Procedure of Site Inspection in Occupancy/Completion Certificate

Checklist of
Preceding Stage Activities performed during Site Visit
Documents

• Completion of the construction,


Inspection Authority (Planning Authority Officials) shall check the following
approved in construction permit
• Whether building as built, is as per approved building plan

Time Frame • Take photographs of the building from all sides


• Check clearances provided by
• Site visit is intimated within 2 • Fire & Emergency Services Department, where applicable
• Clearance
days of document scrutiny • Consent For Operations (CFO) by KSPCB, where applicable Certificates
• Actual Site visit is performed
• Clearance from Airport Authority of India (AAI), where applicable (applicable)
within 5 days of intimation
• Clearances from SEIAA/MoEF, where applicable

Succeeding Stage
After site visit is performed, authority shall compile the observations and create
site inspection report and upload it within 48 hours for further processing, on
• Issual of the Occupancy
the portal to the ULB.
Certificate