You are on page 1of 24

METHOD STATEMENT

to

DESCON

from

Abnormal Load Engineering


for

BARGE VOYAGE No. 6


LAND AND MARINE TRANSPORTATION OF
PAR 001, PAR 011, PAR 208 AND PAR 209 AT
BELLELI YARD, HAMRIYAH, SHARJAH TO DAS
ISLAND, U.A.E.

DOC. NO: 5642-MS-009 REV. A


CONTENTS
SL NO. DESCRIPTION PAGE NO.
1. TRANSPORTATION AND LOAD-OUT PROCEDURE 1
2. LAND TRANSPORTATION AND LOAD OUT 11
2.1 TRANSPORTATION ARRANGEMENTS 12
2.2 STORAGE ARRANGEMENT 21
2.3 TRANSPORT ROUTE 23
2.4 LOAD OUT ARRANGEMENTS 52
2.5 LOAD IN ARRANGEMENTS 54
2.6 OFF LOADING ARRANGEMENT 56
2.7 STABILITY CALCULATIONS 61
2.8 LASHING CALCULATIONS 86
2.9 FIXED PLATE DESIGN AND ARRANGEMENTS 102
2.10 LOAD OUT RAMP CALCULATIONS 119
3 MARINE TRANSPORTATION 123
3.1 DETAILS OF CARGO BARGE 124
3.2 STOWAGE ARRANGEMENT ON CARGO BARGE 129
3.3 MOORING CALCULATION AND ARRANGEMENT 133
3.4 BALLAST PLAN AND CALCULATIONS 138
3.5 SEA FASTENING CALCULATIONS 141
3.6 TUG & BOLLARD PULL CALCULATION 217
3.7 LOAD-IN RAMP DETAIL 221
1.0 TRANSPORTATION AND LOAD-OUT PROCEDURE

DOC. NO. 5642-MS-009 REV. A Page 1 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

1.0 Introduction

The procedure covers the land and marine transportation of Pre-assembled Pipe Racks
(PAR’S) from Belleli Fabrication yard, Hamriyah, Sharjah Port up to Das Island Port. The
Pipe rack Structures will then be land transported from Das Island Port to installation
foundation by self propelled modular trailer.

The physical characteristics of the structures are as below:

Length Width Height Weight


Qty. Description
(m) (m) (m) (Te)
1 PAR 001 30.514 10.375 17.150 513.092
1 PAR 011 28.370 8.362 17.150 169.200
1 PAR 208 24.468 6.362 9.487 64.638
1 PAR 209 23.500 6.320 2.960 38.857

This document may be updated and revised upon receipt of further information, MEPI
comments and revisions.

All operations are subject to our standard terms and conditions of carriage.

2.0 Scope of Work for the Project

Included in the scope of work for the project is:

• Supply of transportation equipment to transport the Pipe rack Structures as detailed.

• Supply of engineering support for the land transport operations and all procedures.

3.0 Pre-requisites & Initial Conditions (See ALE ME Standard Terms & Conditions)

Additional Points:

3.1 Clear and free access is to be provided on and through site for all ALE personnel and
equipment during the operations at Belleli Yard.

3.2 The transport route suitably prepared by DESCON to allow safe passage of the loaded
trailer, and must be capable of withstanding the loads imposed during the transportation
operations.

3.3 MEPI to provide adequate access for aligning of trailers underneath the pipe racks.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 2 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

3.4 Cranage and lifting equipment as required is to be provided by DESCON/ALE for


mobilising and de-mobilising all ALE equipment.

3.5 Structural integrity of the items during transport operation is the responsibility of the
MEPI.

3.6 A 24 hours/day radio watch is to be maintained by ALE on VHF Chanel 22 for


communications with ADGAS.

4.0 Drawings & Reference Documents

5642-T101A Provisional Transportation Arrangement for 169.20Te Pipe Rack


PAR 011 on Self Propelled Trailer
5642-T146 Provisional Transportation Arrangement for 169.20Te Pipe Rack
PAR 011 on Self Propelled Modular Trailer
5642-T89A Provisional Transportation Arrangement for 513.092Te Pipe Rack
PAR 001 on Self Propelled Trailer
5642-T144 Provisional Transportation Arrangement for 513.092Te Pipe Rack
PAR 001 on Self Propelled Modular Trailer
5642-T67A Provisional Transportation Arrangement for 64.64Te Pipe Rack PAR
208 on Self Propelled Modular Trailer
5642-T154A Provisional Transportation Arrangement for 64.64Te Pipe Rack PAR
208 on Self Propelled Modular Trailer
5642-T33A Provisional Transportation Arrangement for 38.857Te Pipe Rack
PAR 209 on Self Propelled Modular Trailer
5642-T155A Provisional Transportation Arrangement for 38.857Te Pipe Rack
PAR 209 on Self Propelled Modular Trailer
5642-PC05 Typical Plate Connections between Pipe Rack 011 on Self Propelled
Modular Trailer
5642-FP-SPMT011 Fixed Plate Detail for SPMT for PAR 011 at Das Island
5642-S8-M01 Provisional Mooring Arrangement for AOS 101 Barge at a Suitable
Quay in Hamriyah Port
5642-S8-L01A Provisional Load-out Arrangement for 4 Nos. Pipe Racks on Typical
Barge from a Suitable Quay in Hamriyah Port, Sharjah
5642-S8-L02A Provisional Load-out Arrangement for 4 Nos. Pipe Racks on AOS
101 Barge from a Suitable Quay in Das island
5642-F05D Typical Sea Fastening Details
5642-F70B Typical Sea Fastening Details
5642-F75 Sea Fastening Details for Module PAR 001
5642-F78 Sea Fastening Details for Module PAR 011
5642-F73 Typical Sea Fastening Arrangement for Modules on Flat Top Barge
5642-F74 Typical Sea Fastening Arrangement for Modules on Flat Top Barge
5642-F39A Typical Sea Fastening Arrangement for Modules on Flat Top Barge
5642-F40 Typical Sea Fastening Arrangement for Modules on Flat Top Barge

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 3 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

5642-S8-RD01A Load-in Ramp Detail and Arrangement


5642-S8-M02A Provisional Mooring Arrangement for AOS 101 Barge at a Suitable
Quay in Das Island
5642-OF29 Provisional offloading arrangement for 169.20Te Pipe Rack PAR 011
at lay-down/storage area in Das island
5642-OF26 Provisional offloading arrangement for 513.092Te Pipe Rack PAR
001 at lay-down/storage area in Das island
5642-OF30 Provisional offloading arrangement for 64.64Te Pipe Rack PAR 208
at lay-down/storage area in Das island
5642-OF31 Provisional offloading arrangement for 38.857Te Pipe Rack PAR 209
at lay-down/storage area in Das island
5642-S8-S01-1/3 Provisional stowage arrangement for 8 no. Items on Barge AOS 101
for Barge Voyage no. 6
5642-S8-S01-2/3 Provisional stowage arrangement for 8 no. Items on Barge AOS 101
for Barge Voyage no. 6
5642-S8-S01-3/3 Provisional stowage arrangement for 8 no. Items on Barge AOS 101
for Barge Voyage no. 6
5642-S8-L02 Provisional Load-in arrangement for 4 Nos. Pipe Racks from AOS
101 Barge to a Suitable Quay in Das Island
5642-S8-S04 Provisional Ballasting Pump Locations on AOS 101 Barge for Barge
Voyage no. 6
5642-PK27 Provisional Storage Arrangement for Modules Barge Trip No. 6
5642-R701 Provisional Transportation Route for Pipe Racks from Jetty to Project
Site – Key Plan
5642-R700 Location Plan of Das Island Jetty and PARs 001/002/010/011
5642-R702 Provisional Transportation Route for Pipe Racks Detail 1
5642-R703 Provisional Transportation Route for Pipe Racks Detail 2
5642-R704 Provisional Transportation Route for Pipe Racks Detail 3
5642-R705 Provisional Transportation Route for Pipe Racks Detail 4
5642-R706 Provisional Transportation Route for Pipe Racks Detail 5
5642-R707 Provisional Transportation Route for Pipe Racks Detail 6
5642-R708 Provisional Transportation Route for Pipe Racks Detail 7
5642-R709 Provisional Transportation Route for Pipe Racks Detail 8
5642-R710 Provisional Transportation Route for Pipe Racks Detail 9
5642-R711 Provisional Transportation Route for Pipe Racks Detail 10
5642-R712 Provisional Transportation Route for Pipe Racks Detail 11
5642-R713 Provisional Transportation Route for Pipe Racks Detail 12
5642-R714 Provisional Transportation Route for Pipe Racks Detail 13
5642-R715 Provisional Transportation Route for Pipe Racks Detail 14
5642-R716 Provisional Transportation Route for Pipe Racks Detail 15
5642-R717 Provisional Transportation Route for Pipe Racks Detail 16
5642-R718 Provisional Transportation Route for Pipe Racks Detail 17
5642-R719 Provisional Transportation Route for Pipe Racks Detail 18
5642-R720 Provisional Transportation Route for Pipe Racks Detail 19

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 4 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

5642-R721 Provisional Transportation Route for Pipe Racks Detail 20


5642-R722 Provisional Transportation Route for Pipe Racks Detail 21
5642-R723 Provisional Transportation Route for Pipe Racks Detail 22
5642-R724 Provisional Transportation Route for Pipe Racks Detail 23
5642-R725 Provisional Transportation Route for Pipe Racks Detail 24
5642-R726 Provisional Transportation Route Detail for PAR 001 in Process Area
5642-R728 Provisional Transportation Route Detail for PAR 011 in Process Area
Document Stability Calculations for Transportation of Pipe Rack Structures
Document Lashing Calculations for Transportation of Pipe Rack Structures
Document Sea Fastening Calculations for Transportation of Pipe Rack Structures
Document Load-out Ramp Calculation
Document Mooring Calculation
Document Spreader Beam Calculation
Document Tug and Bollard Pull Calculation
Document Fixed Plate Design Calculation
Document Risk Assessments
AG-1-A1M-4-0593 Process Area (Train1) Piperack PAR 001 Plan Views &
Details
(9210L-121-DW-1841-004)
AG-1-A1M-4-0592 Process Area (Train1) Piperack PAR 001 Elevations (Sht-1)
(9210L-121-DW-1841-003)
AG-1-A1M-4-0507 Process Area (Train1) Piperack PAR 001 Elevations (Sht-2)
(9210L-121-DW-1841-029)
AG-1-A1M-4-0590 Process Area (Train1) Piperack PAR 001 Plan Views (Sht-1)
(9210L-121-DW-1841-001)
AG-1-A1M-4-0591 Process Area (Train1) Piperack PAR 001 Plan Views (Sht-2)
(9210L-121-DW-1841-002)
AG-21-A1M-4-0522 Interconnecting & Offsites Area PAR208 Plan Views &
Details
(9210L-130-DW-1841-049)
AG-21-A1M-4-0523 Interconnecting & Offsites Piperack Area PAR 208 Elevations
(9210L-130-DW-1841-050)
AG-21-A1M-4-0526 Interconnecting & Offsites Area Piperack PAR 209 Elevations
(9210L-130-DW-1841-053)
AG-21-A1M-4-0525 Interconnecting & Offsites Area Piperack PAR 209 Plan Views
(9210L-130-DW-1841-052)
AG-21-A1M-4-0574 Interconnecting & Offsite Area Piperack PAR 011 Elevations
(9210L-130-DW-1841-014)
AG-21-A1M-4-0573 Interconnecting & Offsite Area Piperack PAR 011 Plan Views
(9210L-130-DW-1841-013)

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 5 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

5.0 Operational Procedure – Transportation of Pipe Rack Structures (See Attached


Drawings)

5.1 The trailers are mobilised to Belleli Yard and built into the required configuration with
steelwork for transportation of the first Pipe Rack Structure.

5.2 The trailers complete with load-spreading steel works are then manoeuvred beneath the
first Pipe Rack Structure in the required position and aligned.

5.3 Necessary steel works and shims are arranged between the first Item and the trailer in
readiness for lifting.

5.4 Once all trailers are in position and aligned, using integral axle hydraulics the bed of
trailers is raised until the trailers/ steelwork comes in firm contact with the underside of the
first Item.

5.5 A final check is made on all hydraulic and electrical connections and the bed further
raised, lifting the structure clear of the temporary supports.

5.6 Transport lashings are secured between the trailers and the first Item.

5.7 The first Item is manoeuvred through the designated route away from Belleli yard to
Hamriyah Port towards the suitable lay down area for temporary storage.

5.8 Using the integral hydraulics of the trailer, the first Item is lowered and offloaded. The
trailers continue to lower until all weight of the first Item is transferred into its legs.

5.9 Transport lashings are removed and the hydraulic trailers are withdrawn from the first Item
and manoeuvred to Belleli yard for the transportation of the remaining items following the
same procedure stated above.

6.0 Operational Procedure – Load-out and Marine transportation of Pipe Rack


Structures

6.1 A suitable barge arrived and moored stern-on in readiness for the load-out operation of Pipe
Racks structures.

6.2 Engineered load-off/load-out steel plates are installed between the barge and the quay side.

6.3 The hydraulic trailers manoeuvred beneath the first Item and aligned in readiness for
transportation.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 6 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

6.4 Once in the required transport position the trailer bed is raised using trailer integral axle
hydraulic, until the trailers are in contact with the underside of the module/transport beam
of the first Item.

6.5 The trailers continue to rise, lifting the first Item off the support steel work.

6.6 Transport lashings are secured between the trailers and the first Item.

6.7 The barge is prepared for roll-on by pre-ballasting if necessary.

6.8 The hydraulic trailers slowly manoeuvre over the load-out plate and roll-on the Barge. The
barge is ballasted throughout this operation to ensure that the barge deck remains level
with the quayside.

6.9 The barge superintendent following the approved ballasting procedure will instruct the
transport (trailer) supervisor when to move and when to stop as per the ballasting
requirement of the barge.

Throughout the load out operation, constant checks will be made on

a) Barge level with quay and clearance between the load out ramp and quay to
be maintained within ± 75 mm.
b) Barge Trim – to be maintained within 1% of barge length.
c) Barge Heel – to be maintained within 0.5% of barge width.
d) Tide level.
e) Water level in Ballast Tank – by measuring ullage of each tank.
f) Structure Level – to be maintained horizontal at all times. No levelling
activities will be performed during load-out operation. Minor corrections (±
50 mm) may have to be carried out to maintain the Module level above ramp
level, by integral trailer hydraulics.

All of the above are checked by means of visual inspection and barge draft
marks.

In addition the performance of trailers, ballast pumps and mooring lines will
also be monitored.

6.10 Once the trailers have moved the first Item over the stowage position on the barge the
Item/with transport beam is lowered onto pre-positioned steel grillages on the barge deck.
Transport lashings are removed and the trailers are withdrawn from beneath the Item and
rolled-off the barge at this stage.

6.11 The trailers manoeuvre to the second Item for transportation. The same procedure applies
to the remaining structures.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 7 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

6.12 Sea-fastening are secured between the Items and the barge is made ready for sail away.
The load-out plates are removed from the barge deck.

7.0 Operational Procedure – Load-in and Land transportation to Temporary Storage


Area and to Installation Area

7.1 Prior to arrival of the barge carrying the Items, the trailers are mobilised to DAS Island port
and built into the required configuration for transportation of the Items.

7.2 The barge transporting the Items arrives and is moored at a suitable jetty.

7.3 Steel load-out plates, mats and wedges are positioned as a bridge between the quayside and
barge deck.

7.4 The trailers complete with load-spreading steel works are then manoeuvred over the load-
out plate on to the barge. The barge is ballasted to ensure that the barge deck remains level
with the quayside.

7.5 The hydraulic trailers are aligned beneath the first Item. All sea-fastenings are removed
between the item and the barge.

7.6 Once in the required transport position the trailer bed is raised using trailer integral axle
hydraulic, until the trailers are in contact with the underside of the first Item.

7.7 The trailers continue to rise, lifting the first Item off the support steel work.

7.8 Transport lashings are secured between the trailers and the first Item.
7.9 The barge is ballasted as required during the roll-off procedure to ensure that the barge
deck remains level with the quayside.

7.10 The barge superintendent following the approved ballasting procedure will instruct the
transport (trailer) supervisor when to move and when to stop as per the ballasting
requirement of the barge.

Throughout the load in operation, constant checks will be made on

a) Barge level with quay and clearance between the load-out ramp and quay to
be maintained within ± 75 mm.
b) Barge Trim – to be maintained within 1% of barge length.
c) Barge Heel – to be maintained within 0.5% of barge width.
d) Tide level.
e) Water level in Ballast Tank – by measuring ullage of each tank.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 8 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

f) Structure Level – to be maintained horizontal at all times. No levelling


activities will be performed during load-in operation. Minor corrections (± 50
mm) may have to be carried out to maintain the Module level above ramp
level, by integral trailer hydraulics.

All of the above are checked by means of visual inspection and barge draft
marks.

In addition the performance of trailers, ballast pumps and mooring lines will
also be monitored.

7.11 The trailers slowly manoeuvre over the load-out plate and roll-off the barge.

7.12 The trailers slowly manoeuvre away from barge and to Das Island port temporary off
loading area.

7.13 The first item is lowered on to the temporary off loading area using the integral axle
hydraulic of the trailer. The transport lashings are then removed.

7.14 The trailers manoeuvre back to barge for transporting the second item. The same procedure
applies to the rest of the items.

7.15 The last item to be offloaded to the barge will be transported directly to the specified
delivery area near the foundation along the specified transport route in readiness for
installation.

7.16 The trailers manoeuvre back to the temporary lay down area in readiness for transportation
of the remaining Items to each designated installation areas.

8.0 The Operational Procedure –Load Out Abort

8.1 The object of this method statement is to describe the operations to be implemented if it is
required to abort the load out procedure.

8.2 The decision to abort the load out and instigate the retrieval procedure will be taken by the
ALE load out manager in consultation with the nominated representative from MEPI. This
decision will be made only if it is safer to abort than continue with the load out operation.

8.3 The responsibility for performing the retrieval operation will be with the ALE load out
manager.

8.4 In principle the retrieval operation will take place after High Water on the falling tide. To
enable this to occur, it will be necessary to ballast the barge up against the falling tide to
maintain the level with the quay.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 9 of 222


Abnormal Load Engineering Middle East L.L.C

LAND AND MARINE TRANSPORTATION OF PAR’S


AT BELLELI, HAMRIYAH, SHARJAH TO DAS ISLAND,U.A.E.

8.5 Tractive effort for the retrieval operation will be provided by the ALE transporters in-built
hydraulic drive system.

8.6 The actual retrieval operation will follow in principle a complete reversal of the load out
procedure. It will be necessary to reverse the ballast pumps by switching hoses, which can
be achieved within the elapsed time prior to retrieval start. Similar barge control methods
and parameters to those imposed on the load out will apply.

Prepared: R.B.C. Date: 03/12/2008 Doc No: 5642-MS-009 Rev. A


P.O. Box: 52875, Abu Dhabi, U.A.E., Tel: +971-2-5511662, Telefax: +971-2-5511424, E-mail: mail@aleme.ae
Note: All contracts are subject to our normal terms and conditions
Paid Up Capital Dhs. 150,000 C.R. No. 47626

DOC. NO. 5642-MS-009 REV. A Page 10 of 222


2.0 LAND TRANSPORTATION AND LOADOUT

DOC. NO. 5642-MS-009 REV. A Page 11 of 222


2.1 TRANSPORTATION ARRANGEMENT

DOC. NO. 5642-MS-009 REV. A Page 12 of 222


DOC. NO. 5642-MS-009 REV. A Page 13 of 222
DOC. NO. 5642-MS-009 REV. A Page 14 of 222
DOC. NO. 5642-MS-009 REV. A Page 15 of 222
DOC. NO. 5642-MS-009 REV. A Page 16 of 222
DOC. NO. 5642-MS-009 REV. A Page 17 of 222
DOC. NO. 5642-MS-009 REV. A Page 18 of 222
DOC. NO. 5642-MS-009 REV. A Page 19 of 222
DOC. NO. 5642-MS-009 REV. A Page 20 of 222
2.2 STORAGE ARRANGEMENT

DOC. NO. 5642-MS-009 REV. A Page 21 of 222


DOC. NO. 5642-MS-009 REV. A Page 22 of 222

You might also like