17/03/2020 9:00am Setup Workplace; Preparation for Meeting


10:00am‐12:00pm Meeting with Project Management Department
12:00pm ‐ 1:00 pm  Lunch Time
1:00pm‐3:00pm Make Report; Review and list Tasks needed to Accomplish by the PM Group
3:00pm ‐ 4:00pm Make an email for the updates in LTO projects
4:00pm ‐ 5:30pm Went to office to get the files needed for reference
5:30pm ‐ 6:00pm Prepare Equipment List as per instruction by Sir Jerome

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

18/03/2020 9:00am‐10:00am Coordination on LTO regarding on requirements on CFEIs


10:00am‐12:00pm Prepare progress reports and billing for SO2018‐047 Megapower Project (Alphaland Balesin)
2:00pm‐4:00pm Prepare progress reports and billing for SO2018‐037 Megapower Project (Alphaland Baguio)
4:00pm ‐ 6:00pm Revision of 5th Progress Billing for SO2018‐089 Aboitiz Project
6:00pm ‐ 7:00pm Reviewing the additional works for Aboitiz Project that subject for creation of proposals

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

19/03/2020 9:00am‐10:00am Follow up status to Ma'am Sushmita of Aboitiz regarding with Extended Pedestal Billing


10:00am‐12:00pm Prepare Progress Reports and Final Billing for Malvez Project
12:00pm ‐ 1:00 pm  Lunch Time
1:00pm‐3:00pm Gathering documents and reference for creation of electrical plan for Caramoan Projects
3:00pm ‐ 6:00pm Went to office to have an assitance to JFY regarding on myqnap acoount to have remote access on NAS

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

20/03/2020 11:00am‐12:00pm Reviewing of emails


12:00pm ‐ 1:00 pm  Lunch Time
3:00pm ‐ 6:00pm Went to office to get the files needed for reference / verification on RITM billing
7:30pm ‐ 9:45pm Conference call meeting with PM Team to wrap‐up our week
21/03/2020 2:00pm ‐ 4:00pm Went to office to convert PDF file to CAD at JVB Desktop (Caramoan Project) and to borrow PC monitor 

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

23/03/2020 10:00am‐11:30am Project updates


11:30am‐12:30pm Break
12:30pm‐1:30pm Preparation for the online meeting regarding Aboitiz 69kV Transmission Line Project
1:30pm ‐ 6:30 pm  Online meeting via Zoom with Sir Domeng, Sir Ruge, Sir Jerome and Royser Enterprise

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

26/03/2020 9:00am ‐ 11:00am Reviewing of Projects


11:00am ‐ 1:00pm Transferring of Maibarara BOQ into CETI's Proposal Template.
1:00pm‐2:00pm Break
2:00pm ‐ 6:00pm Revision of Project Progress Report for Aboitiz Project as per comments of Sir Domeng

PREPARED BY: APPROVED BY:

MARK V. BANIQUED, REE JOHN JEROME G. DIZON, REE
Project Engineer Asst. Project Manager
DAILY ACTIVITY REPORT

COULOMB ENERGY TECHNIK, INC.


Unit 4-L, Amber Place Bldg., Bayani Road,
AFPOVAI Ph. IV, Fort Bonifacio, Taguig City, Philippines 1630

(02) 804 - 1725 / (02) 697 - 6359


info@coulombenergytechnik.com

DATE TIME ACTIVITIES

27/03/2020 9:00am ‐ 10:30am Reviewing of Projects and went to office


10:30am ‐ 12:00pm Coordination to Sir Philip for some clarification matters on Caramoan Projects
12:00pm‐1:00pm Break
1:00pm ‐ 2:00pm Scanning of Billing documents for Wyeth
2:00pm ‐ 3:00pm Requesting Quotation to Sir Orly of Megamaster for Emergency Transformer Rental for Wyeth
3:00pm ‐ 4:00pm Follow‐ups on LTO Project Updates to Engr. Baby thru phone call
4:00pm ‐ 6:00pm Continuation on Revision of Project Progress Report for Aboitiz Project