Lighting Legend

LDB: 701LG100A01
DG Khan Cement Company Ltd
Plant :
HUB 900 TPD
791 – Water Treatment Substation
Department :
762 – Water distribution incl. Water pumps and Cooling system
Contract : 1545366

Approved date : 10-06-2016


Created by : EXTSHW
Approved by : REKH-IN

Doc. No.: 50075339-1.0


Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation

A Lighting Legend gives the following information.

Page 5 contains Key to symbols, used in the general arrangement drawings.


Page 6-7 specify
S. No: Serial Nos.

Symbols: The Symbols used in lighting drawings.

Description: Refers to the details of Light fixtures.

Vendor: Name of the vendor who supplies the equipment.

Page 8 contains the numbers of lighting drawings and documents with revision
number.

Following are the drawings and documents delivered for each department.
a. Overall Single Line Diagram
This drawing is in AutoCad format and gives the following details of Light
Distribution Boards.
I. Metering arrangements
II. Incoming and Outgoing Breaker sizes and numbers.
III. Protection details if any
IV. The destination of the outgoing feeder with the Cable Tag no.
V. Twilight and Push button contactors

b. Breaker Details
The detailed SLD is in Excel format with the following details
I. Circuit Breaker No.
II. Circuit Breaker rating ( 1 phase/3 phase)
III. Destination of the outgoing feeder
IV. FCB Location
V. Plug socket detail / Auxiliary control if any
VI. Relay contactor no.
VII. Reference with any control circuits
VIII. Protection details if any
IX. Cable length from first connection box(FCB) to
last fixture
X. Connected Load (Watts)
XI. Cable tag No.
XII. Cable size from FCB to last fixture.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 2/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
XIII. FCB tag no.

In Detailed SLD, the outgoing feeder shows the installation drawing no. to be referred.
The FCB location is defined as follows
XXX-HH-N00-Q00/EQ00
Breaker Number eg. Q05/EQ05
Grid Number eg. L16
Plan Number eg. H2
Dept Number eg. 791
Lighting Installation Drawings
The Lighting installation drawing is a schematic representation of Light
arrangements. The light arrangement location, the connected phase and the Mounting
arrangement details are shown as follows.
XX M XX -X
Phase Number e.g. U / V / W
Type Number e.g. 01
Mounting Arrangement Drawing
Symbol - Shown in Legends Page 6
The type of fixtures shown in drawings should be identified with the legend.

c. First Connection Box(FCB)


In the lighting installation drawings, FCB (First Connection Box) and the feeder numbers are
reflected as below with an example.
FCB TAG NO. 701LG100X11

MCB: Feeder Number Q11

Upward and downward arrows shown in lighting installation drawing are representing a
connection of two or more level/floors in a single feeder. The number of cores in the circuit is
indicated as /3, /4 and /5 in the installation drawings.

The cable lengths from the LDB/LLDB to the first connection box and cable size can be found
in the cable list Doc no. 80041784.
Cable lengths and sizes from first connection box up to the last fixture are included in the
Single Line Diagrams for each LDB/LLDB.

The cable sizes shown in the SLD are to be pulled up to the last fixture. The sizes of cables
are selected based on the project specific cable list.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 3/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Voltage drop is calculated to maximum of 5 %

d. Notes for Lighting Installation


1. Changes to the lighting design can be approved based on site conditions.
2. Cables shown in this drawing are indicative only.
3. All cables have to be laid in cable trays & closest to wall wherever possible.
4. Wherever cable trays are not available, cables have to be laid in conduits.
5. Junction boxes to be fixed on cable trays wherever available.
6. Cable trays in substation for fixture mounting should be at 3.0 mtr. From FFL.

e. Control circuits Doc no. 80042522.


The control circuit gives the wiring details about the photoelectric cell, switch controls or
push buttons used.

f. Mounting Arrangement Drawings Doc No. 80042521.


The mounting arrangement drawing shows the following details
I. Mounting of fixtures
II. Types of fixtures
III. Details of accessories

g. Bill of Quantities Doc No. 80042816.


The quantity of materials required for light arrangements is calculated for each
department for light fixtures and accessories. Cables are calculated for each
LDB / LLDB.

The information transmitted by this document is the proprietary and confidential property of FLSmidth 4/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation

The information transmitted by this document is the proprietary and confidential property of FLSmidth 5/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
(arrow means
Concrete Structure Steel Structure Secondary Platform
descent)

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No. The information transmitted by this document is the proprietary and confidential property of FLSmidth 6/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 7/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 8/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 9/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 10/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 11/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 12/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 13/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 14/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 15/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 16/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 17/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 18/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 19/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 20/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 21/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 22/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 23/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 24/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation
Key to symbols
Datum point/centre
True North Center Line Flow Direction
of gravity

ISO 7519 ISO 129 ISO 128-24 ISO 81714-1

Earth Grating Embossed plate Concrete

Hole Recess

ISO 7519 ISO 7519 ISO 7519 ISO 7519

Grouting-up Railing Revision Estimated Hold

Stairs (arrow means Ramp (arrow means


Insulation Interrupted line
upwards) upwards)

ISO 7519 ISO 7519 ISO 128-23

For equipment with reference Nos. with , the loads are only specified on outline and load
drawings.

For equipment with reference Nos. and consecutive Nos. , see OL drawing or erection
documentation.
Levels Vertical Slope
Concrete Structure Steel Structure Secondary Platform

ISO 129-1 ISO 129-1 ISO 129-1 ISO 129


Levels Horizontal Direction and %
of slope
Concrete Structure Steel Structure Secondary Platform (arrow means

ISO 129-1 ISO 129-1 ISO 129-1 ISO 7519


NOTE (Levels): Levels are either top of concrete or top of steel structure, without grating or embossed
plate. Levels marked “*” indicate the elevation to the top of the grating or embossed plate.

Sr.
Symbols Description Vendor
No.
The information transmitted by this document is the proprietary and confidential property of FLSmidth 25/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.
Lighting Legend
Doc. No. 50075339-1.0
DG Khan Cement Company Ltd
Plant:
HUB 9000 TPD
Department: 791, 762 – Lighting Installation

Sr.No. Plan No. Drawing No. Description Version

1 80042522 Control Circuits Latest


Mounting Arrangement
2 80042521 Latest
Drawings
Overview Drawing LDB &
3 10401803 Latest
LLDB
4 80041271 Detail SLD for LDB-LLDB 1.0

5 SLD-1 10401569 701LG100A01 Overall SLD 1.0

6 Plan-1 10403827 791 Lighting Installation 1.0

7 Plan-3 10405301 762 Lighting Installation 1.0

The information transmitted by this document is the proprietary and confidential property of FLSmidth 26/26
and may not be duplicated, disclosed or utilized without written consent from FLSmidth.

You might also like