You are on page 1of 20

Direction des Performances Cimentières

Process Group Leaders Network

Process Guidelines V3 October 2005


Click to access the page

- Read me - ReadMe
Raw milling Raw milling
Preheater Preheater
Kiln Kiln
Cooler Cooler
Kiln and Cooler Filter Kiln and Cooler Filter
Kiln by-pass system Kiln By-pass system
Gas analyser Gas analyser
Coal mill Coal mill
Cement grinding Cement Gr
Weighing-dosing Weighing-dosing

05 10 05

Process guidelines - Contents -


Back to table of contents

Process Guidelines V3 - October 2005

Best practice / To be written


recommendation

Specifications These are the figures we give to suppliers in the tender ; this column should contain the same
figures as other documents.
Alternatives In this column we describe alternatives, which could be accepted for cost reason, but also are
necessary for process reasons. Example would be cement mill specification is vertical mill,
Alternative is ball mill and in case of a existing ball mill a roller press

Operating target Operating target is the range where we want to have an equipment operated; this is not to be
given to suppliers, but we will check offers accordingly. Important value for process evaluation of
existing equipment or to calculate operation cost.

Not advisable These are choices we don’t accept. Important if suppliers send alternatives on their own

Comments
Best Practice /
Raw milling Recommendation
Specifications Alternatives Operating target Not advisable Comments

Back to table of contents


Vertical Mill with cyclone and Vertical Mill with cyclone and 2 compartments closed circuit Tube mills without drying
fan with VFD fan with VFD tube mills with drying chamber, or without external
chambers (if moisture < 7-8%) drying.
or Autogenous Mills (only in case
Tube mills in combination with of specific applications).
heated hammer crushers. Roll Press in circuit with V or
CHOICE OF MILL SYSTEM High efficiency separator VSK separator and/or dynamic
or separator.
Roller Press with Ball Mill Pregrinding circuit with two-
compartments ball mill.
Air Swept mill
Central discharge mill
Closed circuit mill Closed circuit mill Roll Press in circuit with V or
High efficiency separator High efficiency separator VSK separator and/or dynamic
separator.
Pregrinding with two-
Modification of existing compartments ball mill circuit.
grinding shop Modification of 1st generation
separator
Addition of external drying
drum

New Equipment Ball Mill with drying chamber

Mill Circuit Closed circuit Partial feed to the separator Open circuit

Ball mill speed 75% critical speed 75 % critical speed <73% or >78% critical speed

Air velocity above ball


charge=1,5 to 2,2 m/s
inside the trunion: 22-25 m/s Air velocity above ball
inside partition:8-14 m/s charge=1,5 to 2,2 m/s
Ventilation ball mill
0,6 - 0,8 Nm3/kg raw mix
hood < 5m/s VFD fan
drop out box < 2m/s
VFD fan

1,5 < L/D < 3,2


Mill L/D ratio First compartment length = 35 -
45% of mill total length

Process guidelines - Raw Milling - Page 1 / 3 06/10/2005 - 10:58


Best Practice /
Raw milling Recommendation
Specifications Alternatives Operating target Not advisable Comments

Back to table of contents


Moderate lifting liners for first Classifying liners in second Duo lift Without classifying liners keep
compartment, classifying liners compartment Ripple liners a maximum of 3 - 4 ball sizes
for second compartment
Ball mill Liners

Central opening adapted to Diaphragms with material flow Slots placed radially.
the filling degree. Slots placed control
concentricly. - 8 to 12 mm slot
for central partition.
Intermediate Partition wall
- open area > 50 % by central
opening

Central opening adapted to Slots placed radially.


the filling degree. Slots placed
Outlet partition wall concentricly. Partition wall slot
size + 2mm (max slot = 0,5
min ball size)
Volume Loading:
- for minimum kWh/t: 26-28%
in C1 and 28-30% in C2
Ball charge - for max output: 32-34% in
C1 and 34-36% in C2

Separator Third Generation High Dust load < 1kg/m3 1st or 2nd generation
Efficiency Qf/Qa < 2.5 separators
Fresh feed control to assure Weighing rejects (belt Control mill fresh feed using Fresh feed control can be done
constant feed to the separator. weigher), measuring elevator only one parameter (only by different ways, using
Mill controled by LUCIE. power, mill presure loss, mill rejects flowrate or only different instruments or signals
Control outlet temperature and elevator power , for example) (rejects flowrate, elevator
electronic ear. power, eletr. Ear, mill kW). It is
recommended to use them in
conjunction.
Feed size 95%< 50 mm Precrushing, screening, The finer, the better
Feed d80 feed < 20mm, external drying

Drying compartment Moisture inlet C1 < 1.5%


Specific drying capacity
<300kg/m3

Process guidelines - Raw Milling - Page 2 / 3 06/10/2005 - 10:58


Best Practice /
Raw milling Recommendation
Specifications Alternatives Operating target Not advisable Comments

Back to table of contents


Equipment VRM
Vertical Roller Mill Recirculation of gas to the mill. Metal detector and extractor in Water injection facilities in the Gas speeds: Feed device with triple flap
Metal detector and extractor in the feeding line (after reject's mill housing Nozzle ring >30 m/s gate or rotary air lock valve,
the feeding line (after reject's return) Mill Body: 5 - 7 m/s heated if wet or sticky raw
return) Bed depth sensor Separator: 3 - 5 m/s materials.
Gas flow measurement after Water injection max 25 kg/t Dust Load: 600 g/m3 at mill Fan max speed typical 700 rpm
cyclone or filter Material External Recirculation outlet and >80% efficiency
Water injection system System >30% Fresh Feed
Central mill feed. Capacity
HE Separator Fan with VFD
Material External Recirculation
System >30% Fresh Feed
Capacity Fan
with VFD
Bed depth sensor

Control Constant mill exit T°


Constant mill gas flow
Mill feed a to mill deltaP

Process guidelines - Raw Milling - Page 3 / 3 06/10/2005 - 10:58


Best practice /
Preheater Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment

5 Stage Preheater - low


moisture < 5% raw materials
Low pressure drop No horizonatal inlet ; no 4 Stage Preheater - high For a 5 stage PH, 4.5 to 5.5
Cyclones See priority study Preheater
horizontal surface moisture >5% raw materials kPa (including kiln)
Bottom of cyclone
> 50° height

Top (stage 1): 100%


Dip Tube Length relative to Hurrivanes - depending on
Stage 2/3: 75%min Top (stage 1): 100% Number in % of inlet height
cyclone inlet height geometry
Stage 4/5 : 50%min

Lafarge design
cleaning devices. At least 55°
to 80° between meal pipe and
Splash box splash box >60o below C3 Splash plates See priority study Preheater
2 m from flap, pipe without
elbow
60° for kiln feed to splash box.
Pendulum flap External knife bearing

Vessel + Hot core preferred


Very specific to fuel and plant
Precalciner Residence time > 6 sec Residence time > 6 sec Riser Duct plus hot core
conditions
for petcoke, Low-Nox

Downward split design


for in-line calciner
Tertiary air duct
Damper control
Duct velocity 20 to 30 m/s

Process
Mini 12 m/s top stage
with 17 m/s bottom
(intermediate proportional)
Gas duct velocity at meal
Can install restriction
entrance
as alternative

Riser velocity 16 m/s minimum

Process guidelines - Preheater - Page 1 / 2 06/10/2005 - 10:58


Best practice /
Preheater Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents

Cyclones Top cyclone efficiency > 95% Top cyclone efficiency > 95%

Considered if high volatile


cycles expected Lateral
Meal curtain
Most common on N-1 stage Consider a splitter
on kiln side

No dead zone
Smooth design (entrance in the
Kiln inlet box middle)
No turbulances
45°- 50° slope of inlet

Cooling by water sprays Water design target able to


Minimum evaporation: 4 sec provide 185 °C. Take care
Downcomer (for target at 185°C) about moisture in gas to coal
No bleed air is recommended, mill take off above water
except for start up injection

Fan Typical Max speed 990


VFD drive
rpm and efficiency >80%.
ID fan preheater Fresh air intake before
Design margin 5% volume and
the fan (fan protection)
1 kPa pressure
3
number of fans ID fan, raw mill fan & Only 2 fans
baghouse fan
Secondary Fuel
Burner preferred for Calciner
usage

Process guidelines - Preheater - Page 2 / 2 06/10/2005 - 10:58


Best Practice /
Kiln Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment
Position in center line of kiln
and aligned on kiln axis (only
MAS burner in case of regular See Lafarge Burner Design
Burner type and position Lafarge Burner if kiln is stable and burner
solid fuel and alternative fuel ; Spreadsheet
having sufficient impulse)

Solid Fuel: 25 - 35 m/s in Solid Fuel: 25 - 35 m/s in Alternative Fuel: 25 - 40 m/s


Fuel speed burner ; >25m/s in conveying burner ; >25m/s in conveying in burner ; >25m/s in
line line conveying line

< 15% primary air (as low as


Total primary air <12% with coal / petcoke possible when firing
alternative fuels)
Liquid (main fuel) > 25 cSt
Swirl Design: 0,15
Final design criteria to be
Impulse Design: >2,2
worked out.
0,6 to 1 m from nosering as Double flat bar
Retaining rings
single ring, triangulkar shape Maggoteaux system

Kiln slope 3 - 3,5 % 4%

>10,5 for preca (> 15 is


required when designing for
L/D
alternaitve fuels)
> 15 for preheater

From kiln hood From kiln hood


Take off velocity 5-6 m/s Take off velocity 5-6 m/s
Tertiary air Settling chamber Heat shield IKN not proven
throat and tertiary air and 25 throat and tertiary air and 25
m/s in the duct m/s in the duct
Fan should be below kiln so
Shell cooling fans 12 to 18 m/s at shell Supplied that air flow comes up on
both sides.

Process guidelines - Kiln - Page 1 / 2 06/10/2005 - 10:58


Best Practice /
Kiln Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Process

Limit for refractory.


< 5 MW/m² (kiln cross
Thermal load < 5 MW/m² < 6.5 MW/m² Some wet and big kilns can
section)
overpass the limit

Kiln hood velocity < 6 m/s

Kiln load <4,5 t/d/m³

Production 24 m/s hearth velocity pc kiln <28 m/s

With > 0,025% of Cl input


Clinker bypass (related to clinker) consider a
bypass

For off specification clinker, 8


Clinker storage hour separate storage
considered

Process guidelines - Kiln - Page 2 / 2 06/10/2005 - 10:58


Best practice /
Cooler Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment
Equipment Selection Cross Bar or Walking Floor Cross Bar or Walking Floor
Design Design
Grate load < 45 t/m² d < 45 t/m² d

Variable speed fans All on 1st grate Variable speed on all on 1st Fan dampers (inlet radial) Flap max speed typical 1500 rpm,
grate fans. 2nd grate fans can Efficiency > 80%. Normally 20-
be with variable inlet vanes 30% pressure reserve.
dampers
Fix inlet rows 5 to 8 (1.5 - 2.5 m)
Max 15 degree angle
Refractory Horseshoe
Air Cannons
Crusher Roller crusher intermediate Hammer Hammer crusher can be the
or at the end Crusher first choice if no need for very
effective cooling
Grate slope 0° 3° maximum
Evacuation hoppers Simple gate and sensor level Double gate mechanically
activated

Process
Air flow design Not < 2,1 Nm3/kg > 2.1 Nm³/kg ck
> 1.7 Nm³/m²/s on first fans, 2
Nm³/m²/s for KIDS

First fans pressure > 10 kPa (100 mbar) for KIDS

Optimal bed depth Lowest stroke permitted with


20% reserve on fans
(6-8 st/min for properly
designed cooler)

Air velocity above clinker 5 to 7 m/s


Clinker transport design Min. 1,5 x nominal capacity Min. 1,5 x nominal capacity
steel conveyor steel conveyor

Process guidelines - Cooler - Page 1 / 1 06/10/2005 - 10:59


Best practice /
Kiln filter Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment
BH sizing must maintain
Max dP< allowed by fan
High Pressure Pulse Jet (HPPJ) Off line cleaning is not operating pressure drop within
Low Pressure Pulse Jet Bag Low Pressure Pulse Jet (LPPJ) capacity at end of bag life.
Equipment Selection Bag Filter (6bar/100psi), acceptable due to the the limits of the ID fan and the
Filter ( 2,5 bars) Bag Filter ( 2,5 bars) Limit cleaning cycles to obtain
Electrostatic precipitator potential damage to the bags. pulse jet filter ability to clean
target bag life.
bag on line.

Gross Air to clothe ratio: Gross Air to clothe ratio:


Equipment Sizing 1m/min average 1m/min average
1.3 m/min max (upset cond) 1.3 m/min max (upset cond)

Fabric with PTFE membrane


Adequate temperature control Other bag materials that are
and fiberglass structure. Bag quality and workmanship
Design temperature 230°C P84 bags of suitable to prevent teflon and SGT not proven.
Bag quality Known suppliers: Gore, BHA, are critical. Bag to cage fit is
Peak temperature 260°C construction. evaporation and bag damage. If using P84 verify the risk of
Tetratec working critical.
working at 180°C- 230°C max hydrolysis.
at 180°C- 230°C max

Scale model to ensure good


Airflow Distribution airflow distribution and correct
fan sizing before purchase

Prevent moisture condensation


Air coolers can be acceptable Use air dryers (dessicant) for
Compressed Air Supply in the bag during the No oil in cleaning air.
for LPPJ. HPPJ (-30deg C due point).
compressed air pulse.

Fan Typical Max speed 990


Exhaust Fan VFD VFD rpm and efficiency >80%.
Design margin 15% volume

Direct < 30% Preheater Gases


False Air Compound < 50% Preheater
Gases

Process guidelines - Kiln and Cooler Filter - Page 1 / 2 06/10/2005 - 12:08


Best practice /
Kiln filter Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
COOLER FILTER
Exhaust system capacity to
Common baghouse for
handle normal operation and Gas flow in BH hopper must
Air to air heat exchanger to Air to air heat exchanger to RM/kiln and cooler
Equipment Selection to provide sufficient capacity not cause abrasion of filter
get 130°C at exit get 130°C at exit ESP when all cooler gas used
for push conditions for the full bags due ro high velocities.
for raw materials drying
length of the bag life.

Exhaust gas flow from the Gas velocity at heat


cooler straight entry and exchanger's inlet in normal Water injection in the exhaust
oriented downwards through conditions: <10 m/s pipe
heat exchanger

Cooling fan are VFD speed

Fan Typical Max speed 990


Exhaust Fan VFD VFD rpm and efficiency >80%.
Design Margin 15% volume

Design upset conditions 450 C Design upset conditions 450 C


System Sizing exhaust gas temp. Design exhaust gas temp. Design
flow 1.7 nm3/kg clinker flow 1.7 nm3/kg clinker

Process guidelines - Kiln and Cooler Filter - Page 2 / 2 06/10/2005 - 12:08


Best practice /
Kiln By-pass system Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment
Wet scrubber may be a
Dedusting Bag filters (240°C) ESP solution when cement Cl is a
limitation
As short as possible
Dust transport Air transport if Cl < 10%
Mechanical
Addition to cooler only if
As small as possible, Direct dust addition to cooler clinker storage does not
Storage intermediate storage
with mechanical extraction filter or heat exchanger promote segregation (quality -
dust separation in pile)

Process
On top of the smoke box, on
the kiln side
Location take-off
Distant from C3 discharge to
avoid dust mixing

Dilution with kiln feed if > Cl control using cyclone system


Level of chlorine in dust
10% Cl with bypass (Taiheyo)

Air quenching as close as


possible to the take out, either Air to air cooler as second
Quenching directly to 200°C or at least to cooling step to minimize the
400°C gas quantity

Raw mill or main stack if SO2 is


acceptable, dioxins still a
To cooler fans to avoid
Exhaust air threat. Detached plume also a Separate stack
SO2/Dioxins
potential issue if organics in
raw mix
Clinker (limiting factor for Cl)
Cement (limiting factor forCl Dust Washing with heavy
Dust management Dust wasting
as allowed by local standard) metal recovery, for low limit of
Cl in cement

Higher concentration
Target level of chlorine in kiln
1,00% acceptable if possible for build-
back-end mat
ups

Process guidelines - Kiln By-pass system - Page 1 / 1 06/10/2005 - 10:59


Best practice /
Gas analyser Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Kiln inlet
Kiln inlet
Probe long enough to enter
the kiln, retractable,
motorised
Oil cooled
Probe Dry probe required
In-situ
Water cooled jacket
Same probe for all gases
Back flush (clean, dry air)
Mandatory
CO Type: IR
Scale: 0-20000 ppm
Mandatory
Type IR
NOx
No NO2 converter needed
Scale: 0-20000 ppm
Mandatory
O2 Type: Paramagnetic
0-10%
Required if Total SO3 input >
1.2% on clinker basis or
S/A ratio > 1.2
SO2 IR (on separated line)
Type UV
Quartz cells
0-20000ppm

Heated line (>180°C)


2 cooler dryer 1 for SO2 and 1
Gas treatment
for other gases
For other gases H2O2 injection

Suspension preheater kiln - no PC

Exit of preheater tower Mandatory for O2 and CO

Exit of Precalciner
Precalciner
Probe at Bottom cyclone exit
retractable,
Dry probe required
Probe
Water cooled jacket
Same probe for all gases
Back flush (clean, dry air)

Process guidelines - Gas analyser - Page 1 / 2 06/10/2005 - 11:02


Best practice /
Gas analyser Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Mandatory
CO Type: IR
Scale: 0-20000 ppm
Mandatory
Type IR
NOx
No NO2 converter needed
Scale: 0-20000 ppm
Mandatory
O2 Type: Paramagnetic
0-10%
Heated line (>180°C)
2 cooler dryer 1 for SO2 and 1
Gas treatment for other gases
For other gases H2O2 injection
3 other in line O2 last

CEM (stack)
Location Follow local regulation
Dust Scattered light system
In-situ system (Zircon)
O2
0-10%
Optical in-situ system IR
H2O
0-10%
Optical in-situ system IR Extractive with heated probe
CO
0-2000 mg/Nm3 and line (>180°C) + FTIR
Optical in-situ system-UV Extractive with heated probe
NOx
0-2000 mg/Nm3 and line (>180°C) + FTIR
Optical in-situ system-UV Extractive with heated probe
SO2
0-500 mg/Nm3 and line (>180°C) + FTIR
Optical in-situ system-IR Extractive with heated probe
HCl
0-100mg/Nm3 and line (>180°C) + FTIR
Extractive FID
COV
0-200mg/Nm3
CO Protection with ESP
Use precalciner exit CO with
Precalciner Kiln
preheater exit CO as back up

Use kiln exit CO with


Suspension preheater kiln
preheater exit CO as back up

Process guidelines - Gas analyser - Page 2 / 2 06/10/2005 - 11:02


Best practice /
Coal Mill Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment
Ball mills are better suited for
very hard fuels and certain
Ball mill ,
Central discharge mills cokes. Also need to consider
Equipment Selection Vertical mill Vertical mill Ring roller mills
"deep bowl" mills turndown ratios if AF is
Pendulum mills
significant - need VFD or
something appropriate.
Process Gas
Hot gas from pre heater with Hot gas from pre heater with
Direct or semi direct firing
de dusting de dusting

CO analysers:
- Raw Coal Bin
Sensors - Mill Filter Exit
- Each Pulverised Fuel Bin

O2 analysers:
- Preheater Exit
- Before Mill
- Mill Filter Exit

Temperature sensors Differential temperature across


- Raw coal hopper/silo separator for ball mill
- Before mill
- After mill
- Hot gas duct
- Filter bottom
- Coal dust after filter
- PF silo bottom ( In banks of
four around cone)
- Differential temperature
across filter
Load Cells
- Raw Coal Bin
- Pulverised Coal Bins
Pressure indication
- Before mill
- After mill
- Mill differential pressure
- Filter differential pressure

Dust monitor
- Coal bag filter main stack

Process guidelines - Coal mill - Page 1 / 2 06/10/2005 - 11:00


Best practice /
Coal Mill Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents

2Kg/m3 of volume of the Bottle CO2 systems can be


system coal mill, filter, silos and considered if local conditions
Fire suppression system Bulk system C02 ducts and enough for 2 or regulations do not allow
complete discharges (X3 for bulk or if delivery time is
remote locations) excessive.

Study fuel - need to have


temperature limit at mill inlet
and mill outlet appropriate for
Safety for mill and feeding See Safety Equipment in Model See Safety Equipment in Model fuel. Favor high gas volume so
system Plant Plant it can be run cooler. High
volatile O2<12%. Moderate
volatile 21% O2 is OK if
temperature < 70C

Install a dynamic 3rd


generation separator
See Combustion manual for
Pet coke grinding According to Combustion BP Open circuit
fineness vs. volatile
the fineness should be less 0.1
% rejects on 200µ

Process guidelines - Coal mill - Page 2 / 2 06/10/2005 - 11:00


Best practice /
Cement Grinding Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents
Equipment

Roller Press
Pregrinding circuit with two-
compartment ball mill Ring roller mills,
Equipment Selection Vertical Mill Vertical Mill
circuit.CKP with 2 central discharge mills
compartment mill,
Ball mill

Closed circuit mill with


Ball Mill Circuit separate filter for mill
ventilation and separator

Single compartment with


lifting and classifying liners*
2,8 < L / D <3,2
Ball mill * 27% <Length first
Compartment< 35% mill
effective length.
1st comp: 8 - 10 kWh/t

Ball mill speed 75% of the critical speed 75% of the critical speed <73% Critical speed >78%

Basket variable tip speed


3rd generation high efficiency 10 to 30 m/s, Static separator for pregrinding
1st generation separators, De
Separator separators, radial process air velocity 3 to circuits,
dusting by cyclones
de dusting by filters 5 m/s, fines to separator

By-pass 5 to 10 %
Imperfection < 0.30

Rosin Rammler specification


Acuity <= 15 µm
value to be provided

Air velocity above ball


>1.5% moisture at mill Static separators for separation
charge:1.4 - 2.2 m/s
inlet(Pozzolanic materials of mill dust to final product for
Ventilation ball mill Inside the trunion: < 22m/s
should be dried before open circuit mills and mills
Inside partition:<12m/s
feeding) with old dynamic separators
VFD fan

Process guidelines - Cement grinding - Page 1 / 2 06/10/2005 - 11:28


Best practice /
Cement Grinding Recommendation
Specifications Alternatives Operating target Not advisable Comments
Back to table of contents

Separator Qf/Qa range: 1.8-


Separator Qf/Qa:1.8 kg/m³, Separator Qf/Qa:1.8 kg/m³,
2.5 kg/m3(200% C.L), Cement
Ventilation separator VFD fan for HES, VFD fan for HES, Final product load<0,8 kg/m3
temp 90-110 deg ,
The circulating load 200% The circulating load 200%
VFD for fan

Reverse step liners in first


Reverse step liners for first
compartment with lifting ht Duo lift
Ball mill internals compartment, classifying liners
range: 70-75mm. Classifying Ripple liners
for second compartment
liners in second compartment

* 6 to 8 mm slot
central opening adapted to the * Central screen open area 60
Single plate, slots
filling degree % minimum
Intermediate Partition wall on reverse side of diaphragm
*Material transport capacity *Provision of Flow control
liners
500t/m2/h gates to regulate material
flow

central opening adapted to the


filling degree Intermediate partition wall slot
Outlet partition wall
*Material transport capacity size+2mm,
500t/m2/h

Nominal ball charge loading Higher filling causes higher


28-30% for both specific energy, problems for
Ball charge compartments, >32% ball charge cooling. Ball charge with
(installed power on 32% pregrinder needs to be
filling) modified
Process

Pre requisites for Lucie - Fresh


feed variation through
weighing of separator rejects, Elevator power
Control Belt weigher for rejects
feed accuracy with in +/- 1%,
electronic ear to detect filling
of first compartment.

Feed size passing on


Precrushing, drying of wet
Feed 100% <30mm,
additives
95% < 25mm

Cement temp range: Water injection from partition


Temperature control Cement cooler
90-110 deg C wall if required

Process guidelines - Cement grinding - Page 2 / 2 06/10/2005 - 11:28


Best Practice /
Weighing Dosing Recommendation
Specifications Alternatives Operating target Not advisable Comments

Back to table of contents


Pulverised Coal
Old Pfister > 40 m. Actual limit
is back pressure. Long distance
means more backpressure but
Small bins close to the burning Small bins close to the burning can be compensated for by
point <50 m point <50 m proper design. Schenk Star
New systems of Pfister and
Equipment Selection on cells for calibration on cells for calibration feeder with high pressure
Pfister Coriolis > 50 m
Schenck Coriolis, Schenck Coriolis, transport line not
Variation < 0,5 % (short term) Variation < 0,5 % (short term) recommended (low tolerance).
Schenk Coriolis + Bremer
Screw + FK pump for long
distance is very good.
Minimum number of elbows Minimum number of elbows
Velocity
velocity >= 25 m/s velocity >= 25 m/s
Solid concentration 4-6 kg/nm3 4-6 kg/nm3 > 7 kg/nm3
Raw meal

Both still recommend level bin


ahead of scale to minimize silo
Equipment Schenk Coriolis Pfister flushes. Using airlift pressure to
Weigh Feeder calculate flow can be
sufficiently accurate.

Effective weighing Variation < 0,5 % (short term) Variation < 0,5 % (short term) Accuracy < 0,5 % (short term)

Transport Elevator Elevator Air-lift

Process guidelines - Weighing-dosing - Page 1 / 1 06/10/2005 - 11:05

You might also like