PT.

NEXELITE CP INDONESIA Saturday

PROJECT : YINSON Public holiday/Sunday

DAILY ADDITIONAL WORK (BMA) SUMMARY

Man
No Day Date Location Job Description Man Hours Remarks
Power (Hour)

1 Saturday 2-Jan-16 Internal Transformer Room Power Tool,Cleaning & T/up 1st coat 2 21
2 Sunday 3-Jan-16 Underneath Power Tool,Cleaning & T/up 1st coat 2 42
3 Sunday 3-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 2 52
4 Monday 4-Jan-16 Internal Transformer Room Power Tool,Cleaning & T/up 1st coat 2 21
5 Monday 4-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 3 36.5
6 Tuesday 5-Jan-16 Internal Transformer Room Power Tool,Cleaning & T/up 1st coat 2 21
7 Tuesday 5-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 3 29.5
8 Tuesday 5-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 2 19
9 Wednesday 6-Jan-16 Underneath Power Tool,Cleaning & T/up 1st coat 3 36.5
10 Wednesday 6-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 2 21
11 Wednesday 6-Jan-16 Equipment Room 1 Floor
st
Power Tool,Cleaning & T/up 1st coat 2 21
12 Thursday 7-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 2 21
13 Friday 8-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 3 35.5
14 Friday 8-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 3 35.5
15 Friday 8-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 3 35.5
16 Saturday 9-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 2 25
17 Saturday 9-Jan-16 Underneath Power Tool,Cleaning & T/up 1st coat 3 47.5
18 Saturday 9-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 2 25
19 Sunday 10-Jan-16 Underneath Power Tool,Cleaning & T/up 1st coat 3 58
20 Sunday 10-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 2 28
21 Sunday 10-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 2 28
22 Tuesday 12-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 4 42
23 Wednesday 13-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 5 67.5
24 Thursday 14-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 5 77.5
25 Friday 15-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 3 25.5
26 Friday 15-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 3 25.5
27 Saturday 16-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 5 62.5
28 Saturday 16-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 3 24
29 Sunday 17-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 4 56
30 Monday 18-Jan-16 Switchboard Room Power Tool,Cleaning & T/up 1st coat 3 36.5
31 Monday 18-Jan-16 Equipment Room 2nd Floor Power Tool,Cleaning & T/up 1st coat 2 31
32 Monday 18-Jan-16 Equipment Room 1st Floor Power Tool,Cleaning & T/up 1st coat 2 33
Total Man Power 89
Total Man Hours 1140.5

Prepared By Acknowledge By Approved By

PT. Nexelite CP Indonesia Painting SPV Project Manager