AMMONIA ELECTRICAL

Cabling and Roughing Ins

- Currently in progress

Energization of MVSG and Transformer is on Shutdown (Holy week) ? and also setting of MVSG
protection.

Pre Energization Inspection of ABB for Transformer and MVSG will be scheduled April 8-12. Confirmation
of schedule will be emailed by John Jerome Dizon

AMMONIA AUTOMATION

PLC AND SCADA PROGRAMMING (Ongoing)

- Target date of Accomplishment is May 3

PLC COMPONENTS AND PANEL

-PLC components estimated time of arrival @ Manila is April 22

-Assembly and Wiring Activities completion is on May 3

-Delivery @ site is May 3

Prior to start of Cabling and Roughing Ins

-Coulomb need Instrument layout/drawing so that we can estimate the length of wires

-Follow up on specification of and wiring of Ammonia Leak Detector