cameron orbit
sequence valve
type LS266-D
1.The set point oil tank cameron valve method LS266-D &
tools needed for the operation.
2.The Concerned thirteen dryer sequence orbit Cameron
valves LS266-D of the facility GTL.
3.Oil requirements & features.
1.The set point oil tank cameron valve method LS266-D & tools needed for the
operation:
Step 2: Remove the upper fluid level plug on the side of the tank, slowly and cautiously, as fluid could
spray from the fill hole if the tank is over-filled and if not this step could give us an idea about oil tank
level as shown on fig1.
Step 3: Fill or drain fluid to bring level to the bottom of the fluid level hole as shown on fig1.
Figure 1
Tools needed:
1.funnel
2. Wrench
Tab1
Tab2