Professional Documents
Culture Documents
Credit hour 3
Duration 14 weeks Lecture + Lab/Tutorial
Instructor
Dr. Mohammed Mahbubur Rahman
1
1
2/17/2018
Water and/or
hydrocarbons Hydraulic valve
recovered in closed
drill pipe during
this flow period
Bypass ports open
1
4
FFP
1 2 3 4 5 6 7 8 9 10 11 12
2
2/17/2018
Sample Report
6
Hydrostatic pressure
Tool open
Initial flowing pressure
Final flowing pressure
Tool closed
Shut-in pressure
Pipe recovery
3
2/17/2018
Types of DST
Open hole (more frequent)
Cased hole
Conventional Bottom hole test
Conventional Straddle test
4
2/17/2018
Figure 1
5
2/17/2018
Wellbore damage
Wellbore damage exhibits (Figure 2) a
weak blow at the surface, very little
recovery, low flowing pressures
a sharp pressure rise after the tool is shut in
a short radius pressure transition during
buildup followed by a flat pressure
increase
Fluid depletion during the test is minimal. If
the wellbore cleans up during the test,
then there will be a change in the
character of the curves from that shown in
Figure 2 to one of those shown in Figure 1 .
Figure 2
Depletion
In a normal DST, a drop in pressure between
the initial and final stabilized shut-in values
indicates a limited or finite reservoir
provided the initial value has not been
affected by supercharging
The produced fluids have caused a
measurable depletion ("drawdown") of the
reservoir. A pressure change of 1.5% or
greater is considered serious and more
careful evaluation or retesting is warranted.
A barrier effect or nearby production may
also cause the same effect to be recorded.
Figure 3
6
2/17/2018
Reservoir barrier
Figure 4 shows example of a decrease in
pressure buildup levels between the initial
and final flow periods.
These are caused by a reservoir barrier or a
permeability problem as opposed to
depletion. The change in the slope of the
buildup curve indicates a reduction in
transmissibility some distance from the
wellbore
Figure 4
Other information that may be obtained are (not discussed in detailed here)
Fluid Recovery
Liquid, Gas, Multi-phase
Anchor plugging
Tool plugging
7
2/17/2018
8
2/17/2018
9
2/17/2018
2. For wells that do flow to surface, we may estimate the average flow rate by metering the
volume produced after it passes through the separator or, alternately, retaining and
measuring the produced fluids in a tank. The average flow rate, in stock tank barrels, is the
volume produced, divided by the time during which production at the surface took place. In
both cases, the measured volumes must be corrected for BSW (basic sediment and water)
content, temperatures different than 60°F meter correction factor, and any shrinkage that
occurred after metering.
The above discussion applies only when the actual variation in flow rate is not substantial.
Strictly speaking, the methods of analysis we have discussed apply only for a constant
production rate preceding the buildup test. If production rate variation is significant, one of
several variable rate analyses should be utilized.
10
2/17/2018
2,200
DST Interpretation: Semi-log Analysis p* = pi
DT (hr) Dt+tp/Dt Pws DT (hr) Dt+tp/Dt Pws
0.017 6.70 406.62 0.100 41.0 1,618.78 2,000
0.033 3.85 597.08 0.117 35.3 1,644.08
0.050 2.90 808.59 0.133 31.0 1,667.36
0.067 2.42 1,005.90 0.150 27.7 1,686.60
0.083 2.14 1,175.90 0.167 25.0 1,704.80 1,800
0.100 1.95 1,327.70 0.200 21.0 1,734.15
0.117 1.81 1,452.20 0.233 18.1 1,758.44
0.133 1.71 1,548.40 0.267 16.0 1,778.67
pws
1,600
0.167 1.57 1,695.10 0.300 14.3 1,796.90
0.200 1.48 1,792.30 0.333 13.0 1,813.09
0.233 1.41 1,854.00 0.367 11.9 1,826.24
0.267 1.36 1,896.50 0.400 11.0 1,838.39 1,400
0.300 1.32 1,927.90 0.433 10.2 1,848.51
0.333 1.29 1,951.10 0.467 9.6 1,857.62
0.367 1.26 1,968.30 0.500 9.0 1,865.71
0.400 1.24 1,982.50 1.000 5.0 1,940.60 1,200
0.433 1.22 1,993.60 1.500 3.7 1,975.01
0.467 1.20 2,003.80 2.000 3.0 1,997.27
0.500 1.19 2,010.80 2.500 2.6 2,011.44
0.583 1.16 2,025.00 3.000 2.3 2,022.57 1,000
0.667 1.14 2,036.10 3.500 2.1 2,030.67 1 10 100
0.750 1.13 2,044.20 4.000 2.0 2,036.74 (DT+tp)/Dt
0.833 1.11 2,050.30 4.500 1.9 2,041.80
0.917 1.10 2,054.40 5.000 1.8 2,045.85 tp 1, hr 0.095 m2 = 220 k= 3 mD
1.000 1.10 2,058.40 5.500 1.7 2,047.87 tp 2, hr 4 p 1hr = 1950 s= -1.44
1.083 1.09 2,061.40 6.000 1.7 2,049.90 q tot, STB 23.14 pi = 2100
1.167 1.08 2,064.50 6.500 1.6 2,051.92 Q1, STB/D 355
1.250 1.08 2,065.50 7.000 1.6 2,055.97
1.333 1.07 2,067.50 7.500 1.5 2,057.99
Bo 1 initial reservoir pressure = pi = p* = 2100 psia
ϕ 0.08
1.417 1.07 2,069.50 8.000 1.5 2,061.03
µ 0.9
1.500 1.06 2,070.60 8.500 1.5 2,062.04
ct 5.00E-06
1.533 1.06 2,071.60 9.000 1.4 2,063.05
h 30
9.500 1.4 2,065.08
rw 0.26
10.000 1.4 2,065.08
pwf = 1176
10.500 1.4 2,066.09 Source: Chapter 9, Well Test Analysis by M A Sabet, Gulf Publishing Co., 1991
DR = 1/1.29 = 0.77
Hydrostatic pr = 0.052 X ρ X d
11