Cc JQ INTERNATIONAL CONSTRUCTION INC.
Unit 9-10 2/F BITC Center, Orligas Ave. Cor. Roosevelt St.
Greenhills San Juan City
Date: January 9, 2019
Ref.No.: — SPICT-SIG-HEO-046L-REV2
HEO
530 Shaw Boulevard, 8” Floor Summit One Tower,
Mandaluyong, Manila
To 2 MARVIN S. DETERA JR.
Management Consultancy
Ce ARCHITECT HORACIO GOLPEO JR.
HEO
Project : THE SIGNATURE RESIDENCE
Lot 5 Bik 15 H.V. Dela Costa and Bautista St.
Makati City, Phils.
Subject 2 REQUEST FOR APPROVAL
WALL SETTING OUT
Sir, Good Day!
With reference to the above mentioned subject, we would like to request your good office for
approval of the propose wall setting out located at Unit 9 and 10 of Level 16 to 18 for the purpose
of the installation of Vent Stack together with Soil Stack and Downspout all in the same Pipe
Please see attached proposed shop drawings for your reference and approval.
We are hoping for your good response regarding this matter.
Regard: Notedby:,
h [oP
Al | Tord Mr. Chen Shandong
Civil engines Project Manager