ID Task Task Name 2016 2017 2018 2019 2020 2021 2022

Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
0 RajMahal_MLCP_FINAL RajMahal_MLCP_FINAL RajMahal_MLCP_FINAL
1 Requisites Requisites
2 Prerequisites Prerequisites Prerequisites
3 Notice Inviting RFP Notice Inviting RFP 29-05
4 Pre-Bid Meeting Pre-Bid Meeting 06-06
5 Technical Bid Evaluation Technical Bid Evaluation
6 Technical Evaluation Meeting Technical Evaluation Meeting 21-07
7 Technical Presentation Technical Presentation 24-07
8 Tender Committee Meeting - 1 Tender Committee Meeting - 1 16-08
9 Tender Committee Meeting - 2 Tender Committee Meeting - 2 18-08
10 Financial Bid Financial Bid 19-08
11 Tender Committee Meeting - 3 Tender Committee Meeting - 3
12 Bid Negotiation Meeting Bid Negotiation Meeting 24-08
13 Tender Committee Meeting - 4 Tender Committee Meeting - 4 11-09
14 7th Board Meeting_BSCL 7th Board Meeting_BSCL 25-09
15 LOA LOA 13-10
16 Work Programme Submission Work Programme Submission 04-11
17 Agreement with BSCL Agreement with BSCL 27-12
18 Kick-Off Kick-Off Kick-Off
03-12
19 Statutory Approvals Statutory Approvals
20 External Linkages External Linkages
21 Sewage & Sanitation Facilities Sewage & Sanitation Facilities
22 Water Supply & Distribution Water Supply & Distribution
23 HVAC Systems HVAC Systems
24 Electricity Supply & Distribution Electricity Supply & Distribution
25 Paved Interconnecting Roads & Lanes Paved Interconnecting Roads & Lanes
26 Fire Safety & Fire Fighting Equipment Fire Safety & Fire Fighting Equipment
27 Security Systems Security Systems
28 Toilets Toilets
29 Tree Plantation & Green Areas Tree Plantation & Green Areas
30 Facilities for Disabled Facilities for Disabled
31 Parking Parking
32 Others, if necessary, to establish Others, if necessary, to establish & Operate the project in accordance with spe
& Operate the project in
accordance with specifications &
33 Approvals Approvals
34 Permission of State Govt for Permission of State Govt for cutting of trees 15-12
cutting of trees
35 Clearance of Pollution Control Clearance of Pollution Control Board for setting up of Batching Plant
Board for setting up of Batching
36 Clearance of Pollution Control Clearance of Pollution Control Board for Asphalt Plant 07-01
Board for Asphalt Plant

Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 1
ID Task Task Name 2016 2017 2018 2019 2020 2021 2022
Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
37 Clearances, Permissions and Clearances, Permissions and approvals required under Building bye-laws 12-01
approvals required under Building
38 Environmental Clearances Environmental Clearances 12-01
39 CRZ clearance, if necessary CRZ clearance, if necessary 12-01
40 Permission of the State Govt for Permission of the State Govt for drawing Ground Water or Water from River / Reservoir 18-04
drawing Ground Water or Water
from River / Reservoir
41 Clearance of Pollution Control Clearance of Pollution Control Board for installation of Diesel Generator Sets 25-04
Board for installation of Diesel
42 Fire Safety Clearance from Fire Authorities Fire Safety Clearance from Fire Authorities 18-04
43 Permission from State Road Permission from State Road Delopment Company and/or any concerned regulating authority 18-05
Delopment Company and/or any
concerned regulating authority
44 Permission from Local Planning Permission from Local Planning Authority and/or any regulating authority for Building Permissions 18-05
Authority and/or any regulating
authority for Building Permissions
45 Any other permits or clearances Any other permits or clearances required under applicable laws at the location of site. 18-05
required under applicable laws at
the location of site.
46 Basement Structure Works Basement Structure Works Basement Structure Works
47 Excavation Works Excavation Works Excavation Works
48 Surface Dressing Surface Dressing
49 Site Boundary Barricading Site Boundary Barricading
50 Excavation Excavation
51 PCC PCC
52 Surface Water Proofing Surface Water Proofing
53 Dewatering Works Dewatering Works
54 Structure Works Structure Works Structure Works
55 Reinforcement, Concrete Works of Reinforcement, Concrete Works of Raft Foundations
Raft Foundations
56 Retaining Wall Construction at Retaining Wall Construction at Basement Level - 2
Basement Level - 2
57 Column Concreting at Level - 2 upto Column Concreting at Level - 2 upto Level - 1
Level - 1
58 Form Works, Reinforcement Works Form Works, Reinforcement Works of Basement Slab - 1
of Basement Slab - 1
59 Basement Level - 1 Slab Casting Basement Level - 1 Slab Casting
60 Basement - 2 Complete (Structurally) Basement - 2 Complete (Structurally) Basement
02-03 - 2 Complete (Structurally)
61 Retaining Wall Construction at Retaining Wall Construction at Basement Level - 1
Basement Level - 1
62 Column Concreting at Level - 1 upto Column Concreting at Level - 1 upto Ground Level
Ground Level
63 Form Works, Reinforcement Works Form Works, Reinforcement Works of Basement Slab Ground Floor
of Basement Slab Ground Floor

Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 2
ID Task Task Name 2016 2017 2018 2019 2020 2021 2022
Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
64 Ground Floor Slab Casting Ground Floor Slab Casting
65 Basement - 1 Complete (Structurally) Basement - 1 Complete (Structurally) Basement
13-04 - 1 Complete (Structurally)
66 Super-Structure Works Super-Structure Works Super-Structure Works
67 External Water Proofing Works External Water Proofing Works
68 Backfilling by Soil upto Ground Level Backfilling by Soil upto Ground Level
69 Ground Floor to 1st Floor Ground Floor to 1st Floor Ground Floor to 1st Floor
70 Columns upto 1st Floor Columns upto 1st Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
71 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
72 Reinforcement Tying of Slab Reinforcement Tying of Slab
73 1st Floor Concreting Clab 1st Floor Concreting Clab
74 1st Floor Complete (Structurally) 1st Floor Complete (Structurally) 1st
01-06
Floor Complete (Structurally)
75 1st Floor to 2nd Floor 1st Floor to 2nd Floor 1st Floor to 2nd Floor
76 Columns upto 2nd Floor Columns upto 2nd Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
Concrete
77 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
78 Reinforcement Tying of Slab Reinforcement Tying of Slab
79 2nd Floor Concreting Clab 2nd Floor Concreting Clab
80 2nd Floor Complete (Structurally) 2nd Floor Complete (Structurally) 2nd
20-07
Floor Complete (Structurally)
81 2nd Floor to 3rd Floor 2nd Floor to 3rd Floor 2nd Floor to 3rd Floor
82 Columns upto 3rd Floor Columns upto 3rd Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
Concrete
83 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
84 Reinforcement Tying of Slab Reinforcement Tying of Slab
85 3rd Floor Concreting Clab 3rd Floor Concreting Clab
86 3rd Floor Complete (Structurally) 3rd Floor Complete (Structurally) 3rd
07-09
Floor Complete (Structurally)
87 3rd Floor to 4th Floor 3rd Floor to 4th Floor 3rd Floor to 4th Floor
88 Columns upto 4th Floor Columns upto 4th Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
Concrete
89 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
90 Reinforcement Tying of Slab Reinforcement Tying of Slab
91 4th Floor Concreting Clab 4th Floor Concreting Clab
92 4th Floor Complete (Structurally) 4th Floor Complete (Structurally) 4th
26-10
Floor Complete (Structurally)
93 4th Floor to 5th Floor 4th Floor to 5th Floor 4th Floor to 5th Floor
94 Columns upto 5th Floor Columns upto 5th Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
Concrete
Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 3
ID Task Task Name 2016 2017 2018 2019 2020 2021 2022
Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
95 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
96 Reinforcement Tying of Slab Reinforcement Tying of Slab
97 5th Floor Concreting Clab 5th Floor Concreting Clab
98 5th Floor Complete (Structurally) 5th Floor Complete (Structurally) 5th
14-12
Floor Complete (Structurally)
99 5th Floor to 6th Floor 5th Floor to 6th Floor 5th Floor to 6th Floor
100 Columns upto 6th Floor Columns upto 6th Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
Concrete
101 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
102 Reinforcement Tying of Slab Reinforcement Tying of Slab
103 6th Floor Concreting Clab 6th Floor Concreting Clab
104 6th Floor Complete (Structurally) 6th Floor Complete (Structurally) 6th
01-02
Floor Complete (Structurally)
105 6th Floor to Terrace 6th Floor to Terrace 6th Floor to Terrace
106 Columns upto Terrace Columns upto Terrace Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
107 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
108 Reinforcement Tying of Slab Reinforcement Tying of Slab
109 Terrace Concreting Clab Terrace Concreting Clab
110 Terrace complete (Structurally) Terrace complete (Structurally) Terrace
21-03 complete (Structurally)
111 Terrace and LMR Room / Mumty Terrace and LMR Room / Mumty Terrace and LMR Room / Mumty
112 Columns upto 1st Floor Columns upto 1st Floor Reinforcement, Shuttering and Concrete
Reinforcement, Shuttering and
113 Column De-shuttering and staging Column De-shuttering and staging and Shuttering of Slab
and Shuttering of Slab
114 Reinforcement Tying of Slab Reinforcement Tying of Slab
115 1st Floor Concreting Clab 1st Floor Concreting Clab
116 LMR Room / Mumty complete LMR Room / Mumty complete (Structurally) LMR
09-05
Room / Mumty complete (Structurally)
(Structurally)
117 Finishing Work Finishing Work Finishing Work
118 Ground Floor to 1st Floor Ground Floor to 1st Floor
119 RCC Grade Slab RCC Grade Slab 01-06
120 Brick Work / Allied Works Brick Work / Allied Works
121 Inside Plaster Inside Plaster
122 1st Floor to 2nd Floor 1st Floor to 2nd Floor
123 RCC Grade Slab RCC Grade Slab 20-07
124 Brick Work / Allied Works Brick Work / Allied Works
125 Inside Plaster Inside Plaster
126 2nd Floor to 3rd Floor 2nd Floor to 3rd Floor
127 RCC Grade Slab RCC Grade Slab 07-09
128 Brick Work / Allied Works Brick Work / Allied Works

Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 4
ID Task Task Name 2016 2017 2018 2019 2020 2021 2022
Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
129 Inside Plaster Inside Plaster
130 3rd Floor to 4th Floor 3rd Floor to 4th Floor
131 RCC Grade Slab RCC Grade Slab 26-10
132 Brick Work / Allied Works Brick Work / Allied Works
133 Inside Plaster Inside Plaster
134 4th Floor to 5th Floor 4th Floor to 5th Floor
135 RCC Grade Slab RCC Grade Slab 14-12
136 Brick Work / Allied Works Brick Work / Allied Works
137 Inside Plaster Inside Plaster
138 5th Floor to 6th Floor 5th Floor to 6th Floor
139 RCC Grade Slab RCC Grade Slab 01-02
140 Brick Work / Allied Works Brick Work / Allied Works
141 Inside Plaster Inside Plaster
142 6th Floor to Terrace & LMR Room / Mumty 6th Floor to Terrace & LMR Room / Mumty
143 RCC Grade Slab RCC Grade Slab 21-03
144 Brick Work / Allied Works Brick Work / Allied Works
145 Inside Plaster Inside Plaster
146 Terrace & LMR Room / Mumty Terrace & LMR Room / Mumty Terrace & LMR Room / Mumty
147 RCC Grade Slab RCC Grade Slab RCC
09-05
Grade Slab
148 Brick Work / Allied Works Brick Work / Allied Works
149 Inside Plaster Inside Plaster
150 Utilities Utilities Utilities
151 Tile Fixing Tile Fixing
152 Inside Paint Inside Paint
153 False Ceiling & False Flooring False Ceiling & False Flooring
154 Outside Plaster Outside Plaster
155 Outside Painting Outside Painting
156 Glass Fixing of Windows Glass Fixing of Windows
157 Electrical Works Electrical Works
158 Plumbing Works & Bathroom Sanitary Plumbing Works & Bathroom Sanitary Fittings
Fittings
159 Fire Fighting Works Fire Fighting Works
160 HVAC HVAC
161 Lift & Escalator Works Lift & Escalator Works
162 Area Development Works Area Development Works
163 Handing Over Handing Over Handing
13-07 Over
164 Transaction Services Transaction Services
165 Existing Site Management Study Existing Site Management Study
166 Land Use Study Land Use Study
167 City Regulation Study City Regulation Study
168 Site Approach & Connectivity Site Approach & Connectivity

Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 5
ID Task Task Name 2016 2017 2018 2019 2020 2021 2022
Mode H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
169 Parking Regulation Study Parking Regulation Study
170 Parking Demand Assessment Parking Demand Assessment
171 Preparation of formats for parking Preparation of formats for parking Demand & Existing Parking
Demand & Existing Parking
172 Existing Traffic Data Survey Existing Traffic Data Survey
173 Study of authorised & unauthorised Study of authorised & unauthorised Parking Places in the influence zone
Parking Places in the influence zone
174 Demand Data Analysis Demand Data Analysis
175 Market assessment Market assessment
176 Identify Influence Zone Identify Influence Zone
177 Existing Commercial Development Pattern Existing Commercial Development Pattern
178 Assessment of Commercial Space Assessment of Commercial Space Potential
Potential
179 Existing Commercial Rentals Existing Commercial Rentals
180 Existing Parking Rate Analysis Existing Parking Rate Analysis
181 Financial Feasibility Financial Feasibility
182 Initial Project Costing for starting Initial Project Costing for starting Operations
Operations
183 Rate of Return Study Rate of Return Study
184 Project Structuring Project Structuring
185 O&M Plan and Responsibility Identification O&M Plan and Responsibility Identification
186 Finalisation of Project Mode Finalisation of Project Mode
187 Finalisation of scope of contractor / Finalisation of scope of contractor / Operator
Operator
188 Finalisation of Bid Parameter Finalisation of Bid Parameter
189 Setting up of Various Enforcements Setting up of Various Enforcements
190 Identification of No-Parking Zone Identification of No-Parking Zone
191 Exploring Connectivity of Feeder Exploring Connectivity of Feeder Services to MLCP
Services to MLCP
192 On-Street Parking Regulations On-Street Parking Regulations
193 Setting up of Parking Tariff for MLCP Setting up of Parking Tariff for MLCP
194 Procurement Procurement
195 Preparation of Bidding Documents Preparation of Bidding Documents
196 Preparation of Commercial Terms Preparation of Commercial Terms
197 Bidding Documents Upload & Bidding Process Bidding Documents Upload & Bidding Process
198 Evaluation of Bidding Documents Evaluation of Bidding Documents
199 Hand Holding Client on signing of Hand Holding Client on signing of Agreement
Agreement
200 Recommendations on Policy level Recommendations on Policy level Interventions
Interventions
201 Recommendations Recommendations

Task Project Summary Manual Task Start-only Deadline

Project: RajMahal_MLCP_FINAL Split Inactive Task Duration-only Finish-only Progress


Date: 11 Apr '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone Critical Path

Page 6