CONSTRUCTION OF 110 KV D/C OHTL FOR AL‐KAMEL S/S MAKKAH, SAUDI ARABIA

FOUNDATION SETTING PLAN          
TOWER TYPE "AS‐120" (PAD & CHIMNEY) FD = 4.5M
(REF. WA ‐ 400860 R.0 SHT. 02 OF 02)
Hv 1343 843 + 500 (Ref. WA‐400860 SHT. 1 R.0) yb 73 Neutral axis

Hf 4000 Chimney height + structure pad (=3700 + 300) Hs 2050 Stub height Bottom of GL      (Ref. 


WA‐400860 SHT. 1 R.0))
Hv + Hf 5343 Hv + Hs 3393

A C Tan (theta) Theta P L R H
NO. EXTENSION Actual b/b  Projected b/b 
(See Ref.)     (See Ref.)   Radian Degrees c/c  dist. c/c diag. dist.
stub dist. stub dist.
1 BB+L2       9,281.00         9,706.00  0.1582 8.991       10,354.73         10,971.82          10,827.62          15,312.56 

2 BB+L4       9,914.00      10,339.00  0.1582 8.991       10,987.73         11,604.82          11,460.62          16,207.76 


3 BB+L6    10,547.00      10,971.00  0.1579 8.970       11,618.21         12,233.84          12,089.63          17,097.32 
4 BB+L8    11,179.00      11,604.00  0.1582 8.991       12,252.73         12,869.82          12,725.62          17,996.74 
5 BB+L10    11,812.00      12,236.00  0.1579 8.970       12,883.21         13,498.84          13,354.63          18,886.30 
6 BB+6BE+L2    11,179.00      11,604.00  0.1582 8.991       12,252.73         12,869.82          12,725.62          17,996.74 
7 BB+6BE+L4    11,812.00      12,236.00  0.1579 8.970       12,883.21         13,498.84          13,354.63          18,886.30 
8 BB+6BE+L6    12,444.00      12,869.00  0.1582 8.991       13,517.73         14,134.82          13,990.62          19,785.72 
9 BB+6BE+L8    13,077.00      13,501.00  0.1579 8.970       14,148.21         14,763.84          14,619.63          20,675.28 
10 BB+6BE+L10    13,709.00      14,134.00  0.1582 8.991       14,782.73         15,399.82          15,255.62          21,574.70 
11 BB+12BE+L2    13,077.00      13,501.00  0.1579 8.970       14,148.21         14,763.84          14,619.63          20,675.28 
12 BB+12BE+L4    13,709.00      14,134.00  0.1582 8.991       14,782.73         15,399.82          15,255.62          21,574.70 
13 BB+12BE+L6    14,342.00      14,767.00  0.1582 8.991       15,415.73         16,032.82          15,888.62          22,469.90 
14 BB+12BE+L8    14,974.00      15,399.00  0.1582 8.991       16,047.73         16,664.82          16,520.62          23,363.68 
15 BB+12BE+L10    15,607.00      16,032.00  0.1582 8.991       16,680.73         17,297.82          17,153.62          24,258.88 

NOTES:
THETA = ATAN ((C ‐ A) / (2 * Hv)
P = A +2 * ( Hv + Hs ) * TAN (teta)
L = A +2 * ( Hv + Hf ) * TAN (teta)
R = L ‐ 2 * yb * COS (teta)
Hv = STUB VERTICAL HEIGHT
Hf = CHIMNEY VERTICAL HEIGHT TO G.L
Yb = STUB NEUTRAL AXIS