You are on page 1of 47

There are no fixed procedures according to which setting out has to be

done since each case can be different.


However, to be able to form an idea of the different measurement activities
and the methods and instruments which can be chosen in each case, the
main parts of a setting out procedure can be described as follows:
1. Planning for setting out
2. Initial setting out
3. Setting out first stage
4. Setting out second stage
5. Setting out levels
6. Transfer of points and lines
7. Measuring with a tape
8. The measuring of distances with EDM instruments
9. Application of International Standard for setting out
• Setting out is the process of
extracting information from the
construction drawings, and
pegs, profiles or other marks
are then set to control the
This can be in the form of
construction works and to
building corners, sewers,
ensure that each features in
the drawings are constructed in earthworks, road works, steel
the right position and to the structures or line works
correct level.
• Setting out is the process of Setting out is defined as the
extracting information from the establishment of marks & lines
construction drawings, and to define the position & level of
pegs, profiles or other marks elements of the construction
are then set to control the work so that works may
construction works and to proceed with reference to
ensure that each features in them.
the drawings are constructed in • This process is contrasted with
the right position and to the the purpose of “surveying”
correct level. which is to determine the
• According to ISO_7078: 1985 positions of existing features on
Building Construction – site by measurement.
Procedures for Setting out,
Measurement & Surveying –
Vocabulary & Guidance Notes:
• Often used definition: setting • Good knowledge is vital, as the
out is the reverse of setting out phase is one of the
“surveying”, i.e. surveying is a most important stages in any
process of producing a plan or civil engineering construction
a map of a particular area, project.
while, setting out begins with • Mistakes in setting out can be
the plan and ends with the costly and should be borne by
various elements of an the contractor.
engineering project correctly
positioned in the area. (Uren, J.
et al., 2006)
• Good work practices &
techniques in setting out is
essential to minimize errors &
to ensure the construction
process proceeds smoothly.
• Even though the “surveying” • Two main aims when
and “setting out” are opposite undertaking setting out
processes to each other, but operation:
the techniques and instruments 1. Various elements of the
used for both processes are scheme in the construction
identical. drawings must be correct
• Among all parties who are in all three dimensions,
involved in construction works, both relatively and
the “setting out” is the absolutely, that is each
responsibility of the contractor. must be in its correct size,
• Three main principles of setting plan position and correct
out operations: reduced level.
1. Horizontal control 2. Once setting out begins, it
technique must proceed quickly with
2. Vertical control technique little or no delay in order
that the works can proceed
3. Positioning technique
smoothly & the cost can be
minimized.
• Overall, there are three stages
of setting out need to be
carried out in construction
works:
1. Initial setting out – limits of
work and site
2. Stage 1: Setting out of
foundation and sewer
pipeline;
3. Stage 2: Setting out the
design points.
• Example of specification with
regards to “setting out” in
Construction Drawing
• Overall, there are three stages
of setting out need to be
carried out in construction
works:
1. Initial setting out – limits of
work and site
2. Stage 1: Setting out of
foundation and sewer
pipeline;
3. Stage 2: Setting out the
design points.
• Example of specification with
regards to “setting out” in
Construction Drawing
• Example of Setting Out
Drawing in Construction
Drawing
• Overall, there are three stages • To set out the limits of works
of setting out need to be and site, at least two
carried out in construction coordinate points are needed –
works: i.e. setting out coordinate
1. Initial setting out – limits of points.
work and site
2. Stage 1: Setting out of
foundation and sewer
pipeline;
3. Stage 2: Setting out the
design points.
• Example of specification with
regards to “setting out” in
Construction Drawing
• Example of Setting Out
Drawing in Construction
Drawing
• Overall, there are two stages of
setting out need to be carried
out in construction works:
1. Stage 1: Setting out limits
of work and site;
2. Stage 2: Setting out the
design points.
• Example of General Notes with
regards to “Setting Out” in
Construction Drawing
• Example of Setting Out
Drawing in Construction
Drawing
• To set out the limits of works
and site, at least to coordinate
points are needed – i.e. setting
out coordinate points.
• Overall, there are three stages • To set out the limits of works
of setting out need to be and site, at least to coordinate
carried out in construction points are needed – i.e. setting
works: out coordinate points.
1. Initial setting out – limits of • BS 5964-1:1990 is concerned
work and site with the complete range of
2. Stage 1: Setting out of setting-out on building sites.
foundation and sewer • In summary, BS has
pipeline; highlighted three-stage order of
3. Stage 2: Setting out the reference systems commonly
design points. adopted for large and complex
• Example of specification with building projects.
regards to “setting out” in 1. Primary system
Construction Drawing 2. Secondary system
• Example of Setting Out 3. Position points
Drawing in Construction • Position points give the
Drawing location of the details of the
building.
• 3 main principles of setting out • 3-stage order of reference
operations: systems commonly adopted
1. Horizontal control for large and complex building
technique projects.
2. Vertical control technique 1. Primary system
3. Positioning technique 2. Secondary system
• 3 stages of setting out need to 3. Position points
be carried out in construction • Position points give the
works: location of the details of the
1. Initial setting out – limits of building.
work and site
2. Stage 1: Setting out of
foundation and sewer
pipeline;
3. Stage 2: Setting out the
design points.
• A reconnaissance of the site 3. The positions of the
and planning of the setting out proposed building and
are essential. ancillary works ;
• Based on the construction 4. The sequence of
drawing, a suitable reference excavation and
system should be selected and construction woks.
established.
• A suitable reference system
selected will depend on:
1. The shape and size of the
site;
2. The positions of any
existing buildings or
obstructions.
• The chosen reference system should be such that redundant
observations are possible and that the measuring points can be
referred to during construction.
• The position of the main ground station should be chosen and
protected such that they are at a min. risk to damage or movement
and unobstructed lines of sight can be maintained.
• Location grids are used to • Site grids can be considered
assist the planning authorities as the transfer of the location
and designers in plotting the grid from the plan or drawing to
location of boundaries, the site by setting out.
buildings, roads, underground • Structural grid are used by
utilities or other features. designers to define the position
• If the building to be set out, it is of structural elements, usually
important to mark on the plan their center-line.
of the building site the
approximate position of the
structural grid or site grid.
• The marking of site clearance
3. Offset method
and excavation areas.
4. Method of free station
• Methods of setting out:
points
1. Polar setting out method
• Establish permanent point
2. Intersection method
• Position of permanent point
• Establish benchmark
• In practice, 1st stage setting out • 2nd stage setting out continues
involves the use of many from the 1st stage setting out.
horizontal and vertical control • E.g.: Beginning at the ground
techniques. floor slab, or road sub-base
• The purpose of this stage is to level, etc.
locate the boundaries of the • Up to this point, all the control
works in their correct position points will be outside the main
on the ground surface and to construction.
define major elements. • E.g.: The pegs defining building
• In order to do this, horizontal corners, center lines and so on
and vertical control points must will be knocked out during
be established on or near the excavation works and only the
site. original control points will be
undisturbed.
• Establish horizontal control 1. The control points should
points in the E and N be located through out the
coordinates points on the site site in order all the design
so that the design points for points can be fixed from at
each of the elements of the least two of them so that
scheme in the construction the work can be
drawings can be correctly fixed independently checked;
in position; 2. The design points must be
• Two factors to consider in set out to the accuracy
establishing horizontal control stated in the specifications.
points:
• The construction and protection
of control points is very
important.
• Wooden pegs are usually used
for non-permanent marking
(control points).
• Concrete mark is used for
permanent marking (control
point).
• Horizontal control points can
be:
1. Baselines
2. Reference grid
3. Offset pegs
1. Two specified points
joined;
• A baseline is a line running 2. Run between two
between two points of a known buildings;
position. 3. Mark the boundary with an
• Any baseline required to set existing building/
out a project should be development;
specified on the setting out 4. Mark the center line for a
plan/drawing by the designer new road;
and included in the contract.
• Baseline can take many forms:
• A control grid enables points
to be set over a large area.
• Several different grids can
be used in setting out:
is drawn on the survey plan from the
– (1) grid survey; original traverse or network. The grid
– (2) grid site; points have known “eastings” and
“northings” related either to some arbitrary
– (3) structural grid; origin or to the national grid.
– (4) grid secondary.
• A control grid enables points
to be set over a large area.
• Several different grids can
be used in setting out:

– (1) grid survey;


– (2) grid site;
– (3) structural grid;
– (4) grid secondary.
• A control grid enables points
to be set over a large area.
• Several different grids can is used by the designer. It is usually related
be used in setting out: in some way to the survey grid and should,
– (1) grid survey; if possible, actually be the survey grid, the
advantage of this being that if the original
– (2) grid site; control stations have been permanently
marked then the design points will be on
– (3) structural grid; the same coordinate system and setting
– (4) grid secondary. out is greatly simplified.
• A control grid enables points
to be set over a large area.
• Several different grids can
be used in setting out:
– (1) grid survey;

– (2) grid site;


– (3) structural grid;
– (4) grid secondary.
• A control grid enables points
to be set over a large area.
• Several different grids can be
used in setting out:
– (1) grid survey;
– (2) grid site; The structural grid is established around a
particular building or structure which
– (3) structural contains much detail such as columns,
which cannot be set out with sufficient
grid; accuracy from the grid site.
– (4) grid secondary.
• A control grid enables points
to be set over a large area.
• Several different grids can be
used in setting out:
– (1) grid survey;
– (2) grid site;

– (3) structural
grid;
– (4) grid secondary.
• A control grid enables points
to be set over a large area.
• Several different grids can be
used in setting out:
– (1) grid survey; The secondary grid is established inside
the structure from the structural grid when
– (2) grid site;
it is no longer possible to use the structural
– (3) structural grid; grid to establish internal features of the
building – as the vision becomes obscured.
– (4)grid
secondary.
• Whether used in the form of a
baseline or a grid, the
horizontal control points are
used to establish design points
on the proposed structure.
• Once excavations for the
foundations begin, the corner
pegs will be lost. To avoid this
extra pegs, offset pegs are
used.
• In order the design points can be positioned at their correct levels,
vertical control points of known elevation relative to some specified
vertical datum are established.
• Some vertical control techniques:
1. TBM
2. Sight rails
3. Travellers and boning rods
4. Slope rails or batter boards
• TBM:
The positions of TBMs should be
fixed during the initial
reconnaissance so that their
construction can be completed in
good time and they can be
allowed to settle before levelling
them in. In practice, 20mm
diameter steel bolts and 100mm
long, driven into existing steps,
ledges, footpaths etc. are ideal.
• Sight rail:
These consist of a horizontal
timber cross piece nailed to a
single upright or a pair of uprights
driven into the ground. The upper
edge of the cross piece is set to a
convenient height above the
required plane of the structure,
usually to the nearest 100mm, and
should be a height above ground to
ensure convenient alignment by
eye with the upper edge.
• Sight rail:
Sight rails are usually offset 2 or 3 m
at right angles to construction lines to
avoid them being damaged as
excavations proceed.
• Travellers and boning rods:
– A traveller is similar in appearance to a sight rail on a single
support and is portable. The length of the upper edge to its
base should be a convenient dimension to the nearest half
meter.
– Travellers are used in conjunction with sight rails. The sight
rails are set some convenient value above the required
plane and the travellers are constructed so that their length
is equal to this value.
– As excavation works proceeds, the traveller is sighted in
between the sight rails and used to monitor the cutting and
filling.
• Slope rails or batter boards:
– For controlling side slopes on embankments and cuttings
slope rails are used.
– For an embankment the slope rails usually define a plane
parallel to the slope of the embankment offset by a
convenient distance:
• Before the excavation for the proposed foundation is commenced, the site
shall be cleared of vegetation, brushwood, stumps of trees, debris, etc.
• Next is to set out a baseline for the work.
• For setting out the foundations of small buildings, the centre line of the
longest outer wall of the building is first marked on the ground by
stretching a string between wooden or mild steel pegs driven at the ends.
• For accurate work, nails can be fixed at the centre of the pegs.
• Two pegs, one on either side of the central peg, are driven at each end of
the line. Each peg is equidistant from the central peg, and the distance
between the outer pegs corresponds to the width of foundation trench to
be excavated.
• Each peg may project about 25 to 50 mm above ground level and may be
driven at a distance of about 2 m from the edge of excavation so that they
are not disturbed.
• When string is stretched joining the corresponding pegs (say 2-2) at the
two extremities of the line, the boundary of the trench to be excavated can
be marked on the ground with dry lime powder.
• The centre lines of other walls, which are perpendicular to the long wall,
are then marked by setting out right angles.
• A right angle can be set out by forming a triangle with 3, 4 and 5 units
long.
• These dimensions should be measured with the help of a steel tape.
Alternatively, a theodolite or prismatic compass may be used for setting
out right angles.
• Similarly, outer lines of the foundation trench of each cross-wall can be set
out, as shown in the following figure.
The six corners of a proposed L shaped excavation shown in Figure 1 (a)
below have been set out on site.

Figure 1 (a)

Offset pegs have been established to help define the sides of the excavation.
The proposed formation level of the surface of the excavation at point R is
95.72 m. The surface is to fall at 1 in 150 from R to W and is to rise at a slope
of 1 in 100 at right angle to the line RW.

Figure 1 (b)

The cross-sections for lines P1RWP2 and P4UTP3 are as depicted in Figure 1
(b) and (c), respectively.
To help with excavation site, sight rails are to be erected above the offset
pegs for use with a 2 m traveler. Given the reduced levels of the offset pegs,
calculate the heights of the sight rails to be used at P1, P2, P3 and P4.

Figure 1 (c)
Solution for line P1RWP2
Formation level at P1 = 95.72 + (3/150) = 95.74m
Formation level at P2 = 95.72 – (48/150) = 95.40m

For offset peg P1


Required top of sight rail level = 95.74 + 2.00 = 97.74 m
Actual of peg level = 96.95 m
Therefore, distance above P1 = 0.79 m

For offset peg P2


Required top of sight rail level = 95.40 + 2.00 = 97.40 m
Actual of peg level = 96.45 m
Therefore, distance above P2 = 0.95 m
Solution for line P4UTP3
Formation level at Z = 95.72 - (15/150) = 95.62m
Formation level at P3 = 95.62 – (28/100) = 95.90m
Formation level at P4 = 95.62 - (3/100) = 95.59m

For offset peg P3


Required top of sight rail level = 95.90 + 2.00 = 97.90m
Actual of peg level = 97.12m
Therefore, distance above P3 = 0.78m

For offset peg P4


Required top of sight rail level = 95.59 + 2.00 = 97.59m
Actual of peg level = 96.75m
Therefore, distance above P4 = 0.84m

You might also like