Professional Documents
Culture Documents
Detailed project management report on construction of a new hostel block with an indoor sport
complex within the existing IIM Shillong Campus in 18 months to accommodate 84 students within a
budget of 2.5 Crores.
Contents
1. Executive Summary ............................................................................................................................... 2
2. Introduction .......................................................................................................................................... 2
3. Project Scope and Basic Assumption .................................................................................................... 3
4. Technical Know-How Requirements ..................................................................................................... 4
5. Foreseeable Difficulties and Constraints .............................................................................................. 5
5.1. Financial Difficulties .......................................................................................................................... 5
5.2. Political difficulties ............................................................................................................................ 5
5.3. Construction difficulties .................................................................................................................... 5
5.4. Other difficulties ............................................................................................................................... 5
6. Risk Register .......................................................................................................................................... 6
7. Work Breakdown Structure .................................................................................................................. 7
8. Milestone PERT Chart of the Proposed Project .................................................................................... 7
9. Project Duration and Project Budget .................................................................................................... 8
9.1. Project Milestones ............................................................................................................................ 8
9.2. Resource Requirements .................................................................................................................... 8
9.3. Construction phase – external and internal ..................................................................................... 9
9.4. Resource cost planning ................................................................................................................... 10
9.5. Assumptions .................................................................................................................................... 11
9.6. Total cost of project ........................................................................................................................ 11
10. Social costs, Risks and Expected Benefits of the Proposed Project ................................................ 11
10.1. Social cost-benefit analysis ......................................................................................................... 11
10.2. Risk & mitigations strategies of our project ............................................................................... 12
11. Critical Success Factors for our project: .......................................................................................... 13
12. Limitations and future scope of research ....................................................................................... 13
13. Lessons Learnt and key difficulties faced while preparing the project plan ................................... 14
13.1. Lessons Learned .......................................................................................................................... 14
13.2. Difficulties Faced ......................................................................................................................... 15
14. Annexures ....................................................................................................................................... 16
Page | 1
1. Executive Summary
This project report summarizes in detail the planning behind the construction of a new hostel block with
an indoor sport complex within the existing IIM Shillong Campus in 18 months to accommodate 84
students within a budget of 2.5 crores.
The project is proposed to be completed in three phases namely, planning, site development and
construction. In the planning phase the major deliverables will be the construction blueprint and
completion of legal formalities which would include permission for erecting a new building within the
campus. In the site development stage, we need to lay a foundation for the building at the proposed
site. The major and final phase of construction will have deliverables such as the completed hostel and
the indoor sports complex on the ground floor.
Once the blueprint was prepared and approved through consultation with the client, the cost estimate
was prepared and scheduling was done consequently. The social costs and risks involved in the project
were accounted for. The benefits of undertaking the construction were outlined with special focus on
the critical success factors. Finally at the end of the report, the limitations are enlisted and learnings
derived from this project are outlined.
The current hostel facility in the institute is operating under overcapacity and the number of
students being inducted every year is on the rise
The sports facility present also needs to be improved to provide the right infrastructure for
students in a premium management institute
The project deals with identification and scheduling of resources to complete the task in a given
time and resource frame
To determine the various types of risks, costs and constraints that could be associated with
managing a project as well as how to mitigate and manage the same
Page | 2
It is an opportunity to apply the principles of project management learnt in class as well as the
tools for the same
3.1. Scope
Providing basic amenities like provision for lights/ fans/ heaters, fully-equipped bathrooms,
drinking water facility, common room with LCD television, gym, squash facility, indoor
badminton court, table tennis etc. to the students of IIM Shillong
After the construction of the facilities it is important to regularly perform maintenance
activities on all the facilities. Understanding the maintenance requirements from the builder
and accordingly allocate resources for maintenance activities
Providing good quality fresh basic eatables and energy drinks through an automatic vending
machine that requires only limited space for installation
Keeping the sports facility open 24 hours at the hostel on all the days, as required by the
Institute
Plumbing and electrical work for the building will be taken care by the contractor
Our job is only the felicitation of the hostel block, day to day job will be carried out by
the contractor
The overseeing of the day to day operations and quality assurance will be done by
Hostel Committee along with a team of experts
3.3. Basic Assumption:
Page | 3
The legal and other approvals for hostel block will be taken by the college
administration and not by us
The location of the hostel block will be in the space where TV room, gym, badminton
court are currently located. The space adjacent to the guest house can also be used
We will construct the hostel block and hand it over to the college administration. Day to
day operations post completion will not be our responsibility
Page | 4
Size (of the building) Ground Floor + 4 floors + one-mess on each floor for cooking and dining
Construction Material Standard building format (Brick & Mortar)
Recreational Facilities Ground floor consists of Table Tennis, Indoor Badminton Court, Gymnasium
and Squash Room
Hostel Capacity 84 rooms
Room specifications Cement Flooring + Provision for 2 tube-lights + 1 fan. The room size and
design will be same as the existing new boy’s hostel rooms.
Floor Specifications Tiled-flooring in the corridors
Bathrooms One bathroom for every 2 rooms
Utilities Connecting the entire building to the main power grid of the campus +
Earthing + Drainage Facility + Automatic vending machine in sports complex
Building construction CDEF concept
The whole of Meghalaya is suffering from strikes and bandhs because of the current political
scenario and the demand for ILP. This may lead to laborers not reporting on time or unable to
work freely.
The schedule might get hampered and it might take more number of days to finish the project.
Also if ILP issue comes into effect, getting manpower from outside might be a problem
5.3. Construction difficulties
Page | 5
Implementation of various project management tool could be of problem as the labor
contractor and other involved parties can be categorized as level 1 organization where these
people might not be well versed with project management control frameworks
Excessive approval procedures in administrative government departments
Low management competency of subcontractors
Unsuitable construction program planning
General safety accident occurrence
Unavailability of sufficient professionals and managers
Various difficulties and constrains mentioned above may pose following problems in the proposed
project:
6. Risk Register
It acts as a central repository for all risks identified by the project or organization and, for each risk,
includes information such as risk probability, impact, counter-measures, and risk owner and so on.
Post identification of the risk, risk register has been created to know the exact probability and their
impact on the project
Page | 6
7. Work Breakdown Structure
1. Getting legal approval: This milestone indicates the readiness of the team for going for the next
phase of the project which is to begin the preparation of site and the construction phase. This task is
a milestone since it signifies the end of the preparation phase for the project and starts with the
implementation of the same.
2. Site development: This is a milestone since it signifies the readiness of site so that the construction
work can start on it properly.
3. Completion of external construction: It involves the finishing of construction of all the 4 floors and
signifies the readiness of the building to start with internal furnishing and layout of the sports
utilities in the same.
4. Completion of sports utilities and ready for handover: This milestone signifies the completion of the
project and is ready to be open for the students.
All the 4 of the milestones along with the expected timeline is shown in the images below:
Page | 7
9. Project Duration and Project Budget
Page | 8
Human For clerical jobs like External resources Average salary would 40000
Resource applying for permits be Rs. 10000 pm ( for 2
and receiving them months only )
Miscellaneous Stationary Cost along To be obtained 200000
Cost with other amenities from suppliers
and utilities --
This phase consists of calculating the cost required for acquiring material (raw material and finished
goods).
Page | 9
Generators Back Up Power From supplier- $95000 per 2470000
(Diesel Operated) system 1000kVA x 4 generator
Manpower Labor work, Daily workforce for Masonry @ Rs.300 220300
Requirement plumbing, masonry : 25 per person per day
electrical fixing Workforce for Plumbing @ Rs.450
and carpentry plumbing : 15 per person per day
Workforce for Electrical @ Rs.450
electrical System: 7 per person per day
Workforce for Painting @ Rs.250
painting : 12 per person per day
Flooring and other
internal civil works
@ Rs.350 per
person per day
Tiles and mosaic Interior to the From supplier Kajaria tiles @ 225000
flooring building Rs.95 for 1x1sq.ft
tiles
Taking into consideration 10% contingency, the total budget becomes = Rs. 13176000
The completion phase includes the final touches required for the completion of the building including,
internal decorations like standardized lighting and fixtures and glass fixtures.
Page | 10
9.5. Assumptions
The salary of permanently hired employees has not been considered in the budget calculation as the
organization has separate salary account to handle the same and this cost is taken care of in the overall
company expenses and is not specific to the project alone.
The total project cost comes out to be approximately Rs. 2.25 crores
Considering contingency cost of 10%, and rounding off the value obtained, the cost of the project stands
to be Rs. 25000000. (Rs. 2.5 Crores)
10. Social costs, Risks and Expected Benefits of the Proposed Project
A social cost-benefit analysis aims to chart all of the effects that would influence the welfare of society
on account of constructing the stadium. It is a systematic and cohesive method to survey all the impacts
caused by the urban development project. It comprises not just the financial effects (investment costs,
direct benefits like tax and fees etc.), but all the social effects, like: pollution, safety, indirect (labor)
market, legal aspects etc.
The social cost-benefit analysis calculates the direct (primary), indirect (secondary) and external effects:
Direct effects are the costs and benefits that can be directly linked to the owners/users of the
project properties (e.g., the users and the owner of stadium).
Indirect effects are the costs and benefits that are passed on to the producers and consumers
outside the market with which the project is involved (e.g., the owner of shops outside the campus )
External effects are the costs and benefits that cannot be passed on to any existing markets because
they relate to issues like the environment (noise, emission of CO2, etc.), safety (traffic, external
security) and nature (biodiversity, dehydration, etc.).
Page | 11
The noise level would increase during construction phase and might disturb the nearby residents.
Risks associated The two major risks identified under this Enter into strictly defined contracts with
with supply head are: Non-availability of resources and the suppliers
chain risk of non-compliance from supplier’s end
Page | 12
Safety related Low management competency of Subcontractors are not in our direct
risks subcontractors control but while contractors previous
Unsuitable construction program work can be checked to understand the
planning kind of subcontractor they use.
General safety accident occurrence
Lack of coordination between Skilled labor scouting should be done well
project participants in advance to avoid such problems.
Unavailability of sufficient amount Usually there are intermediary players
of skilled labor who help in getting the skilled labor. Such
Unavailability of sufficient people should be approached if such an
professionals and managers issue arises
Schedule: It is important for the project to meet the schedule and the proposed timelines. So
the critical success factor is to meet or beat established project milestones
Safety: It is important that all the safety guidelines are followed and thus the success factor in
this case will be- no recordable or lost time injuries and reportable injuries lower than the
industry average
Budget: There are a lot of risks involved in this project. It is imperative that we manage risks to
contain costs within the estimated budget
Quality: Conform to project requirements and quality without adverse effects on milestones or
budget. None of the above success factors should be achieved at the cost of quality
Environmental & Regulation Compliance: Complete project without any violations conforming
to the standards and regulations
There will be just cement flooring (cement) to ensure timely completion. There will be no additional
classrooms or study rooms in this hostel.
Page | 13
We have not taken into account risks associated with the external factors like weather, terrain and
natural disasters. With Shillong being an area affected by extreme climate and prone to natural disasters
like mild earthquakes etc., the ideal project plan should also have strategies to mitigate these risks and
have contingencies planned to meet the success factors.
Taking into account all the above factors are out the scope of the current project plan and are topics for
future scope of research.
Importance of minutes of meetings was established while working on the project. It was
observed that referring past decisions and the discussions becomes important for taking future
decisions and hence for future reference minutes of meetings play a very crucial role. Keeping
track of allocated tasks and responsibilities became much easier with the help of minutes of
meetings.
While managing a project, preparing timeline and budget are not the only key areas. There are
many other important things, like work breakdown structure, know-how of the domain to some
extent for efficient scheduling budget management, social cost-benefit analysis, anticipation of
possible risks and measures to mitigate them etc., which needs to be considered while planning
for any project.
Importance of consensus and discussions between client and project management team is
another key area which was observed. The discussions brought out many new ideas on table but
at the same time it was realized that unnecessary discussions may be time consuming without
adding value to the project. Similarly, agreeing to a point is very important for the project to
proceed further effectively. All of this is accomplished through clear and consistent
communication.
Good project management involves no shortage of dialogue between team members, clients,
and anyone else that should be in the loop. Constructive criticism pushes your team to do their
best and makes expectations clear. If someone is already producing phenomenal work, be sure
to recognize it and let them know. It is important to cultivate creativity whenever possible.
Another aspect to bear in mind throughout the life of a project is that changes will be made.
Turning change into an opportunity is important; re-evaluation of the state of project and using
it to motivate the team should be the step forward. That way, even if drastic changes come up—
your project will end a success.
Also a key learning is that good project management doesn’t end when a project is completed.
Evaluating the results of the team’s hard work is an integral step in the process. Obviously the
Page | 14
views of client about team’s efforts will be communicated by them but a personal introspection
becomes important for future improvement.
Without clear knowledge about the actual resources and schedule involved in a construction
project it was difficult to figure out things at many points in time. With the help of online
resources and batch mates with prior experience in this field, this difficulty was tackled to some
extent.
The team involved people with varied backgrounds who have their own understanding about
various topics. Hence, it became difficult in certain discussions to reach on consensus timely.
Thus meetings sometimes became a time consuming affair but this has its own positives and
negatives. Also dividing the roles as project manager, HR manager, communications manager
etc. helped in dealing with this issue to some extent as the concerned person was the one who
led the discussion of his/her domain, brining everyone on same page and helping in reaching a
consensus.
Lack of proper communication sometimes in the initial phase proved to be bottleneck hindering
the project. But gradually as the project planning continued the team developed a co-ordination
and this issue was addressed soon.
Timely follow-up, which is an important step in project management, was in some points not
adequate and hence revising the points discussed in the past meetings consumed a lot of time
but minutes of meetings came to rescue to a large extent.
Page | 15
Annexure
1 Profile of Builder
2 Name
3 Address in full
5 Fax, Email
Page | 16
Place: Signature of the
Date: Caterer/Hotelier
Page | 17