You are on page 1of 2

JQ INTERNATIONAL CONSTRUCTION INC.

Unit (9-10) 2F BTTC Center 288 Ortigas Ave. Cor.


Roosevelt St., Greenhills, San Juan City

DAILY ACTIVITY REPORT

DATE: April 06, 2019


CONTRACTOR: ARDANI Techno- Services & Trading Corporation
SCOPE OF WORKS: MECHANICAL/ PLUMBING/ FIRE PROTECTION
PROJECT: THE INDEX

MANPOWER ATTENDANCE LOADING


POSITION ON-BOARD ABSENT PRESENT MECH. PLUMBING FIREPRO
PROJECT ENGINEER 1
FOREMAN 3 - 3 1 1 1
LEADMAN 1 - 1 1
WELDER 4 - 4 2 2
PIPE FITTER 2 - 2 1 1
TINSMITH 1 - 1 1
PLUMBER 6 - 6 6
ELECTRICIAN - - -
HELPER 7 - 7 1 3 3
TOTAL 25 - 25 3 14 7

ACTIVITIES
1.0 SLEEVINGING OF BRANCHLINES AND DRAIN / STAB OUT AT ROOFDECK
2.0 INSTALLATION OF CROSSMAIN AT 30/F
3.0 INSTALLATION OF RUBBER GASKET IN RISER LOW AND HIGH ZONE AT B-3 UP
4.0 LAYOUT AND FABRICATION OF DUCT AT 3/F
5.0 INSTALLATION OF CI VERTICAL AT 12/F
6.0 INSTALLATION AND REPAIR WATERLINE AND SANITARY AT 20/F
7.0 PREPARATION OF TESTING WATERLINE AND RESTORATION AT 15/F

Prepared By: Checked By:

ENGR. ALDRIN BAGSIC ENGR. RICO DELOS REYES


ARDANI/ PROJECT ENGINEER JQ/ MECHANICAL ENGINEER
JQ INTERNATIONAL CONSTRUCTION INC.
Unit (9-10) 2F BTTC Center 288 Ortigas Ave. Cor.
Roosevelt St., Greenhills, San Juan City

DAILY ACTIVITY REPORT

DATE: April 06, 2019


6CONTRACTOR: ARDANI Techno- Services & Trading Corporation
SCOPE OF WORKS: MECHANICAL/ PLUMBING/ FIRE PROTECTION
PROJECT: THE INDEX

MANPOWER ATTENDANCE LOADING


POSITION ON-BOARD ABSENT PRESENT MECH. PLUMBING FIREPRO
PROJECT ENGINEER 1
FOREMAN 3 - 3 1 1 1
LEADMAN 1 - 1 1
WELDER 4 - 4 2 2
PIPE FITTER 2 - 2 1 1
TINSMITH 1 - 1 1
PLUMBER 6 - 6 6
ELECTRICIAN - - -
HELPER 7 - 7 1 3 3
TOTAL 25 - 25 3 14 7

ACTIVITIES
1.0 SLEEVINGING OF BRANCHLINES AND DRAIN / STAB OUT AT ROOFDECK
2.0 INSTALLATION OF CROSSMAIN AT 30/F
3.0 INSTALLATION OF RUBBER GASKET IN RISER LOW AND HIGH ZONE AT B-3 UP
4.0 LAYOUT AND FABRICATION OF DUCT AT 3/F
5.0 INSTALLATION OF CI VERTICAL AT 12/F
6.0 INSTALLATION AND REPAIR WATERLINE AND SANITARY AT 20/F
7.0 PREPARATION OF TESTING WATERLINE AND RESTORATION AT 15/F

Prepared By: Checked By:

ENGR. ALDRIN BAGSIC CARLA SULATRA


ARDANI/ PROJECT ENGINEER JQ/ SAFETY OFFICER