COMPOSITE SCHEDULE OF RATES 2008 NWFP

As on Jan-Mar (QTR-1) 2009

Chapter # 01 CARRIAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
01-01-a Carriage of 100 cft / 5 tonne of all materials by truck or 50 Meter 0.00 58.84 50 m 0.00 58.84 a) Cement carried in
other means : 1st 50 meter containers other than
bags will be paid
according to this item
01-01-b Carriage of 100 cft / 5 tonne of all materials by truck or 50 Meter 0.00 9.29 50 m 0.00 9.29 b) Word, pipes and
other means : 2nd 50 meter specials, covers GI ,
CI , AC, RCC,PCC,
PVC and steel pipes
and specials.
01-01-c Carriage of 100 cft / 5 tonne of all materials by truck or 50 Meter 0.00 6.20 50 m 0.00 6.20 c) Reduce the rate in
other means : 3rd to 5th 50 meter case of carriage of
1000 NO. Tiles by:-
01-01-d Carriage of 100 cft / 5 tonne of all materials by truck or 250 Meter 0.00 28.91 250 m 0.00 28.91 33% for 12"x6"x1"
other means : 250 to 1000 meter size
01-01-e Carriage of 100 cft / 5 tonne of all materials by truck or km 0.00 103.24 km 0.00 103.24 25% for 12"x6"x1.5"
other means : 1st kilometer size
01-01-f Carriage of 100 cft / 5 tonne of all materials by truck or km 0.00 24.02 km 0.00 24.02 20% for
other means : 2nd - 5th kilometer 12"x6"x1.25" size
01-01-g Carriage of 100 cft / 5 tonne of all materials by truck or km 0.00 20.23 km 0.00 20.23
other means : 6th to 10th kilometer
01-01-h Carriage of 100 cft / 5 tonne of all materials by truck or km 0.00 16.63 km 0.00 16.63
other means : 11th & subsequent kilometer
01-02-a Carriage of 1000 Nos. bricks or load upto 3 tonne by truck 50 Meter 0.00 37.07 50 m 0.00 37.07 Reduce the rate by
etc : 1st 50 meter 33% for tile size
9"x4.5"x1.5"
01-02-b Carriage of 1000 Nos. bricks or load upto 3 tonne by truck 50 Meter 0.00 5.85 50 m 0.00 5.85
etc : 2nd 50 meter
01-02-c Carriage of 1000 Nos. bricks or load upto 3 tonne by truck 50 Meter 0.00 3.90 50 m 0.00 3.90
etc : 3rd to 5th 50 meter
01-02-d Carriage of 1000 Nos. bricks or load upto 3 tonne by truck 50 Meter 0.00 18.21 250 m 0.00 18.21
etc : 250 - 1000 meter
01-02-e Carriage of 1000 Nos. bricks or load upto 3 tonne by truck km 0.00 65.04 km 0.00 65.04
etc : 1st kilometer
01-02-f Carriage of 1000 Nos. bricks or load upto 3 tonne by truck km 0.00 15.13 km 0.00 15.13
etc : 2nd - 5th kilometer
01-02-g Carriage of 1000 Nos. bricks or load upto 3 tonne by truck km 0.00 12.75 km 0.00 12.75
etc : 6th - 10th kilometer
01-02-h Carriage of 1000 Nos. bricks or load upto 3 tonne by truck km 0.00 10.47 km 0.00 10.47
etc : 11th & subsequent kilometer
01-03-a Carriage of cement(bag), bitumen/lubricants (drum) by Tonne/50 0.00 11.77 tonne/50m 0.00 11.77
truck or other means : 1st 50 meter Meter
01-03-b Carriage of cement (bag) bitumen/lubricant (drum) by truck Tonne/50 0.00 1.86 tonne/50m 0.00 1.86
or other means : 2nd 50 meter Meter

NWFP CSR 2008 - Approved 25-Aug-2008 Page 1 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 01 CARRIAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
01-03-c Carriage of cement (bag), bitumen/lubricant (drum) by Tonne/50 0.00 1.24 tonne/50m 0.00 1.24
truck or other means : 3rd to 5th 50 meter Meter
01-03-d Carriage of cement(bag), bitumen/lubricant (drum) by truck Tonne/25 0.00 5.78 t/250m 0.00 5.78
or other means : 250 to 1000 meter 0 Meter
01-03-e Carriage of cement(bags), bitumen/lubricant (drum) by Tonne/1 0.00 20.65 tonne/km 0.00 20.65
truck or other means : 1st kilometer Km
01-03-f Carriage of cement(bag), bitumen/lubricant (drum) by truck Tonne/1 0.00 4.80 tonne/km 0.00 4.80
or other means : 2nd - 5th kilometer Km
01-03-g Carriage of cement(bag), bitumen/lubricant (drum) by truck Tonne/1 0.00 4.05 tonne/km 0.00 4.05
or other means : 6th - 10th kilometer Km
01-03-h Carriage of cement(bag), bitumen/lubricant (drum) by truck Tonne/1 0.00 3.33 tonne/km 0.00 3.33
or other means : 11th & subsequent km Km
01-04-a Carriage of 100cft of sarkanda, pilchi, frash etc by road or 50 Meter 0.00 35.31 50 m 0.00 35.31
boat : 1st 50 meter
01-04-b Carriage of 100cft of sarkanda, pilchi, frash etc by road or 50 Meter 0.00 5.58 50 m 0.00 5.58
boat : 2nd 50 meter
01-04-c Carriage of 100cft of sarkanda, pichi, frash etc by road or 50 Meter 0.00 3.72 50 m 0.00 3.72
boat : 3rd to 5th kilometer
01-04-d Carriage of 100cft of sarkanda, pilchi, frash etc by road or 250 Meter 0.00 17.34 250 m 0.00 17.34
boat : 250 to 1000 meter
01-04-e Carriage of 100cft of sarkanda, pichi, frash etc by road or km 0.00 61.94 km 0.00 61.94
boat : 1st kilometer
01-04-f Carriage of 100cft of sarkanda, pilchi, frash etc by road or km 0.00 14.41 km 0.00 14.41
boat : 2nd - 5th kilometer
01-04-g Carriage of 100cft of sarkanda, pilchi, frash etc by road or km 0.00 12.14 km 0.00 12.14
boat : 6th - 10th kilometer
01-04-h Carriage of 100cft of sarkanda, pilchi, frash etc by road or km 0.00 9.98 km 0.00 9.98
boat : 11th & subsequent kilometer
01-05-a Carriage of small consignments upto 250kg 1st 50 meter 50 Meter 0.00 2.94 50 m 0.00 2.94 For consignment
weighing over 250
kg, the rate shall be
increased on pro-rate
basis.
01-05-b Carriage of small consigmnments upto 250 kg 2nd 50 50 Meter 0.00 0.46 50 m 0.00 0.46
meter
01-05-c Carriage of small consignments upto 250 kg 3rd to 5th 50 50 Meter 0.00 0.31 50 m 0.00 0.31
meters
01-05-d Carriage of small consignments upto 250 kg 250 - 1000 250 Meter 0.00 1.45 250 m 0.00 1.45
meter
01-05-e Carriage of small consignments upto 250 kg 1st kilometer km 0.00 5.16 km 0.00 5.16
01-05-f Carriage of small consignments upto 250 kg 2nd to 5th km 0.00 1.20 km 0.00 1.20
kilometer

NWFP CSR 2008 - Approved 25-Aug-2008 Page 2 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 01 CARRIAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
01-05-g Carriage of small consignments upto 250 kg 6th to 10th km 0.00 1.01 km 0.00 1.01
kilometer
01-05-h Carriage of small consignments upto 250 kg 11th & km 0.00 0.83 km 0.00 0.83
subsequent kilometer
01-06-a Carriage of consignments (odd job) Coolie load km 27.90 27.90 km 27.90 27.90
01-06-b Carriage of consignments (odd job) Donkey load km 0.00 18.15 km 0.00 18.15
01-06-c Carriage of consignments (odd job) Cart Load km 0.00 13.61 km 0.00 13.61
01-06-d Carriage of consignments (odd job) Camel load km 0.00 18.15 km 0.00 18.15
01-07-a Hire Charges of Truck Day 0.00 5,526.67 Day 0.00 5,526.67 a) This item shall be
allowed with prior
concurrence of
Superintending
Engineer b) The rate
includes pay of driver
and cleaner only. The
cost of repairs shall
be borne by the owner
and the cost of POL,
loading/unloading
shall be paid by the
borrower .
01-07-b Hire charges of Tractor with trolley Day 0.00 4,964.73 Day 0.00 4,964.73
01-07-c Hire charges of Tractor without trolley Day 0.00 4,005.24 Day 0.00 4,005.24
01-08-a Hand shunting loaded railway wagons Upto 500 meter Each 418.50 418.50 Each 418.50 418.50
01-08-b Hand shunting loaded railway wagons Upto 1 kilometer Each 627.75 627.75 Each 627.75 627.75
01-08-c Hand shunting loaded railway wagons Upto 2 kilometer Each 767.25 767.25 Each 767.25 767.25
01-08-d Hand shunting loaded railway wagons 3rd & subsequent Each 348.75 348.75 Each 348.75 348.75
kilometer
01-09-a Hand shunting empty railway wagons Upto 500 meter Each 209.25 209.25 Each 209.25 209.25
01-09-b Hand shunting empty railway wagons Upto 1 kilometer Each 313.88 313.88 Each 313.88 313.88
01-09-c Hand shunting empty railway wagons Upto 2 kilometer Each 383.63 383.63 Each 383.63 383.63
01-09-d Hand shunting empty railway wagons 3rd & subsequent Each 174.38 174.38 Each 174.38 174.38
kilometer

NWFP CSR 2008 - Approved 25-Aug-2008 Page 3 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 02 LOADING, UNLOADING AND STACKING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
02-01 Load into or unload from railway wagons within 50m 100 cft 279.00 279.00 m3 98.53 98.53
shingle, sand, ballast, tiles, etc, laid & stacked
02-02-a Load into or unload from railway wagons within 50m laid 1000 No. 348.75 348.75 1000 No. 348.75 348.75
& stacked : Bricks 10" size
02-02-b Load into or unload from railway wagons within 50m laid 1000 No. 279.00 279.00 1000 No. 279.00 279.00
& stacked : Bricks 9" or smaller size
02-03 Load into or unload from railway wagons, cement in bags 100 No. 348.75 348.75 100 No. 348.75 348.75
and stacking within 50m.
02-04 Load into or unload from railway wagons, empty cement 1000 No. 312.48 312.48 1000 No. 312.48 312.48
bags and stacking
02-05 Load into or unload from railway wagons and stacking tonne 69.75 69.75 tonne 69.75 69.75
white lime in bags
02-06 Load into or unload from railway wagons structural steel, tonne 167.40 167.40 tonne 167.40 167.40
RS joists, rails, rail fastenings etc
02-07 Load into or unload from 45 gallon drums full, into or from Each 22.32 22.32 Each 22.32 22.32
railway wagons,lead upto 50m
02-08 Loading or unloading packages of all sorts upto 50 kg. Each 19.53 19.53 Each 19.53 19.53 Except cement in Jute
or paper bags
02-09-a Load or unload sleepers other than wooden, incl stacking, 100 No. 697.50 697.50 100 No. 697.50 697.50
lead upto 50 m : Broad gauge
02-09-b Load or unload sleepers other than wooden, including 100 No. 348.75 348.75 100 No. 348.75 348.75
stacking, lead upto 50 m : Metre gauge &
02-10 Load or unload timber logs or shuttering into or from tonne 92.07 92.07 tonne 92.07 92.07
railway wagons, including stacking within 50m
02-11 Loading or unloading bhoosa in railway wagons lead upto tonne 209.25 209.25 tonne 209.25 209.25
50 m.
02-12 Load or unload timber scrap or wooden plugs into or from tonne 139.50 139.50 tonne 139.50 139.50
railway wagons & stacking within 50m
02-13 Load or unload pitching stone/spawl from railway wagons 100 cft 103.23 103.23 m3 36.46 36.46
of any guage including clearing 1.5m away
02-14 Loading or unloading building stone including clearing 100 cft 133.92 133.92 m3 47.29 47.29
away 1.5m from rails
02-15-a Unloading oil,bitumen or tar etc : Crude Oil (to be pumped 1000 ltr 83.70 83.70 1000 ltr 83.70 83.70 The rate include
from tank wagon into tank) checking and
weighing the tins
02-15-b Unloading oil,bitumen or tar etc Crude oil (drained by 1000 ltr 83.70 83.70 1000 ltr 83.70 83.70
gravity)
02-15-c Unloading oil,bitumen or tar etc Crude oil materials from Ton 15.90 15.90 Ton 15.90 15.90
railway wagons
02-15-d Unloading oil, bitumen or tar etc : Fuel Oil from tank into tonne 139.50 139.50 tonne 139.50 139.50
empty drums including stacking within 50 m
02-15-e Unloading oil,bitumen or tar etc Petrol (2 gallon tin) 100 No. 175.77 175.77 100 No. 175.77 175.77

NWFP CSR 2008 - Approved 25-Aug-2008 Page 4 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 02 LOADING, UNLOADING AND STACKING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
02-15-f Unloading oil, bitumen or tar etc Kerosine oil (4 gallon tin) 100 No. 348.75 348.75 100 No. 348.75 348.75
02-15-g Unloading oil,bitumen or tar etc Tar & Bitumen in drums 100 No. 0.00 90.75 100 No. 0.00 90.75
with carriage upto 1 km
02-16-a Removing and stacking within 50m. lead Stone, spawl, 100 cft 139.50 139.50 m3 49.26 49.26
brick bats, shingle, sand, lime etc
02-16-b Removing and stacking within 50m. lead Bricks 1000 No. 404.55 404.55 1000 No. 404.55 404.55
02-16-c Removing and stacking within 50m. lead Broad gauge 100 No. 223.20 223.20 100 No. 223.20 223.20
wooden sleepers
02-16-d Removing and stacking within 50m. lead Metre gauge or 100 No. 127.50 127.50 100 No. 127.50 127.50
narrow guage wooden sleepers
02-16-e Removing and stacking within 50m. lead Rails, girders, tonne 64.17 64.17 tonne 64.17 64.17
pipes, cement etc.
02-16-f Removing and stacking within 50m. lead Bridge and 100 No. 744.93 744.93 100 No. 744.93 744.93
crossing timbers, etc.
02-17 Load into wagons girders, rails, MS bars, pipes etc. tonne 178.56 178.56 tonne 178.56 178.56
including 50m lead & stacking inside wagons
02-18 Unload from wagons girders, rails, MS bars, girder etc. tonne 69.75 69.75 tonne 69.75 69.75
including 50m lead but excluding stacking
02-19 Load into wagons wooden baord guage sleepers including 100 No. 558.00 558.00 100 No. 558.00 558.00
50m lead & stacking
02-20 Unload wooden broad gauge sleepers from wagons 100 No. 279.00 279.00 100 No. 279.00 279.00
including 50m lead and stacking
02-21 Loading metre gauge or narrow guage wooden sleepers 100 No. 306.90 306.90 100 No. 306.90 306.90
including 50m lead & stack inside wagons
02-22 Unloading metre gauge or narrow guage wooden sleepers 100 No. 147.87 147.87 100 No. 147.87 147.87
including 50m lead but excluding stacking
02-23 Loading bridge and crossing timber including 50m lead & 100 No. 279.00 279.00 100 No. 279.00 279.00
stacking
02-24 Unloading bridge and crossing timbers including 50m lead 100 No. 139.50 139.50 100 No. 139.50 139.50
but excluding stacking
02-25 Load or unload bitumen, asphalt, tar in drums, into or from tonne 139.50 139.50 tonne 139.50 139.50
railway wagons, lead upto 50m

NWFP CSR 2008 - Approved 25-Aug-2008 Page 5 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-01-a Earth excavation undressed upto single throw of kassi 1000 Cft 1,046.25 1,046.25 m3 36.95 36.95
phaorah or shovel etc : in ashes, sand, soft soil or silt
clearance
03-01-b Earth excavation undressed upto single throw of kassi 1000 Cft 1,255.50 1,255.50 m3 44.34 44.34
phaorah or shove etc : in ordinary soil,
03-02 Earth excavation in ashes, sand & soft soil or silt clearance, 1000 Cft 1,534.50 1,534.50 m3 54.19 54.19
undressed lead upto 25m.
03-03-a Bed clearance and dressing slopes of drains including 1000 Cft 1,953.00 1,953.00 m3 68.97 68.97 The rate is aplicable
removing of weeds and roots etc. Excavated material where the earth of the
undressed within 25m bed to be removed is
of the type of
ordinary soil.When it
is silt or soft soil, it
will be paid per item
No 03-01-a, 03-01-b
or 03-02 above,
whichever is
applicable. The XEN
will specify drains of
each category
03-03-b Bed clearance and dressing slopes of drains including 1000 Cft 2,159.46 2,159.46 m3 76.26 76.26
removing of weeds and roots etc. Excavated material
dressed within 25m lead
03-04-a Borrowpit excavation undressed lead upto 50m in Ordinary 1000 Cft 1,953.00 1,953.00 m3 68.97 68.97
soil
03-04-b Borrowpit excavation undressed lead upto 50m in Hard soil 1000 Cft 2,399.40 2,399.40 m3 84.73 84.73
03-04-c Borrowpit excavation undressed lead upto 50m in 1000 Cft 4,743.00 4,743.00 m3 167.50 167.50
shingle/gravel formation
03-05-a Embankment formation in ordinary soil & compaction by 1000 Cft 551.18 7,039.72 m3 19.46 248.61 The rate includes hire
mechanical means at optimum moistures content to 95% to charges of machinery,
100% max. modified. AASHTO dry density (borrow area) cost of fuel,
lubricants, pay of
driver and cleaner.
The rate also includes
clearing and grubbing
where necessary.
03-05-b Embankment formation in ordinary soil & compaction by 1000 Cft 545.60 6,917.98 m3 19.27 244.31
mechanical means at optimum moistures content to 90%
max. modified AASHTO dry density (borrow area)
03-05-c Embankment formation in ordinary soil & compaction by 1000 Cft 540.02 6,796.24 m3 19.07 240.01
mechanical means at optimum moistures content to 85%
max. modified AASHTO dry density (borrow area)
03-06-a Earth fill in lawns including dressing & compaction with 1000 Cft 1,426.00 1,426.00 m3 50.36 50.36
earth available from cutting/excavation

NWFP CSR 2008 - Approved 25-Aug-2008 Page 6 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-06-b Earth fill in lawns including dressing & compaction with 1000 Cft 2,650.50 2,650.50 m3 93.60 93.60
suitable earth borrowed.
03-07-a Earth excavation in open cut upto 1.5m depth for drains etc 1000 Cft 2,015.00 2,015.00 m3 71.16 71.16
& disposal : in Ordinary Soil
03-07-b Earth excavation in open cut upto 1.5m depth for drains etc 1000 Cft 2,518.75 2,518.75 m3 88.95 88.95
& disposal : in Hard Soil
03-07-c Earth excavation in open cut upto 1.5m depth for drains etc 1000 Cft 2,619.50 2,619.50 m3 92.51 92.51
& disposal : in Very hard Soil
03-07-d Earth excavation in open cut upto 1.5m depth for drains etc 1000 Cft 2,921.75 2,921.75 m3 103.18 103.18
& disposal : in Gravel & shingle
03-08-a Earth excavation in open cut 1.5m - 3m depth for 1000 Cft 2,790.00 2,790.00 m3 98.53 98.53
S.W.Drains etc & disposal : in Ordinary Soil
03-08-b Earth excavation in open cut 1.5m - 3m depth for 1000 Cft 3,152.70 3,152.70 m3 111.34 111.34
S.W.Drains etc & disposal : in Hard Soil
03-08-c Earth excavation in open cut 1.5m - 3m depth for 1000 Cft 3,627.00 3,627.00 m3 128.09 128.09
S.W.Drains etc & disposal : in Very Hard Soil
03-08-d Earth excavation in open cut 1.5m - 3m depth for drains etc 1000 Cft 6,249.60 6,249.60 m3 220.70 220.70
& disposal : in Gravel & shingle
03-09-a Excavation in shingle or gravel formation & rock not 1000 Cft 5,301.00 5,301.00 m3 187.20 187.20
requiring blast, undressed, 50m lead : Dry
03-09-b Excavation in shingle or gravel formation & rock not 1000 Cft 6,138.00 6,138.00 m3 216.76 216.76
requiring blast, undressed, 50m lead : Wet
03-09-c Excavation in shingle or gravel formation & rock not req. 1000 Cft 7,812.00 7,812.00 m3 275.88 275.88
blast, undressed, 50m lead : in Flowing Water
03-10-a Earth excavation in irrigation channels/drains & disposal 1000 Cft 2,263.00 2,263.00 m3 79.92 79.92
upto 25m. & dressing : in Ordinary Soil
03-10-b Earth excavation in irrigation channels/drains & disposal 1000 Cft 2,709.40 2,709.40 m3 95.68 95.68
upto 25m. & dressing : in Hard Soil
03-10-c Earth excavation in irrigation channels/drains & disposal 1000 Cft 3,183.70 3,183.70 m3 112.43 112.43
upto 25m. & dressing : in Very Hard Soil
03-10-d Earth excavation in irrigation channels/drains & disposal 1000 Cft 5,921.00 5,921.00 m3 209.10 209.10
upto 25m. & dressing : in Shingle/Gravel
03-11-a Rock Excavation, dressing & disposal up to 50m Soft 1000 Cft 7,564.00 7,564.00 m3 267.12 267.12 Tools and plants shall
Rock, slate, shale, schist or lateriate be the liability of the
contractor.
03-11-b Rock Excavation, dressing & disposal up to 50m Medium 1000 Cft 8,586.07 9,675.07 m3 303.21 341.67
hard rock, requiring occasional blasting
03-12-a Excavation in hard rock requiring blasting and disposal 1000 Cft 5,409.50 6,498.50 m3 191.03 229.49 a) Tools and plants
upto 25m & dressing : Grade I required shall be the
liabilities of the
contractor.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 7 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-12-b Excavation in hard rock requiring blasting and disposal 1000 Cft 5,936.50 7,751.50 m3 209.65 273.74 b) Reduce the rate by
upto 25m & dressing : Grade II 8 % if the excavated
section is not dressed
or levelled to design
section.
03-12-c Excavation in hard rock requiring blasting and disposal 1000 Cft 7,137.75 9,315.75 m3 252.07 328.98
upto 25m & dressing : Grade III
03-12-d Excavation in hard rock requiring blasting and disposal 1000 Cft 7,959.25 10,500.25 m3 281.08 370.81
upto 25m & dressing : Grade IV
03-12-e Excavation in hard rock requiring blasting and disposal 1000 Cft 8,788.50 11,692.50 m3 310.36 412.92
upto 25m & dressing : Grade V
03-12-f Excavation in hard rock requiring blasting and disposal 1000 Cft 9,455.00 12,722.00 m3 333.90 449.27
upto 25m & dressing : Grade VI
03-13-a Excavation in hard rock requiring blasting but blasting 1000 Cft 10,819.00 10,819.00 m3 382.07 382.07 a) Tools and plants
prohibited, dispose & dress within 25 m : Grade I required shall be the
liabilities of the
contractor.
03-13-b Excavation in hard rock requiring blasting where blasting 1000 Cft 11,873.00 11,873.00 m3 419.29 419.29 b) Reduce the rate by
prohibited, dispose & dress within 25 m : Grade II 8 % if the excavated
section is not dressed
or levelled to design
section.
03-13-c Excavation in hard rock requiring blasting where blasting 1000 Cft 14,275.50 14,275.50 m3 504.14 504.14
prohibited, dispose & dress within 25 m: Grade III
03-13-d Excavation in hard rock requiring blasting where blasting 1000 Cft 15,918.50 15,918.50 m3 562.16 562.16
prohibited, dispose & dress within 25 m: Grade IV
03-13-e Excavation in hard rock requiring blasting where blasting 1000 Cft 17,577.00 17,577.00 m3 620.73 620.73
prohibited, dispose & dress within 25 m: Grade V
03-13-f Excavation in hard rock requiring blasting where blasting 1000 Cft 18,910.00 18,910.00 m3 667.80 667.80
prohibited, dispose & dress within 25 m: Grade VI
03-14-a Rehandling of earthwork Lead upto a single throw of kassi, 1000 Cft 697.50 697.50 m3 24.63 24.63
shovel, phaorah
03-14-b Rehandling of earthwork upto a lead of 25 m. 1000 Cft 976.50 976.50 m3 34.48 34.48
03-15 Rehandling of gravel work or excavated rock, lead upto 1000 Cft 2,790.00 2,790.00 m3 98.53 98.53
25m.
03-16-a Filling, watering and ramming earth under floor with 1000 Cft 1,426.00 1,426.00 m3 50.36 50.36
surplus earth from foundation, etc
03-16-b Filling, watering and ramming earth under floor with earth 1000 Cft 2,960.50 2,960.50 m3 104.55 104.55
excavated from outside lead upto 50m

NWFP CSR 2008 - Approved 25-Aug-2008 Page 8 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-17-a Extra for every 25 m extra lead or part thereof for 1000 Cft 83.70 83.70 m3 2.96 2.96 This rate shall be
earthwork soft, ordinary, hard & very hard aplicable upto 250m
total distance,
including the lead
covered in the item of
earth work.
03-17-b Extra for every 25 m extra lead or part thereof for gravel, 1000 Cft 111.60 111.60 m3 3.94 3.94
shingle or rock.
03-18-a Transportation of earth all types beyond 250 m and upto 1000 Cft 1,980.90 1,980.90 m3 69.95 69.95 This rate will be paid
500 m. in addition to the rate
of earth work, without
deducting the lead
covered in the item of
earth work
03-18-b Transportation of earth all types for every 100m extra lead 1000 Cft 306.90 306.90 m3 10.84 10.84
beyond 500m upto 1.5 km.
03-18-c Transportation of earth all types for every 500m extra lead 1000 Cft 279.00 279.00 m3 9.85 9.85
beyond 1.5 km. upto 8 km.
03-18-d Transportation of earth all types for every 1 km extra lead 1000 Cft 195.30 195.30 m3 6.90 6.90
or part thereof beyond 8 km.
03-19-a Dressing & levelling earth to designed sections Ashes, 1000 Cft 95.48 95.48 m3 3.37 3.37
sand, silt or soft soil upto cut or fill 6 inches
03-19-b Dressing & levelling earth to designed sections Ordinary or 1000 Cft 188.48 188.48 m3 6.66 6.66
hard soil upto cut or fill 6 inches
03-19-c Dressing & levelling earth to designed section Gravel work 1000 Cft 449.50 449.50 m3 15.87 15.87
or soft rock not requiring blasting upto cut or fill 6 inches
03-20 Dowel dressing 1 Chain 105.40 105.40 m 3.46 3.46 This rate is in
addition to pavement
for dressed earth work
03-21 Dressing slopes of banks or ground surface 1000 Sft 387.50 387.50 m2 4.17 4.17 a) To be paid only
when exclusively
dressing is done and
no earh work is
carried out in
embankment or
cutting.
03-22 Dressing of earthwork (done by machinery or otherwise & 1000 Sft 418.50 418.50 m2 4.50 4.50 b) The surface area
left undressed) to designed section dressed is to be taken
for measurement (ii)
The item is aplicable
where the dressing is
done by the
contractor other than
the one who executed
the work

NWFP CSR 2008 - Approved 25-Aug-2008 Page 9 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-23-a Excavation in foundation of building, bridges etc complete 1000 Cft 2,542.00 2,542.00 m3 89.77 89.77
: in sand, ashes or loose soil
03-23-b Excavation in foundation of building, bridges etc complete 1000 Cft 2,976.00 2,976.00 m3 105.10 105.10
: in ordinary soil
03-23-c Excavation in foundation of building, bridges etc complete 1000 Cft 3,332.50 3,332.50 m3 117.69 117.69
: in hard soil or soft murum
03-23-d Excavation in foundation of building, bridges etc complete 1000 Cft 3,782.00 3,782.00 m3 133.56 133.56
: in shingle/gravel
03-24 Cutting hard rock such as granite, ballast, hard lime etc 1000 Cft 19,096.00 29,034.79 m3 674.37 1,025.35 Tools and plants
with chisels/hammers for small foundation required shall be the
liability of the
contractors.
03-25 Extra for excavaton requiring shoring 1000 Cft 426.25 619.85 m3 15.05 21.89 Composite rate
includes material, i.e
plank, etc
03-26-a Mixing & moistening of earthwork to OMC in layers for 1000 Cft 273.42 273.42 m3 9.66 9.66 The rate does not
compaction etc complete include hire charges
of the Roller to be
supplied by the
Department or
through other
agencies.
03-26-b-01 Compaction by rolling with animal driven roller or hand 1000 Cft 759.50 759.50 m3 26.82 26.82
rammed : Soft or sandy soil
03-26-b-02 Compaction by rolling with animal driven roller or hand 1000 Cft 914.50 914.50 m3 32.30 32.30
rammed : Ordinary soil
03-26-b-03 Compaction by rolling with animal driven roller or hand 1000 Cft 1,275.03 1,275.03 m3 45.03 45.03
rammed : Hard soil
03-26-b-04 Compaction by rolling with animal driven roller or hand 1000 Cft 2,251.53 2,251.53 m3 79.51 79.51
rammed : Admixture of shingle
03-26-c Ramming earthwork (all types of soil) 1000 Cft 418.50 418.50 m3 14.78 14.78
03-26-d Ramming earthwork behind retaining wall 1000 Cft 558.00 558.00 m3 19.71 19.71
03-27-a Compaction of earth with power road roller 95% to 100% 1000 Cft 1,178.00 5,534.00 m3 41.60 195.43 The rate alslo inlcude
max. mod. AASHTO dry density hire charges of
machinery, cost of
fuel, lubricant, pay of
driver and cleaner etc
03-27-b Compaction of earth with power road roller 90% max. 1000 Cft 883.50 4,517.86 m3 31.20 159.55
mod. AASHTO dry density
03-27-c Compaction of earth with power road roller 85% max. 1000 Cft 744.00 3,648.00 m3 26.27 128.83
mod. AASHTO dry density
03-28 Extra for wet earthwork 1000 Cft 976.50 976.50 m3 34.48 34.48 That will support a
man's weight.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 10 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-29 Extra for slush or daldal including dewatering 1000 Cft 2,232.00 2,837.00 m3 78.82 100.19 That will not support
a man's weight
03-30 Extra for puddling. 1000 Cft 1,743.75 1,743.75 m3 61.58 61.58
03-31 Earthwork on small rain water drains, along canal banks, Rft 2.79 2.79 m 9.15 9.15
roads, drains, etc complete
03-32 Filling and Compacting Soil, Earth and Boulders behind 1000 Cft 2,511.00 2,511.00 m3 88.68 88.68
retaining walls (Available material)
03-33 Dag belling 75 mm deep. 2500 Rft 434.00 434.00 km 568.54 568.54 Dag belling for layout
of borrow pit, to be
done by contractor at
their own cost.
03-34 Turfing slopes of banks or lawns with grass sods including 1000 Sft 1,116.00 1,116.00 m2 12.01 12.01
ploughing, laying, setting & watering
03-35-a Berm cutting : Lead upto single throw of phaorah or 1000 Cft 1,255.50 1,255.50 m3 44.34 44.34
shovel, without dressing
03-35-b Berm cutting : Upto 25 m lead (including dressing) 1000 Cft 1,953.00 1,953.00 m3 68.97 68.97
03-36-a Berm trimming both sides of channels Upto 1 m depth Mile 3,968.00 3,968.00 km 2,465.72 2,465.72
03-36-b Berm trimming both sides of channels Over 1m to 1.5m Mile 5,254.50 5,254.50 km 3,265.15 3,265.15
depth
03-36-c Berm trimming both sides of channels Over 1.5m to 2.5m Mile 8,354.50 8,354.50 km 5,191.49 5,191.49
depth
03-37-a Ploughing and levelling borrow pits Upto 1m depth Acre 1,798.00 1,798.00 ha 4,442.86 4,442.86 Area ploughed bo be
measured
03-37-b Ploughing and levelling borrow pits Exceeding 1m depth Acre 2,659.80 2,659.80 ha 6,572.37 6,572.37
03-38-a-01 Making boundary or service roads complete in unploughed Chain 434.00 434.00 50 m 711.76 711.76
land : From 3 m to 6 m wide
03-38-a-02 Making boundary or service roads complete in unploughed Chain 589.00 589.00 50 m 965.96 965.96
land : Over 6 m to 12 m wide
03-38-b-01 Making boundary or service roads complete in ploughed Chain 504.99 504.99 50 m 828.18 828.18
land : From 3 m to 6m wide
03-38-b-02 Making boundary or service roads complete in ploughed Chain 724.78 724.78 50 m 1,188.64 1,188.64
land : Over 6 m to 12 m wide
03-39-a Earthwork by boats, Digging and loading into boats, upto 1000 Cft 2,092.50 2,092.50 m3 73.90 73.90 For ordinary soil
25m lead
03-39-b Earthwork by boats, including hire of boats Carriage by 1000 Cft 1,674.00 1,674.00 m3 59.12 59.12
boats upto 250m.
03-39-c Earthwork by boats, including hiring of boats Extra for 1000 Cft 111.60 111.60 m3 3.94 3.94
every additional 50m beyond 250m
03-39-d Earthwork by boats, Unloading earth from boats 1000 Cft 976.50 976.50 m3 34.48 34.48
03-40 Unloading earth from BG trucks and clearing 1.5m from 1000 Cft 837.00 837.00 m3 29.56 29.56
rail

NWFP CSR 2008 - Approved 25-Aug-2008 Page 11 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-41 Earthwork by tramway, digging and loading in trucks, upto 1000 Cft 1,953.00 1,953.00 m3 68.97 68.97
25m lead
03-42 Unloading earth from BG trucks and spreading upto 5m 1000 Cft 1,255.50 1,255.50 m3 44.34 44.34
from rail
03-43 Supplying clean and screened river or pit sand within 150m 1000 Cft 11,780.00 11,780.00 m3 416.01 416.01 The rate include a)
including removal of loose earth or overburden. Removal of top crust
of earth overburden.
b) Royalty to the
government or cost to
the private owner
03-44-a Excavation in open cut for sewers & manhole except 1000 Cft 2,511.00 2,511.00 m3 88.68 88.68 a) The rate does not
shingle, gravel & rock : Upto 2m include back filling
after laying of sewer,
which is payable
seperately b) If the
timbering and
shuttering is not
actually done at site,
the composite rate
may be reduced by 5
%
03-44-b Excavation in open cut for sewers & manholes except 1000 Cft 3,348.00 3,348.00 m3 118.23 118.23
shingle, gravel & rock : 2m to 5m
03-44-c Excavation in open cut for sewers & manholes except 1000 Cft 4,464.00 4,464.00 m3 157.64 157.64
shingle, gravel & rock : Below 5m depth
03-45-a Trench Excavation in open cutting below water level for 1000 Cft 3,828.50 6,691.36 m3 135.20 236.30 The rate does not
sewers & manholes : Upto 1.25m depth include back filling
after laying of sewer,
which is payable
seperately.
03-45-b Trench Excavation in open cutting below water level for 1000 Cft 4,696.50 8,798.40 m3 165.86 310.71
sewers & manholes : 1.25m to 2.5m depth
03-45-c Trench Excavation in open cutting below water level for 1000 Cft 6,773.50 14,372.30 m3 239.20 507.55
sewers & manholes : Exceeding 2.5m depth
03-46 Excavation of trench in all kinds of soils except cutting in 1000 Cft 2,042.90 2,042.90 m3 72.14 72.14 The rate does not
rock for pilelines upto 1.5m depth include back filling
after laying of pipe
line, which is payable
separately.
03-48-a Uprooting stump and removing within 50 m upto 2 m girth Each 697.50 697.50 Each 697.50 697.50
03-48-b Uprooting stump and removing within 50 m above 2 m Each 976.50 1,114.69 Each 976.50 1,114.69
girth
03-48-c Uprooting stump and removing within 50 m upto 2 m girth Each 697.50 1,082.46 Each 697.50 1,082.45
including sand filling and trinches

NWFP CSR 2008 - Approved 25-Aug-2008 Page 12 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-48-d Uprooting stump and removing within 50 m above 2 m Each 976.50 1,643.56 Each 976.50 1,643.56
girth including sand filling and trinches
03-49-a Jungle clearance and removing within 50m Light Jungle Decare 1,501.02 1,501.02 Decare 1,501.02 1,501.02
03-49-b Jungle clearance and removing within 50m Thick Jungle Decare 3,002.04 3,002.04 Decare 3,002.04 3,002.04
03-50 Uprooting sarkanda growth & disposal within 50m 1000 Sft 362.70 362.70 m2 3.90 3.90
03-51 Ploughing 3 times ha 5,359.90 5,359.90 ha 5,359.90 5,359.90
03-52 Levelling, dressing and making lawns 1000 Sft 2,945.00 2,945.00 m2 31.69 31.69
03-53 Turfing of lawn with Dacca Grass 1000 Sft 2,945.00 9,600.00 m2 31.69 103.30
03-54 Clearance of shingle, gravel including sand, soft soil and 1000 Cft 1,422.90 1,422.90 m3 50.25 50.25
silt deposits in channel bed upto 25m
03-55-a Clearance of choked up syphon including dewatering Upto 100 Ft 13,950.00 13,950.00 m 457.68 457.68
1.25m dia
03-55-b Clearance of choked up syphon including dewatering 100 Ft 25,110.00 25,110.00 m 823.82 823.82
Exceeding 1.25m dia
03-56 Clearing & Grubbing 1000 Sft 241.06 1,328.17 m2 2.59 14.29
03-57-a Removal of Tree : Girth 150mm - 300mm including No 18.69 218.55 No 18.69 218.55
removal of stump & backfilling with sand
03-57-b Removal of Tree : Girth 300mm - 600mm including No 37.39 437.09 No 37.39 437.09
removal of stump & backfilling with sand
03-57-c Removal of Tree : Girth over 600mm including removal of No 112.16 1,099.85 No 112.16 1,099.85
stump & backfilling with sand
03-58 Compaction of Natural Ground 1000 Sft 215.11 1,132.54 m2 2.31 12.19
03-59-a Roadway Excavation in Surplus / Unsuitable Common 1000 Cft 157.91 5,572.00 m3 5.58 196.77
Material
03-59-b Roadway Excavation in Surplus / Unsuitable Rock (Hard) 1000 Cft 2,106.76 11,737.61 m3 74.40 414.51
Material requiring blasting.
03-59-c Roadway Excavation in Surplus / Unsuitable Rock 1000 Cft 1,223.26 9,765.11 m3 43.20 344.85
(Medium) Material requiring blasting
03-60-a Structural Excavation in Common Material 1000 Cft 2,606.98 4,880.60 m3 92.06 172.36
03-60-b Structural Excavation in Rock Material requiring blasting 1000 Cft 10,533.71 24,289.44 m3 371.99 857.77
03-60-c Structural backfill using Common Material available at 1000 Cft 3,950.08 21,773.58 m3 139.50 768.93
site.
03-60-d Structural Backfill using Granular Material brought from 1000 Cft 987.66 30,608.66 m3 34.88 1,080.94
outside
03-61-a Formation of Embankment from Roadway Excavation in 1000 Cft 157.91 6,298.37 m3 5.58 222.42
Common Material including compaction by power roller.
03-61-b Formation of Embankment from Roadway Excavation in 1000 Cft 2,106.76 13,817.39 m3 74.40 487.96
Rock Material requiring blasting and compaction of
embankment by power roller.
03-61-c Formation of Embankment from Borrow Excavation in 1000 Cft 158.19 11,444.54 m3 5.59 404.16
Common Material including compaction by power roller.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 13 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 03 EARTHWORK (EXCAVATION AND EMBANKMENT)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
03-61-d Formation of Embankment from Roadway Excavation in 1000 Cft 279.00 6,419.45 m3 9.85 226.70
granular Material including compaction by power roller.
03-62-a Subgrade Preparation in Earth Cut 1000 Sft 215.11 2,107.01 m2 2.31 22.67
03-62-b Subgrade Preparation in Rock Cut 1000 Sft 645.61 5,156.16 m2 6.95 55.48
03-62-c Subgrade Preparation on Existing Road 1000 Sft 430.22 3,010.30 m2 4.63 32.39
03-63-a Earthwork by mechanical means in drains and irrigation 1000 Cft 69.75 1,347.51 m3 2.46 47.59
channels in DRY soil dressed to designed section, grades
profile/with excavated material, disposed off within 50 feet
(15.2 m) lead and dressed as directed.
03-63-b Earthwork by mechanical means in drains and irrigation 1000 Cft 69.75 1,443.34 m3 2.46 50.97
channels in DRY & WET soil dressed to designed section,
grades profile/with excavated material, disposed off within
50 feet (15.2 m) lead and dressed as directed.
03-63-c Earthwork by mechanical means in drains and irrigation 1000 Cft 103.23 1,708.95 m3 3.65 60.35
channels in WET & SLUSH soil dressed to designed
section, grades profile/with excavated material, disposed
off within 50 feet (15.2 m) lead and dressed as directed.
03-63-d Earthwork by mechanical means in drains and irrigation 1000 Cft 103.23 1,949.79 m3 3.65 68.86
channels in SLUSH soil dressed to designed section,
grades profile/with excavated material, disposed off within
50 feet (15.2 m) lead and dressed as directed.
03-63-e Earthwork by mechanical means in drains and irrigation 1000 Cft 139.50 1,865.64 m3 4.93 65.88
channels in DRY & WET to that of SLUSH (1:2) soil
dressed to designed section, grades profile/with excavated
material, disposed off within 50 feet (15.2 m) lead and
dressed as directed.
03-63-f Earthwork by mechanical means in drains and irrigation 1000 Cft 69.75 1,559.31 m3 2.46 55.07
channels in BORROW AREA soil dressed to designed
section, grades profile/with excavated material, disposed
off within 50 feet (15.2 m) lead and dressed as directed.
03-63-g Earthwork by mechanical means in drains and irrigation 1000 Cft 279.00 2,608.01 m3 9.85 92.10
channels in UNDER WATER soil dressed to designed
section, grades profile/with excavated material, disposed
off within 50 feet (15.2 m) lead and dressed as directed.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 14 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 04 DISMANTLING (DEMOLITION)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
04-01 Dismantling dry stone masonry 100 Cft 237.15 237.15 m3 83.75 83.75
04-02 Dismantling stone masonry in mud mortar 100 Cft 348.75 348.75 m3 123.16 123.16
04-03 Dismantling stone masonry in lime or cement mortar 100 Cft 837.00 837.00 m3 295.58 295.58 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively.
04-04-a Dismantling dry stone or spawl pitching 100 Cft 418.50 418.50 m3 147.79 147.79
04-04-b Dismantling stone or spawl pitching (mud grouted) 100 Cft 558.00 558.00 m3 197.06 197.06
04-05 Dismantling stone or spawl pitching and apron in silted 100 Cft 697.50 697.50 m3 246.32 246.32
condition
04-06 Dismantling stone pitching, cement or lime grouted 100 Cft 837.00 837.00 m3 295.58 295.58
04-07-a Dismantling stone in Wooden crates 100 Cft 558.00 558.00 m3 197.06 197.06
04-07-b Dismantling stone in Wire crates 100 Cft 697.50 697.50 m3 246.32 246.32
04-08 Dismantling stone ware drain including base concrete 100 Cft 465.00 465.00 m3 164.21 164.21
04-09 Dismantling mud/pise walling 100 Cft 139.50 139.50 m3 49.26 49.26
04-10 Dismantling sun dried brick masonry 100 Cft 348.75 348.75 m3 123.16 123.16
04-11 Dismantling dry brick masonry 100 Cft 237.15 237.15 m3 83.75 83.75
04-12 Dismantling brick work in mud mortar 100 Cft 488.25 488.25 m3 172.42 172.42 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-12,
04-13, 04-14 and
04-15
04-13 Dismantling brick work in lime or cement mortar 100 Cft 1,185.75 1,185.75 m3 418.74 418.74
04-14 Dismantling cement block masonry 100 Cft 1,046.25 1,046.25 m3 369.48 369.48
04-15 Dismantling Dhajji walling 100 Cft 279.00 279.00 m3 98.53 98.53
04-16 Dismantling mud concrete 100 Cft 558.00 558.00 m3 197.06 197.06
04-17 Dismantling lime concrete 100 Cft 767.25 767.25 m3 270.95 270.95 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-17,
04-19, and 04-20
04-18 Dismantling lime or cement concrete, under water 100 Cft 2,929.50 2,929.50 m3 1,034.54 1,034.54
04-19-a Dismantling : Plain Cement Concrete 1:4:8 100 Cft 1,534.50 1,534.50 m3 541.90 541.90
04-19-b Dismantling : Plain Cement Concrete 1:3:6 100 Cft 2,511.00 2,511.00 m3 886.75 886.75

NWFP CSR 2008 - Approved 25-Aug-2008 Page 15 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 04 DISMANTLING (DEMOLITION)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
04-19-c Dismantling : Plain Cement Concrete 1:2:4 100 Cft 3,069.00 3,069.00 m3 1,083.81 1,083.81
04-19-d Dismantling : Cement Concrete with brick aggregate 100 Cft 837.00 837.00 m3 295.58 295.58
04-19-e Dismantling : DPC of cement concrete 1.5" thick and 100 Sft 379.16 379.16 m2 40.80 40.80
clearing the site
04-20 Dismantling RCC, separating reinforcement, cleaning & 100 Cft 5,022.00 5,022.00 m3 1,773.50 1,773.50
straightening the same
04-21 Dismantling sirki sarkanda or thached roofing supported on 100 Sft 167.40 167.40 m2 18.01 18.01
battens or ballies
04-22-a Dismantling 1st class tile roofing 100 Sft 418.50 418.50 m2 45.03 45.03 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-22-a,
04-22-b, 04-26, 04-27
and 04-30
04-22-b Dismantling 2nd class tile roofing 100 Sft 344.84 344.84 m2 37.11 37.11
04-23 Dismantling from any height, asbestos sheets & ridge 100 Sft 263.50 263.50 m2 28.35 28.35
coping
04-24 Dismantling roof of wooden planks & battens from any 100 Sft 229.40 229.40 m2 24.68 24.68
height
04-25 Dismantling wooden ceiling above 20' height in difficult 100 Sft 851.14 851.14 m2 91.58 91.58
position including lifting along live wire
04-26 Dismantling jack arch roofing, including removing joists 100 Sft 558.00 558.00 m2 60.04 60.04
04-27 Dismantling RB roof complete with mud and mud plaster 100 Sft 697.50 697.50 m2 75.05 75.05
including reinforcement complete
04-28-a Stripping and stacking: Slate or tiles from the truss roofing 100 Sft 259.16 259.16 m2 27.89 27.89
04-28-b Stripping and stacking: GI sheet roofing 100 Sft 338.52 338.52 m2 36.42 36.42
04-29 Extra for dismantling CI sheet roof above 20 ft. in dificult 100 Sft 658.75 658.75 m2 70.88 70.88
position including lifting along live wire
04-30 Dismantling slates or tiles including battens, purlins and 100 Sft 558.00 558.00 m2 60.04 60.04
planking
04-31 Dismantling brick or flagged flooring without concrete 100 Sft 237.15 237.15 m2 25.52 25.52 Add extra 13%, 32%
foundation and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-31 and
04-32
04-32 Dismantling plank or wooden block flooring etc 100 Sft 348.75 348.75 m2 37.53 37.53

NWFP CSR 2008 - Approved 25-Aug-2008 Page 16 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 04 DISMANTLING (DEMOLITION)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
04-33-a Disjointing RCC pipes inside trench & removing pipes & 100 Rft 3,487.50 3,487.50 m 114.42 114.42 a) The rate does not
stacking outside : 6" to 12" diameter include the cost of
excavation and
refilling of trench, or
the demoliation of
any masonry or brick
work.
04-33-b Disjointing RCC pipes inside trench & removing pipes & 100 Rft 4,882.50 4,882.50 m 160.19 160.19 b) Bends, elbows,
stacking outside : 13" to 24" diameter sluice valves, etc
should not be paid for
extra if fixed in the
length of pipe line
that is being
dismantled.
04-33-c Disjointing RCC pipes inside trench & removing pipes & 100 Rft 6,277.50 6,277.50 m 205.95 205.95
stacking outside : 25" to 36" diameter
04-33-d Disjointing RCC pipes inside trench & removing pipes & 100 Rft 8,370.00 8,370.00 m 274.61 274.61
stacking outside : Over 36" diameter
04-34 Removing door with chowkat Each 159.65 159.65 Each 159.65 159.65 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-34 to
04-37
04-35 Removing windows and sky lights with chowkat Each 116.25 116.25 Each 116.25 116.25
04-36 Removing ventilators and wooden sunshades Each 58.13 58.13 Each 58.13 58.13
04-37-a Dismantling: Woden beams up to 12' in length Each 69.75 69.75 Each 69.75 69.75
04-37-b Dismantling: Wooden beams from 12.1' to 23' length Each 139.50 139.50 Each 139.50 139.50
04-37-c Dismantling: Wooden partiton Jaffry Work etc 600 Sft 1,102.11 1,102.11 m2 19.76 19.76
04-37-d Dismantling: Wooden trusses 5 Cwt 1,263.25 1,263.25 100 Kg 492.67 492.67
04-37-e Dismantling: Wooden palisade fencing 50 Rft 868.00 868.00 m 56.96 56.96
04-38 Dismantling iron work of trusses, sheds, water tanks, etc 5 Cwt 1,426.00 1,426.00 100 Kg 556.14 556.14 Add extra 13%, 32%
excluding cutting of rivets and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-38 and
04-39
04-39 Dismantling rolled steel beams or iron rails etc. 12 Cwt 1,395.00 1,395.00 100 Kg 228.78 228.78
04-40 Dismantling iron latrine Each 527.00 527.00 Each 527.00 527.00
04-41 Dismantling tees, bends or sluice valves upto 12" i/d Each/25m 7.75 7.75 Ea/25mm D 7.75 7.75
mD
NWFP CSR 2008 - Approved 25-Aug-2008 Page 17 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 04 DISMANTLING (DEMOLITION)


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
04-42-a Dismantling water column : BG Each 3,968.00 3,968.00 Each 3,968.00 3,968.00
04-42-b Dismantling water column : MG or NG Each 2,697.00 2,697.00 Each 2,697.00 2,697.00
04-43 Dismantling all type of wire fencing, including rolling wire 230 Rft 558.00 558.00 m 7.96 7.96
into bundles and collecting material
04-44 Dismantling wire netting of tennis courts and frame work 100 Sft 111.60 111.60 m2 12.01 12.01
04-45 Dismantling cloth ceiling and supporting timber 100 Sft 209.25 209.25 m2 22.52 22.52
04-46 Dismantling and removing road metalling 100 Cft 558.00 558.00 m3 197.06 197.06
04-47 Dismantling & removing road pavement etc including 100 Sft 3,660.48 3,660.48 m2 393.87 393.87
screening & stacking of by-products upto 50m.
04-48-a Removing from walls: Mud plaster 500 Sft 279.00 279.00 m2 6.00 6.00 Add extra 13%, 32%
and 51% on labour
rates only for 2nd,
3rd, 4th and
subsequent floors
respectively against
item No 04-46 to
04-49
04-48-b Removing from walls: Cement or lime plaster 250 Sft 279.00 279.00 m2 12.01 12.01
04-49-a Scraping : White wash or colour wash 100 Sft 69.75 69.75 m2 7.51 7.51
04-49-b Scraping : Ordinary distemper, oil bound distemper or 100 Sft 209.25 209.25 m2 22.52 22.52
paint off wall
04-50 Dismantling glazed or accoustics tiles etc 100 Sft 868.00 868.00 m2 93.40 93.40
04-51 Scraping boulders. 100 Cft 948.32 948.32 m3 334.90 334.90
04-52 Cleaning mortar of old stones to be used in masonry 100 Cft 976.50 976.50 m3 344.85 344.85
04-53 Dismantling light, fan and call bell point including casing, Point 30.69 30.69 Point 30.69 30.69
capping/strip open type complete
04-54 Dismantling plug point & making good damaged surface Point 25.73 25.73 Point 25.73 25.73
(building portion)
04-55-a Dismantle GI/MS conduit/GI flexible/PVC pipes or Rft 5.97 5.97 m 19.60 19.60
conduit wiring of all sizes : On surface
04-55-b Dismantle GI/MS conduit/GI flexible/PVC pipes or Rft 9.64 9.64 m 31.63 31.63
conduit wiring of all sizes : Recessed in wall

NWFP CSR 2008 - Approved 25-Aug-2008 Page 18 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 05 MORTAR
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
05-01 Lime Sand Mortar 1 : 2 (one Lime: 2 Sand) 100 Cft 1,046.25 6,656.96 m3 369.48 2,350.89
05-02 Lime Sand Mortar 1 : 3 (one Lime: 3 Sand) 100 Cft 1,046.25 5,623.41 m3 369.48 1,985.89
05-03 Lime Surkhi Mortar 1 : 1-1/2 (one Lime: 1-1/2 Surkhi) 100 Cft 1,046.25 6,231.22 m3 369.48 2,200.54
05-04 Lime Surkhi Mortar 1 : 2 (one Lime: 2 Surkhi) 100 Cft 1,046.25 5,492.34 m3 369.48 1,939.60
05-05 Lime Surkhi Mortar 1 : 3 (one Lime: 3 Surkhi) 100 Cft 1,046.25 4,562.21 m3 369.48 1,611.13
05-06 Lime Sand And Surkhi Mortar 1 : 1 : 1 (one Lime: 1 Sand 100 Cft 1,046.25 5,614.35 m3 369.48 1,982.69
And : 1 Surkhi)
05-07 Lime Sand And Surkhi Mortar 1 : 2 : 1 (one Lime: 2 Sand 100 Cft 1,046.25 4,753.17 m3 369.48 1,678.57
And : 1 Surkhi)
05-08 Lime, Cement And Sand Mortar 1 : 1 : 3 (one Lime: One 100 Cft 1,046.25 14,748.01 m3 369.48 5,208.22
Cement And : 3 Sand)
05-09 Lime, Cement And Sand Mortar 1 : 1 : 4 (one Lime: One 100 Cft 1,046.25 12,690.10 m3 369.48 4,481.47
Cement And : 4 Sand)
05-10 Lime, Cement And Sand Mortar 1 : 1 : 5 (one Lime: One 100 Cft 1,046.25 11,229.12 m3 369.48 3,965.53
Cement And : 5 Sand)
05-11 Lime, Cement And Sand Mortar 1 : 1 : 6 (one Lime: One 100 Cft 1,046.25 10,138.36 m3 369.48 3,580.33
Cement And : 6 Sand)
05-12 Lime, Cement And Sand Mortar 1 : 1 : 7 (one Lime: One 100 Cft 1,046.25 9,332.68 m3 369.48 3,295.81
Cement And : 7sand)
05-13 Lime, Cement And Sand Mortar 1 : 1 : 8 (one Lime: One 100 Cft 1,046.25 8,487.10 m3 369.48 2,997.20
Cement And : 8 Sand)
05-14 Lime, Cement And Sand Mortar 1 : 1 : 9 (one Lime: One 100 Cft 1,046.25 8,061.25 m3 369.48 2,846.81
Cement And : 9 Sand)
05-15 Lime, Cement And Sand Mortar 1 : 1 : 10 (one Lime: One 100 Cft 1,046.25 7,629.78 m3 369.48 2,694.44
Cement And : 10 Sand)
05-16 Cement, Lime And Sand Mortar 1 : 2 : 6 (one Cement: 2 100 Cft 1,046.25 9,630.97 m3 369.48 3,401.15
Lime And : 6 Sand)
05-17 Cement, Lime And Sand Mortar 1 : 2 : 9 (one Cement: 2 100 Cft 1,046.25 8,481.66 m3 369.48 2,995.27
Lime And : 9 Sand)
05-18 Cement Sand Mortar 1 : 1 (one Cement: One Sand) 100 Cft 837.00 26,919.88 m3 295.58 9,506.67
05-19 Cement Sand Mortar 1 : 1-1/2 (one Cement: 1-1/2 Sand) 100 Cft 837.00 22,253.79 m3 295.58 7,858.86
05-20 Cement Sand Mortar 1 : 2 (one Cement: 2 Sand) 100 Cft 837.00 19,255.44 m3 295.58 6,800.00
05-21 Cement Sand Mortar 1 : 2-1/2 (one Cement: 2-1/2 Sand) 100 Cft 837.00 16,707.30 m3 295.58 5,900.13
05-22 Cement Sand Mortar 1 : 3 (one Cement: 3 Sand) 100 Cft 837.00 14,633.18 m3 295.58 5,167.66
05-23 Cement Sand Mortar 1 : 4 (one Cement: 4 Sand) 100 Cft 837.00 12,029.29 m3 295.58 4,248.11
05-24 Cement Sand Mortar 1 : 5 (one Cement: 5 Sand) 100 Cft 837.00 10,539.26 m3 295.58 3,721.91
05-25 Cement Sand Mortar 1 : 6 (one Cement: 6 Sand) 100 Cft 837.00 9,244.26 m3 295.58 3,264.58
05-26 Cement Sand Mortar 1 : 7 (one Cement: 7 Sand) 100 Cft 837.00 8,398.89 m3 295.58 2,966.04
05-27 Cement Sand Mortar 1 : 8 (one Cement: 8 Sand) 100 Cft 837.00 7,681.38 m3 295.58 2,712.66
05-28 Clay Mortar. 100 Cft 1,464.75 1,500.30 m3 517.27 529.83
05-29 Clay Mortar Mixed With Chipped Bhoosa Or Straw. 100 Cft 1,464.75 2,861.55 m3 517.27 1,010.55
NWFP CSR 2008 - Approved 25-Aug-2008 Page 19 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 05 MORTAR
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
05-30 Clay Mortar Mixed With Cow-dung 1 : 1 (1 Clay: 1 Cow 200 Cft 1,534.50 5,351.30 m3 270.95 944.90
Dung).
05-31 White Cement And Sand Mortar1 : 3 (1 White Cement 3 100 Cft 837.00 17,801.08 m3 295.58 6,286.40
Sand)
05-32 Coloured Cement Mortar Made By Mixing White Cement 100 Cft 837.00 72,768.63 m3 295.58 25,698.02
And Pigment Of Approved Shade (1 White Cement Mixed
With Pigment Of Approved Shade: 2 Sand)
05-33 White Cement And Sand Mortar1 : 2 (1 White Cement 2 100 Cft 837.00 23,600.55 m3 295.58 8,334.46
Sand)
05-34 Coloured Cement Mortar Made By Mixing Grey Cement 100 Cft 837.00 72,768.63 m3 295.58 25,698.02
And Pigment Of Approved Shade (1 Grey Cement Mixed
With Pigment Of Approved Shade: 2 Sand)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 20 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-01 Mud concrete in foundation using brick ballast or stone 100 Cft 1,262.32 2,926.07 m3 445.78 1,033.33 The stone ballast,
ballast 1.5" gauge to 2" guage crushed bajri, round
shingle from nallah,
or brick ballast may
be used according to
their comparative
cheaper rates in
various areas of the
province.
06-02 Dry rammed shingle brick ballast or stone ballast 1.5" to 2" 100 Cft 837.00 2,234.55 m3 295.58 789.12 ditto
guage
06-03-a Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 9,028.26 m3 593.90 3,188.30
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:3:6)
06-03-b Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 7,300.99 m3 593.90 2,578.32
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:4:8)
06-03-c Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 6,803.68 m3 593.90 2,402.70
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:5:10)
06-03-d Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 6,290.94 m3 593.90 2,221.63
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:6:12)
06-03-e Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 5,652.06 m3 593.90 1,996.01
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:6:18)
06-03-f Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah 100 Cft 1,681.75 5,441.52 m3 593.90 1,921.66
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:7:20)
06-04-a Extra on Item 3 above, for sedimentation tank or filter beds 100 Cft 837.00 837.00 m3 295.58 295.58 The stone ballast,
in PHE works (in bed) crushed bajri, round
shingle from nallah,
or brick ballast may
be used according to
their comparative
cheaper rates in
various areas of the
province.
06-04-b Extra on Item 3 above, for sedimentation tank or filter beds 100 Cft 1,255.50 1,255.50 m3 443.38 443.38
in PHE works (On slope)
06-05-a Plain Cement Conrete including placing, compacting, 100 Cft 1,562.09 17,623.33 m3 551.65 6,223.63
finishing & curing (Ratio 1:1:2)
06-05-b Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 17,510.49 m3 551.65 6,183.78
finishing & curing (Ratio 1:1.5:1.5)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 21 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-05-c Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 13,823.63 m3 551.65 4,881.77
finishing & curing (Ratio 1:1.5:3)
06-05-d Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 13,179.30 m3 551.65 4,654.23
finishing & curing (Ratio 1:2:3)
06-05-e Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 11,656.51 m3 551.65 4,116.46
finishing & curing (Ratio 1:3:3)
06-05-f Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 11,769.65 m3 551.65 4,156.42
finishing & curing (Ratio 1:2:4)
06-05-g Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 10,182.74 m3 551.65 3,596.00
finishing & curing (Ratio 1:2:6)
06-05-h Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 9,846.36 m3 551.65 3,477.21
finishing & curing (Ratio 1:3:6)
06-05-i Plain Cement Concrete including placing, compacting, 100 Cft 1,562.09 8,184.42 m3 551.65 2,890.30
finishing & curing (Ratio 1:4:8)
06-06-a-01 RCC in roof slab, beam, column & other structural 100 Cft 3,158.90 20,059.27 m3 1,115.56 7,083.87 1) The rate include
members, insitu or precast. Type A (1:1:2) rendering floor
surface smooth, and
the plastering done
for making up all
surfaces after
removing centering.
06-06-a-02 RCC in roof slab, beam, column & other structural 100 Cft 3,158.90 16,952.90 m3 1,115.56 5,986.87 2) Plastering done
members, insitu or precast. Type B (1:1.5:3) after soffit of R.C.C
roof slab meant for
human habitaion
buildings shall be
paid extra
06-06-a-03 RCC in roof slab, beam, column & other structural 100 Cft 3,158.90 14,898.92 m3 1,115.56 5,261.51 3) This item shall not
members, insitu or precast. Type C (1:2:4) be applicable to
factory made units.
06-06-b-01 RCC in raft foundation slab, base slab of column & ret. 100 Cft 3,100.00 19,075.33 m3 1,094.76 6,736.40
wall etc, not including in 06-06. Type A (1:1:2)
06-06-b-02 RCC in raft foundation slab, base slab of column & ret. 100 Cft 3,100.00 16,054.87 m3 1,094.76 5,669.73
wall etc, not including in 06-06 Type B (1:1.5:3)
06-06-b-03 RCC in raft foundation slab, base slab of column & ret. 100 Cft 3,100.00 13,308.77 m3 1,094.76 4,699.95
wall etc, not including in 06-06. Type C(1:2:4)
06-06-c-01 RCC including Precast/Prestressed in slab, beam, column, 100 Cft 3,689.00 22,812.75 m3 1,302.76 8,056.25
lintel, girder, etc. Type A (1:1:2)
06-06-c-02 RCC including Precast/Prestressed in slab, beam. column, 100 Cft 3,689.00 19,706.38 m3 1,302.76 6,959.25
lintels, girder, etc. Type B (1:1.5:3)
06-06-c-03 RCC including Precast/Prestressed slab, column, beam, 100 Cft 3,689.00 16,959.07 m3 1,302.76 5,989.04
lintel, girder etc. Type C (1:2:4).
06-06-e Add extra labour for RCC in 2nd & subsequent storeys 100 Cft 1,185.75 1,185.75 m3 418.74 418.74

NWFP CSR 2008 - Approved 25-Aug-2008 Page 22 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-07-a Supply & fabricate M.S. reinforcement for cement concrete Cwt 217.00 4,023.54 Tonne 4,271.47 79,200.15 The rate includes
(Plain bars) wastage, overlap and
chairs, etc
06-07-b Supply & fabricate M.S. reinforcement for cement concrete Cwt 217.00 4,406.38 Tonne 4,271.47 86,736.13
(Hot rolled deformed bars Grade 60)
06-07-c Supply & fabricate M.S. reinforcement for cement concrete Cwt 217.00 4,177.69 Tonne 4,271.47 82,234.55
(Hot rolled deformed bars Grade 40)
06-08 Supplying & fixing high tensile steel wire in prestressing Cwt 434.00 8,238.38 Tonne 8,542.94 162,165.91 The rate includes
cables in precast girders wastage & allowance
for stressing of
cables.
06-09 Precast cement concrete solid or face blocks 1:2:4, 100 Cft 2,588.50 12,415.51 m3 914.12 4,384.50
including cost of templates.
06-10 Precast cem. concrete hollow blocks 1:2:4, including cost 100 Cft 5,595.50 11,172.39 m3 1,976.03 3,945.50
of templates & constructing wall thereof
06-11 Provide & fix ornamental cement jali 1:2:4 2" thick without 100 Sft 2,309.50 4,023.92 m2 248.50 432.97
steel.
06-12-a Extra labour for laying concrete (plain or reinforced) From 100 Cft 1,116.00 1,116.00 m3 394.11 394.11
20' upto 40' height
06-12-b Extra labour for laying concrete (plain or reinforced) For 100 Cft 558.00 558.00 m3 197.06 197.06
every extra10' height
06-13 Extra labour for work of weirs, rails or bridges, syphons & 100 Cft 279.00 279.00 m3 98.53 98.53
concreting in superstructure
06-14 RCC spout, 2.5'x6"x5", including fixing in position Each 217.00 554.17 Each 217.00 554.17
06-15 Making holes upto 3" dia, 18" depth in cement concrete or Each 607.60 607.60 Each 607.60 607.60
stone masonry walls and repairing
06-16 Extra labour for skipping concrete in wells 100 Cft 4,076.50 4,076.50 m3 1,439.60 1,439.60
06-17-a Nicking cement concrete surface. 100 Sft 294.50 294.50 m2 31.69 31.69
06-17-b Nicking lime concrete surface. 100 Sft 97.18 97.18 m2 10.46 10.46
06-18-a Prepare, water and ramming surface for laying concrete (for 100 Sft 217.00 217.00 m2 23.35 23.35
Headworks only) Horizontal floor
06-18-b Prepare, water and ramming surface for laying concrete (for 100 Sft 364.25 364.25 m2 39.19 39.19
Headworks only) Glacis and crest
06-18-c Prepare, water and ramming surface for laying concrete (for 100 Sft 108.50 108.50 m2 11.67 11.67
Headworks only) inverted filters
06-19 Providing and fixing 6" wide GI sheet 18 SWG. stopper to Rft 4.52 51.11 m 14.83 167.67
expansion joint.
06-20 Fill expansion joints with bitumen, sand & saw dust in Rft 2.79 10.35 m 9.15 33.96
Ratio 1:2:2
06-21-a Filling expansion joints with bitumen Rft 27.90 40.38 m 91.54 132.49
06-21-b Laying Asphaltic Mixture in Expansion Joints Rft 27.90 27.90 m 91.54 91.54

NWFP CSR 2008 - Approved 25-Aug-2008 Page 23 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-22-a-01 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 1,010.60 2,730.28 m2 108.74 293.78
coat, 1 layer polythene & 1 coat bitumen (1.5" thick)
06-22-a-02 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 1,010.60 3,106.96 m2 108.74 334.31
coat, 1 layer polythene & 1 coat bitumen (2" thick)
06-22-a-03 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 1,069.50 3,990.56 m2 115.08 429.38
coat, 1 layer polythene & 1 coat bitumen (3" thick)
06-22-b-01 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 804.45 2,773.82 m2 86.56 298.46
coat, 1 layer polythene & 2 coats bitumen (1.5" thick)
06-22-b-02 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 1,010.60 3,356.64 m2 108.74 361.17
coat, 1 layer polythene & 2 coats bitumen (2" thick)
06-22-b-03 Damp proof course of cem. conc. 1:2:4 including bitumen 100 Sft 1,004.71 4,175.45 m2 108.11 449.28
coat, 1 layer polythene & 2 coats bitumen (3" thick)
06-23-a-01 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 1,797.47 m2 99.23 193.41
bitumen Ratio 1:4 (0.5" thick)
06-23-a-02 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 1,974.62 m2 99.23 212.47
bitumen Ratio 1:4 (0.75" thick)
06-23-a-03 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 1,876.24 m2 99.23 201.88
bitumen Ratio 1:3 (0.5" thick)
06-23-a-04 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 2,091.59 m2 99.23 225.06
bitumen Ratio 1:3 (0.75" thick)
06-23-a-05 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 1,993.22 m2 99.23 214.47
bitumen Ratio 1:2 (0.5" thick)
06-23-a-06 Damp proof course in c/s plaster, 1 layer polythene, 1 coat 100 Sft 922.25 2,286.98 m2 99.23 246.08
bitumen Ratio 1:2 (0.75" thick)
06-23-b-01 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,048.16 m2 99.23 220.38
bitumen Ratio 1:4 (0.5" thick)
06-23-b-02 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,224.30 m2 99.23 239.33
bitumen Ratio 1:4 (0.75" thick)
06-23-b-03 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,125.93 m2 99.23 228.75
bitumen Ratio 1:3 (0.5" thick)
06-23-b-04 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,341.28 m2 99.23 251.92
bitumen Ratio 1:3 (0.75" thick)
06-23-b-05 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,242.90 m2 99.23 241.34
bitumen Ratio 1:2 (0.5" thick)
06-23-b-06 Damp proof course in c/s plaster, 1 layer polythene, 2 coats 100 Sft 922.25 2,536.66 m2 99.23 272.94
bitumen Ratio 1:2 (0.75" thick)
06-24-a-01 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 1,807.18 m2 99.23 194.45
bitumen Ratio 1:4 (0.5" thick)
06-24-a-02 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 1,974.62 m2 99.23 212.47
bitumen Ratio 1:4 (0.75" thick)
06-24-a-03 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 1,889.31 m2 99.23 203.29
bitumen Ratio 1:3 (0.5" thick)
NWFP CSR 2008 - Approved 25-Aug-2008 Page 24 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-24-a-04 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 2,091.59 m2 99.23 225.06
bitumen Ratio 1:3 (0.75" thick)
06-24-a-05 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 1,993.22 m2 99.23 214.47
bitumen Ratio 1:2 (0.5" thick)
06-24-a-06 V. Damp proof c/s plaster, 1 layer polythene 1 coat 100 Sft 922.25 2,286.98 m2 99.23 246.08
bitumen Ratio 1:2 (0.75" thick)
06-24-b-01 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,056.87 m2 99.23 221.32
bitumen Ratio 1:4 (0.5" thick)
06-24-b-02 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,224.30 m2 99.23 239.33
bitumen Ratio 1:4 (0.75" thick)
06-24-b-03 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,143.35 m2 99.23 230.62
bitumen Ratio 1:3 (0.5" thick)
06-24-b-04 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,341.28 m2 99.23 251.92
bitumen Ratio 1:3 (0.75" thick)
06-24-b-05 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,242.90 m2 99.23 241.34
bitumen Ratio 1:2 (0.5" thick)
06-24-b-06 V. Damp proof c/s plaster, 1 layer polythene 2 coats 100 Sft 922.25 2,536.66 m2 99.23 272.94
bitumen Ratio 1:2 (0.75" thick)
06-25 Grouting concrete between the grooves of gates including 100 Cft 3,720.00 3,720.00 m3 1,313.71 1,313.71
shuttering
06-26 Chisel dressing concrete surface on sides of grooves 1000 Sft 1,472.50 1,472.50 m2 15.84 15.84
06-27 Laying and ramming dry ballast or kankar 100 Sft 3,373.11 3,373.11 m2 362.95 362.95
06-28 Hoisting & placing in position RCC shelves 100 No 4,466.17 4,466.17 No 44.66 44.66
06-29-a Breaking brick ballast, screening & stacking 2" ring 100 Cft 837.00 837.00 m3 295.58 295.58
06-29-b Breaking brick ballast, screening & stacking 1.5" ring 100 Cft 976.50 976.50 m3 344.85 344.85
06-29-c Breaking brick ballast, screening & stacking 1" ring 100 Cft 1,116.00 1,116.00 m3 394.11 394.11
06-29-d Breaking brick ballast, screening & stacking. Jhama ballast 100 Cft 1,255.50 1,255.50 m3 443.38 443.38
3/4" ring
06-30 Supply & fix broken glasses on court yard walls, including 100 Rft 890.51 5,730.51 m 29.22 188.01
1:3:6 cement concrete coping
06-31 Crushing stone ballast by machine 100 Cft 789.57 789.57 m3 278.83 278.83 This does not include
the chages for
working of crushers ,
but manual labour
for charges of stone to
crusher within 100 m
and also stacking the
product after crushing
within 100 m.
06-32-a Breaking stone ballast screened & stacked 2" ring 100 Cft 976.50 976.50 m3 344.85 344.85
06-32-b Breaking stone ballast screened & stacked 1.5" ring 100 Cft 1,116.00 1,116.00 m3 394.11 394.11
06-32-c Breaking stone ballast screened & stacked 1" ring 100 Cft 1,255.50 1,255.50 m3 443.38 443.38

NWFP CSR 2008 - Approved 25-Aug-2008 Page 25 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-32-d Breaking stone ballast screened & stacked 0.5" ring 100 Cft 1,674.00 1,674.00 m3 591.17 591.17
06-32-e Breaking stone ballast screened & stacked 1/8" to 1/4" ring 100 Cft 2,790.00 2,790.00 m3 985.28 985.28
06-33 Screening and stacking stone ballast, shingle or bajri etc 100 Cft 279.00 279.00 m3 98.53 98.53
06-34 Washing ballast, bajri or shingle 100 Cft 279.00 279.00 m3 98.53 98.53
06-35 Erecting and carting sun shades of precast RCC (upto 5"x Each 198.40 198.40 Each 198.40 198.40
2.5")
06-36-a PCC 1:3:6 in mass concrete less formwork using 50% 100 Cft 1,765.76 6,260.86 m3 623.57 2,211.00
boulders
06-36-b PCC 1:3:6 in mass concrete less formwork using 40% 100 Cft 1,762.97 6,911.68 m3 622.59 2,440.84
boulders
06-36-c PCC 1:3:6 in mass concrete less formwork using 30% 100 Cft 1,762.97 7,574.61 m3 622.59 2,674.95
boulders
06-37-a PCC 1:4:8 in mass concrete less formwork using 50% 100 Cft 1,762.97 5,333.98 m3 622.59 1,883.68
boulders
06-37-b PCC 1:4:8 in mass concrete less formwork using 40% 100 Cft 1,762.97 5,806.19 m3 622.59 2,050.44
boulders
06-37-c PCC 1:4:8 in mass concrete less formwork using 30% 100 Cft 1,762.97 6,278.39 m3 622.59 2,217.19
boulders
06-38-a Erecting & removing formwork to concrete in any shape / 100 Sft 2,325.00 2,539.47 m2 250.17 273.25
position (Horizontal)
06-38-b Erecting & removing formwork to concrete in any shape / 100 Sft 2,604.00 2,849.33 m2 280.19 306.59
position (Vertical)
06-39-a Erection and removal of steel Form work for RCC or Plain 100 Sft 286.75 5,566.16 m2 30.85 598.92
Concrete horizontal
06-39-b Erection and removal of steel Form work for RCC or Plain 100 Sft 232.50 5,475.61 m2 25.02 589.18
Concrete vertical
06-40-a Class A1 concrete in reinforcement/non reinforcement 100 Cft 2,402.50 12,349.91 m3 848.44 4,361.33
concrete structure with minimum cylinder compressive
strength 3000 psi on 28 days other than concrete in water
and piles with consistency range in slump 25-75 mm with
water cement ratio 0.58
06-40-b Class A2 cement concrete for concrete place under water 100 Cft 2,402.50 13,274.05 m3 848.44 4,687.69
with minimum cylinder compressive strength 3500 psi on
28 days with consistency range in slump 100-150 mm with
water cement ratio 0.58
06-40-c Class A3 cement concrete for concrete in pile with 100 Cft 2,402.50 14,883.04 m3 848.44 5,255.90
minimum cylinder compressive strenght 4000 psi on 28
days other than concrete in water and piles with
consistency range in slump 100-150 mm with water cement
ratio 0.58

NWFP CSR 2008 - Approved 25-Aug-2008 Page 26 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 06 CONCRETE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
06-40-d Class B concrete for concrete in pile specified works only 100 Cft 2,402.50 11,123.58 m3 848.44 3,928.26
with minimum cylinder compressive strenght 2418 psi on
28 days and consistency range in slump 25-75 mm with
water cement ratio 0.65
06-40-e Class C concrete for concrete for cribbing or otherwise 100 Cft 2,402.50 11,954.54 m3 848.44 4,221.71
specified in special provision with minimum cylinder
compressive strength 3000 psi on 28 days and consistency
range in slump 25-75 mm with water cement ratio 0.58
06-40-f Class D1 concrete for concrete in pre-stressed & post 100 Cft 2,402.50 15,714.01 m3 848.44 5,549.36
tensioned with minimum cylinder compressive strength
4978.12 psi on 28 days and consistency range in slump
50-100 mm with water cement ratio 0.40
06-40-g Class D2 concrete for concrete in pre-stressed & post 100 Cft 2,402.50 16,980.58 m3 848.44 5,996.64
tensioned with minimum cylinder compressive strength
6045 psi on 28 days and consistency range in slump
50-100 mm with water cement ratio 0.40
06-40-h Class D3 concrete for concrete in pre-stressed & post 100 Cft 2,402.50 18,223.81 m3 848.44 6,435.68
tensioned with minimum cylinder compressive strength
7112 psi on 28 days and consistency range in slump
50-100 mm with water cement ratio 0.40
06-40-i Class Y concrete for concrete use as filler in steel grid, 100 Cft 2,402.50 14,540.62 m3 848.44 5,134.98
Bridge floor, in then reinforced section etc with minimum
cylinder compressive strength 2575 psi on 28 days and
consistency range in slump 50-100 mm with water cement
ratio 0.58
06-40-j Lean concrete for use as thin layer under neath footings 100 Cft 2,402.50 8,958.28 m3 848.44 3,163.59
with cylinder compressive strength of 1423 psi on 28 days.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 27 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-01-a Pacca brickwork in mud mortar in buildings in foundation 100 Cft 1,751.19 7,743.71 m3 618.43 2,734.67
and plinth
07-01-b Pacca brickwork in mud mortar in buildings in ground 100 Cft 2,327.48 8,416.80 m3 821.94 2,972.37
floor
07-02-a Add extra on Item 07-01 for brickwork in First floor 100 Cft 426.25 523.05 m3 150.53 184.71
07-02-b Add extra on Item 07-01 for brickwork in Second floor 100 Cft 999.75 1,096.55 m3 353.06 387.24
07-02-c Add extra on Item 07-01 for brickwork in Third floor 100 Cft 1,573.25 1,670.05 m3 555.59 589.77
07-02-d Add extra on Item 07-01 for brickwork in Fourth & 100 Cft 2,146.75 2,243.55 m3 758.12 792.30
subsequent floors.
07-03-a Pacca brick work in mud mortar other than building Upto 100 Cft 2,433.50 8,426.03 m3 859.38 2,975.63
20 ft. height
07-03-b Pacca brick work in mud mortar other than building Extra 100 Cft 426.25 426.25 m3 150.53 150.53
labour for each 5 ft. addl. height or part
07-04-a-01 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 11,718.02 m3 818.00 4,138.18
mortar 1:2
07-04-a-02 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 10,871.78 m3 818.00 3,839.34
mortar 1:3
07-04-a-03 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 10,364.03 m3 818.00 3,660.03
mortar 1:4
07-04-a-04 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 10,005.57 m3 818.00 3,533.44
mortar 1:5
07-04-a-05 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 9,788.58 m3 818.00 3,456.81
mortar 1:6
07-04-a-06 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 9,604.91 m3 818.00 3,391.94
mortar 1:7
07-04-a-07 Pacca brick work in foundation and plinth in Cement, sand 100 Cft 2,316.32 9,458.50 m3 818.00 3,340.24
mortar 1:8
07-04-b-01 Pacca brick work in foundation and plinth in Lime, cement, 100 Cft 2,316.32 10,005.87 m3 818.00 3,533.54
sand mortar 1:1:6
07-04-b-02 Pacca brick work in foundation and plinth in Lime, cement, 100 Cft 2,316.32 9,822.68 m3 818.00 3,468.85
sand mortar 1:1:7
07-04-b-03 Pacca brick work in foundation and plinth in Lime, cement, 100 Cft 3,029.32 10,388.30 m3 1,069.80 3,668.60
sand mortar 1:1:8
07-04-b-04 Pacca brick work in foundation and plinth in Lime, cement, 100 Cft 2,316.32 9,551.33 m3 818.00 3,373.02
sand mortar 1:1:9
07-04-b-05 Pacca brick work in foundation and plinth in Lime, cement, 100 Cft 2,316.32 9,458.46 m3 818.00 3,340.23
sand mortar 1:1:10
07-04-c Pacca brick work in foundation and plinth in Lime, sand 100 Cft 2,316.32 9,255.33 m3 818.00 3,268.49
mortar 1:2
07-04-c-01 Pacca brick work in foundation and plinth in lime, sand, 100 Cft 2,316.32 9,129.02 m3 818.00 3,223.89
surkhi 1:1:1

NWFP CSR 2008 - Approved 25-Aug-2008 Page 28 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-04-c-02 Pacca brick work in foundation and plinth in lime, coarse 100 Cft 2,316.32 9,582.37 m3 818.00 3,383.99
cinder.
07-04-c-03 Pacca brick work in foundation and plinth in lime, surkhi 100 Cft 2,316.32 9,327.36 m3 818.00 3,293.93
mortar 2:3
07-04-c-04 Pacca brick work in foundation and plinth in lime, surkhi 100 Cft 2,316.32 9,142.42 m3 818.00 3,228.62
mortar 1:2
07-04-c-05 Pacca brick work in foundation and plinth in lime, surkhi 100 Cft 2,316.32 8,909.69 m3 818.00 3,146.43
mortar 1:3
07-05-a-01 Pacca brick work in ground floor Cement, sand mortar 1:2 100 Cft 2,970.42 12,468.92 m3 1,048.99 4,403.36
07-05-a-02 Pacca brick work in ground floor Cement, sand mortar 1:3 100 Cft 2,970.42 11,622.68 m3 1,048.99 4,104.51
07-05-a-03 Pacca brick work in ground floor Cement, sand mortar 1:4 100 Cft 2,970.42 11,114.93 m3 1,048.99 3,925.20
07-05-a-04 Pacca brick work in ground floor Cement, sand mortar 1:5 100 Cft 2,970.42 10,776.43 m3 1,048.99 3,805.66
07-05-a-05 Pacca brick work in ground floor Cement, sand mortar 1:6 100 Cft 2,970.42 10,539.48 m3 1,048.99 3,721.99
07-05-a-06 Pacca brick work in ground floor Cement, sand mortar 1:7 100 Cft 2,970.42 10,355.81 m3 1,048.99 3,657.12
07-05-a-07 Pacca brick work in ground floor Cement, sand mortar 1:8 100 Cft 2,970.42 10,209.40 m3 1,048.99 3,605.42
07-05-b-01 Pacca brick work in ground floor Lime, cement, sand 100 Cft 3,029.32 10,824.38 m3 1,069.80 3,822.60
mortar 1:1:6
07-05-b-02 Pacca brick work in ground floor Lime, cement, sand 100 Cft 3,029.32 10,632.48 m3 1,069.80 3,754.83
mortar 1:1:7
07-05-b-03 Pacca brick work in ground floor Lime, cement, sand 100 Cft 3,029.32 10,485.10 m3 1,069.80 3,702.78
mortar 1:1:8
07-05-b-04 Pacca brick work in ground floor Lime, cement, sand 100 Cft 3,029.32 10,361.13 m3 1,069.80 3,659.00
mortar 1:1:9
07-05-b-05 Pacca brick work in ground floor Lime, cement, sand 100 Cft 3,029.32 10,268.26 m3 1,069.80 3,626.21
mortar 1:1:10
07-05-c Pacca brick work in ground floor Lime, sand mortar 1:2 100 Cft 3,029.32 10,065.13 m3 1,069.80 3,554.47
07-05-c-01 Pacca brick work in foundation and plinth in lime, sand, 100 Cft 3,029.32 9,842.02 m3 1,069.80 3,475.68
surkhi 1:1:1.
07-05-c-02 Pacca brick work in Ground floor lime, coarse cinder. 100 Cft 3,029.32 10,295.37 m3 1,069.80 3,635.78
07-05-c-03 Pacca brick work in Ground floor lime, surkhi mortar 2:3 100 Cft 3,029.32 10,040.36 m3 1,069.80 3,545.72
07-05-c-04 Pacca brick work in Ground floor lime, surkhi mortar 1:2 100 Cft 3,029.32 9,855.42 m3 1,069.80 3,480.41
07-05-c-05 Pacca brick work in Ground floor lime, surkhi mortar 1:3 100 Cft 3,029.32 9,622.69 m3 1,069.80 3,398.22
07-06-a Add extra on item No.07-05 for brick work in First floor 100 Cft 426.25 523.05 m3 150.53 184.71
07-06-b Add extra on item No.07-05 for brick work in in Second 100 Cft 999.75 1,096.55 m3 353.06 387.24
floor
07-06-c Add extra on item No.07-05 for brick work in Third floor 100 Cft 1,573.25 1,670.05 m3 555.59 589.77
07-06-d Add extra on item No.07-05 for brick work in in Fourth & 100 Cft 2,580.75 2,677.55 m3 911.38 945.57
subsequent floors.
07-07-a-01 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 12,226.50 m3 963.39 4,317.75
Cement, sand mortar 1:2

NWFP CSR 2008 - Approved 25-Aug-2008 Page 29 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-07-a-02 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,867.50 11,519.76 m3 1,012.65 4,068.17
Cement, sand mortar 1:3
07-07-a-03 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,872.51 m3 963.39 3,839.59
Cement, sand mortar 1:4
07-07-a-04 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,534.01 m3 963.39 3,720.05
Cement, sand mortar 1:5
07-07-a-05 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,297.06 m3 963.39 3,636.38
Cement, sand mortar 1:6
07-07-a-06 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,113.39 m3 963.39 3,571.51
Cement, sand mortar 1:7
07-07-a-07 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 9,966.98 m3 963.39 3,519.81
Cement, sand mortar 1:8
07-07-b-01 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,514.35 m3 963.39 3,713.11
Lime, cement, sand mortar 1:1:6
07-07-b-02 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,331.56 m3 963.39 3,648.56
Lime, cement, sand mortar 1:1:7
07-07-b-03 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,183.78 m3 963.39 3,596.37
Lime, cement, sand mortar 1:1:8
07-07-b-04 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 10,059.81 m3 963.39 3,552.59
Lime, cement, sand mortar 1:1:9
07-07-b-05 Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 9,966.94 m3 963.39 3,519.79
Lime, cement, sand mortar 1:1:10
07-07-c Pacca brick work other than building upto 10 ft. height : 100 Cft 2,728.00 9,763.81 m3 963.39 3,448.06
Lime, sand mortar 1:2
07-07-c-01 Pacca brick work in other than building upto 10 ft height in 100 Cft 3,983.50 10,893.05 m3 1,406.76 3,846.85
lime, sand, surkhi 1:1:1
07-07-c-02 Pacca brick work in other than building upto 10 ft height in 100 Cft 2,728.00 10,090.85 m3 963.39 3,563.55
lime, coarse cinder 1:1
07-07-c-03 Pacca brick work in other than building upto 10 ft height in 100 Cft 2,728.00 9,835.84 m3 963.39 3,473.50
lime, surkhi mortar 2:3
07-07-c-04 Pacca brick work in other than building upto 10 ft height in 100 Cft 2,309.50 9,232.40 m3 815.59 3,260.39
lime, surkhi mortar 1:2
07-07-c-05 Pacca brick work in other than building upto 10 ft height in 100 Cft 3,029.32 9,719.49 m3 1,069.80 3,432.41
lime, surkhi mortar 1:3
07-08 Add extra on item No. 07-07 for every 10 ft. additional 100 Cft 426.25 445.61 m3 150.53 157.37
height, or part thereof
07-09 Extra labour for arch work in brick masonry, including 100 Cft 1,147.00 1,195.40 m3 405.06 422.15
labour for centring and decentring
07-10 Extra for pacca brick work in steining of wells or any other 100 Cft 736.25 1,032.70 m3 260.00 364.69
circular masonry.
07-11 Extra labour for profile & flared walls 100 Cft 868.00 868.00 m3 306.53 306.53

NWFP CSR 2008 - Approved 25-Aug-2008 Page 30 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-12-a Extra labour for pacca brick work in pier/abutment From 100 Cft 573.50 573.50 m3 202.53 202.53
10 ft.to 20 ft. height.
07-12-b Extra labour for pacca brick work in pier/abutment 100 Cft 1,007.50 1,007.50 m3 355.80 355.80
Exceeding 20 ft height.
07-13 Extra for face work (half brick thick) using special bricks 100 Sft 573.50 573.50 m2 61.71 61.71 This item is to be
instead of first class bricks. executed only on the
written orders of
Superintending
Engineer.
07-14 Reinforced brick work in lintel of openings, laid in 1:3 100 Cft 7,453.02 17,398.49 m3 2,632.01 6,144.22
cement mortar complete
07-15-a Extra for dressing or chamfering bricks for Special 100 No 1,906.50 1,906.50 100 No. 1,906.50 1,906.50
architectural bricks
07-15-b Extra for dressing or chamfering bricks for all other 100 No 1,317.50 1,317.50 100 No. 1,317.50 1,317.50
purposes.
07-16-a Perf. pacca brick wall 1/2 brick thick in ground floor : Mud 100 Sft 1,163.74 2,786.68 m2 125.22 299.85
mortar
07-16-b-01 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 4,089.49 m2 163.28 440.03
Cement, sand mortar 1:2
07-16-b-02 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,877.68 m2 163.28 417.24
Cement, sand mortar 1:3
07-16-b-03 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,750.99 m2 163.28 403.61
Cement, sand mortar 1:4
07-16-b-04 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,666.36 m2 163.28 394.50
Cement, sand mortar 1:5
07-16-b-05 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,606.88 m2 163.28 388.10
Cement, sand mortar 1:6
07-16-b-06 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,561.46 m2 163.28 383.21
Cement, sand mortar 1:7
07-16-b-07 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.73 3,527.09 m2 163.31 379.51
Cement, sand mortar 1:8
07-16-c-01 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,538.75 m2 163.28 380.77
Lime, cement, sand mortar 1:1:6
07-16-c-02 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,496.61 m2 163.28 376.24
Lime, cement, sand mortar 1:1:7
07-16-c-03 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,458.23 m2 163.28 372.11
Lime, cement, sand mortar 1:1:8
07-16-c-04 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,424.62 m2 163.28 368.49
Lime, cement, sand mortar 1:1:9
07-16-c-05 Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,404.66 m2 163.28 366.34
Lime, cement, sand mortar 1:1:10
07-16-d Perf. pacca brick wall 1/2 brick thick in ground floor : 100 Sft 1,517.45 3,349.13 m2 163.28 360.37
Lime, sand mortar 1:2
NWFP CSR 2008 - Approved 25-Aug-2008 Page 31 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-17-a Add extra on item No. 07-16 for pacca brick work in First 100 Sft 213.13 232.49 m2 22.93 25.02
floor
07-17-b Add extra on item No. 07-16 for pacca brick work in 100 Sft 499.88 519.23 m2 53.79 55.87
Second floor
07-17-c Add extra on item No. 07-16 for pacca brick work in Third 100 Sft 786.63 810.83 m2 84.64 87.24
floor
07-17-d Add extra on item No. 07-16 for pacca brick work in 100 Sft 1,290.38 1,324.26 m2 138.84 142.49
Fourth & subsequent floors.
07-18-a Perf. pacca brick wall 1 brick thick in ground floor : Mud 100 Sft 1,745.61 4,838.67 m2 187.83 520.64
mortar
07-18-b-01 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 7,037.71 m2 241.03 757.26
Cement, sand mortar 1:2
07-18-b-02 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 6,614.59 m2 241.03 711.73
Cement, sand mortar 1:3
07-18-b-03 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 6,360.71 m2 241.03 684.41
Cement, sand mortar 1:4
07-18-b-04 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 6,191.47 m2 241.03 666.20
Cement, sand mortar 1:5
07-18-b-05 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 6,072.49 m2 241.03 653.40
Cement, sand mortar 1:6
07-18-b-06 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 5,979.96 m2 241.03 643.44
Cement, sand mortar 1:7
07-18-b-07 Perf. pacca brick wall 1 brick thick in ground floor : 100 Sft 2,240.06 5,908.00 m2 241.03 635.70
Cement, sand mortar 1:8
07-18-c-01 Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 6,181.63 m2 241.03 665.14
cement, sand mortar 1:1:6
07-18-c-02 Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 6,088.06 m2 241.03 655.08
cement, sand mortar 1:1:7
07-18-c-03 Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 6,022.32 m2 241.03 648.00
cement, sand mortar 1:1:8
07-18-c-04 Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 5,954.37 m2 241.03 640.69
cement, sand mortar 1:1:9
07-18-c-05 Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 5,908.99 m2 241.03 635.81
cement, sand mortar 1:1:10
07-18-d Perf. pacca brick wall 1 brick thick in ground floor : Lime, 100 Sft 2,240.06 5,784.18 m2 241.03 622.38
sand mortar 1:2
07-19-a Add extra on item No. 07-18 for perf. pacca brick work in 100 Sft 321.16 321.16 m2 34.56 34.56
First floor
07-19-b Add extra on item No. 07-18 for perf. pacca brick work in 100 Sft 999.75 999.75 m2 107.57 107.57
Second floor
07-19-c Add extra on item No. 07-18 for perf. pacca brick work in 100 Sft 1,790.25 1,790.25 m2 192.63 192.63
Third floor
NWFP CSR 2008 - Approved 25-Aug-2008 Page 32 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-19-d Add extra on item No. 07-18 for perf. pacca brck work in 100 Sft 2,580.75 2,580.75 m2 277.69 277.69
Fourth & subsequent floors
07-20-a Fire brick masonry in fire-clay mortar Upto 20 ft. height 100 Cft 3,022.50 14,336.00 m3 1,067.39 5,062.72
including all charges
07-20-b Fire brick masonry in fire-clay mortar. Extra for every 5 ft. 100 Cft 426.25 474.65 m3 150.53 167.62
additional height, or part thereof
07-21-a 1st class brick wall laid in 1:3 c/s mortar reinfd 4.5" thick 100 Sft 1,046.96 4,436.14 m2 112.65 477.33
wall with hoop iron bonding 6" apart
07-21-b 1st class brick wall laid in 1:3 c/s mortar reinfd 4.5" thick 100 Sft 1,046.96 4,429.59 m2 112.65 476.62
wall with hoop iron bonding 12" apart
07-21-c 1st class brick wall laid in 1:3 c/s mortar reinfd 3" thick 100 Sft 816.01 3,160.33 m2 87.80 340.05
wall with hoop iron bonding 6" apart
07-21-d 1st class brick wall laid in 1:3 c/s mortar reinfd 3" thick 100 Sft 835.45 3,173.21 m2 89.89 341.44
wall with hoop iron banding 12" apart
07-22 Ghilafi work (1.5 brick thick wall) 100 Cft 3,286.00 7,983.52 m3 1,160.44 2,819.36
07-23 Dry brick pitching 100 Cft 1,147.00 7,063.90 m3 405.06 2,494.60
07-24 Sun dried bricks in mud mortar 100 Cft 1,929.75 5,308.67 m3 681.49 1,874.74
07-25 Pise wall (mud walling) 100 Cft 868.00 1,890.45 m3 306.53 667.61
07-26-a Eave brick moulded in 1:3 c/s mortar 3" thick drip course 100 Rft 1,588.75 3,477.86 m 52.12 114.10
cornice
07-26-b Eave brick moulded in 1:3 c/s mortar 4.5" thick drip course 100 Rft 1,805.75 4,406.65 m 59.24 144.57
cornice
07-26-c Eave brick moulded in 1:3 c/s mortar 4.5" thick eave brick 100 Rft 1,526.75 4,165.09 m 50.09 136.65
with back brick
07-27-a Laying dressed or moulded brick cornices in c/s mortar, 100 Rft 1,805.75 2,880.23 m 59.24 94.50
plaster or paint (1 brick)
07-27-b Laying dressed or moulded brick cornices c/s mortar, 100 Rft 2,673.75 5,984.31 m 87.72 196.34
plaster or paint (2 brick)
07-27-c Laying dressed or moulded brick cornices c/s mortar, 100 Rft 3,564.07 9,234.13 m 116.93 302.96
plaster or paint (3 brick)
07-27-d Laying dressed or moulded brick cornices c/s mortar, 100 Rft 4,479.50 12,389.57 m 146.97 406.48
plaster or paint (4 brick)
07-28 Cleaning bricks dismantled from kacha pacca masonry 1000 No. 279.00 279.00 1000 No. 279.00 279.00
07-29 Scraping bricks dismantled from pacca masonry 1000 No. 589.00 589.00 1000 No. 589.00 589.00
07-30 Supplying and filling sand under floor or plugging in wells 100 Cft 88.13 1,186.21 m3 31.12 418.91
07-31 Provide & lay 2" thick & 15" projected tile band, laid in 100 Rft 4,371.00 5,053.44 m 143.41 165.80
1:2 c/s mortar
07-32-a First class brick tiles clad by laying tiles in stretcher course, 100 Sft 1,176.45 3,711.40 m2 126.59 399.35 This item is to be
in cement sand mortar 1:3 executed only on the
written orders of
Superintending
Engineer.
NWFP CSR 2008 - Approved 25-Aug-2008 Page 33 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-32-b First class brick tiles clad by laying tiles in stretcher course, 100 Sft 1,176.45 3,542.21 m2 126.59 381.14
in cement sand mortar 1:4
07-33 Chamfering sides of head regulators and masonry walls to 100 Sft 3,468.53 3,468.53 m2 373.21 373.21
increase width
07-34 Replacing kallar eaten bricks Each 17.36 21.59 Each 17.36 21.59
07-35 Repairing corners of bridges & other hydraulic masonry Each 217.00 217.00 Each 217.00 217.00
works
07-36 Extra labour for drains of bath rooms etc 100 Rft 2,592.72 2,592.72 m 85.06 85.06 Payable in addition to
brickwork
07-37 Maroo corners Each 112.84 112.84 Each 112.84 112.84 Payable in addition to
brickwork
07-38-a Masonry with Facing/Machine/Special Bricks in cement 100Cft 3,099.07 15,211.27 m3 1,094.43 5,371.81
sand mortar 1:2 upto 10 ft. height
07-38-b Masonry using Facing/Machine/Special bricks in cement 100Cft 3,029.32 14,295.28 m3 1,069.80 5,048.34
sand mortar 1:3 upto 10 ft. height
07-38-c Masonry using Facing/Machine/Special bricks in cement 100Cft 3,029.32 13,787.43 m3 1,069.80 4,868.99
sand mortar 1:4 upto 10 ft. height
07-39 Add extra on Item 07-38 for every 10 ft additional height 100Cft 152.05 158.35 m3 53.70 55.92
or part thereof
07-40 Masonry with Machine/Special Bricks in 1:3 c/s mortar in 100Cft 5,333.55 17,797.64 m3 1,883.53 6,285.18
circular core wall of Overhead Reservoir
07-41-a Hollow Block Masonry in walls upto 20 feet height in 1:2 100Cft 1,581.00 10,622.72 m3 558.33 3,751.38
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-41-b Hollow Block Masonry in walls upto 20 feet height in 1:3 100Cft 1,581.00 10,202.10 m3 558.33 3,602.84
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-41-c Hollow Block Masonry in walls upto 20 feet height in 1:4 100Cft 1,581.00 9,945.73 m3 558.33 3,512.30
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of
1900 psi.
07-41-d Hollow Block Masonry in walls upto 20 feet height in 1:5 100Cft 1,581.00 9,776.48 m3 558.33 3,452.53
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-41-e Hollow Block Masonry in walls upto 20 feet height in 1:6 100Cft 1,581.00 9,671.57 m3 558.33 3,415.49
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 34 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-41-f Hollow Block Masonry in walls upto 20 feet height in 1:7 100Cft 1,581.00 9,566.67 m3 558.33 3,378.44
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-41-g Hollow Block Masonry in walls upto 20 feet height in 1:8 100Cft 1,581.00 9,492.62 m3 558.33 3,352.29
cement sand mortar using Hollow Block 16"x8"x8" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-a Hollow Block Masonry in walls upto 20 feet height in 1:2 100Cft 1,829.31 12,479.73 m3 646.02 4,407.18
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-b Hollow Block Masonry in walls upto 20 feet height in 1:3 100Cft 1,829.31 11,971.98 m3 646.02 4,227.87
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-c Hollow Block Masonry in walls upto 20 feet height in 1:4 100Cft 1,829.31 11,667.34 m3 646.02 4,120.29
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-d Hollow Block Masonry in walls upto 20 feet height in 1:5 100Cft 1,829.31 11,464.24 m3 646.02 4,048.56
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of
1900 psi.
07-42-e Hollow Block Masonry in walls upto 20 feet height in 1:6 100Cft 1,829.31 11,320.13 m3 646.02 3,997.67
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-f Hollow Block Masonry in walls upto 20 feet height in 1:7 100Cft 1,829.31 11,211.86 m3 646.02 3,959.43
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-42-g Hollow Block Masonry in walls upto 20 feet height in 1:8 100Cft 1,829.31 11,125.74 m3 646.02 3,929.02
cement sand mortar using Hollow Block 16"x8"x6" factory
manufactured with 1.5" wall thickness and strenght of 1900
psi.
07-43-a Hollow Block Masonry in walls upto 20 feet height in 1:2 100Cft 2,113.27 15,179.46 m3 746.29 5,360.58
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 35 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-43-b Hollow Block Masonry in walls upto 20 feet height in 1:3 100Cft 2,113.27 14,587.58 m3 746.29 5,151.56
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-43-c Hollow Block Masonry in walls upto 20 feet height in 1:4 100Cft 2,113.27 14,231.66 m3 746.29 5,025.87
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-43-d Hollow Block Masonry in walls upto 20 feet height in 1:5 100Cft 2,113.27 13,994.71 m3 746.29 4,942.19
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-43-e Hollow Block Masonry in walls upto 20 feet height in 1:6 100Cft 2,113.27 13,829.82 m3 746.29 4,883.96
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-43-f Hollow Block Masonry in walls upto 20 feet height in 1:7 100Cft 2,113.27 13,700.77 m3 746.29 4,838.39
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-43-g Hollow Block Masonry in walls upto 20 feet height in 1:8 100Cft 2,113.27 13,597.23 m3 746.29 4,801.82
cement sand mortar using Hollow Block 16"x8"x4" factory
manufactured with 1.25" wall thickness and strenght of
1900 psi.
07-44-a Solid Block Masonry in walls upto 20 feet height in 1:2 100Cft 1,581.00 11,034.13 m3 558.33 3,896.67
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-44-b Solid Block Masonry in walls upto 20 feet height in 1:3 100Cft 1,581.00 10,613.50 m3 558.33 3,748.13
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-44-c Solid Block Masonry in walls upto 20 feet height in 1:4 100Cft 1,581.00 10,357.13 m3 558.33 3,657.59
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-44-d Solid Block Masonry in walls upto 20 feet height in 1:5 100Cft 1,581.00 10,187.88 m3 558.33 3,597.82
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-44-e Solid Block Masonry in walls upto 20 feet height in 1:6 100Cft 1,581.00 10,082.97 m3 558.33 3,560.77
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-44-f Solid Block Masonry in walls upto 20 feet height in 1:7 100Cft 1,581.00 9,978.07 m3 558.33 3,523.72
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 36 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-44-g Solid Block Masonry in walls upto 20 feet height in 1:8 100Cft 1,581.00 9,904.02 m3 558.33 3,497.57
cement sand mortar using 16"x8"x8" factory manufactured
solid blocks with strength of 2100 psi.
07-45-a Solid Block Masonry in walls upto 20 feet height in 1:2 100Cft 1,829.31 13,024.23 m3 646.02 4,599.47
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-b Solid Block Masonry in walls upto 20 feet height in 1:3 100Cft 1,829.31 12,516.48 m3 646.02 4,420.16
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-c Solid Block Masonry in walls upto 20 feet height in 1:4 100Cft 1,829.31 12,211.84 m3 646.02 4,312.57
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-d Solid Block Masonry in walls upto 20 feet height in 1:5 100Cft 1,829.31 12,008.74 m3 646.02 4,240.85
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-e Solid Block Masonry in walls upto 20 feet height in 1:6 100Cft 1,829.31 11,864.63 m3 646.02 4,189.96
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-f Solid Block Masonry in walls upto 20 feet height in 1:7 100Cft 1,829.31 11,756.36 m3 646.02 4,151.72
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-45-g Solid Block Masonry in walls upto 20 feet height in 1:8 100Cft 1,829.31 11,670.24 m3 646.02 4,121.31
cement sand mortar using 16"x8"x6" factory manufactured
solid blocks with strength of 1900 psi.
07-46-a Solid Block Masonry in walls upto 20 feet height in 1:2 100Cft 2,113.27 15,956.28 m3 746.29 5,634.91
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.
07-46-b Solid Block Masonry in walls upto 20 feet height in 1:3 100Cft 2,113.27 15,364.40 m3 746.29 5,425.89
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.
07-46-c Solid Block Masonry in walls upto 20 feet height in 1:4 100Cft 2,113.27 15,008.48 m3 746.29 5,300.20
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.
07-46-d Solid Block Masonry in walls upto 20 feet height in 1:5 100Cft 2,113.27 14,771.53 m3 746.29 5,216.52
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.
07-46-e Solid Block Masonry in walls upto 20 feet height in 1:6 100Cft 2,113.27 14,606.64 m3 746.29 5,158.29
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.
07-46-f Solid Block Masonry in walls upto 20 feet height in 1:7 100Cft 2,113.27 14,477.59 m3 746.29 5,112.72
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 37 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 07 BRICK MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
07-46-g Solid Block Masonry in walls upto 20 feet height in 1:8 100Cft 2,113.27 14,374.05 m3 746.29 5,076.15
cement sand mortar using 16"x8"x4" factory manufactured
solid blocks with strength of 1800 psi.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 38 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 08 STONE MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
08-01-a Random rubble masonry in foundn. & plinth Dry masonry. 100 Cft 2,015.00 4,519.70 m3 711.59 1,596.12
08-01-b Random rubble masonry in foundn. & plinth in mud mortar 100 Cft 2,518.75 5,390.99 m3 889.49 1,903.81
08-01-c-01 Random rubble masonry (Un coursed) in foundn. & plinth 100 Cft 3,890.50 7,965.17 m3 1,373.92 2,812.88
in lime, sand mortar 1:2
08-01-c-02 Random rubble masonry (Un coursed) in foundn. & plinth 100 Cft 3,890.50 7,892.58 m3 1,373.92 2,787.24
in lime, sand mortar, Surkhi Ratio 1:1:1
08-01-c-03 Random rubble masonry (Un coursed) in foundn. & plinth 100 Cft 3,890.50 7,819.98 m3 1,373.92 2,761.60
in lime, Surkhi Ratio 1:2
08-01-d-01 Random rubble masonry in foundn. & plinth in cement, 100 Cft 3,890.50 10,652.51 m3 1,373.92 3,761.90
sand mortar : Ratio 1:3
08-01-d-02 Random rubble masonry in foundn. & plinth in cement, 100 Cft 3,890.50 9,890.89 m3 1,373.92 3,492.94
sand mortar : Ratio 1:4
08-01-d-03 Random rubble masonry in foundn. & plinth in cement, 100 Cft 3,890.50 9,019.21 m3 1,373.92 3,185.11
sand mortar : Ratio 1:6
08-01-d-04 Random rubble masonry in foundn. & plinth in cement, 100 Cft 3,890.50 8,536.90 m3 1,373.92 3,014.78
sand mortar : Ratio 1:8
08-02-a Coursed rubble masonry in foundn. & plinth dry masonry. 100 Cft 2,604.00 5,108.70 m3 919.59 1,804.12
08-02-b Coursed rubble masonry in foundn. & plinth in mud mortar 100 Cft 3,611.50 6,483.74 m3 1,275.39 2,289.71
08-02-c-01 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 8,301.56 m3 1,554.55 2,931.67
plinth in lime, sand mortar 1:2
08-02-c-02 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 8,481.97 m3 1,554.55 2,995.38
plinth in lime, sand mortar, Surkhi Ratio 1:1:1
08-02-c-03 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 8,417.50 m3 1,554.55 2,972.62
plinth in lime, Surkhi Ratio 1:2
08-02-d-01 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 10,936.00 m3 1,554.55 3,862.02
plinth in cement,sand mortar : Ratio 1:3
08-02-d-02 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 10,259.00 m3 1,554.55 3,622.94
plinth in cement,sand mortar : Ratio 1:4
08-02-d-03 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 9,481.82 m3 1,554.55 3,348.48
plinth in cement,sand mortar : Ratio 1:6
08-02-d-04 Coursed rubble masonry (Hammer Dressed) in foundn. & 100 Cft 4,402.00 9,057.84 m3 1,554.55 3,198.75
plinth in cement,sand mortar : Ratio 1:8
08-03-a Random rubble masonry in ground floor Dry masonry. 100 Cft 2,309.50 4,814.20 m3 815.59 1,700.12
08-03-b Random rubble masonry in ground floor in mud mortar 100 Cft 3,022.50 5,881.13 m3 1,067.39 2,076.90
08-03-c-01 Random rubble masonry in ground floor in lime, sand 100 Cft 4,254.75 8,329.42 m3 1,502.55 2,941.51
mortar 1:2
08-03-c-02 Random rubble masonry in ground floor in lime, sand 100 Cft 4,254.75 8,256.83 m3 1,502.55 2,915.87
mortar, Surkhi Ratio 1:1:1
08-03-c-03 Random rubble masonry in ground floor in lime, Surkhi 100 Cft 4,254.75 8,184.23 m3 1,502.55 2,890.23
Ratio 1:2
08-03-d-01 Random rubble masonry in ground floor in cement,sand 100 Cft 4,254.75 11,016.76 m3 1,502.55 3,890.54
mortar : Ratio 1:3
NWFP CSR 2008 - Approved 25-Aug-2008 Page 39 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 08 STONE MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
08-03-d-02 Random rubble masonry in ground floor in cement,sand 100 Cft 4,254.75 10,255.14 m3 1,502.55 3,621.57
mortar : Ratio 1:4
08-03-d-03 Random rubble masonry in ground floor in cement,sand 100 Cft 4,254.75 9,383.46 m3 1,502.55 3,313.74
mortar : Ratio 1:6
08-03-d-04 Random rubble masonry in ground floor in cement,sand 100 Cft 4,254.75 8,901.15 m3 1,502.55 3,143.41
mortar : Ratio 1:8
08-04-a Coursed rubble masonry in ground floor Dry masonry. 100 Cft 3,038.00 5,542.70 m3 1,072.86 1,957.39
08-04-b Coursed rubble masonry in ground floor in mud mortar 100 Cft 4,774.00 7,632.63 m3 1,685.92 2,695.44
08-04-c-01 Coursed rubble masonry in ground floor in lime, sand 100 Cft 4,983.25 8,881.81 m3 1,759.82 3,136.59
mortar 1:2
08-04-c-02 Coursed rubble masonry in ground floor in lime, sand 100 Cft 4,983.25 9,063.22 m3 1,759.82 3,200.65
mortar, Surkhi Ratio 1:1:1
08-04-c-03 Coursed rubble masonry in ground floor in lime, Surkhi 100 Cft 4,983.25 8,998.24 m3 1,759.82 3,177.70
Ratio 1:2
08-04-d-01 Coursed rubble masonry in ground floor in cement,sand 100 Cft 4,983.25 11,517.25 m3 1,759.82 4,067.28
mortar : Ratio 1:3
08-04-d-02 Coursed rubble masonry in ground floor in cement,sand 100 Cft 4,983.25 10,840.25 m3 1,759.82 3,828.20
mortar : Ratio 1:4
08-04-d-03 Coursed rubble masonry in ground floor in cement,sand 100 Cft 4,983.25 10,065.07 m3 1,759.82 3,554.45
mortar : Ratio 1:6
08-04-d-04 Coursed rubble masonry in ground floor in cement,sand 100 Cft 4,983.25 9,649.07 m3 1,759.82 3,407.54
mortar : Ratio 1:8
08-05-a-01 Ashlar block masonry in ground floor in lime, sand mortar 100 Cft 13,950.00 19,992.76 m3 4,926.40 7,060.38
1:2
08-05-a-02 Ashlar block masonry in ground floor in lime, sand mortar, 100 Cft 13,950.00 19,944.36 m3 4,926.40 7,043.29
Surkhi Ratio 1:1:1
08-05-a-03 Ashlar block masonry in ground floor in lime, Surkhi 100 Cft 13,950.00 19,895.96 m3 4,926.40 7,026.20
Ratio 1:2
08-05-b-01 Ashlar block masonry in ground floor in cement,sand 100 Cft 13,950.00 21,784.32 m3 4,926.40 7,693.07
mortar : Ratio 1:3
08-05-b-02 Ashlar block masonry in ground floor in cement,sand 100 Cft 13,950.00 21,276.57 m3 4,926.40 7,513.76
mortar : Ratio 1:4
08-05-b-03 Ashlar block masonry in ground floor in cement,sand 100 Cft 13,950.00 20,701.13 m3 4,926.40 7,310.54
mortar : Ratio 1:6
08-06-a-01 Ashlar fine masonry in ground floor in lime, sand mortar 100 Cft 27,373.00 34,512.51 m3 9,666.69 12,187.99
1:2
08-06-a-02 Ashlar fine masonry in ground floor in lime, sand mortar, 100 Cft 27,373.00 34,488.31 m3 9,666.69 12,179.44
Surkhi Ratio 1:1:1
08-06-a-03 Ashlar fine masonry in ground floor in lime, Surkhi Ratio 100 Cft 27,373.00 34,464.11 m3 9,666.69 12,170.90
1:2
08-06-b-01 Ashlar fine masonry in ground floor in cement,sand mortar 100 Cft 27,373.00 35,408.29 m3 9,666.69 12,504.33
: Ratio 1:3
NWFP CSR 2008 - Approved 25-Aug-2008 Page 40 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 08 STONE MASONRY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
08-06-b-02 Ashlar fine masonry in ground floor in cement,sand mortar 100 Cft 27,373.00 35,154.41 m3 9,666.69 12,414.67
: Ratio 1:4
08-06-b-03 Ashlar fine masonry in ground floor in cement,sand mortar 100 Cft 27,373.00 34,870.95 m3 9,666.69 12,314.57
: Ratio 1:6
08-07-a Extra labour on items 08-03-a-01 to 08-06-b-03 for work in 100 Cft 612.25 612.25 m3 216.21 216.21
First floor
08-07-b Extra labour on items 08-03-a-01 to 08-06-b-03 for work in 100 Cft 1,432.20 1,432.20 m3 505.78 505.78
Second floor
08-07-c Extra labour on items 08-03-a-01 to 08-06-b-03 for work in 100 Cft 2,266.10 2,266.10 m3 800.27 800.27
Third floor
08-07-d Extra labour on items 08-03-a-01 to 08-06-b-03 for work in 100 Cft 3,623.90 3,623.90 m3 1,279.77 1,279.77
Fourth & subsequent floors
08-08 Extra labour on items 08-03-a-01 to 08-06-b-03 for every 100 Cft 573.50 573.50 m3 202.53 202.53
5' additional height, other than building
08-09 Extra labour for arch work in stone masonry including 100 Cft 2,294.00 2,294.00 m3 810.12 810.12
centring & decentring etc.
08-10-a Extra labour for coping & caps etc 100 Cft 11,780.00 11,780.00 m3 4,160.07 4,160.07
08-10-b Extra labour for cornice & string course 100 Cft 11,780.00 11,780.00 m3 4,160.07 4,160.07
08-11-a Dressing stones : Hammer dressed 100 Sft 3,642.50 3,642.50 m2 391.93 391.93 a) This rate of
dressing shall be paid
only when supply of
undressed stone is
made
08-11-b Dressing stones : Rough tooled dressed 100 Sft 7,006.00 7,006.00 m2 753.85 753.85 b) In case of masonry,
dressing is already
included and this rate
shall not be added
thereto
08-11-c Dressing stones : Chisel dressed 100 Sft 8,463.00 8,463.00 m2 910.62 910.62 c) Only dressed
surface of stone shall
be measured
08-11-d Dressing stones : Fine dressed 100 Sft 18,476.00 18,476.00 m2 1,988.02 1,988.02
08-12 Dhajji walling 5"x5" thick deodar framing with stone laid 100 Sft 5,468.40 11,599.46 m2 588.40 1,248.10
in 1:6 c/s mortar & 1:4 c/s plaster
08-13 Provide & fix stone blocks from 2 cft. to 6 cft. each, 100 Cft 19,251.00 21,864.60 m3 6,798.43 7,721.42
including lift upto 20 ft.
08-14 Providing and fixing stone blocks, under 2 cft. each, 100 Cft 9,517.00 12,130.60 m3 3,360.90 4,283.88
including lift upto 20 ft.
08-15 Provide & lay stone/boulder dry hand packed as filling 100 Cft 589.00 3,529.30 m3 208.00 1,246.36
behind retaining walls or in pitching

NWFP CSR 2008 - Approved 25-Aug-2008 Page 41 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 09 ROOFING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
09-01 First class tile roofing including earth, mud plaster, gobri 100 Sft 4,172.60 8,973.98 m2 448.97 965.60 Add extra 13%, 32%
leeping, cement plaster etc complete and 51% on labour
rates only are 6%,
15% and 23% on
composite rates for
2nd, 3rd, 4th and
subsequent floors
respectively.
09-02 Second class tile roofing consisting of 4" earth and 1" mud 100 Sft 3,146.50 6,924.95 m2 338.56 745.12 ditto
plaster with gobri leeping etc
09-03 Covering mud roof with coal tar and fine sand 100 Sft 140.43 565.00 m2 15.11 60.79 ditto
09-04-a Filling spaces in between wooden battens over beams, 100 Sft 434.00 2,017.89 m2 46.70 217.12 ditto
filled with deodar wood pieces
09-04-b Filling spaces in between RCC battens, filled with PCC 100 Sft 609.77 886.26 m2 65.61 95.36
block 1:3:6
09-04-c Filling spaces in between spacers filled with bricks 100 Sft 175.46 463.14 m2 18.88 49.83
09-05 Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1" 100 Sft 1,294.25 4,921.19 m2 139.26 529.52 Add extra 13%, 32%
mud plaster on top of RC roof slab and 51% on labour
rates only are 6%,
15% and 23% on
composite rates for
2nd, 3rd, 4th and
subsequent floors
respectively.
09-06-a Jack arch roof 4.5" thick laid in 1:5 c/s mortar a) cement 100 Sft 4,588.00 11,256.83 m2 493.67 1,211.23 a) For steel part and
concrete in haunches 1:6:12 its erection etc. Item
No 25-10 and 25-14
be reffered b) Add
extra 13%, 32% and
51% on labour rates
only are 6%, 15% and
23% on composite
rates for 2nd, 3rd, 4th
and subsequent floors
respectively.
09-06-b Jack arch roof 4.5" thick laid in 1:5 c/s mortar b) cement 100 Sft 4,588.00 12,253.33 m2 493.67 1,318.46
concrete in haunches 1:3:6

NWFP CSR 2008 - Approved 25-Aug-2008 Page 42 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 09 ROOFING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
09-07-a Jack arch roofing 4.5"thick laid in 1:5 c/s mortar complete. 100 Sft 3,727.75 10,105.32 m2 401.11 1,087.33 a) For steel part and
Cement concrete in haunches 1:6:12 its erection etc. Item
No 25-10 and 25-14
be reffered b) Add
extra 13%, 32% and
51% on labour rates
only are 6%, 15% and
23% on composite
rates for 2nd, 3rd, 4th
and subsequent floors
respectively.
09-07-b Jack arch roofing 4.5"thick laid in 1:5 cement mortar, 100 Sft 3,727.75 11,012.40 m2 401.11 1,184.93
including complete. Cement concrete in haunches 1:3:6
09-08 Extra for vaulted jack arch roofing 100 Sft 1,178.00 1,178.00 m2 126.75 126.75 ditto
09-09 Jack arch roofing of shingle & cement concrete 1:3:6, 4.5" 100 Sft 3,673.50 7,254.86 m2 395.27 780.62
at crown & 1/2" cem. plaster complete
09-10-a Earth filling over roof including watering, ramming etc 3" 100 Sft 383.16 951.63 m2 41.23 102.40 Add extra 13%, 32%
thick earth filling and 1" mud plaster and 51% on labour
rates only are 6%,
15% and 23% on
composite rates for
2nd, 3rd, 4th and
subsequent floors
respectively.
09-10-b Earth filling over roof including watering, ramming etc 4" 100 Sft 399.90 1,047.02 m2 43.03 112.66
thick earth filling and 1" mud plaster
09-11 1/8" thick gobri leeping on roofs or floors 100 Sft 87.42 111.70 m2 9.41 12.02 ditto
09-12 2 coats of bitumen laid hot using 34 lbs. for %sft over roof 100 Sft 279.00 1,092.45 m2 30.02 117.55
& blinded with sand at 1 cft per % sft
09-13-a Supply & fix corrugated GI sheet with GI bolts, nuts, 100 Sft 868.00 10,389.73 m2 93.40 1,117.93 Add extra 13%, 32%
limpet etc. complete : 20 BWG and 51% on labour
rates only are 6%,
15% and 23% on
composite rates for
2nd, 3rd, 4th and
subsequent floors
respectively.
09-13-b Supply & fix corrugated GI sheet with GI bolts, nuts, 100 Sft 868.00 9,111.97 m2 93.40 980.45
limpet etc. complete : 22 BWG
09-13-c Supply & fix corrugated GI sheet with GI bolts, nuts, 100 Sft 868.00 7,674.49 m2 93.40 825.78
limpet etc. complete : 24 BWG
09-14 Khassi parnalas in c/s mortar 1:2, 12" outside width Rft 50.56 69.90 m 165.87 229.33 ditto
finished smooth with a floating coat
09-15 Khuras on roof 2'x2'x6" Each 187.55 358.46 Each 187.55 358.46 ditto

NWFP CSR 2008 - Approved 25-Aug-2008 Page 43 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 09 ROOFING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
09-16 Bottom khuras of brick masonry in c/s mortar Each 187.55 571.97 Each 187.55 571.97 ditto
1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8
09-17-a Plain GI sheets 22 SWG rain water down pipe a) 4" Rft 41.59 113.40 m 136.43 372.06 ditto
diameter down pipe
09-17-b Plain GI sheets 22 SWG rain water down pipe b) 5" Rft 41.59 127.77 m 136.43 419.19
diameter down pipe
09-18 Plain galvanized iron sheet flashing, 22 guage 100 Sft 5,537.36 9,426.34 m2 595.82 1,014.27 ditto
09-19-a Cast iron rain water down pipe fixed in position excluding Rft 29.42 321.12 m 96.53 1,053.54 ditto
heads & shoes : 4" dia
09-19-b Cast iron rain water down pipe fixed in position excluding Rft 29.42 407.39 m 96.53 1,336.59
heads & shoes : 3" dia
09-20 Heads for cast iron rain water down pipe fixed in place Each 122.76 500.35 Each 122.76 500.35 ditto
including cost of clamp holdfast and painting
09-21 Shoes, bends or offsets for cast iron ran water down pipe, Each 68.20 445.79 Each 68.20 445.79 ditto
including fixing & painting
09-22 Plain GI sheet spouts fixed in position, including paint Each 145.70 287.54 Each 145.70 287.54 ditto
09-23 Laying 1/2" thick deodar ceiling complete, including 100 Sft 3,193.00 15,486.60 m2 343.57 1,666.36 ditto
sawing, planing & fixing
09-24-a Flat sheet roof with GI plain sheets, including batten rolls, 100 Sft 2,235.88 10,503.20 m2 240.58 1,130.14
screws, clips etc : 22 BWG
09-24-b Flat sheet roof with GI plain sheets, including batten rolls, 100 Sft 2,235.88 9,598.22 m2 240.58 1,032.77
screws, clips etc : 24 BWG
09-25 Asbestos cement corrugated sheet roofing including 100 Sft 1,147.00 13,996.59 m2 123.42 1,506.03
overlaps, GI hooks, bolts, nuts etc
09-26 Extra labour for erection of GI sheets, flat sheet or asbestos 100 Sft 189.10 189.10 m2 20.35 20.35
sheet roofing above 20' height
09-27 Fixing asbestos cement sheet ridges and valleys 1/4" thick 100 RFT 1,441.50 7,595.56 m 47.29 249.20
09-28-a Plain GI sheet ridging including fixture complete 6" lap & Rft 52.93 358.72 m 173.64 1,176.89
18" overall of 22 gauge GI sheet ridging
09-28-b Plain GI sheet ridging including fixture complete 9" lap & Rft 52.93 351.19 m 173.64 1,152.20
24" overall, of 24 gauge GI sheet ridging
09-28-c Plain GI sheet ridging including fixture complete 12" lap & Rft 52.93 391.12 m 173.64 1,283.21
30 overall, of 22 gauge GI sheet ridging
09-29 Plain 22 gauge GI sheet gutter semi circular 8" diameter Rft 26.46 151.58 m 86.82 497.31
09-30 Fixing water spouse or parnala. Each 217.00 217.00 Each 217.00 217.00
09-31 Making masonry ventilators in c/s mortar 1:4 Each 868.00 1,170.75 Each 868.00 1,170.75
09-32 Making drip course 2"x1/2" under RCC slab edges in outer Rft 6.26 7.25 m 20.53 23.78
opening, in c/s mortar 1:2
09-33 Supply and laying of twin GI sheet 20 SWG painted with 100 Sft 1,745.30 14,026.33 m2 187.79 1,509.23
bitumen & polythene fim complete
09-34-a Provide & lay roof insulation complete with Thermopore Sft 13.22 51.37 m2 142.29 552.79
sheet 1/2" thick
NWFP CSR 2008 - Approved 25-Aug-2008 Page 44 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 09 ROOFING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
09-34-b Provide & lay roof insulation complete with Thermopore Sft 13.22 80.16 m2 142.29 862.56
sheet 3/4" thick
09-34-c Provide & lay roof insulation complete with Thermopore Sft 13.22 92.26 m2 142.29 992.76
sheet 1" thick
09-35 Providing and fixing AC rain water down pipe 4" dia, with Rft 28.67 208.29 m 94.08 683.36
shoe, tee, bend & clamp etc
09-36-a Making jharries in existing brick masonry For slabs upto 6" Rft 15.57 37.02 m 51.07 121.45 Rate shall be
thick increased by 1.5
times for stone
masonry or PCC and
2 times for RCC
09-36-b Making jharries in existing brick masonry For slabs Rft 42.14 45.01 m 138.25 147.67
exceeding 6" to 12" thick
09-37-a Making recess in existing brick masonry a) upto 1.0' height Each 161.20 183.18 Each 161.20 183.18 ditto
of girder or beam
09-37-b Making recess in existing brick masonry b) for every 6" Each 65.88 77.76 Each 65.88 77.76
additional height or part thereof
09-38 Hoisting RS Beams & wooden beams and placing in Each 168.33 168.33 Each 168.33 168.33
position
09-39 Hoisting and placing in position sahl ballies, over roof Each 28.64 28.64 Each 28.64 28.64
09-40-a Hoist precast RCC/pre-stressed conc. battens a) From 5' to Each 23.96 23.96 Each 23.96 23.96
6' long
09-40-b Hoist precast RCC/pre-stressed conc. battens b) Over 6' to Each 35.65 35.65 Each 35.65 35.65
7' long
09-40-c Hoist precast RCC/pre-stressed conc. battens c) Over 7' to Each 47.34 47.34 Each 47.34 47.34
8' long
09-40-d Hoist precast RCC/pre-stressed conc. battens d) Over 8' to Each 57.04 57.04 Each 57.04 57.04
9' long
09-40-e Hoist precast RCC/pre-stressed conc. battens e) Exceeding Each 71.30 71.30 Each 71.30 71.30
9' length
09-41-a Hoisting and placing in position RCC troughs Upto 10' in Each 71.30 71.30 Each 71.30 71.30 Applicable only to
length roof troughs (inverted
tees and trough) for
heights of first storey
only
09-41-b Hoisting and placing in position RCC troughs Upto 11' in Each 95.26 95.26 Each 95.26 95.26
length
09-41-c Hoisting and placing in position RCC troughs Upto 12' in Each 118.64 118.64 Each 118.64 118.64
length
09-41-d Hoisting and placing in position RCC troughs Upto 13' in Each 128.90 128.90 Each 128.90 128.90
length
09-41-e Hoisting and placing in position RCC troughs Upto 14' in Each 142.60 142.60 Each 142.60 142.60
length
NWFP CSR 2008 - Approved 25-Aug-2008 Page 45 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 09 ROOFING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
09-41-f Hoisting and placing in position RCC troughs Upto 15' in Each 156.86 156.86 Each 156.86 156.86
length
09-41-g Hoisting and placing in position RCC troughs Upto 16' in Each 178.25 178.25 Each 178.25 178.25
length
09-41-h Hoisting and placing in position RCC troughs Upto 17' in Each 203.05 203.05 Each 203.05 203.05
length
09-41-i Hoisting and placing in position RCC troughs Upto 18' in Each 237.86 237.86 Each 237.86 237.86
length
09-41-j Hoisting and placing in position RCC troughs Upto 19' in Each 285.20 285.20 Each 285.20 285.20
length
09-41-k Hoisting and placing in position RCC troughs Upto 20' in Each 356.50 356.50 Each 356.50 356.50
length
09-42-a Hoist & place in position RCC inverted battens Upto 10' Each 56.54 56.54 Each 56.54 56.54
span
09-42-b Hoist & place in position RCC inverted battens Upto 12' Each 113.09 113.09 Each 113.09 113.09
span
09-42-c Hoist & place in position RCC inverted battens Upto 13' Each 141.79 141.79 Each 141.79 141.79
span
09-42-d Hoist & place in position RCC inverted battens Upto 14' Each 170.50 170.50 Each 170.50 170.50
span
09-42-e Hoist & place in position RCC inverted battens Upto 15' Each 187.55 187.55 Each 187.55 187.55
span
09-42-f Hoist & place in position RCC inverted battens Upto 16' Each 213.13 213.13 Each 213.13 213.13
span
09-42-g Hoist & place in position RCC inverted battens Upto 18' Each 284.73 284.73 Each 284.73 284.73
span
09-42-h Hoist & place in position RCC inverted battens Upto 20' Each 426.25 426.25 Each 426.25 426.25
span
09-43 RCC spout including fixing in position, with top and Each 303.80 482.58 Each 303.80 482.58
bottom khuras
09-44 P/F Burnt Brick Tile Roofing over Tee Iron and Steel 100 Sft 2,781.37 25,464.41 m2 299.27 2,739.97
Girder, in 1:6 c/s mortar (12' max span)
09-45 Providing and Laying Prestressed Roof of Slab/Girder, 2" Sft 24.49 156.59 m2 263.50 1,684.93
thick PCC 1:2:4 with chicken mesh, polythene, mud, tar

NWFP CSR 2008 - Approved 25-Aug-2008 Page 46 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-01 Laying murum flooring complete as per specs 100 Sft 1,271.00 4,610.60 m2 136.76 496.10
10-02 Earth flooring 6" thick consolidated layer of moistened 100 Sft 422.38 994.10 m2 45.45 106.97
earth, including ramming
10-03-a Provide, lay, water & ram clean coarse sand under floor / 100 Cft 1,665.85 2,018.73 m3 588.29 712.91
brick paving, complete
10-03-b Provide, lay, water & ram brick ballast 1.5" to 2" guage 100 Cft 3,333.09 6,226.97 m3 1,177.07 2,199.04
mixed with 25% sand for floor foundations
10-04 Mud floor of 6" thick consolidated layer of moist earth & 100 Sft 806.00 1,690.28 m2 86.73 181.87
finished off with 1" mud plaster
10-05 Dry brick paving laid flat,sand grouted, including prep. of 100 Sft 587.45 2,166.80 m2 63.21 233.15
bed, by 1/2" thick mud plaster
10-06 Dry brick on edge paving, sand grouted, including prep. of 100 Sft 829.56 3,160.02 m2 89.26 340.02
bed, by 1/2" thick mud plaster
10-07 Grouting 4.5" dry brick work with cement sand mortar 1:5 100 Sft 573.50 927.70 m2 61.71 99.82
10-08 Flat brick flooring laid in 1:6 c/s mortar over a bed of 3/4" 100 Sft 999.75 3,156.82 m2 107.57 339.67
thick cement mortar 1:6
10-09 Brick on edge flooring, laid in 1:6 c/s mortar, over a bed of 100 Sft 1,286.50 4,367.10 m2 138.43 469.90
3/4" thick cement mortar 1:6
10-10 Brick tiles (12"x6"x2") laid in 1:6 c/s mortar, over a bed of 100 Sft 999.75 2,837.98 m2 107.57 305.37
3/4" thick c/s mortar 1:6
10-11 Brick tiles (9"x4.5"x1.5") laid flat in 1:3 c/s mortar over a 100 Sft 1,147.00 3,579.34 m2 123.42 385.14
bed of 3/4" thick cement mortar 1:6
10-12 Cement tiles (8"x8"x3/4") laid flat in 1:2 c/s mortar, over 100 Sft 1,533.57 14,369.43 m2 165.01 1,546.15
3/4" thick bed of c/s mortar 1:2
10-13-a Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick 100 Sft 1,533.57 7,835.43 m2 165.01 843.09
bed of c/s mortar 1:2 : 12" x 12" x 1"
10-13-b Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick 100 Sft 1,533.57 6,804.51 m2 165.01 732.17
bed of c/s mortar 1:2 : 9" x 9" x 3/4"
10-13-c Cement concrete tiles laid in 1:2 c/s mortar over 3/4" thick 100 Sft 1,533.57 6,819.03 m2 165.01 733.73
bed of c/s mortar 1:2 : 6" x 6" x 3/4"
10-14 Coloured cement tile (8"x8"x3/4") of dark shade laid flat in 100 Sft 1,533.57 7,109.43 m2 165.01 764.97
1:2 c/s mortar over 3/4" mortar bed
10-15-a Provide & lay topping of concrete 1:2:4, including surface 100 Sft 903.65 1,874.95 m2 97.23 201.74 If glass strips are used
finishing & dividing in panels : 1" thick for paneling, it shall
be paid extra as per
item No. 10-43
10-15-b Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,057.10 2,329.87 m2 113.74 250.69
finishing & dividing in panels: 1.5" thick
10-15-c Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,057.10 2,494.61 m2 113.74 268.42
finishing & dividing in panels: 1.5" thick
10-15-d Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,057.10 2,837.16 m2 113.74 305.28
finishing & dividing in panels : 1.75" thick

NWFP CSR 2008 - Approved 25-Aug-2008 Page 47 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-15-e Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,196.60 3,142.04 m2 128.75 338.08
finishing & dividing in panels : 2" thick
10-15-f Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,736.00 3,963.31 m2 186.79 426.45
finishing & dividing in panels: 2.25" thick
10-15-g Provide & lay topping of concrete 1:2:4, including surface 100 Sft 1,805.75 4,230.19 m2 194.30 455.17
finishing & dividing in panels: 2.5" thick
10-15-h Provide & lay topping of concrete 1:2:4, including surface 100 Sft 2,170.00 4,791.77 m2 233.49 515.59
finishing & dividing in panels: 2.75" thick
10-15-i Provide & lay topping of concrete 1:2:4, including surface 100 Sft 2,022.75 4,893.41 m2 217.65 526.53
finishing & dividing in panels : 3" thick
10-16-a Provide & laying conglomerate floor (two coat work) with 100 Sft 1,906.50 3,215.07 m2 205.14 345.94 ditto
top layer of 1/2" thick wearing surface of one part of
cement 2 parts of stone chips passing 3/16" sieve over
bottom layer of cement concrete (1:3:6) including surface
finishing & dividing in panels: 1.5" thick
10-16-b Provide & laying conglomerate floor (two coat work) with 100 Sft 1,317.50 2,742.15 m2 141.76 295.06
top layer of 1/2" thick wearing surface of one part of
cement 2 parts of stone chips passing 3/16" sieve over
bottom layer of cement concrete (1:3:6) including surface
finishing & dividing in panels: 1.75" thick
10-16-c Provide & laying conglomerate floor (two coat work) with 100 Sft 1,457.00 3,000.56 m2 156.77 322.86
top layer of 1/2" thick wearing surface of one part of
cement 2 parts of stone chips passing 3/16" sieve over
bottom layer of cement concrete (1:3:6) including surface
finishing & dividing in panels : 2" thick
10-17 Add extra in cement concrete floor topping if finished with 100 Sft 434.00 934.46 m2 46.70 100.55
pigment and polishing
10-18 Extra labour for each storey above ground for mosaic, 100 Sft 209.25 209.25 m2 22.52 22.52 Applicable to item No
conglomerate, tiles, stone & wood floor 10-08 to 10-16, 10-19
to 10-25 and 10-30 to
10-35
10-19-a Flag stone flooring in lime mortar 1:2, over 3/4" bedding : 100 Sft 2,605.55 3,870.24 m2 280.36 416.44
2" thick
10-19-b Flag stone flooring in lime mortar 1:2, over 3/4" bedding : 100 Sft 2,429.78 3,959.87 m2 261.44 426.08
3" thick
10-20-a Asphalt floor, including base preparation, remelting, setting 100 Sft 852.50 7,252.37 m2 91.73 780.35
out & finish : 1" thick topping
10-20-b Asphalt floor, including base preparation, remelting, setting 100 Sft 742.45 3,942.38 m2 79.89 424.20
out & finish : 1/2" thick topping
10-20-c Asphalt floor, including base preparation, remelting, setting 100 Sft 520.49 2,122.95 m2 56.00 228.43
out & finish : 1/4" thick topping

NWFP CSR 2008 - Approved 25-Aug-2008 Page 48 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-21-a 1.375" thick mosaic flooring, including rubbing and 100 Sft 3,410.00 5,808.83 m2 366.92 625.03 If glass strips are used
polishing complete : Using grey cement for paneling, it shall
be paid extra as per
item No. 10-43
10-21-b 1.375" thick mosaic flooring, including rubbing and 100 Sft 3,410.00 5,637.58 m2 366.92 606.60
polishing complete : Using white cement
10-22-a 1.5" thick mosaic flooring, including rubbing & polishing 100 Sft 3,493.70 5,765.02 m2 375.92 620.32 ditto
complete : Using grey cement
10-22-b 1.5" thick mosaic flooring, including rubbing & polishing 100 Sft 3,493.70 5,950.15 m2 375.92 640.24
complete : Using white cement
10-23 Laying floor of mosaic marble chips tiles of approved 100 Sft 1,917.35 5,370.63 m2 206.31 577.88
shade including finishing complete
10-24 Lay floor of white glazed tile 1/4" thick in white cement 100 Sft 2,433.50 7,055.58 m2 261.84 759.18
1:2 over 3/4" thick cement mortar 1:2
10-25 Lay floor of approved coloured glazed tiles 1/4" thick laid 100 Sft 2,433.50 7,087.58 m2 261.84 762.62
in white cement & pigment complete
10-26-a Provide & lay marble fine dressed stone flooring on surface 100 Sft 4,898.00 10,709.81 m2 527.02 1,152.38
in white cement complete: 3/4" thick (Badel, Silky black,
Sunny white, Sunny Grey or eq)
10-26-b Provide & lay marble fine dressed stone flooring on surface 100 Sft 4,898.00 13,886.06 m2 527.02 1,494.14
in white cement complete: 1" thick (Badel, Silky black,
Sunny white, Sunny Grey or eq)
10-26-c Provide & lay marble fine dressed stone flooring on surface 100 Sft 4,898.00 9,566.36 m2 527.02 1,029.34
in white cement complete: 1/2" thick (Badel, Silky black,
Sunny white, Sunny Grey or eq)
10-26-d Providing and Laying marble fine dressed stone 4-5 feet 100 Sft 4,898.00 13,206.16 m2 527.02 1,420.98
and 12" wide 1" thick for stairs steps.
10-26-e Providing and Laying marble fine dressed stone 7x1.5 feet 100 Sft 4,898.00 13,206.16 m2 527.02 1,420.98
and
1" thick for stairs steps.
10-26-f Providing and fixing glazed tile colour printed border 2" 100 Rft 454.15 3,895.39 m 14.90 127.80
wide
10-26-g Providing and fixing glazed tile colour printed border 3" 100 Rft 454.15 3,895.39 m 14.90 127.80
wide
10-26-h Providing and fixing glazed tile colour printed border 4" 100 Rft 454.15 3,895.39 m 14.90 127.80
wide
10-27 Rubbing and polishing old grit/mosaic floor, including 100 Sft 2,433.50 2,475.85 m2 261.84 266.40 Reduce the rate by 35
repairing voids, uneven surface, complete % and 40 % for
labour and composite
rate respectively if
polishing is not done.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 49 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-28 Rubbing & polishing grit floor, including repairing voids, 100 Sft 850.95 997.36 m2 91.56 107.32 Reduce the rate by 35
uneen surface, complete % and 40 % for
labour and composite
rate respectively if
polishing is not done.
10-29 Cleaning and washing mosaic or marble floor with caustic 100 Sft 104.78 155.12 m2 11.27 16.69
soda mixture
10-30 Shisham wood boarding or strip flooring 3/4" thick 100 Sft 7,285.00 28,503.04 m2 783.87 3,066.93
including 2 coats of bitumen laid hot complete
10-31 Deodar wood boarding or strip flooring 3/4" thick 100 Sft 5,208.00 38,336.09 m2 560.38 4,124.96
including 2 coats of bitumen laid hot complete
10-32 Teak wood boarding or strip flooring 1/2" thick including 2 100 Sft 7,285.00 39,106.29 m2 783.87 4,207.84
coats of bitumen laid hot complete
10-33 Shisham wood block flooring 1" thick out to required size, 100 Sft 5,208.00 24,480.02 m2 560.38 2,634.05
fixed on a layer of bitumen base
10-34 Teak wood block 1" thick cut to required size, fixed on a 100 Sft 7,285.00 58,802.31 m2 783.87 6,327.13
layer of asphalt bitumen laid on base
10-35-a Laying wooden paving of hard wood on edge in coal tar & 100 Sft 2,015.00 13,958.29 m2 216.81 1,501.91
asphalt : Shisham wood
10-35-b Laying wooden paving of hard wood on edge in coal tar & 100 Sft 2,015.00 9,873.93 m2 216.81 1,062.43
asphalt : Kikar wood
10-36-a Tile skirting laid in 1:2 c/s mortar over 3/4" thick cement 100 Sft 1,673.07 8,165.81 m2 180.02 878.64
mortar 1:2 complete : Cement tiles
10-36-b Tile skirting laid in 1:2 c/s mortar over 3/4" thick cement 100 Sft 1,945.25 10,877.35 m2 209.31 1,170.40
mortar 1:2 complete : Mosaic tiles
10-37-a Provide grey cement skirting 3/8" thick complete 1:2 100 Sft 1,983.07 2,566.23 m2 213.38 276.13
cement, sand mortar
10-37-b Provide grey cement skirting 3/8" thick complete 1:3 100 Sft 1,983.07 2,462.32 m2 213.38 264.95
cement, sand mortar
10-37-c Provide grey cement skirting 3/8" thick complete Extra if 100 Sft 155.00 821.23 m2 16.68 88.36
skirting or dado is finished with pigment
10-38-a Glazed tile 1/4" thick dado jointed in white cement 100 Sft 2,712.50 7,334.58 m2 291.86 789.20
complete : White Plain tiles
10-38-b Glazed tile 1/4" thick dado jointed in white cement 100 Sft 2,712.50 7,247.46 m2 291.86 779.83
complete : Coloured Plain tiles
10-38-c Glazed tile 1/4" thick dado jointed in white cement 100 Sft 2,712.50 7,334.58 m2 291.86 789.20
complete : Printed tiles
10-39 Glazed tile dado 1/4" thick in pigment over 1:2 c/s mortar 100 Sft 2,712.50 7,455.58 m2 291.86 802.22
3/4" thick including finishing complete
10-40-a-01 Mosaic dado or skirting complete as per specs Using grey 100 Sft 3,472.00 5,103.41 m2 373.59 549.13
cement : 3/8" thick
10-40-a-02 Mosaic dado or skirting complete as per specs Using grey 100 Sft 3,472.00 5,486.92 m2 373.59 590.39
cement : 1/2" thick
NWFP CSR 2008 - Approved 25-Aug-2008 Page 50 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-40-b-01 Mosaic dado or skirting complete as per specs Using white 100 Sft 3,472.00 5,085.38 m2 373.59 547.19
cement : 3/8" thick including grinding and polishing
10-40-b-02 Mosaic dado or skirting complete as per specs Using white 100 Sft 3,472.00 5,544.28 m2 373.59 596.56
cement : 1/2" thick including grinding and polishing
10-41-a Provide & lay marble fine dressed and polished stone dado 100 Sft 1,581.00 4,591.78 m2 170.12 494.08
or skirting in white cement complete : 3/8" thick (Badel,
Silky black, Sunny white, Sunny Grey or eq)
10-41-b Provide & lay marble fine dressed and polished stone dado 100 Sft 1,581.00 5,675.34 m2 170.12 610.67
or skirting in white cement complete : 1/2" thick (Badel,
Silky black, Sunny white, Sunny Grey or eq)
10-42 Rubber flooring, consisting of 12"x12"x1/8" rubber tiles 100 Sft 1,144.06 12,744.33 m2 123.10 1,371.29 The cost of base for
laid on firm foundation rubber floor is not
included in the rate
and is payable
separately
10-43-a Provide & fix glass strip 1.5" wide for dividing the floors 100 Rft 37.76 418.91 m 1.24 13.74
into panels : 5mm thick
10-43-b Provide & fix glass strip 1.5" wide for dividing the floors 100 Rft 37.76 418.91 m 1.24 13.74
into panels : 3mm thick
10-43-c Providing and Fixing marble strip 1.5 inch wide 3/8 inch 100 Rft 37.76 291.86 m 1.24 9.58
thick for dividing the floor into panels
10-43-d Providing and Fixing marble strip 2" wide and 3/8" thick 100 Rft 37.76 482.43 m 1.24 15.83
for dividing the floor into panels
10-44 P/F Vinyl Tiles or Vinyl Sheet flooring over firm 100 Sft 1,193.50 13,741.20 m2 128.42 1,478.55
foundation
10-45 P/F Precast Concrete 7000 psi TUFF Tiles over bed of 2" 100 Sft 1,116.00 4,456.14 m2 120.08 479.48
thick sand & 4" thick brick ballast comp
10-46-a P/F Ceramic Floor Tiles (Emco, National or eq) Size : 12" 100 Sft 2,325.00 11,382.70 m2 250.17 1,224.78
x 12"
10-46-b P/F Ceramic Floor Tiles (Emco, National or eq) Size 20" x 100 Sft 2,325.00 17,432.70 m2 250.17 1,875.76
20"
10-47 Burnt brick (1st class) pavement on edge grouted with sand 100 Sft 1,286.50 3,686.84 m2 138.43 396.70
including preparation of bed
10-48-a Porceline tile floor 1/4" thick laid cement 1:2 or 3/4" thick 100 Sft 2,433.50 8,259.53 m2 261.84 888.73
cement mortar 1:2 (Local Master Tiles)
10-48-b Porceline tile floor 1/4" thick laid cement 1:2 over 3/4" 100 Sft 2,433.50 10,437.53 m2 261.84 1,123.08
thick cement mortar 1:2 (Imported Tiles)
10-48-c Granitto tile floor 1/4" thick laid cement 1:2 or 3/4" thick 100 Sft 2,433.50 19,996.53 m2 261.84 2,151.63
cement mortar 1:2 (Imported Tiles UAE) 24"x24"
10-48-d Granitto tile floor 1/4" thick laid cement 1:2 or 3/4" thick 100 Sft 2,433.50 17,317.59 m2 261.84 1,863.37
cement mortar 1:2 (Imported Tiles UAE) 16"x16"

NWFP CSR 2008 - Approved 25-Aug-2008 Page 51 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 10 FLOORING
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
10-49-a Providing and Laying marble fine dressed stone flooring 100 Sft 2,852.00 28,417.06 m2 306.88 3,057.68
on surface in white cement complete using indian green
marble 12"x12"x3/4" thick
10-49-b Providing and Laying marble fine dressed stone flooring 100 Sft 2,852.00 10,025.06 m2 306.88 1,078.70
on surface in white cement complete using Trevera marble
12"x12"x3/4" thick
10-49-c Providing and Laying marble fine dressed stone flooring 100 Sft 2,852.00 12,082.06 m2 306.88 1,300.03
on surface in white cement complete using Botocina
marble 12"x12"x3/4" thick
10-49-d Providing and Laying marble fine dressed stone flooring 100 Sft 2,852.00 11,477.06 m2 306.88 1,234.93
on surface in white cement complete using
Veroona/Lasbela marble 12"x12"x3/4" thick
10-50 Chemical polishing of marble floor/Dado 100 Sft 558.00 1,616.75 m2 60.04 173.96
10-51 Replaced coloured glass panes of sizes upto 4 mm Sft 21.70 106.40 m2 233.49 1,144.86
thickness with iron, nails and putty including removing
broken ones if required in all floors.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 52 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 11 SURFACE RENDERING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
11-01-a Mud plaster on walls (excluding gobri leeping) upto 20' 100 Sft 253.58 390.31 m2 27.29 42.00
height : 1/2" thick
11-01-b Mud plaster on walls (excluding gobri leeping) upto 20' 100 Sft 346.58 620.04 m2 37.29 66.72
height : 1" thick
11-02-a Mud plaster on floor / roof (excluding gobri leeping) upto 100 Sft 227.85 364.58 m2 24.52 39.23 Add extra 13%, 32%
20' height : 1/2" thick and 51% above the
labour rates only or
6%, 15% and 23% on
composite rates for
2nd, 3rd, 4th and
subsequent floors
respectively.
11-02-b Mud plaster on floor / roof (excluding gobri leeping) upto 100 Sft 429.04 702.50 m2 46.16 75.59
20' height : 1" thick
11-03-a Cement lime plaster 1:7:12 (c/l/s) upto 20' height 1/4" thick 100 Sft 790.50 915.16 m2 85.06 98.47
11-03-b Cement lime plaster 1:7:12 (c/l/s) upto 20' height 1/2" thick 100 Sft 790.50 1,040.03 m2 85.06 111.91
11-04-a Cement Neru plaster 1:2 (c/s) upto 20' height 1/4" thick 100 Sft 790.50 1,207.11 m2 85.06 129.88
11-04-b Cement Neru plaster 1:2 (c/s) upto 20' height 1/2" thick 100 Sft 790.50 1,501.75 m2 85.06 161.59
11-05 2" stucco cement plaster 1:2:4 (c/s/shingle) upto 20' height 100 Sft 1,788.70 3,402.60 m2 192.46 366.12
11-06-a Provide/lay machine sprayed plaster 1/2" thick using 100 Sft 581.87 1,756.14 m2 62.61 188.96
cement & zero guage chips : Ratio 1:1
11-06-b Provide/lay machine sprayed plaster 1/2" thick using 100 Sft 587.45 1,675.81 m2 63.21 180.32
cement & zero guage chips : Ratio 1:1.5
11-06-c Provide/lay machine sprayed plaster 1/2" thick using 100 Sft 599.54 1,644.62 m2 64.51 176.96
cement & zero guage chips : Ratio 1:2
11-07-a Cement plaster 1:2, upto 20' height 3/8" thick 100 Sft 790.50 1,242.34 m2 85.06 133.68 The rate be allowed
only on written orders
of Superintending
Engineer
11-07-b Cement plaster 1:2, upto 20' height 1/2" thick 100 Sft 790.50 1,373.66 m2 85.06 147.81
11-07-c Cement plaster 1:2, upto 20' height 3/4" thick 100 Sft 1,007.50 1,906.83 m2 108.41 205.18
11-08-a Cement plaster 1:3 upto 20' height 3/8" thick 100 Sft 790.50 1,107.81 m2 85.06 119.20 ditto
11-08-b Cement plaster 1:3 upto 20' height 1/2" thick 100 Sft 790.50 1,212.12 m2 85.06 130.42
11-08-c Cement plaster 1:3 upto 20' height 3/4" thick 100 Sft 1,007.50 1,642.11 m2 108.41 176.69
11-09-a Cement plaster 1:4 upto 20' height 3/8" thick 100 Sft 790.50 1,073.10 m2 85.06 115.47
11-09-b Cement plaster 1:4 upto 20' height 1/2" thick 100 Sft 790.50 1,148.78 m2 85.06 123.61
11-09-c Cement plaster 1:4 upto 20' height 3/4" thick 100 Sft 1,007.50 1,567.70 m2 108.41 168.68

NWFP CSR 2008 - Approved 25-Aug-2008 Page 53 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 11 SURFACE RENDERING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
11-10-a Cement plaster 3/8" thick under soffit of RCC roof slabs 100 Sft 1,007.50 1,354.17 m2 108.41 145.71 i) This item shall be
only upto 20' height : (1:2) applicable to building
meant for human
habitation only, such
as building like
residence, offices,
educational
institutions and
hospitals etc. It shall
no admissible on
godowns, bins,
agricultural, poultry
etc.
11-10-b Cement plaster 3/8" thick under soffit of RCC roof slabs 100 Sft 1,007.50 1,344.63 m2 108.41 144.68 ii) The thickness of
only upto 20' height : (1:3) the plaster will not be
more than 3/8" thick.
11-10-c Cement plaster 3/8" thick under soffit of RCC roof slabs 100 Sft 1,007.50 1,231.83 m2 108.41 132.55
only upto 20' height : (1:4)
11-11-a Cement plaster 1:5, upto 20' height 3/8" thick 100 Sft 790.50 1,042.60 m2 85.06 112.18
11-11-b Cement plaster 1:5, upto 20' height 1/2" thick 100 Sft 790.50 1,122.28 m2 85.06 120.76
11-11-c Cement Plaster 1:5, upto 20' height 3/4" thick 100 Sft 1,007.50 1,511.71 m2 108.41 162.66
11-12-a Cement plaster 1:6, upto 20' height 3/8" thick 100 Sft 790.50 999.04 m2 85.06 107.50
11-12-b Cement plaster 1:6, upto 20' height 1/2" thick 100 Sft 790.50 1,065.65 m2 85.06 114.66
11-12-c Cement plaster 1:6, upto 20' height 3/4" thick 100 Sft 1,007.50 1,420.23 m2 108.41 152.82
11-13 Applying floating coat of cement 1/32" thick 100 Sft 539.40 718.00 m2 58.04 77.26
11-14 Lime pointing flush upto 20' height, including racking 100 Sft 573.50 663.46 m2 61.71 71.39
joints in lime sand mortar 1:2
11-15 Lime pointing struck joints on walls, upto 20' height 100 Sft 937.75 1,027.71 m2 100.90 110.58
including racking joints, in lime sand mortar 1:2
11-16-a Cement pointing flush, upto 20' height Ratio 1:2 100 Sft 790.50 1,126.46 m2 85.06 121.21
11-16-b Cement pointing flush, upto 20' height Ratio 1:3 100 Sft 790.50 1,050.05 m2 85.06 112.98
11-17-a Cement pointing 1:2 flush, on floor 100 Sft 573.50 909.46 m2 61.71 97.86
11-18-a Cement pointing struck joints, on walls, upto 20' height : 100 Sft 937.75 1,273.71 m2 100.90 137.05
Ratio 1:2
11-18-b Cement pointing struck joints, on walls, upto 20' height : 100 Sft 937.75 1,197.30 m2 100.90 128.83
Ratio 1:3
11-19-a Pointing flush on stone work, upto 20' height in lime sand 100 Sft 798.25 913.50 m2 85.89 98.29
mortar 1:2 (lime, sand)
11-19-b Pointing flush on stone work, upto 20' height in cement 100 Sft 798.25 1,057.80 m2 85.89 113.82
sand mortar 1:3
11-19-c-01 Pointing flush on stone work, upto 20' height On stone 100 Sft 1,526.75 1,642.00 m2 164.28 176.68
work raised : in lime sand mortar 1:2

NWFP CSR 2008 - Approved 25-Aug-2008 Page 54 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 11 SURFACE RENDERING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
11-19-c-02 Pointing flush on stone work, upto 20' height On stone 100 Sft 1,526.75 1,786.30 m2 164.28 192.21
work raised : in c/s mortar 1:3
11-20 Racking and washing joints of stone masonry (old work) 100 Sft 348.75 348.75 m2 37.53 37.53
11-21 Racking and washing joints of brick masonry (old work) 100 Sft 209.25 209.25 m2 22.52 22.52
11-22 Priming coat of chalk under distemper 100 Sft 86.80 117.08 m2 9.34 12.60
11-23-a-01 Distempering New surface : One coat 100 Sft 217.00 342.53 m2 23.35 36.86
11-23-a-02 Distempering New surface : Two coats 100 Sft 217.00 371.18 m2 23.35 39.94
11-23-a-03 Distempering New surface : Three coats 100 Sft 217.00 390.71 m2 23.35 42.04
11-23-b-01 Distempering Old surface : One coat 100 Sft 60.76 141.96 m2 6.54 15.27
11-23-b-02 Distempering Old surface : Two coats 100 Sft 86.80 190.80 m2 9.34 20.53
11-24-a-01 Colour washing: New surface : One coat 100 Sft 46.50 73.27 m2 5.00 7.88
11-24-a-02 Colour washing: New surface : Two coats 100 Sft 119.35 163.27 m2 12.84 17.57
11-24-b-01 Colour washing: Old surface : One coat 100 Sft 52.70 73.27 m2 5.67 7.88
11-24-b-02 Colour washing: Old surface : Two coats 100 Sft 91.76 125.10 m2 9.87 13.46
11-25-a-01 White washing: New surface : One coat 100 Sft 43.40 52.66 m2 4.67 5.67
11-25-a-02 White washing: New surface : Two coats 100 Sft 121.83 135.71 m2 13.11 14.60
11-25-a-03 White washing: New surface : Three coats 100 Sft 155.93 177.89 m2 16.78 19.14
11-25-b-01 White washing: Old surface : One coat 100 Sft 52.70 69.59 m2 5.67 7.49
11-25-b-02 White washing: Old surface : Two coats 100 Sft 91.76 103.53 m2 9.87 11.14
11-26-a Gobri leeping: On walls 100 Sft 87.42 95.44 m2 9.41 10.27
11-26-b Gobri leeping: Over roofs 100 Sft 87.42 105.06 m2 9.41 11.30
11-27 Striking joints of burnt brick in lime or cement mortar 100 Sft 206.15 206.15 m2 22.18 22.18 Payable with fresh
masonry when the
face of the work is
not to be
plastered/pointed.
11-28 Extra for lime, mud or cement plaster & pointing from 20' 100 Sft 140.43 140.43 m2 15.11 15.11
& above for each additional 10' height
11-29 Caulking joints of sleeper wall, with sand and coaltar 100 Sft 294.50 574.95 m2 31.69 61.86
11-30 Caulking joints of sleepers, with mud and chopped straw 100 Sft 294.50 373.76 m2 31.69 40.22
11-31 Extra cost of labour & material for red oxide pigment in 100 Sft 46.50 257.04 m2 5.00 27.66
cement pointing to match bricks
11-32-a Provide grooved c/s plaster 1:3 over existing plastered & 100 Sft 705.25 1,040.12 m2 75.88 111.92
roughened surface 3/8" thick
11-32-b Provide grooved c/s plaster 1:3 over existing plastered & 100 Sft 705.25 1,124.15 m2 75.88 120.96
roughened surface 1/2" thick
11-32-c Providing ornamental plaster 3/4" thick with (1:3) cement 100 Sft 5,246.75 6,353.70 m2 564.55 683.66
sand mortar on walls, columns chajja and slabs finished
smooth including all charges for Labour and Material.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 55 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 11 SURFACE RENDERING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
11-32-d Providing ornamental moulding of approved design in 100 Sft 4,732.15 6,639.42 m2 509.18 714.40
column with base/top and nosing and shade of lintle or
pediments in cement mortar(1:3) 1-1/8" thick(1 feet under
coat x 1/8" finish layer) including all charges for
curing/finishing complete
11-33 Provide & fit expanded metal edge bead for corners, with Rft 4.23 18.22 m 13.89 59.76
nails on both sides of edges
11-34-a Petty repairs to Fire Place Each 136.40 317.90 Each 136.40 317.90
11-34-b Petty repairs to Verandah Each 195.30 401.00 Each 195.30 401.00
11-34-c Petty repairs to Room upto 100 sft area Each 136.40 438.90 Each 136.40 438.90
11-34-d Petty repairs to Room exceeding 100 sft area Each 224.75 648.25 Each 224.75 648.25
11-35 Extra labour for white washing, priming etc. from 20' m3 / coat 0.93 0.93 m3 / coat 0.93 0.93 The will be taken
height & above for every extra 10' height from the floor, roof or
ground underneath as
the case may be, on
the side towards
which the work is to
be done
11-36 Providing and fixing of clad stones over 1/2" c/s mortar 1:1 100 Sft 2,015.00 8,012.89 m2 216.81 862.19
incl curing etc.
11-37 Supply & apply acrylic wall coating 10 to 12mm thick of 100 Sft 1,216.75 11,458.11 m2 130.92 1,232.89 The rate of plastering
approved quality over plastered surface over walls is not
included in this rate
and is to be paid
separately.
11-38 P/F Ceramic Exterior Finish Tiles over 1/2" cement sand 100 Sft 2,534.25 12,065.06 m2 272.69 1,298.20
mortar 1:1 including curing complete
11-39-a Providing and fixing Chakwal tiles red colour in 1:3 100 Sft 2,030.50 5,770.91 m2 218.48 620.95
cement mortar complete.
11-39-b Providing and fixing Chakwal tiles white colour in 1:3 100 Sft 2,030.50 6,375.91 m2 218.48 686.05
cement mortar complete.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 56 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-01-a Plain wood work sawn, wrought, planed & fixed in Cft 364.25 3,172.05 m3 12,863.38 112,020.17
position, including nails & screws : Deodar wood
12-01-b Plain wood work sawn, wrought, planed & fixed in Cft 511.50 1,770.51 m3 18,063.47 62,524.85
position, including nails & screws : Shisham wood
12-02-a Plain woodwork for regulation karries or needles etc. Cft 264.12 3,047.12 m3 9,327.32 107,608.13
complete as per specs : Deodar wood
12-02-b Plain woodwork for regulation karries or needles etc. Cft 423.15 1,657.35 m3 14,943.42 58,528.82
complete as per specs : Shisham wood
12-03-a 1st class teak wood wrought joinery in doors & windows, Sft 136.18 1,152.48 m2 1,465.28 12,400.72
panelled or glazed complete : 2" thick
12-03-b 1st class teak wood wrought joinery in doors & windows, Sft 136.18 1,076.86 m2 1,465.28 11,586.99
panelled or glazed complete : 1.75" thick
12-03-c 1st class teak wood wrought joinery in doors & windows, Sft 136.18 1,001.23 m2 1,465.28 10,773.22
panelled or glazed complete : 1.5" thick
12-04-a-01 1st class teak wood wrought joinery Teak wood frame Sft 84.55 605.34 m2 909.71 6,513.50 a) This also includes
1.75" thick w/o spring/hinge the cost of woods
required for extra
thickness of
chowkats.
12-04-a-02 1st class teak wood wrought joinery Teak wood frame Sft 84.55 617.34 m2 909.71 6,642.62
1.75" thick w/o spring/hinge
12-04-b-01 1st Class Teak Wood Wrought Joinery : Teak Wood Sft 84.55 526.60 m2 909.71 5,666.25
framing 1.5" thick w/ wire guaze w/o springs
12-04-b-02 1st Class Teak Wood wrought joinery : Teak Wood Sft 84.55 539.59 m2 909.71 5,806.03
framing 1.5" thick w/ wire guaze w/ springs
12-04-c 1st class teak wood wrought joinery GI wire guaze 22 Sft 30.35 183.24 m2 326.61 1,971.64
SWG, fixed to chowkat
12-04-d 1st class teak wood wrought joinery GI wire guaze 22 Sft 45.53 438.24 m2 489.92 4,715.43
SWG, fixed on teak wood frame
12-05 Provide & fix exp. metal 1/2"-3/4" mesh, 16 guage fixed to Sft 30.35 189.79 m2 326.61 2,042.16
chowkat, with 1" teak wood cover strips
12-06 Provide & fix expanded metal 1/2" to 3/4", 16 guage fixed Sft 30.35 189.79 m2 326.61 2,042.16
to chowkat with 1" cover moulding
12-07-a First class deodar wood wrought joinery in doors and Sft 83.59 734.31 m2 899.42 7,901.13
windows etc. complete : 2" thick
12-07-b First class deodar wood wrought joinery in doors and Sft 83.59 647.88 m2 899.42 6,971.16
windows etc. complete : 1-3/4" thick
12-07-c First class deodar wood wrought joinery in doors and Sft 67.81 614.38 m2 729.66 6,610.75
windows etc. complete : 1.5" thick
12-08-a Deodar wood framed, braced & battened doors & windows Sft 97.31 736.51 m2 1,047.01 7,924.81
: 2.25" thick, 1.25" battens & 1" planks
12-08-b Deodar wood framed, braced & battened doors & windows Sft 74.72 602.70 m2 803.97 6,485.03
: 1.75" thick, 1" battens & 3/4" planks
NWFP CSR 2008 - Approved 25-Aug-2008 Page 57 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-09 1" thick battened doors & windows fitted in position, Sft 56.04 448.15 m2 602.97 4,822.08
complete with iron fittings
12-10 Deodar wood battened ledged & braced doors & windows Sft 83.40 735.60 m2 897.44 7,915.08
2.25" thick complete
12-11-a Deodar wood doors framed with braces & 22 SWG GI Sft 38.75 316.70 m2 416.95 3,407.73
sheet facing on one side complete
12-11-b Deodar wood doors framed with braces & 22 SWG GI Sft 38.75 322.15 m2 416.95 3,466.28
sheet facing on both sides complete
12-12-a Partal wood doors framed with braces & 22 SWG GI sheet Sft 27.37 212.19 m2 294.47 2,283.14
facing on one side complete
12-12-b Partal wood doors framed with braces & 22 SWG GI sheet Sft 38.75 156.98 m2 416.95 1,689.13
facing on both sides complete
12-13-a-01 First class deodar wood wrought joinery work Deodar Sft 71.62 390.67 m2 770.66 4,203.62
wood frame 1-3/4" thick w/o springs
12-13-a-02 First class deodar wood wrought joinery work Deodar Sft 71.62 404.53 m2 770.66 4,352.70
wood frame 13/4" thick with springs
12-13-b-01 First class deodar wood wrought joinery work Deodar Sft 71.62 354.69 m2 770.66 3,816.42
wood frame 1.5" thick w/o springs
12-13-b-02 First class deodar wood wrought joinery work Deodar Sft 71.62 368.54 m2 770.66 3,965.50
wood frame 1" thick with springs
12-13-c First class deodar wood wrought joinery work GI wire Sft 30.35 124.96 m2 326.61 1,344.58
guaze fixed to chowkat with 3/4" strip
12-13-d First class deodar wood wrought joinery work GI wire Sft 30.35 108.83 m2 326.61 1,170.99
guaze fixed to chowkat with 1/2" strip
12-14 Making and fixing trellis doors & windows of deodar wood Sft 64.58 393.82 m2 694.92 4,237.51
complete.
12-15-a Provide & fix MS chowkat of doors, windows etc MS Sft 20.65 91.90 m2 222.21 988.86
angle iron 1.5"x1.5"x1/4" welded with MS flat
12-15-b Provide & fix MS chowkat of doors, windows etc MS tee Sft 20.76 97.95 m2 223.39 1,053.93
iron 1.5"x 1.5"x 1/4" welded with MS flat
12-16 Extra for providing & fixing iron double spring hinges with Sft 20.67 61.65 m2 222.37 663.30
brass fittings including finger plate etc
12-17-a P/F brass spring hinges to wire gauzed door. Each 43.40 219.82 Each 43.40 219.82
12-17-b P/F hydraulic Door Closer (Best Quality) Each 89.90 755.40 Each 89.90 755.40
12-18-a-01 Providing and fixing sliding bolt to doors Iron sliding bolts Each 43.71 146.32 Each 43.71 146.32
: 10" long
12-18-a-02 Providing and fixing sliding bolt to doors Iron sliding bolts Each 43.71 170.52 Each 43.71 170.52
: 12" long
12-18-b-01 Providing and fixing sliding bolt to doors CP sliding bolts : Each 43.71 473.02 Each 43.71 473.02
10" long
12-18-b-02 Providing and fixing sliding bolt to doors CP sliding bolts : Each 43.71 533.52 Each 43.71 533.52
12" long
NWFP CSR 2008 - Approved 25-Aug-2008 Page 58 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-18-c-01 Providing and fixing sliding bolt to doors Brass sliding Each 43.71 594.02 Each 43.71 594.02
bolts : 10" long
12-18-c-02 Providing and fixing sliding bolt to doors Brass sliding Each 43.71 654.52 Each 43.71 654.52
bolts : 12" long
12-19-a Extra for brass fittings to doors & windows Deodar Sft 0.97 10.26 m2 10.42 110.42
panelled, panelled+glazed or fully glazed
12-19-b Extra for brass fittings to doors & windows Deodar wood Sft 1.05 9.92 m2 11.28 106.69
wire guazed shutters
12-20-a-01 Extra for providing/fixing approved quality Rim locks : Each 187.55 913.55 Each 187.55 913.55
Imported
12-20-a-02 Extra for providing/fixing approved quality Rim locks : Each 187.55 611.05 Each 187.55 611.05
Local
12-20-b-01 Extra for providing/fixing approved quality Rim locks : Each 132.65 737.65 Each 132.65 737.65
Imported
12-20-b-02 Extra for providing/fixing approved quality Rim locks : Each 132.65 495.65 Each 132.65 495.65
Local
12-21-a Provide & fix exp. metal 1/2"-3/4"mesh 16 gauge Fixed to Sft 15.18 183.92 m2 163.31 1,978.99
chowkat with 1" deodar wood strip etc
12-21-b Provide & fix exp. metal 1/2"-3/4"mesh 16 gauge Fixed Sft 12.40 282.26 m2 133.42 3,037.12
with 1" cover mould & screws including frame
12-22-a Provide & fix deodar wood almirah 9"-12" depth including Sft 136.45 953.79 m2 1,468.20 10,262.79
boxing with back, shelves, shutters etc
12-22-b Provide & fix deodar wood almirah 9"-12" depth With Sft 97.17 538.61 m2 1,045.53 5,795.49
shelves, shutters etc w/o boxing & back
12-23-a Provide & fix wooden box type wardrobe 22" deep Partal Sft 145.99 608.06 m2 1,570.80 6,542.75
wood boxing & deodar wood shelves etc
12-23-b Provide & fix wooden box type wardrobe 22" deep Deodar Sft 145.99 687.93 m2 1,570.80 7,402.09
wood boxing & deodar shelves etc
12-24-a Provide & fix chowkat for doors, windows & CS windows, Sft 26.02 300.86 m2 279.95 3,237.24
including holdfast etc : Teak wood
12-24-b Provide & fix chowkat for doors, windows & CS windows, Sft 20.76 106.21 m2 223.37 1,142.85
including holdfast etc : Shisham wood
12-24-c Provide & fix chowkat for doors, windows & CS windows, Sft 13.01 187.38 m2 139.98 2,016.17
including holdfast etc : Deodar wood
12-25-a Make & fix deodar planking in eave boards etc planed on 100 Sft 2,635.00 26,475.85 m2 283.53 2,848.80
both sides complete : 1" thick
12-25-b Make & fix deodar planking in eave boards etc planed on 100 Sft 2,635.00 20,716.21 m2 283.53 2,229.06
both sides complete : 3/4" thick
12-25-c Make & fix deodar planking in eave boards etc planed on 100 Sft 2,635.00 14,980.81 m2 283.53 1,611.94
both sides complete : 1/2" thick
12-26-a Make & fix deodar wood shelves, incl brackets 1" thick 100 Sft 2,635.00 26,366.91 m2 283.53 2,837.08
12-26-b Make & fix deodar wood shelves, incl brackets 1.5" thick 100 Sft 2,635.00 37,872.98 m2 283.53 4,075.13
NWFP CSR 2008 - Approved 25-Aug-2008 Page 59 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-26-c Make & fix deodar wood shelves, incl brackets 2" thick 100 Sft 2,635.00 49,379.05 m2 283.53 5,313.19
12-27-a Make & fix cleats for doors & windows including hinges Each 36.42 84.91 Each 36.42 84.91
and screws.
12-27-b Make & fix cleats with brass hooks for roof ventilators 1 No 36.42 83.19 no 36.42 83.19
12-27-c Make & fix Door stops of 1.5" dia rubber block Each 21.70 100.35 Each 21.70 100.35
12-27-d Make & fix GI hook with clamps for doors Each 26.04 56.29 Each 26.04 56.29
12-28-a Teak wood railing of any shape & design including bends, Rft 124.81 898.71 m 409.47 2,948.54
corners, polishing etc complete
12-28-b Shisham wood railing of any shape & design including Rft 124.81 412.04 m 409.47 1,351.84
bends, corners, polishing etc complete
12-29 Deodar wood dado or picture rail 3"x1.5" as per approved Rft 51.06 241.09 m 167.51 790.97
design, including moulding etc. complete
12-30-a Sawing wood by hand : Soft wood (deodar, kail or chir) 100 Sft 837.00 837.00 m2 90.06 90.06
12-30-b Sawing wood by hand : Hard wood (shisham, kikar, teak or 100 Sft 1,674.00 1,674.00 m2 180.12 180.12
sahl)
12-31-a Sawing wood by machine : Soft Wood 100 Sft 452.14 452.14 m2 48.65 48.65
12-31-b Sawing wood by machine : Hard Wood 100 Sft 488.28 488.28 m2 52.54 52.54
12-32 Making and fixing sun-shade of deodar wood including 100 Sft 3,363.50 32,138.51 m2 361.91 3,458.10
fixing brackets
12-33 Making and fixing 1" thick kail or chir wooden notice Sft 40.47 112.73 m2 435.48 1,212.99
board with frame
12-34 Making deodar punkha pole 10'x6"x6" Each 307.61 6,339.46 Each 307.61 6,339.46
12-35 Dismantling and refixing eave boards Rft 14.47 14.47 m 47.46 47.46
12-36 Wooden stair-cases complete 2'-3' wide frame 1.5" thick Rft 145.70 1,862.59 m 478.02 6,110.85
planks of deodar wood including hand rails
12-37-a-01 Providing and fixing partition including framework : Sheet 100 Sft 868.00 5,897.36 m2 93.40 634.56
on one side of frame : Hard board
12-37-a-02 Providing and fixing partition including framework : Sheet 100 Sft 868.00 6,230.11 m2 93.40 670.36
on one side of frame : Ply wood 1/4" thick
12-37-a-03 Providing and fixing partition including framework : Sheet 100 Sft 868.00 8,745.10 m2 93.40 940.97
on one side of frame : Masonite
12-37-b-01 Providing and fixing partition including framework : 100 Sft 1,596.50 7,431.72 m2 171.78 799.65
Sheets on both sides of frame : Hard board
12-37-b-02 Providing and fixing partition including framework : 100 Sft 1,596.50 8,056.08 m2 171.78 866.83
Sheets on both sides of frame : Ply wood 1/4"
12-37-b-03 Providing and fixing partition including framework : 100 Sft 1,596.50 12,668.00 m2 171.78 1,363.08
Sheets on both sides of frame : Masonite
12-38-a Providing and fixing ceiling, including frame work : Hard 100 Sft 2,294.00 7,323.36 m2 246.83 787.99
board
12-38-b Providing and fixing ceiling, including frame work : Chip 100 Sft 2,294.00 9,747.60 m2 246.83 1,048.84
Board

NWFP CSR 2008 - Approved 25-Aug-2008 Page 60 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-38-c Providing and fixing ceiling, including frame work : Ply 100 Sft 2,294.00 7,621.63 m2 246.83 820.09
wood 1/4" thick
12-38-d Providing and fixing ceiling, including frame work : 100 Sft 2,294.00 10,715.60 m2 246.83 1,153.00
Masonite
12-39-a-01 Provide & fix, thermorpore false ceiling complete Deodar 100 Sft 1,736.00 12,390.05 m2 186.79 1,333.17
wood frame panelling : 3/4" thick
12-39-a-02 Provide & fix, thermorpore false ceiling complete Deodar 100 Sft 1,736.00 14,350.25 m2 186.79 1,544.09
wood frame panelling : 1" thick
12-39-b-01 Provide & fix, thermorpore false ceiling complete Partal 100 Sft 1,736.00 8,572.50 m2 186.79 922.40
wood frame panelling : 3/4" thick
12-39-b-02 Provide & fix, thermorpore false ceiling complete Partal 100 Sft 1,736.00 9,398.33 m2 186.79 1,011.26
wood frame panelling : 1" thick
12-40 Supply and Fixing accoustic miller fibre tile ceiling fixed 100 Sft 1,444.60 29,660.59 m2 155.44 3,191.48
with aluminium tee hung by GI wire fixed in roof
12-41-a Fixing Door including chowkats Each 364.25 364.25 Each 364.25 364.25
12-41-b Fixing Windows including chowkats Each 182.13 182.13 Each 182.13 182.13
12-42-a Glazing with panes (16-18 oz) including cost of putty Sft 13.84 40.97 m2 148.91 440.85
12-42-b Glazing with panes (16-18 oz) using deodar wooden fillets Sft 19.38 62.07 m2 208.48 667.82
& putty
12-42-c Glazing with panes (24-26 oz) using putty & deodar Sft 19.38 62.07 m2 208.48 667.82
wooden fillets
12-43-a Cutting to required size & fixing glass panes with putty. 100 Sft 193.75 387.35 m2 20.85 41.68
12-43-b Cutting to required size & fixing glass panes Using deodar Sft 3.75 15.58 m2 40.30 167.65
wood fillets & putty
12-44-a Glazing with plate glass 6 mm thick including cost of Sft 23.41 102.72 m2 251.93 1,105.24
deodar wood fillet & putty : Upto 0.75 m2
12-44-b Glazing with plate glass 6 mm thick including cost of Sft 23.41 101.81 m2 251.92 1,095.47
deodar wood fillet & putty : 0.75m2 to 2.25 m2
12-45-a 1.5" thick deodar doors & windows, chowkat of MS angle Sft 104.08 642.61 m2 1,119.88 6,914.46
iron 1.5"x1.5"x1/4" welded with MS flat
12-45-b 1.5" thick deodar doors & windows, chowkat of MS tee Sft 114.59 619.90 m2 1,232.95 6,670.12
iron 1.5"x 1.5"x 1/4" welded with MS flat
12-46-a 1.5" thick hollow flush door/window, chowkat of MS angle Sft 88.53 459.47 m2 952.63 4,943.90
iron 1.5"x1.5"x1/4" welded with MS flat
12-46-b 1.5" thick hollow flush door/window, chowkat of MS tee Sft 87.53 424.21 m2 941.78 4,564.50
iron 1.5"x 1.5"x 1/4" welded with MS flat
12-47 Panelled door of MS sheet with forged door leaves of MS Sft 146.20 401.07 m2 1,573.06 4,315.53
sheet 22 SWG etc complete
12-48 24 SWG aluminium kick plate 4" high, on bottom rail of Rft 23.01 34.97 m 75.50 114.72
flush doors of commercial ply
12-49 Curtain railing to doors & windows comprising TOSO-elite Rft 22.87 100.52 m 75.02 329.80
Japanese railing or equiv. including paint
NWFP CSR 2008 - Approved 25-Aug-2008 Page 61 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-50 MS flat 1/2"x1/8" grill in windows of approved design Sft 23.12 140.31 m2 248.79 1,509.75
including painting 3 coats, complete
12-51 Provide & fix GI wire gauze 22 SWG, 12x12 mesh per sq. Sft 32.12 128.81 m2 345.65 1,386.04
in, fixed to steel window complete
12-52-a Hollow flush door 1.5"-2" thick including iron mongery Sft 17.52 420.02 m2 188.52 4,519.43
excluding chowkat & lock : Teak veneered
12-52-b Hollow flush door 1.5"-2" thick including iron mongery Sft 17.52 388.56 m2 188.52 4,180.92
excluding chowkat & lock : Shisham veneered
12-52-c Hollow flush door 1.5"-2" thick including iron mongery Sft 17.50 407.89 m2 188.32 4,388.85
excluding chowkat & lock : Deodar veneered
12-52-d Hollow flush door 1.5"-2" thick including iron mongery Sft 17.52 371.61 m2 188.53 3,998.48
excluding chowkat & lock : Commercial veneered
12-53-a-01 Supply and Fixing aluminium door/window, Economy Sft 29.33 273.75 m2 315.58 2,945.54
model Sliding window
12-53-a-02 Supply and Fixing aluminium door/window, Economy Sft 29.33 356.03 m2 315.58 3,830.87
model Hinges window
12-53-a-03 Supply and Fixing aluminium door/window, Economy Sft 29.33 410.37 m2 315.58 4,415.58
model Fixed louver in door frame
12-53-a-04 Supply and Fixing aluminium door/window, Economy Sft 29.33 340.30 m2 315.58 3,661.62
model Fixed louver in 2" frame
12-53-b-01 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Sliding window
12-53-b-02 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Hinges window
12-53-b-03 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed glazing
12-53-b-04 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed arch
12-53-b-05 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 394.64 m2 315.58 4,246.38
sect. Fixed louvers
12-53-b-06 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 383.20 m2 315.58 4,123.25
sect. Sliding door
12-53-b-07 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 407.94 m2 315.58 4,389.40
sect. Swing door single action (short handle)
12-53-b-08 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 418.74 m2 315.58 4,505.59
sect. Swing door single action (long handle)
12-53-b-09 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 407.94 m2 315.58 4,389.40
sect. Swing door double action (short handle)
12-53-b-10 Supply and Fixing aluminium door/window, Deluxe 3" Sft 29.33 380.76 m2 315.58 4,097.02
sect. Swing door double action (short handle)
12-53-c-01 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Sliding window
NWFP CSR 2008 - Approved 25-Aug-2008 Page 62 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-53-c-02 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Hinges window
12-53-c-03 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Fixed glazing
12-53-c-04 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed arch
12-53-c-05 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 383.18 m2 315.58 4,123.03
sect. Sliding door
12-53-c-06 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 394.64 m2 315.58 4,246.38
sect. Swing door single action (short handle)
12-53-c-07 Supply and Fixing aluminium door/window, Deluxe 3.5" Sft 29.33 407.85 m2 315.58 4,388.43
sect. Swing door single action (long handle)
12-53-d-01 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 404.38 m2 315.58 4,351.17
sect. Sliding window
12-53-d-02 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 398.48 m2 315.58 4,287.65
sect. Hinges window
12-53-d-03 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Fixed glazing
12-53-d-04 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 373.57 m2 315.58 4,019.56
sect. Fixed arch
12-53-d-05 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 417.78 m2 315.58 4,495.33
sect. Sliding door
12-53-d-06 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 394.64 m2 315.58 4,246.38
sect. Swing door single action (short handle)
12-53-d-07 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 407.94 m2 315.58 4,389.40
sect. Swing door single action (long handle)
12-53-d-08 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 565.09 m2 315.58 6,080.40
sect. Swing door double action (short handle)
12-53-d-09 Supply and Fixing aluminium door/window, Premium 4" Sft 29.33 578.68 m2 315.58 6,226.62
sect. Swing door double action (long handle)
12-53-e-01 Supply and Fixing aluminium door/window. Other items : Sft 6.20 308.70 m2 66.71 3,321.61
Fly screen shutter for Deluxe model
12-53-e-02 Supply and Fixing aluminium door/window. Other items : Sft 6.20 257.88 m2 66.71 2,774.79
Fly screen shutter for Premium model
12-53-e-03 Supply and Fixing aluminium door/window. Other items : Sft 6.20 308.70 m2 66.71 3,321.61
Fly screen shutter with separate outer frame
12-54-a-01 Supply and Fixing aluminium bronze/black. Economy Sft 29.33 356.03 m2 315.58 3,830.87
model Sliding window
12-54-a-02 Supply and Fixing aluminium bronze/black. Economy Sft 29.33 356.03 m2 315.58 3,830.87
model Hinges window
12-54-a-03 Supply and Fixing aluminium bronze/black. Economy Sft 29.33 505.46 m2 315.58 5,438.73
model Fixed louver in door frame
NWFP CSR 2008 - Approved 25-Aug-2008 Page 63 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-54-a-04 Supply and Fixing aluminium bronze/black. Economy Sft 29.33 505.46 m2 315.58 5,438.73
model Fixed louver in 2" frame
12-54-b-01 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Sliding window
12-54-b-02 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Hinges window
12-54-b-03 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed glazing
12-54-b-04 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed arch
12-54-b-05 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 505.46 m2 315.58 5,438.73
sect. Fixed louvers
12-54-b-06 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 417.79 m2 315.58 4,495.37
sect. Sliding door
12-54-b-07 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 429.23 m2 315.58 4,618.50
sect. Swing door single action (short handle)
12-54-b-08 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 380.76 m2 315.58 4,097.02
sect. Swing door single action (long handle)
12-54-b-09 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 604.77 m2 315.58 6,507.34
sect. Swing door double action (short handle)
12-54-b-10 Supply and Fixing aluminium bronze/black. Deluxe 3" Sft 29.33 566.03 m2 315.58 6,090.52
sect. Swing door double action (long handle)
12-54-c-01 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Sliding window
12-54-c-02 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Hinges window
12-54-c-03 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed glazing
12-54-c-04 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed arch
12-54-c-05 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 417.79 m2 315.58 4,495.37
sect. Sliding door
12-54-c-06 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 429.23 m2 315.58 4,618.50
sect. Swing door single action (short handle)
12-54-c-07 Supply and Fixing aluminium bronze/black. Deluxe 3.5" Sft 29.33 407.94 m2 315.58 4,389.40
sect. Swing door single action (long handle)
12-54-d-01 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Sliding window
12-54-d-02 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 356.03 m2 315.58 3,830.87
sect. Hinges window
12-54-d-03 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed glazing
NWFP CSR 2008 - Approved 25-Aug-2008 Page 64 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-54-d-04 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 340.30 m2 315.58 3,661.62
sect. Fixed arch
12-54-d-05 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 417.79 m2 315.58 4,495.37
sect. Sliding door
12-54-d-06 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 429.23 m2 315.58 4,618.50
sect. Swing door single action (short handle)
12-54-d-07 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 407.94 m2 315.58 4,389.40
sect. Swing door single action (long handle)
12-54-d-08 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 599.68 m2 315.58 6,452.52
sect. Swing door double action (short handle)
12-54-d-09 Supply and Fixing aluminium bronze/black. Premium 4" Sft 29.33 578.39 m2 315.58 6,223.42
sect. Swing door double action (long handle)
12-54-e-01 Supply and Fixing aluminium bronze/black. Other items : Sft 6.20 308.70 m2 66.71 3,321.61
Fly screen shutter for Deluxe model
12-54-e-02 Supply and Fixing aluminium bronze/black. Other items : Sft 6.20 257.88 m2 66.71 2,774.79
Fly screen shutter for Premium model
12-54-e-03 Supply and Fixing aluminium bronze/black. Other items : Sft 6.20 236.10 m2 66.71 2,540.44
Fly screen shutter with separate outer frame
12-55-a Wall Panelling over 0.5" thick chipboard & wood frame Sft 46.52 105.69 m2 500.54 1,137.27
(2"x0.75") 2'x2' grid : Sheesham Ply
12-55-b Wall Panelling over 0.5" thick chipboard & wood frame Sft 34.86 135.84 m2 375.06 1,461.62
(2"x0.75") 2'x2'grid : Lamination Sheet
12-55-c Wall Panelling over 0.5" thick chipboard & wood frame Sft 46.51 96.65 m2 500.42 1,040.00
(2"x0.75") 2'x2' grid : Commercial Ply
12-56-a Supply and Fixing MS Sheet 16 guage(10x20 feet) box Rft 30.95 161.99 m 101.53 531.47
type chowkats including fixing in position with all charges
for Hold fast, Hinges and Painting etc
12-56-b Wood plastic composite door patio door leap delux (laker Rft 41.33 319.81 m2 444.75 3,441.11
coated)
12-56-c Wood plastic composite door patio door leap premium Rft 41.33 341.13 m2 444.75 3,670.51
grade ( UV coated )
12-56-d Wood plastic composite door patio door with frame and Sft 35.74 710.63 m2 384.59 7,646.33
beading deluxe grade (laker coated)
12-56-e Wood plastic composite patio door with frame and beading Sft 35.74 710.63 m2 384.59 7,646.33
premium grade(UV coated)
12-57-a Wood plastic composite door bukhara flush door steppe Sft 35.74 934.63 m2 384.59 10,056.62
type
12-57-b Wood plastic composite door rock type single side door Sft 35.74 934.63 m2 384.59 10,056.62
12-57-c Wood plastic composite door rock type double side door Sft 35.74 934.63 m2 384.59 10,056.62
12-58 Wood plastic composite door image type single side door Sft 35.74 934.63 m2 384.59 10,056.62
12-59 Wood plastic composite door carving type single side door Sft 35.74 934.63 m2 384.59 10,056.62
12-60-a Composite windows deluxe grade (laker coated) Sft 15.68 681.02 m2 168.71 7,327.74
NWFP CSR 2008 - Approved 25-Aug-2008 Page 65 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 12 WOOD WORK, WOODEN/ALUMINIUM JOINERY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
12-60-b Composite windows premium grade (UV coated) Sft 15.62 703.31 m2 168.11 7,567.65
12-61-a Wood Plastic Fly Screen Delux Grade Sft 23.56 281.29 m2 253.51 3,026.68
12-61-b Wood Plastic Screen Premium Grade Sft 23.56 281.29 m2 253.51 3,026.68
12-62-a Kitchen Floor Cabinet as per MES Design/Specification.. Sft 108.50 642.61 m2 1,167.46 6,914.53
12-62-b Kitchen Wall Cabinet as per MES Design/Specification. Sft 86.80 518.16 m2 933.97 5,575.46
12-62-c Providing and Fixing Sink Cabinet as per MES Each 1,302.00 5,735.14 Each 1,302.00 5,735.14
Design/Specification.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 66 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 13 PAINTING AND VARNISHING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
13-01 Cleaning painted woodwork with oil & water 100 Sft 62.00 116.45 m2 6.67 12.53
13-02 Oiling woodwork with boiled linseed oil 100 Sft 62.00 119.47 m2 6.67 12.86
13-03 Brushing & scraping blisters of old paints from woodwork 100 Sft 139.50 139.50 m2 15.01 15.01
13-04 Scraping, brushing and removing old paint, from metal 100 Sft 558.00 558.00 m2 60.04 60.04
surface
13-05-a-01 Painting old corrugated surfaces, pent roofing etc. with oil 100 Sft 286.44 561.11 m2 30.82 60.38
paint : First coat
13-05-a-02 Painting old corrugated surfaces, pent roofing etc. with oil 100 Sft 217.00 437.10 m2 23.35 47.03
paint : Each subsequent coat
13-05-b-01 Painting old surfaces : Sashes, fanlights, doors or windows 100 Sft 173.60 336.65 m2 18.68 36.22
: First coat
13-05-b-02 Painting old surfaces : Sashes, fanlights, doors or windows 100 Sft 147.56 283.32 m2 15.88 30.49
: Each subsequent coat
13-05-c-01 Painting old surfaces : Doors / windows any type First coat 100 Sft 286.44 561.11 m2 30.82 60.38
13-05-c-02 Painting old surfaces : Doors / windows any type Each 100 Sft 217.00 437.10 m2 23.35 47.03
subsequent coat
13-05-d-01 Painting old surfaces : Guard bars, gratings, railing & 100 Sft 173.60 336.65 m2 18.68 36.22
similar open work : First coat
13-05-d-02 Painting old surfaces : Guard bars, gratings, railing & 100 Sft 147.56 283.32 m2 15.88 30.49
similar work : Each subsequent coat
13-05-e-01 Painting old surfaces : Fillets, framing, skirting pipes, etc. 100 Rft 147.56 285.92 m 4.84 9.38
less than 6" girth : First coat
13-05-e-02 Painting old surfaces : Fillets, framing, skirting pipes, etc. 100 Rft 104.16 215.24 m 3.42 7.06
less than 6" girth : Each subseq. coat
13-05-f-01 Painting old surfaces : Small detached articles Not 100 No. 658.75 1,156.67 100 No. 658.75 1,156.67
exceeding 1 sft : First coat
13-05-f-02 Painting old surfaces : Small detached articles Not 100 No. 511.50 840.74 100 No. 511.50 840.74
exceeding 1 sft : Each subsequent coat
13-05-g-01 Painting old surfaces : Small detached articles 1sft-3sft area 100 No. 1,317.50 2,267.96 100 No. 1,317.50 2,267.96
: First coat
13-05-g-02 Painting old surfaces : Small detached articles 1sft-3sft area 100 No. 728.50 1,306.88 100 No. 728.50 1,306.88
: Each subsequent coat
13-06-a-01 Prepare & Paint new corrugated surface, pent roofing etc : 100 Sft 327.98 714.27 m2 35.29 76.86
Priming coat
13-06-a-02 Prepare & Paint new corrugated surface, pent roofing etc : 100 Sft 169.57 501.29 m2 18.25 53.94
Each subsequent coat of paint
13-06-b-01 Prepare & Paint new surface, sashes, doors & windows etc 100 Sft 194.68 442.06 m2 20.95 47.57
: Priming coat
13-06-b-02 Prepare & Paint new surface, sashes, doors & windows etc 100 Sft 104.16 311.86 m2 11.21 33.56
: Each subsequent coat of paint
13-06-c-01 Prepare & Paint new surface, doors & windows Priming 100 Sft 327.98 714.27 m2 35.29 76.86
coat
NWFP CSR 2008 - Approved 25-Aug-2008 Page 67 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 13 PAINTING AND VARNISHING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
13-06-c-02 Prepare & Paint new surface, doors & windows Each 100 Sft 169.57 501.29 m2 18.25 53.94
subsequent coat of paint
13-06-d-01 Prepare & Paint new surfaces of guard bars, railing & 100 Sft 194.68 411.21 m2 20.95 44.25
similar open work : Priming coat
13-06-d-02 Prepare & Paint new surfaces of guard bars, railing & 100 Sft 104.16 281.00 m2 11.21 30.24
similar work : Each subsequent coat
13-06-e-01 Prepare & Paint new surface of fillets, framing, skirtings 100 Rft 147.56 328.52 m 4.84 10.78
etc : Priming coat
13-06-e-02 Prepare & Paint new surface of fillets, framing, skirtings 100 Rft 69.44 218.15 m 2.28 7.16
etc : Each subsequent coat of paint
13-06-f-01 Prepare & Paint new surface of small detached articles upto 100 No. 651.00 1,366.11 100 No. 651.00 1,366.11
1 sft : Priming coat
13-06-f-02 Prepare & Paint new surface of small detached articles upto 100 No. 327.67 906.35 100 No. 327.67 906.35
1 sft : Each subsequent coat
13-06-g-01 Prepare & paint surf. of small detached articles 1sft - 3sft 100 No. 1,309.75 2,700.65 100 No. 1,309.75 2,700.65
area : Priming coat
13-06-g-02 Prepare & paint surf. of small detached articles 1sft - 3sft 100 No. 581.25 1,624.88 100 No. 581.25 1,624.88
area : Subsequent coat of paint
13-06-h Extra for knotting & stopping to prime coat on new surface 100 Sft 35.34 114.60 m2 3.80 12.33
of wood
13-06-i Providing and applying 3 coats of approved type of Plastic 100 Sft 868.00 2,570.97 m2 93.40 276.64
emulsion paint to Plastic surface as per manufucture
specification.
13-07-a Khanki mixture, applied hot to barrage gates First coat 2000 Sft 4,340.00 8,641.00 m2 23.35 46.49
13-07-b Khanki mixture, applied hot to barrage gates Second coat 2000 Sft 3,279.80 6,471.59 m2 17.65 34.82
13-08-a French polishing complete: On new work 100 Sft 2,790.00 3,872.10 m2 300.20 416.64
13-08-b French polishing complete: On old work 100 Sft 1,395.00 1,950.74 m2 150.10 209.90
13-09-a Varnishing wood work, including cleaning & preparing 100 Sft 173.60 482.62 m2 18.68 51.93
surface : First coat
13-09-b Varnishing wood work, including cleaning & preparing 100 Sft 86.80 323.79 m2 9.34 34.84
surface : Second coat
13-09-c Varnishing wood work, including cleaning & preparing 100 Sft 86.80 282.09 m2 9.34 30.35
surface : Third coat
13-10-a Bitumen coating to plastered / cement concrete surface : 20 100 Sft 86.80 661.40 m2 9.34 71.17
Ibs. per 100 sft.
13-10-b Bitumen coating to plastered / cement concrete surface : 14 100 Sft 520.80 947.60 m2 56.04 101.96
Ibs. per 100 sft.
13-10-c Bitumen coating to plastered / cement concrete surface : 10 100 Sft 347.20 675.39 m2 37.36 72.67
Ibs. per 100 sft.
13-11 Writing letters or figures Each 5.15 6.16 Each 5.15 6.16
13-12-a Coaltar paint applied hot: First coat 100 Sft 102.30 703.48 m2 11.01 75.69
13-12-b Coaltar paint applied hot: Second coat 100 Sft 62.00 400.94 m2 6.67 43.14
NWFP CSR 2008 - Approved 25-Aug-2008 Page 68 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 13 PAINTING AND VARNISHING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
13-13-a Solignum paint applied hot: First coat 100 Sft 194.37 626.95 m2 20.91 67.46
13-13-b Solignum paint applied hot: Second coat 100 Sft 100.13 799.51 m2 10.77 86.03
13-14-a Creosote paint applied hot: First coat 100 Sft 194.37 471.58 m2 20.91 50.74
13-14-b Creosote paint applied hot: Second coat 100 Sft 100.13 285.93 m2 10.77 30.77
13-15 Burning off or rubbing down with pumice stone, old paint 100 Sft 356.50 561.09 m2 38.36 60.37
from wood work
13-16 Removing with caustic soda,old paint from wood work 100 Sft 139.50 163.70 m2 15.01 17.61
13-17 Painting distance marks with white ground and black Each 26.50 65.13 Each 26.50 65.13
letterin on both faces
13-18 Painting two feet wide gauges, reading to 1/10th of a foot. 100 RFT 5,821.95 6,873.51 m 191.01 225.51
13-19 Painting sounding rods and other guages, reading to 1/10th 100 RFT 2,910.98 3,310.64 m 95.50 108.62
of a foot
13-20 Painting levelling staves 100 RFT 8,704.57 9,230.92 m 285.58 302.85
13-21-a Painting & lettering (2 coats) on both sides with syn. Each 217.00 317.13 Each 217.00 317.13 The ratio in the rate
enamel paint : Mile/km posts of 1st coat to 2nd coat
is 60 % to 40 % in the
labour as well as
composite rate
13-21-b Painting & lettering (2 coats) on both sides with syn. Each 27.17 39.72 Each 27.17 39.72
enamel paint : Furlong or 1/10 km posts
13-21-c Painting & lettering (2 coats) on both sides with syn. Each 286.44 386.57 Each 286.44 386.57
enamel paint : Sign posts
13-22 Removing paint or varnish from wall 100 Sft 279.00 279.00 m2 30.02 30.02
13-23-a Scraing of Khanki paint from barrage gates 100 Sft 3.49 76.09 m2 0.38 8.19
13-23-b Scraping of Aluminium paint from barrage headworks 100 Sft 69.75 142.35 m2 7.51 15.32
13-24 Painting letters with shade letter 13.89 18.95 letter 13.89 18.95
13-25 Scraping rust from old rails or girders 100 Sft 418.50 491.10 m2 45.03 52.84
13-26 Chiselling old paint from brick work 100 Sft 558.00 630.60 m2 60.04 67.85
13-27 Cleaning glasses with chalk and spirit etc 100 Sft 279.00 351.60 m2 30.02 37.83
13-28 Cleaning and oiling rafter or rolled steel beams 100 Sft 139.50 146.84 m2 15.01 15.80
13-29 Cleaning and painting punkha poles, including fixing Each 279.00 300.27 Each 279.00 300.27
hooks
13-30-a Preparing surface and painting with emulsion paint : First 100 Sft 347.20 793.33 m2 37.36 85.36
coat
13-30-b Preparing surface and painting with emulsion paint : 2nd & 100 Sft 173.60 336.83 m2 18.68 36.24
each subsequent coat.
13-31 Pavement Marking using Reflective Chlorinated Rubber 100 Sft 573.50 3,431.76 m2 61.71 369.26
Paint with Glass Beads as per specification
13-33 Repainting of ceiling fan (all sizes & types) incl painting of Job 41.23 129.87 Job 41.23 129.87
blades, canopy etc with syn. enamel

NWFP CSR 2008 - Approved 25-Aug-2008 Page 69 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 13 PAINTING AND VARNISHING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
13-34 Repainting of iron poles with cross arms, with bitumen or Job 286.75 348.25 Job 286.75 348.25
other approved paint
13-35-a Repainting of pipes and specials of GI, MS or PVC conduit 100 RFT 179.57 370.47 m 5.89 12.15
etc : Upto 1.5" i/d
13-35-b Repainting of pipes and specials of GI, MS or PVC conduit 100 RFT 269.36 631.35 m 8.84 20.71
etc : From 1.5" to 2" i/d
13-35-c Repainting of pipes and specials of GI, MS or PVC conduit 100 RFT 359.15 777.41 m 11.78 25.51
etc : From 2" to 4" i/d
13-36 Repainting main switches & branch distribution boards of Job 44.17 88.04 Job 44.17 88.04
all sizes & types with approved paint
13-37 Extra labour for painting, varnishing etc from 20' height & 100/coat 50.22 50.22 m2 5.40 5.40 The height will be
above, for every additional 10' taken from the floor,
road or ground
underneath, as the
case may be, on side
towards which the
work is to be done.
13-38-a Preparing surface & painting with snowcem / weathershield 100/coat 434.00 811.04 m2 46.70 87.27
paint : First coat
13-38-b Preparing surface & painting with snowcem / weathershield 100/coat 217.00 422.10 m2 23.35 45.42
paint : 2nd & subsequent coats

NWFP CSR 2008 - Approved 25-Aug-2008 Page 70 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-01-a Providing and Fixing glazed earthen ware WC European Each 265.98 3,290.98 Each 265.98 3,290.98
type excluding cost of seat & cover : White
14-01-b Providing and Fixing glazed earthen ware WC European Each 265.98 3,508.78 Each 265.98 3,508.78
type excluding cost of seat & cover : Coloured
14-02-a Providing and Fixing double seat & cover only : Bakelite Each 4.96 458.71 Each 4.96 458.71
14-02-b Providing and Fixing double seat & cover only : Plastic Each 4.96 307.46 Each 4.96 307.46
14-03-a Providing and Fixing glazed earthen ware WC squatting Each 241.80 1,288.45 Each 241.80 1,288.45
type with built-in foot rests : White
14-03-b Providing and Fixing glazed earthen ware WC squatting Each 241.80 1,669.60 Each 241.80 1,669.60
type with built-in foot rests : Coloured
14-04 Providing and Fixing white glazed earthernware WC Each 241.80 943.60 Each 241.80 943.60
squatting type with separate foot rests
14-05-a-01 Providing and Fixing glazed earthen ware WHB complete Each 322.40 1,611.05 Each 322.40 1,611.05
Size 22"x16" : White with pedestal
14-05-a-02 Providing and Fixing glazed earthen ware WHB complete Each 322.40 2,324.95 Each 322.40 2,324.95
Size 22"x16" : Coloured with pedestal
14-05-a-03 Providing and Fixing glazed earthen ware WHB complete Each 241.80 1,355.00 Each 241.80 1,355.00
Size 22"x16" : White without pedestal
14-05-a-04 Providing and Fixing glazed earthen ware WHB complete Each 241.80 1,415.50 Each 241.80 1,415.50
Size 22"x16' : Coloured without pedestal
14-05-b-01 Providing and Fixing glazed earthen ware WHB complete Each 322.40 2,072.06 Each 322.40 2,072.06
Size 25"x18" : White with pedestal
14-05-b-02 Providing and Fixing glazed earthen ware WHB complete Each 322.40 2,766.60 Each 322.40 2,766.60
Size 25"x18" : Coloured with pedestal
14-05-b-03 Providing and Fixing glazed earthen ware WHB complete Each 241.80 1,113.00 Each 241.80 1,113.00
Size 25"x18" : White without pedestal
14-05-b-04 Providing and Fixing glazed earthen ware WHB complete Each 241.80 1,173.50 Each 241.80 1,173.50
Size 25"x18" : Coloured without pedestal
14-06-a Providing and Fixing stainless steel sink with drain board Each 322.40 2,524.60 Each 322.40 2,524.60
size 48"x24", including set of brackets, waste pipe etc
14-06-b Providing and fixing stainless steel sink with drain board Each 322.40 1,822.80 Each 322.40 1,822.80
size 18"x36" including set of brackets, waste pipe etc
14-06-c Providing and fixing stainless steel sink with drain board Each 322.40 2,600.23 Each 322.40 2,600.23
size 18"x48" including set of brackets, waste pipe etc
14-06-d Providing and fixing stainless steel sink with drain board Each 322.40 6,578.10 Each 322.40 6,578.10
size 20"x60" including set of brackets, waste pipe etc
14-06-e Providing and fixing stainless steel sink with drain board Each 322.40 7,425.10 Each 322.40 7,425.10
size 20"x72" including set of brackets, waste pipe etc
14-07 Providing and Fixing terrazzo concrete sink 25"x18", with Each 372.00 1,545.70 Each 372.00 1,545.70
drain board of mosaic, including set of brackets etc
14-08-a Providing and Fixing glazed earthen ware sink including Each 322.40 1,133.10 Each 322.40 1,133.10
set of brackets, waste pipe etc : 25"x18"
NWFP CSR 2008 - Approved 25-Aug-2008 Page 71 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-08-b Providing and Fixing glazed earthen ware sink including Each 322.40 951.60 Each 322.40 951.60
set of brackets, waste pipe etc : 25"x18"
14-09 Providing and Fixing white glazed earthernware flat back Each 322.40 866.90 Each 322.40 866.90
urinal
14-10-a Providing and Fixing glazed earthen ware low down Each 322.40 1,484.00 Each 322.40 1,484.00
flushing cistern 3 gallons capacity : White
14-10-b Providing and Fixing glazed earthen ware low down Each 322.40 1,544.50 Each 322.40 1,544.50
flushing cistern 3 gallons capacity : Coloured
14-11 Providing and Fixing white enamelled CI low down Each 322.40 2,306.80 Each 322.40 2,306.80
flushing cistern (3 gallons capacity) including CP water
connection
14-12-a Providing and Fixing cast iron high level flushing cistern, Each 322.40 2,082.95 Each 322.40 2,082.95
including high level flushing cistern including CP : 3
gallons
14-12-b Providing and Fixing cast iron high level flushing cistern, Each 322.40 975.80 Each 322.40 975.80
including high level flushing cistern including CP : 1
gallon
14-13 Providing and Fixing CP soap dish. Each 34.72 395.30 Each 34.72 395.30
14-14-a Providing and Fixing glazed earthen ware soap dish White Each 34.72 185.97 Each 34.72 185.97
14-14-b Providing and Fixing glazed earthen ware soap dish Each 34.72 216.22 Each 34.72 216.22
Coloured
14-15 Providing and Fixing CP toilet paper holder Each 34.72 295.48 Each 34.72 295.48
14-16-a Providing and Fixing CP towel rail : 24" long, 3/4" dia Each 34.72 403.77 Each 34.72 403.77
14-16-b Providing and Fixing CP towel rail : 20" long, 1/2" dia Each 34.72 216.22 Each 34.72 216.22
14-17 Providing and Fixing best quality 5mm mirror 22"x16" size Each 100.75 645.25 Each 100.75 645.25
14-18-a Providing and Fixing best quality 5mm glass shelf 24"x5" Each 39.68 463.18 Each 39.68 463.18
With chromium plated brackets & railing
14-18-b Providing and Fixing best quality 5mm glass shelf 24"x5" Each 14.88 317.38 Each 14.88 317.38
Glass shelf only, w/o chromium plated brackets
14-19-a Providing and Fixing glazed earthen ware shelf 24"x5" Each 39.68 342.18 Each 39.68 342.18
with CP brackets & railing of : 24" length, 3/4" dia
14-19-b Providing and Fixing glazed earthen ware shelf 24"x5" Each 39.68 402.68 Each 39.68 402.68
with CP brackets & railing of : 20" length, 1/2" dia
14-20-a Providing and Fixing Plastic soap dish. Each 34.72 107.32 Each 34.72 107.32
14-20-b Providing and Fixing Plastic toilet paper holder. Each 34.72 125.47 Each 34.72 125.47
14-20-c Providing and Fixing Plastic towel rail. Each 34.72 137.57 Each 34.72 137.57
14-20-d Providing and Fixing Plastic shelf 24"x5" with Each 34.72 77.07 Each 34.72 77.07
14-21-a Providing and Fixing CP pillar-cock, heavy type : 3/4" Each 34.72 473.95 Each 34.72 473.95
14-21-b Providing and Fixing CP pillar-cock, heavy type : 1/2" Each 34.72 417.08 Each 34.72 417.08
14-22-a Providing and Fixing CP stop-cock, heavy type : 3/4" Each 34.72 579.22 Each 34.72 579.22
14-22-b Providing and Fixing CP stop-cock, heavy type : 1/2" Each 34.72 343.27 Each 34.72 343.27
NWFP CSR 2008 - Approved 25-Aug-2008 Page 72 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-23 Providing and Fixing underground stop-cock 1/2" with CP Each 39.68 379.08 Each 39.68 379.08
cover
14-24-a Providing and Fixing CP bib-cock, heavy type : 3/4" Each 34.72 343.27 Each 34.72 343.27
14-24-b Providing and Fixing CP bib-cock, heavy type : 1/2" Each 34.72 343.27 Each 34.72 343.27
14-25 Providing and Fixing 1/2" CP tee stop cock Each 34.72 343.27 Each 34.72 343.27
14-26-a Providing and Fixing CP shower rose : 1/2"x4" Each 34.72 285.80 Each 34.72 285.80
14-26-b Providing and Fixing CP shower rose : 3/4"x6" Each 34.72 322.10 Each 34.72 322.10
14-27 Providing and Fixing CP mixing valve for WHB, sink or Each 34.72 1,933.21 Each 34.72 1,933.21
shower
14-28-a Providing and Fixing gun metal peet / gate valve (screwed) Each 39.68 668.88 Each 39.68 668.88 Reduce the composite
1¬" dia rate by 10 % incase
brase peet / gate valve
are used.
14-28-b Providing and Fixing gun metal peet / gate valve (screwed) Each 39.68 965.33 Each 39.68 965.33
1«" dia
14-28-c Providing and Fixing gun metal peet / gate valve (screwed) Each 39.68 1,171.03 Each 39.68 1,171.03
2" dia
14-28-d Providing and Fixing gun metal peet / gate valve (screwed) Each 39.68 2,828.73 Each 39.68 2,828.73
2«" dia
14-28-e Providing and Fixing gun metal peet / gate valve (screwed) Each 39.68 3,114.29 Each 39.68 3,114.29
3" dia
14-29-a Providing and Fixing CP or brass oxidized swan-neck cock Each 34.72 579.22 Each 34.72 579.22
1/2" dia : Single way
14-29-b Providing and Fixing CP or brass oxidized swan-neck cock Each 39.68 947.18 Each 39.68 947.18
1/2" dia : Double way
14-29-c Providing and Fixing CP or brass oxidized swan-neck cock Each 49.60 1,259.60 Each 49.60 1,259.60
1/2" dia : Three way
14-30-a Providing and Fixing brass union 1/2" dia Each 34.72 234.37 Each 34.72 234.37
14-30-b Providing and Fixing brass union 3/4" dia Each 34.72 288.82 Each 34.72 288.82
14-31-a Providing and Fixing CI floor trap including CI grating & Each 77.50 240.85 Each 77.50 240.85
concrete chamber all round : 4"x2"
14-31-b Providing and Fixing CI floor trap including CI grating & Each 77.50 579.65 Each 77.50 579.65
concrete chamber all round : 4"x3"
14-32-a Providing and Fixing 'P' trap including GI grating & PCC Each 69.75 1,128.50 Each 69.75 1,128.50
chamber 4" of cast iron
14-32-b Providing and Fixing 'P' trap including GI grating & PCC Each 69.75 163.52 Each 69.75 163.52
chamber 4" glazed
14-33 Providing and Fixing 4" gully trap with PCC, including Each 116.25 418.75 Each 116.25 418.75
masonry chamber 1'x1' and PVC grating 6"x6"
14-34-a-01 Providing and fitting CI soil pipe with : Lead & yarn Rft 23.63 381.17 m 77.52 1,250.55
caulked joint : 4" dia.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 73 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-34-a-02 Providing and fitting CI soil pipe with : Lead & yarn Rft 11.81 264.69 m 38.76 868.40
caulked joint : 2" dia.
14-34-b-01 Providing and fitting CI soil pipe with : Cement caulked Rft 23.63 366.41 m 77.52 1,202.14
joint : 4" dia
14-34-b-02 Providing and fitting CI soil pipe with : Cement caulked Rft 11.81 249.93 m 38.76 819.99
joint : 2" dia
14-35-a Providing and Fixing AC soil pipe with cement caulked Rft 5.91 75.63 m 19.38 248.13
joint including all specials : 1¬" i/d
14-35-b Providing and Fixing AC soil pipe with cement caulked Rft 7.09 92.38 m 23.26 303.10
joint including all specials : 3¬" i/d
14-35-c Providing and Fixing AC soil pipe with cement caulked Rft 11.81 126.44 m 38.76 414.83
joint including all specials : 4" i/d
14-35-d Providing and Fixing AC soil pipe with cement caulked Rft 18.90 180.66 m 62.02 592.71
joint including all specials : 6" i/d
14-36-a Providing and Fixing CI specials, such as tees, bends etc Each 96.88 475.00 Each 96.88 475.00 Increase the
Lead caulked joint composite rate by 3
%, in case of plug
type.
14-36-b Providing and Fixing CI specials, such as tees, bends etc Each 96.88 426.60 Each 96.88 426.60
Cement caulked joint
14-37-a Supply and Fixing CI manhole cover with frame etc Each 50.06 830.52 Each 50.06 830.52
complete 12" dia
14-37-b Supply and Fixing CI manhole cover with frame etc Each 50.06 1,538.36 Each 50.06 1,538.36
complete 18" dia
14-37-c Supply and Fixing CI manhole cover with frame etc Each 50.06 2,742.31 Each 50.06 2,742.31
complete 24" dia
14-37-d Providing & Fixing Steel manhole cover with frame Each 217.00 2,122.75 Each 217.00 2,122.75
18"x18" full heavy duty
14-38 Providing and Fixing RCC pipe 4" dia, including laying & Rft 69.18 142.08 m 226.98 466.14
jointing in trenches
14-39-a Providing and Fixing brass stop/bib cock : 1/2" dia Each 34.72 179.92 Each 34.72 179.92
14-39-b Providing and Fixing brass stop/bib cock : 3/4" dia Each 34.72 225.29 Each 34.72 225.29
14-40 Hoisting & Placing in position precast RC latrine seat Each 209.25 209.25 Each 209.25 209.25
14-41-a Providing and Fixing CP waste coupling : 1.25" Each 39.68 262.32 Each 39.68 262.32
14-41-b Providing and Fixing CP waste coupling : 1.5" Each 39.68 299.83 Each 39.68 299.83
14-42-a Providing and Fixing rubber plug with chain : 1.25" Each 1.49 74.09 Each 1.49 74.09
14-42-b Providing and Fixing rubber plug with chain : 1.5" Each 1.49 86.19 Each 1.49 86.19
14-43-a Providing and Fixing waste pipe of PVC : 1.25" Each 34.72 83.12 Each 34.72 83.12
14-43-b Providing and Fixing waste pipe of PVC : 1.5" Each 34.72 116.39 Each 34.72 116.39
14-44-a Providing and Fixing flushing bend of PVC : 1.25" Each 24.80 67.15 Each 24.80 67.15
14-44-b Providing and Fixing flushing bend of PVC : 1.5" Each 24.80 97.40 Each 24.80 97.40

NWFP CSR 2008 - Approved 25-Aug-2008 Page 74 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-45-a Providing and Fixing CP bottle trough with waste pipe : Each 39.68 1,131.70 Each 39.68 1,131.70
1.25" i/d
14-45-b Providing and Fixing CP bottle trough with waste pipe : Each 39.68 1,322.28 Each 39.68 1,322.28
1.5" i/d
14-46-a Providing and Fixing angle iron brackets for : WHB and Each 39.68 112.28 Each 39.68 112.28
cistern
14-46-b Providing and Fixing angle iron brackets for : Sink Each 39.68 124.38 Each 39.68 124.38
14-47-a Providing and Fixing 1/2" dia connection including check Each 14.88 69.33 Each 14.88 69.33
nuts etc Plastic rubber connection
14-47-b Providing and Fixing 1/2" dia connection including check Each 14.88 81.43 Each 14.88 81.43
nuts etc Copper connection
14-47-c Providing and Fixing 1/2" dia connection including check Each 14.88 147.98 Each 14.88 147.98
nuts etc CP connection
14-48-a Providing and Fixing brass ball float valve 1/2" dia Each 34.72 179.92 Each 34.72 179.92
14-48-b Providing and Fixing brass ball float valve 3/4" dia Each 34.72 204.12 Each 34.72 204.12
14-48-c Providing and Fixing brass ball float valve 1" dia Each 34.72 337.22 Each 34.72 337.22
14-48-d Providing and Fixing brass ball float valve 1.25" dia Each 34.72 486.05 Each 34.72 486.05
14-48-e Providing and Fixing brass ball float valve 1.5" dia Each 34.72 657.87 Each 34.72 657.87
14-48-f Providing and Fixing brass ball float valve 2" dia Each 34.72 887.77 Each 34.72 887.77
14-49-a Providing and Fixing 4" dia MS high pressure seamwelded Rft 96.90 318.21 m 317.92 1,044.00
pipe & specials complete : 2" dia
14-49-b Providing and Fixing 4" dia MS high pressure seamwelded Rft 77.52 261.93 m 254.34 859.34
pipe & specials complete : 1" dia
14-50-a Providing and Fixing Audco type valve : 4" dia Each 387.50 10,067.50 Each 387.50 10,067.50
14-50-b Providing and Fixing Audco type valve : 2" dia Each 155.00 5,600.00 Each 155.00 5,600.00
14-50-c Providing and Fixing Audco type valve : 1" dia Each 116.25 1,931.25 Each 116.25 1,931.25
14-51-a Providing and Fixing pressure regulator : No. 103 Each 124.00 1,309.80 Each 124.00 1,309.80
14-51-b Providing and Fixing pressure regulator : No. 043 Each 124.00 1,092.00 Each 124.00 1,092.00
14-51-c Providing and Fixing pressure regulator : People type Each 124.00 704.80 Each 124.00 704.80
14-52-a Providing and Fixing high pressure flange type valve : 4" Each 387.50 10,672.50 Each 387.50 10,672.50
dia
14-52-b Providing and Fixing high pressure flange type valve : 2" Each 155.00 4,874.00 Each 155.00 4,874.00
dia
14-52-c Providing and Fixing high pressure flange type valve : 1" Each 77.50 1,892.50 Each 77.50 1,892.50
dia
14-53 Providing and Fixing nipple or bush 1/4" to 3/8" i/d Each 14.88 24.56 Each 14.88 24.56
14-54-a Providing and Fixing eclipse cock : 1" dia Each 77.50 803.50 Each 77.50 803.50
14-54-b Providing and Fixing eclipse cock : 3/4" dia Each 77.50 779.30 Each 77.50 779.30
14-55-a Providing and Fixing GI pipe & including specials Rft 30.94 156.78 m 101.52 514.38
complete 2" dia

NWFP CSR 2008 - Approved 25-Aug-2008 Page 75 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-55-b Providing and Fixing GI pipe & including specials Rft 30.94 131.07 m 101.52 430.02
complete 1.5" dia
14-55-c Providing and Fixing GI pipe & including specials Rft 30.94 110.80 m 101.52 363.53
complete 1.25" dia
14-55-d Providing and Fixing GI pipe & including specials Rft 17.98 79.69 m 58.98 261.44
complete 1" dia
14-55-e Providing and Fixing GI pipe & including specials Rft 17.89 61.94 m 58.70 203.20
complete 3/4" dia
14-55-f Providing and Fixing GI pipe & including specials Rft 15.47 46.93 m 50.76 153.98
complete 1/2" dia
14-56-a Providing and Fixing oxidized gas cock : 1" dia. Each 12.40 302.80 Each 12.40 302.80
14-56-b Providing and Fixing oxidized gas cock : 3/4" dia. Each 12.40 212.05 Each 12.40 212.05
14-56-c Providing and Fixing oxidized gas cock : 1/2" dia. Each 12.40 145.50 Each 12.40 145.50
14-57-a Providing and Fixing brass gas cock : 1/2" dia Each 2.48 117.43 Each 2.48 117.43
14-57-b Providing and Fixing brass gas cock : 3/4" dia Each 2.48 196.08 Each 2.48 196.08
14-58-a Providing and Fixing 1/4" CP or oxidized gas cock Single Each 14.88 55.42 Each 14.88 55.42
way
14-58-b Providing and Fixing 1/4" CP or oxidized gas cock Two Each 24.80 103.45 Each 24.80 103.45
way
14-58-c Providing and Fixing 1/4" CP or oxidized gas cock Three Each 39.68 148.58 Each 39.68 148.58
way
14-59-a Providing and Fixing approved best quality light burners Each 496.00 1,088.90 Each 496.00 1,088.90
Single
14-59-b Providing and Fixing approved best quality light burners Each 496.00 1,569.88 Each 496.00 1,569.88
Double
14-60-a Providing and Fixing approved best quality gas room Each 496.00 3,194.30 Each 496.00 3,194.30
heaters Single pannel
14-60-b Providing and Fixing approved best quality gas room Each 496.00 2,347.30 Each 496.00 2,347.30
heaters Double pannel
14-61-a Providing and Fixing approved best quality cooking range Each 496.00 10,720.50 Each 496.00 10,720.50
with 2 burners & oven
14-61-b Providing and Fixing approved best quality cooking range Each 496.00 10,720.50 Each 496.00 10,720.50
with 2 burners, oven & rostary
14-61-c Providing and Fixing approved best quality cooking range Each 496.00 14,048.00 Each 496.00 14,048.00
with 3 burners, oven & hot case
14-61-d Providing and Fixing approved best quality cooking range Each 496.00 14,048.00 Each 496.00 14,048.00
with 3 burners, oven, hot case & roastary
14-61-e Providing and Fixing approved best quality cooking range Each 496.00 14,350.50 Each 496.00 14,350.50
with 5 burners, oven, hot case & roastary
14-62-a Providing and Fixing approved best quality gas water Each 496.00 10,236.50 Each 496.00 10,236.50
heaters 20 gallons capacity

NWFP CSR 2008 - Approved 25-Aug-2008 Page 76 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-62-b Providing and Fixing approved best quality gas water Each 496.00 12,777.50 Each 496.00 12,777.50
heaters 30 gallons capacity
14-62-c Providing and Fixing approved best quality gas water Each 496.00 15,863.00 Each 496.00 15,863.00
heaters 50 gallons capacity
14-63-a Providing and Fixing gas cross burners : 6" Size Each 62.00 279.80 Each 62.00 279.80
14-63-b Providing and Fixing gas cross burners : 9" Size Each 62.00 400.80 Each 62.00 400.80
14-63-c Providing and Fixing gas cross burners : 12" Size Each 62.00 400.80 Each 62.00 400.80
14-64-a Providing and Fixing gas nozzle star burner with injector Each 148.80 487.60 Each 148.80 487.60
12" nozzle
14-64-b Providing and Fixing gas nozzle star burner with injector Each 148.80 784.05 Each 148.80 784.05
18" nozzle
14-64-c Providing and Fixing gas nozzle star burner with injector Each 148.80 1,026.05 Each 148.80 1,026.05
24" nozzle
14-64-d Providing and Fixing gas nozzle star burner with injector Each 148.80 1,177.30 Each 148.80 1,177.30
32" nozzle
14-65 Providing and Fixing flue pipe for gas room heater any Each 49.60 158.50 Each 49.60 158.50
type/make
14-66 Providing and Fixing gas twin burners with stand complete Each 148.80 4,383.80 Each 148.80 4,383.80
Imperial make
14-67 Providing and Fixing angle iron frame wall type brackets Pair 62.00 304.00 Pair 62.00 304.00
for gas room heater
14-68-a Providing and Fixing gas tandoor complete : 24" nozzle Each 387.50 1,022.75 Each 387.50 1,022.75
14-68-b Providing and Fixing gas tandoor complete : 32" nozzle Each 581.25 1,458.50 Each 581.25 1,458.50
14-68-c Providing and Fixing gas tandoor complete : 48" nozzle Each 581.25 2,384.15 Each 581.25 2,384.15
14-69-a-01 P/F Fibre Glass Water Tank 300 gallons Each 775.00 11,009.39 Each 775.00 11,009.39
14-69-a-02 P/F Fibre Glass Water Tank 400 gallons Each 775.00 13,796.83 Each 775.00 13,796.83
14-69-b-01 P/F Polyethylene Water Tank 200 gallons (Horizontal) Each 775.00 10,525.39 Each 775.00 10,525.39
14-69-b-02 Supplying and Fixing Polyethylene Water Tank 400 Each 1,581.00 18,880.32 Each 1,581.00 18,880.32
gallons (Vertical)
14-69-b-03 P/F Polyethylene Water Tank 500 gallons (Vertical) Each 1,581.00 21,928.84 Each 1,581.00 21,928.84
14-69-b-04 P/F Polyethylene Water Tank 1000 gallons (Vertical) Each 2,108.00 42,607.86 Each 2,108.00 42,607.86
14-69-b-05 P/F Polyethylene Water Tank 1500 gallons (Vertical) Each 3,162.00 61,490.68 Each 3,162.00 61,490.68
14-70-a Providing and Fixing of pipe type B nikasi system Rft 23.63 339.30 m 77.52 1,113.19
including testing in all respect 110 mm (using dadex, or eq)
14-70-b Providing and Fixing of pipe type B nikasi system Rft 23.63 188.36 m 77.52 617.99
including testing in all respect 75 mm (using dadex, or eq)
14-71-a Providing and Fixing of poly dex high pressure PPR(green Rft 15.47 81.02 m 50.76 265.83
including testing ect complete 25 mm(including all special
etc)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 77 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-71-b Providing and Fixing of poly dex high pressure PPR(green Rft 15.47 73.96 m 50.76 242.64
including testing ect complete 20 mm(including all special
etc)
14-72-a Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 25.83 m 1.94 4.24
complete 1/2" dia
14-72-b Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 32.84 m 1.94 5.39
complete 3/4" dia
14-72-c Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 39.85 m 1.94 6.54
complete 1" dia
14-72-d Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 46.86 m 1.94 7.69
complete 1.5" dia
14-72-e Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 53.87 m 1.94 8.84
complete 2" dia
14-72-f Providing of plumbing tape insulation on G.I pipe 20 Rft 11.81 60.88 m 1.94 9.99
complete 2.5" dia
14-73-a Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 636.00 m 5.09 104.33
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 1/2" dia
14-73-b Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 678.35 m 5.09 111.28
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 3/4" dia
14-73-c Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 817.50 m 5.09 134.10
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 1" dia
14-73-d Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 896.15 m 5.09 147.01
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 1.5" dia
14-73-e Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 926.40 m 5.09 151.97
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 2" dia
14-73-f Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 1,071.60 m 5.09 175.79
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 2.5" dia
14-73-g Providing of thermal insulation of high density (64kg/m3) 20 Rft 31.00 1,228.90 m 5.09 201.59
fiber glass pipe insulation faced with aluminium foil for
chilled/hot water piping complete 3" dia
14-74-a Providing and Fixing Gas water Geyser 30 gallons SG 35 Each 496.00 19,704.75 Each 496.00 19,704.75
DLX with imported Thermostat
14-74-b Providing and Fixing Gas water Geyser 35 gallons SG 35 Each 496.00 19,704.75 Each 496.00 19,704.75
DLX with imported Thermostat
14-75-a Providing & Fixing "Singer" Cooking Range Model 307 (3 Each 124.00 17,487.50 Each 124.00 17,487.50
Burners Black), Bigger size

NWFP CSR 2008 - Approved 25-Aug-2008 Page 78 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-75-b Providing & Fixing "Singer" Cooking Range Model 308 (3 Each 124.00 15,854.00 Each 124.00 15,854.00
Burners Black), Smaller size
14-76 Providing & Fixing "Singer" Cooking Range Model 310 (3 Each 124.00 19,786.50 Each 124.00 19,786.50
Burners White)
14-77 Providing & Fixing "Singer" Cooking Range Model 312 (5 Each 124.00 21,904.00 Each 124.00 21,904.00
Burners), (Automatic)
14-78 Supply and Fixing low level plastic flushing cistern. Each 77.50 1,015.25 Each 77.50 1,015.25
14-79-a Supply and fixing of 0.5 HP Monoblock water pump Each 306.90 6,701.75 Each 306.90 6,701.75
1.25"x1" single phase upto 72 ft head (Type SE) i/c all
accessories.
14-79-b Supply and fixing of 1.0 HP Monoblock water pump Each 306.90 8,250.55 Each 306.90 8,250.55
1.25"x1" single phase upto 90 ft head (Type SE) i/c all
accessories.
14-79-c Supply and fixing of 1.0 HP Monoblock water pump Each 306.90 9,187.09 Each 306.90 9,187.09
1.25"x1" single phase upto 88 ft head (Type DE-S2) i/c all
accessories.
14-79-d Supply and fixing of 1.5 HP Monoblock water pump Each 306.90 9,541.62 Each 306.90 9,541.62
1.25"x1" single phase upto 130 ft head (Type DE-S2) i/c
all accessories.
14-80-a Supply and fixing of 2.0 HP Monoblock water pump Each 306.90 13,202.17 Each 306.90 13,202.17
1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single
phase for 150 ft head with all accessories.
14-80-b Supply and fixing of 2.0 HP Monoblock water pump Each 306.90 14,155.65 Each 306.90 14,155.65
1.5"x1.5" 4 stage model DE-S4 single phase for 190 ft
head with all accessories.
14-80-c Supply and fixing of 2.0 HP Monoblock water pump Each 306.90 14,520.77 Each 306.90 14,520.77
2"x2" size 1 stage SE model single phase for 65 ft head
with all accessories and fittings.
14-81-a Supply and fixing of 3.0 HP Monoblock water pump Each 306.90 16,174.54 Each 306.90 16,174.54
1.5"x1.5" size 5 stage DE-S5 model single phase for 220 ft
head with all accessories
14-81-b Supply and fixing of 3.0 HP Monoblock water pump Each 306.90 19,877.74 Each 306.90 19,877.74
1.5"x1.25" size 6 stage DE-S6 model single phase for 260
ft head with all accessories
14-81-c Supply and fixing of 4.0 HP Monoblock water pump Each 306.90 21,006.67 Each 306.90 21,006.67
1.5"x1.25" size 7 stage DN-S7 model single phase for 300
ft head with all accessories
14-81-d Supply and fixing of 3.0 HP Monoblock water pump Each 542.50 21,003.60 Each 542.50 21,003.60
2.5"x2" size 2 stage DE-S2 model single phase for 100 ft
head with all accessories
14-81-e Supply and fixing of 4.0 HP Monoblock water pump Each 306.90 19,927.35 Each 306.90 19,927.35
1.5"x2" size 3 stage DN-S3 model single phase for 130 ft
head with all accessories
NWFP CSR 2008 - Approved 25-Aug-2008 Page 79 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 14 PLUMBING, SANITARY INSTALLATION AND GAS FITTINGS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
14-81-f Supply and fixing of 4.0 HP Monoblock water pump Each 542.50 21,129.74 Each 542.50 21,129.74
1.5"x2" size 4 stage DN-S4 model single phase for 160 ft
head with all accessories
14-81-g Supply and fixing of 3.0 HP Monoblock water pump Each 306.90 21,173.35 Each 306.90 21,173.35
3"x3" size 1 stage P.P model single phase for 60 ft head
with all accessories
14-81-h Supply and fixing of 4.0 HP Monoblock water pump Each 306.90 23,065.79 Each 306.90 23,065.79
3"x2.5" size 1stage P.P model single phase for 60 ft head
with all accessories
14-82-a Supply and fixing of 1.0 HP Deep well water pump 1"x1" Each 1,100.50 9,165.15 Each 1,100.50 9,165.15
size 1stage Jet S-1 model single phase for 60 ft suction
and upto 60 ft head with all accessories
14-82-b Supply and fixing of 2.0 HP Deep well water pump 1"x1" Each 1,100.50 12,423.68 Each 1,100.50 12,423.68
size 2 stage Jet S-2 model single phase for 80 ft suction
and upto 80 ft head with all accessories
14-82-c Supply and fixing of 3.0 HP Deep well water pump 1"x1" Each 1,100.50 15,085.68 Each 1,100.50 15,085.68
size 3 stage Jet S-3 model single phase for 120 ft suction
and upto 120 ft head with all accessories
14-82-d Supply and fixing of 4.0 HP Deep well water pump 1"x1" Each 1,100.50 17,829.96 Each 1,100.50 17,829.96
size 4 stage Jet S-4 model single phase for 160 ft suction
and upto 160 ft head with all accessories
14-83 Providing & Fixing Solar Geysers 35 gallons capacity (a Each 806.00 27,426.00 Each 806.00 27,426.00
product of Enercon, National Energy Conservation Centre
Islamabad)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 80 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-01-a-01 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 26.37 m 23.57 86.50
comp. On surface including clamps etc: 1/2" i/d
15-01-a-02 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 32.64 m 23.57 107.08
comp. On surface including clamps etc: 3/4" i/d
15-01-a-03 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 40.05 m 23.57 131.40
comp. On surface including clamps etc: 1" i/d
15-01-a-04 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 45.73 m 23.57 150.04
comp. On surface including clamps etc: 1.25" i/d
15-01-a-05 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 51.27 m 23.57 168.20
comp. On surface including clamps etc: 1.5" i/d
15-01-a-06 Supply and Erection MS conduit pipe for wiring purpose Rft 7.18 68.81 m 23.57 225.75
comp. On surface including clamps etc: 2" i/d
15-01-b-01 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 46.36 m 58.92 152.11
comp. Recessed in walls including chase etc : 1/2" i/d
15-01-b-02 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 52.63 m 58.92 172.68
comp. Recessed in walls including chase etc : 3/4" i/d
15-01-b-03 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 60.05 m 58.92 197.01
comp. Recessed in walls including chase etc : 1" i/d
15-01-b-04 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 65.73 m 58.92 215.65
comp. Recessed in walls including chase etc : 1.25" i/d
15-01-b-05 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 71.26 m 58.92 233.80
comp. Recessed in walls including chase etc : 1.5" i/d
15-01-b-06 Supply and Erection MS conduit pipe for wiring purpose Rft 17.96 85.47 m 58.92 280.40
comp. Recessed in walls including chase etc : 2" i/d
15-02-a-01 Supply and Erection PVC pipe for wiring purpose Rft 3.59 18.23 m 11.78 59.81
complete On surface including clamps etc: 1/2" i/d
15-02-a-02 Supply and Erection PVC pipe for wiring purpose Rft 3.59 9.70 m 11.78 31.81
complete On surface including clamps etc: 3/4" i/d
15-02-a-03 Supply and Erection PVC pipe for wiring purpose Rft 3.59 22.92 m 11.78 75.20
complete On surface including clamps etc: 1" i/d
15-02-a-04 Supply and Erection PVC pipe for wiring purpose Rft 5.30 36.29 m 17.39 119.06
complete On surface including clamps etc: 1.25" i/d
15-02-a-05 Supply and Erection PVC pipe for wiring purpose Rft 7.18 34.74 m 23.57 113.98
complete On surface including clamps etc: 1.5" i/d
15-02-a-06 Supply and Erection PVC pipe for wiring purpose Rft 4.58 30.62 m 15.02 100.47
complete On surface including clamps etc: 2" i/d
15-02-a-07 Supply and Erection PVC pipe for wiring purpose Rft 5.48 53.25 m 17.97 174.70
complete On surface including clamps etc: 3" i/d
15-02-a-08 Supply and Erection PVC pipe for wiring purpose Rft 7.07 63.33 m 23.19 207.76
complete On surface including clamps etc: 4" i/d
15-02-b-01 Supply and Erection PVC pipe for wiring purpose Rft 10.77 25.41 m 35.35 83.38
complete Recessed in walls including chase etc : 1/2" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 81 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-02-b-02 Supply and Erection PVC pipe for wiring purpose Rft 10.77 35.40 m 35.35 116.13
complete Recessed in walls including chase etc : 3/4" i/d
15-02-b-03 Supply and Erection PVC pipe for wiring purpose Rft 10.77 39.84 m 35.35 130.72
complete Recessed in walls including chase etc : 1" i/d
15-02-b-04 Supply and Erection PVC pipe for wiring purpose Rft 10.77 53.76 m 35.35 176.36
complete Recessed in walls including chase etc : 1.25" i/d
15-02-b-05 Supply and Erection PVC pipe for wiring purpose Rft 14.37 51.85 m 47.13 170.10
complete Recessed in walls including chase etc : 1.5" i/d
15-02-b-06 Supply and Erection PVC pipe for wiring purpose Rft 17.96 54.48 m 58.92 178.74
complete Recessed in walls including chase etc : 2" i/d
15-02-b-07 Supply and Erection PVC pipe for wiring purpose Rft 21.55 78.54 m 70.70 257.69
complete Recessed in walls including chase etc : 3" i/d
15-02-b-08 Supply and Erection PVC pipe for wiring purpose Rft 26.94 93.52 m 88.37 306.83
complete Recessed in walls including chase etc : 4" i/d
15-03-a Supply and Erection GI flexible pipe for wiring purpose Rft 4.15 32.92 m 13.61 108.02
complete 1/2" i/d
15-03-b Supply and Erection GI flexible pipe for wiring purpose Rft 6.00 48.06 m 19.70 157.67
complete 3/4" i/d
15-03-c Supply and Erection GI flexible pipe for wiring purpose Rft 7.01 67.51 m 22.99 221.48
complete 1" i/d
15-03-d Supply and Erection GI flexible pipe for wiring purpose Rft 7.59 87.28 m 24.92 286.34
complete 1.25" i/d
15-03-e Supply and Erection GI flexible pipe for wiring purpose Rft 7.59 102.03 m 24.92 334.76
complete 1.5" i/d
15-03-f Supply and Erection GI flexible pipe for wiring purpose Rft 12.44 128.27 m 40.81 420.84
complete 2" i/d
15-03-g Supply and Erection GI flexible pipe for wiring purpose Rft 12.83 202.80 m 42.11 665.37
complete 3" i/d
15-04-a Supply and Erection Sahl wood strip batten for wiring Rft 1.85 5.39 m 6.09 17.67 Additional width
complete 1/2" i/d required to
accommodate wire
will be provided by
erection of additional
strips.
15-04-b Supply and Erection Sahl wood strip batten for wiring Rft 1.85 8.41 m 6.09 27.59
complete 3/4" i/d
15-04-c Supply and Erection Sahl wood strip batten for wiring Rft 1.85 4.09 m 6.09 13.43
complete 1" i/d
15-05-a Supply and Erection single core PVC insulated copper Rft 2.50 8.73 m 8.21 28.65
conductor 250/440 V grade cable : 3/0.029"
15-05-b Supply and Erection single core PVC insulated copper Rft 2.51 12.96 m 8.25 42.53
conductor 250/440 V grade cable : 3/0.036"

NWFP CSR 2008 - Approved 25-Aug-2008 Page 82 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-05-c Supply and Erection single core PVC insulated copper Rft 2.36 12.94 m 7.73 42.47
conductor 250/440 V grade cable : 7/0.029"
15-05-d Supply and Erection single core PVC insulated copper Rft 2.36 16.32 m 7.73 53.54
conductor 250/440 V grade cable : 7/0.036"
15-05-e Supply and Erection single core PVC insulated copper Rft 5.89 25.25 m 19.33 82.85
conductor 250/440 V grade cable : 7/0.044"
15-05-f Supply and Erection single core PVC insulated copper Rft 8.84 50.14 m 28.99 164.52
conductor 250/440 V grade cable : 7/0.064"
15-05-g Supply and Erection single core PVC insulated copper Rft 14.73 118.01 m 48.32 387.19
conductor 250/440 V grade cable : 19/0.064"
15-06-a Supply and Erection single core PVC insulated+sheathed Rft 4.12 8.91 m 13.53 29.25
copper conductor 250/440 V grade cable : 3/0.029"
15-06-b Supply and Erection single core PVC insulated+sheathed Rft 4.12 11.13 m 13.53 36.51
copper conductor 250/440 V grade cable : 3/0.036"
15-06-c Supply and Erection single core PVC insulated+sheathed Rft 4.71 14.67 m 15.46 48.13
copper conductor 250/440 V grade cable : 7/0.029"
15-06-d Supply and Erection single core PVC insulated+sheathed Rft 4.71 31.27 m 15.46 102.60
copper conductor 250/440 V grade cable : 7/0.036"
15-06-e Supply and Erection single core PVC insulated+sheathed Rft 7.66 29.41 m 25.12 96.50
copper conductor 250/440 V grade cable : 7/0.044"
15-06-f Supply and Erection single core PVC insulated+sheathed Rft 11.78 57.90 m 38.66 189.95
copper conductor 250/440 V grade cable : 7/0.064"
15-07-a Supply and Erection single core PVC insulated & sheathed Rft 11.78 70.81 m 38.66 232.31
copper conductor, 660/1100V cable : 7/0.064"
15-07-b Supply and Erection single core PVC insulated & sheathed Rft 20.03 62.45 m 65.70 204.89
copper conductor, 660/1100V cable : 19/0.052"
15-07-c Supply and Erection single core PVC insulated & sheathed Rft 20.03 108.56 m 65.70 356.17
copper conductor, 660/1100V cable : 19/0.064"
15-07-d Supply and Erection single core PVC insulated & sheathed Rft 29.46 203.44 m 96.65 667.47
copper conductor, 660/1100V cable : 19/0.083"
15-07-e Supply and Erection single core PVC insulated & sheathed Rft 73.65 311.96 m 241.63 1,023.48
copper conductor, 660/1100V cable : 37/0.072"
15-07-f Supply and Erection single core PVC insulated & sheathed Rft 73.65 372.82 m 241.63 1,223.17
copper conductor, 660/1100V cable : 37/0.083"
15-07-g Supply and Erection single core PVC insulated & sheathed Rft 73.65 534.03 m 241.63 1,752.06
copper conductor, 660/1100V cable : 37/0.103"
15-08-a Supply and Erection twin core PVC insulated & sheathed Rft 2.94 12.17 m 9.66 39.91
copper conductor 250/440 V grade cable : 3/0.029"
15-08-b Supply and Erection twin core PVC insulated & sheathed Rft 2.94 17.33 m 9.66 56.86
copper conductor 250/440 V grade cable : 3/0.036"
15-08-c Supply and Erection twin core PVC insulated & sheathed Rft 4.12 24.78 m 13.53 81.29
copper conductor 250/440 V grade cable : 7/0.029"
NWFP CSR 2008 - Approved 25-Aug-2008 Page 83 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-08-d Supply and Erection twin core PVC insulated & sheathed Rft 4.12 40.31 m 13.53 132.26
copper conductor 250/440 V grade cable : 7/0.036"
15-08-e Supply and Erection twin core PVC insulated & sheathed Rft 4.12 50.24 m 13.53 164.82
copper conductor 250/440 V grade cable : 7/0.044"
15-08-f Supply and Erection twin core PVC insulated & sheathed Rft 4.12 89.33 m 13.53 293.08
copper conductor 250/440 V grade cable : 7/0.064"
15-09-a Supply and Erection MS sheet box of 16 SWG, 4"deep Each 44.17 89.55 Each 44.17 89.55
with 3/16" thick bakelite sheet top etc. complete : 4"x4"
15-09-b Supply and Erection MS sheet box of 16 SWG, 4"deep Each 58.90 119.40 Each 58.90 119.40
with 3/16" thick bakelite sheet top etc. complete : 7"x4"
15-09-c Supply and Erection MS sheet box of 16 SWG, 4"deep Each 73.63 152.27 Each 73.63 152.27
with 3/16" thick bakelite sheet top etc. complete : 9"x4"
15-09-d Supply and Erection MS sheet box of 16 SWG, 4"deep Each 88.35 254.73 Each 88.35 254.73
with 3/16" thick bakelite sheet top etc. complete : 8"x10"
15-09-e Supply and Erection MS sheet box of 16 SWG, 4"deep Each 106.02 323.82 Each 106.02 323.82
with 3/16" thick bakelite sheet top etc. complete : 10"x12"
15-09-f Supply and Erection MS sheet box of 16 SWG, 4"deep Each 123.69 456.44 Each 123.69 456.44
with 3/16" thick bakelite sheet top etc. complete : 12"x14"
15-10-a Supply and Erection Sahl wood board, 1.75" deep : 3" dia Each 8.84 14.89 Each 8.84 14.89
15-10-b Supply and Erection Sahl wood board, 1.75" deep : 4"x4" Each 26.50 33.76 Each 26.50 33.76
15-10-c Supply and Erection Sahl wood board, 1.75" deep : 7"x4" Each 26.50 62.81 Each 26.50 62.81
15-10-d Supply and Erection Sahl wood board, 1.75" deep : 8"x10" Each 26.50 74.90 Each 26.50 74.90
15-10-e Supply and Erection Sahl wood board, 1.75" deep : Each 29.45 89.95 Each 29.45 89.95
10"x12"
15-10-f Supply and Erection Sahl wood board, 1.75" deep : Each 29.45 114.15 Each 29.45 114.15
12"x14"
15-11-a-01 Supply and Erection of iron/aluminium clad, 500V main Each 265.05 567.55 Each 265.05 567.55 Reduce the labour
switch Double pole : 15/20 Amp. and composite rates
by 20 % in case, base
frame is already
installed.
15-11-a-02 Supply and Erection of iron/aluminium clad, 500V main Each 265.05 567.55 Each 265.05 567.55
switch Double pole : 30/35 Amp.
15-11-a-03 Supply and Erection iron/aluminium clad 500 volts main Each 265.05 1,233.05 Each 265.05 1,233.05
switch Double Pole : 60/65 Amp
15-11-a-04 Supply and Erection iron/aluminium clad 500 volts main Each 265.05 2,382.55 Each 265.05 2,382.55
switch Double Pole : 100 Amp
15-11-b-01 Supply and Erection of iron/aluminium clad, 500V main Each 265.05 567.55 Each 265.05 567.55
switch Triple pole with neutral link : 15/20 Amp.
15-11-b-02 Supply and Erection of iron/aluminium clad, 500V main Each 265.05 1,293.55 Each 265.05 1,293.55
switch Triple pole with neutral link : 30/35 Amp.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 84 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-11-b-03 Supply and Erection of iron/aluminium clad, 500V main Each 353.40 1,744.90 Each 353.40 1,744.90
switch Triple pole with neutral link : 60/65 Amp.
15-11-b-04 Supply and Erection of iron/aluminium clad, 500V main Each 441.75 2,619.75 Each 441.75 2,619.75
switch Triple pole with neutral link : 100 Amp.
15-12-a Supply and Erection or iron/aluminium clad, 500V main Each 147.25 3,777.25 Each 147.25 3,777.25 Reduce the labour
switch with triple pole, complete : 60 Amp. and composite rates
by 20 % in case, base
frame is already
installed.
15-12-b Supply and Erection or iron/aluminium clad, 500V main Each 147.25 4,382.25 Each 147.25 4,382.25
switch with triple pole, complete : 100 Amp.
15-12-c Supply and Erection or iron/aluminium clad, 500V main Each 235.60 5,075.60 Each 235.60 5,075.60
switch with triple pole, complete : 200 Amp.
15-12-d Supply and Erection or iron/aluminium clad, 500V main Each 235.60 6,043.60 Each 235.60 6,043.60
switch with triple pole, complete : 300 Amp.
15-12-e Supply and Erection or iron/aluminium clad, 500V main Each 235.60 8,463.60 Each 235.60 8,463.60
switch with triple pole, complete : 500 Amp.
15-13 Supply and Erection plain pendent lamp holder, complete Each 5.89 165.42 Each 5.89 165.42 Reduce the labour
with bakelite lamp holder & flexible twin wire of 2m and composite rates
by 20 % in case, base
frame is already
installed.
15-14 Supply and Erection 9" long swan neck plain Each 11.04 53.39 Each 11.04 53.39
brass/steel/brass oxidised bracket lamp holder, complete
15-15 Supply and Erection wall/pole type bracket with double Each 23.56 53.81 Each 23.56 53.81
cover water tight reflector, flexible wire & brass holder
15-16 Supply and Erection call bell 220/250V, fixed on Sahl Each 14.73 75.22 Each 14.73 75.22
wood board 7"x4"
15-17 Supply and Erection bell push or bed switch, with 5m. twin Each 4.42 58.38 Each 4.42 58.38
flexible wire 23/0.0076"
15-18-a Supply and Erection switches 10/15 Amp : Open type Each 8.84 45.13 Each 8.84 45.13
15-18-b Supply and Erection switches 10/15 Amp : Recessed type Each 8.84 48.16 Each 8.84 48.16
15-19-a Supply and Erection 3 pin 10/15 Amp. wall socket : Open Each 14.73 38.92 Each 14.73 38.92
type
15-19-b Supply and Erection 3 pin 10/15 Amp. wall socket : Each 14.73 38.92 Each 14.73 38.92
Recessed
15-20-a Supply and Erection 3 pin switch & plug combined Each 14.73 159.93 Each 14.73 159.93
recessed type : 5 Amp
15-20-b Supply and Erection 3 pin switch & plug combined Each 14.73 147.82 Each 14.73 147.82
recessed type : 10/15 Amp
15-21 Supply and Erection 3 pin 10/15 Amp. wall socket with Each 14.73 57.08 Each 14.73 57.08
shoe open type

NWFP CSR 2008 - Approved 25-Aug-2008 Page 85 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-22-a Supply and Erection button holder/angle holder Bakelite Each 7.36 34.59 Each 7.36 34.59
large size
15-22-b Supply and Erection button holder/angle holder Brass Each 7.36 55.76 Each 7.36 55.76
15-23-a Supply and Erection porcelain fuses (china made) with Each 14.73 75.22 Each 14.73 75.22
plastic sheet base on angle iron board : 10/15 Amp.
15-23-b Supply and Erection porcelain fuses (china made) with Each 14.73 75.22 Each 14.73 75.22
plastic sheet base on angle iron board : 30 Amp.
15-23-c Supply and Erection porcelain fuses (china made) with Each 14.73 184.13 Each 14.73 184.13
plastic sheet base on angle iron board : 60 Amp.
15-23-d Supply and Erection porcelain fuses (china made) with Each 14.73 232.52 Each 14.73 232.52
plastic sheet base on angle iron baord : 100 Amp.
15-23-e Supply and Erection porcelain fuses (china made) with Each 14.73 317.23 Each 14.73 317.23
plastic sheet base on angle iron board : 200 Amp.
15-24-a Supply and Erection tube light, including rod, choke etc Set 58.90 966.40 Set 58.90 966.40
complete Double rod (80 watts) with 2 chokes & 2 starters
15-24-b Supply and Erection tube light, including rod, choke etc Set 44.17 528.17 Set 44.17 528.17
complete Single rod (40 watts) with 1 choke & 1 starter
15-24-c Supply and Erection tube light, including rod, choke etc Each 32.40 165.49 Each 32.40 165.49
complete Round tube (10 watt) 1 choke + 1 starter w/o
cover
15-25 Supply and Erection girder clamp hook, 5/8" dia.for Each 14.73 63.13 Each 14.73 63.13
hanging ceiling fans
15-26-a Supply and Erection circuit breaker (imported) on sahl Each 44.17 304.32 Each 44.17 304.33
wood board complete : 2/5/15 Amp.
15-26-b Supply and Erection circuit breaker (imported) on sahl Each 44.17 316.42 Each 44.17 316.42
wood board complete : 20/25/30 Amp.
15-27 Supply and Erection stay for house service pipe, erected Rft 5.30 61.26 m 17.39 200.98
with straining screws and 7/14 SWG stay wire
15-28 Supply and Erection of house service pipe Henley or pole, Rft 7.07 191.54 m 23.19 628.40
type 2" dia. erected to install insulated wire etc
15-29 Supply and Erection shackle/pin insulator, medium size Each 14.73 535.03 Each 14.73 535.03
15-30 Supply and Erection bare copper conductor wire, No. 2 to kg 7.36 769.66 kg 7.36 769.66
16 SWG, including binding wire No. 16 SWG
15-31 Supply and Erection GI wire of sizes, including binding kg 7.36 104.16 kg 7.36 104.16
wire No. 16 SWG for support of rubber wire, pole to pole
15-32-a Wiring overhead line in 2 single core, PVC insulated cable Rft 4.12 43.14 m 13.53 141.54
with GI wire #8 SWG : 3/0.029"
15-32-b Wiring overhead line in 2 single core, PVC insulated cable Rft 4.12 51.86 m 13.53 170.14
with GI wire #8 SWG : 7/0.029"
15-32-c Wiring overhead line in 2 single core, PVC insulated cable Rft 4.12 58.61 m 13.53 192.29
with GI wire #8 SWG : 7/0.036"

NWFP CSR 2008 - Approved 25-Aug-2008 Page 86 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-32-d Wiring overhead line in 2 single core, PVC insulated cable Rft 7.07 72.35 m 23.19 237.37
with GI wire #8 SWG : 7/0.044"
15-33 Supply and Erection street light pole bracket 1.25" GI pipe Each 132.52 605.64 Each 132.52 605.64
2m. long, complete with 2 pole clamps
15-34 Supply and Fixing dust & weather proof street light fitting Each 235.60 6,285.60 Each 235.60 6,285.60
with reflector, 400W mercury vapour lamp etc comp.
15-35-a Supply and Erection pole mounted street light complete for Each 235.60 1,403.25 Each 235.60 1,403.25
fitting 125/250 W mercury lamp : GEC make
15-35-b Supply and Erection pole mounted street light complete for Each 235.60 3,018.60 Each 235.60 3,018.60
fitting 125/250 W mercury lamp : Philips make
15-36-a Supply and Fixing 125 W mercury vapour lamp with choke Each 58.90 506.60 Each 58.90 506.60
15-36-b Supply and Fixing 250 W mercury vapour lamp with choke Each 58.90 1,244.70 Each 58.90 1,244.70
15-36-c Supply and Fixing 400 W mercury vapour lamp with choke Each 58.90 2,569.65 Each 58.90 2,569.65
15-37 Supply and Fixing mercury sodium lamp 360 Sunlux 400 Each 58.90 1,571.40 Each 58.90 1,571.40
W complete with choke
15-38 Supply and Fixing mercury blended lamp 160 W Each 58.90 343.25 Each 58.90 343.25
15-39 Supply and Erection MS angle lattice structure pole 36' Each 3,534.00 15,634.00 Each 3,534.00 15,634.00 a) Increase/Reduce
long 14"sq at base & 8"sq. at top for elec. distribution composite rate of
addition/reduction in
height of pole above
ground level b) The
item does not cover
cost of excavation,
which is payable
separately.
15-40-a-01 Supply and Fixing GI tubular street light pole, 8' of 5" dia, Each 883.50 17,158.00 Each 883.50 17,158.00 The item does not
7' 4" dia, 5' of 3" dia, Single arm of 5' of 1.5" dia cover cost of
excavation, which is
payable separately.
15-40-a-02 Supply and Fixing GI tubular street light pole, 8' of 5" dia, Each 883.50 17,763.00 Each 883.50 17,763.00
7' 4" dia, 5' of 3" dia, Double arm of 5' of 1.5" dia
15-40-b-01 Supply and Fixing GI tubular street light pole, 8' of 4" dia, Each 883.50 14,133.00 Each 883.50 14,133.00
7' 3" dia, 5' of 2" dia, Single arm of 5' of 1.5" dia
15-40-b-02 Supply and Fixing GI tubular street light pole, 8' of 4" dia, Each 883.50 14,738.00 Each 883.50 14,738.00
7' 3" dia, 5' of 2" dia, Double arm of 5' of 1.5" dia
15-40-b-03 Providing street light poles of 40 ft height without arms Each 136.40 22,361.65 each 136.40 22,361.65
including fixing complete.
15-41 Earthing of iron clad/aluminium switches etc with GI wire Job 1,178.00 3,515.66 Job 1,178.00 3,515.66 The item does not
#8 SWG in GI pipe 0.5" dia cover cost of
excavation, which is
payable separately.
15-42 Supply and Erection 2'x2'x1/8" copper plate including Each 294.50 2,956.50 Each 294.50 2,956.50
rivetting to copper tape & placing in mixture of salt etc

NWFP CSR 2008 - Approved 25-Aug-2008 Page 87 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-43-a Supply and Erection copper tape, including copper stapple Rft 4.12 119.98 m 13.53 393.62
& copper nails etc : Size 1.5"x1/8"
15-43-b Supply and Erection copper tape, including copper stapple Rft 4.12 156.59 m 13.53 513.75
& copper nails etc : Size 2"x1/8"
15-44 Supply and Erection 1" dia & 1m long lightening Job 736.25 2,309.25 Job 736.25 2,309.25
conductor copper rod with 5 spikes ball & base etc.
15-45 Wiring of light/fan/call-bell point in 3/0.029 PVC insulated Each 17.67 653.41 Each 17.67 653.41
& sheathed cable on sahl wood strip
15-46 Wiring of 2/3-pin 5-Amp plug point in 3/0.029 PVC Each 17.67 418.37 Each 17.67 418.37
insulated & sheathed cable on sahl wood
15-47-a Wiring of main & sub-main in 2 single core PVC insulated Rft 3.68 25.44 m 12.08 83.48
& sheathed cable : 3/0.029
15-47-b Wiring of main & sub-main in 2 single core PVC insulated Rft 3.68 48.31 m 12.08 158.51
& sheathed cable : 7/0.029
15-47-c Wiring of main & sub-main in 2 single core PVC insulated Rft 5.89 104.39 m 19.32 342.48
& sheathed cable : 7/0.044
15-47-d Wiring of main & sub-main in 2 single core PVC insulated Rft 10.60 187.29 m 34.78 614.47
& sheathed cable : 7/0.064
15-48-a Wiring of sub main/earthing in 1 single core PVC insulated Rft 2.50 12.42 m 8.21 40.75
& sheathed cable : 3/0.029
15-48-b Wiring of sub main/earthing in 1 single core PVC insulated Rft 2.36 16.63 m 7.73 54.57
& sheathed cable : 7/0.029
15-48-c Wiring of sub main/earthing in 1 single core PVC insulated Rft 2.36 27.99 m 7.73 91.82
& sheathed cable : 7/0.044
15-48-d Wiring of sub main/earthing in 1 single core PVC insulated Rft 4.12 51.70 m 13.53 169.63
& sheathed cable : 7/0.064
15-49 Wiring of light point in 3/0.029 PVC insulated sheathed Each 28.27 1,125.04 Each 28.27 1,125.04
cable on sahl wood strip batten
15-50 Wiring of light/fan/call-bell point in 3/0.029 PVC insulated Each 26.50 867.02 Each 26.50 867.02
bare cable in PVC pipe recessed
15-51 Wiring of 2/3-pin 5-Amp. plug point in 3/0.029 PVC Each 12.96 432.75 Each 12.96 432.75
insulated bare cable in PVC pipe recessed
15-52 Wiring of light point in 3/0.029 PVC insulated bare cable Each 40.05 1,592.54 Each 40.05 1,592.54
in PVC pipe recessed in wall comp.
15-53 Special earthing of iron/metal clad switches etc with copper Each 471.20 6,220.81 Each 471.20 6,220.81
wire No. 8 SWG in GI pipe 1/2" dia
15-54 Supply and Erection enclosed switch of bakelite DP Each 29.45 271.81 Each 29.45 271.81
(China) 15/30 Amp. fixed on wooden board complete
15-55-a Supply and erection of fancy wall type bracket with brass Each 23.56 265.56 Each 23.56 265.56
holder & fancy shade : Single
15-55-b Supply and erection of fancy wall type bracket with brass Each 23.56 386.56 Each 23.56 386.56
holder & fancy shade : Double
NWFP CSR 2008 - Approved 25-Aug-2008 Page 88 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-56-a Supply and Erection white round globe with holder, gallery Each 29.45 285.97 Each 29.45 285.97
& 100 Watt bulb complete : 6" dia.
15-56-b Supply and Erection white round globe with holder, gallery Each 29.45 285.97 Each 29.45 285.97
& 100 Watt bulb complete : 8" dia.
15-56-c Supply and Erection white round globe with holder, gallery Each 29.45 406.97 Each 29.45 406.97
& 100 Watt bulb complete : 10" dia.
15-57-a Supply and Erection white flat globe with holder, gallery & Each 29.45 285.97 Each 29.45 285.97
100 W bulb complete : 8" dia
15-57-b Supply and Erection white flat globe with holder, gallery & Each 29.45 406.97 Each 29.45 406.97
100 W bulb complete : 10" dia
15-57-c Supply and Erection white flat globe with holder, gallery & Each 29.45 406.97 Each 29.45 406.97
100 W bulb complete : 12" dia
15-58 Supply and Erection white round globe 6" dia with angle Each 29.45 634.45 Each 29.45 634.45
type bakelite gallery, holder & 60-W bulb complete
15-59 Supply and Erection 1' long strip light fitting comp. with Each 58.90 319.05 Each 58.90 319.05
cover of opalescent perspex in plain finish 10-Watt
15-60 Supply and Erection double fluorescent tube light fitting 2 Each 73.63 799.63 Each 73.63 799.63
No. 4' long, 40-W with 2 chokes & starters complete
15-61-a Supply and Erection fluorescent tube light fitting including Each 58.90 784.90 Each 58.90 784.90
4' rod, choke, starter, flexible wire etc : Single
15-61-b Supply and Erection fluorescent tube light fitting including Each 58.90 905.90 Each 58.90 905.90
4' rod, choke, starter, flexible wire etc : Double
15-62 Supply and Erection porch-light fitting round/square type Each 44.17 467.67 Each 44.17 467.67
with gallery, holder & 40 W bulb
15-63-a Supply and Erection gate-light fitting complete with holder Each 58.90 663.90 Each 58.90 663.90
& 160-Watt mercury blended lamp: Small
15-63-b Supply and Erection gate-light fitting complete with holder Each 58.90 663.90 Each 58.90 663.90
& 160-Watt mercury blended lamp: Medium
15-63-c Supply and Erection gate-light fitting complete with holder Each 58.90 784.90 Each 58.90 784.90
& 160-Watt mercury blended lamp: Large
15-64-a Supply and Erection garden-light fitting with holder and Each 147.25 1,296.75 Each 147.25 1,296.75 The rate does not
160 W mercury blended lamp & choke : 18" dia include cost of GI
pipe and excavation
and are to be paid
separatively
15-64-b Supply and Erection garden-light fitting with holder and Each 147.25 1,478.25 Each 147.25 1,478.25
160 W mercury blended lamp & choke : 19" dia
15-64-c Supply and Erection garden-light fitting with holder and Each 147.25 1,962.25 Each 147.25 1,962.25
160 W mercury blended lamp & choke : 22" dia

NWFP CSR 2008 - Approved 25-Aug-2008 Page 89 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-65-a Supply and Erection garden-light fitting with porcelain Each 147.25 1,327.00 Each 147.25 1,327.00 The rate does not
holder 125 W mercury vapour lamp & choke : 18" dia include cost of GI
pipe and excavation
and are to be paid
separatively
15-65-b Supply and Erection garden-light fitting with porcelain Each 147.25 1,871.50 Each 147.25 1,871.50
holder 125 W mercury vapour lamp & choke : 19" dia
15-65-c Supply and Erection garden-light fitting with porcelain Each 147.25 2,355.50 Each 147.25 2,355.50
holder 125 W mercury vapour lamp & choke : 22" dia
15-66-a Supply and Erection flood-light fitting with holder, Each 147.25 1,962.25 Each 147.25 1,962.25
complete 14" dia with 500-W lamp
15-66-b Supply and Erection flood-light fitting with holder, Each 147.25 3,353.75 Each 147.25 3,353.75
complete 19«" dia with 1000-W lamp
15-67 Making hole in wall with necessary masonry work for Each 88.35 142.80 Each 88.35 142.80
exhaust fan any size complete
15-68-a Supply and Erection best quality AC ceiling fan complete Each 73.63 1,888.63 Each 73.63 1,888.63 Asia, Breeze, Climax,
with GI rod, canopy, blades & regulator : 36" sweep Millat, National &
Pak fans are the
approved makes.
15-68-b Supply and Erection best quality AC ceiling fan complete Each 73.63 2,130.63 Each 73.63 2,130.63
with GI rod, canopy, blades & regulator : 48" sweep
15-68-c Supply and Erection best quality AC ceiling fan complete Each 73.63 2,191.13 Each 73.63 2,191.13
with GI rod, canopy, blades & regulator : 56" sweep
15-69-a Supply and Erection best quality exhaust fan complete with Each 58.90 1,571.40 Each 58.90 1,571.40 Asia, Breeze, Climax,
shutter & regulator : 12"sweep Millat, National &
Pak fans are the
approved makes.
15-69-b Supply and Erection best quality exhaust fan complete with Each 58.90 1,752.90 Each 58.90 1,752.90
shutter & regulator : 16"sweep
15-69-c Supply and Erection best quality exhaust fan complete with Each 58.90 1,825.50 Each 58.90 1,825.50
shutter & regulator : 18"sweep
15-70-a Supply and Erection transpower auto circuit breaker Each 235.60 2,232.10 Each 235.60 2,232.10
3-phase, 400V fungus moisture proofing : 30 Amp.
15-70-b Supply and Erection transpower auto circuit breaker Each 235.60 1,506.10 Each 235.60 1,506.10
3-phase, 400V fungus moisture proofing : 60 Amp.
15-70-c Supply and Erection transpower auto circuit breaker Each 279.77 5,724.77 Each 279.77 5,724.77
3-phase, 400V fungus moisture proofing : 100 Amp.
15-71-a Supply and Erection single phase imported auto circuit Each 44.17 322.48 Each 44.17 322.48
breaker 6 Amp.
15-71-b Supply and Erection single phase imported auto circuit Each 44.17 467.67 Each 44.17 467.67
breaker 15 Amp.
15-71-c Supply and Erection single phase imported auto circuit Each 44.17 588.67 Each 44.17 588.67
breaker 20 Amp.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 90 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-71-d Supply and Erection single phase imported auto circuit Each 44.17 322.48 Each 44.17 322.48
breaker 30 Amp.
15-72-a Supply and Erection of bus bars for 500 volts 3 phase AC Each 511.50 4,365.35 Each 511.50 4,365.35
S/W 4 copper bars 40 Amp with bar size 1 1/2" X 1/8"
15-72-b Supply and Erection of bus bars 500 volts 3 phase AC Each 511.50 4,380.48 Each 511.50 4,380.48
supply with 4 copper bars - 100 Amp with bar size1 1 1/2"
X 1/8"
15-72-c Supply and Erection of bus bars 500 volts 3 phase AC Each 899.00 5,218.70 Each 899.00 5,218.70
supply with 4 copper bars - 200 Amp with bar size 2"X
1/8"
15-72-d Supply and Erection of bus bars 500 volts 3 phase AC Each 1,092.75 5,427.58 Each 1,092.75 5,427.58
supply with 4 copper bars - 300 Amp with bar zise 2" X
3/16"
15-72-e Supply and Erection of bus bars 500 volts 3 phase AC Each 1,271.00 8,040.95 Each 1,271.00 8,040.95
supply with 4 copper bars - 500 Amp with zise 2" X 1/4"
15-73-a Supply and Erection of bracket of channel 3" X 1 1/2" X Each 111.91 338.42 Each 111.91 338.42
1/4" section 2' long for 2 lines
15-73-b Supply and Erection of bracket of MS channel 3" X 1 1/2" Each 141.36 553.00 Each 141.36 553.00
X 1/4" Section:- 4' long for 4 lines
15-74 Supply and Erection of anchor rod honley type for poles Rft 4.35 48.34 m 14.26 158.59
i/e clamps & 7/13 SWG stay wire straning screws PCC
1:3:6
15-75-a Supply and Erection cubical type factory fabricated Each 1,472.50 9,821.50 Each 1,472.50 9,821.50
floor/wall mounting steel main board comp. : On surface
15-75-b Supply and Erection cubical type factory fabricated Each 1,708.10 10,057.10 Each 1,708.10 10,057.10
floor/wall mounting steel main board comp. : Recessed
15-76-a Flouresent tube lights fitting 2.5x2.5 feet square type Each 124.00 1,939.00 Each 124.00 1,939.00
suitable for fixing in recess or direct on complete with 4
Nos 2 ft 20 watts tubes, chokes, starters, holders complete
in all respect in steel body.
15-76-b Supply and Fixing of fluoresent tube fitting rectanglular each 124.00 1,576.00 Each 124.00 1,576.00
box types housing made of 22 SWG stave enamelled steel
sheet having spring load inner frame attachement with
acrylic or polythene complete with 2 No 4 ft 40 watts
15-77-a Supply and Fixing electric AC exhuast/fresh air each 196.85 1,644.36 Each 196.85 1,644.36
circulation(double way) 220/230 single phase plastic frame
body and blade complete 8"x8"
15-77-b Supply and Fixing electric AC exhuast/fresh air each 196.85 1,726.91 Each 196.85 1,726.91
circulation(double way) 220/230 single phase plastic frame
body and blade complete 10"x10"
15-77-c Supply and fixing electric AC exhaust/fresh air each 73.78 5,196.62 Each 73.78 5,196.62
circulation(Double way) 220/230 single phase plastic frame
body and blade complete 12"x12"
NWFP CSR 2008 - Approved 25-Aug-2008 Page 91 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 15 ELECTRIC INSTALLATIONS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
15-78 Supply and Fixing bracket fan pak made complete each 99.20 1,853.70 Each 99.20 1,853.70
15-79-a Supply and Fixing PVC conduit for surface wiring (dura Rft 4.54 8.77 m 14.88 28.78
duct) 1/2" including all charges for nail screws etc
15-79-b PVC conduit for surface wiring (dura duct) 1" including all Rft 4.54 10.34 m 14.88 33.94
charges for nail screws etc complete
15-79-c PVC conduit for surface wiring (dura duct) 1.5" including Rft 4.54 19.66 m 14.88 64.51
all charges for nail screws etc complete
15-79-d PVC conduit for surface wiring (dura duct) 2" including all Rft 4.54 26.32 m 14.88 86.34
charges for nail screws etc complete
15-80 Supply and Fixing dimmer switch complete each 49.60 122.20 Each 49.60 122.20
15-81 Supply and Fixing 20 Amp power plug each 49.60 182.70 Each 49.60 182.70
15-82 Supply and Fixing Asia porcelin power plug 30 Amp each 49.60 219.00 Each 49.60 219.00
15-83 Supply and fixing light plug 10 Amp each 49.60 110.10 Each 49.60 110.10
15-84 Supply and fitting of capacitor 2.2 uf for ceiling fans each 29.45 65.75 Each 29.45 65.75
15-85 Supply and fitting of ball bearing of size 6201, 6202 or each 36.81 145.71 Each 36.81 145.71
6203 for ceiling fans
15-86 Supply and erection of cut out, bakelite open type each 6.48 34.31 Each 6.48 34.31
15-87 Supply and erection of cut out bakelite Recessed type cut each 6.48 40.36 Each 6.48 40.36
out
15-88 Supply and erection of kit kat 500 volts 15/20 Amp each 10.58 57.77 Each 10.58 57.77
15-89 Supply and erection of kit kat 500 volts 30/35 Amp Each 11.86 95.35 Each 11.86 95.35
15-90 Supply and erection of kit kat 500 volts 60/65 Amp each 17.00 130.74 Each 17.00 130.74
15-91 Supply and erection of kit kat 500 volts 100 Amp each 20.37 243.01 Each 20.37 243.01
15-92 Supply and erection of kit kat 500 volts 200 Amp Each 23.52 391.36 Each 23.52 391.36
15-93 Supply and erection of kit kat 500 volts 300 Amp Each 23.52 391.36 Each 23.52 391.36
15-94 Supply and erection of kit kat 500 volts 400 Amp Each 29.14 359.47 Each 29.14 359.47
15-95-a Providing & Fixing Honda Generator EP 2500ex, 2.2 KVA Each 449.50 58,771.26 Each 449.50 58,771.26
Petrol driven.
15-95-b Providing & Fixing Honda Generator EP 2500ex, 2.2 KVA Each 449.50 61,796.26 Each 449.50 61,796.26
Petrol-cum-Gas driven
15-95-c Providing & Fixing Honda Generator EP 2800ex, 3.1 KVA Each 449.50 96,886.26 Each 449.50 96,886.26
Petrol-cum-Gas driven.
15-95-d Providing & Fixing Honda Generator EP 2800ex, 3.1 KVA Each 449.50 93,861.26 Each 449.50 93,861.26
Petrol driven.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 92 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-01 Providing and Laying sub-base course of brick on edge 100 Cft 2,222.39 8,159.25 m3 784.83 2,881.42 The Item has been
4.5" thick including compaction to required camber & Deleted
grade
16-02 Providing and Laying sub-base course of brick aggregate, 100 Cft 837.00 2,692.68 m3 295.58 950.91 To be used only when
including compaction to required camber, grade & density brick aggregate is
cheaper than stone
aggregate.
16-03-a Granular Sub Base Course using Pit Run Gravel 100 Cft 439.58 1,795.34 m3 155.24 634.02 a) The carriage of the
whole distance to side
of work shall be
calculated on the
basis of the rates of
the actual means of
transport used in
carriage that is i.e
road and rail is the
case may be. b) It
shall be payable from
the nearest approved
quarry.
16-03-b Granular Sub Base Using Crushed Stone Aggregate 100 Cft 265.98 2,439.20 m3 93.93 861.40 c) The quantity of pit
run or bed run gravel
in crush stone
aggregate for payment
of carriage shall be
taken as per actual
volume but not more
than 120 Cft.
16-04-a Aggregate Base Course 100 Cft 265.98 2,787.84 m3 93.93 984.52
16-04-b Water Bound Macadam Base Course 100 Cft 265.98 2,819.65 m3 93.93 995.75
16-05 Providing and Laying road edging of 3" wide & 9" deep 100 Rft 852.50 2,546.50 m 27.97 83.55
brick on end, complete
16-06 Bitumenous Prime Coat 100 Sft 7.20 738.79 m2 0.77 79.49
16-07 Bitumenous Tack Coat 100 Sft 20.16 332.74 m2 2.17 35.80
16-08-a Single bitumenous Surface Treatment 100 Sft 13.69 1,252.86 m2 1.47 134.81
16-08-b Double bitumenous Surface Treatment 100 Sft 20.83 2,607.88 m2 2.24 280.61
16-08-c Triple bitumenous Surface Treatment 100 Sft 34.44 3,158.15 m2 3.71 339.82
16-09-a Resurfacing of road complete with per 100sft : 22 Ibs. 100 Sft 35.03 809.16 m2 3.77 87.07
bitumen, 2.5"cft bajri/crush aggregate
16-09-b Resurfacing of road complete with per 100sft : 20 Ibs. 100 Sft 49.03 754.88 m2 5.28 81.23
bitumen, 2"cft bajri/crush aggregate
16-10 Scarifying/Dismantling old road surface, including removal 100 Sft 139.50 139.50 m2 15.01 15.01
of debris within one chain (NHA specified)
16-11-a Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 1" 100 Sft 149.73 1,810.34 m2 16.11 194.79
Thick, without prime coat or tack coat
NWFP CSR 2008 - Approved 25-Aug-2008 Page 93 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-11-b Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 1.5" 100 Sft 214.52 2,650.25 m2 23.08 285.17
Thick
16-11-c Dense Graded Hot Bitmac (Mobile Asphalt Mixer) 2" 100 Sft 279.31 3,510.59 m2 30.05 377.74
Thick
16-12-a Asphaltic Base Course (Asphalt Batch Plant Hot Mixed) 100 Cft 324.78 29,799.80 m3 114.70 10,523.71
16-12-b Asphaltic Wearing Course (Asphalt Batch Plant Hot 100 Cft 324.78 34,210.05 m3 114.70 12,081.18
Mixed)
16-12-c Carriage of asphalt concrete from asphalt batch plant to the Mile 0.00 5.35 t/km 0.00 5.35
site of work by dump trucks.
16-13 Providing RCC railing on bridges (3 feet high) 100 Rft 8,915.34 42,116.53 m 292.50 1,381.78 The rate includes the
cost of steel, its
fabrication, laying in
position and
fastening, including
cost of binding wire
and removal of rust
from the bars, etc
16-14 Providing and fixing GI pipe railing (3 feet high) 100 4,227.94 51,226.68 m/3rows 138.68 1,680.24
Rft/3rows
16-15-a P&E at site : RCC km stone Each 951.70 2,025.80 Each 951.70 2,025.80 The rate is for
complete item of
work according to
standard design
including cement
concrete foundation
block and painting
letters etc.
16-15-b P&E at site : RCC 1/10th km stone. Each 228.16 378.41 Each 228.16 378.41
16-15-c P&E at site : RCC boundry pillar. Each 140.43 645.26 Each 140.43 645.26
16-16-a Road signs (not exceeding 1 m2) without reflection sheet & 100 Sft 7,689.08 68,252.95 m2 827.35 7,344.02 The cost of pedestal,
lettering : Supply and Fixing at site with PCC 1:3:6 upto PCC and excavation
max 3' depth is included in the rate.
16-16-b Road signs (not exceeding 1 m2) without reflection sheet & 100 Sft 6,393.51 62,288.51 m2 687.94 6,702.24
lettering : Supply to the C&W store/site of work
16-17-a Road sign (any size) double pedestal 4"x2"x0.25" 11' long 100 Sft 8,824.27 55,585.34 m2 949.49 5,980.98 The cost of pedestal,
without reflection sheet & lettering: Supply and Fixing at PCC and excavation
site with PCC 1:3:6 max 3' depth is included in the rate.
16-17-b Road sign (any size) double pedestal 4"x2"x0.25" 11' long 100 Sft 9,835.06 46,740.15 m2 1,058.25 5,029.24
without reflection sheet & lettering: Supply to the C&W
store/site of work

NWFP CSR 2008 - Approved 25-Aug-2008 Page 94 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-18-a Supply and Fixing reflective sheet on MS/aluminium road 100 Sft 1,036.80 49,436.80 m2 111.56 5,319.40 a) The rate does not
signs etc including lettering : Diamond grade include the cost of
road signs b) The
work with sub-items a
and b shall only be
carried out on the
written permission of
the SE.
16-18-b Supply and Fixing reflective sheet on MS/aluminium road 100 Sft 1,036.80 27,656.80 m2 111.56 2,975.87
signs etc including lettering : High intensity grade
16-18-c Supply and Fixing reflective sheet on MS/aluminium road 100 Sft 1,036.80 7,086.80 m2 111.56 762.54
signs etc including lettering : Engineering grade
16-19-a-01 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 521.00 Each 279.00 521.00
Large, strip 146x30mm, 171 beads: Uni-direction
16-19-a-02 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 763.00 Each 279.00 763.00
Large, strip 146x30mm, 171 beads: Bi-direction
16-19-b-01 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 490.75 Each 279.00 490.75
Medium, strip 114x18mm, 74 beads: Uni-direction
16-19-b-02 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 702.50 Each 279.00 702.50
Medium, strip 114x18mm, 74 beads: Bi-direction
16-19-c-01 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 430.25 Each 279.00 430.25
Small, strip 75x14mm, 43 beads: Uni-directional
16-19-c-02 Supply and Fixing aluminium alloy road studs as per specs Each 279.00 581.50 Each 279.00 581.50
Small, strip 75x14mm, 43 beads: Bi-directional
16-19-c-03 Supply & Fixing Cat Eye single as specified Each 139.50 502.50 Each 139.50 502.50
16-20 Providing and Fixing gantry of structural steel sections as Cwt 1,015.75 5,275.48 kg 19.91 103.40 The cost of RCC base
per design / drawings including foundation complete for the foundation is
not included in the
rate which is payable
separately.
16-21 Providing and Laying dry brick pavement/soling in streets 100 Cft 1,147.00 7,459.31 m3 405.06 2,634.23 The nominal
etc including prep, water, compaction & sand cushion thickness of bricks
shall be taken for the
purpose of
measurement and
payment.
16-22 Supply & spreading 1"-1.5" guage shingle on road surface 100 Cft 4.18 1,042.05 m3 1.48 368.00 For different
including compaction thicknesses, rate is to
be calculated on
pro-rate basis.
16-23-a Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 8,689.92 40,053.74 m 285.10 1,314.10
460mm
16-23-b Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 10,865.78 60,657.72 m 356.49 1,990.08
610mm

NWFP CSR 2008 - Approved 25-Aug-2008 Page 95 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-23-c Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 13,039.29 81,252.15 m 427.80 2,665.75
760mm
16-23-d Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 15,210.86 115,031.41 m 499.04 3,774.00
910mm
16-23-e Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 17,384.59 152,131.34 m 570.36 4,991.18
1070mm
16-23-f Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 19,561.37 187,717.39 m 641.78 6,158.71
1220mm
16-23-g Reinforced Concrete Pipe Culvert (AASHTO M-170) Dia: 100 Rft 21,731.90 324,533.44 m 712.99 10,647.42
1520mm
16-24 Granular Material in Bed to RCC Pipe Culvert 100 Cft 260.70 3,141.22 m3 92.06 1,109.31
16-25-a Confirmatory Boring including SPT's, samples, lab test 100 Rft 90,732.04 160,823.70 m 2,976.77 5,276.37 a) The bore hole dia
bore-hole logs & Report : Alluvial Soils shall not be less than
200mm and the
method of execution
of pre-construction
boring shall be done
with casing and
appropriate to soil
encountered.
16-25-b Confirmatory Boring including SPT's, samples, lab test, 100 Rft 90,732.04 179,268.95 m 2,976.77 5,881.53 b) Preparation and
bore-hole logs, report : in Gravelly Soil submission of
bore-logs based on
soil classification
with SPT's values as
per BS-1377 is
included in the rate.
16-26-a Pile Load Testing : Max Load up to 240 tonne Job 0.00 377,898.63 Job 0.00 377,898.59 Rates includes all
material, equipment,
instruments and
temporary work
required to construct
test pile, load test and
load settlement
readings and
preparation of graphs
of the test pile.
16-26-b Pile Load Testing : Max Load 240 - 300 tonne Job 0.00 408,148.63 Job 0.00 408,148.59
16-26-c Pile Load Testing : Max Load 300 - 360 tonne Job 0.00 438,398.63 Job 0.00 438,398.59
16-26-d Pile Load Testing : Max Load 360 - 600 tonne Job 0.00 468,648.63 Job 0.00 468,648.59
16-27-a Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia 100 Rft 0.00 70,091.67 m 0.00 2,299.60
up to 760mm
16-27-b Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia 100 Rft 0.00 88,536.91 m 0.00 2,904.75
760 - 1220 mm

NWFP CSR 2008 - Approved 25-Aug-2008 Page 96 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-27-c Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia 100 Cft 0.00 110,670.23 m 0.00 3,630.91
1220 - 2000 mm
16-28-a Boring for Cast-in-place RCC Piles in Gravelly Soils : Dia 100 Rft 0.00 88,536.91 m 0.00 2,904.75
up to 660mm
16-28-b Boring for Cast-in-place RCC Piles in Gravelly Soils : Dia 100 Rft 0.00 140,183.34 m 0.00 4,599.19
660 - 910 mm
16-29 Supply fabricate & install welded MS lining in piles of Cwt 349.99 5,513.50 kg 6.86 108.06
thickness as per specs/drwg
16-30-a Supply and Fixing Neoprene Bearing Pad as per specs & Cubic 2.41 21.77 cm3 0.15 1.33
design Inch
16-30-b Supply and Fixing Steel Bearing Pads as per specs & Cwt 834.64 6,674.33 kg 16.36 130.82
design
16-34 Supply and Fixing spirally wound sheath of 50mm dia. for 100 Rft 510.23 3,146.94 m 16.74 103.25
pre-stressing of cables in precast conc. girders
16-35 Supply and Fixing stressing anchorages for high tensile Set 83.70 688.70 Set 83.70 688.70
steel wire cables in precast girders
16-36 Launching girders in place, including lifting & handli any Ft 221.15 294.90 m 725.57 967.53
number of time including temporary works comp
16-37 Stressing Cable of High Tensile Steel Wire Strands Each 474.30 837.30 Each 474.30 837.30
16-38 Inject Cement Grout in Sheath Pipe after stressing 100 Rft 396.84 1,590.94 m 13.02 52.20
16-39 Cut off projecting wire ends of cables & make good Each 83.05 142.04 Each 83.05 142.04
anchorage recess with 1:2:4 cem. conc.
16-40 Supply and place in position MS expansion joint Cwt 881.89 5,141.62 kg 17.29 100.78
assemblies as specified & as per drawing
16-41 Supply and place in position galvanised steel 3" dia drain Each 85.25 297.30 Each 85.25 297.30
scuppers in deck slab as per specs/drwg
16-42 Providing and Fixing rain water outlet of AC pipe Each 43.40 250.57 Each 43.40 250.57
16-43 Supply and Fixing polystrene fill in expansion joints & 100 Cft 2,169.81 2,308.96 m3 766.26 815.40
under diaphragms at transoms.
16-44 Providing and Laying expansion joint of neoprene strip 100 Rft 3,118.60 12,709.06 m 102.32 416.96
4"x1/4" and plastic bitumen
16-46 Repair to cracks to reinforced or plain cement concrete 100 Rft 1,216.75 1,936.09 m 39.92 63.52
work by grouting with cement gun in (1:2) cement sand
mortar including cutting the chase of required size.
16-47 Dismantling bitumen carpet of any description from 100 Sft 279.00 279.00 m2 30.02 30.02
existing roads surface including its removal and disposal
within 3 chains lead as desired.
16-48 Removing the existing worn out bitumanious surface 100 Sft 658.72 3,416.91 m2 70.88 367.66
having pot holes and ruts in patches of regular shape
brushing and re-carpeting with 1" thick (consolidated)
asphalt macadam as per specifications.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 97 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-49 Providing and Laying 1" thick(consolidated) asphalt 100 Sft 449.47 3,207.66 m2 48.36 345.14
macadam with liquid asphalt (cut backs) of any approved
grade with premixed sand seal coat, as specified.
16-50 Removing the existing worn out bitumanious surface pot 100 Sft 679.64 4,465.67 m2 73.13 480.51
holes and ruts in patches of regular shape brushing and
re-carpeting with 2" thick(consolidated) asphalt macadam
as per specificaiton complete
16-51 Providing and Laying 2" thick (consolidated) asphalt 100 Sft 470.39 4,256.42 m2 50.61 457.99
macadam with liquid asphalt(cut backs) of approved grade
with precoated bajri seal coat as specified.
16-52 Removing of existing worn out bitumanious surface pot 100 Sft 864.62 6,345.02 m2 93.03 682.72
holes and ruts in patches and re-carpeting with 3"
thick(consolidated) asphalt macadam as per
specifiedcomplete including disposal of excavated stuff
within one chain
16-53 Providing and Laying 3" thick (consolidated) asphalt 100 Sft 655.37 6,135.77 m2 70.52 660.21
macadam with liquid asphalt(cut backs) of approved grade
with precoated bajri seal coat as specified.
16-54 Surface dressing with bituman 80/100 or any other 100 Sft 18.94 2,057.71 m2 2.04 221.41
approved grade on a primary coat of liquid asphalt (cut
backs) of any approved grade primer at 22lbs&bituman at
35lbs with 5cft of 1/2 standard size bajri per %sft of road
surface complete with rolling.
16-55 Providing and Laying PVC pipe (b) 8" dia in foot path of 10 Rft 49.60 2,545.23 m 16.27 835.05
bridge for utilities.
16-56 Providing and filling sand behind abutment of bridges, 100 Cft 653.48 1,651.73 m3 230.77 583.30
culverts.
16-57 Formation of shoulder with permeable material less than 7 1000 Cft 932.48 10,588.24 m3 32.93 373.92
% from 200 seive and P.I less than 4 as specified by NHA
16-58-a Cold Milling of asphalt concrete 0-70 mm 100 Sft 41.85 897.56 m2 4.50 96.58
16-58-b Cold Milling of asphalt concrete 0-50 mm 100 Sft 27.90 622.94 m2 3.00 67.03
16-58-c Cold Milling of asphalt concrete 0-30 mm 100 Sft 16.74 351.10 m2 1.80 37.78
16-59 Seal Coat / Pad Coat 100 Sft 109.74 681.30 m2 11.81 73.31
16-60 Providing and Laying Asphalt concrete in pot holes/ deep 100 Cft 1,705.00 15,337.30 m3 602.12 5,416.32
patching upto 30 cm including ramming completel
16-61 Grooving in existing BT road of size 4x4 cm @ 2 meter 100 Sft 170.50 170.50 m2 18.35 18.35
c/c.
16-62 Leveling dressing and compaction with power roller of 100 Sft 356.50 646.88 m2 38.36 69.60
existing base coarse layer after asphalt scarification.
16-63-a Providing and fixing kerb stone (12"x18"x6") in cement 100 Rft 1,147.00 13,063.62 m 37.63 428.60
sand mortar 1:3 in center media or round about as
specified.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 98 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-63-b Providing and fixing kerb stone (12"x14"x6") in cement 100 Rft 1,147.00 12,458.62 m 37.63 408.75
sand mortar 1:3 in center media or round about as
specified.
16-63-c Providing and fixing kerb stone (12"x12"x6") in cement 100 Rft 1,147.00 11,853.62 m 37.63 388.90
sand mortar 1:3 in center media or round about as
specified.
16-64 Bailing out water by Mechanical mean. 100 Cft 5.74 26.91 m3 2.03 9.50
16-65-a Pavement marking in reflective thermoplast paint with 100 Rft 153.45 2,754.95 m 5.03 90.39
glass beads for line 15 cm width.
16-65-b Pavement marking in reflective thermoplast paint with 100 Rft 153.45 3,639.46 m 5.03 119.40
glass beads for line 20 cm width.
16-66-a Pavement marking in non-reflective thermoplast paint for 100 Rft 153.45 1,544.95 m 5.03 50.69
line 15 cm width.
16-66-b Pavement marking in non-reflective thermoplast paint for 100 Rft 153.45 2,018.06 m 5.03 66.21
line 20 cm width.
16-67-a Pavement marking in reflective chlorinated rubber paint 100 Rft 153.45 1,060.95 m 5.03 34.81
with glass beads for line 15 cm width.
16-67-b Pavement marking in reflective chlorinated rubber paint 100 Rft 153.45 1,369.50 m 5.03 44.93
with glass beads for line 20 cm width.
16-68-a Pavement marking in reflective chlorinated rubber paint for 100 Rft 153.45 818.95 m 5.03 26.87
line 15 cm width.
16-68-b Pavement marking in reflective chlorinated rubber paint 100 Rft 153.45 1,045.22 m 5.03 34.29
for line 20 cm width.
16-69 Providing & laying stone soling in water logged area 100 Cft 565.75 3,479.56 m3 199.79 1,228.80
including granular filling & compaction complete.
16-70 Tucking and chipping of road surface before hot surface 100 Sft 139.50 139.50 m2 15.01 15.01
dressing over existing road.
16-71 Leveling course on existing surface of road. 100 Cft 283.77 24,741.48 m3 100.21 8,737.38
16-72-a Jack Anchorage For 20 to 24 Wires 0.5" Strand Each 83.70 11,578.70 Each 83.70 11,578.70
(Comprising Trumpet, Stressing Block & Wedges
Complete)
16-72-b Jack Anchorage For 16 to 19 Wires 0.5" Strand Each 83.70 9,279.70 Each 83.70 9,279.70
(Comprising Trumpet, Stressing Block & Wedges
Complete)
16-72-c Jack Anchorage For 10 to 12 Wires 0.5" Strand Each 83.70 5,528.70 Each 83.70 5,528.70
(Comprising Trumpet, Stressing Block & Wedges
Complete)
16-72-d Jack Anchorage For 13 to 15 Wires 0.5" Strand Each 83.70 7,464.70 Each 83.70 7,464.70
(Comprising Trumpet, Stressing Block & Wedges
Complete)
16-72-e Jack Anchorage For 8 to 9 Wires 0.5" Strand (Comprising Each 83.70 4,318.70 Each 83.70 4,318.70
Trumpet, Stressing Block & Wedges Complete)
NWFP CSR 2008 - Approved 25-Aug-2008 Page 99 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 16 ROADS AND BRIDGES


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
16-72-f Jack Anchorage For 5 to 7 Wires 0.5" Strand (Comprising Each 83.70 3,471.70 Each 83.70 3,471.70
Trumpet, Stressing Block & Wedges Complete)
16-72-g Jack Anchorage For upto 4 Wires 0.5" Strand (Comprising Each 83.70 2,261.70 Each 83.70 2,261.70
Trumpet, Stressing Block & Wedges Complete)
16-73-a Un-galvanized Sheath for 20 to 24 Wires 0.5" Strand Cable Rft 5.10 129.73 m 16.73 425.62
16-73-b Un-galvanized Sheath for 16 to 19 Wires 0.5" Strand Cable Rft 5.10 112.79 m 16.73 370.05
16-73-c Un-galvanized Sheath for 13 to 15 Wires 0.5" Strand Cable Rft 5.10 97.06 m 16.73 318.44
16-73-d Un-galvanized Sheath for 10 to 12 Wires 0.5" Strand Cable Rft 5.10 84.96 m 16.73 278.74
16-73-e Un-galvanized Sheath for 8 to 9 Wires 0.5" Strand Cable Rft 5.10 77.70 m 16.73 254.92
16-73-f Un-galvanized Sheath for 5 to 7 Wires 0.5" Strand Cable Rft 5.10 70.44 m 16.73 231.10
16-73-g Un-galvanized Sheath for upto 4 Wires 0.5" Strand Cable Rft 5.10 59.55 m 16.73 195.37
16-73-h Stressing and Grouting for Cables upto 24/0.5" (Single End Each 623.10 2,075.10 Each 623.10 2,075.10
Stressing).
16-73-i Stressing and Grouting for Cables ranging from 13/0.5" to Each 415.40 1,867.40 Each 415.40 1,867.40
24/.05" (Single End Stressing).
16-73-j Stressing and Grouting for Cable below 13/0.5" (Single Each 297.60 1,749.60 Each 297.60 1,749.60
End Stressing).
16-74-a Supply of High Tensile Pre-stressed concrete steel wire Tonne 0.00 139,150.00 ton 0.00 141,382.94
strand Grade 270K 0.5" dia. Packed in standard
reeless/weldless coils of two 2000 kgs approximately
binded and wraped in Hessian Cloth.
16-74-b Supply of P.C Steel wire Dia 7 mm and 8 mm. Packed in tonne 0.00 127,050.00 ton 0.00 129,088.77
reeless coils of 600 kgs to 800kgs properly binded.
16-74-c Supply of P.C Steel wire Dia 4 mm and 5 mm. Packed in Tonne 0.00 114,950.00 ton 0.00 116,794.60
reeless coils of 600 kgs to 800kgs properly binded.
16-75-a Galvanized Sheath for 20 to 24 Wires 0.5" Strand Cable Rft 5.10 173.29 m 16.73 568.54
16-75-b Galvanized Sheath for 16 to 19 Wires 0.5" Strand Cable Rft 5.10 150.30 m 16.73 493.11
16-75-c Galvanized Sheath for 13 to 15 Wires 0.5" Strand Cable Rft 5.10 129.73 m 16.73 425.62
16-75-d Galvanized Sheath for 10 to 12 Wires 0.5" Strand Cable Rft 5.10 112.79 m 16.73 370.05
16-75-e Galvanized Sheath for 8 to 9 Wires 0.5" Strand Cable Rft 5.10 103.11 m 16.73 338.29
16-75-f Galvanized Sheath for 5 to 7 Wires 0.5" Strand Cable Rft 5.10 93.43 m 16.73 306.53
16-75-g Galvanized Sheath for upto 4 Wires 0.5" Strand Cable Rft 5.10 78.91 m 16.73 258.89
16-76-a Precast Reinfored Concrete Kerb New Jersy Barrier for 8 Rft 0.00 12,438.19 m 0.00 5,100.96
Median (Double Face)
16-76-b Precast Reinforced Concrete Kerb New Jersy Barrier for 8 Rft 0.00 8,659.55 m 0.00 3,551.32
Bridge (Single Face)
16-77 Repair to pot holes including cleaning, brushing, removal 100 Sft 917.91 3,836.66 m2 98.77 412.82
of loose material and filling of the same with clean stone of
size 0.75" to 1.5" with hot bitumen manual compaction
with rammer (water bound 3% biutmen)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 100 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 17 LINING OF CANALS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
17-01-a Formation, dressing and preparing sub-grade in bed 100 Sft 311.55 311.55 m2 33.52 33.52
17-01-b Formation, dressing and preparing sub-grade On slope 100 Sft 434.00 434.00 m2 46.70 46.70
17-02 Stabilized layer of cement, sand mortar 1:30 2" thick on 100 Sft 852.50 1,249.98 m2 91.73 134.50
slope
17-03-a 1/2" thick plaster of cement, sand motar 1:10 in bed 100 Sft 612.87 802.90 m2 65.94 86.39
17-03-b 1/2" thick plaster of cement, sand motar 1:10 On slope 100 Sft 782.75 972.78 m2 84.22 104.67
17-04-a 1«" thick plaster of cement, sand mortar 1:6 in bed 100 Sft 782.75 1,618.29 m2 84.22 174.13
17-04-b 1«" thick plaster of cement, sand mortar 1:6 On slope 100 Sft 999.75 1,835.29 m2 107.57 197.48
17-05-a 3/8" thick plaster of cement, sand mortar 1:3 in bed 100 Sft 612.87 947.10 m2 65.94 101.91
17-05-b 3/8" thick plaster of cement, sand mortar 1:3 On slope 100 Sft 782.75 1,116.98 m2 84.22 120.19
17-06-a Lining with Brick tiles 12"x6"x2", in c/s mortar 1:6 over a 100 Cft 3,076.75 12,091.76 m3 1,086.55 4,270.17 The rates covers
layer of 1/8" thick c/s mortar 1:6 (in bed) laying tiles including
mortar item 17.01 to
17.05 are payable
separately.
17-06-b Lining with Brick tiles 12"x6"x2", in c/s mortar 1:6 over a 100 Cft 3,503.00 12,518.01 m3 1,237.07 4,420.70
layer of 1/8" thick c/s mortar 1:6 (On slope)
17-07-a Lining with Brick tiles 12"x6"x2", in c/s mortar 1:3 over a 100 Cft 3,076.75 13,174.96 m3 1,086.55 4,652.70 ditto
layer of 1/8" thick c/s mortar 1:3 (in bed)
17-07-b Lining with Brick tiles 12"x6"x2", in c/s mortar 1:3 over a 100 Cft 3,503.00 13,601.21 m3 1,237.07 4,803.23
layer of 1/8" thick c/s mortar 1:3 (On slope)
17-08-a Lining with bricks 9"x4.5"x3" (First Class) in c/s mort. 1:6 100 Cft 3,076.75 10,549.01 m3 1,086.55 3,725.35 ditto
ove a layer of 1/8" thick c/s mortar 1:6 (in bed)
17-08-b Lining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:6 100 Cft 3,503.00 10,975.26 m3 1,237.07 3,875.88
over a layer of 1/8" thick c/s mortar 1:6 (On slope)
17-09-a Lining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:3 100 Cft 3,076.75 11,632.21 m3 1,086.55 4,107.88 ditto
over a layer of 1/8" thick c/s mortar 1:3 (in bed)
17-09-b Lining with bricks 9"x4.5"x3" (First Class), in c/s mort. 1:3 100 Cft 3,503.00 12,058.46 m3 1,237.07 4,258.41
over a layer of 1/8" thick c/s mortar 1:3 (On slope)
17-10-a-01 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,402.50 11,848.00 m3 848.44 4,184.09
aggregate : in bed : Ratio 1:2:4
17-10-a-02 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,402.50 9,916.00 m3 848.44 3,501.80
aggregate : in bed : Ratio 1:3:6
17-10-a-03 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,402.50 8,254.06 m3 848.44 2,914.90
aggregate : in bed : Ratio 1:4:8
17-10-b-01 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,828.75 12,274.25 m3 998.96 4,334.61
aggregate : On slope : Ratio 1:2:4
17-10-b-02 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,828.75 10,342.25 m3 998.96 3,652.33
aggregate : On slope : Ratio 1:3:6
17-10-b-03 4" thick PCC lining, using washed screened & graded stone 100 Cft 2,828.75 8,680.31 m3 998.96 3,065.43
aggregate : On slope : Ratio 1:4:8

NWFP CSR 2008 - Approved 25-Aug-2008 Page 101 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 17 LINING OF CANALS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
17-11-a Providing and Laying segments in Precast lining (Parabola Rft 117.64 445.25 m 385.97 1,460.80
type) Type A
17-11-b Providing and Laying segments in Precast lining (Parabola Rft 78.43 215.87 m 257.32 708.22
type) Type B
17-11-c Providing and Laying PCC segments in Precast lining Rft 63.96 158.34 m 209.85 519.50
(Parabola type) Type C
17-11-d Providing and Laying PCC segments in Precast lining Rft 63.96 135.10 m 209.85 443.24
(Parabola type) Type D
17-11-e Providing and Laying PCC segments in Precast lining Rft 58.80 112.69 m 192.90 369.72
(Parabola type) Type SPL D
17-11-f Providing and Laying PCC segments in Precast lining Rft 58.80 102.25 m 192.90 335.45
(Parabola type) Type E

NWFP CSR 2008 - Approved 25-Aug-2008 Page 102 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 18 SHEET PILING


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
18-01 Cutting Ransome & Larson piles. Each 147.25 147.25 Cut 147.25 147.25
18-02 Cutting universal piles Each 159.03 159.03 Cut 159.03 159.03
18-03-a Driving steel piles to depth of: Upto 15' Rft 43.81 43.81 m 143.72 143.72 a) The rates includes
laying and removing
of track and also
carriage way of piles
to machine, average
distance of 100 ft.
18-03-b Driving steel piles to depth of: More than 15' to 25' Rft 58.93 58.93 m 193.33 193.33 b) The rates are for
the trackle ganges
only supplied by the
contractor. Mechincal
staff on machine will
be supplied by the
Govt;
18-03-c Driving steel piles to depth of: More than 25' to 30' Rft 61.48 61.48 m 201.71 201.71 c) T-piles and
adjustable junction
piles will be counted
as two piles.
18-04 Dolleying piles upto 5' Each 130.20 130.20 Each 130.20 130.20
18-05 Drilling holes in piles by hand Each 17.67 17.67 Each 17.67 17.67
18-06 Raising and lowering machine Each 5,020.76 5,020.76 Each 5,020.76 5,020.76
18-07-a Turning Machine : 90 Job 2,883.00 2,883.00 Job 2,883.00 2,883.00
18-07-b Turning Machine : 135 Job 3,596.00 3,596.00 Job 3,596.00 3,596.00
18-07-c Turning Machine : 180 Job 4,619.00 4,619.00 Job 4,619.00 4,619.00
18-08 Travelling machine (light) 50 meter 4,501.20 4,501.20 50 m 4,501.20 4,501.20
18-09 Loading and unloading piles tonne 103.23 103.23 tonne 103.23 103.23 To be done by hand
carts or ramps,
including cost of
ropes.
18-10 Carriage of piling machine under different conditions 50 meter 2,317.25 2,317.25 50 m 2,317.25 2,317.25
18-11 Erecting piling machines Each 13,726.80 13,726.80 Each 13,726.80 13,726.80
18-12 Dismantling piling machine Each 13,726.80 13,726.80 Each 13,726.80 13,726.80

NWFP CSR 2008 - Approved 25-Aug-2008 Page 103 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-01 Cutting pilchi, frash or sarkanda including carriage within 100 Cft 530.10 530.10 m3 187.20 187.20
1.5 km.
19-02 Weaving matresses 100 Sft 1,004.40 1,004.40 m2 108.07 108.07
19-03-a Supply & fill used synthetic fibre/plastic bags 1.25cft Each 22.60 28.65 Each 22.60 28.65 The rate dones not
capacity with sand or earth, sewing & stacking : in dry include supply of
sand or earth for
filling of bags, which
shall be paid extra.
19-03-b Supply & fill used synthetic fibre/plastic bags 1.25cft Each 28.18 34.23 Each 28.18 34.23
capacity with sand or earth, sewing & stacking : Under
water
19-03-c Supply & fill used cotton bags 1.25 cft capacity with sand Each 22.60 38.33 each 22.60 38.33
or earth, sewing & stacking : in dry
19-03-d Supply & fill used cotton bags 1.25 cft capacity with sand Each 28.18 43.91 each 28.18 43.91
or earth, sewing & stacking : Under Water
19-04-a Supply & fill new synthetic fibre/plastic bags 4-5cft Each 90.40 103.71 Each 90.40 103.71 ditto
capacity with sand or earth,sewing, stacking : in dry
19-04-b Supply & fill new synthetic fibre/plastic bags 4-5cft Each 112.72 126.03 Each 112.72 126.03
capacity with sand or earth,sewing, stacking : Under water
19-04-c Supply & fill used cotton bags 4-5 cft capacity with sand or Each 90.40 117.02 Each 90.40 117.02
earth, sewing & stacking : in dry
19-04-d Supply & fill used cotton bags 4-5 cft capacity with sand or Each 112.72 139.34 Each 112.72 139.34
earth, sewing & stacking : Under Water
19-05-a Carriage of synthetic fibre/plastic bags 1.25 cft capacity 100 No. 114.39 114.39 100 No. 114.39 114.39
filled with sand / earth : 1st 50 m
19-05-b Carriage of synthetic fibre/plastic bags 1.25 cft capacity 100No/50 86.49 86.49 100No/50m 86.49 86.49
filled with sand / earth : 2nd & 3rd 50 m m
19-05-c Carriage of synthetic fibre/plastic bags 1.25 cft capacity 100No/50 9.49 9.49 100No/50m 9.49 9.49
filled with sand / earth : 4th and subsequent 50 m m
19-06-a Carriage of new synthetic fibre/plastic bags 4-5 cft capacity 100 No. 457.56 457.56 100 No. 457.56 457.56
filled with sand/earth : 1st 50 m
19-06-b Carriage of new synthetic fibre/plastic bags 4-5 cft capacity 100No/50 345.96 345.96 100No/50m 345.96 345.96
filled with sand/earth : 2nd & 3rd 50 m m
19-06-c Carriage of new synthetic fibre/plastic bags 4-5 cft capacity 100No/50 37.94 37.94 100No/50m 37.94 37.94
filled with sand/earth : 4th & subsequent 50 m m
19-07-a Rolling matresses to river edge & floating, after unrolling 100 Sft 306.90 306.90 m2 33.02 33.02
with area : Upto 200 m2
19-07-b Rolling matresses to river edge & floating, after unrolling 100 Sft 488.25 488.25 m2 52.54 52.54
with area : Over 200 to 250 m2
19-07-c Rolling matresses to river edge & floating, after unrolling 100 Sft 583.11 583.11 m2 62.74 62.74
with area : Over 250 m2
19-08 Sewing empty cement bags in sheets 100 No. 404.55 492.64 100 No. 404.55 492.64

NWFP CSR 2008 - Approved 25-Aug-2008 Page 104 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-09 Making compact round pilchi, frash or sarkanda round 100 Cft 544.05 544.05 m3 192.13 192.13 Measured in the
bundles of specified size for the work shape of compact
round bundles and of
size specified for the
work before filling at
site.
19-10 Launching the bundles mentioned in Item 19-09 above & 100 Cft 334.80 334.80 m3 118.23 118.23
placing in position
19-11-a Supply within 150m (500 feet) : Boulders 9" and above 100 Cft 1,009.98 1,009.98 m3 356.67 356.67
19-11-b Supply within 150m (500 feet) : Over size shingle 3" to 9" 100 Cft 675.18 675.18 m3 238.44 238.44
19-11-c Supply within 150m (500 feet): Mixed graded shingle 100 Cft 797.94 797.94 m3 281.79 281.79
19-12 Supplying munj or patha trungers (6" mesh to hold 3 cft) Each 69.75 102.60 Each 69.75 102.60
stones/boulders
19-13-a-01 Provide & weave GI wire netting for wire crates 6"x9" 100 Sft 651.00 1,014.00 m2 70.05 109.11
mesh : 15 SWG wire
19-13-a-02 Provide & weave GI wire netting for wire crates 6"x9" 100 Sft 651.00 1,828.03 m2 70.05 196.70
mesh : 10 SWG wire
19-13-a-03 Provide & weave GI wire netting for wire crates 6"x9" 100 Sft 651.00 2,899.45 m2 70.05 311.98
mesh : 8 SWG wire
19-13-b-01 Provide & weave GI wire netting for wire crates 6"x6" 100 Sft 781.20 1,060.71 m2 84.06 114.13
mesh : 15 SWG wire
19-13-b-02 Provide & weave GI wire netting for wire crates 6"x6" 100 Sft 781.20 1,686.88 m2 84.06 181.51
mesh : 10 SWG wire
19-13-b-03 Provide & weave GI wire netting for wire crates 6"x6" 100 Sft 781.20 2,504.42 m2 84.06 269.48
mesh : 8 SWG wire
19-13-c-01 Provide & weave GI wire netting for wire crates 4"x4" 100 Sft 868.00 1,288.17 m2 93.40 138.61
mesh : 15 SWG wire
19-13-c-02 Provide & weave GI wire netting for wire crates 4"x4" 100 Sft 868.00 2,226.53 m2 93.40 239.57
mesh : 10 SWG wire
19-13-c-03 Provide & weave GI wire netting for wire crates 4"x4" 100 Sft 868.00 3,452.28 m2 93.40 371.47
mesh : 8 SWG wire
19-14 Providing and Laying shingle on top of bund, including 100 Cft 279.00 1,065.50 m3 98.53 376.28
handling of materials within 100 m.
19-15-a Supply & dump at site, without boat, including handling 100 Cft 558.00 1,828.50 m3 197.06 645.73
within 100m : Stone or boulder
19-15-b Supply & dump at site, without boat, including handling 100 Cft 558.00 1,344.50 m3 197.06 474.81
within 100m : Shingle or spawls
19-15-c Supply & dump at site, without boat, including handling 100 Cft 418.50 2,838.50 m3 147.79 1,002.41
within 100m : Brick bats
19-16-a Supplying and dumping by boat, including loading within 100 Cft 1,395.00 2,605.00 m3 492.64 919.95
100m lead : Stone or boulder
19-16-b Supplying and dumping by boat, including loading within 100 Cft 1,395.00 2,181.50 m3 492.64 770.39
100m lead : Shingle or spawls
NWFP CSR 2008 - Approved 25-Aug-2008 Page 105 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-16-c Supplying and dumping by boat, including loading within 100 Cft 1,116.00 3,536.00 m3 394.11 1,248.73
100m lead : Brick bats
19-17-a Provide & fill brick bats in crates, excluding cost of crates : 100 Cft 697.50 3,117.50 m3 246.32 1,100.94
without hand packing.
19-17-b Provide & fill brick bats in crates, excluding cost of crates : 100 Cft 837.00 3,257.00 m3 295.58 1,150.20
with hand packing.
19-18-a Supply & fill bricks in wire crates including sewing crates, 100 Cft 602.64 1,812.64 m3 212.82 640.13
excl cost of crates : Stone or boulder
19-18-b Supply & fill bricks in wire crates including sewing crates, 100 Cft 599.85 1,386.35 m3 211.84 489.59
excl cost of crates : Shingle or spawls
19-19 Extra for anchoring boat for dumping by boats or tipping 100 Cft 55.80 55.80 m3 19.71 19.71
crates
19-20 Extra for tipping crates (in addition to achoring boats) 100 Cft 558.00 558.00 m3 197.06 197.06
19-21 Pilchi revetment, including carriage upto 1.5 km 100 Sft 279.00 1,852.00 m2 30.02 199.28
19-22 Surface protection with pilchi matresses including carriage 100 Sft 0.00 36.30 m2 0.00 3.91
upto 1.5 km.
19-23 Pilchi, sarkanda or frash pitching on slopes, incl supply 100 Sft 558.00 7,181.54 m2 60.04 772.73
within 1.5 km, pegging & tying with wire
19-24-a P&E groynes, vertical wooden stakes 7"-12" dia Upto 1.5 100 Sft 589.00 4,097.88 m2 63.38 440.93
m high, single row of stakes at 0.3m
19-24-b P&E groynes, vertical wooden stakes 7"-12" dia Upto 3 m 100 Sft 1,038.50 5,031.38 m2 111.74 541.38
high, double row of stakes at 0.6m
19-25 Providing and Laying stone pithcing/filling, dry hand 100 Cft 868.00 3,046.00 m3 306.53 1,075.69
packed in pitching & aprons
19-26 Supplying stone and stone filling in GI wire crate and its 100 Cft 899.00 3,077.00 m3 317.48 1,086.63
sewing, excluding cost of crates
19-27 Providing and Laying stone pitching with hammer dressed 100 Cft 2,015.00 4,628.60 m3 711.59 1,634.58
stones on surface, laid in courses
19-28-a Providing and Laying stone pitching for top layer only : On 100 Cft 2,573.00 5,186.60 m3 908.65 1,831.63
slope
19-28-b Providing and Laying stone pitching for top layer only : On 100 Cft 2,015.00 4,628.60 m3 711.59 1,634.58
level
19-29-a Providing and Laying stone or spawl filling : On slope 100 Cft 426.25 2,822.05 m3 150.53 996.60
19-29-b Providing and Laying stone or spawl filling : On level 100 Cft 356.50 2,752.30 m3 125.90 971.97
19-30-a Providing and Laying grouted stone pitching, in 1:8 c/s 100 Cft 3,146.50 7,222.54 m3 1,111.18 2,550.62
mortar Top layer on slope
19-30-b Providing and Laying grouted stone pitching, in 1:8 c/s 100 Cft 2,573.00 6,649.04 m3 908.65 2,348.09
mortar Top layer on level
19-30-c Providing and Laying grouted stone pitching, in 1:8 c/s 100 Cft 2,146.75 6,222.79 m3 758.12 2,197.56
mortar Stone pitching/filling on slope or on level
19-31-a Grouting stone pitching or apron etc, in : Cement, sand 100 Sft 1,209.00 4,047.21 m2 130.09 435.48
mortar 1:3
NWFP CSR 2008 - Approved 25-Aug-2008 Page 106 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-31-b Grouting stone pitching or apron etc, in : Cement, sand 100 Sft 1,209.00 2,633.83 m2 130.09 283.40
mortar 1:8
19-32 Sand grouting in stone apron, with high pressure hose 100 Sft 426.25 907.22 m2 45.86 97.62
19-33 Grouting stone filling or pitching with bajri 100 Cft 348.75 802.50 m3 123.16 283.40
19-34 Remove stone & repitching hand packed, on slopes or 100 Cft 2,046.00 2,046.00 m3 722.54 722.54
level, making good damaged portion
19-35 Collect & stack boulders from nullah beds or loose shale 100 Cft 837.00 837.00 m3 295.58 295.58
etc within 100m lead
19-36 Levelling and dressing stone filling under blocks and 100 Cft 426.25 662.20 m3 150.53 233.85
grouting with shingle
19-37 Grouting jharies between blocks with bajri 100 Cft 713.00 1,166.75 m3 251.79 412.03
19-38-a Breaking stone into spawls and stacking 100 Cft 418.50 418.50 m3 147.79 147.79
19-38-b Stone pitching with hammer dressed stone on surface laid 100 Cft 2,720.25 5,333.85 m3 960.65 1,883.63
in courses including carriage of material with in 91.50 (300
feet) meters.
19-38-c Stone pitching hand packed with surface levelled off to the 100 Cft 3,146.50 7,199.76 m3 1,111.18 2,542.57
correct section with hammer dressed stone and voids filled
in 1:8 cement mortar in floors of bridges and along banks
and in aprons etc including 91.50 meter lead.
19-38-d Removing stone and repitching, hand packed on slopes 100 Cft 1,131.50 1,131.50 m3 399.59 399.59
after making good damage slope.
19-38-e Collecting and stacking boulders from nullah beds or loose 100 Cft 558.00 558.00 m3 197.06 197.06
shale from any other site, within 91.50 (300 feet) meter
lead
19-38-f-01 Stone pitching for top layer only on slop 100 Cft 2,573.00 5,186.60 m3 908.65 1,831.63
19-38-f-02 Stone pitching for top layer only on Bed 100 Cft 2,015.00 4,628.60 m3 711.59 1,634.58
19-38-g-01 Laying stone or spawl filling. a)on level 100 Cft 356.50 2,752.30 m3 125.90 971.97
19-38-g-02 Laying stone or spawl filling. a)on slop 100 Cft 426.25 2,822.05 m3 150.53 996.60
19-39-a Fix floating spurs, with material from canal plantation Each 14.26 14.26 Each 14.26 14.26
within 1 km : Upto 2' FS depth
19-39-b Fix floating spurs, with material from canal plantation Each 20.24 20.24 Each 20.24 20.24
within 1 km : Over 2' to 3' FS depth
19-39-c Fix floating spurs, with material from canal plantation Each 28.52 28.52 Each 28.52 28.52
within 1 km : Over 3' to 4' FS depth
19-39-d Fix floating spurs, with material from canal plantation Each 57.04 57.04 Each 57.04 57.04
within 1 km : Exceeding 4' depth
19-40-a-01 Stake & bush from canal plantation etc : Pegs 3.5' long, 100 No. 929.07 1,171.07 100 No. 929.07 1,171.07 Royalty to be paid to
3"-6" dia: Unsharpened within 1km the forest Department
or cost to the private
owner, as the case
may be, if and when
required.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 107 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-40-a-02 Stake & bush from canal plantation etc : Pegs 3.5' long, 100 No. 441.75 441.75 100 No. 441.75 441.75
3"-6" dia: Sharpening one end
19-40-a-03 Stake & bush from canal plantation etc : Pegs 3.5' long, 100 No. 348.75 348.75 100 No. 348.75 348.75
3"-6" dia: Driving 1' below ground
19-40-a-04 Stake & bush from canal plantation etc : Pegs 3.5' long, 100 Rft 139.50 157.65 100 Rft 139.50 157.65
3"-6" dia: Tying with munj, patha ban
19-40-a-05 Stake & bush from canal plantation etc : Pegs 3.5' long, 100 Rft 976.50 1,339.50 100 Rft 976.50 1,339.50
3"-6" dia: Wattle+intertwine brushwood
19-40-b-01 Stake & bush from canal plantation etc : Pegs 4' long, 3"-6" 100 No. 1,068.57 1,431.57 100 No. 1,068.57 1,431.57
dia: Unsharpened within 1km
19-40-b-02 Stake & bush from canal plantation etc : Pegs 4' long, 3"-6" 100 No. 441.75 441.75 100 No. 441.75 441.75
dia: Sharpening one end
19-40-b-03 Stake & bush from canal plantation etc : Pegs 4' long, 3"-6" 100 No. 488.25 488.25 100 No. 488.25 488.25
dia: Driving 1.25' below ground
19-40-b-04 Stake & bush from canal plantation etc : Pegs 4' long, 3"-6" 100 Rft 139.50 157.65 100 Rft 139.50 157.65
dia: Tying with munj, patha ban
19-40-b-05 Stake & bush from canal plantation etc : Pegs 4' long, 3"-6" 100 Rft 1,185.75 1,548.75 100 Rft 1,185.75 1,548.75 ditto
dia: Wattle+intertwine brushwood
19-40-c-01 Stake & bush from canal plantation etc : Pegs 5' long, 3"-6" 100 No. 1,286.50 1,528.50 100 No. 1,286.50 1,528.50
dia: Unsharpened within 1km
19-40-c-02 Stake & bush from canal plantation etc : Pegs 5' long, 3"-6" 100 No. 471.20 471.20 100 No. 471.20 471.20
dia: Sharpening one end
19-40-c-03 Stake & bush from canal plantation etc : Pegs 5' long, 3"-6" 100 No. 412.30 412.30 100 No. 412.30 412.30
dia: Driving 1.5' below ground
19-40-c-04 Stake & bush from canal plantation etc : Pegs 5' long, 3"-6" 100 Rft 139.50 157.65 100 Rft 139.50 157.65
dia: Tying with munj, patha ban
19-40-c-05 Stake & bush from canal plantation etc : Pegs 5' long, 3"-6" 100 Rft 1,450.80 1,813.80 100 Rft 1,450.80 1,813.80 Royalty to be paid to
dia: Wattle+intertwine brushwood the forest Department
or cost to the private
owner, as the case
may be, if and when
required.
19-40-d-01 Stake & bush from canal plantation etc : Pegs 6' long, 3"-6" 100 No. 1,573.25 1,815.25 100 No. 1,573.25 1,815.25
dia: Unsharpened within 1km
19-40-d-02 Stake & bush from canal plantation etc : Pegs 6' long, 3"-6" 100 No. 547.77 547.77 100 No. 547.77 547.77
dia: Sharpening one end
19-40-d-03 Stake & bush from canal plantation etc : Pegs 6' long, 3"-6" 100 No. 485.77 485.77 100 No. 485.77 485.77
dia: Driving 1.75' below ground
19-40-d-04 Stake & bush from canal plantation etc : Pegs 6' long, 3"-6" 100 Rft 139.50 157.65 100 Rft 139.50 157.65
dia: Tying with munj, patha ban
19-40-d-05 Stake & bush from canal plantation etc : Pegs 6' long, 3"-6" 100 Rft 1,813.50 2,176.50 100 Rft 1,813.50 2,176.50 ditto
dia: Wattle+intertwine brushwood

NWFP CSR 2008 - Approved 25-Aug-2008 Page 108 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-40-e-01 Stake & bush from canal plantation etc : Pegs 8' long, 4"-8" 100 No. 3,286.00 3,528.00 100 No. 3,286.00 3,528.00
dia: Unsharpened within 1km
19-40-e-02 Stake & bush from canal plantation etc : Pegs 8' long, 4"-8" 100 No. 689.13 689.13 100 No. 689.13 689.13
dia: Sharpening one end
19-40-e-03 Stake & bush from canal plantation etc : Pegs 8' long, 4"-8" 100 No. 537.23 537.23 100 No. 537.23 537.23
dia: Driving 2' below ground
19-40-e-04 Stake & bush from canal plantation etc : Pegs 8' long, 4"-8" 100 Rft 139.50 161.28 100 Rft 139.50 161.28
dia: Tying with munj, patha ban
19-40-e-05 Stake & bush from canal plantation etc : Pegs 8' long, 4"-8" 100 Rft 2,092.50 2,455.50 100 Rft 2,092.50 2,455.50 ditto
dia: Wattle+intertwine brushwood
19-41-a-01 Stake, market bamboo, bush from any source 8'-10' long, 100 No. 0.00 18,150.00 100 No. 0.00 18,150.00 ditto
2.5"-5" dia : Supply bamboo
19-41-a-02 Stake, market bamboo, bush from any source 8'-10' long, 100 No. 589.00 589.00 100 No. 589.00 589.00
2.5"-5" dia : Sharpen one end
19-41-a-03 Stake, market bamboo, bush from any source 8'-10' long, 100 No. 620.00 620.00 100 No. 620.00 620.00
2.5"-5" dia : Driving bamboo 2.5'
19-41-a-04 Stake, market bamboo, bush from any source 8'-10' long, 100 Rft 279.00 300.78 100 Rft 279.00 300.78
2.5"-5" dia : Tying bamboo with wire
19-41-a-05 Stake, market bamboo, bush from any source 8'-10' long, 100 Rft 2,650.50 3,231.30 100 Rft 2,650.50 3,231.30 Royalty to be paid to
2.5"-5" dia : Wattle & intertwine the forest Department
or cost to the private
owner, as the case
may be, if and when
required.
19-41-b-01 Stake, market bamboo, bush from any source 10'-12' long, 100 No. 0.00 21,780.00 100 No. 0.00 21,780.00
2.5"-5" dia : Supply bamboo
19-41-b-02 Stake, market bamboo, bush from any source 10'-12' long, 100 No. 689.13 689.13 100 No. 689.13 689.13
2.5"-5" dia : Sharpen one end
19-41-b-03 Stake, market bamboo, bush from any source 10'-12' long, 100 No. 651.00 651.00 100 No. 651.00 651.00
2.5"-5" dia : Driving bamboo 2.75'
19-41-b-04 Stake, market bamboo, bush from any source 10'-12' long, 100 Rft 139.50 1,582.43 100 Rft 139.50 1,582.43
2.5"-5" dia : Tying bamboo with wire
19-41-b-05 Stake, market bamboo, bush from any source 10'-12' long, 100 Rft 3,292.20 4,018.20 100 Rft 3,292.20 4,018.20 ditto
2.5"-5" dia : Wattle & intertwine
19-41-c-01 Stake, market bamboo, bush from any source 12'-14' long, 100 No. 0.00 25,410.00 100 No. 0.00 25,410.00
2.5"-5" dia : Supply bamboo
19-41-c-02 Stake, market bamboo, bush from any source 12'-14' long, 100 No. 777.48 777.48 100 No. 777.48 777.48
2.5"-5" dia : Sharpen one end
19-41-c-03 Stake, market bamboo, bush from any source 12'-14' long, 100 No. 723.23 723.23 100 No. 723.23 723.23
2.5"-5" dia : Driving bamboo 3.5'
19-41-c-04 Stake, market bamboo, bush from any source 12'-14' long, 100 Rft 139.50 1,582.43 100 Rft 139.50 1,582.43
2.5"-5" dia : Tying bamboo with wire

NWFP CSR 2008 - Approved 25-Aug-2008 Page 109 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 19 PROTECTION AND DIVERSION WORKS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
19-41-c-05 Stake, market bamboo, bush from any source 12'-14' long, 100 Rft 3,841.83 4,858.23 100 Rft 3,841.83 4,858.23 ditto
2.5"-5" dia : Wattle & intertwine
19-41-d-01 Stake, market bamboo, bush from any source 14'-16' long, 100 No. 0.00 29,040.00 100 No. 0.00 29,040.00
2.5"-5" dia : Supply bamboo
19-41-d-02 Stake, market bamboo, bush from any source 14'-16' long, 100 No. 883.50 883.50 100 No. 883.50 883.50
2.5"-5" dia : Sharpen one end
19-41-d-03 Stake, market bamboo, bush from any source 14'-16' long, 100 No. 806.00 806.00 100 No. 806.00 806.00
2.5"-5" dia : Driving bamboo 4'
19-41-d-04 Stake, market bamboo, bush from any source 14'-16' long, 100 Rft 139.50 1,582.43 100 Rft 139.50 1,582.43
2.5"-5" dia : Tying bamboo with wire
19-41-d-05 Stake, market bamboo, bush from any source 14'-16' long, 100 Rft 3,906.00 5,067.60 100 Rft 3,906.00 5,067.60 Royalty to be paid to
2.5"-5" dia : Wattle & intertwine the forest Department
or cost to the private
owner, as the case
may be, if and when
required.
19-41-e-01 Stake, market bamboo, bush from any source 16'-20' long, 100 No. 0.00 36,300.00 100 No. 0.00 36,300.00
2.5"-5" dia : Supply bamboo
19-41-e-02 Stake, market bamboo, bush from any source 16'-20' long, 100 No. 1,036.64 1,036.64 100 No. 1,036.64 1,036.64
2.5"-5" dia : Sharpen one end
19-41-e-03 Stake, market bamboo, bush from any source 16'-20' long, 100 No. 971.23 971.23 100 No. 971.23 971.23
2.5"-5" dia : Driving bamboo 4'
19-41-e-04 Stake, market bamboo, bush from any source 16'-20' long, 100 Rft 139.50 1,582.43 100 Rft 139.50 1,582.43
2.5"-5" dia : Tying bamboo with wire
19-41-e-05 Stake, market bamboo, bush from any source 16'-20' long, 100 Rft 4,185.00 5,491.80 100 Rft 4,185.00 5,491.80 ditto
2.5"-5" dia : Wattle & intertwine
19-42 Cut & supply brushwood from canal plantation or from any 100 Cft 279.04 533.40 m3 98.54 188.37 ditto
other source, within 1.5 km.
19-43 Filling brush wood only, thoroughly packed 100 Cft 139.05 139.05 m3 49.10 49.10 Measured in
compacted and
packed shape before
filling.
19-44 Covering road 10' to 12' wide, with 3" sarkanda or jungle, 100 Rft 166.84 166.84 50 m 273.62 273.62
upto 50m lead
19-45 Gachi pitching 1' thick 100 Sft 1,815.06 1,815.06 m2 195.30 195.30
19-46 Gachi pitching done with silt clearance and berm dressing 100 Sft 1,535.02 1,535.02 m2 165.17 165.17
19-47 Filter granular backfill behind retaining wall (stone/boulder 100 Cft 589.00 2,116.63 m3 208.00 747.48
filling upto one meter to prevent choking of weep holes).

NWFP CSR 2008 - Approved 25-Aug-2008 Page 110 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 20 OUTLETS
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
20-01-a Earthwork for Outlets : Exc/Refill/Ram/Puddle Upto 50 Job 697.50 697.50 Job 697.50 697.50 Includes
cusecs channel discharge consolidation of earth
after refilling
20-01-b Earthwork for outlets : Exc/Refill/Ram/Puddle 51-100 Job 920.70 920.70 Job 920.70 920.70
cusecs channel discharge
20-01-c Earthwork for outlets : Exc/Refill/Ram/Puddle 101-200 Job 1,395.00 1,395.00 Job 1,395.00 1,395.00
cusecs channel discharge
20-01-d Earthwork for outlets : Exc/Refill/Ram/Puddle 201-350 Job 1,883.25 1,883.25 Job 1,883.25 1,883.25
cusecs channel discharge
20-01-e Earthwork for Outlets : Ex/Refill/Ram/Puddle Over 350 Job 2,790.00 2,790.00 Job 2,790.00 2,790.00
cusecs channel discharge
20-02-a Dismantling outlets: Old types such as KGO's orfices, etc Each 697.50 697.50 Each 697.50 697.50 The rates are for total
dismantlement and
remaoval of material.
The rates do not
include earthwork for
which rates are given
in item No 20-01
above.
20-02-b Dismantling outlets: APM or OF, 'H' upto 2.0 ft. Each 1,046.25 1,046.25 Each 1,046.25 1,046.25
20-02-c Dismantling outlets: APM or OF, 'H' from 2.1-3.0ft Each 1,395.00 1,395.00 Each 1,395.00 1,395.00
20-02-d Dismantling outlets: APM or OF, 'H' above 3.0 ft Each 1,743.75 1,743.75 Each 1,743.75 1,743.75
20-02-e Dismantling outlets: Tail cluster bifurcation Each 1,046.25 1,046.25 Each 1,046.25 1,046.25
20-02-f Dismantling outlets: Tail cluster trifurcation Each 1,395.00 1,395.00 Each 1,395.00 1,395.00
20-02-g Dismantling outlets: Tail cluster quardification Each 1,743.75 1,743.75 Each 1,743.75 1,743.75
20-03 Making temporary APM brick block & fixing at site Each 286.44 490.02 Each 286.44 490.02
20-04 Dismantling walls, taking out temporary APM brick block, Job 720.75 720.75 Job 720.75 720.75
fixing iron block & rebuilding walls
20-05 Dismantling walls & fitting iron block of OF outlet Each 720.75 720.75 Each 720.75 720.75
20-06-a Constructing, watching & removing bund for outlet built in Each 1,395.00 1,395.00 Each 1,395.00 1,395.00
running water : Upto 3' depth
20-06-b Constructing, watching & removing bund for outlet built in Each 1,883.25 1,883.25 Each 1,883.25 1,883.25
running water : Over 3' depth
20-07 Adjusting "B" of tail cluster by dismantling and rebuilding Each 444.85 722.54 Each 444.85 722.54
throat walls
20-08 Adjusting "Y" of an APM outlet, including dismantling and Each 860.25 1,309.77 Each 860.25 1,309.77
rebuilding
20-09-a Extra labour in fixing APM and OF outlet blocks Depth Each 868.00 965.10 Each 868.00 965.10
exceeding 5.0'
20-09-b Extra labour in fixing APM and OF outlet blocks Depth Each 651.00 748.10 Each 651.00 748.10
more than 4.0' to 5.0'
20-09-c Extra labour in fixing APM and OF outlet blocks Depth Each 520.80 617.90 Each 520.80 617.90
more than 3.0' to 4.0'
NWFP CSR 2008 - Approved 25-Aug-2008 Page 111 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 20 OUTLETS
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
20-09-d Extra labour in fixing APM and OF outlet blocks Depth Each 434.00 509.32 Each 434.00 509.32
more than 2.0' to 3.0'
20-09-e Extra labour in fixing APM and OF outlet blocks Depth Each 347.20 400.74 Each 347.20 400.74
upto 2.0'
20-10 Repairing damaged reducing collar of hume pipe outlets Each 286.44 413.19 Each 286.44 413.19
20-11 Laying iron pipes for outlets. Rft 23.01 23.01 m 75.50 75.50
20-12 Water allowance for constructing outlets or culverts, when Each 348.75 348.75 Each 348.75 348.75 At the discretion of
canal water not flowing the
Engineer-in-Charge
depending upon the
distance and the
source of supply.
20-13 Hoisting and placing RC slab or stone in position on Each 299.15 299.15 Each 299.15 299.15
outlets or WC culverts
20-14-a Fixing pipe outlet, including backfilling of earth & Rft 58.74 66.87 m 192.71 219.37
puddling : Portion under bank
20-14-b Fixing pipe outlet, including backfilling of earth & Rft 27.31 35.44 m 89.61 116.27
puddling : Portion under road, beyond bank
20-15-a Removing pipe outlet,refilling earth & puddling Portion Rft 46.53 46.53 m 152.65 152.65
under bank
20-15-b Removing pipe outlet,refilling earth & puddling Portion Rft 17.44 17.44 m 57.21 57.21
under road, beyond
20-16-a Changing pipe outlets by removing one pipe & replacing : Rft 68.06 76.18 m 223.29 249.95
Portion under bank
20-16-b Changing pipe outlets by removing one pipe & replacing : Rft 33.94 42.07 m 111.35 138.01
Portion under road, beyond

NWFP CSR 2008 - Approved 25-Aug-2008 Page 112 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 21 SINKING OF WELLS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
21-01-a-01 Excavate well in dry & dispose of soil within 50m in 100 Cft 206.99 206.99 m3 73.10 73.10
ordinary soil or sand : Upto 1.5 m depth
21-01-a-02 Excavate well in dry & dispose of soil within 50m in 100 Cft 216.47 216.47 m3 76.45 76.45
ordinary soil or sand : 1.5 to 3 m depth
21-01-a-03 Excavate well in dry & dispose of soil within 50m in 100 Cft 244.12 244.12 m3 86.21 86.21
ordinary soil or sand : 3 to 4.5 m depth
21-01-a-04 Excavate well in dry & dispose of soil within 50m in 100 Cft 278.88 278.88 m3 98.49 98.49
ordinary soil or sand : 4.5 to 6 m depth
21-01-b-01 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 252.81 252.81 m3 89.28 89.28
soil : Upto 1.5 m depth
21-01-b-02 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 263.87 263.87 m3 93.19 93.19
soil : Above 1.5 to 3 m depth
21-01-b-03 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 288.36 288.36 m3 101.83 101.83
soil : Above 3 to 4.5 m depth
21-01-b-04 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 324.71 324.71 m3 114.67 114.67
soil : Above 4.5 to 6 m depth
21-01-c-01 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 544.34 544.34 m3 192.23 192.23
strata like shingle : Upto 1.5 m depth
21-01-c-02 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 564.09 564.09 m3 199.21 199.21
strata like shingle :1.5 to 3 m depth
21-01-c-03 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 587.79 587.79 m3 207.58 207.58
strata like shingle : 3 to 4.5 m depth
21-01-c-04 Excavate well in dry & dispose of soil within 50m in hard 100 Cft 631.24 631.24 m3 222.92 222.92
strata like shingle : 4.5 to 6 m depth
21-02-a-01 Dry sinking of well & disposal of soil within 50m in 100 Cft 1,116.33 1,116.33 m3 394.23 394.23
ordinary soil : 3 to 4.5 m depth
21-02-a-02 Dry sinking of well & disposal of soil within 50m in 100 Cft 1,395.21 1,395.21 m3 492.71 492.71
ordinary soil : 4.5 to 6 m depth
21-02-a-03 Dry sinking of well & disposal of soil within 50m in 100 Cft 1,674.09 1,674.09 m3 591.20 591.20
ordinary soil : 6 to 7.5 m depth
21-02-a-04 Dry sinking of well & disposal of soil within 50m in 100 Cft 1,952.98 1,952.98 m3 689.69 689.69
ordinary soil : 7.5 to 9 m depth
21-02-a-05 Dry sinking of well & disposal of soil within 50m in 100 Cft 2,231.86 2,231.86 m3 788.17 788.17
ordinary soil : 9 to 10.5 m depth
21-02-a-06 Dry sinking of well & disposal of soil within 50m in 100 Cft 2,510.74 2,510.74 m3 886.66 886.66
ordinary soil : 10.5 to 12 m depth
21-02-a-07 Dry sinking of well & disposal of soil within 50m in 100 Cft 2,790.42 2,790.42 m3 985.43 985.43
ordinary soil : 12 to 13.5 m depth
21-02-a-08 Dry sinking of well & disposal of soil within 50m in 100 Cft 3,069.30 3,069.30 m3 1,083.91 1,083.91
ordinary soil : Exceeding 13.5 m depth
21-02-b-01 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 1,534.26 1,534.26 m3 541.82 541.82
soil : 3 to 4.5 m depth
NWFP CSR 2008 - Approved 25-Aug-2008 Page 113 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 21 SINKING OF WELLS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
21-02-b-02 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 1,813.14 1,813.14 m3 640.30 640.30
soil : 4.5 to 6 m depth
21-02-b-03 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,092.81 2,092.81 m3 739.07 739.07
soil : 6 to 7.5 m depth
21-02-b-04 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,371.70 2,371.70 m3 837.56 837.56
soil : 7.5 to 9 m depth
21-02-b-05 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,650.58 2,650.58 m3 936.05 936.05
soil : 9 to 10.5 m depth
21-02-b-06 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,929.47 2,929.47 m3 1,034.53 1,034.53
soil : 10.5 to 12 m depth
21-02-b-07 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 3,208.35 3,208.35 m3 1,133.02 1,133.02
soil : 12 to 13.5 m depth
21-02-b-08 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 3,487.23 3,487.23 m3 1,231.51 1,231.51
soil : Exceeding 13.5 m depth
21-02-c-01 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,092.02 2,092.02 m3 738.79 738.79
strata like shingle : 3 to 4.5 m depth
21-02-c-02 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,371.70 2,371.70 m3 837.56 837.56
strata like shingle : 4.5 to 6 m depth
21-02-c-03 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,650.58 2,650.58 m3 936.05 936.05
strata like shingle : 6 to 7.5 m depth
21-02-c-04 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 2,929.47 2,929.47 m3 1,034.53 1,034.53
strata like shingle : 7.5 to 9 m depth
21-02-c-05 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 3,208.35 3,208.35 m3 1,133.02 1,133.02
strata like shingle : 9 to 10.5 m depth
21-02-c-06 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 3,487.23 3,487.23 m3 1,231.51 1,231.51
strata like shingle : 10.5 to 12 m depth
21-02-c-07 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 3,766.91 3,766.91 m3 1,330.27 1,330.27
strata like shingle : 12 to 13.5 m depth
21-02-c-08 Dry sinking of well & disposal of soil within 50m in hard 100 Cft 4,045.79 4,045.79 m3 1,428.76 1,428.76
strata like shingle : Over 13.5 m depth
21-03-a-01 Wet sinking of well for depths below spring level Upto 1.5 100 Cft 1,325.60 1,325.60 m3 468.13 468.13 The outer dimensions
m depth of the curb shall from
basis of payment.
21-03-a-02 Wet sinking of well for depths below spring level Above 100 Cft 2,665.68 2,665.68 m3 941.38 941.38
1.5 to 3 m depth
21-03-a-03 Wet sinking of well for depths below spring level Above 3 100 Cft 4,102.24 4,102.24 m3 1,448.69 1,448.69
to 4.5 m depth
21-03-a-04 Wet sinking of well for depths below spring level Above 100 Cft 5,553.27 5,553.27 m3 1,961.12 1,961.12
4.5 to 6 m depth
21-03-a-05 Wet sinking of well for depths below spring level Above 6 100 Cft 7,322.87 7,322.87 m3 2,586.05 2,586.05
to 7.5 m depth

NWFP CSR 2008 - Approved 25-Aug-2008 Page 114 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 21 SINKING OF WELLS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
21-03-a-06 Wet sinking of well for depths below spring level Above 100 Cft 9,354.33 9,354.33 m3 3,303.45 3,303.45
7.5 to 9 m depth
21-03-a-07 Wet sinking of well for depths below spring level Above 9 100 Cft 11,345.75 11,345.75 m3 4,006.72 4,006.72
to 10.5 m depth
21-03-a-08 Wet sinking of well for depths below spring level Above 100 Cft 14,029.52 14,029.52 m3 4,954.48 4,954.48
10.5 to 12 m depth
21-03-a-09 Wet sinking of well for depths below spring level Above 100 Cft 16,659.65 16,659.65 m3 5,883.31 5,883.31
12 to 13.5 m depth
21-03-a-10 Wet sinking of well for depths below spring level 100 Cft 20,044.70 20,044.70 m3 7,078.73 7,078.73
Exceeding 13.5 m depth
21-03-b-01 Wet sinking of well for depths below spring level in 100 Cft 1,705.52 1,705.52 m3 602.30 602.30
cohesive soil : Upto 1.5 m depth
21-03-b-02 Wet sinking of well for depths below spring level in 100 Cft 3,333.00 3,333.00 m3 1,177.04 1,177.04
cohesive soil : 1.5 to 3 m depth
21-03-b-03 Wet sinking of well for depths below spring level in 100 Cft 5,030.79 5,030.79 m3 1,776.61 1,776.61
cohesive soil : Above 3 to 4.5 m depth
21-03-b-04 Wet sinking of well for depths below spring level in 100 Cft 6,665.21 6,665.21 m3 2,353.80 2,353.80
cohesive soil : Above 4.5 to 6 m depth
21-03-b-05 Wet sinking of well for depths below spring level in 100 Cft 9,192.81 9,192.81 m3 3,246.41 3,246.41
cohesive soil : Above 6 to 7.5 m depth
21-03-b-06 Wet sinking of well for depths below spring level in 100 Cft 11,591.90 11,591.90 m3 4,093.64 4,093.64
cohesive soil : Above 7.5 to 9 m depth
21-03-b-07 Wet sinking of well for depths below spring level in 100 Cft 14,218.25 14,218.25 m3 5,021.13 5,021.13
cohesive soil : Above 9 to 10.5 m depth
21-03-b-08 Wet sinking of well for depths below spring level in 100 Cft 17,775.71 17,775.71 m3 6,277.44 6,277.44
cohesive soil : Above 10.5 to 12 m depth
21-03-b-09 Wet sinking of well for depths below spring level in 100 Cft 20,825.26 20,825.26 m3 7,354.38 7,354.38
cohesive soil : Above 12 to 13.5 m depth
21-03-b-10 Wet sinking of well for depths below spring level in 100 Cft 24,913.98 24,913.98 m3 8,798.30 8,798.30
cohesive soil : Exceeding 13.5 m depth
21-03-c-01 Wet sinking of well for depths below spring level in 100 Cft 3,372.59 3,372.59 m3 1,191.02 1,191.02
shingle/gravel etc : Upto 1.5 m depth
21-03-c-02 Wet sinking of well for depths below spring level in 100 Cft 8,030.75 8,030.75 m3 2,836.03 2,836.03
shingle/gravel etc : 1.5 to 3 m depth
21-03-c-03 Wet sinking of well for depths below spring level in 100 Cft 10,950.47 10,950.47 m3 3,867.13 3,867.13
shingle/gravel etc : 3 to 4.5 m depth
21-03-c-04 Wet sinking of well for depths below spring level in 100 Cft 15,163.14 15,163.13 m3 5,354.82 5,354.81
shingle/gravel etc : 4.5 to 6 m depth
21-03-c-05 Wet sinking of well for depths below spring level in 100 Cft 22,788.77 22,788.77 m3 8,047.79 8,047.79
shingle/gravel etc : 6 to 7.5 m depth
21-03-c-06 Wet sinking of well for depths below spring level in 100 Cft 29,484.97 29,484.97 m3 10,412.53 10,412.53
shingle/gravel etc : 7.5 to 9 m depth
NWFP CSR 2008 - Approved 25-Aug-2008 Page 115 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 21 SINKING OF WELLS


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
21-03-c-07 Wet sinking of well for depths below spring level in 100 Cft 36,979.11 36,979.11 m3 13,059.06 13,059.06
shingle/gravel etc : 9 to 10.5 m depth
21-03-c-08 Wet sinking of well for depths below spring level in 100 Cft 47,902.71 47,902.71 m3 16,916.70 16,916.70
shingle/gravel etc : 10.5 to 12 m depth
21-03-c-09 Wet sinking of well for depths below spring level in 100 Cft 60,229.09 60,229.09 m3 21,269.72 21,269.72
shingle/gravel etc : 12 to 13.5 m depth
21-03-c-10 Wet sinking of well for depths below spring level in 100 Cft 76,638.20 76,638.20 m3 27,064.55 27,064.55
shingle/gravel etc : Exceeding 13.5 m depth
21-04 Making & fixing in position, kikar wood well curb 100 Cft 94,247.55 184,997.55 m3 33,283.24 65,331.31
21-05 Laying well curb in position only Each 565.75 565.75 Each 565.75 565.75
21-06-a Providing & laying RCC well curb in position, using 100 Cft 7,703.67 20,817.77 m3 2,720.53 7,351.73 a) If concrete mixer is
coarse sand : Ratio 1:1.5:3 supplied by
government, all
charges including
depreciation will be
recoverd from the
contractor.
21-06-b Providing & laying RCC well curb in position, using 100 Cft 7,703.67 22,187.61 m3 2,720.53 7,835.49 b) The rate does not
coarse sand : Ratio 1:2:4 include cost of steel
reinforcement and its
labour for
bending/binding,
which is payable
separately.
21-07 Providing and fixing structural steel for cutting edge Ton 14,570.00 60,671.00 tonne 14,339.79 59,712.40

NWFP CSR 2008 - Approved 25-Aug-2008 Page 116 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 22 SURFACE DRAINAGE


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
22-01-a-01 Tega formed of pacca bricks on end, laid in and over c/s 100 Rft 566.10 1,898.65 m 18.57 62.29
mortar : 3" thick : Ratio 1:3
22-01-a-02 Tega formed of pacca bricks on end, laid in and over c/s 100 Rft 566.10 1,705.30 m 18.57 55.95
mortar : 3" thick : Ratio 1:5
22-01-b-01 Tega formed of pacca bricks on end, laid in and over c/s 100 Rft 624.82 2,206.27 m 20.50 72.38
mortar : 4.5" thick : Ratio 1:3
22-01-b-02 Tega formed of pacca bricks on end, laid in and over c/s 100 Rft 624.82 2,072.89 m 20.50 68.01
mortar : 4.5" thick : Ratio 1:5
22-02-a Pacca flat brick 3" thick, laid in reimbursement, in c/s 100 Sft 790.79 2,931.97 m2 85.09 315.48
mortar, on sides of drains etc : Ratio 1:3
22-02-b Pacca flat brick 3" thick, laid in reimbursement, in c/s 100 Sft 790.79 2,717.37 m2 85.09 292.39
mortar, on sides of drains etc : Ratio 1:5
22-02-c Pacca flat brick 3" thick, laid in reimbursement, in c/s 100 Sft 790.79 2,656.36 m2 85.09 285.82
mortar, on sides of drains etc : Ratio 1:6
22-03-a Pacca brick on edge, laid in reimbursement, in c/s mortar, 100 Sft 882.73 4,088.93 m2 94.98 439.97
on sides of drains etc : Ratio 1:3
22-03-b Pacca brick on edge, laid in reimbursement, in c/s mortar, 100 Sft 882.73 3,769.75 m2 94.98 405.63
on sides of drains etc : Ratio 1:5
22-03-c Pacca brick on edge, laid in reimbursement, in c/s mortar, 100 Sft 882.73 3,676.73 m2 94.98 395.62
on sides of drains etc : Ratio 1:6
22-04-a Pacca flat brick, Herring bond pitching in c/s mortar laid to 100 Sft 740.27 3,153.07 m2 79.65 339.27
line, grade, slope etc : Ratio 1:3
22-04-b Pacca flat brick, Herring bond pitching in c/s mortar laid to 100 Sft 740.27 2,909.06 m2 79.65 313.02
line, grade, slope etc : Ratio 1:5
22-04-c Pacca flat brick, Herring bond pitching in c/s mortar laid to 100 Sft 740.27 2,855.55 m2 79.65 307.26
line, grade, slope etc : Ratio 1:6
22-05-a Construct Punjab standard drains, of cement concrete 100 Rft 723.97 4,371.31 m 23.75 143.42 The rate does not
1:1.5:3, complete : Type I include cost of
excavation, which is
to be paid separately.
22-05-b Construct Punjab standard drains, of cement concrete 100 Rft 1,839.76 10,122.69 m 60.36 332.11
1:1.5:3, complete : Type II
22-05-c Construct Punjab standard drains, of cement concrete 100 Rft 2,338.98 12,819.26 m 76.74 420.58
1:1.5:3, complete : Type III
22-05-d Construct Punjab standard drains, of cement concrete 100 Rft 2,519.67 14,478.51 m 82.67 475.02
1:1.5:3, complete : Type IV
22-05-e Construct Punjab standard drains, of cement concrete 100 Rft 3,379.28 19,086.44 m 110.87 626.20
1:1.5:3, complete : Type V
22-05-f Construct Punjab standard drains, of cement concrete 100 Rft 3,819.70 21,384.53 m 125.32 701.59
1:1.5:3, complete : Type VI
22-05-g Construct Punjab standard drains, of cement concrete 100 Rft 3,877.91 22,121.13 m 127.23 725.76
1:1.5:3, complete : Type VII

NWFP CSR 2008 - Approved 25-Aug-2008 Page 117 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 22 SURFACE DRAINAGE


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
22-05-h Construct Punjab standard drains, of cement concrete 100 Rft 5,841.10 32,943.28 m 191.64 1,080.82
1:1.5:3, complete : Type VIII
22-05-i Construct Punjab standard drains, of cement concrete 100 Rft 6,658.88 37,327.45 m 218.47 1,224.65
1:1.5:3, complete : Type IX
22-05-j Construct Punjab standard drains, of cement concrete 100 Rft 7,184.26 43,184.61 m 235.70 1,416.82
1:1.5:3, complete : Type X
22-05-k Construct Punjab standard drains, of cement concrete 100 Rft 7,852.83 45,812.55 m 257.64 1,503.04
1:1.5:3, complete : Type XI
22-05-l Construct Punjab standard drains, of cement concrete 100 Rft 8,027.16 46,889.16 m 263.36 1,538.36
1:1.5:3, complete : Type XII
22-06-a Laying RC hume pipes in position including jointing 6" to 100 Rft 4,263.89 4,560.76 m 139.89 149.63
12" dia
22-06-b Laying RC hume pipes in position including jointing 12" to 100 Rft 6,360.47 6,965.00 m 208.68 228.51
24" dia
22-06-c Laying RC hume pipes in position including jointing 24" to 100 Rft 8,542.64 9,453.12 m 280.27 310.14
36" dia

NWFP CSR 2008 - Approved 25-Aug-2008 Page 118 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 23 SEWERAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
23-01-a Providing and Laying RCC pipe, moulded with cement Rft 46.55 87.12 m 152.71 285.82
concrete 1:1.5:3, including cost of reinforcement, testing
etc : 4" dia:
23-01-b Providing and Laying RCC pipe, moulded with cement Rft 52.22 98.32 m 171.32 322.57
concrete 1:1.5:3, including cost of reinforcement, testing
etc : 6" dia:
23-01-c Providing and Laying RCC pipe, moulded with cement Rft 59.31 140.46 m 194.57 460.83
concrete 1:1.5:3, including cost of reinforcement, testing
etc : 9" dia:
23-02-a Providing and Laying non-reinforced concrete pipe, Rft 40.17 93.65 m 131.78 307.25
moulded with cement concrete 1:1.5:3 complete : 4"
internal diameter
23-02-b Providing and Laying non-reinforced concrete pipe, Rft 52.22 125.99 m 171.32 413.36
moulded with cement concrete 1:1.5:3 complete : 6" i/d
23-02-c Providing and Laying non-reinforced concrete pipe, Rft 76.32 157.47 m 250.39 516.64
moulded with cement concrete : 9" i/d wall thickness 1".
23-03-a-01 Providing and Laying RCC pipe sewers complete As per Rft 130.54 296.50 m 428.30 972.76
ASTM C-76-79, Class II : 12" i/d, Wall B
23-03-a-02 Providing and Laying RCC pipe sewers complete As per Rft 160.67 379.98 m 527.13 1,246.66
ASTM C-76-79, Class II : 15" i/d, Wall B
23-03-a-03 Providing and Laying RCC pipe sewers complete As per Rft 195.82 464.29 m 642.45 1,523.25
ASTM C-76-79, Class II : 18" i/d, Wall B
23-03-a-04 Providing and Laying RCC pipe sewers complete As per Rft 237.57 600.57 m 779.42 1,970.37
ASTM C-76-79, Class II : 21" i/d, Wall B
23-03-a-05 Providing and Laying RCC pipe sewers complete As per Rft 261.09 684.59 m 856.59 2,246.03
ASTM C-76-79, Class II : 24" i/d, Wall B
23-03-a-06 Providing and Laying RCC pipe sewers complete As per Rft 351.38 880.76 m 1,152.83 2,889.62
ASTM C-76-79, Class II : 27" i/d, Wall B
23-03-a-07 Providing and Laying RCC pipe sewers complete As per Rft 391.63 996.63 m 1,284.89 3,269.80
ASTM C-76-79, Class II : 30" i/d, Wall B
23-03-a-08 Providing and Laying RCC pipe sewers complete As per Rft 426.78 1,183.03 m 1,400.20 3,881.34
ASTM C-76-79, Class II : 33" i/d, Wall B
23-03-a-09 Providing and Laying RCC pipe sewers complete As per Rft 466.61 1,358.98 m 1,530.87 4,458.61
ASTM C-76-79, Class II : 36" i/d, Wall B
23-03-a-10 Providing and Laying RCC pipe sewers complete As per Rft 602.52 1,827.64 m 1,976.76 5,996.19
ASTM C-76-79, Class II : 42" i/d, Wall B
23-03-a-11 Providing and Laying RCC pipe sewers complete As per Rft 692.90 2,235.65 m 2,273.28 7,334.80
ASTM C-76-79, Class II : 48" i/d, Wall B
23-03-a-12 Providing and Laying RCC pipe sewers complete As per Rft 903.77 3,021.27 m 2,965.13 9,912.31
ASTM C-76-79, Class II : 54" i/d, Wall B
23-03-a-13 Providing and Laying RCC pipe sewers complete As per Rft 1,245.20 4,118.95 m 4,085.30 13,513.61
ASTM C-76-79, Class II : 60" i/d, Wall B

NWFP CSR 2008 - Approved 25-Aug-2008 Page 119 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 23 SEWERAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
23-03-a-14 Providing and Laying RCC pipe sewers complete As per Rft 1,709.76 5,188.51 m 5,609.46 17,022.68
ASTM C-76-79, Class II : 66" i/d, Wall B
23-03-a-15 Providing and Laying RCC pipe sewers complete As per Rft 2,324.71 6,257.21 m 7,626.99 20,528.89
ASTM C-76-79, Class II : 72" i/d, Wall B
23-03-b-01 Providing and Laying RCC pipe sewers complete As per Rft 130.54 314.99 m 428.30 1,033.42
ASTM C-76-79, Class III : 12" i/d, Wall B
23-03-b-02 Providing and Laying RCC pipe sewers complete As per Rft 160.67 387.55 m 527.13 1,271.48
ASTM C-76-79, Class III : 15" i/d, Wall B
23-03-b-03 Providing and Laying RCC pipe sewers complete As per Rft 195.82 479.41 m 642.45 1,572.87
ASTM C-76-79, Class III : 18" i/d, Wall B
23-03-b-04 Providing and Laying RCC pipe sewers complete As per Rft 237.29 630.54 m 778.50 2,068.69
ASTM C-76-79, Class III : 21" i/d, Wall B
23-03-b-05 Providing and Laying RCC pipe sewers complete As per Rft 261.09 729.96 m 856.59 2,394.90
ASTM C-76-79, Class III : 24" i/d, Wall B
23-03-b-06 Providing and Laying RCC pipe sewers complete As per Rft 351.51 911.13 m 1,153.23 2,989.27
ASTM C-76-79, Class III : 27" i/d, Wall B
23-03-b-07 Providing and Laying RCC pipe sewers complete As per Rft 391.63 1,110.07 m 1,284.89 3,641.97
ASTM C-76-79, Class III : 30" i/d, Wall B
23-03-b-08 Providing and Laying RCC pipe sewers complete As per Rft 426.78 1,372.09 m 1,400.20 4,501.62
ASTM C-76-79, Class III : 33" i/d, Wall B
23-03-b-09 Providing and Laying RCC pipe sewers complete As per Rft 466.91 1,450.03 m 1,531.85 4,757.33
ASTM C-76-79, Class III : 36" i/d, Wall B
23-03-b-10 Providing and Laying RCC pipe sewers complete As per Rft 602.52 1,963.77 m 1,976.76 6,442.80
ASTM C-76-79, Class III : 42" i/d, Wall B
23-03-b-11 Providing and Laying RCC pipe sewers complete As per Rft 693.20 2,356.95 m 2,274.28 7,732.77
ASTM C-76-79, Class III : 48" i/d, Wall B
23-03-b-12 Providing and Laying RCC pipe sewers complete As per Rft 903.77 3,323.77 m 2,965.13 10,904.77
ASTM C-76-79, Class III : 54" i/d, Wall B
23-03-b-13 Providing and Laying RCC pipe sewers complete As per Rft 1,245.20 5,303.11 m 4,085.30 17,398.67
ASTM C-76-79, Class III : 60" i/d, Wall B
23-03-b-14 Providing and Laying RCC pipe sewers complete As per Rft 1,702.11 4,878.36 m 5,584.34 16,005.11
ASTM C-76-79, Class III : 66" i/d, Wall B
23-03-b-15 Providing and Laying RCC pipe sewers complete As per Rft 2,324.71 8,979.71 m 7,626.99 29,460.97
ASTM C-76-79, Class III : 72" i/d, Wall B
23-03-c-01 Providing and Laying RCC pipe sewers complete As per Rft 130.54 327.17 m 428.30 1,073.39
ASTM C-76-79, Class IV : 12" i/d, Wall B
23-03-c-02 Providing and Laying RCC pipe sewers complete As per Rft 160.67 417.80 m 527.13 1,370.72
ASTM C-76-79, Class IV : 15" i/d, Wall B
23-03-c-03 Providing and Laying RCC pipe sewers complete As per Rft 195.82 517.22 m 642.45 1,696.93
ASTM C-76-79, Class IV : 18" i/d, Wall B
23-03-c-04 Providing and Laying RCC pipe sewers complete As per Rft 237.29 706.16 m 778.50 2,316.80
ASTM C-76-79, Class IV : 21" i/d, Wall B
NWFP CSR 2008 - Approved 25-Aug-2008 Page 120 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 23 SEWERAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
23-03-c-05 Providing and Laying RCC pipe sewers complete As per Rft 261.09 896.34 m 856.59 2,940.75
ASTM C-76-79, Class IV : 24" i/d, Wall B
23-03-c-06 Providing and Laying RCC pipe sewers complete As per Rft 351.35 1,069.79 m 1,152.74 3,509.81
ASTM C-76-79, Class IV : 27" i/d, Wall B
23-03-c-07 Providing and Laying RCC pipe sewers complete As per Rft 391.63 1,329.38 m 1,284.89 4,361.50
ASTM C-76-79, Class IV : 30" i/d, Wall B
23-03-c-08 Providing and Laying RCC pipe sewers complete As per Rft 426.78 1,697.28 m 1,400.20 5,568.51
ASTM C-76-79, Class IV : 33" i/d, Wall B
23-03-c-09 Providing and Laying RCC pipe sewers complete As per Rft 466.40 1,827.65 m 1,530.18 5,996.22
ASTM C-76-79, Class IV : 36" i/d, Wall B
23-03-c-10 Providing and Laying RCC pipe sewers complete As per Rft 602.52 2,538.52 m 1,976.76 8,328.46
ASTM C-76-79, Class IV : 42" i/d, Wall B
23-03-c-11 Providing and Laying RCC pipe sewers complete As per Rft 693.20 3,415.70 m 2,274.28 11,206.36
ASTM C-76-79, Class IV : 48" i/d, Wall B
23-03-c-12 Providing and Laying RCC pipe sewers complete As per Rft 903.77 3,928.77 m 2,965.13 12,889.68
ASTM C-76-79, Class IV : 54" i/d, Wall B
23-03-c-13 Providing and Laying RCC pipe sewers complete As per Rft 1,245.20 4,875.20 m 4,085.30 15,994.74
ASTM C-76-79, Class IV : 60" i/d, Wall B
23-03-c-14 Providing and Laying RCC pipe sewers complete As per Rft 1,702.11 6,693.36 m 5,584.34 21,959.83
ASTM C-76-79, Class IV : 66" i/d, Wall B
23-03-c-15 Providing and Laying RCC pipe sewers complete As per Rft 2,324.71 9,206.58 m 7,626.99 30,205.32
ASTM C-76-79, Class IV : 72" i/d, Wall B
23-04-a Lowering of sub-soil water table by tubewells Upto 1 ft Rft 0.00 147.56 m 0.00 484.12 a) This rate shall be
below SSWL payable, in addition
to the item of
excavation below
SSWL for sewer and
manholes under
chapter 3 earthwork
23-04-b Lowering of sub-soil water table by tubewells 0 - 2 ft Rft 0.00 313.57 m 0.00 1,028.76 b) The grant of these
below SSWL rates shall be subject
to Superintending
Engineer's approval.
23-04-c Lowering of sub-soil water table by tubewell 0 - 3 ft below Rft 0.00 494.33 m 0.00 1,621.82 c) The rate includes
SSWL cost of providing
pumps, POL and all
operation charges at
the site of work, etc
23-04-d Lowering of sub-soil water table by tubewells 0 - 4 ft Rft 0.00 686.16 m 0.00 2,251.18
below SSWL
23-04-e Lowering of sub-soil water table by tubewells 0 - 5 ft Rft 0.00 900.12 m 0.00 2,953.16
below SSWL
23-04-f Lowering of sub-soil water table by tubewells 0 - 6 ft Rft 0.00 1,121.46 m 0.00 3,679.34
below SSWL
NWFP CSR 2008 - Approved 25-Aug-2008 Page 121 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 23 SEWERAGE
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
23-04-g Lowering of sub-soil water table by tubewells 0 - 7 ft Rft 0.00 1,328.05 m 0.00 4,357.12
below SSWL
23-04-h Lowering of sub-soil water table by tubewells 0 - 8 ft Rft 0.00 1,519.88 m 0.00 4,986.48
below SSWL
23-04-i Lowering of sub-soil water table by tubewells 0 - 9 ft Rft 0.00 1,726.46 m 0.00 5,664.25
below SSWL
23-04-j Lowering of sub-soil water table by tubewells 0 - 10 ft Rft 0.00 2,036.34 m 0.00 6,680.91
below SSWL
23-04-k Lowering of sub-soil water table by tubewells 0 - 11 ft Rft 0.00 2,154.39 m 0.00 7,068.21
below SSWL
23-04-l Lowering of sub-soil water table by tubewells 0 - 12 ft Rft 0.00 2,360.98 m 0.00 7,745.98
below SSWL
23-05-a Constructing gully grating chamber complete With CI Each 805.66 4,076.19 Each 805.66 4,076.19 Pipe connection to be
gully trap,weighing 81 lbs. frame hinged paid separately.
23-05-b Constructing gully grating chamber complete Concrete Each 805.66 2,874.37 Each 805.66 2,874.37
gully trap
23-06 Fixing manhole frame and cover in RCC slab, including Set 593.65 593.65 Set 593.65 593.65
carriage to site
23-07 Providing and Fixing 3" thick RCC manhole cover, 22" dia Set 1,362.18 4,127.35 Set 1,362.18 4,127.35
with tee shaped CI frame of 20" clear i/d complete
23-08-a RCC manhole cover 22" dia with: Tee shaped CI frame, Set 1,899.31 13,013.54 Set 1,899.31 13,013.54
22" i/d complete
23-08-b RCC manhole cover 22" dia with: 3"x3"x1/4" angle iron Set 1,897.76 11,713.86 Set 1,897.76 11,713.86
frame, 22" i/d complete
23-09-a Providing and Fixing CI ventilating shaft of 9" i/d, painted 100 Kg 158.10 7,960.18 100 Kg 158.10 7,960.18
with bitumenous paint complete : 18 ft. long
23-09-b Providing and Fixing CI ventilating shaft of 9" i/d, painted 100 Kg 210.80 8,012.88 100 Kg 210.80 8,012.88
with bitumenous paint complete : 24 ft. long
23-09-c Providing and Fixing CI ventilating shaft of 9" i/d, painted 100 Kg 263.50 8,065.58 100 Kg 263.50 8,065.58
with bitumenous paint complete : 30 ft. long
23-09-d Providing and Fixing CI ventilating shaft of 9" i/d, painted 100 Kg 316.20 8,118.28 100 Kg 316.20 8,118.28
with bitumenous paint complete : 36 ft. long
23-10 Septic Tank (int.Size: 7'x2'x5') complete Each 1,426.00 10,154.55 Each 1,426.00 10,154.55
23-11 Soakage Pit (6'dia x 15' deep) complete Each 1,426.00 9,917.15 Each 1,426.00 9,917.15

NWFP CSR 2008 - Approved 25-Aug-2008 Page 122 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-01 Mobilization of plant, equipment and camping Job 0.00 19,360.00 Job 0.00 19,360.00
arrangements etc & demobilization after completion
24-02-a-01 Tubewell boring in all soils except shingle/rock From Rft 48.22 96.55 m 158.20 316.75
ground upto 100' below ground : 3" i/d
24-02-a-02 Tubewell boring in all soils except shingle/rock From Rft 71.82 144.31 m 235.64 473.47
ground upto 100' below ground : 4" i/d
24-02-a-03 Tubewell boring in all soils except shingle/rock From Rft 108.26 213.37 m 355.19 700.05
ground upto 100' below ground : 5" i/d
24-02-a-04 Tubewell boring in all soils except shingle/rock From Rft 162.74 309.90 m 533.92 1,016.72
ground upto 100' below ground : 6" i/d
24-02-a-05 Tubewell boring in all soils except shingle/rock From Rft 244.11 442.77 m 800.90 1,452.67
ground upto 100' below ground : 8" i/d
24-02-a-06 Tubewell boring in all soils except shingle/rock From Rft 366.17 614.50 m 1,201.34 2,016.06
ground upto 100' below ground : 10" i/d
24-02-a-07 Tubewell boring in all soils except shingle/rock From Rft 457.71 755.70 m 1,501.68 2,479.35
ground upto 100' below ground : 12" i/d
24-02-a-08 Tubewell boring in all soils except shingle/rock From Rft 572.15 914.84 m 1,877.12 3,001.44
ground upto 100' below ground : 15" i/d
24-02-a-09 Tubewell boring in all soils except shingle/rock From Rft 715.19 1,092.15 m 2,346.42 3,583.17
ground upto 100' below ground : 18" i/d
24-02-b-01 Tubewell boring in all soils except shingle/rock From 100' Rft 184.44 363.13 m 605.13 1,191.38
to 200' below ground : 5" i/d
24-02-b-02 Tubewell boring in all soils except shingle/rock From 100' Rft 260.39 592.49 m 854.29 1,943.88
to 200' below ground : 6" i/d
24-02-b-03 Tubewell boring in all soils except shingle/rock From 100' Rft 317.35 575.61 m 1,041.17 1,888.48
to 200' below ground : 8" i/d
24-02-b-04 Tubewell boring in all soils except shingle/rock From 100' Rft 344.89 642.88 m 1,131.53 2,109.20
to 200' below ground : 10" i/d
24-02-b-05 Tubewell boring in all soils except shingle/rock From 100' Rft 484.84 827.53 m 1,590.69 2,715.00
to 200' below ground : 12" i/d
24-02-b-06 Tubewell boring in all soils except shingle/rock From 100' Rft 657.96 1,052.05 m 2,158.66 3,451.62
to 200' below ground : 15" i/d
24-02-b-07 Tubewell boring in all soils except shingle/rock From 100' Rft 822.45 1,255.95 m 2,698.32 4,120.58
to 200' below ground : 18" i/d
24-02-c-01 Tubewell boring in all soils except shingle/rock From 200' Rft 249.04 490.27 m 817.06 1,608.51
to 300' below ground : 5" i/d
24-02-c-02 Tubewell boring in all soils except shingle/rock From 200' Rft 325.53 619.85 m 1,068.03 2,033.62
to 300' below ground : 6" i/d
24-02-c-03 Tubewell boring in all soils except shingle/rock From 200' Rft 311.74 634.57 m 1,022.77 2,081.91
to 300' below ground : 8" i/d
24-02-c-04 Tubewell boring in all soils except shingle/rock From 200' Rft 527.28 884.87 m 1,729.93 2,903.13
to 300' below ground : 10" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 123 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-02-c-05 Tubewell boring in all soils except shingle/rock From 200' Rft 631.64 1,042.87 m 2,072.31 3,421.49
to 300' below ground : 12" i/d
24-02-c-06 Tubewell boring in all soils except shingle/rock From 200' Rft 723.75 1,157.26 m 2,374.52 3,796.78
to 300' below ground : 15" i/d
24-02-c-07 Tubewell boring in all soils except shingle/rock From 200' Rft 906.03 1,382.89 m 2,972.55 4,537.04
to 300' below ground : 18" i/d
24-02-d-01 Tubewell boring in all soils except shingle/rock From 300' Rft 476.02 863.41 m 1,561.74 2,832.70
to 400' below ground : 8" i/d
24-02-d-02 Tubewell boring in all soils except shingle/rock From 300' Rft 632.74 1,061.85 m 2,075.91 3,483.76
to 400' below ground : 10" i/d
24-02-d-03 Tubewell boring in all soils except shingle/rock From 300' Rft 757.97 1,251.44 m 2,486.77 4,105.79
to 400' below ground : 12" i/d
24-02-d-04 Tubewell boring in all soils except shingle/rock From 300' Rft 868.90 1,389.10 m 2,850.72 4,557.43
to 400' below ground : 15" i/d
24-02-d-05 Tubewell boring in all soils except shingle/rock From 300' Rft 1,085.63 1,657.86 m 3,561.78 5,439.16
to 400' below ground : 18" i/d
24-03-a-01 Rotary drilling except in shingle, gravel & rock From Rft 0.00 836.91 m 0.00 2,745.76
ground to 250' below ground : 5"-18" i/d
24-03-a-02 Rotary drilling except in shingle, gravel & rock From Rft 0.00 1,018.35 m 0.00 3,341.04
ground to 250' below ground : 20"-26" i/d
24-03-b-01 Rotary drilling except in shingle, gravel & rock Exceeding Rft 0.00 1,046.14 m 0.00 3,432.20
250' below ground : 5"-18" i/d
24-03-b-02 Rotary drilling except in shingle, gravel & rock Exceeding Rft 0.00 1,272.94 m 0.00 4,176.30
250' below ground : 20"-26" i/d
24-04-a-01 Boring for tubewell in shingle, gravel & rock From ground Rft 0.00 2,092.27 m 0.00 6,864.41 Location and depth of
to 200' below ground : 12"-18" i/d shingle, gravel or
rock is to be
determined from the
bore log.
24-04-a-02 Boring for tubewell in shingle, gravel & rock From ground Rft 0.00 2,545.87 m 0.00 8,352.59
to 200' below ground : 20"-26" i/d
24-04-b-01 Boring for tubewell in shingle, gravel & rock Over 200' Rft 0.00 2,619.52 m 0.00 8,594.24
depth below ground : 12"-18" i/d
24-04-b-02 Boring for tubewell in shingle, gravel & rock Over 200' Rft 0.00 3,187.43 m 0.00 10,457.44
depth below ground : 20"-26" i/d
24-05 Providing strong substantially built box of deodar Job 662.63 6,569.85 Job 662.63 6,569.85
4'x2«'x9", with compartments & lock
24-06 Furnishing sample of water from bore hole Per set 1,116.00 1,285.40 Per set 1,116.00 1,285.40
24-07-a Providing and installing brass strainer in tubewell bore Rft 200.84 2,136.84 m 658.92 7,010.62 Cost/labour of
hole 6" i/d, 3/16" thick jointing both ends is
included in the rate.
24-07-b Providing and installing brass strainer in tubewell bore Rft 291.81 2,651.31 m 957.37 8,698.51
hole 8" i/d, 3/16" thick
NWFP CSR 2008 - Approved 25-Aug-2008 Page 124 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-07-c Providing and installing brass strainer in tubewell bore Rft 301.26 3,144.76 m 988.38 10,317.45
hole 10" i/d 3/16" thick
24-07-d Providing and installing brass strainer in tubewell bore Rft 301.26 3,695.16 m 988.38 12,123.23
hole 10" i/d, 1/4" thick
24-07-e Providing and installing brass strainer in tubewell bore Rft 321.34 3,890.84 m 1,054.27 12,765.23
hole 12" i/d, 1/4" thick
24-08-a Providing and installing MS bail plug in tubewell bore Rft 133.07 1,790.77 m 436.59 5,875.24 In the case of increase
hole 6" i/d, 2 ft. long and decreas in the
length of bail plug, tie
rates will be increased
or decreased as per
rates given in section
No 12 to this
diameter.
24-08-b Providing and installing MS bail plug in tubewell bore Rft 137.04 1,837.09 m 449.62 6,027.21
hole 8" i/d, 2 ft. long
24-08-c Providing and installing MS bail plug in tubewell bore Rft 137.04 1,921.79 m 449.62 6,305.10
hole 10" i/d, 2 ft. long
24-08-d Providing and installing MS bail plug in tubewell bore Rft 146.12 2,118.42 m 479.38 6,950.18
hole 12" i/d, 2 ft. long
24-09-a-01 Providing and installing PVC strainer, in tubewell Rft 192.80 363.72 m 632.56 1,193.30
borehole comp. BSS Class 'B' working pressure : 6" i/d
24-09-a-02 Providing and installing PVC strainer, in tubewell Rft 241.01 498.13 m 790.70 1,634.29
borehole comp. BSS Class 'B' working pressure : 8" i/d
24-09-a-03 Providing and installing PVC strainer, in tubewell Rft 257.07 653.35 m 843.42 2,143.53
borehole comp. BSS Class 'B' working pressure : 10" i/d
24-09-a-04 Providing and installing PVC strainer, in tubewell Rft 289.21 879.08 m 948.84 2,884.13
borehole comp. BSS Class 'B' working pressure : 12" i/d
24-09-b-01 Providing and installing PVC strainer, in tubewell Rft 192.80 452.95 m 632.56 1,486.07
borehole comp. BSS Class 'C' working pressure : 6" i/d
24-09-b-02 Providing and installing PVC strainer, in tubewell Rft 241.01 634.26 m 790.70 2,080.89
borehole comp. BSS Class 'C' working pressure : 8" i/d
24-09-b-03 Providing and installing PVC strainer, in tubewell Rft 257.07 862.07 m 843.42 2,828.32
borehole comp. BSS Class 'C' working pressure : 10" i/d
24-09-b-04 Providing and installing PVC strainer, in tubewell Rft 289.21 1,174.02 m 948.84 3,851.77
borehole comp. BSS Class 'C' working pressure : 12" i/d
24-09-c-01 Providing and installing PVC strainer, in tubewell Rft 192.80 525.55 m 632.56 1,724.26
borehole comp. BSS Class 'D' working pressure : 6" i/d
24-09-c-02 Providing and installing PVC strainer, in tubewell Rft 241.01 762.82 m 790.70 2,502.69
borehole comp. BSS Class 'D' working pressure : 8" i/d
24-09-c-03 Providing and installing PVC strainer, in tubewell Rft 257.07 1,051.14 m 843.42 3,448.61
borehole comp. BSS Class 'D' working pressure : 10" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 125 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-09-c-04 Providing and installing PVC strainer, in tubewell Rft 289.21 1,423.58 m 948.84 4,670.54
borehole comp. BSS Class 'D' working pressure : 12" i/d
24-10-a-01 Providing and installing PVC pipe with wooden bail plug Each 210.80 532.27 Each 210.80 532.27
in tubewell BSS Class 'B' working pressure : 6" i/d : 2' long
24-10-a-02 Providing and installing PVC pipe with wooden bail plug Each 263.50 754.64 Each 263.50 754.64
in tubewell BSS Class 'B' working pressure : 8" i/d : 2' long
24-10-a-03 Providing and installing PVC pipe with wooden bail plug Each 263.50 1,028.49 Each 263.50 1,028.49
in tubewell BSS Class 'B' working pressure : 10" i/d : 2'
long
24-10-a-04 Providing and installing PVC pipe with wooden bail plug Each 316.20 1,447.31 Each 316.20 1,447.31
in tubewell BSS Class 'B' working pressure : 12" i/d : 2'
long
24-10-b-01 Providing and installing PVC pipe with wooden bail plug Each 210.80 704.92 Each 210.80 704.92
in tubewell BSS Class 'C' working pressure : 6" i/d : 2' long
24-10-b-02 Providing and installing PVC pipe with wooden bail plug Each 263.50 1,016.58 Each 263.50 1,016.58
in tubewell BSS Class 'C' working pressure : 8" i/d : 2' long
24-10-b-03 Providing and installing PVC pipe with wooden bail plug Each 263.50 1,427.35 Each 263.50 1,427.35
in tubewell BSS Class 'C' working pressure : 10" i/d : 2'
long
24-10-b-04 Providing and installing PVC pipe with wooden bail plug Each 316.20 2,027.74 Each 316.20 2,027.74
in tubewell BSS Class 'C' working pressure : 12" i/d : 2'
long
24-10-c-01 Providing and installing PVC pipe with wooden bail plug Each 210.80 847.79 Each 210.80 847.79
in tubewell BSS Class 'D' working pressure : 6" i/d : 2' long
24-10-c-02 Providing and installing PVC pipe with wooden bail plug Each 263.50 1,260.66 Each 263.50 1,260.66
in tubewell BSS Class 'D' working pressure : 8" i/d : 2' long
24-10-c-03 Providing and installing PVC pipe with wooden bail plug Each 263.50 1,799.43 Each 263.50 1,799.43
in tubewell BSS Class 'D' working pressure : 10" i/d : 2'
long
24-10-c-04 Providing and installing PVC pipe with wooden bail plug Each 316.20 2,515.91 Each 316.20 2,515.91
in tubewell BSS Class 'D' working pressure : 12" i/d : 2'
long
24-11-a Providing and installing MS blind pipe socket/welded Rft 361.51 721.48 m 1,186.05 2,367.07
joint MS reducer in tubewell borehole : 6" i/d, 3/16" thick
24-11-b Providing and installing MS blind pipe socket/welded Rft 421.76 899.49 m 1,383.73 2,951.08
joint MS reducer in tubewell borehole : 8" i/d, 3/16" thick
24-11-c Providing and installing MS blind pipe socket/welded Rft 502.10 1,082.75 m 1,647.30 3,552.33
joint MS reducer in tubewell borehole : 10" i/d 3/16" thick
24-11-d Providing and installing MS blind pipe socket/welded Rft 578.41 1,243.91 m 1,897.69 4,081.09
joint MS reducer in tubewell borehole : 12" i/d, 1/4" thick
24-12-a-01 Providing and installing PVC blind pipe in tubewell with Rft 337.41 500.76 m 1,106.98 1,642.91
strainer BSS Class 'B' working pressure : 6" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 126 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-12-a-02 Providing and installing PVC blind pipe in tubewell with Rft 401.68 651.24 m 1,317.84 2,136.61
strainer BSS Class 'B' working pressure : 8" i/d
24-12-a-03 Providing and installing PVC blind pipe in tubewell with Rft 546.04 934.76 m 1,791.48 3,066.79
strainer BSS Class 'B' working pressure : 10" i/d
24-12-a-04 Providing and installing PVC blind pipe in tubewell with Rft 542.26 1,117.01 m 1,779.08 3,664.74
strainer BSS Class 'B' working pressure : 12" i/d
24-12-b-01 Providing and installing PVC blind pipe in tubewell with Rft 341.43 592.50 m 1,120.16 1,943.90
strainer BSS Class 'C' working pressure : 6" i/d
24-12-b-02 Providing and installing PVC blind pipe in tubewell with Rft 401.68 784.34 m 1,317.84 2,573.29
strainer BSS Class 'C' working pressure : 8" i/d
24-12-b-03 Providing and installing PVC blind pipe in tubewell with Rft 441.84 1,033.23 m 1,449.62 3,389.87
strainer BSS Class 'C' working pressure : 10" i/d
24-12-b-04 Providing and installing PVC blind pipe in tubewell with Rft 542.26 1,411.95 m 1,779.08 4,632.39
strainer BSS Class 'C' working pressure : 12" i/d
24-12-c-01 Providing and installing PVC blind pipe in tubewell with Rft 341.43 665.10 m 1,120.16 2,182.09
strainer BSS Class 'D' working pressure : 6" i/d
24-12-c-02 Providing and installing PVC blind pipe in tubewell with Rft 401.68 908.36 m 1,317.84 2,980.20
strainer BSS Class 'D' working pressure : 8" i/d
24-12-c-03 Providing and installing PVC blind pipe in tubewell with Rft 441.84 1,222.29 m 1,449.62 4,010.15
strainer BSS Class 'D' working pressure : 10" i/d
24-12-c-04 Providing and installing PVC blind pipe in tubewell with Rft 542.26 1,660.00 m 1,779.08 5,446.20
strainer BSS Class 'D' working pressure : 12" i/d
24-13-a Test & develop tubewell of size 6" i/d & above Hour 0.00 423.50 Hour 0.00 423.50 Compressor,
continuously : Upto 1.5 cusecs discharge accessories along
with working staff to
be supplied by Govt;
24-13-b Test & develop tubewell of size 6" i/d & above Hour 0.00 496.10 Hour 0.00 496.10
continuously : Over 1.5 cusecs discharge with DNT unit
24-14 Shrouding with graded pack grave 3/8" to 1/8" around Rft 106.33 129.77 m 348.84 425.74 The rate includes
tubewell in bore hole wastage etc.
24-15-a Providing and Laying cut, joint, test & disinfect, CI Rft 30.13 368.93 m 98.84 1,210.39 a) Pipes to be
pipeline in trenches, complete : 3" i/d supplied by Govt;
24-15-b Providing and Laying cut, joint, test & disinfect, CI Rft 40.17 294.27 m 131.78 965.45 b) Providing and
pipeline in trenches, complete : 4" i/d installing specials and
valves is not included
in the rate, which is
payable separately.
24-15-c Providing and Laying cut, joint, test & disinfect, CI Rft 60.25 834.65 m 197.68 2,738.36
pipeline in trenches, complete : 6" i/d
24-15-d Providing and Laying cut, joint, test & disinfect, CI Rft 100.42 1,350.63 m 329.46 4,431.20
pipeline in trenches. complete : 8" i/d
24-15-e Providing and Laying cut, joint, test & disinfect, CI Rft 130.54 1,716.83 m 428.30 5,632.63
pipeline in trenches, complete : 10" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 127 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-15-f Providing and Laying cut, joint, test & disinfect, CI Rft 130.54 2,380.85 m 428.30 7,811.19
pipeline in trenches, complete : 12" i/d
24-16-a-01 Providing and Laying cut, joint, test & disinfect GI pipe Rft 38.16 431.41 m 125.19 1,415.38
line Using heavy quality GI Pipe : 4" Dia
24-16-a-02 Providing and Laying cut, joint, test & disinfect GI pipe Rft 54.23 628.98 m 177.91 2,063.57
line Using heavy quality GI Pipe : 6" Dia
24-16-a-03 Providing and Laying cut, joint, test & disinfect GI pipe Rft 70.29 735.79 m 230.62 2,414.02
line Using heavy quality GI Pipe : 8" Dia
24-16-b-01 Providing and Laying cut, joint, test & disinfect GI pipe Rft 38.16 364.86 m 125.19 1,197.05
line Using medium quality GI Pipe : 4" Dia
24-16-b-02 Providing and Laying cut, joint, test & disinfect GI pipe Rft 54.23 538.23 m 177.91 1,765.83
line Using medium quality GI Pipe : 6" Dia
24-16-b-03 Providing and Laying cut, joint, test & disinfect GI pipe Rft 70.29 632.94 m 230.62 2,076.59
line Using medium quality GI Pipe : 8" Dia
24-16-c-01 Providing and Laying cut, joint, test & disinfect GI pipe Rft 10.04 41.50 m 32.95 136.16 Cost of sockets, tees,
line Using light quality GI Pipe : 1/2" i/d elbows, bends, valves,
crosses, unions and
plugs etc is included
in the rates.
24-16-c-02 Providing and Laying cut, joint, test & disinfect GI pipe Rft 12.05 56.09 m 39.54 184.04
line Using light quality GI Pipe : 3/4" i/d
24-16-c-03 Providing and Laying cut, joint, test & disinfect GI pipe Rft 13.11 74.82 m 43.02 245.48
line Using light quality GI Pipe : 1" i/d
24-16-c-04 Providing and Laying cut, joint, test & disinfect GI pipe Rft 16.07 95.93 m 52.71 314.72
line Using light quality GI Pipe : 1.25" i/d
24-16-c-05 Providing and Laying cut, joint, test & disinfect GI pipe Rft 18.08 118.20 m 59.30 387.81
line Using light quality GI Pipe : 1.5" i/d
24-16-c-06 Providing and Laying cut, joint, test & disinfect GI pipe Rft 20.12 145.96 m 66.02 478.88
line Using light quality GI Pipe : 2" i/d
24-16-c-07 Providing and Laying cut, joint, test & disinfect GI pipe Rft 22.09 196.33 m 72.48 644.13
line Using light quality GI Pipe : 2.5" i/d
24-16-c-08 Providing and Laying cut, joint, test & disinfect GI pipe Rft 30.13 233.41 m 98.84 765.77
line Using light quality GI Pipe : 3" i/d
24-16-c-09 Providing and Laying cut, joint, test & disinfect GI pipe Rft 38.16 340.66 m 125.19 1,117.65
line Using light quality GI Pipe : 4" i/d
24-17-a-01 Providing and Laying cut, joint, test & disinfect AC pipe Rft 16.07 79.23 m 52.71 259.94 Providing and
line BSS Class 'B'working pressure : 3" i/d installing specials and
valves is not included
in the rate, which is
payable separately.
24-17-a-02 Providing and Laying cut, joint, test & disinfect AC pipe Rft 18.08 110.57 m 59.30 362.76
line BSS Class 'B'working pressure : 4" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 128 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-17-a-03 Providing and Laying cut, joint, test & disinfect AC pipe Rft 26.11 165.73 m 85.66 543.74
line BSS Class 'B'working pressure : 6" i/d
24-17-a-04 Providing and Laying cut, joint, test & disinfect AC pipe Rft 36.15 267.37 m 118.61 877.20
line BSS Class 'B'working pressure : 8" i/d
24-17-a-05 Providing and Laying cut, joint, test & disinfect AC pipe Rft 43.17 427.75 m 141.63 1,403.40
line BSS Class 'B'working pressure : 10" i/d
24-17-a-06 Providing and Laying cut, joint, test & disinfect AC pipe Rft 60.25 590.41 m 197.68 1,937.05
line BSS Class 'B'working pressure : 12" i/d
24-17-a-07 Providing and Laying cut, joint, test & disinfect AC pipe Rft 70.29 789.24 m 230.62 2,589.37
line BSS Class 'B'working pressure : 14" i/d
24-17-a-08 Providing and Laying cut, joint, test & disinfect AC pipe Rft 80.34 1,014.37 m 263.57 3,327.99
line BSS Class 'B'working pressure : 16" i/d
24-17-a-09 Providing and Laying cut, joint, test & disinfect AC pipe Rft 92.39 1,249.94 m 303.10 4,100.87
line BSS Class 'B'working pressure : 18" i/d
24-17-a-10 Providing and Laying cut, joint, test & disinfect AC pipe Rft 108.45 1,517.30 m 355.82 4,978.03
line BSS Class 'B'working pressure : 20" i/d
24-17-a-11 Providing and Laying cut, joint, test & disinfect AC pipe Rft 128.54 2,120.39 m 421.71 6,956.66
line BSS Class 'B'working pressure : 24" i/d
24-17-b-01 Providing and Laying cut, joint, test & disinfect AC pipe Rft 16.07 79.59 m 52.71 261.13
line BSS Class 'C'working pressure : 3" i/d
24-17-b-02 Providing and Laying cut, joint, test & disinfect AC pipe Rft 18.08 115.24 m 59.30 378.08
line BSS Class 'C'working pressure : 4" i/d
24-17-b-03 Providing and Laying cut, joint, test & disinfect AC pipe Rft 26.11 225.38 m 85.66 739.45
line BSS Class 'C'working pressure : 6" i/d
24-17-b-04 Providing and Laying cut, joint, test & disinfect AC pipe Rft 36.15 330.19 m 118.61 1,083.31
line BSS Class 'C'working pressure : 8" i/d
24-17-b-05 Providing and Laying cut, joint, test & disinfect AC pipe Rft 46.19 550.07 m 151.55 1,804.70
line BSS Class 'C'working pressure : 10" i/d
24-17-b-06 Providing and Laying cut, joint, test & disinfect AC pipe Rft 65.57 774.94 m 215.12 2,542.46
line BSS Class 'C'working pressure : 12" i/d
24-17-b-07 Providing and Laying cut, joint, test & disinfect AC pipe Rft 70.29 1,053.01 m 230.62 3,454.75
line BSS Class 'C'working pressure : 14" i/d
24-17-b-08 Providing and Laying cut, joint, test & disinfect AC pipe Rft 80.34 1,465.65 m 263.57 4,808.57
line BSS Class 'C'working pressure : 16" i/d
24-17-b-09 Providing and Laying cut, joint, test & disinfect AC pipe Rft 92.39 1,812.85 m 303.10 5,947.66
line BSS Class 'C'working pressure : 18" i/d
24-17-b-10 Providing and Laying cut, joint, test & disinfect AC pipe Rft 108.45 2,201.70 m 355.82 7,223.44
line BSS Class 'C'working pressure : 20" i/d
24-17-b-11 Providing and Laying cut, joint, test & disinfect AC pipe Rft 128.54 3,125.65 m 421.71 10,254.74
line BSS Class 'C'working pressure : 24" i/d
24-17-c-01 Providing and Laying cut, joint, test & disinfect AC pipe Rft 16.07 79.59 m 52.71 261.13
line BSS Class 'D'working pressure : 3" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 129 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-17-c-02 Providing and Laying cut, joint, test & disinfect AC pipe Rft 19.67 145.11 m 64.54 476.09
line BSS Class 'D'working pressure : 4" i/d
24-17-c-03 Providing and Laying cut, joint, test & disinfect AC pipe Rft 28.41 278.66 m 93.22 914.25
line BSS Class 'D'working pressure : 6" i/d
24-17-c-04 Providing and Laying cut, joint, test & disinfect AC pipe Rft 39.34 468.53 m 129.07 1,537.16
line BSS Class 'D'working pressure : 8" i/d
24-17-c-05 Providing and Laying cut, joint, test & disinfect AC pipe Rft 55.66 816.42 m 182.60 2,678.54
line BSS Class 'D'working pressure : 10" i/d
24-17-c-06 Providing and Laying cut, joint, test & disinfect AC pipe Rft 65.57 1,162.51 m 215.12 3,813.99
line BSS Class 'D'working pressure : 12" i/d
24-17-c-07 Providing and Laying cut, joint, test & disinfect AC pipe Rft 76.50 1,479.14 m 250.97 4,852.82
line BSS Class 'D'working pressure : 14" i/d
24-17-c-08 Providing and Laying cut, joint, test & disinfect AC pipe Rft 87.42 2,127.87 m 286.82 6,981.20
line BSS Class 'D'working pressure : 16" i/d
24-17-c-09 Providing and Laying cut, joint, test & disinfect AC pipe Rft 100.54 2,649.16 m 329.85 8,691.47
line BSS Class 'D'working pressure : 18" i/d
24-17-c-10 Providing and Laying cut, joint, test & disinfect AC pipe Rft 118.02 3,356.03 m 387.21 11,010.60
line BSS Class 'D'working pressure : 20" i/d
24-17-c-11 Providing and Laying cut, joint, test & disinfect AC pipe Rft 139.88 4,278.70 m 458.92 14,037.71
line BSS Class 'D'working pressure : 24" i/d
24-18-a-01 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 17.48 74.96 m 57.36 245.93 a) Providing and
line BSS Class 'B'working pressure : 3" i/d installing specials and
valves is not included
in the rate, which is
payable separately.
24-18-a-02 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 19.67 101.35 m 64.54 332.50 b) When sockets are
line BSS Class 'B'working pressure : 4" i/d used for jointing of
pipes instead of by
overlap pipe. Its
providing installation
will be paid extra.
24-18-a-03 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 28.41 191.76 m 93.22 629.14
line BSS Class 'B'working pressure : 6" i/d
24-18-a-04 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 39.34 288.90 m 129.07 947.85
line BSS Class 'B'working pressure : 8" i/d
24-18-a-05 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 50.27 438.98 m 164.92 1,440.23
line BSS Class 'B'working pressure : 10" i/d
24-18-a-06 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 65.57 640.32 m 215.12 2,100.78
line BSS Class 'B'working pressure : 12" i/d
24-18-b-01 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 17.48 52.27 m 57.36 171.50
line BSS Class 'C'working pressure : 2.5" i/d
24-18-b-02 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 17.48 87.06 m 57.36 285.63
line BSS Class 'C'working pressure : 3" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 130 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-18-b-03 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 19.67 137.65 m 64.54 451.59
line BSS Class 'C'working pressure : 4" i/d
24-18-b-04 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 28.41 279.49 m 93.22 916.95
line BSS Class 'C'working pressure : 6" i/d
24-18-b-05 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 39.34 422.00 m 129.07 1,384.53
line BSS Class 'C'working pressure : 8" i/d
24-18-b-06 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 50.27 641.66 m 164.92 2,105.17
line BSS Class 'C'working pressure : 10" i/d
24-18-b-07 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 65.57 935.26 m 215.12 3,068.42
line BSS Class 'C'working pressure : 12" i/d
24-18-c-01 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 13.99 35.16 m 45.89 115.36
line BSS Class 'D' working pressure : 1.25" i/d
24-18-c-02 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 16.28 41.99 m 53.40 137.75
line BSS Class 'D' working pressure : 1.5" i/d
24-18-c-03 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 16.28 55.60 m 53.40 182.41
line BSS Class 'D' working pressure : 2" i/d
24-18-c-04 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 17.48 119.73 m 57.36 392.81
line BSS Class 'D' working pressure : 2.5" i/d
24-18-c-05 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 17.48 127.59 m 57.36 418.62
line BSS Class 'D' working pressure : 3" i/d
24-18-c-06 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 19.67 175.46 m 64.54 575.65
line BSS Class 'D' working pressure : 4" i/d
24-18-c-07 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 28.41 352.09 m 93.22 1,155.14
line BSS Class 'D' working pressure : 6" i/d
24-18-c-08 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 39.34 546.03 m 129.07 1,791.43
line BSS Class 'D' working pressure : 8" i/d
24-18-c-09 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 50.27 830.72 m 164.92 2,725.46
line BSS Class 'D' working pressure : 10" i/d
24-18-c-10 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 65.57 1,183.31 m 215.12 3,882.23
line BSS Class 'D' working pressure : 12" i/d
24-18-d-01 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 15.07 28.68 m 49.43 94.09
line BSS Class 'E' working pressure : 3/4" i/d
24-18-d-02 Providing and Laying cut, joint, test, disinfect PVC pipe Rft 8.26 27.92 m 27.10 91.61
line BSS Class 'E' working pressure : 1" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 131 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-19-a-01 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 28.67 188.40 kg 28.67 188.40 a) Labour rates
CISS specials, with spigot & socket : 3"-6" i/d include the cost of
jointing material and
labour b) The internal
dia of the pipe, from
which the branch is
taken out, will be
considered internal
dia for the purpose of
payment of specials.
24-19-a-02 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 34.56 194.29 kg 34.56 194.29
CISS specials, with spigot & socket : 8"-12" i/d
24-19-b-01 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 14.34 174.06 kg 14.34 174.06
CI flanged specials with flanged joint : 3"-6" i/d
24-19-b-02 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 22.94 182.66 kg 22.94 182.66
CI flanged specials with flanged joint : 8"-12" i/
24-19-c-01 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 6.58 166.30 kg 6.58 166.30
CI specials with tyton joints : 3"-6" i/d
24-19-c-02 Providing and Fixing CI specials of BSS class 'B', 'C' & 'D' kg 11.98 171.70 kg 11.98 171.70
CI specials with tyton joints : 8"-12" i/d
24-20-a Providing and Fixing CI specials of BSS Class 'B', 'C' & 'D' kg 37.02 196.74 kg 37.02 196.74 a) Labour rates
working pressure for AC pipe line : 3" to 6" i/d include the cost of
jointing material and
labour b) The internal
dia of the pipe, from
which the branch is
taken out, will be
considered internal
dia for the purpose of
payment of specials.
24-20-b Providing and Fixing CI specials of BSS Class 'B', 'C' & 'D' kg 57.35 217.07 kg 57.35 217.07
working pressure for AC pipe line : 8" to 18" i/d
24-21-a Providing and Fixing sluice valve, BSS quality/weight, Each 867.22 2,682.23 Each 867.22 2,682.23 Labour rates include
Class 'B' working pressure for CI & AC pipe line : 3" i/d the cost of jointing
material and labour
24-21-b Providing and Fixing sluice valve, BSS quality/weight, Each 229.40 2,649.40 Each 229.40 2,649.40
Class 'B' working pressure for CI & AC pipe line : 4" i/d
24-21-c Providing and Fixing sluice valve, BSS quality/weight, Each 911.40 4,783.40 Each 911.40 4,783.40
Class 'B' working pressure for CI & AC pipe line : 6" i/d
24-21-d Providing and Fixing sluice valve, BSS quality/weight, Each 911.40 8,776.40 Each 911.40 8,776.40
Class 'B' working pressure for CI & AC pipe line : 8" i/d
24-21-e Providing and Fixing sluice valve, BSS quality/weight, Each 1,147.00 12,642.00 Each 1,147.00 12,642.00
Class 'B' working pressure for CI & AC pipe line : 10" i/d
24-21-f Providing and Fixing sluice valve, BSS quality/weight, Each 1,720.50 17,450.50 Each 1,720.50 17,450.50
Class 'B' working pressure for CI & AC pipe line : 12" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 132 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-22-a Providing and Fixing sluice valve of BSS quality weight Each 926.13 2,922.63 Each 926.13 2,922.63 ditto
for GI & PVC pipe line including jointing material : 3" i/d
24-22-b Providing and Fixing sluice valve of BSS quality weight Each 926.13 3,588.13 Each 926.13 3,588.13
for GI & PVC pipe line including jointing material : 4" i/d
24-22-c Providing and Fixing sluice valve of BSS quality weight Each 1,147.00 5,406.20 Each 1,147.00 5,406.20
for GI & PVC pipe line including jointing material : 6" i/d
24-22-d Providing and Fixing sluice valve of BSS quality weight Each 1,433.75 10,085.25 Each 1,433.75 10,085.25
for GI & PVC pipe line including jointing material : 8" i/d
24-22-e Providing and Fixing sluice valve of BSS quality weight Each 1,867.75 14,512.25 Each 1,867.75 14,512.25
for GI & PVC pipe line including jointing material : 10" i/d
24-22-f Providing and Fixing sluice valve of BSS quality weight Each 2,294.00 19,597.00 Each 2,294.00 19,597.00
for GI & PVC pipe line including jointing material : 12" i/d
24-23 Providing and Fixing fire hydrants BSS quality and weight Each 1,720.50 5,985.75 Each 1,720.50 5,985.75 a) Labour rates
of 2.5" dia (including cost of jointing material) include cost of
jointing material and
labour b) Connecting
pipes and specials , if
used will be paid
extra.
24-24-a Providing and Fixing air valve 2«" i/d of BSS quality and Each 1,147.00 3,034.60 Each 1,147.00 3,034.60
weight complete with jointing material : Single
24-24-b Providing and Fixing air valve 2«" i/d of BSS quality and Each 1,720.50 4,793.90 Each 1,720.50 4,793.90
weight complete with jointing material : Double
24-25-a Providing and Fixing CI flanges 5/8" thick on pipes Each 702.92 1,307.93 Each 702.92 1,307.93
including turning, facing & fitting etc complete : 3" to 6"
i/d
24-25-b Providing and Fixing CI flanges 5/8" thick on pipes Each 1,033.07 2,073.68 Each 1,033.07 2,073.68
including turning, facing & fitting etc complete : 8" to 12"
i/d
24-26-a-01 Providing and installing PVC bends BSS Class 'B'working Each 98.19 162.08 Each 98.19 162.08
pressure : 2" i/d
24-26-a-02 Providing and installing PVC bends BSS Class 'B'working Each 107.53 247.29 Each 107.53 247.29
pressure : 3" i/d
24-26-a-03 Providing and installing PVC bends BSS Class 'B'working Each 143.38 328.38 Each 143.38 328.38
pressure : 4" i/d
24-26-a-04 Providing and installing PVC bends BSS Class 'B'working Each 207.89 813.50 Each 207.89 813.50
pressure : 6" i/d
24-26-a-05 Providing and installing PVC bends BSS Class 'B'working Each 286.75 3,055.23 Each 286.75 3,055.23
pressure : 8" i/d
24-26-a-06 Providing and installing PVC bends BSS Class 'B'working Each 329.38 4,655.13 Each 329.38 4,655.13
pressure : 10" i/d
24-26-a-07 Providing and installing PVC bends BSS Class 'B'working Each 395.25 5,586.15 Each 395.25 5,586.15
pressure : 12" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 133 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-26-b-01 Providing and installing PVC bends BSS Class 'C'working Each 90.29 176.80 Each 90.29 176.80
pressure : 2" i/d
24-26-b-02 Providing and installing PVC bends BSS Class 'C'working Each 98.81 271.84 Each 98.81 271.84
pressure : 3" i/d
24-26-b-03 Providing and installing PVC bends BSS Class 'C'working Each 131.75 339.39 Each 131.75 339.39
pressure : 4" i/d
24-26-b-04 Providing and installing PVC bends BSS Class 'C'working Each 191.04 1,318.39 Each 191.04 1,318.40
pressure : 6" i/d
24-26-b-05 Providing and installing PVC bends BSS Class 'C'working Each 263.50 3,724.10 Each 263.50 3,724.10
pressure : 8" i/d
24-26-b-06 Providing and installing PVC bends BSS Class 'C'working Each 329.38 5,520.27 Each 329.38 5,520.27
pressure : 10" i/d
24-26-b-07 Providing and installing PVC bends BSS Class 'C'working Each 395.25 6,624.33 Each 395.25 6,624.33
pressure : 12" i/d
24-26-c-01 Providing and installing PVC bends BSS Class 'D'working Each 90.29 194.11 Each 90.29 194.11
pressure : 2" i/d
24-26-c-02 Providing and installing PVC bends BSS Class 'D'working Each 98.81 358.36 Each 98.81 358.36
pressure : 3" i/d
24-26-c-03 Providing and installing PVC bends BSS Class 'D'working Each 143.38 489.43 Each 143.38 489.43
pressure : 4" i/d
24-26-c-04 Providing and installing PVC bends BSS Class 'D'working Each 207.89 1,938.19 Each 207.89 1,938.19
pressure : 6" i/d
24-26-c-05 Providing and installing PVC bends BSS Class 'D'working Each 286.75 5,304.62 Each 286.75 5,304.62
pressure : 8" i/d
24-26-c-06 Providing and installing PVC bends BSS Class 'D'working Each 358.44 6,587.52 Each 358.44 6,587.52
pressure : 10" i/d
24-26-c-07 Providing and installing PVC bends BSS Class 'D'working Each 430.13 7,351.33 Each 430.13 7,351.33
pressure : 12" i/d
24-27-a-01 Providing and installing PVC tees BSS Class 'B'working Each 143.38 217.91 Each 143.38 217.91
pressure : 2" i/d
24-27-a-02 Providing and installing PVC tees BSS Class 'B'working Each 172.05 386.34 Each 172.05 386.34
pressure : 3" i/d
24-27-a-03 Providing and installing PVC tees BSS Class 'B'working Each 229.40 528.88 Each 229.40 528.88
pressure : 4" i/d
24-27-a-04 Providing and installing PVC tees BSS Class 'B'working Each 315.42 1,293.71 Each 315.42 1,293.71
pressure : 6" i/d
24-27-a-05 Providing and installing PVC tees BSS Class 'B'working Each 465.97 3,018.83 Each 465.97 3,018.83
pressure : 8" i/d
24-27-a-06 Providing and installing PVC tees BSS Class 'B'working Each 537.66 3,133.11 Each 537.66 3,133.11
pressure : 10" i/d
24-27-a-07 Providing and installing PVC tees BSS Class 'B'working Each 645.19 3,327.15 Each 645.19 3,327.15
pressure : 12" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 134 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-27-b-01 Providing and installing PVC tees BSS Class 'C'working Each 143.38 264.50 Each 143.38 264.50
pressure : 2" i/d
24-27-b-02 Providing and installing PVC tees BSS Class 'C'working Each 172.05 431.60 Each 172.05 431.60
pressure : 3" i/d
24-27-b-03 Providing and installing PVC tees BSS Class 'C'working Each 229.40 671.29 Each 229.40 671.29
pressure : 4" i/d
24-27-b-04 Providing and installing PVC tees BSS Class 'C'working Each 315.42 1,197.88 Each 315.42 1,197.88
pressure : 6" i/d
24-27-b-05 Providing and installing PVC tees BSS Class 'C'working Each 465.97 6,522.02 Each 465.97 6,522.02
pressure : 8" i/d
24-27-b-06 Providing and installing PVC tees BSS Class 'C'working Each 534.71 7,801.97 Each 534.71 7,801.97
pressure : 10" i/d
24-27-b-07 Providing and installing PVC tees BSS Class 'C'working Each 645.19 9,902.29 Each 645.19 9,902.29
pressure : 12" i/d
24-27-c-01 Providing and installing PVC tees BSS Class 'D'working Each 143.38 406.91 Each 143.38 406.91
pressure : 2" i/d
24-27-c-02 Providing and installing PVC tees BSS Class 'D'working Each 172.05 695.13 Each 172.05 695.13
pressure : 3" i/d
24-27-c-03 Providing and installing PVC tees BSS Class 'D'working Each 229.40 852.31 Each 229.40 852.31
pressure : 4" i/d
24-27-c-04 Providing and installing PVC tees BSS Class 'D'working Each 315.42 1,293.71 Each 315.42 1,293.71
pressure : 6" i/d
24-27-c-05 Providing and installing PVC tees BSS Class 'D'working Each 465.97 4,618.69 Each 465.97 4,618.69
pressure : 8" i/d
24-27-c-06 Providing and installing PVC tees BSS Class 'D'working Each 537.66 5,921.55 Each 537.66 5,921.55
pressure : 10" i/d
24-27-c-07 Providing and installing PVC tees BSS Class 'D'working Each 645.19 6,874.27 Each 645.19 6,874.27
pressure : 12" i/d
24-28-a-01 Providing and installing PVC sockets BSS Class Each 48.05 95.97 Each 48.05 95.97
'B'working pressure : 2" i/d
24-28-a-02 Providing and installing PVC sockets BSS Class Each 50.18 146.01 Each 50.18 146.01
'B'working pressure : 3" i/d
24-28-a-03 Providing and installing PVC sockets BSS Class Each 71.69 188.82 Each 71.69 188.82
'B'working pressure : 4" i/d
24-28-a-04 Providing and installing PVC sockets BSS Class Each 564.28 1,296.33 Each 564.28 1,296.33
'B'working pressure : 6" i/d
24-28-a-05 Providing and installing PVC sockets BSS Class Each 143.38 1,089.72 Each 143.38 1,089.72
'B'working pressure : 8" i/d
24-28-a-06 Providing and installing PVC sockets BSS Class Each 179.07 1,468.81 Each 179.07 1,468.81
'B'working pressure : 10" i/d
24-28-a-07 Providing and installing PVC sockets BSS Class Each 215.06 1,918.74 Each 215.06 1,918.74
'B'working pressure : 12" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 135 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-28-b-01 Providing and installing PVC sockets BSS Class Each 48.05 117.26 Each 48.05 117.26
'C'working pressure : 2" i/d
24-28-b-02 Providing and installing PVC sockets BSS Class Each 282.10 428.91 Each 282.10 428.91
'C'working pressure : 3" i/d
24-28-b-03 Providing and installing PVC sockets BSS Class Each 71.69 244.72 Each 71.69 244.72
'C'working pressure : 4" i/d
24-28-b-04 Providing and installing PVC sockets BSS Class Each 100.36 1,032.06 Each 100.36 1,032.06
'C'working pressure : 6" i/d
24-28-b-05 Providing and installing PVC sockets BSS Class Each 143.38 1,474.38 Each 143.38 1,474.38
'C'working pressure : 8" i/d
24-28-b-06 Providing and installing PVC sockets BSS Class Each 179.22 1,909.52 Each 179.22 1,909.52
'C'working pressure : 10" i/d
24-28-b-07 Providing and installing PVC sockets BSS Class Each 215.06 2,544.31 Each 215.06 2,544.31
'C'working pressure : 12" i/d
24-28-c-01 Providing and installing PVC sockets BSS Class Each 48.05 169.17 Each 48.05 169.17
'D'working pressure : 2" i/d
24-28-c-02 Providing and installing PVC sockets BSS Class Each 50.18 400.23 Each 50.18 400.23
'D'working pressure : 3" i/d
24-28-c-03 Providing and installing PVC sockets BSS Class Each 71.69 670.64 Each 71.69 670.64
'D'working pressure : 4" i/d
24-28-c-04 Providing and installing PVC sockets BSS Class Each 100.36 1,205.09 Each 100.36 1,205.09
'D'working pressure : 6" i/d
24-28-c-05 Providing and installing PVC sockets BSS Class Each 143.38 1,740.57 Each 143.38 1,740.57
'D'working pressure : 8" i/d
24-28-c-06 Providing and installing PVC sockets BSS Class Each 179.22 2,375.37 Each 179.22 2,375.37
'D'working pressure : 10" i/d
24-28-c-07 Providing and installing PVC sockets BSS Class Each 215.06 3,143.26 Each 215.06 3,143.26
'D'working pressure : 12" i/d
24-29-a-01 Providing and installing PVC Tapered core BSS Class Each 98.19 176.06 Each 98.19 176.06
'B'working pressure : 2" i/d
24-29-a-02 Providing and installing PVC Tapered core BSS Class Each 107.53 202.70 Each 107.53 202.70
'B'working pressure : 3" i/d
24-29-a-03 Providing and installing PVC Tapered core BSS Class Each 143.38 259.31 Each 143.38 259.31
'B'working pressure : 4" i/d
24-29-a-04 Providing and installing PVC Tapered core BSS Class Each 207.89 360.16 Each 207.89 360.16
'B'working pressure : 6" i/d
24-29-a-05 Providing and installing PVC Tapered core BSS Class Each 286.75 546.29 Each 286.75 546.29
'B'working pressure : 8" i/d
24-29-a-06 Providing and installing PVC Tapered core BSS Class Each 358.44 791.01 Each 358.44 791.01
'B'working pressure : 10" i/d
24-29-a-07 Providing and installing PVC Tapered core BSS Class Each 424.55 909.03 Each 424.55 909.03
'B'working pressure : 12" i/d
NWFP CSR 2008 - Approved 25-Aug-2008 Page 136 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-29-b-01 Providing and installing PVC Tapered core BSS Class Each 98.19 184.71 Each 98.19 184.71
'C'working pressure : 2" i/d
24-29-b-02 Providing and installing PVC Tapered core BSS Class Each 107.53 211.35 Each 107.53 211.35
'C'working pressure : 3" i/d
24-29-b-03 Providing and installing PVC Tapered core BSS Class Each 143.38 267.96 Each 143.38 267.96
'C'working pressure : 4" i/d
24-29-b-04 Providing and installing PVC Tapered core BSS Class Each 208.19 369.11 Each 208.19 369.11
'C'working pressure : 6" i/d
24-29-b-05 Providing and installing PVC Tapered core BSS Class Each 286.75 554.95 Each 286.75 554.95
'C'working pressure : 8" i/d
24-29-b-06 Providing and installing PVC Tapered core BSS Class Each 358.44 818.70 Each 358.44 818.70
'C'working pressure : 10" i/d
24-29-b-07 Providing and installing PVC Tapered core BSS Class Each 430.96 976.01 Each 430.96 976.01
'C'working pressure : 12" i/d
24-29-c-01 Providing and installing PVC Tapered core BSS Class Each 98.19 167.40 Each 98.19 167.40
'D'working pressure : 2" i/d
24-29-c-02 Providing and installing PVC Tapered core BSS Class Each 107.53 197.51 Each 107.53 197.51
'D'working pressure : 3" i/d
24-29-c-03 Providing and installing PVC Tapered core BSS Class Each 143.38 286.99 Each 143.38 286.99
'D'working pressure : 4" i/d
24-29-c-04 Providing and installing PVC Tapered core BSS Class Each 207.89 424.18 Each 207.89 424.18
'D'working pressure : 6" i/d
24-29-c-05 Providing and installing PVC Tapered core BSS Class Each 286.75 650.11 Each 286.75 650.11
'D'working pressure : 8" i/d
24-29-c-06 Providing and installing PVC Tapered core BSS Class Each 358.44 1,033.25 Each 358.44 1,033.26
'D'working pressure : 10" i/d
24-29-c-07 Providing and installing PVC Tapered core BSS Class Each 430.13 1,314.31 Each 430.13 1,314.31
'D'working pressure : 12" i/d
24-30-a-01 Providing and Laying HDPE pipe Din-/Din-/ISO-4427 Rft 13.14 24.40 m 43.10 80.06
incl testing & disinfect complete (20mm dia)
24-30-a-02 Providing and Laying HDPE pipe Rft 13.14 27.78 m 43.10 91.14
Din-8074/Din-8075/ISO-4427 including testing & disinfect
complete (25mm dia)
24-30-a-03 Providing and Laying HDPE pipe Rft 13.14 37.69 m 43.10 123.67
Din-8074/Din-8075/ISO-4427 incl testing & disinfect
complete (32mm dia)
24-30-a-04 Providing and Laying HDPE pipe Rft 17.48 55.16 m 57.36 180.97
Din-8074/Din-8075/ISO-4427 including testing & disinfect
complete (40mm dia)
24-30-a-05 Providing and Laying HDPE pipe Rft 17.48 75.59 m 57.36 247.98
Din-8074/Din-8075/ISO-4427 including testing & disinfect
complete (50mm dia)

NWFP CSR 2008 - Approved 25-Aug-2008 Page 137 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-30-a-06 Providing and Laying HDPE pipe Rft 17.48 148.64 m 57.36 487.66
Din-8074/Din-8075/ISO-4427 incl testing & disinfect
complete (75mm dia)
24-30-a-07 Providing and Laying HDPE pipe Rft 19.67 295.90 m 64.54 970.79
Din-8074/Din-8075/ISO-4427 including testing & disinfect
complete (110mm dia)
24-30-b-01 Providing and installing HDPE Socket 20mm dia Each 34.41 56.19 Each 34.41 56.19
24-30-b-02 Providing and installing HDPE Socket 25mm dia Each 34.41 47.72 Each 34.41 47.72
24-30-b-03 Providing and installing HDPE Socket 32mm dia Each 34.41 50.14 Each 34.41 50.14
24-30-b-04 Providing and installing HDPE Socket 40mm dia Each 48.05 81.93 Each 48.05 81.93
24-30-b-05 Providing and installing HDPE Socket 50mm dia Each 255.21 285.46 Each 255.21 285.46
24-30-b-06 Providing and installing HDPE Socket 75mm dia Each 50.18 146.98 Each 50.18 146.98
24-30-b-07 Providing and installing HDPE Socket 110mm dia Each 71.69 192.69 Each 71.69 192.69
24-30-c-01 Providing and installing HDPE Tee 20mm dia Each 114.70 135.27 Each 114.70 135.27
24-30-c-02 Providing and installing HDPE Tee 25mm dia Each 114.70 144.95 Each 114.70 144.95
24-30-c-03 Providing and installing HDPE Tee 32mm dia Each 114.70 158.26 Each 114.70 158.26
24-30-c-04 Providing and installing HDPE Tee 40mm dia Each 143.38 215.98 Each 143.38 215.98
24-30-c-05 Providing and installing HDPE Tee 50mm dia Each 143.38 297.05 Each 143.38 297.05
24-30-c-06 Providing and installing HDPE Tee 75mm dia Each 172.05 2,646.50 Each 172.05 2,646.50
24-30-c-07 Providing and installing HDPE Tee 110mm dia Each 229.40 3,107.39 Each 229.40 3,107.39
24-30-d-01 Providing and installing HDPE bend 20mm dia Each 77.65 95.81 Each 77.65 95.81
24-30-d-02 Providing and installing HDPE bend 25mm dia Each 77.65 101.86 Each 77.65 101.86
24-30-d-03 Providing and installing HDPE bend 32mm dia Each 77.65 113.96 Each 77.65 113.96
24-30-d-04 Providing and installing HDPE bend 40mm dia Each 98.19 153.85 Each 98.19 153.85
24-30-d-05 Providing and installing HDPE bend 50mm dia Each 98.19 170.79 Each 98.19 170.79
24-30-d-06 Providing and installing HDPE bend 75mm dia Each 107.53 422.13 Each 107.53 422.13
24-30-d-07 Providing and installing HDPE bend 110mm dia Each 143.38 415.63 Each 143.38 415.63
24-30-e-01 Providing and installing HDPE adaptor 20mm Each 40.15 109.11 Each 40.15 109.11
24-30-e-02 Providing and installing HDPE adaptor 25mm Each 40.15 188.98 Each 40.15 188.98
24-30-e-03 Providing and installing HDPE adaptor 32mm Each 40.15 167.20 Each 40.15 167.20
24-30-e-04 Providing and installing HDPE adaptor 40mm Each 48.05 314.25 Each 48.05 314.25
24-30-e-05 Providing and installing HDPE adaptor 50mm Each 48.05 392.90 Each 48.05 392.90
24-30-e-06 Providing and installing HDPE adaptor 75mm Each 50.18 957.68 Each 50.18 957.68
24-30-e-07 Providing and installing HDPE adaptor 110mm Each 71.69 1,959.29 Each 71.69 1,959.29
24-31-a S/H/J G.I. Flanged Pipe 18" i/d 6.35mm thick Rft 629.45 3,101.09 m 2,065.13 10,174.19
24-31-b S/H/J G.I. Flanged Pipe 16" i/d 6.35mm thick Rft 240.06 3,732.12 m 787.60 12,244.49
24-31-c S/H/J G.I. Flanged Pipe 12" i/d 6.35mm thick Rft 314.73 2,934.38 m 1,032.56 9,627.22
24-31-d S/H/J G.I. Flanged Pipe 10" i/d 6.35mm thick Rft 262.27 2,264.82 m 860.47 7,430.52
24-31-e S/H/J G.I. Flanged Pipe 8" i/d 5mm thick Rft 209.82 1,884.46 m 688.38 6,182.60

NWFP CSR 2008 - Approved 25-Aug-2008 Page 138 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-31-f S/H/J G.I. Flanged Pipe 6" i/d 5mm thick Rft 157.36 980.16 m 516.28 3,215.76
24-31-g S/H/J G.I. Flanged Pipe 4" i/d 5mm thick Rft 104.91 556.24 m 344.19 1,824.93
24-32-a S/H/J MS Flanged Pipe 18" i/d 6.35mm thick Rft 524.54 3,472.10 m 1,720.94 11,391.41
24-32-b S/H/J MS Flanged Pipe 16" i/d 6.35mm thick Rft 349.70 2,969.35 m 1,147.29 9,741.95
24-32-c S/H/J MS Flanged Pipe 12" i/d 6.35mm Rft 262.27 2,227.31 m 860.47 7,307.45
24-32-d S/H/J MS Flanged Pipe 10" i/d 6.35mm thick Rft 209.82 1,734.42 m 688.38 5,690.34
24-32-e S/H/J MS Flanged Pipe 8" i/d 5mm thick Rft 174.85 1,404.21 m 573.65 4,606.98
24-32-f S/H/J MS Flanged Pipe 6" i/d 5mm thick Rft 139.88 902.18 m 458.92 2,959.90
24-32-g S/H/J MS Flanged Pipe 4" i/d 5mm thick Rft 87.42 516.97 m 286.82 1,696.11
24-33 Supplying and Fixing MS manhole cover of 0.25" thick Sft 41.20 417.95 m2 443.30 4,497.10
sheet & angle iron frame 2"x2"x0.25" with lock complete
24-34 Supplying and Fixing flat iron (2"x3/8") ladder for OHR, Rft 23.82 459.64 m 78.14 1,508.00
holes @ 15" c/c, steps of MS bars 5/8" i/d & paint compl
24-35 Supplying and Fixing C.I. vent pipe for storage tanks Rft 1.75 46.02 m 5.74 150.97
including jally etc
24-36-a Supplying and Fixing MS cap of 3/16" thick sheet : 10" i/d Each 11.78 858.78 Each 11.78 858.78
24-36-b Supplying and Fixing MS Cap of 3/16" thick sheet : 8" i/d Each 11.78 798.28 Each 11.78 798.28
24-36-c Supplying and Fixing MS Cap of 3/16" thick sheet : 6" i/d Each 11.78 737.78 Each 11.78 737.78
24-38-a Supplying and Fixing Flanged Expansion Joints BSS Each 16,058.00 76,558.00 Each 16,058.00 76,558.00
2035: 18" i/d
24-38-b Supplying and Fixing Flanged Expansion Joint BS-2035 : Each 11,470.00 59,870.00 Each 11,470.00 59,870.00
16" i/d
24-38-c Supplying and Fixing Flanged Expansion Joint BS-2035 : Each 5,059.20 29,259.20 Each 5,059.20 29,259.20
12" i/d
24-38-d Supplying and Fixing Flanged Expansion Joint BSS-2035 Each 3,670.40 18,190.40 Each 3,670.40 18,190.40
: 10" i/d
24-38-e Supplying and Fixing Flanged Expansion Joint BSS 2035 Each 2,982.20 13,388.20 Each 2,982.20 13,388.20
: 8" i/d
24-38-f Supplying and Fixing Flanged Expansion Joints BSS 2035 Each 1,605.80 8,865.80 Each 1,605.80 8,865.80
: 6" i/d
24-38-g Supplying and Fixing Flanged Expansion Joint BSS-2035 Each 1,376.40 6,821.40 Each 1,376.40 6,821.40
: 4" i/d
24-39-a Supplying and Fixing MS Suspension Clamp 3/8" thick Each 1,376.40 2,828.40 Each 1,376.40 2,828.40
for housing pipe : 18" i/d
24-39-b Supplying and Fixing MS Suspension Clamp 3/8" thick Each 917.60 1,825.10 Each 917.60 1,825.10
for housing pipe : 16" i/d
24-39-c Supplying and Fixing MS Suspension Clamp 3/8" thick Each 573.50 1,057.50 Each 573.50 1,057.50
for housing pipe : 12" i/d
24-39-d Supplying and Fixing MS Suspension Clamp 3/8" thick Each 344.10 707.10 Each 344.10 707.10
for housing pipe : 10" i/d

NWFP CSR 2008 - Approved 25-Aug-2008 Page 139 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 24 TUBEWELL AND WATER SUPPLY


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
24-39-e Supplying and Fixing MS Suspension Clamp 3/8" thick Each 229.40 471.40 Each 229.40 471.40
for housing pipe : 8" i/d
24-39-f Supplying and Fixing MS Suspension Clamp 3/8" thick Each 172.05 353.55 Each 172.05 353.55
for housing pipe : 6" i/d
24-39-g Supplying and Fixing MS Suspension Clamp 3/8" thick Each 114.70 296.20 Each 114.70 296.20
for housing pipe : 4" i/d
24-40 Supplying and Fixing PVC Water Stopper 8" wide 3/8" Rft 6.99 191.45 m 22.95 628.10
thick
24-41 Conducting Elec: Resistivity survey of the area and No 697.50 30,342.50 no 697.50 30,342.50
furnishing its reports.
24-42 Logging of bore hole with electrical equipment and Job 837.00 12,937.00 job 837.00 12,937.00
furnishing reports.
24-43 Providing and lowering pezu meter 1.25" GI pipe including Rft 38.15 118.01 m 125.18 387.19
all accessories.
24-44 P&L Reflux valves (C.I) of BSS quality/weight including Rft 321.34 1,538.72 m 1,054.27 5,048.29
jointing material 3" i/d-6" i/d.
24-45-a Laying cut, joint, test & disinfect of 8"i/d of GI pipe line No 125.15 996.35 joint 125.15 996.35
including cost of welding, excavation and filling
compaction etc complete.
24-45-b Laying cut, joint, test & disinfect of 6"i/d of GI pipe line joint 125.15 803.96 joint 125.15 803.96
including cost of welding, excavation and filling
compaction etc complete.
24-45-c Laying cut, joint, test & disinfect of 4"i/d of GI pipe line joint 125.15 611.57 joint 125.15 611.57
including cost of welding, excavation and filling
compaction etc complete.
24-45-d Laying cut, joint, test & disinfect of 3"i/d of GI pipe line Joint 125.15 420.39 joint 125.15 420.39
including cost of welding, excavation and filling
compaction etc complete.
24-46 Testing of soil for bearing capacity & chemical contents Rft 340.24 5,504.88 m 1,116.29 18,060.62
upto any depth.

NWFP CSR 2008 - Approved 25-Aug-2008 Page 140 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 25 IRON WORK


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
25-01 Laying, linking and packing tramway line Rft 8.58 8.58 m 28.15 28.15
25-02 Dismantling tramway track Rft 2.84 2.84 m 9.32 9.32
25-03 Laying, linking of BG track, including packing, Rft 22.95 22.95 m 75.29 75.29
straightening and levelling
25-04 Linking points and crossings, complete with fastenings Each 2,247.50 2,247.50 Each 2,247.50 2,247.50
25-05 Bending or straightening BG rail with jim crow Each 286.75 286.75 Each 286.75 286.75
25-06 Fixing street lamp posts Each 837.00 837.00 Each 837.00 837.00
25-07 Binding ends of sleepers and timbers of all sizes & kinds, Each 32.40 32.40 Each 32.40 32.40
including spreading & restacking
25-08 Opening stacks of sleepers & timber of all kinds and sizes, Each 3.46 3.46 Each 3.46 3.46
including spreading for inspection
25-09 Small iron work, such as gusset plates, knees, bends, tonne 27,032.00 106,892.00 tonne 27,032.00 106,892.00
stirrups, straps, rings etc excluding erection
25-10 Fabrication of heavy steel work with angle, tees, sheet iron tonne 17,980.00 97,840.00 tonne 17,980.00 97,840.00
etc for making trusses, girders etc
25-11 Erection and fitting in position iron trusses, staging of tonne 4,920.48 4,920.48 tonne 4,920.48 4,920.48
water tanks, etc
25-12 Fixing corrugated iron sheet including rivetting, etc Sft 6.92 6.92 m2 74.41 74.41
25-13 Erecting corrugated iron sheet tanks, upto 20' height tonne 6,125.60 6,125.60 tonne 6,125.60 6,125.60
25-14 Erecting rolled steel beams or old rails, in roof etc, erection tonne 347.20 347.20 tonne 347.20 347.20
& fixing in position
25-15 Erecting rolled steel beams or rails, erection for posts etc tonne 174.22 174.22 tonne 174.22 174.22
(other than in roofs)
25-16 Making bolts & nuts of iron rods kg 61.85 120.94 kg 61.85 120.94
25-17-a Cutting rails,rolled steel joist & beams, with hacksaw : Each cut 129.16 129.16 Each cut 129.16 129.16
Upto 6" size
25-17-b Cutting rails,rolled steel joist & beams, with hacksaw : Each cut 193.75 193.75 Each cut 193.75 193.75
Above 6" size
25-18 Cutting rails or rolled steel beams of size below 6" with jim Each cut 64.58 64.58 Each cut 64.58 64.58
25-19 Bending rolled steel beams or rails Per Bend 110.72 240.36 Per Bend 110.72 240.36
25-20 Drilling holes,in plates upto 1/2" thick per inch dia. or part Each hole 26.86 26.86 Each hole 26.86 26.86
thereof
25-21 Extra for drilling holes in plates over 1/2" thick per inch Each hole 12.40 12.40 Each hole 12.40 12.40
dia, or part thereof
25-22 Rivetting 1/8" dia Each 3.88 3.88 Each 3.88 3.88
25-23 Cutting out Rivets, all sizes. Each 11.19 11.19 Each 11.19 11.19
25-24 Fitting and erection of gutters of sheet iron Rft 19.38 19.38 m 63.59 63.59
25-25 Cutting and fixing iron bars, for barred windows Each 27.38 27.38 Each 27.38 27.38
25-26 Cutting GI sheets of 2'-8" wide. Each 13.43 13.43 Each 13.43 13.43
25-27 Notching web or foot of rail posts for housing rail beams Each cut 299.66 304.71 Each cut 299.66 304.71
25-28 Hoop iron netted trellis work fixed with nails Sft 24.98 26.41 m2 268.80 284.15
NWFP CSR 2008 - Approved 25-Aug-2008 Page 141 of 144
COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 25 IRON WORK


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
25-29 Fixing zinc, iron or GI sheet on table tops Sft 11.58 12.11 m2 124.58 130.30
25-30 Making and fixing steel grated doors, complete with Sft 218.96 412.11 m2 2,356.00 4,434.30
locking arrangements & angle iron frame
25-31 Making and fixing steel grated door, with 1/16" thick Sft 215.07 549.98 m2 2,314.15 5,917.73
sheeting, including angle iron frame & lock
25-32 Making and fixing grating in opening, including fixing at Sft 58.91 126.31 m2 633.82 1,359.07
site with flat iron 2"x3/8" and 3/4" sq. bars
25-33 Providing and Fixing terrace railing of 2" i/d conduit pipe Sft 39.65 221.14 m2 426.68 2,379.47
16 SWG welded with 5/8"x5/8" sq bar 2.75' high complete
25-34 Providing and Fixing collapsible gate made of 2"x2"x1/4" Sft 135.09 476.62 m2 1,453.56 5,128.39
tee iron at top & bottom, lock etc complete
25-35 Providing and Fixing 24 SWG GI sheet rolling shutter of Sft 16.90 171.49 m2 181.86 1,845.23
steel frame of MS channel 2"x1.25"x1/8" complete
25-36 Providing and Fixing MS angle iron 1«"x1«"x1/4" edge Rft 18.84 150.65 m 61.80 494.25
protector nozing of steps of stairs, complete
25-37 Providing and Fixing stair railing of 2.5" i/d GI pipe, Rft 67.29 302.55 m 220.77 992.63
welded with 5/8"x5/8" MS bars 2'-9" high, fixed in each
step
25-38 Providing and Fixing GI wire gauze 24 SWG, 12x12 Sft 46.95 110.60 m2 505.20 1,190.05
meshes per sq.in., fixed to steel windows or doors etc
25-39-a-01 Providing and Fixing steel windows with openable glazed Sft 14.58 354.80 m2 156.83 3,817.68
panels Without wire guaze : Glass pane 2mm thick
25-39-a-02 Providing and Fixing steel windows with openable glazed Sft 14.58 353.59 m2 156.83 3,804.66
panels Without wire gauze : Glass pane 2.5mm thick
25-39-a-03 Providing and Fixing steel windows with openable glazed Sft 14.58 362.06 m2 156.83 3,895.80
panels Without wire gauze : Glass pane 3mm thick
25-39-a-04 Providing and Fixing steel windows with openable glazed Sft 14.58 364.48 m2 156.83 3,921.84
panels Without wire gauze : Glass pane 4mm thick
25-39-a-05 Providing and Fixing steel windows with openable glazed Sft 14.58 372.35 m2 156.83 4,006.46
panels Without wire gauze : Glass pane 5mm thick
25-39-b-01 Providing and Fixing steel windows with openable glazed Sft 16.05 413.22 m2 172.68 4,446.23
panels With 22 SWG wire gauze : Glass pane 2mm
25-39-b-02 Providing and Fixing steel windows with openable glazed Sft 16.05 412.01 m2 172.68 4,433.21
panels With 22 SWG wire gauze : Glass pane 2.5mm
25-39-b-03 Providing and Fixing steel windows with openable glazed Sft 16.05 420.48 m2 172.68 4,524.35
panels With 22 SWG wire gauze : Glass pane 3mm
25-39-b-04 Providing and Fixing steel windows with openable glazed Sft 16.05 422.90 m2 172.68 4,550.39
panels With 22 SWG wire gauze : Glass pane 4mm
25-39-b-05 Providing and Fixing steel windows with openable glazed Sft 16.05 430.76 m2 172.68 4,635.02
panels With 22 SWG wire gauze : Glass pane 5mm
25-40 Supply and Fixing iron grating for fire place Sft 263.60 505.70 m2 2,836.31 5,441.35

NWFP CSR 2008 - Approved 25-Aug-2008 Page 142 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 25 IRON WORK


:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
25-41 Providing and Fixing angle iron railing, using Rft 153.51 777.40 m 503.65 2,550.52
2.5"x2.5"x3/8" angle iron post 4.5'long, 5'to 6" apart,
complete
25-42 Providing and Fixing barbed wire fencing of Rft 29.63 97.30 m 97.21 319.23
1.5"x1.5"x3/16" angle iron post 3.25' long, 5 to 6 ft. centre
to centre
25-43 Providing and Fixing barbed wire fencing on compound Rft 31.80 110.06 m 104.34 361.10
wall of 1.5"x1.5"x3/16" angle iron post 3' long, 4' apart
25-46 Supplying and Fixing 18SWG Steel Almirah, 12" max Sft 57.64 340.89 m2 620.20 3,668.00
depth including box shelves, back, shelves, lock, spray
paint complete
25-47-a Supplying and Fixing 18 SWG MS Sheet Door with angle Sft 64.49 244.24 m2 693.90 2,628.03
iron frame (1.5"x1.5"x1/8"), bolt, hinges, paint etc
complete
25-47-b Supplying and Fixing 18 SWG MS Sheet Gate with angle Sft 99.89 375.15 m2 1,074.77 4,036.66
iron frame (2"x2"x3/16") with side window, lock, painting
etc

NWFP CSR 2008 - Approved 25-Aug-2008 Page 143 of 144


COMPOSITE SCHEDULE OF RATES 2008 NWFP
As on Jan-Mar (QTR-1) 2009

Chapter # 26 MISCELLANEOUS
:
Rate (British System) Rate (Metric System)
Item Code Description Spec. Remarks
Unit Labour Composite Unit Labour Composite No
26-01 Supplying bamboo jhandies 10' to 12' with iron shoes and Each 43.40 316.26 Each 43.40 316.26
flags 15" square
26-02 Supplying wooden pegs for levelling 1.5" square 6" long 100 No. 182.13 654.03 100 No. 182.13 654.03
26-03 Supplying wooden pegs for alignment, 2" to 3" square, 9" 100 No. 658.75 1,590.45 100 No. 658.75 1,590.45
long
26-04 Fixing enamelled iron gauges flush with masonry including Each 868.00 1,013.20 Each 868.00 1,013.20
cost of hooks
26-05 Supply & fix boundry pillars in position, including digging Each 139.50 425.61 Each 139.50 425.61
pits
26-06 Fixing main line type distance mark in position including Each 83.70 315.91 Each 83.70 315.91 Composite rate does
making 1:3:6 cement concrete base block not include cost of
iron distance marks.
26-07-a Boring and fixing 1.5" dia pressure pipe in ordinary soil Rft 44.89 44.89 m 147.29 147.29
26-07-b Boring and fixing 1.5 dia pressure pipe in clay Rft 83.17 83.17 m 272.87 272.87
26-07-c Boring and fixing 1.5" dia pressure pipe in shingle Rft 121.45 121.45 m 398.45 398.45
26-08 Repairs to hand pump, pulling out & refitting Rft 32.80 32.80 m 107.60 107.60
26-09 Fixing hand pump (machine only) Each 198.40 198.40 Each 198.40 198.40
26-10-a Washing of Durries / Synthetic Matting 100 Sft 1,080.56 1,080.56 m2 116.27 116.27 Capacity of cart, 20
cubic feet
26-10-b Washing of Bed Sheets Each 23.34 23.34 Each 23.34 23.34
26-10-c Washing of Table Cloth / Napkins / Dusters etc Each 11.66 11.66 Each 11.66 11.66
26-11-a Recaning of chairs/stools : With plastic cane. kg 69.75 287.55 kg 69.75 287.55
26-11-b Recaning of chairs/stools : With willow cane. kg 97.65 1,307.65 kg 97.65 1,307.65
26-12 Sweeping chimneys Each 69.75 109.44 Each 69.75 109.44
26-13 Cleaning of water tanks upto 400 gallons capacity Each 70.31 70.31 Each 70.31 70.31 For capacity other
than 400 gallons, the
rate shall be work out
on proper rate basis.
26-14 Supplying manure Cart load 111.60 325.25 Cart load 111.60 325.25 Capacity of cart, 20
cubic feet
26-15 Spraying anti-termite liquid mixed with water in the ratio 100 7.75 122.26 m2 0.83 13.16
of 1:40 Sft/spray
26-16-a Providing and Fixing barbed wire fencing with 4 horizontal Rft 4.41 137.53 m 14.47 451.22
& 2 cross wires : Without PCC base
26-16-b Providing and Fixing barbed wire fencing with 4 horizontal Rft 4.41 139.38 m 14.47 457.28
& 2 cross wires : With PCC 1:4:8 base 12"x12"x21"
26-17 Making notice board 1/2" thick of c/s mortar 1:3 with 100 Sft 5,016.90 5,582.40 m2 539.82 600.67
2"x1/2" beading
26-18 Binding office books/registers. Each 13.95 31.50 Each 13.95 31.50

NWFP CSR 2008 - Approved 25-Aug-2008 Page 144 of 144