Annexure-IV

TYPICAL ESTIMATE OF A RAINWATER COLLECTION UNIT


(110 mm / 150 mm dia PVC Pipelines)

A. 110 mm dia PVC Pipeline (to collect rainwater from roof)


Laying and fitting of 110 mm PVC pipes of 6 metres length including
transportation of pipe to work sites
Plumber 0.25 no @ Rs.190.00/no Rs. 47.50
Helper to Plumber 0.25 no @ Rs.150.00/no Rs. 37.50
Sangi mulia 2 no @ Rs.170.00/no Rs. 340.00
O.H.C. 10% Rs. 42.50
Cost & Carriage of pipes for 6 m @ Rs.250.00/mtr. Rs. 1500.00
Cost of solvent, bend, socket etc. for jointing LS Rs. 432.50
Rs.2400.00/6 m
Rs. 400.00/m
For 12 m length 110 mm dia PVC pipe Rs.400.00 x 12 = Rs. 4800.00
Cost of 2 PVC Control Valves @ Rs.350.00/no = Rs. 700.00
Sub-Total (A) Rs. 5500.00

B. 150 mm dia PVC Pipeline (to covey collected rainwater to underground


Filter Unit / Storage Unit / Recharge Unit
Laying and fitting of 150 mm PVC pipes of 6 metres length including
transportation of pipe to work sites
Plumber 0.50 no @ Rs.190.00/no Rs. 95.00
Helper to plumber 0.50 no @ Rs.150.00/no Rs. 75.00
Sangi mulia 02 no @ Rs.170.00/no Rs. 340.00
O.H.C. 10% Rs. 51.00
Cost & Carriage of pipes for 6 mtr. @ Rs.450.00/m Rs. 2700.00
Cost of solvent, bend, socket etc. for jointing LS Rs. 39.00
Rs.3300.00/6 m
Rs. 550.00/m
1. Earth work in hard soil or gravelly soil within 50m initial lead
and 1.5m initial lift incl. rough dressing and breaking clods to
maximum 5 -7 cm size, as directed by the engineer in charge
20.00m.x0.45m.x0.60m. = 5.40 cum. @ Rs.8746.20/ % cum. Rs. 472.29
2. Filling the F & P with sand well watered & rammed.
20.00m.x0.45m.x0.15 m. = 1.35 cum @ Rs.271.91/cum. Rs. 367.07
3. Filling the F & P with excavated materials
Qnty as per item no.1 = 5.40 cum @ Rs.5830.80/% cum. Rs. 314.86
4. Cost of 150 mm dia PVC pipe including
labour charges for laying pipeline ,carriage at site,
cost of fitting materials such as sockets, bends,
T-joints, solvent for joints etc. complete @ Rs.550.00/m for 20 m Rs. 11000.00
5. Add for unforeseen items. LS Rs. 345.78
Sub-Total (B) Rs. 12500.00
TOTAL (A+B) Rs. 18000.00

(Rupees Twelve Thousand) Only


Annexure-V

TYPICAL ESTIMATE OF A BRICK MASONRY RAINWATER FILTER UNIT


(L-100 cm X B-100 cm X D-120 cm Size)

1. Earth work in hard soil within 50m. initial lead and


1.5 m initial lift including rough dressing and braking
clods to max. 5- 7cm size as directed by the engineer in charge
1.82 m.x 1.82 m.x 0.65 m = 2.153 cum. @ Rs.8746.20/% cum Rs. 188.30
2. Filling the F & P with sand well watered and rammed
1.82 m.x 1.82 m.x 0.15 m = 0.496 cum. @ Rs.271.91/ cum Rs. 134.86

3. CC (1:4:8) with 40 mm. size hard broken granite metal


Hard granite metal
1.82 m.x 1.82 m.x 0.15 m = 0.496 cum. @ Rs.3129.53/ cum Rs. 1552.24
4. Well burnt K.B. brick (25cm x12cm x8cm) having
crushing strength not less than 75Kg/cm2 in C.M. (1:6)
including mortar joint with necessary scaffolding carrying etc.
2x 1.50 m.x 0.25 m.x 1.21 m = 0.907 cum.
2x 0.50 m.x 0.25 m.x 1.21 m. = 0.302 cum.
Total : 1.209 cum. @ Rs.3400.01/ cum Rs. 4110.61

5. C.C. (1:2:4) with 12 mm. size hard broken granite chips


Hard granite chips
Top Slab : 1x1.50 m.x 1.50 m.x 0.10 m.= 0.225 cum.
( - ) Opening = 0.785x (0.45)2 x 0.10 m. = 0.015 cum.
Net = 0.210 cum. @ Rs.4723.62/ cum Rs. 991.96

6. Rigid and smooth centering and shuttering for


RCC works including false works and dismantling
then after casing including cost of materials
1 x 1.82 m.x 1.82 m. = 3.312 sqm. @ Rs.258.43/ sqm Rs. 855.92
7. Cost of MS steel for reinforcement including
cost of bending & binding with cost of wire
etc. complete.
Quantity = 0.210 cum @ 78.50/cum = 0.16 qntl. @ Rs.6647.97/qntl Rs.1063.67

8. 12mm. thick cement plaster in CM (1:6) over brick work.


Inside : 4x1.00 m.x 1.21 m = 4.840 sqm.
Outside : 2x1.50 m.x 1.21 m. = 3.630 sqm.
Top : 2x0.25 mx (1.50+0.50)m = 1.000 sqm.
Total 9.470 sqm. @ Rs.80.69/ sqm Rs. 764.13

9. Cost of one manhole / filter materials LS Rs. 1000.00

10. Add for unforeseen items Rs. 338.31


TOTAL Rs.11,000.00

(Rupees Eleven Thousand) Only


Annexure-VI

TYPICAL ESTIMATE OF A RCC RAINWATER STORAGE UNIT


(5000 Litres Capacity)

1. Earth work in hard soil within 50m. initial lead and


1.5m initial lift including rough dressing and braking
clods to max. 5-7cm.size as directed by the engineer in charge
1.82 m.x 1.82 m.x 2.28 m = 7.552 cum @ Rs.8746.20/% cum Rs. 660.51
2. Filling the F & P with sand well watered and rammed
1.82 m.x 1.82 m.x 0.30 m = 0.993 cum. @ Rs.271.91/ cum Rs. 270.00
3. CC (1:4:8) with 40 mm. size hard broken granite metal
hard granite metal
1.82 m.x 1.82 m.x 0.15 m = 0.496 cum. @ Rs.3129.53/ cum Rs. 1552.24
4. C.C. (1:2:4) with 12 mm. size hard broken granite chips
Hard granite chips
2x1.52 m.x 1.52 m.x 0.10 m = 0.462 cum
4x1.82 m.x 1.52 m.x 0.10 m.= 1.106 cum
Total : 1.568 cum
( - )Opening=0.785x (0.45)2 x 0.10 m.= 0.015 cum
Net = 1.553 cum @ Rs.4723.62/ cum Rs. 7335.78
5. Rigid and smooth centering and shuttering for
RCC works including false works and dismantling
then after casing including cost of materials
1 x 2.13 m.x 2.13 m. = 4.536 sqm.
1 x 2.43 m. x 2.43 m. = 5.904 sqm.
Total : 10.440 sqm. @ Rs.258.43/ sqm Rs. 2698.00
6. Cost of MS steel for reinforcement including
cost of bending & binding with cost of wire
etc. complete.
Quantity = 1.553 cum @ 100 kg/cum = 1.55 qntl.@ Rs.6647.97/qntl Rs. 10304.35
7. Cost of one manhole LS Rs. 1000.00
8. Add for unforeseen items Rs. 179.12
TOTAL Rs.24000.00

(Rupees Twenty Four Thousand) Only


Annexure-VII

TYPICAL ESTIMATE OF A RCC RAINWATER STORAGE UNIT


(10000 Litres Capacity)

1. Earth work in hard soil within 50m. initial lead and


1.5m initial lift including rough dressing and braking
clods to maximum 5-7cm size as directed by the engineer in charge
3.35 m.x 1.82 m.x 2.28 m = 13.901 cum. @ Rs.8746.20/% cum Rs.1215.80

2. Filling the F & P with sand well watered and rammed


3.35 m.x 1.82 m.x 0.30 m = 1.829 cum. @ Rs.271.91/ cum Rs. 497.32

3. C.C. (1:4:8) with 40 mm. size hard broken granite metal


Hard granite metal
3.35 m.x 1.82 m.x 0.15 m = 0.914 cum. @ Rs.3129.53/ cum Rs.2860.39

4. C.C. (1:2:4) with 12 mm. size hard broken granite chips


Hard granite chips
2x3.05 m.x 1.52 m.x 0.10 m = 0.927 cum.
4x1.82 m.x 1.52 m.x 0.10 m.= 1.106 cum.
Total : 2.033 cum.
( - ) Opening = 0.785x (0.45)2 x 0.10m.= 0.015 cum.
Net = 2.018 cum. @ Rs.4723.62/ cum Rs.9532.26
5. Rigid and smooth centering and shuttering for
RCC works including false works and dismantling
then after casing including cost of materials
1 x 3.65 m.x 2.13 m. = 7.774 sqm.
1 x 2.43 m. x 2.43 m. = 5.904 sqm.
Total : 13.678 sqm @ Rs.258.43/ sqm Rs.3534.80
6. Cost of MS steel for reinforcement including
cost of bending & binding with cost of wire etc. complete.
Quantity = 2.018 cum @ 100 kg/cum = 2.01 qntl. @ Rs.6647.97/qntl Rs.13362.41

7. Cost of one manhole LS Rs. 1000.00

8. Add for unforeseen items Rs. 497.02


TOTAL Rs.32500.00

(Rupees Thirty Two Thousand Five Hundred) Only


Annexure-VIII

TYPICAL ESTIMATE OF A RECHARGE DUG WELL


[Size - 110 cm dia X 10 metres depth]

1. Earth work in hard soil within 50m Initial lead and


1.5m initial lift including rough dressing and braking of
clods to maximum 5 -7 cm size as directed by the engineer in charge
1st depth = π/4 x (2.00 m)2 x 1.50 m = 4.710 cum.
@ Rs.8746.20 /% cum Rs. 411.94
2nd depth = π/4 x (2.00 m)2 x 1.50 m = 4.710 cum
@ Rs.14161.72 /% cum Rs. 667.01
3rd depth = π/4 x (2.00 m) 2 x 1.50 m = 4.710 cum
@ Rs.19229.77 /% cum Rs. 905.72
2. Earth work excavation in stony earth and gravel mixed
with stone and boulder not exceeding on 0.014 cum in
volume within 50m initial lead and 1.5m initial lift including
rough dressing and breaking clods and maximum 5- 7 cm
and lying in layer not exceed 0.3 m in depth as per
specification approved by the department.
4th depth = π/4 x (1.50 m.)2 x 1.50 m. = 2.649 cum
@ Rs.36532.32 /% cum Rs. 967.74
5th depth = π/4 x (1.50 m.)2 x 1.50 m. = 2.649 cum
@ Rs.44047.27 /% cum Rs.1166.81
6th depth = π/4 x (1.50 m.)2 x 1.50 m. = 2.649 cum
@ Rs.51562.22 /% cum Rs.1365.88
7th depth = π/4 x (1.50 m.)2 x 1.00 m. = 1.766 cum
@ Rs.59077.17 /% cum Rs.1043.30
3. Lowering of 1.00 m. dia x 0.30m height precast
RCC Ring including cost and transportation.
Qnty =. 33 nos. for 10.00 mtr. @ Rs.600.00 /each Rs.19800.00
4. Add for other unforeseen items / well cover L.S. Rs. 171.60

TOTAL Rs. 26500.00

(Rupees Twenty Six Thousand Five Hundred) Only


Annexure-IX
LEAD STATEMENT

1. Carriage of sand(screened & washed): 10 Kms. Distance


by truck including cost & tax. .
S.R.cost Rs.42.00/cum.
1st. 5Kms. Rs.124.00
Next 5 Kms. @Rs.7.30/km. Rs.36.50
Royality Rs.19.60
_____________________
Total : Rs.222.10/cum.
2. Carriage of Cement : 5 kms.distance
by truck including cost & tax.
S.R.cost Rs.670.00/qntl
1st 5 kms. Rs.134.00
_____________________
Total :Rs.134.00/10.00 tons Or , Rs.1.34 /qntl.
Total = Rs.670.00+Rs.1.34 = Rs.671.34/qntl.
3. Carriage of K.B. bricks brick (25cm x12cm x8cm) having
crushing strength not less than 75Kg/cm2 incl.cost & tax.
20 kms. Distance by truck
SR Cost Rs.4500.00/1000 nos.
1st 5 kms. Rs. 799.00
Next 15 kms @ Rs.33.00/km Rs.495.00
____________________
Total : Rs.1294.00/2000 nos.
Or, Rs.647.00/1000 nos.
Total = Rs.4500.00+Rs.647.00 = Rs.5147.00/1000 nos.
Or. Rs.1801.45/350 nos.(1 cum.)
4. Carriage of pebbles/gravels of 4 cm size : 20 kms distance
S.R.cost Rs.1000.00/cum.
1st. 5Kms. Rs.124.00
Next 15 Kms. @Rs.7.30/km. Rs.109.50
Royality Rs.19.60/cum.
_____________________
Total : Rs.1253.10/cum.

5. Carriage of 40 mm.size H.G.C.B.chips : 20 kms.Distance


By Truck including cost & tax.
S.R.cost Rs.620.00/cum.
1st 5 kms. Rs.124.00
Next 15 kms. .@ Rs.7.30/km. Rs.109.50
Royality Rs.70.56
____________________
Total Rs.924.06/ cum.

6. Carriage of 12 mm.size H.G.C.B.chips : 20 kms.distance


by truck including cost & tax.
S.R.cost Rs.910.00/cum.
1st 5 kms. Rs.124.00
Next 15 kms. .@ Rs.7.30/km. Rs.109.50
Royality Rs.70.56
____________________
Total Rs.1214.06/ cum.
Annexure-X

ANALYSIS OF RATES

1. Earth work in hard soil within 50m. initial lead and


1.5m initial lift including rough dressing and braking
clods to max. 5cm. to 7cm.as directed by the engineer in charge
Man mulia 21.50 nos. @ Rs.150.00/each Rs.3225.00
Female mulia 21.50 nos. @ Rs.150.00/each Rs.3225.00
Overhead charges @ 10% Rs. 645.00
Sundries and T & P @ 2% Rs. 129.00
Cess @1% Rs.64.50
___________________
Total : Rs.7288.50/% cum.
Add 20 % for foundation excavation Rs.1457.70
____________________
G.Total :Rs.8746.20 /% cum.
2. Extra lift of 1.5 m or part there of over the initial lift of
1.5 mtr. in all kinds of embankment and road works
and ordinary in general
1st extra lift of 1.5 mtr.
Man mulia 4.10 nos. @ 150.00/each Rs.615.00
Overhead charges @ 10% Rs.61.50
Sundries and T & P @ 2% Rs.12.30
Cess @1% Rs.6.15
____________________
Total : Rs.694.95/% cum
3. (i) 2nd depth of 1.5 mtr. = 1.50 x8746.20 + 1.5 x 694.95
Rs.14161.72/%cum.
(ii) 3nd depth of 1.5 mtr. = 2.0 x 8746.20 + 2.5 x 694.95 Rs.19229.77/%cum.

4. Earth work excavation in stony earth and gravel mixed


with stone and boulder not exceeding on 0.014 cum in
volume within 50m initial lead and 1.5m initial lift including
rough dressing and breaking clods and max. 5 cm to 7 cm
and lying in layer not exceed 0.3 mtr in depth as per
specification approved by the department.
Man mulia 33.53 nos. @ 150.00/each Rs.5029.50
Women mulia 33.53 nos. @ 150.00/each Rs.5029.50
Overhead charges @ 10% Rs.1005.90
Sundries and T & P @ 2% Rs.201.18
Cess @1% Rs.100.59
____________________
Total : Rs.11366.67/% cum.
Add 20 % for foundation excavation Rs.2273.33
____________________
G.Total :Rs.13640.00 /% cum.

5. (i) 4th depth of 1.5 mtr. = 2.5 x 13640.00 + 3.5 x 694.95


Rs.36532.32/%cum.
(ii) 5th depth of 1.5 mtr. = 3.0 x 13640.00 + 4.5 x 694.95
Rs.44047.27/%cum.
(iii) 6th depth of 1.5 mtr. = 3.5 x 13640.00 + 5.5 x 694.95
Rs.51562.22/%cum.
(iv) 7th depth of 1.5 mtr. = 4.0 x 13640.00 + 6.5 x 694.95
Rs.59077.17/%cum.
(v) 8th depth of 1.5 mtr. = 4.5 x 13640.00 + 7.5 x 694.95
Rs.66592.12/%cum.
(vi) 9th depth of 1.5 mtr. = 5.0 x 13640.00 + 8.5 x 694.95
Rs.74107.07/%cum.
(vii) 10th depth of 1.5 mtr. = 6.0 x 13640.00 + 9.5 x 694.95
Rs.88442.02/%cum.
6. Filling the F & P with sand well watered and rammed
Sand 1.00 cum. @ Rs.222.10/cum. Rs.222.10
Man mulia 0.1236 nos. @ Rs.150.00/no. Rs.18.54
Overhead charges @ 10% Rs.24.06
Sundries and T & P @ 2% Rs. 4.81
Cess @1% Rs. 2.40
____________________
Total : Rs.271.91/ cum.

7. Well burnt K.B. brick (25cm x12cm x8cm) having


crushing strength not less than 75Kg/cm2 in C.M. (1:6)
including mortar joint with necessary scaffolding carrying etc.
Bricks 350 nos. @ Rs.1801.45/ 350 nos. Rs.1801.45
Sand 0.28cum. @ Rs.222.10/cum Rs.62.18
Cement 0.672qtl. @ Rs.671.34/cum Rs.451.14
Mason special 0.35nos. @ Rs.205.00/each Rs.71.75
Mason 2nd class 1.05nos. @ Rs.190.00/each Rs.199.50
Man mulia 1.41nos. @ Rs.150.00/each Rs.211.50
Woman mulia 1.41nos. @ Rs.150.00/each Rs.211.50
Overhead charges @ 10% Rs.300.90
Sundries and T & P @ 2% Rs.60.18
Cess @1% Rs.30.09
_____________________
Total : Rs.3400.01/cum
8. C.C. (1:4:8) with 40 mm. size hard broken granite metal
Hard granite metal 0.96cum @ Rs.924.06 /cum. Rs.887.09
Sand 0.48cum @ Rs.222.10/cum Rs.106.60
Cement 1.72 qtl @ Rs.671.34/qntl.
Rs.1154.70
Mason 0.18 nos. @ Rs.190.00/each Rs.34.20
Man mulia 2.50 nos. @ Rs.150.00/each Rs.375.00
Woman mulia 1.40 nos. @ Rs.150.00/each Rs.210.00
Overhead charges @ 10% Rs.276.95
Sundries and T & P @ 2% Rs.55.35
Cess @1% Rs.29.64
___________________
Total : Rs.3129.53/cum.
9. C.C. (1:2:4) with 12 mm. size hard broken granite chips
Hard granite chips 0.90cum @ Rs.1214.06 / cum. Rs.1092.65
Sand 0.45cum @ Rs.222.10/cum Rs.99.94
Cement 3.23qtl @ Rs.671.34/qntl. Rs.2168.42
Mason 0.68nos. @ Rs.190.00/each Rs.129.20
Man mulia 3.20nos. @ Rs.150.00/each Rs.480.00
Woman mulia 1.40nos. @ Rs.150.00/each Rs.210.00
Overhead charges @ 10% Rs.418.02
Sundries and T & P @ 2% Rs.83.60
Cess @1% Rs.41.80
___________________
Total : Rs.4723.62/cum.
10. Rigid and smooth centering and shuttering for
RCC works including false works and dismantling
then after casing including cost of materials
complete in ground floor.
RCC floor and roof slabs, landings, balconies
projecting sub shades and chajjas up to 4.3 m height
Details for 10 sqm
Non sal wood scantling 0.112 cum @Rs.7280.00/cum. Rs.815.36
Planks 38mm 0.34 cum@Rs 16800.00/cum. Rs.5712.00
120 mm dia bullah 56 meter @Rs.84.00/mtr. Rs.4704.00
Carriage of wood 1.142 cum @Rs.328.00/ cum Rs.374.57
__________________
Total : Rs.11605.93/10
Or Say, Rs.1160.59
Considering 10 times use of the materials for use once
Carpenter (2nd class) 2.75 nos.@Rs.205.00/each Rs.563.75
Semi-skilled mulia 2.75 nos.@Rs.170.00/each Rs.467.50
Overhead charges @ 10% Rs.103.12
Sundries and T & P @ 2% Rs.20.62
Cess @1% Rs.10.31
_____________________
Total : Rs.2325.89/9 sqm.
Or Say; Rs.258.43 /sqm.

11. Cost of MS steel for reinforcement including


cost of bending & binding with cost of wire
etc. complete.
Bars including 5%
Overlaps and wastage 1.05 MT. @ Rs.55000.00/ton. Rs.57750.00
Blinding Wire 8.0 kg. @ Rs.60.00/Kg. Rs.480.00
Blacksmith 1st Class 3.00 nos. @129.00/day Rs.387.00
Mate 0.44 nos. @Rs170.00/day Rs.74.80
Man Mulia 8 nos.@Rs150.00/day Rs.1200.00
Overhead charges @ 10% Rs.5989.08
Cess @1% Rs 598.91
___________________
Total : Rs.66479.79/10qtl
Or Rs.6647.97/qntl.
12. 12mm. thick cement plaster in CM (1:6) over brick work.
Sand 0.015cum @ Rs.222.10/cum Rs.3.33
Cement 0.035qtl @ Rs.671.34/cum Rs.23.49
Mason 0.14nos. @ Rs.190.00/each Rs.26.60
Man mulia 0.07nos. @ Rs.150.00/each Rs.10.50
Woman mulia 0.05nos. @ Rs.150.00/each Rs.7.50
Overhead charges @ 10% Rs.7.14
Sundries and T & P @ 2% Rs.1.42
Cess @1% Rs.0.71
____________________
Total : Rs.80.69/ sqm.
13. Filling of pebbles/gravels
Cost and transportation of pebbles. 1cum Rs.1253.10
Mason 0.17 nos. @ Rs.190.00/each. Rs.32.30
Stone packer 0.35 nos. @ Rs.190.00/each. Rs.66.50
Women mulia 0.52 nos. @ Rs.150.00/each. Rs.78.00
Man mulia 0.52 nos. @ Rs.150.00/each Rs.78.00
Extra mulia 0.35 nos. @ Rs.150.00/each. Rs.52.50
Overhead charges @ 10% Rs.156.04
Sundries and T & P @ 2% Rs.31.20
Cess @1% Rs.15.60
____________________
Total : Rs.1763.24/ cum
14. Cost of RCC ring 1.00 m. dia x 0.30 m. height including transportation and
laying in the well etc. complete as per local market rate. Rs.500.00/each
Annexure-XI

TYPICAL ESTIMATE OF RECHARGE BORE WELL IN HARD ROCK FORMATION


[Size – 125 X 100 mm dia X 50 metres depth]

Sl. Item of Work Unit Unit Rate Quantity Total Cost


No. in Rupees in Rupees
1 2 3 4 5 6
A Labour Cost

Drilling a perfectly vertical


1 Metre 600/- 20 12000/-
150 mm dia bore hole in
hard rock formation from
ground level to 20 metres
depth

Drilling of 100 mm dia bore


2 Metre 500/- 30 15000/-
hole from 20 metres depth
to 50 metres depth

Lowering of 125 mm dia PVC


3
casing pipe of with or
without slots from ground
Metre 100/- 20 2000/-
level to 20 meters depth in
perfectly vertical position

Operation of air-compressor
4 for development of bore well LS - - 2000/-

B Material Cost

1 PVC pipe (125 mm dia) for


20 meter Metre 550/- 20 11000/-

2 PVC well cap No. 500/- 01 500/-

3 Unforeseen items LS - - 500/-

Total Cost (in Rupees) 43000/-

(Rupees Forty Three Thousand Only)


Annexure-XII

TYPICAL ESTIMATE OF A RECHARGE TUBE WELL IN ALLUVIAL FORMATION


[Size – 125 mm dia X 30 metres depth]

Sl. Item of Work Unit Unit Rate Quantity Total Cost


No. in Rupees in Rupees
1 2 3 4 5 6
A Labour Cost

Sinking a perfectly vertical


1 Metre 1700/- 30 51000/-
tube well of 125 mm dia X
30 metres depth below
ground level in alluvial
formation including gravel
packing and assembly
lowering

Operation of air-compressor
2 LS - - 3400/-
for development of tube well

Slotting cost of PVC pipe


3 (125 mm dia) for 10 metres Metre 300/- 10 3000/-

B Material Cost

1 PVC pipe (125 mm dia) for


30 meters Metre 550/- 30 16500/-

2 PVC well cap No. 500/- 01 500/-

3 Unforeseen items LS - - 600/-

Total Cost (in Rupees) 75000/-

(Rupees Seventy Five Thousand Only)