COROMANDEL, VISAKHAPATNAM

MAINT SERVICES – SCOPE & ESTIMATION SHEET

PR No: 533672 Plant: RG/RMH

Job Text Modification jobs on OBM & NBM as per FLSMITH audit points

Scope of Job

1. 4" pipeline to be installed in NBM from NBM bagfilter discharge to bottom Air Slide.( approx- 6 mtr) 2
.OBM vent line modification to be done 10" pipe has ot be fabricate d & installed from OBM bafilter to GRS silo. Old line to be removed and new
line with slope angle to be fixed.( approx- 25 mtrs).
3 .6" line has to be modified from OBM Elevator discharge to bagfilter.Line to be modified as per NBM discharge line.( approx-12 mtrs).
4.4" line from NBM bag filter to top air slide

Period of PO to be
Service Dec-18 placed by 11/20/2018

PO
Validity 1 month

Scope of Materials & Consumables : COROMANDEL / CONTRACTOR

Contractor Scope Coromandel Scope


Materials Coromandel Scope
Consumables Coromandel Scope
Tools/Tackles Contractor Scope
Safety Appliances Contractor Scope
Crane Hydra under contractor scope Big crane under Coromandel Scope
Transportation Contractor Scope

TECHNICAL ESTIMATE FOR THE SERVICES To be filled by


Purchase section
Sno Service No Activity Description (Detailed Scope) UOM Qty (appx) Rate Amount (Rs)

6" pipeline to be installed in NBM from NBM bagfilter discharge


1 to bottom Air Slide MTR 12 L.S
OBM vent line modification to be done 10" pipe has ot be
fabricate d & installed from OBM bafilter to GRS silo. Old line to
2 be removed and new line with slope angle to be fixed MTR 25 L.S

3 4" line from NBM bag filter to top air slide & top air slide to silo. MTR 12 L.S
6" line has to be modified from OBM Elevator discharge to
4 bagfilter.Line to be modified as per NBM discharge line MTR 12 L.S
Scope
1 Lines modifcation to be done as per FLSmith proposal.
2
*** scaffolding to be planned & arranged before starting the job as per field requirment.
Total : 33232.70

Approx Height of the activity to be carried out : 80 Ft

Materials cost (if any) - for Outside fabrication jobs only

Safety (Add %) 5 % 1661.64

Emergency/Criticality (Add %) 5 % 1661.64

Profit (Add %) 5 % 1661.64

Transportation (if any) or other charges


Total Estimation Cost: 38217.61

PLEASE NEGOTIATE AND FINALIZE PO ON THE BASIS OF ABOVE ESTIMATE

Requested by Manager/ Sr.Mgr-Maint HOD-MAINT


MAINTENANCE DEPARTMENT
ESTMATION SHEET FOR SERVICES (LUMSUM JOBS)
Job Title : Modification jobs on OBM & NBM as per FLSMITH audit points PR No:

ROUGH ESTIMATE OF JOB


S No Skill level Approx No of Current Cost Current
shifts planned Rate / day OT
(8hrs / shift) Rate
1494.86 /hour
1 Skilled 2 747.43 115.37

2 Semi skilled 3 609.47 1828.41 93.98

3 Un skilled 517.31 0.00 79.72


Total 3323.27
Total / shift 3323.27
No. of shifts 10
Total Estimate 33232.70
Safety (Add %) 5% 1661.64
Emergency/Criticality (Add %) 5% 1661.64
Profit (Add %) 5% 1661.64

38217.61
533672

OT Hours Total
planned/
day
0 0

0 0.00

0
0