recommend
quality of the power increases (refer the use of surge protectors. The
degradation or physical damage of 4
most electronic loads.
to Figure 1.4-11). SPD shunt short duration voltage
disturbances to ground, thereby Wherever possible, consultants,
preventing the surge from affecting specifiers and application engineers
5
electronic loads. When installed as should ensure similar loads are fed
part of the facility-wide design, SPDs from the same source. In this way,
are cost-effective compared to all disturbance-generating loads are
6
Cost Per kVA

other solutions (on a $/kVA basis). separated from electronic circuits


affected by power disturbances. For
The IEEE Emerald Book recommends example, motor loads, HVAC systems
7
the use of a two-stage protection and other linear loads should be
concept. For large surge currents, separated from the sensitive process
diversion is best accomplished in control and computer systems.
8
two stages: the first diversion should
be performed at the service entrance The most effective and economic
5. Uninterruptible Power Supply to the building. Then, any residual solution for protecting a large number 9
(UPS, Gen. Sets, etc.) of loads is to install parallel SPDs at
voltage resulting from the action
4. Harmonic Distortion can be dealt with by a second the building service entrance feeder
3. Voltage Regulation protective device at the power and panelboard locations. This reduces 10
panel of the computer room the cost of protection for multiple
2. Surge Protection
(or other critical loads). sensitive loads.
1. Grounding 11
Figure 1.4-11. Power Quality Pyramid
12
1. Grounding Input—high energy
SPD
transient disturbance; IEEE Category
Grounding represents the foundation CP
SPD C3 Impulse 20,000V; 10,000A 13
of a reliable power distribution 480V 120/208V
20,000V
PEAK VOLTAGE

system. Grounding and wiring


problems can be the cause of up to Computer or
Sensitive
Best achievable
performance with single SPD
14
80% of all power quality problems. Stage 1 Protection Loads
at main panel (950V, at Stage 1)
All other forms of power quality (Service Entrance) Stage 2 Protection
solutions are dependent upon good
System Test Parameters:
(Branch Location)
800V 15
grounding procedures. 400V
IEEE C62.41[10] and C62.45 [10]
test procedures using category; 0
480V main entrance panels; 25 uS 50 uS
TIME (MICROSECONDS)
16
100 ft (30m) of three-phase wire;
480/208V distribution transformer; Two stage (cascade
and 208V branch panel. approach) achieves best
possible protection (less
17
= SPD than 200V at Stage 2)

Figure 1.4-12. Cascaded Network Protection


18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-20 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 076
Power Quality

The recommended system approach ■ Building entrance SPDs protect tion wires, the area between wires is
i for installing SPDs is summarized in the facility against large external reduced and the mutual inductance
Figure 1.4-13. transients, including lightning affect minimized.
■ SPDs are bi-directional and prevent
ii transient and noise disturbances
Increasing the diameter of the installation
1. wires is of negligible benefit. Induc-
Identify Critical Loads from feeding back within a system tance is a “skin effect” phenomenon and
when installed at distribution or
1 branch panels
a function of wire circumference. Since
2. only a marginal reduction in inductance
Identify Non-Critical Loads ■ Two levels of protection safeguard is achieved when the diameter of the
sensitive loads from physical
2 damage or operational upset
installation conductors is increased,
3.
the use of large diameter wire results
Identify Noise and in only minimal improvement (see
Side-Mounted SPD vs. Integral SPD
3 Disturbance Generating Loads
Directly connecting the surge sup-
Figure 1.4-15).
presser to the bus bar of electrical Further benefits provided by integrated
4. distribution equipment results in surge suppression designs are the
4 Review Internal Power Distribution Layout
the best possible level of protection. elimination of field installation costs and
Compared to side-mounted devices, the amount of expensive “outboard”
5. connecting the SPD unit to the bus wall space taken up by side-mounted
5 Identify Facility Exposure to bar eliminates the need for lead wires SPD devices.
Expected Levels of Disturbance
and reduces the let-through voltage
up to 50% (see Figure 1.4-14). Building Entrance Feeder Installation
6 6. Considerations
Apply Mitigating Equipment to: Given that surges are high frequency Installing an SPD device immediately
a) Service Entrance Main Panels disturbances, the inductance of the after the switchgear or switchboard
7 b) Key Sub-Panels installation wiring increases the main breaker is the optimal location
c) Critical Loads
let-through voltage of the protective for protecting against external distur-
d) Data and Communication Lines
device. Figure 1.4-15 shows that bances such as lightning. When placed
8 for every inch of lead length, the in this location, the disturbance is
Figure 1.4-13. System Approach for Installing SPDs let-through voltage is increased by “intercepted” by the SPD and reduced
There may be specific critical loads an additional 15–25V above the to a minimum before reaching the
9 within a facility that require a higher manufacturers stated suppression distribution and/or branch panel(s).
level of protection. A series SPD is best performance.
suited for protecting such loads. The use of a disconnect breaker
10 Lead length has the greatest effect on eliminates the need to de-energize
Advantages of the system approach are: the actual level of protection realized. the building entrance feeder equip-
Twisting of the installation wires is ment should the SPD fail or require
11 ■ The lowest possible investment the second most important installation
in mitigating equipment to protect isolation for Megger testing.
consideration. By twisting the installa-
a facility
12
208Y/120 Panelboard
13 (integrated versus side mounted SPD)

1000 Side-Mounted SPD Device


Side-Mounted SPD SPD Integrated
Let-Through Voltage at Bus Bar

(assuming 14-inch (355.6 mm) lead length to bus)


14 used for Retrofit into Panelboards,
800
Applications Switchboards, MCCs

15 600

N 400
SPD
16 Integrated SPD
SPD (direct bus bar connection)
200

17 0
GRO UND G RO UND

Surge
Event
18 G
G
–200
–2.00 0.00 2.00 4.00 6.00 8.00 10.00
N
\
Microseconds
19
Figure 1.4-14. Performance Comparison of Side-Mounted vs. Integrated SPD
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-21
August 2013 System Application Considerations
Sheet 01 077
Power Quality

Reference Tab 34 for detailed


Additional Let-Through Voltage Using IEEE C1(6000V, 3000A)[3] information on SPDs. i
Additional Let-Through Voltage ➀

Waveform (UL 1449 Test Wave)[12]


900 14 AWG 3. Voltage Regulation
800
700
209V (23%) 10 AWG
Voltage regulation (i.e., sags or over-
ii
4 AWG
600
673V (75%) voltage) disturbances are generally
500
site- or load-dependent. A variety of
400
mitigating solutions are available
1
300
200 depending upon the load sensitivity,
100 fault duration/magnitude and the
0
specific problems encountered. It is
2
3 ft (914.4 mm) 1 ft (304.8 mm)
Lead Length Lead Length, recommended to install monitoring
Loose Wiring Twisted Wires Twisted Wires equipment on the AC power lines to 3
assess the degree and frequency of
Figure 1.4-15. The Effect of Installation Lead Length on Let-Through Voltage occurrences of voltage regulation
 Additional to UL 1449 ratings. problems. The captured data will allow 4
for the proper solution selection.
The size or capacity of a suppressor is switch is about 50–60V. This increase
measured in surge current per phase. in disturbance voltage can result in 4. Harmonics Distortion 5
Larger suppressers rated at approxi- process disruption and downtime.
mately 250 kA per phase should be Harmonics and Nonlinear Loads
installed at the service entrance to Installing Dataline Surge Protection
survive high-energy surges associated Most facilities also have communica-
Until recently, most electrical loads were 6
linear. Linear loads draw the full sine
with lightning. tion lines that are potential sources wave of electric current at its 60 cycle
for external surges. As identified by
A 250 kA per phase surge rating allows the power quality pyramid, proper
(Hz) fundamental frequency—Figure 7
for over a 25-year life expectancy 1.4-16 shows balance single-phase,
grounding of communication lines is linear loads. As the figure shows,
assuming an IEEE defined high essential for dependable operation.
exposure environment. Lower surge NEC Article 800 states that all data,
little or no current flows in the neutral 8
rating devices may be used; however, conductor when the loads are non-
power and cable lines be grounded linear and balanced.
device reliability and long-term and bonded.
performance may be compromised. With the arrival of nonlinear electronic
9
Power disturbances such as lightning loads, where the AC voltage is con-
For aerial structures, the 99.8 percentile can elevate the ground potential verted to a DC voltage, harmonics are
recorded lightning stroke current is between two communicating pieces created because of the use of only part
10
less than 220 kA. The magnitude of of electronic equipment with different
surges conducted or induced into a of the AC sine wave. In this conversion
ground references. The result is current from AC to DC, the electronics are turned
facility electrical distribution system is flowing through the data cable, causing on in the 60 cycle wave at a given point
11
considerably lower given the presence component failure, terminal lock-up,
of multiple paths for the surge to travel in time to obtain the required DC level.
data corruption and interference. The use of only part of the sign wave
along. It is for this reason that IEEE
causes harmonics.
12
C62.41 recommends the C3 (20 kV, NFPA 780 D—4.8 warns that “surge
10 kA) test wave for testing SPDs suppression devices should be installed It is important to note that the current
installed at building entrance feeders. on all wiring entering or leaving elec- distortion caused by loads such as rec- 13
tronic equipment, usually power, data tifiers or switch mode power supplies
SPDs with surge ratings greater than or communication wiring.” causes the voltage distortion. That
250 kA are not required, however, higher
ratings are available and may provide Surge suppressers should be installed voltage distortion is caused by distorted 14
longer life. at both ends of a data or communica- currents flowing through an impedance.
tion cable. In those situations where The amount of voltage distortion
Installing Panelboard Surge one end of the cable is not connected depends on: 15
Protection Devices into an electronic circuit (e.g., contactor ■ System impedance
Smaller surge capacity SPDs (120 kA coil), protection on the electronic end 16
■ Amount of distorted current
per phase) are installed at branch pan- only is required.
elboards where power disturbances Devices that can cause harmonic
To prevent the coupling or inducing of
are of lower energy, but occur much
power disturbances into communication
disturbances include rectifiers, thrust- 17
more frequently. This level of surge ers and switching power supplies, all
current rating should result in a lines, the following should be avoided:
of which are nonlinear. Further, the
greater than 25-year life expectancy. ■ Data cables should not be run over proliferation of electronic equipment 18
fluorescent lighting fixtures such as computers, UPS systems,
When isolated ground systems are
■ Data cables should not be in the variable speed drives, programmable
used, the SPD should be installed such
that any common mode surges are vicinity of electric motors logic controllers, and the like: non- 19
linear loads have become a significant
shunted to the safety ground. ■ The right category cable should
part of many installations. Other types
be used to ensure transmission
The use of a disconnect breaker is performance
of harmonic-producing loads include 20
optional. The additional let-through arcing devices (arc furnaces, fluores-
■ Data cables must be grounded at cent lights) and iron core storable
voltage resulting from the increased
inductance caused by the disconnect both ends when communicating devices (transformers, especially 21
between buildings during energization).

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-22 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 078
Power Quality

Nonlinear load currents vary widely present on the three phases add Harmonic Issues
i from a sinusoidal wave shape; often together in the neutral, as shown in
Harmonic currents perform no work
they are discontinuous pulses. This Figure 1.4-17, rather than cancel each
means that nonlinear loads are other out, as shown in Figure 1.4-16. and result in wasted electrical energy
ii that may over burden the distribution
extremely high in harmonic content. Odd non-triplen harmonics are
system. This electrical overloading
classified as “positive sequence”
Triplen harmonics are the 3rd, 9th, may contribute to preventing an
or “negative sequence” and are the
existing electrical distribution system
1 15th,...harmonics. Further, triplen 1st, 5th, 7th, 11th, 13th, etc.
from serving additional future loads.
harmonics are the most damaging
to an electrical system because these In general, as the order of a harmonic In general, harmonics present on
2 harmonics on the A-phase, B-phase gets higher, its amplitude becomes a distribution system can have the
and C-phase are in sequence with each smaller as a percentage of the funda- following detrimental effects:
other. Meaning, the triplen harmonics mental frequency.
3 1. Overheating of transformers and
rotating equipment.
60 Hz Fundamental
2. Increased hysteresis losses.
4
3. Decreased kVA capacity.
A Phase
4. Overloading of neutral.
5
5. Unacceptable neutral-to-ground
voltages.
6 120º 6. Distorted voltage and current
Lagging waveforms.
B Phase
7 7. Failed capacitor banks.
8. Breakers and fuses tripping.
8 9. Double or ever triple sized neutrals
120º
Lagging
to defy the negative effects of
C Phase triplen harmonics.
9
In transformers, generators and
uninterruptible power supplies (UPS)
10 Balance
systems, harmonics cause overheating
Neutral and failure at loads below their ratings
Current because the harmonic currents cause
11 greater heating than standard 60 Hz
current. This results from increased
Figure 1.4-16. Balanced Neutral Current Equals Zero eddy current losses, hysteresis losses
12 in the iron cores, and conductor skin
effects of the windings. In addition,
60 Hz Fundamental the harmonic currents acting on the
13 3rd Harmonic impedance of the source cause
harmonics in the source voltage, which
A Phase is then applied to other loads such as
14 motors, causing them to overheat.
The harmonics also complicate the
15 application of capacitors for power
120º factor correction. If, at a given harmonic
B Phase
Lagging
frequency, the capacitive impedance
16 equals the system reactive impedance,
the harmonic voltage and current can
reach dangerous magnitudes. At the
17 120º C Phase
same time, the harmonics create
Lagging problems in the application of power
factor correction capacitors, they
18 lower the actual power factor. The
rotating meters used by the utilities for
watthour and various measurements
19 Neutral
Triplen
do not detect the distortion component
caused by the harmonics. Rectifiers
Current
with diode front ends and large DC side

20 Phase Triplen Harmonics


capacitor banks have displacement
Added in the Neutral power factor of 90% to 95%. More
recent electronic meters are capable
21 Figure 1.4-17. Unbalanced Single-Phase Loads with Triplen Harmonics
of metering the true kVA hours taken
by the circuit.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-23
August 2013 System Application Considerations
Sheet 01 079
Power Quality

Single-phase power supplies for Total Harmonic Distortion Table 1.4-7. Current Distortion Limits for
computer and fixture ballasts are
Revised standard IEEE 519-1992
General Distribution Systems (120– 69,000V) i
rich in third harmonics and their Maximum Harmonic Current Distortion in
odd multiples. indicates the limits of current distor-
Percent of IL
tion allowed at the PCC (Point of ii
Individual Harmonic Order (Odd Harmonics)
Even with the phase currents perfectly Common Coupling) point on the
balanced, the harmonic currents in system where the current distortion ISC /IL <11 11 17 23 35 TDD
<h <h <h <h
the neutral can total 173% of the is calculated, usually the point of
connection to the utility or the main
<17 <23 <35 1
phase current. This has resulted in
overheated neutrals. The Information supply bus of the system. <20  4.0 2.0 1.5 0.6 0.3 5.0
Technology Industry Council (ITIC)
The standard also covers the harmonic
20<50
50<100
7.0
10.0
3.5
4.5
2.5
4.0
1.0
1.5
0.5
0.7
8.0
12.0
2
formerly known as CBEMA, recom-
mends that neutrals in the supply to limits of the supply voltage from the 100<1000 12.0 5.5 5.0 2.0 1.0 15.0
utility or cogenerators. >1000 15.0 7.0 6.0 2.5 1.4 20.0
electronic equipment be oversized  All power generation equipment is limited 3
to at least 173% of the ampacity of Table 1.4-5. Low Voltage System Classification to these values of current distortion,
the phase conductors to prevent and Distortion Limits for 480V Systems regardless of actual ISC/IL where:
problems. ITIC also recommends Class C AN DF ISC = Maximum short-circuit current at PCC. 4
derating transformers, loading them IL = Maximum demand load current
to no more than 50% to 70% of their Special application  10 16,400 3% (fundamental frequency component) at PCC.
nameplate kVA, based on a rule-of- General system
Dedicated system
5
2
22,800
36,500
5%
10%
TDD = Total Demand Distortion. Even
harmonics are limited to 25% of the odd
5
thumb calculation, to compensate harmonic limits above. Current distortions
for harmonic heating effects.  Special systems are those where the rate that result in a DC offset, e.g., half-wave
In spite of all the concerns they
of change of voltage of the notch might
mistrigger an event. AN is a measurement
converters, are not allowed. 6
cause, nonlinear loads will continue of notch characteristics measured in
volt-microseconds, C is the impedance
Harmonic Solutions
to increase. Therefore, the design of
nonlinear loads and the systems that ratio of total impedance to impedance In spite of all the concerns nonlinear 7
at common point in system. DF is loads cause, these loads will continue
supply them will have to be designed distortion factor.
so that their adverse effects are greatly to increase. Therefore, the design
reduced. Table 1.4-4 shows the typical of nonlinear loads and the systems 8
Table 1.4-6. Utility or Cogenerator Supply that supply them will need design so
harmonic orders from a variety of Voltage Harmonic Limits
harmonic generating sources. adverse harmonic effects are greatly
Voltage 2.3–69 kV 69–138 kV >138 kV reduced. Table 1.4-8 and depicts many 9
Range harmonic solutions along with their
Table 1.4-4. Source and Typical Harmonics
Source Typical Maximum 3.0% 1.5% 1.0% advantages and disadvantages.
Harmonics  individual 10
harmonic Eaton’s Engineering Services &
6-pulse rectifier 5, 7, 11, 13, 17, 19… Total 5.0% 2.5% 1.5%
Systems Group (EESS) can perform
12-pulse rectifier
18-pulse rectifier
11, 13, 23, 25…
17, 19, 35, 37…
harmonic harmonic studies and recommend 11
distortion solutions for harmonic problems.
Switch-mode power
supply
Fluorescent lights
3, 5, 7, 9, 11, 13…
3, 5, 7, 9, 11, 13… V 12
Arcing devices 2, 3, 4, 5, 7…
Percentages are −−−h x 100 for each
harmonic V1
Transformer energization 2, 3, 4
 Generally, magnitude decreases as harmonic and
13
order increases.

h = hmax 1/2 14
Vthd = ∑ 2
Vh
h=2 15
It is important for the system designer
to know the harmonic content of the
utility’s supply voltage because it will 16
affect the harmonic distortion of
the system.
17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-24 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 080
Power Quality

Table 1.4-8. Harmonic Solutions for Given Loads


i Load Solutions Advantages Disadvantages
Type

ii Drives and rectifiers—


includes three-phase
Line reactors ■ Inexpensive ■ May require additional compensation
■ For 6-pulse standard drive/rectifier, can
UPS loads reduce harmonic current distortion from
80% down to about 35–40%
1 K-rated/drive isolation ■ Offers series reactance (similar to line ■ No advantage over reactors for
transformer reactors) and provides isolation for reducing harmonics unless in pairs
some transients for shifting phases
2 DC choke ■ Slightly better than AC line reactors ■ Not always an option for drives
for 5th and 7th harmonics ■ Less protection for input semiconductors

3 12-pulse convertor ■ 85% reduction versus standard


6-pulse drives
■ Cost difference approaches 18-pulse drive
and blocking filters, which guarantee
IEEE 519 compliance
Harmonic mitigating ■ Substantial (50–80%) reduction in harmonics ■ Harmonic cancellation highly dependent
4 transformers/phase shifting when used in tandem on load balance
■ Must have even multiples of matched loads
Tuned filters ■ Bus connected—accommodates ■ Requires allocation analysis
5 load diversity ■ Sized only to the requirements of that system;
■ Provides PF correction must be resized if system changes
Broadband filters ■ Makes 6-pulse into the equivalent ■ Higher cost
6 of 18-pulse ■ Requires one filter per drive
18-pulse converter ■ Excellent harmonic control for drives ■ High cost
above 100 hp
7 ■ IEEE 519 compliant
Active filters ■ Handles load/harmonic diversity ■ High cost
■ Complete solution up to 50th harmonic
8 Computers/ Neutral blocking filter ■ Eliminates the 3rd harmonic from load ■ High cost
switch-mode ■ Relieves system capacity ■ May increase voltage distortion
power supplies ■ Possible energy savings
9 Harmonic mitigating ■ 3rd harmonic recalculated back to the load ■ Requires fully rated circuits and
transformers ■ When used as phase-shifted transformers, oversized neutrals to the loads
reduces other harmonics
10 ■ Reduces voltage “flat-topping”
Oversized neutral/derated ■ Tolerate harmonics rather than correct ■ Upstream and downstream equipment
transformer fully rated for harmonics
11 ■ Typically least expensive
K-rated transformer ■ Tolerate harmonics rather than correct ■ Does not reduce system harmonics
Fluorescent Harmonic mitigating ■ 3rd harmonic recalculated back to the load ■ Requires fully rated circuits and
12 lighting transformers ■ When used as phase-shifted transformers, oversized neutrals to the loads
reduces other harmonics
■ Reduces voltage “flat-topping”
13 K-rated transformer ■ Tolerate harmonics rather than correct them ■ Does not reduce system harmonics
Low distortion ballasts ■ Reduce harmonics at the source ■ Additional cost and typically more
expensive than “system” solutions
14 Welding/arcing Active filters ■ Fast response and broadband ■ High cost
loads harmonic correction
■ Reduces voltage flicker
15 Tuned filters ■ SCR controlled tuned filters simulates ■ SCR controlled units are high cost
an active filter response but fixed filters are reasonable
System Tuned filters ■ Provides PF correction ■ System analysis required to verify application.
16 solutions ■ Lower cost compared to other systems Must be resized if system changes
Harmonic mitigating ■ Excellent choice for new design or upgrade ■ No PF correction benefit
transformers
17 Active filters ■ Ideal solution and handles system diversity ■ Highest cost

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-25
August 2013 Uninterruptible Power Systems (UPS)
Sheet 01 081

5. Uninterruptible Power The normal power source supplied by Uninterruptible power supply (UPS)
Systems (UPS) the local utility or provider is not stable systems have evolved to serve the i
enough over time to continuously needs of sensitive equipment and
The advent of solid-state semiconduc- serve these loads without interruption. can supply a stable source of electrical
tors over 40 years ago, and their It is possible that a facility outside a power, or switch to backup to allow ii
subsequent evolution to transistors, major metropolitan area served by the for an orderly shutdown of the loads
and the miniaturization of electronics utility grid will experience outages of without appreciable loss of data or
into microprocessor over 25 years ago, some nature 15–20 times in one year. process. In the early days of main- 1
has created numerous computation Certain outages are caused by the frame computers, motor-generator
machines that assist us in every weather, and others by the failure sets provide isolation and clean power
conceivable manner. These machines, of the utility supply system due to to the computers. They did not have 2
and their clever configurations, equipment failures or construction deep reserves, but provided extensive
whether they take the form of interruptions. Some outages are ride-through capability while other
computers, appliance controls, fax only several cycles in duration, while sources of power (usually standby 3
machines, phone systems, computers others may be for hours at a time. emergency engine generator sets) were
of all sizes, server systems and server brought to serve the motor-generator
farms, emergency call centers, data In a broader sense, other problems sets while the normal source of power 4
processing at banks, credit companies, exist in the area of power quality, and was unstable or unavailable.
private company communication many of those issues also contribute
networks, government institutions and to the failure of the supply to provide UPS systems have evolved along the 5
defense agencies, all rely on a narrow that narrow range of power to the lines of rotary types and static types
range of nominal AC power in order sensitive loads mentioned above. of systems, and they come in many
for these devices to work properly. Power quality problems take the configurations, and even hybrid 6
Indeed, many other types of equip- form of any of the following: power designs having characteristics of
ment also require that the AC electrical failure, power sag, power surge, both types. The discussion that
power source be at or close to nominal undervoltage, overvoltage, line noise, follows attempts to compare and 7
voltage and frequency. Disturbances frequency variations, switching contrast the two types of UPS
of the power translate into failed transients and harmonic distortion. systems, and give basic guidance
processes, lost data, decreased Regardless of the reason for outages on selection criteria. This discussion 8
efficiency and lost revenue. and power quality problems, the will focus on the medium, large and
sensitive loads can not function very large UPS systems required by
normally without a backup power users who need more than 10 kVA of 9
source, and in many cases, the loads clean reliable power.
must be isolated from the instabilities
of the utility supply and power quality 10
problems and given clean reliable
power on a continuous basis, or be
able to switch over to reliable clean 11
electrical power quickly.

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-26 Power Distribution Systems
Uninterruptible Power Systems (UPS) August 2013
Sheet 01 082

Power Ratings of UPS Systems types of hybrid UPS systems are not system checks are performed then
i ■ Small UPS: Typically 300 VA to 10 kVA,
the focus of this discussion, because the input contactor is closed. The static
only one or two vendors offer these disconnect switch is turned on and the
and sometimes as high as 18 kVA hybrid types of rotary UPS systems, conduction angle is rapidly increased
ii ■ Medium UPS: 10–60 kVA although admittedly they continue to from zero to an angle that causes the
■ Large UPS: 100–200 kVA units, and be used in very large-scale data center DC bus voltage between the utility
higher when units are paralleled applications. See Figure 1.4-18 for the converter and the flywheel converter
1 ■ Very Large UPS: 200–750 kVA modern high speed Rotary UPS to reach approximately 650V through
units, and higher when units systems discussed in this section the rectifying action of the freewheel-
are paralleled of the guide. These types of modern ing diodes in the utility converter.
2 rotary UPS systems are advanced, As soon as this level of DC voltage is
Each of these categories is arbitrary integrated designs using scalable reached, the static disconnect turns
because manufacturers have many configurations of high-speed fly- on fully. The next steps involved the
3 different UPS offerings for the same wheel, motor and generator in one utility converter IGBTs to start firing,
application. The choice of UPS type compact UPS package. The new rotary which allows the converter to act as
and the configuration of UPS modules technologies have the potential to a rectifier, a regulating voltage source
4 for a given application depends upon replace battery backup systems, or and an active harmonic filter. As the
many factors, including how many at least reduce the battery content IGBTs begin to operate, the DC bus
power quality problems the UPS is for certain applications. The appeal is increased to a normal operating
5 expected to solve; how much future of rotary systems is the avoidance of voltage of approximately 800V, and
capacity is to be purchased now for the purchase, maintenance and facility the output bus is transferred from
future loads; the nature of the sensi- space required by DC battery based bypass to the output of the power
6 tive loads and load wiring; which backup systems. electronics module. The transfer from
type of UPS system is favored, rotary bypass is completed when the output
or static; choices of battery or DC High-Speed Rotary contactor is closed and the bypass
7 storage technology considered; and
Concept of Operation contactor opened in a make-before-
a host of other application issues. break manner.
The modern rotary type of UPS
8 Rotary UPS Systems operation is understood by reviewing The firing of the SCRs in the static
the four topics below: startup mode, disconnect switch is now changed so
Typical Ratings normal operation mode, discharge that each SCR in each phase is only
9 300–900 kVA/720 kW maximum. mode and recharge mode. turned on during the half-cycle, which
permits real power to flow from the
Typical Rotary Configurations Startup Mode utility supply to the UPS. This firing
10 Rotary UPS systems are among the The UPS output is energized on pattern at the static disconnect switch
oldest working systems developed bypass as soon as power is applied prevents power from the flywheel
to protect sensitive loads. Many of from the source to the system input. from feeding backward into the
11 these systems are complicated engine- The UPS continues the startup utility supply and ensures that all of
generator sets coupled with high procedure automatically when the the flywheel energy is available to
inertial flywheels operated at relatively front panel controls are placed into support the load.
12 low rotational speeds. These legacy the “Online” position. Internal UPS

13 Static Bypass Option


It = Input Current
Ir = Real Load Current
14 Ic = Charging Current
Ig = Voltage Regulation Current
Bypass Contactor
15
It = Ir + Ic + Ig Id = Ih + Ix + Ir
Input Static Disconnect
Output
Contactor Switch Line Inductor
16 Source
Contactor
Load

Flywheel Converter Utility Converter Ic Inverter


17 Fuse Output Transformer

Ix
Filter Inductor Ig
18 Field Coil ac dc Id = Output Current
Ih = Harmonic Current
Driver dc ac Ix = Reactive Load Current
Ir = Real Load Current
19 Ih
Integrated Motor/Flywheel/
and Generator
20
Figure 1.4-18. Typical-High Speed Modern Rotary UPS
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-27
August 2013 Uninterruptible Power Systems (UPS)
Sheet 01 083

Immediately after the output is trans- causes a voltage boost across the line as the load power is completely
ferred from bypass to the power elec- inductor, and a lagging current causes transferred to the input source, the util- i
tronic module, the flywheel field is a bucking voltage. By controlling the ity converter and flywheel converter
excited, which also provides magnetic utility converter to maintain nominal start to recharge the flywheel and
lift to unload the flywheel bearings. output voltage, just enough reactive return to normal operation mode. The ii
The flywheel inverter is turned on current flows through the line inductor flywheel recharge power is program-
and gradually increases frequency to make up the difference between the mable between a slow and fast rate,
at a constant rate to accelerate the input voltage and the output voltage. and using the fast rate results in an 1
flywheel to approximately 60 rpm. increase of UPS input current over
Once the flywheel reaches 60 rpm, The load current consists of three nominal levels. Recharging the flywheel
the flywheel inverter controls the components: the harmonic current is accomplished by controlling the 2
acceleration to keep currents below the required by the load, the reactive load utility and flywheel converter in a
maximum charging and the maximum current, and the real current, which similar manner as is used to maintain
input settings. Once the flywheel does the work. The utility converter full charge in the normal operation 3
reaches 4000 rpm, the UPS is fully supplies both the harmonic and mode, however the IGBT gating points
functional and capable of supporting reactive currents. Because these are changed to increase current into
the load during a power quality event. currents supply no net power to the the flywheel. 4
flywheel acceleration continues until load, the flywheel supplies no energy
the Flywheel reaches “full charge” at for these currents. They circulate High-Speed Rotary Advantages
7700 rpm. The total time to complete between the utility converter and the ■ Addresses all power quality 5
startup is less than 5 minutes. load. The power stage controls analyze problems
the harmonic current requirements of
■ Battery systems are not required
Normal Operation Mode the load and set the firing angle of
or used 6
Once the UPS is started and the the inverter IGBTs to make the utility
converter a very low impedance source ■ No battery maintenance required
flywheel is operating at greater than
4000 rpm, the UPS is in the normal to any harmonic currents. Thus, ■ Unlimited discharge cycles 7
operating mode where it is regulating nonlinear load currents are supplied ■ 150-second recharge time available
output voltage and supplying reactive almost entirely from the utility ■ Wide range of operating tempera-
and harmonic currents required by the converter with little effect on the tures can be accommodated 8
load. At the same time it cancels the quality of the UPS output voltage (–20° to 40°C)
effect of load current harmonics on the waveform and with almost no
■ Small compact size and less floor
UPS output voltage. transmission of load harmonics
space required (500 kW systems
9
currents to the input of the UPS.
Input current consists of three compo- takes 20 sq ft)
nents: real load current, charging Discharge Mode ■ N+1 reliability available up to 10
current, and voltage regulation current. The UPS senses the deviation of 900 kVA maximum
Real current is current that is in phase the voltage or frequency beyond ■ No disposal issues
with the supply voltage and supplies programmed tolerances and quickly
High-Speed Rotary Disadvantages
11
real power to the load. Real current disconnects the supply source by
flowing through the line inductor causes turning off the static disconnect switch ■ Flywheel does not have deep
a slight phase shift of the current and opening the input contactor. The reserve capacity—rides through 12
lagging the voltage by 10 degrees disconnect occurs in less than one-half for up to 13 seconds at 100% load
and ensures that the UPS can quickly cycle. Then the utility converter starts ■ Some enhanced flywheel systems
transfer to bypass without causing delivering power from the DC bus to may extend the ride through to 13
unacceptable switching transients. The the load, and the flywheel converter 30 seconds at 100% load
second component is charging current changes the firing point of its IGBTs ■ Mechanical flywheel maintenance
required by the flywheel to keep the to deliver power to the DC bus. The required every 2–3 years, and oil 14
rotating mass fully charged at rated UPS maintains a clean output voltage changes required every year
rpm, or to recharge the rotating mass within 3% or nominal voltage to the
after a discharge. The power to main- load when input power is lost. ■ Recharge fast rates require the 15
tain full charge is low at 2 kW and input to be sized for 125% of
is accomplished by the IGBTs of the Recharge Mode nominal current
flywheel converter gating to provide When input power is restored to ■ Flywheels failures in field not 16
small pulses of motoring current to the acceptable limits, the UPS synchronizes understood
flywheel. This current can be much the output and input voltages, closes ■ Requires vacuum pumps for
higher if fast recharge times are the input contactor and turns on the high-speed flywheels 17
selected. The final component of input static disconnect switch. The utility ■ Limited number of vendors and
current is the voltage regulation current, converter then transfers power from experience
which is usually a reactive current that the flywheel to the input source by 18
circulates between the input and the linearly increasing the real input
utility converter to regulate the output current. The transfer time is program-
voltage. Leading reactive current mable from 1 to 15 seconds. As soon 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-28 Power Distribution Systems
Uninterruptible Power Systems (UPS) August 2013
Sheet 01 084

Static UPS Systems 2. The Rectifier/Charger function mode in 150–120 milliseconds.


i converts the normal AC power to When the UPS recognizes a
Typical Ratings DC power to charge the battery requirement to transfer to the
40–750 kVA/600 kW, and higher when and power the inverter. The load bypass mode, it simultaneously
ii multiple units are paralleled. is isolated from the normal turns the static switch ON, the
input source. output breaker to OPEN, and the
Typical Static UPS Configurations bypass breaker to CLOSE. The
1 Static UPS systems modules are
3. The battery stores DC energy output breaker opens and the
for use when input power to the bypass breaker closes in about
available in three basic types of
UPS fails. The amount of power 50 milliseconds. The restoration
configurations known as standby, line
2 interactive and double conversion.
available from the DC battery of normal conditions at the UPS
system and time to discharge results in the automatic restoration
See Tab 33 in this guide for details on
voltage is a function of the type of of the UPS module powering the
all the UPS configurations available
3 from Eaton. The lighter power ratings
battery selected and the ampere- load through the rectifier/charger
hour sized used. Battery systems and inverter with load isolation
are likely to be one of the first two
should be sized for no less than from power quality problems, and
types of configurations, e.g., standby
4 or line interactive. Most medium or
5 minutes of clean power usage the opening of the bypass circuit.
from a fully charged state, and, in
large static UPS installations use the
many cases, are sized to provide Static Double Conversion Advantages
double conversion technology in one
5 or multiple module configurations,
more time on battery power. ■ Addresses all power quality
i.e., or multiple UPS units in parallel. 4. The DC link connects the output problems
Figure 1.4-19 illustrates the one-line of the rectifier/charger to the input ■ Suitable for applications from
6 diagram of a simple single Double of the inverter and to the battery. 5 kVA to over 2500 kVA
Conversion UPS module. Brief Typically the rectifier/charger is ■ Simple battery systems are
explanations appear for the standby sized slightly higher than 100% of sized for application
7 and line interactive UPS systems UPS output because it must power ■ Long battery backup times and
after the text explaining the Double the inverter and supply charger long life batteries are available
Conversion static UPS type of system. power to the battery.
8 ■ Higher reliability is available
A. Double conversion concept of 5. The bypass circuit provides a using redundant UPS modules
operation—the basic operation of path for unregulated normal
9 the Double Conversion UPS is: power to be routed around the
major electronic sub-assemblies
1. Normal power is connected to
of the UPS to the load so that the
10 the UPS input through the facility
load can continue to operate during
electrical distribution system.
maintenance, or when the UPS
This usually involves two input
electronics fails. The bypass static
11 circuits that must come from the
switch can switch to conducting
same source.

12
Bypass Breaker (Optional) UPS Module
13
Bypass Static Switch

14 Source Load
Normal Rectifier/Charger Output
Inverter
Breaker Breaker
15 AC DC
DC AC
16 Battery Breaker

17 Battery

18 Figure 1.4-19. Typical Static UPS, Double Conversion Type with Battery Backup

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-29
August 2013 Uninterruptible Power Systems (UPS)
Sheet 01 085

Static Double Conversion Disadvantages 3. The battery stores DC energy for C. Static line interactive UPS
■ Battery systems, battery maintenance use by the inverter when input concept of operation—the basic i
and battery replacement are required power to the UPS fails. The operation of the Line Interactive
amount of power available from UPS is:
■ Large space requirement for
battery systems (higher life takes
the DC battery system and time to ii
discharge voltage is a function of 1. The Line Interactive type of UPS
more space, e.g., 500 kW takes has a different topology than the
the type of battery selected and
80–200 sq ft depending upon the static double conversion and 1
the ampere-hour sized used.
type of battery used, VRLA 10 year, standby systems. The normal
Battery systems should be sized
VRLA 20 year or flooded) input power is connected to the
for the anticipated outage.
■ Limited discharge cycles of load in parallel with a battery 2
battery system 4. The DC link connects the output of and bi-directional inverter/charger
■ Narrow temperature range the rectifier/charger to the input of assembly. The input source usu-
for application the inverter and to the battery. ally terminates at a line inductor 3
Typically the rectifier/charger and the output of the inductor is
■ Efficiencies are in the 90–94%
is sized only to supply charger connected to the load in parallel
range, which is lower than some
line interactive configurations
power to the battery, and is with the battery and inverter/ 4
rated far lower than in the charger circuit. See Figure 1.4-21
■ Bypass mode places load at risk double conversion UPS. for more details.
unless bypass has UPS backup
5. The bypass circuit provides a 2. The traditional rectifier circuit
5
■ Redundancy of UPS modules
results in higher costs direct connection of input source is eliminated and this results
to the load. The load operates in a smaller footprint and
■ Output faults are cleared by the
from unregulated power. The weight reduction. However, line
6
bypass circuit
bypass static switch can switch conditioning is compromised.
■ Output rating of the UPS is 150% to non-conducting mode in 150–
for 30 seconds 120 milliseconds. When the UPS 3. When the input power fails, the 7
■ Battery disposal and safety recognizes the loss of normal battery/inverter charger circuit
issues exist input power, it transfers to battery/ reverses power and supplies the
inverter mode by simultaneously load with regulated power. 8
B. Standby UPS concept of
turning the Inverter ON and the Static Line Interactive UPS Advantages
operation—The basic operation of
static switch OFF. 9
the Standby UPS is: ■ Slight improvement of power
Static Standby UPS Advantages conditioning over standby
1. The Standby UPS topology is UPS systems
■ Lower costs than double conversion
similar to the double conversion
■ Small footprints and weights 10
type, but the operation of the UPS ■ Rectifier and charger are
is different in significant ways. economically sized ■ Efficient design
Normal power is connected to ■ Efficient design ■ Batteries are sized for the 11
the UPS input through the facility ■ Batteries are sized for the application
electrical distribution system. This application Static Line Interactive UPS Disadvantages
usually involves two input circuits 12
that must come from the same Static Standby UPS Disadvantages ■ Impractical over 5 kVA
source. See Figure 1.4-20 for ■ Impractical over 2 kVA ■ Not as good conditioning as
details.
■ Little to no isolation of load from double conversion 13
2. The rectifier/charger function power quality disturbances ■ Standby power is from battery alone
converts the normal AC power to ■ Standby power is from battery alone ■ Battery systems, battery mainte-
DC power to charge the battery nance and battery replacement 14
■ Battery systems, battery mainte-
only, and does not simultaneously nance and battery replacement are required
power the inverter. The load is Limited discharge cycles for the
connected to the input source
are required ■
battery system
15
■ Limited discharge cycles of
through the bypass static switch. ■ Narrow temperature range for
battery system
The inverter is in the standby
mode ready to serve the load ■ Narrow temperature range for application 16
application ■ Battery disposal and safety
from battery power if the input
■ Output faults are cleared by the issues exist
power source fails. 17
bypass circuit
■ Battery disposal and safety
issues exist 18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-30 Power Distribution Systems
Uninterruptible Power Systems (UPS) August 2013
Sheet 01 086

i UPS Module

ii Bypass Static Switch

2 Source Load
Rectifier/
Normal Output
3 Breaker
Charger Inverter
Breaker
AC DC

4 DC AC
Battery
Breaker
5
Battery
6

7 Figure 1.4-20. Typical Static UPS, Standby Type with Battery Backup

8 UPS Module

9
Source Load
10
Inductor

11
Bidirectional
12 Inverter/Charger

DC
13 AC

14

15 Battery

16
Figure 1.4-21. Typical Static UPS, Line Interactive Type with Battery Backup

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-31
August 2013 System Application Considerations
Sheet 01 087
Other Application Considerations

Secondary Voltage Selection Technical Factors supplied from a 480V system through
The choice between 208Y/120V and The principal advantage of the use of step-down transformers, voltage drop i
higher secondary voltages in buildings in the 480V supply conductors can be
480Y/277V secondary distribution for compensated for by the tap adjust-
commercial and institutional buildings is that for a given load, less current
depends on several factors. The most means smaller conductors and lower ments on the transformer, resulting ii
voltage drop. Also, a given conductor in full 120V output. Because these
important of these are size and types transformers are usually located close
size can supply a large load at the
of loads (motors, fluorescent lighting,
same voltage drop in volts, but a lower to the 120V loads, secondary voltage 1
incandescent lighting, receptacles) drop should not be a problem. If it is,
and length of feeders. In general, large percentage voltage drop because of
the higher supply voltage. Fewer or taps may be used to compensate by
motor and fluorescent lighting loads,
smaller circuits can be used to transmit raising the voltage at the transformer. 2
and long feeders, will tend to make the
higher voltages, such as 480Y/277V, the power from the service entrance The interrupting ratings of circuit
point to the final distribution points.
more economical. Very large loads
Smaller conductors can be used in many
breakers and fuses at 480V have 3
and long runs would indicate the use increased considerably in recent years,
of medium voltage distribution and branch circuits supplying power loads, and protective devices are now available
and a reduction in the number of light-
loadcenter unit substations close to
ing branch circuits is usually possible.
for any required fault duty at 480V. 4
the loads. Conversely, small loads, In addition, many of these protective
short runs and a high percentage of It is easier to keep voltage drops within devices are current limiting, and can
incandescent lighting would favor acceptable limits on 480V circuits than be used to protect downstream equip- 5
lower utilization voltages such as on 208V circuits. When 120V loads are ment against these high fault currents.
208Y/120V.
Industrial installations, with large
6
motor loads, are almost always 480V,
often ungrounded delta or resistance
grounded delta or wye systems (see Elevator
7
section on ground fault protection). Panel

Practical Factors
Typical
8
Because most low voltage distribution
Emergency
equipment available is rated for up to Typical
600V, and conductors are insulated for
HVAC
Panel
Lighting Panel 9
(Typical Every
600V, the installation of 480V systems Third Floor)
uses the same techniques and is
essentially no more difficult, costly, or 10
480Y/277 V 208Y/120 V Typical
hazardous than for 208V systems. The Panel Panel
major difference is that an arc of 120V Dry Type Transformer

to ground tends to be self-extinguishing,


480∆-208Y/120 V
(Typical Every Floor)
11
while an arc of 277V to ground tends HVAC Busway Emergency Elevator
to be self-sustaining and likely to Feeder Riser Lighting
cause severe damage. For this reason, Riser
Riser
12
the National Electrical Code requires
ground fault protection of equipment
on grounded wye services of more
Building and
Miscellaneous
Typical Typical
13
Loads
than 150V to ground, but not exceeding Typical
600V phase-to-phase (for practical
purpose, 480Y/277V services), for any
14
Typical Typical
service disconnecting means rated Spare
1000A or more. The National Electrical 15
Code permits voltage up to 300V ➀ ➀ ➀ ➀ ➀ ➀ ➀
to ground on circuits supplying
permanently installed electric discharge Automatic 16
lamp fixtures, provided the luminaires ➀
4000 A
Transfer Switch
Main CB
do not have an integral manual switch Gen. CB
Emergency
and are mounted at least 8 ft (2.4m) CTs
Utility
or Standby 17
Metering
above the floor. This permits a three- PTs Generator
phase, four-wire, solidly grounded Utility 4000A at 480Y/277V
480Y/277V system to supply directly all Service 100,000A Available Fault Current

of the fluorescent and high-intensity


18
discharge (HID) lighting in a building Figure 1.4-22. Typical Power Distribution and Riser Diagram for a Commercial Office Building
at 277V, as well as motors at 480V.  Include ground fault trip. 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-32 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 088
Other Application Considerations

Economic Factors Motors and controls are another cause and consider the cost of losses as well
i Utilization equipment suitable for of wasted energy that can be reduced. as the initial cost of the transformers
principal loads in most buildings New, energy-efficient motor designs in purchasing.
is available for either 480V or 208V are available using more and better
ii systems. Three-phase motors and core steel, and larger windings. NEMA standard TP-1 is being adopted
by many states and is another method
their controls can be obtained for either For any motor operating 10 or more of energy-efficient design. NEMA TP-1
voltage, and for a given horsepower
1 are less costly at 480V. Fluorescent and
hours per day, it is recommended to establishes minimum operating
use the energy-efficient types. These efficiencies for each distribution
HID lamps can be used with either 277V motors have a premium cost of about transformer size at a loading equal to
or 120V ballasts. However, in almost all
2 cases, the installed equipment will have
20% more than standard motors. 35% of the transformer full load kVA.
Depending on loading, hours of use The 35% loading value in the NEMA
a lower total cost at the higher voltage. and the cost of energy, the additional standard reflects field studies con-
3 Energy Conservation
initial cost could be repaid in energy ducted by the U.S. Department of
saved within a few months, and it Energy, which showed that dry-type
Because of the greatly increased cost rarely takes more than two years. transformers installed in commercial
4 of electrical power, designers must Because, over the life of a motor, the facilities are typically loaded at an
consider the efficiency of electrical cost of energy to operate it is many average of 35% of their full load
distribution systems, and design for times the cost of the motor itself, any capacity over a 24-hour time period.
5 energy conservation. In the past, motor with many hours of use should Table 1.4-9 compares losses for
especially in commercial buildings, be of the energy-efficient type. both low temperature rise and TP-1
design was for lowest first cost, transformers using a 75 kVA design.
Where a motor drives a load with
6 because energy was inexpensive.
variable output requirements such Table 1.4-9. Load Losses
Today, even in the speculative office
building, operating costs are so high as a centrifugal pump or a large fan, Temp. Load Losses in Watts
customary practice has been to run the
7 that energy-conserving designs can
motor at constant speed, and to throttle
Rise ºC No 25% 35% 50% 75% Full
justify their higher initial cost with a Loss Load Load Load Load Load
rapid payback and continuing savings. the pump output or use inlet vanes or
outlet dampers on the fan. This is highly 150 360 490 620 885 1535 2450
8 Buildings that must meet LEED certifi-
inefficient and wasteful of energy. In 115 420 480 610 805 1170 1950
cations may require energy-saving 80 500 535 615 730 945 1410
designs. There are four major sources recent years, solid-state variable-
frequency, variable-speed drives for TP-1 150 230 310 480 745 1235 2280
9 of energy conservation in a commercial
ordinary induction motors have been
building—the lighting system, the Efficiencies above TP-1. Candidates
motors and controls, the transformers available, reliable and relatively
inexpensive. Using a variable-speed Standard Level (CSL) is a DOE
10 and the HVAC system.
drive, the throttling valves, inlet vanes efficiency evaluation for transformers.
The lighting system must take or output dampers can be eliminated, CSL-1 is equivalent to TP-1. Levels
saving their initial cost and energy are from CSL-1 to CSL-5. CSL-3 is
11 advantage of the newest equipment
over the life of the system. An being promoted for higher efficiency
and techniques. New light sources,
familiar light sources with higher additional benefit of both energy- applications. A NEMA white paper
Clarifications on the Use of DOE
12 efficiencies, solid-state ballasts with efficient motors and variable-speed
drives (when operated at less than Design—Lines 6, 7 and 8 is available
dimming controls, use of daylight,
environmental design, efficient full speed) is that the motors operate from NEMA that elaborates on
the matter.
13 luminaires, computerized or at reduced temperatures, resulting in
programmed control, and the like, increased motor life. HVAC systems have traditionally been
are some of the methods that can very wasteful of energy, often being
Transformers have inherent losses.
14 increase the efficiency of lighting
Transformers, like motors, are designed designed for lowest first cost. This,
systems. They add up to providing too, is changing. For example, reheat
the necessary amount of light, with the for lower losses by using more and
better core materials, larger conductors, systems are being replaced by variable
15 desired color rendition, from the most
etc., and this results in increased initial air volume systems, resulting in equal
efficient sources, where and when it is comfort with substantial increases in
needed, and not providing light where cost. Because the 480V to 208Y/120V
stepdown transformers in an office efficiency. While the electrical engineer
16 or when it is not necessary. Using the
building are usually energized 24 hours has little influence on the design of the
best of techniques, office spaces that HVAC system, he/she can specify that
originally required as much as 3.5W a day, savings from lower losses can
be substantial, and should be consid- all motors with continuous or long duty
17 per square foot have been given
ered in all transformer specifications. cycles are specified as energy-efficient
improved lighting, with less glare types, and that the variable-air-volume
and higher visual comfort, using as One method of obtaining reduced
losses is to specify transformers with fans do not use inlet vanes or outlet
18 little as 1.0 to 2.0W per square foot.
220°C insulation systems designed for dampers, but are driven by variable-
In an office building of 200,000 square speed drives. Variable-speed drives
feet (60,960m), this could mean a 150°C average winding temperature
rise, with no more than 80°C (or can often be desirable on centrifugal
19 saving of 400 kW, which, at $0.05 per
sometimes 115°C) average winding compressor units as well. Since some
kWh, 250 days per year, 10 hours per of these requirements will be in HVAC
day, could save $50,000 per year in temperature rise at full load. A
better method would be to evaluate specifications, it is important for the
20 energy costs. Obviously, efficient
transformer losses, based on actual energy-conscious electrical engineer
lighting is a necessity. to work closely with the HVAC engineer
loading cycles throughout the day,
at the design stage.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-33
August 2013 System Application Considerations
Sheet 01 089
Other Application Considerations

Building Control Systems Because building design and control been changed by the high cost of
In order to obtain the maximum benefit
for maximum energy saving is impor- purchased energy, plus a federal law i
tant and complex, and frequently (Public Utility Regulatory Policies Act,
from these energy-saving lighting, involves many functions and several known as PURPA) that requires public
power and HVAC systems, they must systems, it is necessary for the design utilities to purchase any excess power ii
be controlled to perform their functions engineer to make a thorough building generated by the cogeneration plant.
most efficiently. Constant monitoring and environmental study, and to In many cases, practical commercial
would be required for manual operation,
so some form of automatic control
weigh the costs and advantages of cogeneration systems have been built 1
many systems. The result of good that provide some or all of the electric
is required. The simplest of these design can be economical, efficient power required, plus hot water, steam,
energy-saving controls, often very operation. Poor design can be wasteful and sometimes steam absorption-type 2
effective, is a time clock to turn various and extremely costly. air conditioning. Such cogeneration
systems on and off. Where flexible systems are now operating success-
control is required, programmable Distributed Energy Resources fully in hospitals, shopping centers, 3
controllers may be used. These range high-rise apartment buildings and
from simple devices, similar to multi- Distributed energy resources (DER)
are increasingly becoming prominent even commercial office buildings.
function time clocks, up to full micro-
sources of electric power. Distributed
4
processor-based, fully programmable Where a cogeneration system is being
devices, really small computers. For energy resources are usually small-to- considered, the electrical distribution
complete control of all building systems, medium sources of electric generation, system becomes more complex. The 5
computers with specialized software either from renewable or non-renewable interface with the utility company is
can be used. Computers can not only sources. Sources include: critical, requiring careful relaying
control lighting and HVAC systems,
■ Photovoltaic (PV) systems to protect both the utility and the 6
and provide peak demand control, to cogeneration system. Many utilities
(solar systems)
minimize the cost of energy, but they have stringent requirements that
■ Wind
can perform many other functions. must be incorporated into the system. 7
Fire detection and alarm systems can ■ Fossil-fueled (diesel, natural gas, Proper generator control and protec-
operate through the computer, which landfill gas, coal-bed methane) tion is necessary, as well. An on-site
can also perform auxiliary functions generators (reciprocating engines) electrical generating plant tied to an 8
such as elevator control and building ■ Gas-fired turbines (natural gas, electrical utility, is a sophisticated
communication in case of fire. Building landfill gas, coal-bed methane) engineering design.
security systems, such as closed-circuit ■ Water-powered (hydro) Utilities require that when the
9
television monitoring, door alarms and
■ Fuel cells protective device at their substation
intruder sensing, can be performed by
the same building computer system. ■ Microturbines opens that the device connecting a 10
■ Wave power cogenerator to the utility open also.
The time clocks, programmable
■ Coal-fired boilers One reason is that most cogenerators
controllers and computers can 11
obtain data from external sensors are connected to feeders serving other
Distributed energy resources may also
and control the lighting, motors and customers. Utilities desire to reclose
be termed alternative energy resources.
other equipment by means of hard the feeder after a transient fault is
wiring-separate wires to and from Prime Power cleared. Reclosing in most cases will 12
each piece of equipment. In the more DER can be used for generating prime damage the cogenerator if it had
complex systems, this would result in remained connected to their system.
a tremendous number of control
power or for cogeneration. Prime power
concerns a system that is electrically
13
Islanding is another reason why the
wires, so other methods are frequently separated from the electrical grid. utility insists on the disconnection of
used. A single pair of wires, with elec- Prime power is generated at remote the cogenerator. Islanding is the event 14
tronic digital multiplexing, can control sites where commercial electrical that after a fault in the utility’s system
or obtain data from many different power is not available. is cleared by the operation of the
points. Sometimes, coaxial cable is protective devices, a part of the 15
used with advanced signaling equip- Cogeneration system may continue to be supplied
ment. Some systems dispense with by cogeneration. Such a condition is
Cogeneration is another outgrowth of
control wiring completely, sending
the high cost of energy. Cogeneration dangerous to the utility’s operation 16
and receiving digital signals over the during restoration work.
is the production of electric power
power wiring. The newest systems
concurrently with the production of
may use fiber-optic cables to carry
steam, hot water and similar energy
Major cogenerators are connected to 17
tremendous quantities of data, free the subtransmission or the transmission
uses. The electric power can be the
from electromagnetic interference. system of a utility. Major cogenerators
main product, and steam or hot water
The method used will depend on
the byproduct, as in most commercial
have buy-sell agreements. In such 18
the type, number and complexity cases, utilities use a trip transfer
installations, or the steam or hot water
of functions to be performed. scheme to trip the cogenerator breaker.
can be the most required product,
and electric power a byproduct, as Guidelines that are given in ANSI 19
in many industrial installations. In Guide Standard 1001 are a good
some industries, cogeneration has starting point, but the entire design
been common practice for many should be coordinated with the utility. 20
years, but until recently it has not been
economically feasible for most
commercial installations. This has 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-34 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 090
Other Application Considerations

PV System Design Considerations in determining the maximum number High Temperature Equation
i Successful photovoltaic (PV) design
of solar modules per string for the Once the maximum number of
open-circuit photovoltaic (PV) voltage modules per string is established,
and construction is a complex multi- rise in cold weather (Voc < 600V as per the minimum number of modules per
ii discipline endeavor. Proper planning
includes the site-layout study for
NEC). Its low 300V MPPT lower-limit string needs to be calculated. Here,
ensures that multiple configurations more site-related aspects come into
maximizing the sun’s energy harvest- are possible for solar systems hot play, as the voltage of solar modules
1 ing for solar module selection, and weather voltage drop (i.e., Vmp decreases with increasing tempera-
for updating the electrical/mechanical as a function of temperature, solar
design and construction to the latest ture. The modules’ (photovoltaic cell)
irradiance and array-conductor voltage temperature is influenced by the
2 code and local constraints, including drop). The following equations are the ambient temperature, reflected sun-
fire marshal and seismic regulations. basis of all solar system layout and
Professionally prepared bid, permit, loads from nearby structures, parapet
design. Consult professional engineer- walls, roof-coatings, etc. Air-flow
3 construction and as-build drawings ing to help when planning any solar above and behind the solar modules
shall be required and maintained. system. Engineering design firms
For installation in/on/for existing affect the cell temperature. The
offering complete solar systems accepted industry standards to add
4 structures and sites, it is advised “turn-key” calculations, drawings, to the module heating is listed below.
that, at the minimum, pre-design construction management and
and construction tests be performed Unusual mounting systems may
procurement are a good place to adjust these figures, and it is best to
5 for existing power-quality issues, start. Eaton offers professional S-Max seek assistance in establishing and
water drainage and the utility feeder/ inverter application assistance, on-site
transformer, and that electrical planning such installations.
commissioning and maintenance
6 distribution panel ratings are verified services. Eaton maintains a working ■ 20°C for ground or pole mounted
sufficient for the planned solar system, relationship with the best engineering solar systems
and the necessary arc flash studies be services firms across the country, and ■ 25°C for roof-top solar systems
7 performed. Connection to the utility helps arrange the successful implanta- mounted at inclined angles
is always a utility interconnect agree- tion of your solar system. The S-Max (offers improved air-flow behind
ment (application) process, and is 250 kW inverter and up-fit solutions the modules)
8 typically required for the available easily perform well in Mega-Watt and ■ 30°C for roof-top solar systems
solar incentives and programs offered Utility-Scale systems. Eaton also offers
by the utility, municipality, state, and mounted flat, yet at least 6.00 inches
a wide range of balance-of-system (152.4 mm) above the roof surface
9 various federal agencies and depart- (BOS) products, ranging from solar
ments. State, and IRS tax incentives module source and array combiners, Vmp_min = Vmp + (temp-differential x
require well-documented records. to DC and AC breakers, electrical and temp-coefficient-of-Vmp)
10 Solar systems, while low mainte- distribution panels and switchgear.
The temp-differential in this case
nance, do require periodic service. includes the above temperature
Low Temperature Equation
11 The solar modules need to be washed- “adders.” The Vmp and related
clean on a regular basis and electrical Voc_max = Voc + (temp-differential x
temp-coefficient-of-Voc) temperature coefficients are listed
terminations require initial and annual on the solar module’s data sheets.
12 checks. Cooling system filters are The temp-differential is the difference
periodic maintenance items, with the between the standard module rating While the code doesn’t indicate the
re-fresh rate dependent upon typical at 25°C and the low temperature. high temperature to use (i.e., because
13 and unusual circumstances. The voltage (Voc) will rise with it is an equipment application issue),
temperatures under 25°C. the industry standard is to evaluate the
Solar systems installed near other new ASHRAE 2% and 4% high temperature
construction where dust is generated Seek the solar module data sheet for
14 (e.g., grading, paving) or agricultural a list of standard test condition (STC)
figures, coupled to known location
differences. Record high temperatures
environments may require additional data, temperature coefficients, and provide an indication of system
solar-system checks and services. any special module-related informa-
15 Planning for such contingencies is tion to determine the low-temperature
performance when climatic condition
reaches these levels.
the business of solar-system design, open circuit voltage. The NEC 2011,
construction and on-going operation. Beyond the damaging temperature
16 Performance-based incentives
and industry practice, requires the
use of the site’s Extreme Annual affects on photovoltaic module Vmp
require verifiable metering, often Mean Minimum Design Dry Bulb voltage levels, voltage drop in PV
by registered/approved independent conductors under such conditions also
17 third parties. Such monitoring periods
Temperature data, available in the
ASHRAE Handbook. Code requires need to be calculated and evaluated,
are typically for 60 or more months. that the resulting maximum voltage beyond normal temperatures. The
inverter only uses (knows) the Vmp
18 The S-Max inverter offers a wide range (Voc) when added in the “string of
voltage at the inverter, not at the
of features and options to enable a modules” be under 600V. Record
low temperatures provide an PV modules.
successful and long-lived solar-energy
19 harvesting solution. The isolation step- indication of system performance Increasing grid voltages also puts a
up transformer, coupled to either a when temperatures drop to these constraint on the minimum Vmp
negative or a positive grounded solar levels. The S-Max inverter is designed voltage at the DC input stage.
20 array, ensures that the S-Max can to standards higher than 600 Vdc.
match to all (known) solar module
technologies. The S-Max follows
21 standard industry and code practices

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-35
August 2013 System Application Considerations
Sheet 01 091
Other Application Considerations

To ensure the full MPPT range without federal or other codes, or by any nation, with a rechargeable battery,
power-clipping (reduced power governmental agency having jurisdic- a charger to keep it at full capacity i
output), prudent PV system designs tion. Optional standby systems, not when normal power is on, one or more
shall consider the PV array’s Vmp legally required, are also covered in lamps, and a relay to connect the
voltage drop to the point of the the NEC (Article 702). battery to the lamps on loss of normal ii
inverter connection, ambient power, is also permitted. Because
temperatures and the PV system Emergency systems are intended to of the critical nature of emergency
installation type’s effects on Vmp, supply power and illumination essen- power, ground fault protection is not 1
solar module miss-match and tial for safety to human life, when the required. It is considered preferable
tolerance variations, degradation of normal supply fails. NEC requirements to risk arcing damage, rather than to
solar modules over time (solar system are stringent, requiring periodic testing disconnect he emergency supply com- 2
life), etc. Typical Vmp design values, under load and automatic transfer to pletely. For emergency power, ground
based upon known and expected emergency power supply on loss of fault alarm is required by NEC 700.7(D)
conditions are 5–10% over the normal supply. See Figure 1.4-23. to indicate a ground fault in solidly 3
minimum MPPT tracking voltage. All wiring from emergency source to grounded wye emergency systems
Reference NEC 2011 Section 690, emergency loads must be kept separate of more than 150V to ground and
Solar Photovoltaic Systems. from all other wiring and equipment, circuit-protective devices rated 1000A 4
in its own distribution and raceway or more.
Emergency Power system, except in transfer equipment

Most areas have requirements


enclosures and similar locations. The Legally required standby systems, as 5
most common power source for large required by the governmental agency
for emergency and standby power emergency loads is an engine-generator having jurisdiction, are intended to
systems. The National Electrical Code set, but the NEC also permits the supply power to selected loads, other 6
does not specifically call for any emergency supply (subject to local code than those classed as emergency
emergency or standby power, but requirements) to be storage batteries, systems, on loss of normal power.
does have requirements for those
systems when they are legally
uninterruptible power supplies, a These are usually loads not essential 7
separate emergency service, or a to human safety, but loss of which
mandated and classed as emergency connection to the service ahead of the could create hazards or hamper
(Article 700), legally required standby normal service disconnecting means. rescue or fire-fighting operations. 8
(Article 701) by municipal, state, Unit equipment for emergency illumi-

9
Utility
Source
Typical Application: Three engine generator sets serve the load, plus one additional engine
generator set for redundancy to achieve N+1 level of performance. Open or Closed transition is available. 10
G1 G2 G3 G4
Paralleling Switchgear
with Distribution
11
Revenue
Metering
HMI 12
Touchscreen
52G1 52G2 52G3 52G4

Main D1 D2 D3 D4
13
Service

14

15

16
ATS1 N E ATS2 N E ATS3 N E ATS4 N E
To Normal To Emergency
Distribution Circuits 17
Circuits

EDP1 EDP2 EDP3 EDP4 18

Optional Remote PC 19
with Software
LP1 BP1 LP2 BP2 LP3 BP3 LP4 BP4
20
Figure 1.4-23. Typical Emergency Power System
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-36 Power Distribution Systems
System Application Considerations August 2013
Sheet 01 092
Other Application Considerations

NEC requirements are similar to those Industrial plants, especially in process It is important that the electrical sys-
i for emergency systems, except that industries, usually have some form tem designer providing a substantial
wiring may occupy the same distribu- of alternate power source to prevent source of emergency and standby
tion and raceway system as the extremely costly shutdowns. These power investigate the possibility of
ii normal wiring if desired. Optional standby generating systems are using it for peak shaving, and even
standby systems are those not legally critical when needed, but they are of partial utility company financing.
required, and are intended to protect needed only infrequently. They Frequently, substantial savings in
1 private business or property where represent a large capital investment. power costs can be realized for a
life safety does not depend on To be sure that their power will be small additional outlay in distribution
performance of the system. Optional available when required, they should and control equipment.
2 systems can be treated as part of the be tested periodically under load.
normal building wiring system. Both Peak shaving equipment operating in
legally required and optional standby The cost of electric energy has risen parallel with the utility are subject to the
3 systems should be installed in such to new high levels in recent years, and comments made under cogeneration
a manner that they will be fully avail- utilities bill on the basis not only of as to separation from the utility under
able on loss of normal power. It is power consumed, but also on the fault conditions.
4 preferable to isolate these systems basis of peak demand over a small
as much as possible, even though not interval. As a result, a new use for Sound Levels
required by code. in-house generating capacity has
5 developed. Utilities measure demand Sound Levels of Electrical Equipment
Where the emergency or standby charges on the basis of the maximum for Offices, Hospitals, Schools and
source, such as an engine generator demand for electricity in any given Similar Buildings
6 or separate service, has capacity to specific period (typically 15 or 30 Insurance underwriters and building
supply the entire system, the transfer minutes) during the month. Some owners desire and require that the
scheme can be either a full-capacity utilities have a demand “ratchet clause” electrical apparatus be installed
7 automatic transfer switch, or, less that will continue demand charges on for maximum safety and the least
costly but equally effective, normal a given peak demand for a full year, interference with the normal use of
and emergency main circuit breakers, unless a higher peak results in even the property. Architects should take
8 electrically interlocked such that on higher charges. One large load, coming particular care with the designs for
failure of the normal supply the on at a peak time, can create higher hospitals, schools and similar build-
emergency supply is connected to the electric demand charges for a year. ings to keep the sound perception of
9 load. However, if the emergency or
Obviously, reducing the peak demand such equipment as motors, blowers
standby source does not have capacity and transformers to a minimum.
for the full load, as is usually the can result in considerable savings in
10 case, such a scheme would require the cost of electrical energy. For those Even though transformers are
automatic disconnection of the installations with engine generators relatively quiet, resonant conditions
nonessential loads before transfer. for emergency use, modern control may exist near the equipment, which
11 Simpler and more economical in systems (computers or programmable will amplify their normal 120 Hz hum.
such a case is a separate emergency controllers) can monitor the peak Therefore, it is important that consid-
bus, supplied through an automatic demand, and start the engine-generator eration be given to the reduction of
12 transfer switch, to feed all critical to supply part of the demand as it
approaches a preset peak value. The
amplitude and to the absorption of
loads. The transfer switch connects energy at this frequency. This problem
this bus to the normal supply, in engine-generator must be selected begins in the designing stages of the
13 normal operation. On failure of the to withstand the required duty cycle. equipment and the building. There are
normal supply, the engine-generator The simplest of these schemes trans- two points worthy of consideration: 1)
is started, and when it is up to speed fer specific loads to the generator. What sound levels are desired in the
14 the automatic switch transfers the More complex schemes operate the normally occupied rooms of this build-
emergency loads to this source. On generator in parallel with the normal ing? 2) To effect this, what sound level
return of the normal source, manual or utility supply. The savings in demand in the equipment room and what type
15 automatic retransfer of the emergency charges can reduce the cost of owning of associated acoustical treatment
loads can take place. the emergency generator equipment. will give the most economical
In some instances, utilities with little installation overall?
16 Peak Shaving reserve capacity have helped finance A relatively high sound level in the
Many installations now have the cost of some larger customer- equipment room does not indicate
emergency or standby generators. owned generating equipment. In an abnormal condition within the
17 In the past, they were required for return, the customer agrees to take apparatus. However, absorption may
hospitals and similar locations, but some or all of his load off the utility be necessary if sound originating in
not common in office buildings or system and on to his own generator at
18 shopping centers. However, many the request of the utility (with varying
an unoccupied equipment room is
objectionable outside the room.
costly and unfortunate experiences limitations) when the utility load Furthermore, added absorption
during utility blackouts in recent years approaches capacity. In some cases,
19 have led to the more frequent installa- the customer’s generator is paralleled
material usually is desirable if
there is a “build-up” of sound
tion of engine generators in commer- with the utility to help supply the peak due to reflections.
utility loads, with the utility buying the
20 cial and institutional systems for safety
and for supplying important loads. supplied power. Some utilities have
been able to delay large capital expen-
ditures for additional generating
21 capacity by such arrangements.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-37
August 2013 System Application Considerations
Sheet 01 093
Other Application Considerations

Some reduction or attenuation takes Table 1.4-11. Maximum Average Sound Levels—Decibels
place through building walls, the kVA Liquid-Filled Transformers Dry-Type Transformers i
remainder may be reflected in various Self-Cooled Forced-Air Self-Cooled Forced-Air
directions, resulting in a build-up or Rating (OA) Cooled Rating (FA) Rating (AA) Cooled Rating (FA)
apparent higher levels, especially if ii
resonance occurs because of room 300 55 — 58 67
dimensions or material characteristics. 500 56 67 60 67
750 58 67 64 67 1
Area Consideration 1000 58 67 64 67
In determining permissible sound lev- 1500 60 67 65 68
2000 61 67 66 69
els within a building, it is necessary to
2500 62 67 68 71
2
consider how the rooms are to be used
3000 63 67 68 71
and what levels may be objectionable 3750 64 67 70 73
to occupants of the building. The
5000 65 67 71 73
3
ambient sound level values given in 6000 66 68 72 74
Table 1.4-10 are representative average 7500 67 69 73 75
values and may be used as a guide in 10,000 68 70 — 76
4
determining suitable building levels.
Because values given in Table 1.4-11 transmitted vibration is approximately
Decrease in sound level varies at an
are in general higher than those given 98%. If the floor or beams beneath 5
approximate rate of 6 dB for each
doubling of the distance from the in Table 1.4-10, the difference must be the transformer are light and flexible,
attenuated by distance and by proper the isolator must be softer or have
source of sound to the listener. For
use of materials in the design of the improved characteristics in order to 6
example, if the level 6 ft (1.8m) from
a transformer is 50 dB, the level at a building. An observer may believe keep the transmitted vibrations to a
that a transformer is noisy because minimum. (Enclosure covers and
distance of 12 ft (3.7m) would be 44 dB
the level in the room where it is ventilating louvers are often improp- 7
and at 24 ft (7.3m) the level decreases
to 38 dB, etc. However, this rule applies located is high. Two transformers of erly tightened or gasketed and
the same sound output in the same produce unnecessary noise.) The
only to equipment in large areas
room increase the sound level in the building structure will assist the 8
equivalent to an out-of-door installation,
with no nearby reflecting surfaces. room approximately 3 dB, and three dampeners if the transformer is
transformers by about 5 dB, etc. mounted above heavy floor members
Table 1.4-10. Typical Sound Levels or if mounted on a heavy floor slab. 9
Sounds due to structure-transmitted Positioning of the transformer in
Description Average vibrations originating from the trans- relation to walls and other reflecting
Decibel
Level (dB) former are lowered by mounting the surfaces has a great effect on reflected
10
transformers on vibration dampeners noise and resonances. Often, placing
Radio, recording and TV studios 25–30 or isolators. There are a number of the transformer at an angle to the wall,
Theatres and music rooms 30–35 different sound vibration isolating rather than parallel to it, will reduce
11
Hospitals, auditoriums and churches 35–40
materials that may be used with noise. Electrical connections to a
Classrooms and lecture rooms 35–40 good results. Dry-type power trans- substation transformer should
Apartments and hotels
Private offices and conference rooms
35–45
40–45
formers are often built with an isolator be made with flexible braid or
12
mounted between the transformer conductors; connections to an
Stores 45–55
support and case members. The individually mounted transformer
Residence (radio, TV off)
and small offices 53 natural period of the core and coil should be in flexible conduit.
13
Medium office (3 to 10 desks) 58 structure when mounted on vibration
Residence (radio, TV on) 60 dampeners is about 10% of the funda-
Large store (5 or more clerks) 61 mental frequency. The reduction in the 14
Factory office 61
Large office 64
Average factory 70 15
Average street 80

Transformer Sound Levels 16


Transformers emit a continuous
120 Hz hum with harmonics when
connected to 60 Hz circuits. The 17
fundamental frequency is the “hum”
that annoys people primarily because
of its continuous nature. For purposes 18
of reference, sound measuring
instruments convert the different
frequencies to 1000 Hz and a 40 dB 19
level. Transformer sound levels based
on NEMA publication TR-1 are listed
in Table 1.4-11. 20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-38 Power Distribution Systems
August 2013
Sheet 01094

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-1
August 2013 Reference Data
Sheet 01 095
IEEE Protective Relay Numbers

Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus


Device Function Definition Typical i
Number Uses

2 Time-delay starting or closing relay A device that functions to give a desired amount Used for providing a time-delay for
of time delay before or after any point of operation re-transfer back to the normal source
ii
in a switching sequence or protective relay system, in an automatic transfer scheme.
except as specifically provided by device functions
48, 62 and 79 described later. 1
6 Starting circuit breaker A device whose principal function is to connect —
a machine to its source of starting voltage.
19 Starting to running transition timer A device that operates to initiate or cause the Used to transfer a reduced voltage
2
automatic transfer of a machine from the starting starter from starting to running.
to the running power connection.
21 Distance relay A device that functions when the circuit — 3
admittance, impedance or reactance increases or
decreases beyond predetermined limits.
23 Temperature control device A device that functions to raise or to lower the Used as a thermostat to control 4
temperature of a machine or other apparatus, or space heaters in outdoor equipment.
of any medium, when its temperature falls below
or rises above, a predetermined level. 5
24 Volts per hertz relay A device that operates when the ratio of voltage —
to frequency is above a preset value or is below
a different preset value. The relay may have any
combination of instantaneous or time delayed
6
characteristics.
25 Synchronizing or synchronism check device A device that operates when two AC circuits are In a closed transition breaker
within the desired limits of frequency, phase angle transfer, a 25 relay is used to ensure 7
or voltage, to permit or cause the paralleling of two-sources are synchronized before
these two circuits. paralleling. Eaton FP-5000/EDR-5000
feeder protective relays. 8
27 Undervoltage relay A device which functions on a given value of Used to initiate an automatic transfer
undervoltage. when a primary source of power is lost.
Eaton FP-5000/FP-4000/MP-4000/
EDR-5000/EDR-4000 protective relays.
9
30 Annunciator relay A non-automatically reset device that gives a Used to remotely indicate that a
number of separate visual indications upon the
functioning of protective devices, and which may
protective relay has functioned, or
that a circuit breaker has tripped.
10
also be arranged to perform a lockout function. Typically, a mechanical “drop” type
annunciator panel is used.
32 Directional power relay A relay that functions on a desired value of power Used to prevent reverse power from 11
flow in a given direction, or upon reverse power feeding an upstream fault. Often
resulting from arc back in the anode or cathode used when primary backup generation
circuits of a power rectifier. is used in a facility. Eaton FP-5000/
EDR-5000 protective relays.
12
33 Position switch A device that makes or breaks contact when the Used to indicate the position of a
main device or piece of apparatus, which has no
device function number, reaches a given point.
drawout circuit breaker (TOC switch). 13
34 Master sequence device A device such as a motor-operated multi-contact —
switch, or the equivalent, or a programmable
device, that establishes or determines the operating
14
sequence of the major devices in equipment
during starting and stopping, or during sequential
switching operations. 15
37 Undercurrent or underpower relay A relay that functions when the current or power Eaton MP-3000/MP-4000/EMR-3000
flow decreases below a predetermined value. motor protective relays.
38 Bearing protective device A device that functions on excessive bearing Eaton MP-3000/MP-4000 motor 16
temperature, or on other abnormal mechanical protective relays.
conditions, such as undue wear, which may
eventually result in excessive bearing temperature. 17
40 Field relay A device that functions on a given or abnormally —
high or low value or failure of machine field current,
or on an excessive value of the reactive component
of armature current in an AC machine indicating
18
abnormally high or low field excitation.
41 Field circuit breaker A device that functions to apply, or to remove, —
the field excitation of a machine. 19
42 Running circuit breaker A device whose function is to connect a machine —
to its source of running or operating voltage.
This function may also be used for a device, such 20
as a contactor, that is used in series with a circuit
breaker or other fault-protecting means, primarily
for frequent opening and closing of the circuit. 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-2 Power Distribution Systems
Reference Data August 2013
Sheet 01 096
IEEE Protective Relay Numbers

Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
i Device Function Definition Typical
Number Uses

ii 43 Manual transfer or selector device A manually operated device that transfers control
or potential circuits in order to modify the plan of

operation of the associated equipment or of some


of the associated devices.
1 44 Unit sequence starting relay A device that functions to start the next available —
unit in multiple-unit equipment upon the failure or
non-availability of the normally preceding unit.
2 46 Reverse-phase, or phase balance, A relay that functions when the polyphase Eaton FP-5000/FP-4000/EDR-5000/
current relay currents are of reverse-phase sequence, or when EDR-4000 feeder protective relays and
the polyphase currents are unbalanced or contain MP-3000/MP-4000/EMR-3000 motor
3 the negative phase-sequence components above protective relays.
a given amount.
47 Phase-sequence voltage relay A relay that functions upon a predetermined Eaton FP-5000/FP-4000/EDR-5000/
4 value of polyphase voltage in the desired phase
sequence.
EDR-4000 feeder protective relays
and MP-3000/MP-4000 motor
protective relays.

5 48 Incomplete sequence relay A relay that generally returns the equipment to the —
normal, or off, position and locks it out of the
normal starting, or operating or stopping sequence
is not properly completed within a predetermined
6 amount of time. If the device is used for alarm
purposes only, it should preferably be designated
as 48A (alarm).
7 49 Machine, or transformer, thermal relay A relay that functions when the temperature of a Eaton MP-3000/MP-4000/EMR-3000/
machine armature, or other load carrying winding ETR-4000 motor protective relays.
or element of a machine, or the temperature
of a power rectifier or power transformer
8 (including a power rectifier transformer) exceeds
a predetermined value.
50 Instantaneous overcurrent, A relay that functions instantaneously on an Used for tripping a circuit breaker
9 or rate-of-rise relay excessive value of current, or an excessive rate of instantaneously during a high-level
current rise, thus indicating a fault in the apparatus short circuit. Can trip on phase-
of the circuit being protected. phase (50), phase-neutral (50N),
10 phase-ground (50G) faults.
Eaton Digitrip 3000, FP-5000/
FP-4000/EDR-5000/EDR-4000/
EDR-3000 protective relays,
11 MP-3000/MP-4000/EMR-3000/
ETR-4000 motor protective relays.
51 AC time overcurrent relay A relay with either a definite or inverse time Used for tripping a circuit breaker
12 characteristic that functions when the current in an after a time delay during a sustained
AC circuit exceeds a predetermined value. overcurrent. Used for tripping a
circuit breaker instantaneously
during a high-level short circuit.
13 Can trip on phase (51), neutral (51N)
or ground (51G) overcurrents.
Eaton Digitrip 3000, FP-5000/
14 FP-4000/EDR-5000/EDR-4000/
EDR-3000 protective relays,
MP-3000/MP-4000/EMR-3000/
ETR-4000 motor protective relays.
15 52 AC circuit breaker A device that is used to close and interrupt an A term applied typically to medium
AC power circuit under normal conditions or to voltage circuit breakers, or low
interrupt this circuit under fault or emergency voltage power circuit breakers.
16 conditions. Eaton VCP-W vacuum circuit
breaker, magnum DS low voltage
power circuit breaker
17 53 Exciter or DC generator relay A device that forces the DC machine field excitation —
to build up during starting or that functions when
the machine voltage has built up to a given value.
18 55 Power factor relay A relay that operates when the power factor Eaton FP-5000/FP-4000/EDR-5000
in an AC circuit rises above or below a feeder protective relays and MP-4000
predetermined value. motor protective relay.
19 56 Field application relay A device that automatically controls the application —
of the field excitation to an AC motor at some
predetermined point in the slip cycle.

20 59 Overvoltage relay A relay that functions on a given value of


overvoltage.
Used to trip a circuit breaker,
protecting downstream equipment
from sustained overvoltages.
Eaton FP-5000/FP-4000/EDR-5000
21 feeder protective relays and MP-4000
motor protective relay.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-3
August 2013 Reference Data
Sheet 01 097
IEEE Protective Relay Numbers

Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
Device Function Definition Typical i
Number Uses

60 Voltage or current balance relay A relay that operates on a given difference in


voltage, or current input or output of two circuits.
— ii
62 Time-delay stopping or opening relay A time-delay relay that serves in conjunction with Used in conjunction with a 27 device
the device that initiates the shutdown, stopping
or opening operation in an automatic sequence.
to delay tripping of a circuit breaker
during a brief loss of primary voltage,
1
to prevent nuisance tripping.
63 Pressure switch A switch that operates on given values or on a Used to protect a transformer during
given rate of change of pressure. a rapid pressure rise during a short 2
circuit. This device will typically act
to open the protective devices above
and below the transformer. Typically 3
used with a 63-X auxiliary relay to
trip the circuit breaker.
64 Ground protective relay A relay that functions on a failure of the insulation Used to detect and act on a ground-
of a machine, transformer or of other apparatus to fault condition. In a pulsing high
4
ground, or on flashover of a DC machine to ground. resistance grounding system, a 64
device will initiate the alarm.
65 Governor A device consisting of an assembly of fluid, —
5
electrical or mechanical control equipment used for
regulating the flow of water, steam or other media
to the prime mover for such purposes as starting, 6
holding speed or load, or stopping.
66 Notching or jogging device A device that functions to allow only a specified Eaton MP-3000/MP-4000/EMR-3000
number of operations of a given device, or motor protective relays. 7
equipment, or a specified number of successive
operations within a given time of each other. It also
functions to energize a circuit periodically or for
fractions of specified time intervals, or that is used 8
to permit intermittent acceleration or jogging of a
machine at low speeds for mechanical positioning.
67 AC directional overcurrent relay A relay that functions on a desired value of AC Eaton FP-5000/EDR-5000 feeder 9
overcurrent flowing in a predetermined direction. protective relays.
69 Permissive control device A device that is generally a two-position manually Used as a remote-local switch for
operated switch that in one position permits the circuit breaker control. 10
closing of a circuit breaker, or the placing of
equipment into operation, and in the other position
prevents the circuit breaker to the equipment from
being operated.
11
71 Level switch A switch that operates on given values, or on a Used to indicate a low liquid level within
given rate of change of level. a transformer tank in order to save
transformers from loss-of-insulation 12
failure. An alarm contact is available
as a standard option on a liquid level
gauge. It is set to close before an unsafe 13
condition actually occurs.
72 DC circuit breaker A device that is used to close and interrupt a —
DC power circuit under normal conditions or to
interrupt this circuit under fault or emergency
14
conditions.
73 Load-resistor contactor A device that is used to shunt or insert a step of
load limiting, shifting or indicating resistance in

15
a power circuit; to switch a space heater in circuit;
or to switch a light or regenerative load resistor
of a power rectifier or other machine in and out 16
of circuit.
74 Alarm relay A device other than an annunciator, as covered —
under device number 30, which is used to operate, 17
or to operate in connection with, a visible or
audible alarm.
78 Phase-angle measuring relay A device that functions at a predetermined phase
angle between two voltages, between two currents,
— 18
or between voltage and current.
79 AC reclosing relay A relay that controls the automatic closing and
locking out of an AC circuit interrupter.
Used to automatically reclose a
circuit breaker after a trip, assuming
19
the fault has been cleared after the
power was removed from the circuit.
The recloser will lock-out after a 20
predetermined amount of failed
attempts to reclose.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-4 Power Distribution Systems
Reference Data August 2013
Sheet 01 098
IEEE Protective Relay Numbers

Table 1.5-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
i Device Function Definition Typical
Number Uses

ii 81 Frequency relay A relay that functions on a predetermined value of


frequency—either under or over, or on normal
Used to trip a generator circuit
breaker in the event the frequency
system frequency—or rate of change frequency. drifts above or below a given value.
Eaton FP-5000/FP-4000/EDR-5000/
1 EDR-4000 feeder protective
relays and MP-4000 motor
protective relay.
2 83 Automatic selective control or transfer relay A relay that operates to select automatically Used to transfer control power
between certain sources or conditions in sources in a double-ended
equipment, or performs a transfer operation switchgear lineup.
3 automatically.
85 Carrier or pilot-wire relay A device that is operated or restrained by a signal —
transmitted or received via any communications
media used for relaying.
4 86 Locking-out relay An electrically operated hand, or electrically, reset Used in conjunction with protective
relay that functions to shut down and hold an relays to lock-out a circuit breaker
equipment out of service on the occurrence of (or multiple circuit breakers) after
5 abnormal conditions. a trip. Typically required to be
manually reset by an operator before
the breaker can be reclosed.
6 87 Differential protective relay A protective relay that functions on a percentage or Used to protect static equipment,
phase angle or other quantitative difference of two such as cable, bus or transformers,
currents or of some other electrical quantities. by measuring the current differential
7 between two points. Typically the
upstream and/or downstream circuit
breaker will be incorporated into the
“zone of protection.” Eaton FP-5000
8 feeder protective relay (87B) and
MD-3000 protective relay.
90 Regulating device A device that functions to regulate a quantity or —
9 quantities, such as voltage, current, power, speed,
frequency, temperature and load, at a certain value
or between certain (generally close) limits for
machines, tie lines or other apparatus.
10 91 Voltage directional relay A device that operates when the voltage across an —
open circuit breaker or contactor exceeds a given
value in a given direction.
11 94 Tripping or trip-free relay A relay that functions to trip a circuit breaker, —
contactor or equipment, or to permit immediate
tripping by other devices, or to prevent immediate
12 reclosure of a circuit interrupter, in case it should
open automatically even though its closing circuit
is maintained closed.
13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-5
August 2013 Reference Data
Sheet 01 099
Suggested IEEE Designations for Suffix Letters

Suggested IEEE Designations Main Device Other Suffix Letters


i
for Suffix Letters The following letters denote the main The following letters cover all other
device to which the numbered device distinguishing features, characteris-
Auxiliary Devices is applied or is related: tics or conditions not specifically ii
described in Auxiliary Devices through
These letters denote separate auxiliary A Alarm/auxiliary power Main Device Parts, which serve to
devices, such as the following:
AC Alternating current describe the use of the device in the 1
C Closing relay/contactor equipment, such as:
BP Bypass
A Automatic
CL Auxiliary relay, closed
BT Bus tie 2
(energized when main device BF Breaker failure
is in closed position) C Capacitor
C Close 3
CS Control switch DC Direct current
D Decelerating/down
D “Down” position switch relay E Exciter
E Emergency 4
L Lowering relay F Feeder/field
F Failure/forward
O Opening relay/contactor G Generator/ground
HS High speed 5
OP Auxiliary relay, open M Motor/metering
(energized when main device L Local/lower
is in open position) MOC Mechanism operated contact
M Manual
6
PB Push button S Synchronizing/secondary
O Open
R Raising relay T Transformer 7
OFF Off
U “UP” position switch relay TOC Truck-operated contacts
ON On
8
X Auxiliary relay Main Device Parts R Raise/reclosing/remote/reverse
Y Auxiliary relay These letters denote parts of the
main device, except auxiliary contacts, T Test/trip 9
Z Auxiliary relay position switches, limit switches and TDC Time-delay closing contact
torque limit switches:
Actuating Quantities TDDO Time delayed relay coil 10
C Coil/condenser/capacitor drop-out
These letters indicate the condition or
electrical quantity to which the device CC Closing coil/closing contactor
responds, or the medium in which it is
TDO Time-delay opening contact 11
located, such as the following: HC Holding coil TDPU Time delayed relay coil pickup
A Amperes/alternating M Operating motor THD Total harmonic distortion 12
C Current OC Opening contactor

F Frequency/fault S Solenoid 13
I0 Zero sequence current SI Seal-in

I-, I2 Negative sequence current T Target 14


I+, I1 Positive sequence current TC Trip coil
15
P Power/pressure
PF Power factor
16
S Speed
T Temperature 17
V Voltage/volts/vacuum
VAR Reactive power 18
VB Vibration
W Watts 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-6 Power Distribution Systems
Reference Data August 2013
Sheet 01 100
Codes and Standards

Codes and Standards a number of other testing laboratories A design engineer should conform
i The National Electrical Code (NEC),
have been recognized and accepted. to all applicable codes, and require
The Institute of Electrical and Electronic equipment to be listed by UL or
NFPA Standard No. 70, is the most Engineers (IEEE) publishes a number another recognized testing laboratory
ii prevalent electrical code in the United
States. The NEC, which is revised every
of books (the “color book” series) on wherever possible, and to meet
recommended practices for the design ANSI or NEMA standards. ANSI/IEEE
three years, has no legal standing of of industrial buildings, commercial recommended practices should
1 its own, until it is adopted as law by buildings, emergency power systems, be followed to a great extent. In
a jurisdiction, which may be a city, grounding, and the like. Most of these many cases, standards should be
county or state. Most jurisdictions IEEE standards have been adopted as exceeded to get a system of the
2 adopt the NEC in its entirety; some ANSI standards. They are excellent quality required. The design goal
adopt it with variations, usually more guides, although they are not in any should be a safe, efficient, long-
rigid, to suit local conditions and way mandatory. lasting, flexible and economical
3 requirements. A few large cities, such electrical distribution system.
as New York and Chicago, have their
own electrical codes, basically similar Professional Organizations
4 to the NEC. The designer must deter-
American National Standards Institute National Electrical Manufacturers
mine which code applies in the area
of a specific project. (ANSI) Association (NEMA)
5 The Occupational Safety and Health Headquarters: 1300 North 17th Street
Suite 1847
Act (OSHA) of 1970 sets uniform 1819 L Street, NW Rosslyn, VA 22209
national requirements for safety in the 6th Floor
6 workplace—anywhere that people are Washington, DC 20036
703-841-3200
employed. Originally OSHA adopted 202-293-8020 www.nema.org
the 1971 NEC as rules for electrical
7 safety. As the NEC was amended every Operations: National Fire Protection Association
three years, the involved process for 25 West 43rd Street (NFPA)
modifying a federal law such as OSHA 4th Floor 1 Battery March Park
8 made it impossible for the act to adopt New York, NY 10036 Quincy, MA 02169-7471
each new code revision. To avoid this 212-642-4900 617-770-3000
problem, the OSHA administration
9 in 1981 adopted its own code, a con- www.ansi.org www.nfpa.org
densed version of the NEC containing Institute of Electrical and Electronic Underwriters Laboratories (UL)
10 only those provisions considered Engineers (IEEE) 333 Pfingsten Road
related to occupational safety. OSHA
Northbrook, IL 60062-2096
was amended to adopt this code, Headquarters:
847-272-8800
11 based on NFPA Standard 70E, Part 1, 3 Park Avenue
which is now federal law. 17th Floor www.ul.com
The NEC is a minimum safety New York, NY 10016-5997
International Code Council (ICC)
12 standard. Efficient and adequate 212-419-7900
5203 Leesburg Pike
design usually requires not just Operations: Suite 600
meeting, but often exceeding NEC
13 requirements to provide an effective,
445 Hoes Lane Falls Church, VA 22041
1-888-422-7233
Piscataway, NJ 08854-1331
reliable, economical electrical system.
732-981-0060
www.iccsafe.org
14 Many equipment standards have been
www.ieee.org
established by the National Electrical The American Institute of Architects (AIA)
Manufacturers’ Association (NEMA) International Association of Electrical 1735 New York Avenue, NW
15 and the American National Standards Inspectors (IAEI) Washington, DC 20006-5292
Institute (ANSI). Underwriters 202-626-7300
901 Waterfall Way
Laboratories (UL) has standards that
Suite 602
16 equipment must meet before UL will
Richardson, TX 75080-7702
www.aia.org
list or label it. Most jurisdictions and
972-235-1455
OSHA require that where equipment
17 listed as safe by a recognized labora- www.iaei.org
tory is available, unlisted equipment
may not be used. UL is by far the most
18 widely accepted national laboratory,
although Factory Mutual Insurance
Company lists some equipment, and
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-7
August 2013 Reference Data
Sheet 01 101
Motor Protective Device Data

Motor Protection Table 1.5-2. Motor Circuit Protector (MCP), Circuit Breaker and Fusible Switch Selection Guide
Consistent with the 2011 NEC Horsepower Full Load Fuse Size NEC 430.52 Recommended Eaton i
Amperes Maximum Circuit Motor Circuit
430.6(A)(1) circuit breaker, HMCP and (NEC) FLA Amperes
fuse rating selections are based on Breaker Protector Type HMCP
full load currents for induction motors Time Delay Non-Time Delay Amperes Amperes Adj. Range
ii
running at speeds normal for belted 230V, Three-Phase
motors and motors with normal 1 3.6 10 15 15 7 21–70 1
torque characteristics using data taken 1-1/2 5.2 10 20 15 15 45–150
from NEC Table 430.250 (three-phase). 2 6.8 15 25 15 15 45–150
3 9.6 20 30 20 30 90–300
Actual motor nameplate ratings shall 2
be used for selecting motor running 5 15.2 30 50 30 30 90–300
overload protection. Motors built 7-1/2 22 40 70 50 50 150–500
10 28 50 90 60 50 150–500
special for low speeds, high torque 15 42 80 150 90 70 210–700 3
characteristics, special starting
20 54 100 175 100 100 300–1000
conditions and applications will 25 68 125 225 125 150 450–1500
require other considerations as 30 80 150 250 150 150 450–1500 4
defined in the application section 40 104 200 350 150 150 750–2500
of the NEC. 50 130 250 400 200 150 750–2500
These additional considerations may
60 154 300 500 225 250 1250–2500 5
75 192 350 600 300 400 2000–4000
require the use of a higher rated HMCP, 100 248 450 800 400 400 2000–4000
or at least one with higher magnetic
pickup settings.
125
150
312
360
600
700
1000
1200
500
600
600
600
1800–6000
1800–6000
6
200 480 1000 1600 700 600 1800–6000
Circuit breaker, HMCP and fuse
ampere rating selections are in 460V, Three-Phase 7
line with maximum rules given in 1 1.8 6 6 15 7 21–70
1-1/2 2.6 6 10 15 7 21–70
NEC 430.52 and Table 430.250. Based
on known characteristics of Eaton type
2
3
3.4
4.8
6
10
15
15
15
15
7
15
21–70
45–150
8
breakers, specific units are recom- 5 7.6 15 25 15 15 45–150
mended. The current ratings are no 7-1/2 11 20 35 25 30 90–300
more than the maximum limits set by 10 14 25 45 35 30 90–300 9
the NEC rules for motors with code 15 21 40 70 45 50 150–500
letters F to V or without code letters. 20 27 50 90 50 50 150–500
Motors with lower code letters will 25 34 60 110 70 70 210–700 10
require further considerations. 30 40 70 125 70 100 300–1000
40 52 100 175 100 100 300–1000
In general, these selections were 50 65 125 200 110 150 450–1500 11
based on: 60 77 150 150 125 150 750–2500
75 96 175 300 150 150 750–2500
1. Ambient—outside enclosure not
more than 40°C (104°F).
100 124 225 400 175 150 750–2500
12
125 156 300 500 225 250 1250–2500
150 180 350 600 250 400 2000–4000
2. Motor starting—infrequent 200 240 450 800 350 400 2000–4000
starting, stopping or reversing.
575V, Three-Phase
13
3. Motor accelerating time— 1 1.4 3 6 15 3 9–30
10 seconds or less. 1-1/2
2
2.1
2.7
6
6
10
10
15
15
7
7
21–70
21–70
14
4. Locked rotor—maximum 6 times 3 3.9 10 15 15 7 21–70
motor FLA. 5 6.1 15 20 15 15 45–150
7-1/2 9 20 30 20 15 45–150 15
Type HMCP motor circuit protector 10 11 20 35 25 30 90–300
may not set at more than 1300% of 15 17 30 60 40 30 90–300
the motor full-load current to comply 20 22 40 70 50 50 150–500 16
with NEC 430.52. (Except for NEMA 25 27 50 90 60 50 150–500
Design B energy high-efficiency 30 32 60 100 60 50 150–500
motors that can be set up to 1700%.) 40 41 80 125 80 100 300–1000 17
50 52 100 175 100 100 300–1000
Circuit breaker selections are based 60 62 110 200 125 150 750–2500
on types with standard interrupting 75
100
77
99
150
175
250
300
150
175
150
150
750–2500
750–2500
18
ratings. Higher interrupting rating types
may be required to satisfy specific 125 125 225 400 200 250 1250–2500
150 144 300 450 225 250 1250–2500
system application requirements.
200 192 350 600 300 400 2000–4000 19
For motor full load currents of
208V and 200V, increase the
corresponding 230V motor values
20
by 10 and 15% respectively.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-8 Power Distribution Systems
Reference Data August 2013
Sheet 01 102
Motor Protective Device Data

Table 1.5-3. 60 Hz, Recommended Protective Setting for Induction Motors


i hp Full Load Minimum Wire Size Minimum Conduit Size, Fuse Size NEC 430.52 Recommended Eaton:
Amperes 75°C Copper Ampacity Inches (mm) Maximum Amperes  Circuit Motor Circuit
(NEC) FLA at 125% FLA THW THWN Time Non-Time Breaker  Protector
ii Size Amperes XHHN Delay Delay Amperes Amperes Adjustable Range
115V, Single-Phase
1 3/4 13.8 14 20 0.50 (12.7) 0.50 (12.7) 25 45 30 Two-pole device
1 16 14 20 0.50 (12.7) 0.50 (12.7) 30 50 35 not available
1-1/2 20 12 30 0.50 (12.7) 0.50 (12.7) 35 60 40
2 2
3
24
34
10
8
30
50
0.50 (12.7)
0.75 (19.1)
0.50 (12.7)
0.50 (12.7)
45
60
80
110
50
70
5 56 4 85 1.00 (25.4) 0.75 (19.1) 100 175 100
7-1/2 80 3 100 1.00 (25.4) 1.00 (25.4) 150 250 150
3 230V, Single-Phase
3/4 6.9 14 20 0.50 (12.7) 0.50 (12.7) 15 25 15 Two-pole device
4 1
1-1/2
8
10
14
14
20
20
0.50 (12.7)
0.50 (12.7)
0.50 (12.7)
0.50 (12.7)
15
20
25
30
20
25
not available

2 12 14 20 0.50 (12.7) 0.50 (12.7) 25 40 30


3 17 12 30 0.50 (12.7) 0.50 (12.7) 30 60 40
5 5 28 10 50 0.50 (12.7) 0.50 (12.7) 50 90 60
7-1/2 40 8 50 0.75 (19.1) 0.50 (12.7) 70 125 80
 Consult fuse manufacturer’s catalog for smaller fuse ratings.
6  Types are for minimum interrupting capacity breakers. Ensure that the fault duty does not exceed breaker’s I.C.

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-9
August 2013 Reference Data
Sheet 01 103
Chart of Short Circuit Currents for Transformers

Table 1.5-4. Secondary Short-Circuit Current of Typical Power Transformers


Trans- Maximum 208V, Three-Phase 240V, Three-Phase 480V, Three-Phase 600V, Three-Phase i
former Short- Rated Short-Circuit Current Rated Short-Circuit Current Rated Short-Circuit Current Rated Short-Circuit Current
Rating Circuit Load rms Symmetrical Amps Load rms Symmetrical Amps Load rms Symmetrical Amps Load rms Symmetrical Amps
Three-
Phase
kVA
Available
Contin- Trans- 50% Com- Contin- Trans- 100% Com- Contin- Trans- 100% Com- Contin- Trans- 100% Com-
ii
uous former Motor bined uous former Motor bined uous former Motor bined uous former Motor bined
kVA and from Current, Current, Current, Current,
Impedance Primary Alone  Load  Alone  Load  Alone  Load  Alone  Load 
Amps Amps Amps Amps
Percent System 1
300 50,000 834 14,900 1700 16,600 722 12,900 2900 15,800 361 6400 1400 7800 289 5200 1200 6400
5% 100,000 834 15,700 1700 17,400 722 13,600 2900 16,500 361 6800 1400 8200 289 5500 1200 6700
150,000 834 16,000 1700 17,700 722 13,900 2900 16,800 361 6900 1400 8300 289 5600 1200 6800 2
250,000 834 16,300 1700 18,000 722 14,100 2900 17,000 361 7000 1400 8400 289 5600 1200 6800
500,000 834 16,500 1700 18,200 722 14,300 2900 17,200 361 7100 1400 8500 289 5700 1200 6900
Unlimited 834 16,700 1700 18,400 722 14,400 2900 17,300 361 7200 1400 8600 289 5800 1200 7000 3
500 50,000 1388 21,300 2800 25,900 1203 20,000 4800 24,800 601 10,000 2400 12,400 481 8000 1900 9900
5% 100,000 1388 25,200 2800 28,000 1203 21,900 4800 26,700 601 10,900 2400 13,300 481 8700 1900 10,600
150,000 1388 26,000 2800 28,800 1203 22,500 4800 27,300 601 11,300 2400 13,700 481 9000 1900 10,900
250,000 1388 26,700 2800 29,500 1203 23,100 4800 27,900 601 11,600 2400 14,000 481 9300 1900 11,200
4
500,000 1388 27,200 2800 30,000 1203 23,600 4800 28,400 601 11,800 2400 14,200 481 9400 1900 11,300
Unlimited 1388 27,800 2800 30,600 1203 24,100 4800 28,900 601 12,000 2400 14,400 481 9600 1900 11,500
750 50,000 2080 28,700 4200 32,900 1804 24,900 7200 32,100 902 12,400 3600 16,000 722 10,000 2900 12,900 5
5.75% 100,000 2080 32,000 4200 36,200 1804 27,800 7200 35,000 902 13,900 3600 17,500 722 11,100 2900 14,000
150,000 2080 33,300 4200 37,500 1804 28,900 7200 36,100 902 14,400 3600 18,000 722 11,600 2900 14,500
250,000 2080 34,400 4200 38,600 1804 29,800 7200 37,000 902 14,900 3600 18,500 722 11,900 2900 14,800 6
500,000 2080 35,200 4200 39,400 1804 30,600 7200 37,800 902 15,300 3600 18,900 722 12,200 2900 15,100
Unlimited 2080 36,200 4200 40,400 1804 31,400 7200 38,600 902 15,700 3600 19,300 722 12,600 2900 15,500
1000
5.75%
50,000
100,000
2776
2776
35,900
41,200
5600
5600
41,500 2406
46,800 2406
31,000
35,600
9800
9800
40,600 1203
45,200 1203
15,500
17,800
4800
4800
20,300
22,600
962
962
12,400
14,300
3900
3900
16,300
18,200
7
150,000 2776 43,300 5600 48,900 2406 37,500 9800 47,100 1203 18,700 4800 23,500 962 15,000 3900 18,900
250,000 2776 45,200 5600 50,800 2406 39,100 9800 48,700 1203 19,600 4800 24,400 962 15,600 3900 19,500
500,000 2776 46,700 5600 52,300 2406 40,400 9800 50,000 1203 20,200 4800 25,000 962 16,200 3900 20,100 8
Unlimited 2776 48,300 5600 53,900 2406 41,800 9800 51,400 1203 20,900 4800 25,700 962 16,700 3900 20,600
1500 50,000 4164 47,600 8300 55,900 3609 41,200 14,400 55,600 1804 20,600 7200 27,800 1444 16,500 5800 22,300
5.75% 100,000 4164 57,500 8300 65,800 3609 49,800 14,400 64,200 1804 24,900 7200 32,100 1444 20,000 5800 25,800 9
150,000 4164 61,800 8300 70,100 3609 53,500 14,400 57,900 1804 26,700 7200 33,900 1444 21,400 5800 27,200
250,000 4164 65,600 8300 73,900 3609 56,800 14,400 71,200 1804 28,400 7200 35,600 1444 22,700 5800 28,500
500,000 4164
Unlimited 4164
68,800
72,500
8300
8300
77,100 3609
80,800 3609
59,600
62,800
14,400
14,400
74,000 1804
77,200 1804
29,800
31,400
7200
7200
37,000 1444
38,600 1444
23,900
25,100
5800
5800
29,700
30,900
10
2000 50,000 — — — — — — — — 2406 24,700 9600 34,300 1924 19,700 7800 27,500
5.75% 100,000 — — — — — — — — 2406 31,000 9600 40,600 1924 24,800 7800 32,600
150,000 — — — — — — — — 2406 34,000 9600 43,600 1924 27,200 7800 35,000 11
250,000 — — — — — — — — 2406 36,700 9600 46,300 1924 29,400 7800 37,200
500,000 — — — — — — — — 2406 39,100 9600 48,700 1924 31,300 7800 39,100
Unlimited — — — — — — — — 2406 41,800 9600 51,400 1924 33,500 7800 41,300 12
2500 50,000 — — — — — — — — 3008 28,000 12,000 40,000 2405 22,400 9600 32,000
5.75% 100,000 — — — — — — — — 3008 36,500 12,000 48,500 2405 29,200 9600 38,800
150,000
250,000 —
— —













3008
3008
40,500
44,600
12,000
12,000
52,500 2405
56,600 2405
32,400
35,600
9600
9600
42,000
45,200
13
500,000 — — — — — — — — 3008 48,100 12,000 60,100 2405 38,500 9600 48,100
Unlimited — — — — — — — — 3008 52,300 12,000 64,300 2405 41,800 9600 51,400
3000 50,000 — — — — — — — — 3609 30,700 14,000 44,700 2886 24,600 11,500 36,100
14
5.75% 100,000 — — — — — — — — 3609 41,200 14,000 55,200 2886 33,000 11,500 44,500
150,000 — — — — — — — — 3609 46,600 14,000 60,600 2886 37,300 11,500 48,800
250,000 — — — — — — — — 3609 51,900 14,000 65,900 2886 41,500 11,500 53,000 15
500,000 — — — — — — — — 3609 56,800 14,000 70,800 2886 45,500 11,500 57,000
Unlimited — — — — — — — — 3609 62,800 14,000 76,800 2886 50,200 11,500 61,700
3750
5.75%
50,000
100,000
















4511
4511
34,000
47,500
18,000
18,000
52,000 3608
65,500 3608
27,200
38,000
14,400
14,400
41,600
52,400
16
150,000 — — — — — — — — 4511 54,700 18,000 72,700 3608 43,700 14,400 58,100
250,000 — — — — — — — — 4511 62,200 18,000 80,200 3608 49,800 14,400 64,200
500,000 — — — — — — — — 4511 69,400 18,000 87,400 3608 55,500 14,400 69,900 17
Unlimited — — — — — — — — 4511 78,500 18,000 96,500 3608 62,800 14,400 77,200
 Short-circuit capacity values shown correspond to kVA and impedances shown in this table. For impedances other than these, short-circuit currents
are inversely proportional to impedance. 18
 The motor’s short-circuit current contributions are computed on the basis of motor characteristics that will give four times normal current.
For 208V, 50% motor load is assumed while for other voltages 100% motor load is assumed. For other percentages, the motor short-circuit
current will be in direct proportion. 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-10 Power Distribution Systems
Reference Data August 2013
Sheet 01 104
Transformer Full Load Amperes

Table 1.5-5. Transformer Full-Load Current, Three-Phase, Self-Cooled Ratings


i Voltage, Line-to-Line
kVA 208 240 480 600 2400 4160 7200 12,000 12,470 13,200 13,800 22,900 34,400
ii 30 83.3 72.2 36.1 28.9 7.22 4.16 2.41 1.44 1.39 1.31 1.26 0.75 0.50
45 125 108 54.1 43.3 10.8 6.25 3.61 2.17 2.08 1.97 1.88 1.13 0.76
75 208 180 90.2 72.2 18.0 10.4 6.01 3.61 3.47 3.28 3.14 1.89 1.26
1 112-1/2
150
312
416
271
361
135
180
108
144
27.1
36.1
15.6
20.8
9.02
12.0
5.41
7.22
5.21
6.94
4.92
6.56
4.71
6.28
2.84
3.78
1.89
2.52
225 625 541 271 217 54.1 31.2 18.0 10.8 10.4 9.84 9.41 5.67 3.78
300 833 722 361 289 72.2 41.6 24.1 14.4 13.9 13.1 12.6 7.56 5.04
2 500 1388 1203 601 481 120 69.4 40.1 24.1 23.1 21.9 20.9 12.6 8.39
750 2082 1804 902 722 180 104 60.1 36.1 34.7 32.8 31.4 18.9 12.6
1000 2776 2406 1203 962 241 139 80.2 48.1 46.3 43.7 41.8 25.2 16.8
3 1500 4164 3608 1804 1443 361 208 120 72.2 69.4 65.6 62.8 37.8 25.2
2000 — 4811 2406 1925 481 278 160 96.2 92.6 87.5 83.7 50.4 33.6
2500 — — 3007 2406 601 347 200 120 116 109 105 63.0 42.0
4 3000
3750




3609
4511
2887
3608
722
902
416
520
241
301
144
180
139
174
131
164
126
157
75.6
94.5
50.4
62.9
5000 — — — 4811 1203 694 401 241 231 219 209 126 83.9
7500 — — — — 1804 1041 601 361 347 328 314 189 126
5 10,000 — — — — 2406 1388 802 481 463 437 418 252 168

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-11
August 2013 Reference Data
Sheet 01 105
Impedances Data

Approximate Impedance Data Table 1.5-9. 600V Primary Class Three-Phase Table 1.5-10. 600V Primary Class Three-Phase
Table 1.5-6. Typical Impedances—
NEMA TP-1 Energy-Efficient Dry-Type NEMA TP-1 Energy-Efficient Dry-Type i
Distribution Transformers, Aluminum Wound Distribution Transformers, Copper Wound
Three-Phase Transformers Liquid-Filled 
kVA %Z %R %X X/R kVA %Z %R %X X/R
kVA Liquid-Filled
150°C Rise Aluminum 150°C Rise Copper
ii
Network Padmount
15 4.8 4.6 1.4 0.30 15 4.8 4.0 2.6 0.65
30 4.6 3.5 3.0 0.86 30 5.2 3.1 4.1 1.33
37.5
45



— 45 5.1 3.8 3.4 0.91 45 4.6 3.5 3.0 0.86
1
50 — — 75 5.3 3.5 4.0 1.14 75 4.3 3.4 2.5 0.72
75 — 3.4 112.5 6.0 2.9 5.2 1.79 112.5 5.1 2.9 4.2 1.44
112.5 — 3.2 150 5.3 3.0 4.4 1.50 150 4.3 2.5 3.5 1.39 2
150 — 2.4
225 5.1 2.6 4.4 1.68 225 7.4 2.9 6.8 2.32
225 — 3.3 300 7.6 2.5 7.2 2.88 300 5.5 2.4 4.9 2.04
300 5.00 3.4 500 7.2 1.7 7.0 4.20 500 6.8 1.4 6.7 4.86 3
500 5.00 4.6
750 8.0 1.5 7.9 5.42 750 8.2 0.8 8.1 10.13
750 5.00 5.75
115°C Rise Aluminum 115°C Rise Copper
1000
1500
5.00
7.00
5.75
5.75 15 4.4 4.3 1.2 0.27 15 4.8 3.8 2.9 0.76
4
2000 7.00 5.75 30 4.8 4.4 1.8 0.41 30 4.6 3.0 3.5 1.19
2500 7.00 5.75 45 4.6 2.8 3.7 1.35 45 4.4 3.1 3.1 0.99
3000 — 6.50 75 5.9 2.8 5.1 1.82 75 4.7 2.7 3.9 1.43
5
3750 — 6.50 112.5 3.1 2.5 1.9 0.79 112.5 5.0 2.3 4.5 1.98
5000 — 6.50 150 5.2 2.2 4.7 2.16 150 4.4 1.9 4.0 2.09
 Values are typical. For guaranteed values, 225 6.2 2.0 5.8 2.93 225 8.1 2.6 7.7 2.99
6
refer to transformer manufacturer. 300 5.4 2.0 4.9 2.44 300 5.2 1.7 4.9 2.80
500 6.6 1.1 6.5 6.09 500 6.8 1.3 6.6 5.16
Table 1.5-7. 15 kV Class Primary— 80°C Rise Aluminum 80°C Rise Copper 7
Oil Liquid-Filled Substation Transformers 15 3.5 2.6 2.3 0.89 15 2.1 1.7 1.3 0.75
30 3.4 2.4 2.5 1.02 30 3.0 2.0 2.1 1.05
kVA %Z %R %X X/R
45 3.3 1.6 2.9 1.76 45 3.9 2.5 3.1 1.25 8
65°C Rise
75 4.3 1.9 3.9 2.05 75 4.3 2.0 3.8 1.93
112.5 5.00 1.71 4.70 2.75 112.5 4.1 1.8 3.7 2.04 112.5 3.3 1.8 2.8 1.60
150
225
5.00
5.00
1.88
1.84
4.63
4.65
2.47
2.52
150 4.7 1.4 4.5 3.22 150 3.7 1.8 3.2 1.78 9
225 5.6 1.4 5.4 3.77 225 5.4 1.5 5.2 3.60
300 5.00 1.35 4.81 3.57
300 6.1 1.4 5.9 4.18 300 6.1 1.2 6.0 5.07
500 5.00 1.50 4.77 3.18
750 5.75 1.41 5.57 3.96 500 5.4 0.8 5.3 6.57 10
Note: Values are typical. Measurements at
1000 5.75 1.33 5.59 4.21 Note: Values are typical. Measurements at
1500 5.75 1.12 5.64 5.04
temperature rise +20ºC.
2000 5.75 0.93 5.67 6.10 temperature rise +20°C. 11
2500 5.75 0.86 5.69 6.61
Table 1.5-11. 600V Primary Class
NEMA Type TP-1 Dry-Type Transformers 12
Table 1.5-8. 15 kV Class Primary—
Dry-Type Substation Transformers kVA Temperature Rise Impedance

kVA %Z %R %X X/R 300 80 3.16 at 100ºC


150°C Rise 300 115 3.03 at 135ºC 13
300 150 7.06 at 170ºC
300 4.50 2.87 3.47 1.21
500 115 5.97 at 135ºC
500
750
5.75
5.75
2.66
2.47
5.10
5.19
1.92
2.11 500 150 6.04 at 170ºC 14
1000 5.75 2.16 5.33 2.47 750 115 7.21 at 135ºC
1500 5.75 1.87 5.44 2.90 750 150 No test
2000 5.75 1.93 5.42 2.81 15
2500 5.75 1.74 5.48 3.15
80°C Rise
16
300 4.50 1.93 4.06 2.10
500 5.75 1.44 5.57 3.87
750 5.75 1.28 5.61 4.38
1000 5.75 0.93 5.67 6.10
17
1500 5.75 0.87 5.68 6.51
2000 5.75 0.66 5.71 8.72
2500 5.75 0.56 5.72 10.22 18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-12 Power Distribution Systems
Reference Data August 2013
Sheet 01 106
Transformer Losses

Transformer Loss Data Transformer losses for various At 0% load:


i See product sections for data.
loading can be estimated in the 1800 watts
following manner. The no load watt
Transformer Losses at Reduced Loads losses of the transformer are due to At 50% load:
ii Information on losses based on actual
magnetization and are present 1800 watts + (13,300)(0.5)2 =
whenever the transformer is 1800 watts + 3325 watts = 5125 watts
transformer test data can be obtained
energized. The load watt losses are
1 from the manufacturer. Transformer At 100% load:
the difference between the no load
manufacturers provide no load watt 1800 watts + 13,300 watts = 15,100 watts
watt losses and the full load watt
losses and total watt losses in accor-
losses. The load watt losses are
2 dance with ANSI standards. The At 110% load:
proportional to I2R and can be
calculated difference between the 1800 watts + (13,300)(1.1)2 =
estimated to vary with the transformer
no load losses and the total losses 1800 watts + 16,093 watts = 17,893 watts
load by the square of the load current.
3 are typically described as the load
losses. Although transformer coils For example, the approximate watts Because transformer losses vary
are manufactured with either aluminum loss data for a 1000 kVA oil-filled between designs and manufacturers,
additional losses such as from
4 or copper conductors, the industry
has sometimes referred to these load
substation transformer is shown in
cooling fans can be ignored for
the table as having 1800 watts no
losses as the “copper losses.” load losses and 15,100 watts full load these approximations.
5 losses, so the load losses are approxi- Note: 1 watthour = 3.413 Btu.
mately 13,300 watts (15,100–1800). The
transformer losses can be calculated
6 for various loads as follows.

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-13
August 2013 Reference Data
Sheet 01 107
Power Equipment Losses and Enclosures/Knockout Dimensions

Power Equipment Losses Enclosures


Table 1.5-12. Power Equipment Losses The following are reproduced from NEMA 250.
i
Equipment Watts Table 1.5-13. Comparison of Specific Applications of Enclosures for Indoor Nonhazardous Locations
Loss
Provides a Degree of Protection Against the Enclosure Type
ii
Medium Voltage Switchgear (Indoor, 5 and 15 kV) Following Environmental Conditions 1 2 4 4X 5 6 6P 12 12K 13
1200A breaker 600
2000A breaker 1400 Incidental contact with the enclosed equipment ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ 1
3000A breaker 2100 Falling dirt ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
4000A breaker 3700 Falling liquids and light splashing ■ ■ ■ ■ ■ ■ ■ ■ ■
Medium Voltage Switchgear (Indoor, 5 and 15 kV) Circulating dust, lint, fibers and flyings  ■ ■ ■ ■ ■ ■ ■ 2
Settling airborne dust, lint, fibers and flyings  ■ ■ ■ ■ ■ ■ ■ ■
600A unfused switch 500 Hosedown and splashing water ■ ■ ■ ■
1200A unfused switch 750
100A CL fuses 840 Oil and coolant seepage
Oil or coolant spraying and splashing
■ ■ ■

3
Medium Voltage Starters (Indoor, 5 kV) Corrosive agents ■ ■
400A starter FVNR 600 Occasional temporary submersion ■ ■
800A starter FVNR 1000 Occasional prolonged submersion ■ 4
600A fused switch 500  These enclosures may be ventilated.
1200A fused switch 800
 These fibers and flying are nonhazardous materials and are not considered the Class III type
Low Voltage Switchgear (Indoor, 480V) ignitable fibers or combustible flyings. For Class III type ignitable fibers or combustible flyings, 5
800A breaker 400 see the National Electrical Code, Article 500.
1600A breaker 1000
2000A breaker 1500 Table 1.5-14. Comparison of Specific Applications of Enclosures for Outdoor Nonhazardous Locations 6
3200A breaker 2400 Provides a Degree of Protection Against the Enclosure Type
4000A breaker 3000 Following Environmental Conditions 3 3R  3S 4 4X 6 6P
5000A breaker 4700 7
Fuse limiters—800A CB 200 Incidental contact with the enclosed equipment ■ ■ ■ ■ ■ ■ ■
Fuse limiters—1600A CB 500 Rain, snow and sleet  ■ ■ ■ ■ ■ ■ ■
Sleet  ■
Fuse limiters—2000A CB 750
Windblown dust ■ ■ ■ ■ ■ ■
8
Fuse truck—3200A CB 3600
Hosedown ■ ■ ■ ■
Fuse truck—4000A CB 4500
Corrosive agents ■ ■
Structures—3200A
Structures—4000A
4000
5000
Occasional temporary submersion ■ ■ 9
Occasional prolonged submersion ■
Structures—5000A 7000
 These enclosures may be ventilated.
High resistance grounding 1200
 External operating mechanisms are not required to be operable when the enclosure is ice covered. 10
Panelboards (Indoor, 480V)  External operating mechanisms are operable when the enclosure is ice covered.
225A, 42 circuit 300
Low Voltage Busway (Indoor, Copper, 480V) Table 1.5-15. Comparison of Specific Applications of Enclosures for Indoor Hazardous Locations 11
800A 44 per foot Provides a Degree of Protection Against Class Enclosure Types Enclosure Type
1200A 60 per foot Atmospheres Typically Containing 7 and 8, Class I Groups  9, Class II Groups 
1350A 66 per foot
(For Complete Listing, See NFPA 497M) A B C D E F G 10 12
1600A 72 per foot Acetylene I ■
2000A 91 per foot Hydrogen, manufactured gas I ■
2500A 103 per foot diethyl ether, ethylene, cyclopropane I ■ 13
3200A 144 per foot Gasoline, hexane, butane, naphtha, propane,
4000A 182 per foot acetone, toluene, isoprene I ■
5000A 203 per foot Metal dust II ■ 14
Motor Control Centers (Indoor, 480V) Carbon black, coal dust, coke dust II ■
Flour, starch, grain dust II ■
NEMA Size 1 starter 39
NEMA Size 2 starter 56
Fibers, flyings 
Methane with or without coal dust
III
MSHA


15
NEMA Size 3 starter 92
 For Class III type ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.
NEMA Size 4 starter 124
NEMA Size 5 starter 244
 Due to the characteristics of the gas, vapor or dust, a product suitable for one class or group may
not be suitable for another class or group unless so marked on the product.
16
Structures 200
Note: If the installation is outdoors and/or additional protection is required by Tables 1.5-13 and
Adjustable Frequency Drives (Indoor, 480V) 1.5-14, a combination-type enclosure is required.
Adjustable frequency drives > 96% 17
efficiency

Note: The information provided on power 18


equipment losses is generic data intended
to be used for sizing of HVAC equipment.
19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-14 Power Distribution Systems
Reference Data August 2013
Sheet 01 108
Conductor Resistance, Reactance, Impedance

2 2
Average Characteristics of Application Notes ■ Z = X +R
i 600V Conductors— ■ Resistance and reactance are ■ For busway impedance data, see
phase-to-neutral values, based on Tab 21 of this catalog
Ohms per 1000 ft (305m)
ii The tables below are average charac-
60 Hz AC, three-phase, four-wire
distribution, in ohms per 100 ft
■ For PF (power factor) values less
than 1.0, the effective impedance Z e
teristics based on data from IEEE (30m) of circuit length (not total is calculated from
Standard 141-1993. Values from
1 different sources vary because of
conductor lengths) Z e = R × PF + X sin (arc cos PF)
■ Based upon conductivity of 100%
operating temperatures, wire ■ For copper cable data, resistance
for copper, 61% for aluminum
stranding, insulation materials based on tinned copper at 60 Hz;
2 and thicknesses, overall diameters, ■ Based on conductor temperatures
600V and 5 kV nonshielded cable
random lay of multiple conductors of 75°C. Reactance values will
based on varnished cambric insula-
in conduit, conductor spacing, and have negligible variation with
3 tion; 5 kV shielded and 15 kV cable
other divergences in materials, test temperature. Resistance of both
based on neoprene insulation
conditions and calculation methods. copper and aluminum conductors
will be approximately 5% lower ■ For aluminum cable data, cable is
These tables are for 600V 5 kV and
4 15 kV conductors, at an average at 60°C or 5% higher at 90°C. cross-linked polyethylene insulated
temperature of 75°C. Other parameters Data shown in tables may be
are listed in the notes. For medium used without significant error
5 voltage cables, differences among between 60° and 90°C
manufacturers are considerably ■ For interlocked armored cable,
greater because of the wider variations use magnetic conduit data for
6 in insulation materials and thick- steel armor and non-magnetic
nesses, shielding, jacketing, overall conduit data for aluminum armor
7 diameters, and the like. Therefore,
data for medium voltage cables should
be obtained from the manufacturer
8 of the cable to be used.

Table 1.5-16. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305m) at 75ºC (a) Three Single Conductors
9 Wire Size, In Magnetic Duct In Non-Magnetic Duct
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
10 R X Z R X Z R X Z R X Z

8 0.811 0.0754 0.814 0.811 0.0860 0.816 0.811 0.0603 0.813 0.811 0.0688 0.814
8 (solid) 0.786 0.0754 0.790 0.786 0.0860 0.791 0.786 0.0603 0.788 0.786 0.0688 0.789
11 6 0.510 0.0685 0.515 0.510 0.0796 0.516 0.510 0.0548 0.513 0.510 0.0636 0.514
6 (solid) 0.496 0.0685 0.501 0.496 0.0796 0.502 0.496 0.0548 0.499 0.496 0.0636 0.500
4 0.321 0.0632 0.327 0.321 0.0742 0.329 0.321 0.0506 0.325 0.321 0.0594 0.326
12 4 (solid)
2
0.312
0.202
0.0632
0.0585
0.318
0.210
0.312
0.202
0.0742
0.0685
0.321
0.214
0.312
0.202
0.0506
0.0467
0.316
0.207
0.312
0.202
0.0594
0.0547
0.318
0.209
1 0.160 0.0570 0.170 0.160 0.0675 0.174 0.160 0.0456 0.166 0.160 0.0540 0.169

13 1/0
2/0
0.128
0.102
0.0540
0.0533
0.139
0.115
0.128
0.103
0.0635
0.0630
0.143
0.121
0.127
0.101
0.0432
0.0426
0.134
0.110
0.128
0.102
0.0507
0.0504
0.138
0.114
3/0 0.0805 0.0519 0.0958 0.0814 0.0605 0.101 0.0766 0.0415 0.0871 0.0805 0.0484 0.0939
4/0 0.0640 0.0497 0.0810 0.0650 0.0583 0.0929 0.0633 0.0398 0.0748 0.0640 0.0466 0.0792
14 250 0.0552 0.0495 0.0742 0.0557 0.0570 0.0797 0.0541 0.0396 0.0670 0.0547 0.0456 0.0712
300 0.0464 0.0493 0.0677 0.0473 0.0564 0.0736 0.0451 0.0394 0.0599 0.0460 0.0451 0.0644
350 0.0378 0.0491 0.0617 0.0386 0.0562 0.0681 0.0368 0.0393 0.0536 0.0375 0.0450 0.0586
15 400 0.0356 0.0490 0.0606 0.0362 0.0548 0.0657 0.0342 0.0392 0.0520 0.0348 0.0438 0.0559
450 0.0322 0.0480 0.0578 0.0328 0.0538 0.0630 0.0304 0.0384 0.0490 0.0312 0.0430 0.0531
500 0.0294 0.0466 0.0551 0.0300 0.0526 0.0505 0.0276 0.0373 0.0464 0.0284 0.0421 0.0508
16 600
750
0.0257
0.0216
0.0463
0.0495
0.0530
0.0495
0.0264
0.0223
0.0516
0.0497
0.0580
0.0545
0.0237
0.0194
0.0371
0.0356
0.0440
0.0405
0.0246
0.0203
0.0412
0.0396
0.0479
0.0445

Note: More tables on Page 1.5-15.


17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-15
August 2013 Reference Data
Sheet 01 109
Conductor Resistance, Reactance, Impedance

Table 1.5-17. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305m) at 75ºC (b) Three Conductor Cable
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor i
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
ii
8 0.811 0.0577 0.813 0.811 0.0658 0.814 0.811 0.0503 0.812 0.811 0.0574 0.813
8 (solid) 0.786 0.0577 0.788 0.786 0.0658 0.789 0.786 0.0503 0.787 0.786 0.0574 0.788
6
6 (solid)
0.510
0.496
0.0525
0.0525
0.513
0.499
0.510
0.496
0.0610
0.0610
0.514
0.500
0.510
0.496
0.0457
0.0457
0.512
0.498
0.510
0.496
0.0531
0.0531
0.513
0.499
1
4 0.321 0.0483 0.325 0.321 0.0568 0.326 0.321 0.0422 0.324 0.321 0.0495 0.325
4 (solid)
2
0.312
0.202
0.0483
0.0448
0.316
0.207
0.312
0.202
0.0508
0.0524
0.317
0.209
0.312
0.202
0.0422
0.0390
0.315
0.206
0.312
0.202
0.0495
0.0457
0.316
0.207
2
1 0.160 0.0436 0.166 0.160 0.0516 0.168 0.160 0.0380 0.164 0.160 0.0450 0.166
1/0 0.128 0.0414 0.135 0.128 0.0486 0.137 0.127 0.0360 0.132 0.128 0.0423 0.135
2/0 0.102 0.0407 0.110 0.103 0.0482 0.114 0.101 0.0355 0.107 0.102 0.0420 0.110 3
3/0 0.0805 0.0397 0.0898 0.0814 0.0463 0.0936 0.0766 0.0346 0.0841 0.0805 0.0403 0.090
4/0 0.0640 0.0381 0.0745 0.0650 0.0446 0.0788 0.0633 0.0332 0.0715 0.0640 0.0389 0.0749
250 0.0552 0.0379 0.0670 0.0557 0.0436 0.0707 0.0541 0.0330 0.0634 0.0547 0.0380 0.0666 4
300 0.0464 0.0377 0.0598 0.0473 0.0431 0.0640 0.0451 0.0329 0.0559 0.0460 0.0376 0.0596
350 0.0378 0.0373 0.0539 0.0386 0.0427 0.0576 0.0368 0.0328 0.0492 0.0375 0.0375 0.0530
400 0.0356 0.0371 0.0514 0.0362 0.0415 0.0551 0.0342 0.0327 0.0475 0.0348 0.0366 0.0505 5
450 0.0322 0.0361 0.0484 0.0328 0.0404 0.0520 0.0304 0.0320 0.0441 0.0312 0.0359 0.0476
500 0.0294 0.0349 0.0456 0.0300 0.0394 0.0495 0.0276 0.0311 0.0416 0.0284 0.0351 0.0453
600 0.0257 0.0343 0.0429 0.0264 0.0382 0.0464 0.0237 0.0309 0.0389 0.0246 0.0344 0.0422
750 0.0216 0.0326 0.0391 0.0223 0.0364 0.0427 0.0197 0.0297 0.0355 0.0203 0.0332 0.0389 6
Table 1.5-18. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Ft (305m) at 90ºC (a) Three Single Conductors
Wire Size, In Magnetic Duct In Non-Magnetic Duct
7
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z 8
6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —
4 0.532 0.050 0.534 0.532 0.068 0.536 0.532 0.040 0.534 0.532 0.054 0.535
2 0.335 0.046 0.338 0.335 0.063 0.341 0.335 0.037 0.337 0.335 0.050 0.339 9
1 0.265 0.048 0.269 0.265 0.059 0.271 0.265 0.035 0.267 0.265 0.047 0.269
1/0 0.210 0.043 0.214 0.210 0.056 0.217 0.210 0.034 0.213 0.210 0.045 0.215
2/0
3/0
0.167
0.133
0.041
0.040
0.172
0.139
0.167
0.132
0.055
0.053
0.176
0.142
0.167
0.133
0.033
0.037
0.170
0.137
0.167
0.132
0.044
0.042
0.173
0.139
10
4/0 0.106 0.039 0.113 0.105 0.051 0.117 0.105 0.031 0.109 0.105 0.041 0.113
250
300
0.0896
0.0750
0.0384
0.0375
0.0975
0.0839
0.0892
0.0746
0.0495
0.0479
0.102
0.0887
0.0894
0.0746
0.0307
0.0300
0.0945
0.0804
0.0891
0.0744
0.0396
0.0383
0.0975
0.0837
11
350 0.0644 0.0369 0.0742 0.0640 0.0468 0.0793 0.0640 0.0245 0.0705 0.0638 0.0374 0.0740
400 0.0568 0.0364 0.0675 0.0563 0.0459 0.0726 0.0563 0.0291 0.0634 0.0560 0.0367 0.0700
500 0.0459 0.0355 0.0580 0.0453 0.0444 0.0634 0.0453 0.0284 0.0535 0.0450 0.0355 0.0573 12
600 0.0388 0.0359 0.0529 0.0381 0.0431 0.0575 0.0381 0.0287 0.0477 0.0377 0.0345 0.0511
700 0.0338 0.0350 0.0487 0.0332 0.0423 0.0538 0.0330 0.0280 0.0433 0.0326 0.0338 0.0470
750 0.0318 0.0341 0.0466 0.0310 0.0419 0.0521 0.0309 0.0273 0.0412 0.0304 0.0335 0.0452 13
1000 0.0252 0.0341 0.0424 0.0243 0.0414 0.0480 0.0239 0.0273 0.0363 0.0234 0.0331 0.0405

Table 1.5-19. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 ft (30m) at 90ºC (b) Three Conductor Cable 14
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor
AWG or 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z 15
6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —
4
2
0.532
0.335
0.050
0.046
0.534
0.338

0.335

0.056

0.340
0.532
0.335
0.040
0.037
0.534
0.337

0.335

0.045

0.338
16
1 0.265 0.048 0.269 0.265 0.053 0.270 0.265 0.035 0.267 0.265 0.042 0.268
1/0 0.210 0.043 0.214 0.210 0.050 0.216 0.210 0.034 0.213 0.210 0.040 0.214
2/0 0.167 0.041 0.172 0.167 0.049 0.174 0.167 0.033 0.170 0.167 0.039 0.171 17
3/0 0.133 0.040 0.139 0.133 0.048 0.141 0.133 0.037 0.137 0.132 0.038 0.138
4/0 0.106 0.039 0.113 0.105 0.045 0.114 0.105 0.031 0.109 0.105 0.036 0.111
250 0.0896 0.0384 0.0975 0.0895 0.0436 0.100 0.0894 0.0307 0.0945 0.0893 0.0349 0.0959 18
300 0.0750 0.0375 0.0839 0.0748 0.0424 0.0860 0.0746 0.0300 0.0804 0.0745 0.0340 0.0819
350 0.0644 0.0369 0.0742 0.0643 0.0418 0.0767 0.0640 0.0245 0.0705 0.0640 0.0334 0.0722
400 0.0568 0.0364 0.0675 0.0564 0.0411 0.0700 0.0563 0.0291 0.0634 0.0561 0.0329 0.0650
19
500 0.0459 0.0355 0.0580 0.0457 0.0399 0.0607 0.0453 0.0284 0.0535 0.0452 0.0319 0.0553
600 0.0388 0.0359 0.0529 0.0386 0.0390 0.0549 0.0381 0.0287 0.0477 0.0380 0.0312 0.0492
700 0.0338 0.0350 0.0487 0.0335 0.0381 0.0507 0.0330 0.0280 0.0433 0.0328 0.0305 0.0448
750 0.0318 0.0341 0.0466 0.0315 0.0379 0.0493 0.0309 0.0273 0.0412 0.0307 0.0303 0.0431 20
1000 0.0252 0.0341 0.0424 0.0248 0.0368 0.0444 0.0239 0.0273 0.0363 0.0237 0.0294 0.0378

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-16 Power Distribution Systems
Reference Data August 2013
Sheet 01 110
Conductor Ampacities

Current Carrying Capacities of Copper and Aluminum and Copper-Clad Aluminum Conductors
i From National Electrical Code (NEC), 2011 Edition (NFPA 70-2011)
Table 1.5-20. Allowable Ampacities of Insulated Conductors Rated 0–2000V, 60° to 90°C (140° to 194°F).
ii Not more than three current-carrying conductors in raceway, cable or earth (directly buried), based on ambient temperature of 30°C (86°F).
Size Temperature Rating of Conductor (See Table 310.15 [B][16]) Size
AWG or 60°C (140°F) 75°C (167°F) 90°C (194°F) 60°C (140°F) 75°C (167°F) 90°C (194°F) AWG or
1 kcmil Types Types kcmil

TW, UF RHW, THHW, TBS, SA, SIS, TW, UF RHW, THHW, TBS, SA, SIS,
2 THW, THWN,
XHHW, USE, ZW
FEP, FEPB, MI,
RHH, RHW-2,
THW, THWN,
XHHW, USE
THHN, THHW,
THW-2, THWN-2,
THHN, THHW, RHH, RHW-2,
THW-2, THWN-2, USE-2, XHH,
3 USE-2, XHH, XHHW, XHHW-2,
XHHW, XHHW-2, ZW-2
ZW-2
4 Copper Aluminum or Copper-Clad Aluminum

18 — — 14 — — — —
16 — — 18 — — — —
5 14  15 20 25 — — — —
12  20 25 30 20 20 25 12 
10  30 35 40 25 30 35 10 
6 8 40 50 55 30 40 45 8
6 55 65 75 40 50 60 6
4 70 85 95 55 65 75 4
7 3 85 100 110 65 75 85 3
2 95 115 130 75 90 100 2
1 110 130 150 85 100 115 1
8 1/0 125 150 170 100 120 135 1/0
2/0 145 175 195 115 135 150 2/0
3/0 165 200 225 130 155 175 3/0
9 4/0 195 230 260 150 180 205 4/0
250 215 255 290 170 205 230 250
300 240 285 320 190 230 255 300
10 350 260 310 350 210 250 280 350
400 280 335 380 225 270 305 400
500 320 380 430 260 310 350 500
600 355 420 475 285 340 385 600
11 700 385 460 520 310 375 420 700
750 400 475 535 320 385 435 750
800 410 490 555 330 395 450 800
12 900 435 520 585 355 425 480 900
1000 455 545 615 375 445 500 1000
1250 495 590 665 405 485 545 1250
13 1500 520 625 705 435 520 585 1500
1750 545 650 735 455 545 615 1750
2000 560 665 750 470 560 630 2000
14  See NEC Section 240.4 (D).
Note: For complete details of using Table 1.5-20, see NEC Article 310 in its entirety.

15 Table 1.5-21. Correction Factors From NFPA 70-2011 (See Table 310.15 [B][2][a])
Ambient For ambient temperatures other than 30°C (86°F), multiply the allowable ampacities shown Ambient
Temperature °C above by the appropriate factor shown below. Temperature °F
16
21–25 1.08 1.05 1.04 1.08 1.05 1.04 070–77
26–30 1.00 1.00 1.00 1.00 1.00 1.00 078–86
17 31–35 0.91 0.94 0.96 0.91 0.94 0.96 087–95
36–40 0.82 0.88 0.91 0.82 0.88 0.91 096–104
41–45 0.71 0.82 0.87 0.71 0.82 0.87 105–113
18 46–50 0.58 0.75 0.82 0.58 0.75 0.82 114–122
51–55 0.41 0.67 0.76 0.41 0.67 0.76 123–131
56–60 — 0.58 0.71 — 0.58 0.71 132–140
61–70 — 0.33 0.58 — 0.33 0.58 141–158
19 71–80 — — 0.41 — — 0.41 159–176

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-17
August 2013 Reference Data
Sheet 01 111
Conductor Ampacities

Ampacities for Conductors (4) Preservation of the safety benefits (4) Adjustment factors shall not
i
of established industry practices apply to Type AC cable or to
Rated 0–2000V (Excerpted and standardized procedures. Type MC cable under the following
from NFPA 70-2011, 310.15) (1) General. For explanation of type
conditions:
ii
Note: Fine Print Note (FPN) was changed letters used in tables and for a. The cables do not have an overall
to Informational Note in the 2011 NEC. recognized sizes of conductors for outer jacket.

(A) General.
the various conductor insulations,
b. Each cable has not more than three 1
see Table 310.104(A) and Table
310.104(B). For installation current-carrying conductors.
(1) Tables or Engineering Supervision.
Ampacities for conductors shall requirements, see 310.1 through c. The conductors are 12 AWG copper. 2
be permitted to be determined by 310.15(A)(3) and the various
tables as provided in 310.15(B) or articles of this Code. For flexible d. Not more than 20 current-carrying
under engineering supervision, cords, see Table 400.4, Table conductors are installed without 3
as provided in 310.15(C). 400.5(A)(1) and Table 400.5(A)(2). maintaining spacing, are stacked,
or are supported on”bridle rings.”
Note: Informational Note No. 1: Ampacities (3) Adjustment Factors.
provided by this section do not take voltage (5) An adjustment factor of 60 percent 4
drop into consideration. See 210.19(A), (a) More Than Three Current- shall be applied to Type AC cable or
Informational Note No. 4, for branch circuits Carrying Conductors in a Raceway Type MC cable under the following
and 215.2(A), Informational No. 2, for feeders. or Cable. Where the number of conditions: 5
Note: Informational Note No. 2: For the current-carrying conductors in a
allowable ampacities of Type MTW wire, raceway or cable exceeds three, or a. The cables do not have an overall
see Table 13.5.1 in NFPA 79-2007, Electrical where single conductors or multi- outer jacket. 6
Standard for Industrial Machinery. conductor cables are installed
b. The number of current carrying
without maintaining spacing for
(2) Selection of Ampacity. Where a continuous length longer than
conductors exceeds 20. 7
more than one ampacity applies 24.00-inch (600 mm) and are not c. The cables are stacked or bundled
for a given circuit length, the installed in raceways, the allowable longer that 24.00-inch (600 mm)
lowest value shall be used. ampacity of each conductor shall without spacing being maintained. 8
Exception: Where two different be reduced as shown in Table
ampacities apply to adjacent 310.15(B)(3)(a). Each current-carrying (b) More Than One Conduit, Tube,
portions of a circuit, the higher conductor of a paralleled set of or Raceway. Spacing between 9
ampacity shall be permitted to conductors shall be counted as a conduits, tubing, or raceways
be used beyond the point of current-carrying conductor. shall be maintained.
transition, a distance equal to 10 ft
(c) Circular Raceways Exposed to
10
(3.0m) or 10 percent of the circuit Note: Informational Note No. 1: See Annex
length figured at the higher B, Table B.310.15(B)(2)(11), for adjustment Sunlight on Rooftops.
ampacity, whichever is less. factors for more than three current-carrying
conductors in a raceway or cable with Where conductors or cables are 11
Note: Informational Note: See 110.14(C) for load diversity. installed in circular raceways exposed
conductor temperature limitations due to to direct sunlight on or above rooftops,
termination provisions. Note: Informational Note No. 2: See 366.23(A) the adjustments shown in Table 1.5-22 12
for adjustment factors for conductors in shall be added to the outdoor
(B) Tables. Ampacities for conductors sheet metal auxiliary gutters and 376.22(B) temperature to determine the
rated 0–2000V shall be as specified for adjustment factors for conductors in applicable ambient temperature 13
metal wireways.
in the Allowable Ampacity for application of the correction
Table 310.15(B)(16) through factors in Table 310.15(B)(2)(a) or
Table 310.15(B)(19), and
(1) Where conductors are installed in
Table 310.15(B)(2)(b). 14
cable trays, the provisions of
Ampacity Table 310.15(B)(20) and 392.80 shall apply. Note: Informational Note: One source for
Table 310.15(B)(21) as modified
by 310.15(B)(1) through (B)(7). (2) Adjustment factors shall not apply
the average ambient temperatures in various 15
locations is the ASHRAE Handbook
to conductors in raceways having —Fundamentals.
Note: Informational Note: Table
a length not exceeding 24.00-inch
310.15(B)(16) through Table 310.15(B)(19)
(600 mm). Table 1.5-22. NEC (2011) Table 310.15(B)(3)(c)
16
are application tables for use in determining
conductor sizes on loads calculated in Ambient Temperature Adjustment for Circular
(3) Adjustment factors shall not apply Raceways Exposed to Sunlight On or
accordance with Article 220. Allowable
ampacities result from consideration of one to underground conductors enter- Above Rooftops
17
or more of the following: ing or leaving an outdoor trench
Distance Above Roof to Temperature
if those conductors have physical
(1) Temperature compatibility with protection in the form of rigid
Bottom of Conduit Adder ºF (ºC) 18
connected equipment, especially metal conduit, intermediate metal 0–0.51-inch (0–13.0 mm) 60 (33)
the connection points. conduit, rigid polyvinyl chloride Above 0.51-inch (13.0 mm)– 40 (22)
conduit (PVC), or reinforced 3.54-inch (90.0 mm) 19
(2) Coordination with circuit and thermosetting resin conduit (RTRC) Above 3.54-inch (90.0 mm)– 30 (17)
system overcurrent protection. having a length not exceeding 11.81-inch (300.0 mm)
(3) Compliance with the requirements 10 ft (3.05m), and if the number of Above 12.00-inch (300.0 mm)– 25 (14)
20
of product listings or certifications. conductors does not exceed four. 36.00-inch (900.0 mm)
See 110.3(B). 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-18 Power Distribution Systems
Reference Data August 2013
Sheet 01 112
Conductor Ampacities

(4) Bare or Covered Conductors. (b) In a three-wire circuit consisting (6) Grounding or Bonding Conductor.
i Where bare or covered conductors of two phase conductors and the A grounding or bonding conductor
are installed with insulated neutral conductor of a four-wire, shall not be counted when applying
conductors, the temperature three-phase, wye-connected the provisions of 310.15(B)(3)(a).
ii rating of the bare or covered system, a common conductor
conductor shall be equal to the carries approximately the same
lowest temperature rating of the current as the line-to-neutral load
1 insulated conductors for the currents of the other conductors
purpose of determining ampacity. and shall be counted when applying
the provisions of 310.15(B)(3)(a).
2 (5) Neutral Conductor.
(c) On a four-wire, three-phase wye
(a) A neutral conductor that carries circuit where the major portion of
only the unbalanced current from
3 other conductors of the same
the load consists of nonlinear
loads, harmonic currents are
circuit shall not be required to present in the neutral conductor;
be counted when applying the
4 provisions of 310.15(B)(3)(a).
the neutral conductor shall there-
fore be considered a current-
carrying conductor.
5

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-19
August 2013 Reference Data
Sheet 01 113
Formulas and Terms

Table 1.5-23. Formulas for Determining Amperes, hp, kW and kVA


To Direct Alternating Current i
Find Current Single-Phase Two-Phase—Four-Wire  Three-Phase

Amperes (l) when −−−−−×−−746


−hp −−−− hp × 746
−−−−−−−−−−−−−−−−−−−−−−−
hp × 746
−−−−−−−−−−−−−−−−−−−−−−−−−−−−
hp × 746
−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
ii
horsepower is known E × % eff E × % eff × pf 2 × E × % eff × pf 3 × E × % eff × pf
Amperes (l) when kW × 1000 kW × 1000 kW × 1000 kW × 1000
−−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−−−−−−−
kilowatts is known E E × pf 2 × E × pf 3 × E × % pf 1
Amperes (l) when — kVA × 1000
−−−−−−−−−−−−−−−−−−− kVA × 1000 −−−−−−−−
kVA ×−−1000
−−−−−−
−−−−−−−−−−−−−−−−−−−
kva is known E 2×E 3×E
Kilowatts I×E
−−−−−−−
l × E × pf
−−−−−−−−−−−−−−
l × E × 2 × pf
−−−−−−−−−−−−−−−−−−−−
l × E × 3 × pf
−−−−−−−−−−−−−−−−−−−−−−
2
1000 1000 1000 1000
kVA — I×E I×E×2 I×E× 3
−−−−−−− −−−−−−−−−−−− −−−−−−−−−−−−−−−
1000 1000 1000 3
Horsepower (output) I × E × % eff I × E × % eff × pf I × E × 2 × % eff × pf I × E × 3 × % eff × pf
−−−−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−− −−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−−
746 746 746 746
 For two-phase, three-wire circuits, the current in the common conductor is 2 times that in either of the two other conductors. 4
Note: Units of measurement and definitions for E (volts), I (amperes), and other abbreviations are given below under Common Electrical Terms.

Common Electrical Terms How to Compute Power Factor 5


Ampere (l) = unit of current or rate of flow of electricity
Watts
Determining Watts pf = ----------------------------------------------
Volt (E) = unit of electromotive force Volts × Amperes 6
Ohm (R) = unit of resistance 1. 1. From watthour meter.
Watts = rpm of disc x 60 x Kh
E
Ohms law: I = −− (DC or 100% pf) 7
R
Where Kh is meter constant
Megohm = 1,000,000 ohms
printed on face or nameplate
Volt Amperes (VA) = unit of apparent power of meter. 8
= E × l (single-phase)
If metering transformers are used,
= E×l× 3 above must be multiplied by the 9
Kilovolt Amperes (kVA) = 1000 volt-amperes transformer ratios.

Watt (W) = unit of true power 2. Directly from wattmeter reading. 10


Where:
= VA × pf
= 0.00134 hp Volts = line-to-line voltage as 11
measured by voltmeter.
Kilowatt (kW) = 1000 watts
Power Factor (pf) = ratio of true to apparent power Amperes = current measured in 12
W kW line wire (not neutral) by ammeter.
= -------- ------------
Watthour (Wh)
VA kVA
= unit of electrical work
Table 1.5-24. Temperature Conversion 13
(F° to C°) C° = 5/9 (F°–32°)
= 1 watt for 1 hour (C° to F°) F° = 9/5(C°)+32°
= 3.413 Btu C° –15 –10 –5 0 5 10 15 20
14
= 2655 ft-lbs F° 5 14 23 32 41 50 59 68

Kilowatt-hour (kWh) = 1000 watthours


Cº 25
F° 77
30
86
35 40 45
95 104 113
50 55
122 131
60
140
15
C° 65 70 75 80 85 90 95 100
Horsepower (hp) = measure of time rate of doing work
F° 149 158 167 176 185 194 203 212
= equivalent of raising 33,000 lbs 1 ft in 1 minute 16
= 746 watts 1 Inch = 2.54 centimeters

Demand Factor = ratio of maximum demand to the total connected load


1 Kilogram = 2.20 lbs 17
1 Square Inch = 1,273,200 circular mills
Diversity Factor = ratio of the sum of individual maximum demands of 1 Circular Mill = 0.785 square mil
the various subdivisions of a system to the maximum 18
1 Btu = 778 ft lbs
demand of the whole system
= 252 calories
Load Factor = ratio of the average load over a designated period 1 Year = 8760 hours 19
of time to the peak load occurring in that period

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-20 Power Distribution Systems
Reference Data August 2013
Sheet 01 114
Seismic Requirements

i Seismic Requirements

ii

1
General
2 In the 1980s, Eaton embarked on a
comprehensive program centered
around designing and building
3 electrical distribution and control
equipment capable of meeting and
exceeding the seismic load require-
4 ments of the Uniform Building Code
(UBC) and California Building Code
(CBC). These codes emphasize build-
5 ing design requirements. Electrical
equipment and distribution system
components are considered attach-
6 ments to the building. The entire
program has been updated to show
compliance with the 2009 International
7 Building Code (IBC) and the 2010 CBC
seismic requirements. A cooperative Figure 1.5-1. Typical Earthquake Ground Motion Map for the United States
effort with the equipment user, the
8 building designer and the equipment International Building Code (IBC) California Building Code
installer ensures that the equipment On December 9, 1994, the International The 2001 CBC was based upon the
is correctly anchored such that it can Code Council (ICC) was established 1997 UBC. In August of 2006, it was
9 withstand the effects of an earthquake. as a nonprofit organization dedicated repealed by the California Building
Eaton’s electrical distribution and to developing a single set of compre- Standards Commission (CBSC) and
control equipment has been tested hensive and coordinated codes. The replaced by the 2007 CBC, California
10 and seismically proven for require- ICC founders—the Building Officials Code of Regulations (CCR), Title 24,
ments exceeding the IBC and CBC. and Code Administrators (BOCA), the Part 2 and used the 2006 IBC as the
Over 100 different assemblies International Conference of Building basis for the code. The 2010 CBC
11 representing essentially all product Officials (ICBO), and the Southern is based upon the 2009 IBC, with
lines have been successfully tested Building Code Congress International amendments as deemed appropriate
and verified to seismic levels higher (SBCCI)—created the ICC in response by the CBSC. Eaton’s seismic
12 than the maximum seismic require- to technical disparities among the qualification program fully envelopes
ments specified in the IBC and CBC. three nationally recognized model the requirements of the 2010 CBC.
The equipment maintained structural codes now in use in the U.S. The
13 integrity and demonstrated the ability ICC offers a single, complete set of Process
to function immediately after the construction codes without regional
seismic tests. A technical paper, According to Chapter 16 of the 2009
limitations—the International
14 Earthquake Requirements and Eaton Building Code.
IBC, structure design, the seismic
Distribution and Control Equipment requirements of electrical equipment
in buildings may be computed in two
Seismic Capabilities (SA12501SE), Uniform Building Code (UBC)
15 provides a detailed explanation steps. The first step is to determine
of the applicable seismic codes 1997 was the final year in which the the maximum ground motion to be
and Eaton’s equipment qualification UBC was published. It has since been considered at the site. The second step
16 program. The paper may be found replaced by the IBC. is to evaluate the equipment mounting
at www.eaton.com/seismic. Type and attachments inside the building
in SA12501SE in the document or structure. These are then evaluated
17 search field. to determine appropriate seismic test
requirements. The ground motion,
seismic requirements of the equipment,
18 and the seismic response spectrum
requirements are discussed on
Page 1.5-22, see Figure 1.5-3.
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-21
August 2013 Reference Data
Sheet 01 115
Seismic Requirements

Ground Motion If the latitude and longitude of the SDS, the peak spectral acceleration,
According to the code, the first and
building location is not known, extends between the values of T 0 and i
another convenient Web site is TS. T0 and TS are defined in the codes
most important step in the process available that will provide this as follows:
is to determine the maximum information based upon a street ii
considered earthquake spectral address: http://geocoder.us/ T0 = 0.2 SD1/SDS = 0.2 x 1.24/1.90 =
response acceleration at short 0.131 seconds (7.63 Hz)
periods of 0.2 seconds (SS) and at
a period of 1.0 second (S1). These
To determine the maximum consid-
TS = SD1/SDS = 1.24/1.90 = 1
ered earthquake ground motion for
values are determined from a set most site classes (A through D), the 0.653 seconds (1.53 Hz)
of 24 spectral acceleration maps code introduces site coefficients, According to the IBC and ASCE 7, the 2
(Figure 1.5-1) and include numerous which when applied against the spectral acceleration (Sa) at periods
contour lines indicating the severity location-specific site class, produces less than 1.45 seconds may be com-
of the earthquake requirements at a the adjusted maximum considered puted by using the following formula: 3
particular location in the country. earthquake spectral response
acceleration for the required site. Sa = SDS (0.6 T/T0 + 0.4)
The spectral acceleration maps
indicate low to moderate seismic
The site coefficients are defined as Where T is the period where Sa is 4
Fa at 0.2 seconds short period and being calculated:
requirements for the entire country, FV at 1.0 second period. From the
with the exception of two particular
areas; the West Coast and the Midwest
tables in the code, the highest adjust- Therefore, the acceleration at 5
ing factor for SS is equal to 1.0 and the 0.0417 seconds (24 Hz), for example,
(the New Madrid area). The seismic highest adjusting factor for S1 is 1.50. is equal to:
requirements at the New Madrid area
are approximately 30% higher than the As a result, the adjusted maximum Sa = 1.90 (0.6 (0.0417/0.131) + 0.4) = 1.12g
6
maximum requirements of the West considered earthquake spectral
Coast. The maps also suggest that the response for 0.2 second short period The acceleration at 0.03 seconds
high seismic requirements in both (SMS) and at 1.0 second (SM1), adjusted (33 Hz) is equal to: 7
regions, West Coast and Midwest, for site class effects, are determined Sa = 1.90 (0.6 (0.03/0.131) + 0.4) = 1.02g
quickly decrease as one moves away from the following equations:
from the fault area. Therefore, the high At zero period (infinite frequency), 8
requirements are only limited to a SMS = Fa SS = 1.0 x 2.85g = 2.85g T = 0.0, the acceleration (ZPA) is
relatively narrow strip along the fault equal to:
lines. Just a few miles away from this
SM1 = Fv S1 = 1.5 x 1.24g = 1.86g 9
Sa = 1.90 (0.6 (0.0/0.131) + 0.4) =
strip, only a small percentage of the ASCE 7 (American Society of Civil
0.76g (ZPA)
maximum requirements are indicated. Engineers), Section 11.4, provides a
plot of the final shape of the design The acceleration to frequency
10
Assuming the worse condition, which response spectra of the seismic relationship in the frequency range
is a site directly located near a fault, ground motion. The plot is shown in
the maximum considered earthquake Figure 1.5-2. ASCE 7 is referenced
of 1.0 Hz to TS is stated equal to: 11
spectral response acceleration at short throughout the IBC as the source for Sa = SD1/T
periods of 0.2 seconds (SS) is equal to numerous structural design criteria.
285% gravity and at 1.0 second period Where Sa is the acceleration at the 12
(S1) is 124% gravity. These numbers The design spectral acceleration curve T period.
are the maximum numbers for the can now be computed. The peak spec- At 1.0 Hz (T=1.0) this equation yields
entire country except for the New tral acceleration (SDS) and the spectral the following acceleration:
13
Madrid area. These particular sites are acceleration at 1.0 second (SD1) may
on the border of California and Mexico now be computed from the following Sa = 1.24/1 = 1.24g
(S1) and in Northern California (SS). formulas in the code: 14
To help understand the 2009 IBC (and SDS = 2/3 x SMS = 2/3 x 2.85g = 1.90g
2010 CBC) seismic parameters for a
SD1 = 2/3 x SM1 = 2/3 x 1.8g = 1.24g
15
specific building location, the link to
the US Geological Society is extremely
helpful: http://earthquake.usgs.gov/ 16
Spectural Response Acceleration Sa(g)

research/hazmaps/design/
SDS
Download the file “Java Ground 17
Motion Parameter Calculator”—and SD1
Sa =
save it to your hard drive, then run the T
executable that was downloaded. 18
The program will allow one to enter SD1 S T
Sa = D12 L
the latitude and longitude of a T
location. (One must be connected 19
to the Internet to run this application,
even after downloading the program.)
The IBC (CBC) seismic parameters for 20
T0 TS 1.0 TL
that location will then be displayed. Period T (sec)
21
Figure 1.5-2. Design Response Spectrum

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-22 Power Distribution Systems
Reference Data August 2013
Sheet 01 116
Seismic Requirements

Testing has demonstrated that the It can be seen that Eaton has elected to This completes the ground motion
i lowest dominant natural frequency of develop generic seismic requirements design response spectrum. The
Eaton’s electrical equipment is above that envelop two criteria: spectral accelerations are equal to
3.2 Hz. This indicates that testing at 0.76g at ZPA, or 33 Hz, and increases
ii 1.24g at 1 Hz is not necessary. In ■ The highest possible spectral peak linearly to a peak acceleration of 1.90g
addition, having the low end of the accelerations and ZPA at 0.09 seconds (or 11.49 Hz) and stays
spectra higher than realistically ■ The maximum frequency range constant to 0.653 seconds (1.53 Hz),
1 required forces the shake table to required for many different sites then gradually decreases to 1.24g at
move at extremely high displacements 1 second (or 1.0 Hz). This curve is
to meet the spectral acceleration at shown in Figure 1.5-3.
2 the low frequencies.
Testing to accommodate the low end
3 of the spectra using this acceleration 10
9
component can result in testing to a 8
7 Test Response Spectrum Zero Period
factor 2 to 3 times greater than that Acceleration (g peak) 6 (TRS) Acceleration = Maximum
4 realistically required. 5

4
Table Test Motion

Through testing experience and data 3


analysis, the seismic acceleration at
5 1.0 Hz is taken equal to 0.7g, which 2 Spectrum Dip – Not Important
will ensure that the seismic levels are Because Frequency is Not an
achieved well below 3.2 Hz. This yields Equipment Natural Frequency
6 a more vigorous test over a wider 1.0
.9
range of seismic intensities. .8
.7
7 In developing the seismic requirements .6 Required Response Spectrum
(RRS)
Zero Period
Acceleration = Maximum
.5
above, it is important to recognize Floor Motion
.4
the following:
8 .3
T0 and TS are dependent on SMS and
SD1. If SD1 is small relative to SMS then .2

9 T0 and TS will be smaller and the


associated frequencies will shift
.1
higher. The opposite is also true. 1 2 3 4 5 6 78 9 10 20 30 40 60 80 100

10 This must be realized in developing Frequency Hz


the complete required response
spectrum (RRS). Therefore, it is not Figure 1.5-3. Design Response Spectrum
11 adequate to stop the peak spectral
acceleration at 7.63 Hz. There are other ASCE 7 Section 13.3—Seismic Rp = Component response modifica-
contour line combinations that will tion factor that for electrical equipment
12 produce higher T0. To account for this Demands on Non-Structural varies from 2.5 to 6.0.
variation it is almost impossible to Components
consider all combinations. However, Ip = Component importance factor that
ASCE 7 Paragraph 13.3.1 (IBC Section is either 1.0 or 1.5.
13 a study of the spectral acceleration 1621.1.4) provides a formula for
maps indicates that all variations with computing the seismic requirements Z = Highest point of equipment in a
high magnitude of contour lines could of electrical and mechanical equipment building relative to grade elevation.
14 very well be enveloped by a factor inside a building or a structure. The
of 1.5. Therefore, T0 is recomputed formula is designed for evaluating the h = Average roof height of building
as follows: equipment attachment to the equip- relative to grade elevation.
15 T0 = 0.2 SD1/(SDS x 1.5) = 0.2 x 1.24/ ment foundations. The seismic loads The following parameters produce the
(1.90 x 1.5) = 0.087 seconds (11.49 Hz) are defined as: maximum required force:
16 Eaton ensures maximum certification Fp = 0.4 ap SDS Wp (1 + 2 Z/h)/(Rp/Ip) ■ Z is taken equal to h (equipment
by requiring peak acceleration during Where: on roof)
testing to extend to 12 Hz. ■ Ip is taken equal to 1.5
17 Fp = Seismic design force imposed ■ ap is taken equal to 2.5
at the component’s center of gravity
(C.G.) and distributed relative to ■ Rp is taken equal to 2.5
18 component mass distribution. ■ SDS is equal to 1.90g as indicated
in the previous section
ap = Component amplification factor
19 that varies from 1.00 to 2.50. The acceleration (Fp/Wp) at the C.G.
of the equipment is then computed
SDS = Ground level spectral equal to:
20 acceleration, short period.
Acceleration = Fp/Wp = 0.4 x 2.5 x
Wp = Component operating weight. 1.90g (1 + 2) / (2.5/1.5) = 3.42g
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-23
August 2013 Reference Data
Sheet 01 117
Seismic Requirements

For equipment on (or below) grade,


the acceleration at the equipment C.G. 10 i
is then computed equal to:
Acceleration = Fp/Wp = 0.4 x 2.5 x ii
1.90g (1 + 0) / (2.5 /1.5) = 1.14g IBC 2009/CBC 2010 IBC 2009 New Madrid

It is impractical to attempt to measure


the actual acceleration of the C.G. of a 1
piece of equipment under seismic test.

Acceleration (g)
The seismic response at the middle of
base mounted equipment close to its 1 2
C.G. is at least 50% higher than the
Eaton Seismic
floor input at the equipment natural
frequency. The base accelerations 3
associated with the accelerations of
FP/WP at the C.G. of the equipment
could then be computed as 3.42 /1.5 4
= 2.28g. It is the equipment base input
acceleration that is measured and
documented during seismic testing
0.1 5
1 10 100
and is the acceleration value shown
on Eaton’s seismic certificates. Frequency (Hz)
6
Final Combined Requirements Figure 1.5-4. Required Response Spectrum Curve
To better compare all seismic levels 7
and determine the final envelope
10
seismic requirements, the 2010 CBC,
2009 IBC for California, and 2009 IBC 8
for New Madrid area seismic require-
ments are plotted in Figure 1.5-4. All Eaton 120% Seismic Envelope
curves are plotted at 5% damping. An 9
envelopment of the seismic levels in
the frequency range of 3.2 Hz to 100 Hz
10
Acceleration (g)

is also shown. This level is taken as Eaton 100% Seismic Envelope


Eaton’s generic seismic test require- 1
ments for all certifications. Eaton
performed additional seismic test runs 11
on the equipment at approximately
120% of the generic enveloping seismic
requirements (see Figure 1.5-5). Eaton 12
has established this methodology to
provide additional margin to accom-
modate potential changes with the 13
spectral maps, thus eliminating the
0.1
need for additional testing. 1 10 100
14
Frequency (Hz)

Figure 1.5-5. Eaton Test Required Response Spectrum Curve 15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-24 Power Distribution Systems
Reference Data August 2013
Sheet 01 118
Seismic Requirements

Product Specific Test Summaries


i Table 1.5-25. Distribution Equipment
Tested and Seismically Proven Against
Requirements within IBC 2009 y
ii
Eaton Equipment

Low voltage metal-enclosed switchgear


1 DS II
Magnum DS
High resistance ground
2 Panelboards
Pow-R-Line C 1a, 1a-LX, 2a, 2a-LX, 3a, 3E, 4,
5P, F-16 and Pow-R-Command™
3 Switchboards
Instant Pow-R-Line 5P
Integrated facilities Pow-R-Line C
Multimeter Pow-R-Line i
4 MCC
Advantage® IT.
FlashGard® Series 2100
5 Freedom 2100
Low voltage busway
Pow-R-Way® and associated fittings
6 Pow-R-Way III® and associated fittings
Dry type transformers
Mini powercenters
EP, EPT, DS-3, DT-3
7 Transfer switches
Automatic transfer switch equipment
Uninterruptible power supplies (UPS)
8 Battery modules
UPSs
Enclosed control safety switches
9 General-duty
Heavy-duty
Elevator control module
10 Medium voltage switchgear
Type VacClad-W Type MMVS
MEF Type MVS/MEB
MV bus
11 Metal-enclosed non-segregated phase bus
Network protectors
Type CM-22
12 Type CMD
Medium voltage control
AMPGARD®
13 SC9000 drives
Substation transformers
Dry-type
14 Liquid type
Unitized dry-type power centers Figure 1.5-6. Sample Seismic Certificate

Note: See www.eaton.com/seismic for


15 current seismic certificates.

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-25
August 2013 Reference Data
Sheet 01 119
Seismic Requirements

Additional Design and If steel, factors such as thickness or Stand-Alone or Free-Standing Equipment
Installation Considerations gauge, attachment via bolts or welding, If stand-alone or free-standing, then i
and the size and type of hardware this may require that additional width
When installing electrical distribution must be considered. space be allowed at each end of the
and control equipment, consideration equipment for additional seismic ii
must be given as to how the methods If concrete, the depth, the PSI, the type
of re-enforcing bars used, as well as bracing supplied by the manufacturer.
employed will affect seismic forces
imposed on the equipment, equipment the diameter and embedment of Additional thought must be given to 1
mounting surface, and conduits anchorage all must be considered. the clearances around the equipment
entering the equipment. The designer must also give consider- to rigid structural edifices. Space must
ation if the equipment will be secured be allowed for the differing motions of 2
Eaton recommends that when specify- the equipment and the structure, so
ing a brand of electrical distribution to the wall, versus stand-alone or free-
standing, which requires the equip- that they do not collide during a seis-
and control equipment, the designer
ment to withstand the highest level of mic event and damage one another. 3
references the installation manuals of
that manufacturer to ascertain that the seismic forces. Top cable entry should Note: If the equipment is installed as stand-
be avoided for large enclosures, as alone or free-standing, with additional
requirements can be met through the
accommodation for cable/conduit seismic bracing at each end and not
4
design and construction process.
flexibility will need to be designed attached to the structure as tested, and yet,
For Eaton electrical distribution and into the system. it is fitted tightly against a structural wall,
control products, the seismic installa- then this would be an incorrect installation 5
tion guides for essentially all product For a manufacturer to simply state for the application of the seismic certificate.
lines can be found at our Web site: “Seismic Certified” or “Seismic
http://www.eaton.com/seismic. Qualified” does not tell the designer Furthermore, if conduits are to be 6
if the equipment is appropriate for installed overhead into the equipment,
Electrical designers must work closely the intended installation. does the design call for flexible conduits
with the structural or civil engineers of sufficient length to allow for the 7
for a seismic qualified installation. Note: Eaton recommends that designers conflicting motion of the equipment
confirm with the manufacturer if the and the structure during a seismic event
seismic certification supplied with the
Consideration must be given to the
equipment is based on:
so as to not damage the conductors 8
type of material providing anchorage contained therein, and the terminations
for the electrical equipment. points within the equipment.
1. ACTUAL shaker table test as
required by the IBC and CBC. 9
Structure Attached Equipment
2. The seismic certificate and test The designer must work closely
data clearly state if the equipment with the structural engineer if the 10
was tested as free-standing— equipment is to be attached to the
anchored at the bottom of the structure to ascertain that the internal
equipment to the shaker table. wall re-enforcement of the structure, 11
type of anchor, and depth of embed-
3. Structure attached, that is, ment is sufficient to secure the
anchored at the center of gravity equipment so that the equipment, 12
(C.G.) or at the TOP of the equip- conduits and structure move at or
ment to a simulated wall on the near the same frequency.
shaker table. 13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-26 Power Distribution Systems
August 2013
Sheet 01120

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E

You might also like