Professional Documents
Culture Documents
INCOLD JOURNAL
Volume 1, No. 1 January 2012
• Dr. Martin Wieland, Chairman, ICOLD • ICOLD in the process of bringing out a World Declaration
Committee on Seismic Aspects during 2012 Annual Session in Kyoto on Water Storage
for Sustainable Development 3
• Dr. D.V. Thareja, Director – Technical,
• History of Rockfill Dam Construction 5
SNC Lavalin Engg. India Ltd.
• Definition of Rockfill Versus Earthfill Material 8
• Mr. S.P. Kakran, Member – CWC
• Identification, Mitigation and Management of Risks in
• Mr. V.K. Gupta, Executive Director – Hydropower Projects 13
Hydro Engg, NTPC Limited
• Hydropower Development in India : Need of Commitment
• Mr. Satish Kumar Sharma, VP, and Synergy 18
Moserbaer India Limited
• Dam Safety: Illusion and Reality 25
• Mr. R.K. Vishnoi, AGM-Designs,
THDC India Limited • ICOLD Activity 31
• INCOLD Activities 35
Editors
• Mr. V.K. Kanjlia, Secretary General, • Seminar on Roller Compacted Concrete Dams 35
INCOLD and Secretary, CBIP • Workshop on Dam Safety Management 39
• Mr. A.C. Gupta, Director – Water
• Proceedings of Short Course on Scour of Rock 41
Resources, CBIP
Associate Editor • ICOLD Events - 80th Annual Meeting and 24th ICOLD
• Mr. Sunil Sharma, Sr. Manager, Congress 42
CBIP • Calendar 43
• The IEA Hydropower Roadmap Advances 44
ABOUT JOURNAL
INCOLD Journal is a national half yearly journal for fully-reviewed quantitative articles on aspects of the planning,
design, construction and maintenance of reservoirs, dams and barrages, foundation and scientific aspects of
the design, analysis and modeling of dams and associated structures.
In addition to the information on the research work on the relevant subjects, the journal shall provide information
on the related technical events in India and abroad such as conferences/training programmes/exhibitions etc.
Information related to ICOLD activities shall also be highlighted
EDITORIAL
Water is an essential resource for life and the environment. During the second half of
the twentieth century, an increase in the world’s population and the economic and
social progress of the developed countries has put serious pressures on water.
Numerous countries across the planet are now affected by a water crisis.
The renewable water resources in the world, which emanate from the hydrological cycle, are distributed
extremely irregularly, not only in time but also geographically. With the available of only limited quantity of
water that too unevenly distributed, a need was felt to store the water to use it at the time of need. Over the
past 5000 years, more than 50,000 large dams have been constructed in different parts of the world to ensure
water is available for domestic and agricultural purposes throughout the year. The water that is stored and
regulated by dams and reservoirs produces irreplaceable water resources and brings benefits to water supply,
irrigation, hydropower, flood mitigation, river navigation, recreation, tourism and the environment.
The contribution of dam projects in India’s battle against hunger is striking and self-evident. Agriculture and
industrial revolution in the State of Punjab and Haryana are good example. The “Green Revolution” has
contributed progressive improvement in yield of major food crops in Punjab and Haryana besides poverty
alleviation. The contribution of storage dams are important for contributing towards the development of irrigated
agriculture and improved productivity, enhanced hydropower generation and also enhanced domestic and
industrial water supply, leading to the well-being of people in the country. Many multi-purpose projects like
Bhakra-Nangal, Tehri, Sardar Sarovar etc. are shining example of this.
Providing information on the advancement of dams planning, development, and management its associated
research works besides providing information Service to all concerned with dam engineering about the
development, techniques, new trends and experience gained by others to enable updating of knowledge are
the main aim and objective of the Indian Committee on Large Dams (INCOLD). INCOLD acts as a coordinating
body in India for International Commission on Large Dams (ICOLD) which has 92 Members as its national
group with India being one of them.
As a part of the activities of INCOLD, the first issue of its technical journal, “INCOLD journal” is in your hand.
The journal will be published on half-yearly basis (January-June and July-December)
We are grateful to the contribution of authors, the work of reviewers and support of editorial board who
managed the review process and submission of final papers for the first issue of INCOLD Journal. I request
also the readers to contribute technical papers/articles, news etc. which would be of interest for publishing in
the subsequent issues of the journal. I also request for the comments/suggestions of the readers so as to
improve the utility of the journal.
V.K. Kanjlia
Secretary General
Indian Committee on Large Dams
New Delhi
30% of the population spread over rural areas. The need to optimize reservoir regulation to store more floodwater
for food will double by this mid-century, most extra needs for maximizing the use of flood resources while
being in the countries with long dry seasons. Since arable considering requirements of both the upstream and
land area is limited, the additional production will require downstream. It is expected that based on the monitoring
efficient use of existing irrigation facilities and extending and inflow forecasting system based on technological
the area under irrigation through increased water storage progress in satellite observations, meteorological
facilities. It is estimated that 80% of additional food predictions and higher computing capabilities, real time
production by 2025 will need to come from irrigated land. operation for varied water level control of reservoirs is
• For Clean Drinking Water implemented to achieve a balance between infrastructure
safety and wise use of water resources.
One of the Millennium Development Goals consists in
We, therefore, call for joint efforts for developing
halving the proportion of people without sustainable access
water storage infrastructure in a better and
to safe drinking water by 2015. In 2000, there were 61
sustainable way.
countries with 2.1 billion people who could not have access
to water, that is to say the minimal quantity of 50 liters per Today, water and energy schemes can be built in a safe,
day and per capita. With the expected population growth, economic, and eco-friendly way. Based on the multi-
this number will reach 4.2 billion by 2025. In addition, faceted and cross-boundary nature of water issues in
municipal water supply and industrial plants and processes the present world,
require a significant amount of water to run safely.
• We call for more cooperation among various
• For Electricity stakeholders, government authorities, knowledge
Hydropower supplies about 16% of the world’s electricity institutions, business companies, civil societies, and
today. Hydro supplies more than 50% of national local communities to speed up the development and
electricity in about 65 countries, more than 80% in 32 implementation of effective and sustainable water
countries and almost all of the electricity in 13 countries. solutions.
• We call for improved policies, frameworks and
But only 22% of the globe’s hydropower potential has been guidelines to evaluate and mitigate environmental and
developed. Many countries have thus a vast hydropower social impacts of various storage options and to address
potential waiting to be developed. Transforming this potential the concerns of affected vulnerable communities.
into reality would save fossil fuels and reduce greenhouse
• We call for more multilateral and bilateral funding
gas emissions. Reservoirs created for Hydropower will
agencies to engage with countries on dams and
contribute to the development of other intermittent sources
reservoirs, promoting national and regional project
of electricity production such as solar and wind. This will
development facilities through innovative funding
play a key role in sustainable development of energy supply
mechanisms.
and in environmental protection.
In conclusion
• For Navigation
Water is life and water storage infrastructure is an
Inland navigation for goods transportation, compared with indispensable tool meeting the water needs of the
trucks on highways, rail or airplane, has many evident society in a highly variable climate.
environmental and economical advantages. Inland
To meet growing demands for water, food and energy,
navigation is also unique for handling cargo with large
it is time to develop solutions for better use of water
dimensions. For those reasons, nations have encouraged
resources, especially for most developing countries,
inland navigation on canals but also in natural river
and to match political commitments with delivery.
conditions. Storages are essential to keep the navigation
routes active during the lean flow periods. A balanced approach combining large, medium and
small reservoirs is required; one that fully takes into
There is need to improve the maintenance and account sustainable development, in harmony with
operation of water storage infrastructure. nature, and all other alternatives and ways to
Taking into account the aging process, higher safety minimize negative impact.
requirements from society, and the need to adapt to The organizations signing this declaration agreed to
increasing number of extreme events, we need to collaborate actively with the partners and
increase maintenance to decrease the risks to water stakeholders of this declaration.
storage infrastructure, especially during earthquakes, The functions of water storages will be more and
extreme floods, etc. more crucial in the climate change context as
Climate change has made reservoir regulation more investment in water storage infrastructure is
difficult as river hydrological patterns change. We need investment in green economy.
INTRODUCTION
Modern day rockfill dam construction must rely heavily
on past experiences for guidance pertaining to the
placement and compaction of large rock fragments in a
compacted fill structure. Special rock equipment and
procedures are required for rock borrow development, Photo 2
hauling, placing, and compacting to produce a stable
and acceptable engineered fill structure. The years ago during the mining gold rush era. Drill and blast
conventional earthfill test methods for controlling lift mining techniques by miners provided an abundant
thickness, gradation, moisture content, and compaction supply of rock materials for use in dam construction. Gold
are not applicable to rockfills and must be modified to a mining in the 1850’s also required a large and steady
site specific compactive effort specification using test supply of water for sluicing and extracting the heavier
fills and large vibratory roller compactors. gold nuggets from alluvial placer deposits. The miners
This article presents a brief history of rockfill dam used the rock quarry materials to construct water storage
construction from about 1850 to present day. Rockfill dams in remote areas by hand or with available mine
construction at a gold mine site in Northern Peru is shown haul and dump equipment.
on Photos 1 and 2. The early rockfill dams were small and generally
consisted of a single lift of loosely dumped rockfill with
ROCKFILL HISTORY an upstream timber facing to retard seepage. The
First Milestone downstream slope was typically at the natural angle of
repose approaching 1.2 horizontal to 1.0 vertical
Rockfill materials have been used in dam construction (1.2H:1V). The upstream slope was sometimes hand
since ancient times. However, modern day rockfill dam shaped to as steep as 0.75 horizontal to 1.0 vertical
construction essentially originated in California about 150 (0.75H:1V) for the timber facing.
One of the highest dumped rockfill dams constructed in Rockfill dam heights began to exceed 300 feet (100 m)
the California Sierras during this early gold mining era in the 1940’s to more than 500 feet (152 m) in the 1950’s.
was the Meadow Lake dam at 75 feet (23 m) high. The High-pressure jet wetting or irrigation flooding techniques
upstream slope was constructed to 0.75H:1V with the were developed on the dry rock dump surfaces to
crest freeboard area at 0.5H:1V using hand placed rocks consolidate and reduce large post-construction
to maintain the face slope during rock dumping. The settlements to acceptable levels. Thorough wetting during
downstream slope was constructed to 1H:1V in the lower construction reduced typical post-construction rockfill
section and hand shaped to 0.5H:1V in the upper section dam settlements from 5 to 7 percent without wetting to
similar to the upstream facing. about 1 percent with wetting, thus reducing leakage and
repair costs.
Second Milestone
Prior to 1955, the loose rock dump lifts for in-place wetting
The second milestone covers the time period from the
or flooding typically ranged from 35 to 165 feet (11 to 50
1910’s to 1940’s in which rockfill dump water storage
m) in loose lift thickness with the maximum known rock
dams began to exceed 100 feet (30 m) in height. The
dump lift placed at 200 feet (61 m). After 1955, the dry
“dry rock dump” technique in rockfill dam construction
rock dump lift placement was modified on some dams to
developed into the placement of thick single or multiple
thinner lifts to incorporate the use of weaker rockfill
rockfill lifts in combination with relatively low permeability
materials in dam construction (weathered rock or poor
upstream facing materials (timber, steel, concrete, or
quality rock materials that were locally available at the
asphaltic concrete). One of the highest dry rock dump
dam sites). The thinner rockfill lifts also reduced rock
dams in this time period was the Salt Springs Dam in
segregation where larger sized rocks tend to roll to the
California at 328 feet (100 m) in height.
bottom of the lift during dumping and dozing operations.
The unprecedented water storage dam heights for rock Rock segregation in a dumped fill slope can be seen in
dumps constructed in thick dry loose rock lifts at the Photos 1 and 2, where boulder-sized rocks to 3 feet (1
angle-of-repose was possible because the rockfill dams m) in diameter rolled to the bottom of a 45 feet (15 m)
remained stable with no slope failures. However, the thick dry rock dump lift composed primarily of sand, gravel
larger dams were beginning to experience seepage and cobble sized fill material.
problems on the upstream facing due to post-construction
By the late 1950’s, the rock dump lift thickness on several
settlement movements.
large dams was reduced to 10 to 12 feet (3 to 4 m) thick
The dry rock dump dams experienced undetermined self- with the top surface leveled and tracked by dozer passes
weight settlements during construction loading and large and loaded haul truck traffic. This type of lift construction
observable post-construction settlements during initial thickness and equipment provided a limited amount of
reservoir filling. The post-construction settlements compaction effort in the upper half of the loose lift with
appeared to be directly caused by hydraulic loading on the lower half remaining relatively loose and
the upstream facing. This in turn caused some differential uncompacted.
movement of the relatively rigid facing materials and
No rockfill water storage dam failures occurred for both
leakage along separated facing panel joints.
the earlier “dry” and subsequent “wet” rockfill dumps.
Additional settlements may have occurred from However, there was growing concern for the stability of
subsequent wetting of the dry rockfill due to facing large rockfill dams in more populated areas with the
leakage or abutment foundation seepage. The post- limited amount of engineering knowledge about rockfill
construction wetting action increased the total moist unit strengths and the lack of established rockfill placement
weight of the dry and fully drained rock dump mass. and test control procedures. This concern led to a rapid
Repair of facing leaks during reservoir operations was change in rockfill dam construction by the late 1950’s,
expensive and involved underwater repairs or reservoir after 110 years of relatively successful rock dump fill
drainage. construction.
Third Milestone Fourth Milestone
The third milestone covers the time period from the 1940’s The fourth milestone covers the time period from the
to 1950’s in which the dry rock dump placement 1960’s to the present day in which rockfill construction
continued, except the dry and loose rockfill lifts were changed from wet rock dump placement in relatively thick
wetted to promote self-weight settlement during loose lifts to compacted rockfill placement in thin
construction of the larger rockfill dams. The 1940’s also controlled lifts for heavy roller compaction. The wet rock
included the first use of earthfill core and filter materials dump technique was essentially discontinued by 1965
in the interior section of the rockfill dams. on large rockfill dams around the world. The current
maximum compacted rockfill dam height is 800 feet (243 dam slope conditions on large and small dams for more
m) for the Alberto Lleras Dam constructed in 1989 in than 100 years after this type of rockfill construction began
Columbia. Other compacted earth and rockfill dams are in the 1850’s. However, several larger dams constructed
under construction to greater heights, including Tehri Dam between 1910 and 1940, and exceeding 100 feet (30 m)
in India at 853 feet (260 m) high and Rogun Dam in in height, experienced excessive post-construction
Tadjikistan at 1,100 feet (335 m) high. The highest settlement and movement of the upstream facing
compacted earth and rockfill dam in the USA is the New materials during first reservoir filling.
Melones Dam in California at 627 feet (191 m) high. Thorough wetting or flooding of the dry rock dump lifts
Compacted rockfills starting in the late 1950’s into the during lift placement in the 1940’s to 1950’s, as well as a
early 1960’s utilized dozer track passes, controlled routing reduction of the loose lift thickness in the mid to late
of loaded haul truck equipment or the use of heavy steel 1950’s, minimized post-construction settlement
drum or pneumatic rubber tired roller passes for movements in the larger dams during reservoir filling.
compaction. Rockfill loose lift thicknesses for compaction
From the 1960’s to the present day, the accepted practice
varied, but generally were in the range of 3 to 10 feet (1
for modern-day rockfill dam construction is moisture
to 3 m) in thickness. The movement away from rock dump
conditioning and compaction in controlled lifts with
techniques toward controlled thinner rockfill lifts and
vibratory steel drum roller compactors. Self-propelled
compaction improved the rockfill density and strength,
rollers are more efficient over tractor-pulled rollers,
as well as further reducing the post-construction
particularly at dam abutments. Rockfill moisture
settlement movements.
conditioning is generally site-specific with wetting of rock
Large scale engineering test fill studies by the Corps of materials in the borrow or on the fill.
Engineers and Bureau of Reclamation in the early 1960’s
In comparison to the earlier rock dump techniques, the
confirmed better compaction by heavy steel drum
placement and compaction of rockfills in controlled lifts
vibratory rollers compared to non-vibrating heavy
significantly reduced post-construction settlement,
pneumatic rubber-tired or steel drum rollers. Large scale
reduced material segregation due to high lift rock fall on
test fill lift thicknesses for the early studies varied from
the slopes, increased the rockfill density and related
1.5 to 3 feet (0.5 to 1 m). The vibratory roller static steel
strength, and allowed lateral and vertical placement of
drum weight for the study was 10 tons and the pneumatic
transitional zones for fine to coarse rock materials and
rubber-tired roller static weight was 50 tons.
internal earthfill core and drain filter systems within the
The vibratory roller compactors are a relatively new dam embankment.
concept in compacted rockfill construction, having been REFERENCES
developed within the last 40 years. The tractor-pulled
rollers began to change to self-propelled rollers in the Cooke, J.B. (October 1984), “Progress in Rockfill Dams”,
1970’s for improved rockfill lift compaction, particularly ASCE, Journal of Geotechnical Engineering, Vol. 110,
at the dam abutments. Single and double drum rollers No. 10, pp. 1,383 to 1,414.
with static drum weights of 8 to 20 tons are typical for Glozè, Alfred R. et al, 1977, “Design of Rockfill Dams”,
use in modern day compacted rockfills. Rockfill materials Chap. 7, Handbook of Dam Engineering.
are moistened in the borrow or fill area, if required, and
compacted under fully drained conditions. Water storage Pope, R. J., 1966, "Evaluation of Cougar Dam
dam rockfill loose lift thicknesses are generally less than Embankment Performance", ASCE Soil Mechanics and
5 feet (1.5 m) for the 10 to 20 ton static smooth steel Foundations Division Conference, Berkeley, CA; ASCE,
drum weight vibratory rollers. New York.
Part 1 summarized rockfill placement and compaction guidelines for mine structures, including dams and structure
foundations. Part 2 provided an historical perspective to rockfill dam construction. Part 3 for this article defines
rockfill versus earthfill materials. The terms “rockfill” and “earthfill” are commonly used in the geotechnical engineering
profession, but the transition between the two types of fill, to this author’s knowledge, has not been accurately
defined to the present day.
An earthfill material with various mixtures of clay, silt, sand or fine-grained gravel sizes is well defined by the Unified
Soil Classification System (ASTM D-2487-00). As larger sized rock fragments are added to an earthfill, at some
point the “earthfill” becomes a “rockfill” with predominantly coarse-grained gravel, cobble and boulder sized rock
fragments. A review of past rockfill definitions and suggested upper and lower rock fragment size boundary limits
are presented in this article for compacted rockfills.
Photo 1 - Segregated Earthfill at Top and Rockfill at Bottom Photo 2 - Earthfill and Rockfill Placed in Controlled Fill Lift
of Ore Stockpile Thickness
rock material sizes at the bottom of the thick lifts made it In 1963 and 1964, the Corps of Engineers first
difficult to determine a representative gradation size for experimented with vibratory roller compactors on test fills
the overall rockfill lift thickness. Examples of rock at Cougar Dam, a 445 feet (136 m) high earth and rockfill
segregation on stockpile and fill slopes can be seen in dam near Eugene, Oregon. Large-scale bulk gradation
Photos 1 and 2, respectively. tests were conducted along with other testing to evaluate
the performance of the compactors. Prior to this time
Large rock fragments were also used for dam
period, a limited mount of large-scale gradations had been
embankment upstream slope protection and spillway
performed on other rockfill dams.
channels. Selective borrow rock quality and sizing in
combination with controlled placement of thinner fill lifts The large-scale test fill gradations for the first time
made visual gradation estimates for these type of less established a basis for defining rockfill materials
segregated rockfill structures more approximate. according to measured rock fragment screen sizes, rather
The visual gradation estimates by volume were generally than by visual estimations. The large-scale screen mesh
specified as the largest and smallest permissable rock gradations are significant from the standpoint that
fragment sizes in cubic yards or cubic feet (cubic meters). geotechnical engineers, from this author’s experience,
have a tendency to over estimate the visual size of rock
The visual gradation estimates by weight were generally fragments in a rockfill. As an example, an elongated rock
specified as D85, D50 and D15 sizes representing the rock fragment can be more than 12 inches (0.3 m) in length
size by dry weight passing 85, 50 and 15 percent of the and yet pass through a 6 inch by 6 inch (0.15 m by 0.15
total rock sample dry weight, respectively. As an m) square mesh screen opening, therefore classifying
example, the D50 size represents the estimated rock the fragment as a minus 6 inch (0.15 m) rock fragment.
fragment size at which half of the total sample dry weight
Another error that commonly occurs in visual rockfill
is larger or smaller than the rock size determined by
gradation estimates is to under estimate the percentage
visual gradation estimates or by large-scale bulk
of large rock fragment sizes to small earthfill particle sizes
gradation testing as 50%.
by dry weight passing a given screen size. A rockfill can
The transition from rock dumps to compacted rockfills appear visually to have a larger percentage of clay, silt,
reduced the lift thickness and limited the maximum rock sand or fine to medium grained gravel earthfill materials
fragment size allowable for controlled lift placement and versus larger coarse gravel, cobble and boulder rockfill
compaction. By the late 1950’s the more controlled rockfill sizes. However, if a large-scale gradation test is
lifts made it possible to physically conduct large-scale conducted on a bulk sample of the material, the test
gradation tests on the compacted rockfills. results by dry weight passing the various square mesh
Early Rockfill Gradation Tests screen sizes will generally show a larger percentage of
rockfill to earthfill materials, when compared to the visual
By the late 1950’s, rock dump construction in thick lifts estimate.
was changing to thinner rockfill lifts leveled by dozers for
tracking the surface or for loaded haul truck and heavy USBR Rock Definition
rubber-tired roller compaction. The earliest reported In 1968, the USBR published the Earth Manual, which
large-scale rockfill gradation tests were being conducted further defined cobble and boulder rock particles as
on these type of rockfills by 1959. follows: “Rounded particles are called cobbles, if they
are between 3 and 12 inches (0.07 to 0.30 m) in size, Rock dump fill construction for large dams essentially
and boulders, if they are greater than 12 inches (0.30 m) ended by 1965 in favor of compacted rockfills, where
in size. Angular particles above 3 inches (0.07 m) in size rock materials were placed in thinner controlled lifts for
are classified as rock fragments.” No further distinction compaction by heavy rollers. This limited the maximum
was made about the rock fragment quality or gradation allowable rock fragment sizes within the compacted
required for defining rockfill structures. From this author’s rockfills to where any over sized rocks greater than the
experience, the “cobble” definition is commonly used by lift thickness were raked or dozed to the downstream
engineers to the present day for defining both rounded slope outside of the roller compacted rockfill limits.
and angular rock fragments falling within the 3 to 12 inch With the development of vibratory steel drum compactors
(0.07 to 0.30 m) square mesh size range. in the last 40 years, rockfill dams are now constructed in
The term “rock fragment” is defined for this article as any controlled lift thickness placement, typically less than 5
rock (rounded to angular in shape) retained on the ¾ feet (1.5 m) in loose lift thickness, and compacted with a
inch (19 mm) square mesh screen size. determined number of passes by conventional vibratory
compactor rollers. With the development of large rock
SUGGESTED DEFINITION FOR ROCKFILL haul trucks in recent years capable of hauling more than
MATERIALS 240 tons (218 tonnes) of mined rock material, the
Upper Rock Fragment Limit for Compacted comparable lift thickness for loaded rubber-tired haul
Rockfills truck compaction can approach 10 feet (3 m) in depth.
The greater depth of rockfill compaction requires more
From the original rockfill dams in the 1850’s to the present control of moisture conditioning and a followup large-
day, it appears that rockfills have been loosely defined scale density test in test fills to confirm the effective depth
by the engineering community as predominantly rock of compaction.
fragment materials larger than gravel sizes containing
The maximum target rock fragment size in past practice
some sand and gravel and minimal fines (silt and clay
from this author’s experience has been 2/3 of the
sizes).
maximum loose lift thickness with some allowance for
Rock dump fills constructed by massive lift thickness larger rocks that do not protrude from the rockfill lift.
placement generally had no limit on the maximum rock Therefore, the upper limit of rock fragment size for
fragment size. The largest rock fragment in rock dumps compacted rockfills is controlled by the lift thickness and
was the largest rock size that the available construction available construction equipment at a general range of 2
equipment could move and dump in the fill by large to 5 feet (0.6 to 1.5 m) in rockfill loose lift thickness with
loaders, haul trucks and draglines. The largest rock the use of conventional vibratory steel drum compaction
fragment sizes shown in Photo 3 at the downhill toe of equipment. The upper limit of rock fragment size
the 400 feet ( 60 m) high dump were in the range of 8 to increases at a general range of 5 to 10 feet (1.5 to 3 m)
12 feet (2.4 to 3.7 m) rock fragment sizes. The blasted in rockfill loose lift thickness with the use of large loaded
rock fragment rubble shown in Photo 4 contained rock rock haul trucks for rubber-tired compaction.
fragments larger than 20 feet (6 m) at the downhill toe of
Applying the “2/3 lift height rule of thumb” for the upper
the dump slope.
rock fragment limit is recommended to minimize the
potential for zones of less compaction around the flanks
of the larger rock fragments.
Lower Rock Fragment Limit for Compacted
Rockfills
The transition from earthfill to rockfill materials for
geotechnical engineers is readily defined as the point at
which standard field and laboratory soils testing methods
are no longer applicable to earthfill soils that contain
excessive rock fragments.
The American Standards for Testing Materials (ASTM)
defines the upper rock limit for determining laboratory
maximum dry density and optimum moisture content of
soil materials as no more than 30 percent of the sample
Photo 3 – Predominantly Earthfill Waste Dump with Boulders retained by dry weight on a 3/4 inch (19 mm) square
at Downhill Toe mesh sieve size. Rock correction procedures and
passing the No. 200 (0.074 mm) sieve size. This fine Pope, R. J., 1966, “Evaluation of Cougar Dam Embankment
particle limitation is required from past observations and Performance”, ASCE Soil Mechanics and Foundations Division
experience for maintaining a high strength granular rock- Conference, Berkeley, CA; ASCE, New York.
to-rock skeleton structure conducive to drainage and Sherard, J. L., Woodward, R. J., Gizienski, S. F., and
vibratory compaction efficiency. The reduction in fines Clevenger, W. A, 1963, Earth and Earth-Rock Dams, Wiley,
content also allows compaction by large loaded haul London.
trucks without rutting of the wetted fill surface. Soil Mechanics and Foundations Division Conference, 1966,
REFERENCES “Stability and Performance of Slopes and Embankments”
Proceedings of the ASCE, Berkeley, Califorina, ASCE, New
American Society for Testing and Materials; 1978, Standard York.
Test Methods for Moisture-Density Relations of Soils and Soil-
United States Department of the Interior, Bureau of
Aggregate Mixtures, ASTM.
Reclamation, 1968, Earth Manual, Water Resources Technical
Publication, Denver, Colorado.
Rajeev Vishnoi
THDC India Ltd., Rishikesh
Abstract : Hydro projects are complex infrastructure projects and it is common for disputes to arise between the
developer and the contractor. If these disputes are not efficiently addressed and resolved, it can lead to delays in
project implementation and higher costs. At the same time, the risks occurring during construction may provide the
opportunities which need to be exploited. Indian hydropower projects in particular, have suffered significant time
and cost overruns as a result of disputes between developers and contractors. Primary reasons for these disputes
are the inadequate technical information and ambiguous allocation of risks in the conventional contract documents.
This article presents in brief the criteria followed in identifying the risks, assigning the risks to the party competent
to handle the risk, assessing the probability of occurrence of risk and formation of the Risk Matrix for a hydro
project.
tunnel excavation can be advanced is very much Hydrological risk during construction: Unlike most civil
dependant on rock conditions and the type of temporary engineering construction, hydropower construction
support required. Tunnelling rates might vary from 150 involves building important structures adjacent to rivers
meters per month down to say 10 meters per month in and in the riverbed itself. Therefore the river needs to be
heavily faulted water laden ground. In addition, under diverted to allow the construction to proceed. In designing
certain conditions large water inflows may be diversion works, it is necessary to choose a design flood
encountered and occasionally very high temperatures. for design of diversion works. This implies taking a
Both of these conditions require special driving and calculated risk balancing the cost of the diversion works
support measures which substantially affect tunnelling against potential loss if the design flood is exceeded.
time and costs. Of particular concern are tunnels in karstic Hydrological risk during operation : There are two types
ground where large water inflows and very large solution of hydrological risks. Firstly, the risk of overestimation
cavities may be encountered. Perhaps the main problem of long term flows. With good records and rigorous
is geological uncertainty associated with underground design, this risk can be minimised. Secondly, even if
excavations. With a dam, one can drill several estimates of long term flow are reliable there can be
exploratory holes and obtain quite a good coverage of substantial variation from year to year. Unless the project
the dam site area. This can also apply for a surface has a very large storage (which is very rare in small
powerhouse. However, for a tunnel the most that one hydropower projects), there is nothing that can be done
could expect is a few holes along a tunnel alignment to control this variation. However, with the avoided cost
which are of little use except in very uniform geologic power pricing methodology, it is possible to reduce the
conditions. Underground powerhouses are usually magnitude of revenue fluctuations if the project has some
located deep underground such that it is difficult to reach storage. The storage allows energy production in the
their location with drill holes. Therefore, engineers and dry season to be concentrated into the peaking and
geologists have to rely to a large extent on painstaking shoulder period when prices for power and energy are
geological mapping at the surface which is the projected highest. Therefore, any shortfall in flow is likely to only
underground. This gives some idea of conditions along affect the quantity of lower value off peak energy
a tunnel or at a powerhouse but with much less precision produced. While such measures will reduce the impact
than with surface structures. of flows lower than average, drought scenarios need to
Risks can be alleviated to some extent with adequate be investigated and input into risk management models.
site investigations. However, because tunnels often
Designer’s or Contractor’s incompetence : In both the
extend over considerable lengths, it is impractical to
cases, there is a very substantial risk. Because of the
investigate the entire length by drilling. It is usually
risk profile and because designs are site specific, design
necessary to place considerable trust on detailed surface
of hydropower plants requires well qualified designers
geological mapping supplemented by limited drilling.
with substantial experience in the field. Similarly, while
Specialist geologists are able to project surface geology
the construction risks identified above can be easily
to the tunnel alignment and make predictions as to what
handled by a contractor with adequate resources and
conditions will be encountered along its length. The
experience, they can present insurmountable difficulties
design team, including experienced geotechnical and
to an inexperienced contractor with inadequate
tunnelling engineers, is then able to design the tunnel
resources.
taking into account the predicted geological conditions.
Design measures that can be taken to alleviate risks Non Technical Risks : The above discussion has focused
include: provision of intermediate access adits so that on technical risks since these are particularly relevant
the tunnel can be drilled from several faces concurrently; for large hydropower projects. However, there are also
drilling from downstream to upstream so that ground non-technical risks which may be even more important
water inflows will drain from the tunnel by gravity. than technical risks in some instances. These include
Appropriate support designs for various classes of rock (but are not necessarily limited to) the following:
can be specified including special support measures and Financial Risks : These are particularly important for
construction techniques for very poor rock. Measures that hydropower because of the capital intensive nature of
can be taken during construction include: (a) supporting the projects. For a thermal power project capital charges,
the tunnel immediately after excavation preventing may only be a small proportion (as low as 10%) of overall
relaxation of stresses which can cause failure; (b) drilling annual costs. However, in a hydropower project, capital
ahead of the tunnel face to identify potential water inflows charges may be in the order of 90% of overall annual
and grout these areas before excavation; (c) installing costs. Therefore, any effect on capital cost has an almost
some support ahead of the excavation (usually referred similar effect on annual costs. The potential effect on
to as fore-poling). costs of technical risks has been outlined above.
However, there are other factors such as: communities that they are partners in project
• Cost Escalation Risks : This aspect is of renewed development.
importance in India with higher levels of inflation now The above list of risks is not necessarily exhaustive.
emerging after many years of price stability. The best Particular projects may have other site specific risks such
defence against inflation is to receive bids for main as security, safety etc. These need to be identified and
works and equipment before final decision to proceed addressed adequately.
is made. The fastest possible construction schedule
4. CONCLUSION
(facilitated by a very experienced contractor) will then
minimize the difference between base cost and final Hydro projects are to be executed under a complex set
cost. of site conditions and therefore, management of all
• Interest Rate Risks : In the current environment of categories of risks is essentially required in order to timely
rising and floating interest rates, these risks can be complete the project within the allocated financial
particularly important for hydropower projects. resources. Risk is the product of likelihood of an event
• Market Risks : Again hydropower projects are more occurring and the severity of any consequences and
susceptible than thermal power projects if the severity is a contextual matter. Adoption of risk
expected market does not materialize since the fixed management is now-a-days becoming an industry
costs constitute such a large proportion of total costs. requirement. However, the perceptions like ‘risks happen
to other people’, ‘things cannot go wrong’, ‘things can’t
• Power Price Risks : Up until the present, agreement
be that bad’ and ‘things can’t really get that bad’ are typical
of an appropriate PPA has been a major hurdle to
and still in reality. Risk management therefore, first
developing a hydropower project. If power prices will
requires realism before really practicing it.
change regularly posing a risk for developers, there
should be a provision for the developer to cap the Risk matrix prepared for the hydro project is to be included
risk of falling power prices provided he also accepts in the contract document so that there is no speculation
a cap on rising power prices. It will be important for on the part of the bidders at the time of bidding. The risks
developers and their bankers to carefully consider are clearly allocated and the mitigation measures are
and evaluate strategies in this area. specified. Management of various categories of risks
• Political Risks : There may be political risk involved involved at different stages of the hydro project is to be
in the regulatory process through which the process planned to be carried out through a well defined
is approved. Hydropower projects may be especially mechanism in the contract document at tender stage and
prone to such risks. in the agreement at construction stage. Risk management
is a continuous process and hence risk register shall be
• Environmental Risks : There may be real
updated regularly during project execution as per the
environmental risks in developing the project. These
mutual agreement between employer and contractor.
are more likely to arise in the planning phases if field
Risk register shall be a part of the contract document.
studies disclose factors resulting in cancellation of
This together with GBR and BOQ shall supplement the
the project. The risk should diminish after approval
risk management mechanism.
of the Environmental Assessment and Environmental
Management Plan. There is of course the risk of Risk register for the hydro project has to be specific to
project disruption because of political lobbying by that project. However, a standard list can be helpful as a
environmental activists. These risks can probably checklist. Contractors, design engineers, site supervision
better be categorized as political risks. The best and experts shall according to the project phase be
defence against such risks are well prepared involved in the ‘Comprehensive Risk Management’
environmental studies and a developer committed process.
to best practice environmental management
practices. REFERENCES
• Social Risks : Hydropower projects, particularly (i) Central Board of Irrigation & Power. Tunnel
those involving reservoirs of any size, are likely to construction in India – current status and future task.
require significant land acquisition and sometimes Presentation to World Tunnelling Congress, ITA,
resettlement. These activities become increasingly Agra, 2008
difficult as expectations are raised by generous
(ii) Central Electricity Authority. Guidelines for
compensation packages for larger projects. The best
formulation of detailed project reports for hydro
defence against potential difficulties in this area is
electric schemes, their acceptance and examination
an enlightened policy for compensation and benefit
for concurrence. January 2007.
sharing, encouraging an attitude among local
(iii) ASCE. Geotechnical baseline reports for (vii) US Committee on Tunnelling Technology. Better
underground construction. American Society of Civil contracting for underground construction. National
Engineers, 1997. Academy of Sciences, Washington, DC, 1974.
(iv) ASCE. Geotechnical baseline reports for (viii) World Bank. Emerging Issues in Hydropower
underground construction – Suggested guidelines. Planning and Development in Himalayan Basins.
American Society of Civil Engineers, 2007 Post-Workshop Note on Priorities. Delhi, March
(v) British Tunnelling Society. The joint code of practice 2007.
for risk management of tunnel works in the UK. (ix) International Tunnelling Insurance Group. A code
British Tunnelling Society & Association of British of practice for risk management of tunnel works.
Insurers, 2003 International Tunnelling Association & International
(vi) Tait J, Delmar R, Charalambu H, Everdell R. Design/ Association of Engineering Insurers, 2006.
build agreement for the Niagara tunnel project. (x) Draft Project Appraisal Document of Vishnugad
Rapid Excavation & Tunnelling Conf Proc. 2007. Pipalkoti HEP, India.
Hydropower, in addition being renewable, economical, non-polluting and environmentally benign source of energy,
also have the inherent ability for instantaneous starting, stopping, load variations, etc. and help in improving reliability
of the power system. Furthermore, there is no escalation in cost during the life of the station as it utilises water as
source for generation which is non inflationary in nature. The need for its accelerated development also comes from
its capability of enhanced system reliability and economics of utilization of resources with lowering cost of generation
over a period of time. Despite of having so many advantages of hydropower, actual capacity addition and growth of
hydropower projects is meagre. Although in India, allotment of hydro projects are being done under faster and
speedy manner to public sector undertakings and private developers, yet actual growth in capacity addition is way
behind than the allotment of projects by government to project developers. This can be attributed to:
• Forfeiture of large number of hydro projects due to the financial as well as technical non-feasibility that arise
because of lack of reliable data availability and over demanding competitive bidding quotations,
• Halting of Project in development stage due to various administration bottlenecks like clearances and R & R
issues,
• Problem of sufficient finance arrangement because of higher gestation period and long loan repayment
period.
Water being State Subject, in addition to detailed power policy formulated by central agencies, state governments
also have their separate policies related to allotment, execution and revenue sharing. Though State Governments
facilitate to nurture the speedy development of hydropower in their respective States, yet, the policy framework of
State requires detailed study and understanding which are putting obstruction on techno-economical feasibility and
speedy execution of hydropower projects.
Due to lack of hydro capacity addition, today we are in proper consideration to hydro addition, which will also
bad shape in respect of hydro - thermal energy ratio which create proper balance between peak demand and base
is 28:72 against desired 40:60, which is considered to be load, as hydro projects are best used in peaking load for
ideal for grid stability. We need to improve the mix by giving its nature of spontaneous response to load variation.
There is a broad consensus in the Government of India Central Government agencies are largely concentrating
to expand power generation by developing the country’s on mega-hydel projects, the private sector is being also
hydropower potential of which, very less has been roped in to execute unexploited hydel projects. Funding
harnessed so far. For the purpose of hydroelectric for these projects has come in from the World Bank,
development, the river basins have been in principle various State Banks, private banks and financial
categorized into six major groups namely Indus, institutions like IFCI and PFC. A detail given of hydro
Brahmaputra, Ganga, Central Indian Rivers, West power potential in various states reflects that still there
Flowing Rivers and East Flowing Rivers. While State and is huge untapped potential in the country.
Table 1: State wise Hydropower Potential3
As per the estimates of Central Electricity Authority, Govt. of India, region wise hydropower potential has been
given in Table 2 :
Table 2: Hydropower Potential of India3
The planned survey and study of hydro potential in India • Reassessment of Hydroelectric Potential (2003) –
started way back in 1953 as per the following details: 150,000 MW.
• First Hydroelectric Survey of India (1953-59) –about Even after 50 years of first survey, capacity addition in
42,000 MW (250 schemes), hydro has not reached to envisaged potential of 42 GW.
• Reassessment of Hydroelectric Potential (1978-87) While hydropower holds an important role in the energy
– 94,000 MW (845 schemes & 56 pump storage and development strategies of India, such natural
schemes). resource based projects are inherently challenging.
Environmental and social impacts, potentially both duration above 12-13 years unlike foreign Financial
positive and negative, are inherent. The responsible way Institutions which easily provide loan for period above
to tackle is to develop a clear understanding of such 15 years. As hydro projects normally require development
impacts, drawing from analytical as well as local phase of 5-6 years and further repayment period of 12-
knowledge, and minimize the negative impacts through 15 years, it becomes extremely difficult to arrange loan
appropriate design. Any residual negative impacts should component for the projects. And the new competitive
then be appropriately mitigated and compensated with bidding route has further increased the financial problem
ongoing monitoring and adaptive management wherever for the developer as by giving substantial energy of the
necessary. In the past decade, the development of net saleable power free to the Government leads to
hydropower in India has substantially paced-up. The significant uncertainty of the financial viability of the
government has ensured that the methodology used by project. And also if the developer executes long term PPA,
central power agencies to select sites has to be reviewed the cost of free energy offered to government can not be
with greater public consultation, better monitoring of covered. The developer is left with no other option but to
environmental and social aspects of projects, sell power in short-term market which itself is uncertain
improvements in resettlement policy and practices. scenario. It is difficult to demonstrate the reliability of
Impetus is also given to enhance the institutional capacity future cash flows for giving comfort to the financiers of
related to project identification, engineering and design. the project. On other side, a power project developed by
other sources of fuel requires less time for development
2. GOVERNMENT POLICIES FOR ALLOTMENT AND and there are unlikely natural surprises as compared to
PROFIT SHARING the Hydro projects. Hence the developers are more
The government of India has taken several policy inclined towards the development of thermal power
initiatives to boost the hydro power generation. Some of projects .The policies of state government to collect
the initiatives are:- higher royalty from hydro projects has resulted in
encouraging the development of fossil fuel based energy
• Policy on hydro power development-1998. generation plants.
• Policy Liberalisation.
2.1 Term of Allotment
• Electricity Act, 2003 and consequent changes in
Industry Structure. Each hydro potential state is having its own set of
procedure and provisions of allotments of hydro projects
• National Water Policy- 2005. in terms of;
• National Electricity Policy. - Upfront premium,
• National Rehabilitation & Resettlement Policy- - Free Energy (other than specified by CERC),
2007. - Right for equity participation by State
• Mega Power Projects Policy. Government up to 49%,
• 50,000 MW Hydroelectric Initiative. - First Right for Refusal for purchase of electricity
• New Hydro power policy, 2008 etc. by state govt.
Present royalty structure as per tariff policy (Central – 1% free saleable energy to Local Area
Electricity Regulatory Commission, CERC) is as below; Development Fund.
– 12% free saleable energy to the State Being electricity on concurrent list of the state govern-
Government and ments, they are also imposing additional royalty over and
above the 13% mandatory royalty, stated by centre:
Table 3 : Royalty Structure of State Governments in India4
Sr. No State Wt. Avg. Royalty Royalty Over the Concession Period (%)
1. Himachal Pradesh 19.20% 12% (1st–12th year of operation);18%(13th–30th year of operation)
& 30% (31st –40th year of operation)
2. Uttaranchal 15.43% 12% (1st–15th year of operation) &18% (Balance period)
3. Sikkim 15.43% 12% (1st – 15th year of operation) &; 18% (16th – 35th year of
operation)
4. Arunachal Pradesh 12.00% 12% (excluding 1% for LADF)
5. J&K 14.57% 15% (6th–15th yr of operation) & 18% (Balance period)
As of now the new projects are allotted on the basis of 3. ADMINISTRATIVE CHALLENGES
the International competitive bidding the qualified bidders
Even after allotment of project developer can not go
are awarded projects on the basis of the additional
ahead with development work of the hydro projects due
premium paid by the developer to the state govt. This
to following reasons:
premium may be in terms of additional free power (over
and above the mandatory free power) or in monetary (a) Lengthy and cumbersome process of clearances
terms at the state govt.’s discretion. on account of number of regulations and
committees.
2.3 Local Area Development Committees (LADC)
(b) Difficulties in raising finances for the projects.
In addition to above, some state government also charges (c) Inaccessibility and unavailability of power
on account of LADC (Local Area Development evacuation network.
Committee), in terms of percentage of project cost (1.5%
(d) Time lost due to slow Resettlement and
of Total project cost in Himachal Pradesh) this is in
Rehabilitation process.
addition to LADF. However, this is applicable to all
projects whether located in remote area or in developed (e) Hydro projects incurred various risk in
region. This entails unnecessary expenditure for LADC comparison to any other source of energy:
by project developer thereby increasing project cost. (i) Geological surprise (even well studied
Neither the goal nor the modus-operandi is clear even in project can face this situation)
the mind of policy developers. (ii) Remotely located position.
2.4 Green Cess There were some major reasons for the slippage from
the targeted hydro capacity during the 10th five year plan.
States like Sikkim, also imposing green cess as 1 paisa These were:
per unit (kWH) of generated energy.
1. Land acquisition problems: Land acquisition
2.5 Catchment Area Treatment (CAT) Plan is done by the State Government and often gets
Government of Himachal Pradesh issued notification delayed due to litigation, poor maintenance of
regarding minimum expenditure under head of CAT plan land records, etc. Further it is time consuming
is 2.50% of project cost. The arbitrary imposition of such process which affects the progress of project.
expenditure post bid, to be borne by project developer More flexibility should be given to the project
has resulted in increasing the project cost to the point of authorities to acquire land. The procedure for
un-viability and unfeasibility. fixation of compensation for land should also be
streamlined.
The Government should amend the Land Even if, extensive investigation using new
Acquisition Act in order to mitigate the problems techniques of investigations, are undertaken an
encountered while acquiring land. State element of uncertainty remains in the sub-surface
governments should be persuaded to provide geology and the geological surprises during
land to the project authority in the agreed time actual construction can not be ruled out. So, a
frame to facilitate shifting of project-affected margin of safety needs to be ensured.
persons. 7. Delays in environment and forest clearances:
2. Resettlement & Rehabilitation problems: The process for getting clearance is cumbersome
Reservoir schemes require large extents of lands and involves inputs from both State and Central
to be acquired resulting in displacement of Agencies. The activities for getting environment
families. The national R&R policy addresses and forest clearance should be simplified and
some of these issues and needs to be modified processed faster. There is need to provide single
for early settlement of issues arising due to window clearance for speedy approvals related
displacement of families. to project.
3. Dam Safety: In view of complexity in 8. Inter-State Aspects: Inter-State water disputes
development of hydroelectric projects, particularly have come in the way of taking up of many
large ones, emanating from dam height, process projects. There should be coordination between
of clearances obviously gets linked with multiple the states before allocating the projects and
agencies and authorities. Dealing with number developer should not suffer due to such
of authorities’ results in delaying project progress differences between the states.
and single window for getting clearances is 9. Funding of hydro power projects: Hydro
recommended to fasten the process of getting projects were funded only by Government
clearances. Agencies and hence limited options are available
4. Law & Order problems: Most hydro projects are with the developers. The projects which require
located along the Himalayas. Projects in J&K and huge cost should be developed with private public
States of the North East face problems on account partnership model so that getting funding for these
of insurgency, terrorists, etc. In such eventualities projects is easier due to involvement of
insurance policies to cover such risk may not be government in the project.
enough to compensate the developer and state 10. Reliability of Detailed project reports: Lack of
government should ensure that such events bankable Detailed Project Report of the projects
should not take place at projects site. for development in the private sector before their
5. Difficult / Inaccessible sites: Much of the allotment makes it very difficult for the private
untapped hydro potential is in the remote areas investors/ developers to take investment
of the Himalayas for which excess roads running decisions. The developer need to follow the
into over 100 km at a time have to be first existing procedure for DPR preparation as per
constructed before work can commence. Further, the policy guidelines. Thorough research and
power would have to be transmitted over long investigations need to be done in order to
distances to load centers from these areas formulate each sub-section of DPR as it would
requiring construction of long transmission lines. help in reduction of uncertainties regarding the
The power evacuation system should be first project and ensure optimum utilisation of the
planned with the coordination with state available resources.
authorities before allocating any hydro project
4. LOGISTIC HURDLES
6. Geological Surprises: In the Himalayan
Mountains in particular, geological surprises while Some basic reasons providing real hurdle in way are
tunneling causes large time and cost overruns. listed below;
This results in huge time and cost overruns in • Poor Infrastructure: Most of the identified sites
project which make the project unviable. In such for hydro power plants are in remote hilly terrains
event, the government should facilitate of which face lack of basic infrastructure such as
developers and provide finance at low cost. It is transportation links, Residential facilities etc.
essential that state-of-the-art investigation and which results in the increased Project cost and
construction techniques are adopted to minimize time over-run.
geological risks as well as the overall gestation
period of hydel projects. • Lack of Centralized Data Bank: There is very
limited availability of the input data (discharge
data, Geological and topographical data) for the government prior to project commissioning. This
development of hydro project because of which will help in techno-economical viability of many
there is always a fear of occurrence of any projects.
unanticipated event like extreme deviation in • To have better, effective and time bound
water discharge. utilisation, local development (such as LADF,
• Political Euphoria, LADA etc) shall be spend through a collegiums,
• Poor keenness from Private Players, wherein project developer has to have major say.
V.C. Shelke
Consultant and Former Chief Engineer, Koyna Project, Pune, WRD, Government of Maharashtra
ABSTRACT: Water is an important element for origin and development of human life. Therefore it has
special importance. The different civilizations flourished on the banks of rivers are the evidence of the
relationship between water and human being. There is no alternative to water for the existence of human
civilization till today. During the evolution of human being, an attempt to damn the uncontrolled flood is
the first attempt for development. Though the first dam built one thousand years BC is a matter of research,
the existing oldest dam is the world was built 1500 years ago in Spain. In India dam on Cauvery River
built during ‘Choul’ dynasty called as ‘Grand Anicut’ is the first known attempt. This paper describes the
perception of Dam safety as an Illusion and reality. The causes of failure of Dams and analysis of failure
are also described. A novel idea of ‘Dam Insurance’ is also explained at the end.
1.0 DAMS, TYPES AND CATEGORIES dam with masonry /concrete dam is (1:3) while in India it
is (20:1) In Maharashtra this proportion is same as that
Due to population growth, the number of dams have been
of USA i.e. (1:3). From Dam-safety point of view,
increased fastly, e.g. After World War II, the number of
numbers, types and categories of dam has special
dams in next twenty years were increased from 5200 to
importance, because earthen dams are safest. The
13000. Dams built in last ten years (1970-80) are 13000.
accident proneness and hazard potential depends largely
The population of dams in the some countries (including
on the type of dam.
large and small dams) is 60,000 in USA, 2,00,000 in
Japan and 1000 large and 1,00,000 small dams in India. 4.0. FAILURE MECHANISM OF DAMS
Karnataka is having maximum number of 35000; most It is revealed from the study that about one third dams
of them are medium, small dams. fail due to faulty foundation, one third dam fail due to
According to International Commission on Large Dam unanticipated floods and rest of the one third dam due to
(ICOLD) Register of 1962, the large dams having height other several reasons. Dam break is an catastrophy
of more than 15m were 9315; however actual number is however nowhere in the world the rate of dam building is
much higher than this. Due to some technical norms those retarded, on the other hand in decade 1946 -1955 even
dams have not been included in this list. after 12 major dam breaks, 200 new dams were built
and is the next decade 1956-1965 though dam break
Country As Per ICOLD Register As Per Actual incidents were 24, new 2500 dams were built.
Great Britain 400 2000
Probability of Dam break can be in three stages.
North America 2641 28,000
1. After first impoundment
India 334 43,000
2. After 12-15 years.
2.0. TYPES OF DAMS 3. After long period of construction.
Due to advancement in technology though dams of From above it is seen that rest period of dam is very
different types are being built, the main types of dams less. Hence continuous vigil of dam behavior is inevitable.
are earthen embankments, Masonry dams and concrete Future prediction of behavior of dam depends on
dams. Off course other than these three main types of expertise of individual. For this more attention is required
dams, Rockfilled dams, steel and wooden dams, Rubber on following points.
dams, Concrete Faced Rockfilled Dams are also
constructed. 1. Generally average result of foundation and dams
are considered however failures occur on the
3.0. CATEGORIES OF DAMS weakest section or least line of resistance. This
Considering above mentioned three main types of dams, is important to understand the failure mechanism
66% are Earthen – embankment while 33% are either of a dam.
Masonry / Concrete dam. In Japan 90% of dams are in 2. Deformation of a dam is it’s life long process. In
Masonry / concrete. In USA the proportion of earthen the first half, the dam adjusts itself to surrounding
conditions, this is hyperbolic action, while in next (B) DUE TO INTERNAL REASONS:
half due to changes in stresses is a cyclic action, 1. Heavy Downpour
and however the centre of gravity of dam is
2. Erosion due to waves
always linear.
3. Earth quake
3. The assumption regarding uplift pressure may go
wrong because uplift is measured only at few 4. War
points. Therefore a clear picture of uplift is not (A) DUE TO EXTERNAL REASONS:
available. Depending on the grout curtain to
Due to heavy rainfall, earthen dams can fail because of
reduce the uplift is also not correct, because due
sliding of slopes, landslide on either banks of the dam
to micro movement of foundation strata may tear
may cause dam break. Waves may cause external
of the grout curtain thereby causing increase in
erosion leading to failure. Earthquake is the most
seepage and uplift.
dangerous calamity, because it’s prediction is difficult and
5.0 DAM SAFETY if it’s magnitude is more tensile forces in the dam may
Dam being massive huge structure, it appears safe and lead to breach of dam. For this, necessary precaution is
permanent thing to a common man. Though the oldest taken while designing the dam located in different
dam in the world in Spain is 1500 years old, is it really seismological zones. Fortunately large area of
safe? Are the dams are safe forever? Expert Engineers Maharashtra is made up of Lava Matrix and therefore
have to answer this question. The assumption of dam as was considered seismologically stable, however due to
a safe thing is not a truth on the contrary it is not so and some tremors in recent past it is necessary to reconsider
it gets unsafe due to various reasons. Accordingly to its stability. Government of Maharashtra has set up at
Edward Gruner, “All manmade works carry within Koyna Tremor Committee. This high level committee has
them the seeds of their own decay and eventual scope for study of seismological activities for entire states
destruction” and all dams. The geologist and seismologist of this
committee have prepared a map which will help to
Dam is not an exception to this saying. Dams are enhance the dam safety. Now government has issued
manmade works and though built up accurately and the orders and the use of this map is being done.
scientifically, in the process of establishing the equilibrium
of nature, failure is inevitable. From this point of view Reservoir Induced Seismsity (RIS) has been observed
dam can not be a permanent. However in relative sense in case of some large dams after their first impoundment.
of permanency the proportion of dam safety is different e.g. Kremasta (Greece), Kariba (Africa), Hoover
in different country. India and USA are the relatively Marathon, Oroville (USA), Koyna (India). This has been
unsafe countries as compare to France and Japan. India for about 30 dams in the world. The Khardi Tremors (May
is having 10% unsafe dams while Japan is having only 1983) in the vicinity of Bhrtsta dam is also to be studied
1% unsafe dams. on this background by the experts.
Safety of dams depends on their age because the risk of Besides these natural calamities, a new man made fear
dam failure is more during construction stage. Therefore to dam safety is the war. Great Britain had acquired the
emergency action plan shall be prepared for newly built technique of breaching the dam and they have used it in
dams. Dams between five to ten years old are safer. World War II against the Germany. This is also one of
Dams having age of more than twenty five years are to the reason of the victory of Great Britain. Therefore this
be ascertain for their safety. Failure of Macchu dam in aspect is also needs to be consider while thinking about
Gujarat is an example which was old more than 25 years. safety of dams, on this background the confidentiality of
papers and maps of the dam is very important.
This may jeopardizes the safety of a dam. The above
mentioned points are only indicative and well experienced (B) DUE TO INTERNAL REASONS:
and expert engineers can suggest the cause and Pore, Pressure: Seepage through the body of the dam
remedies about the failure. and underneath the foundation increases pore pressure
REASONS FOR DAM INCIDENTS: and makes the dam unsafe. Therefore incase of earthen
dam, it is necessary to control pore pressure by providing
(A) DUE TO EXTERNAL REASONS: relief wells.
1. Pore pressure Foundation Problem: Earlier dams were built on good
2. Fault in foundation. and strong foundations. Now a days dams are being built
on comparatively geologically unsound foundation.
3. Spillway.
Number of such dams, is increasing causing concern to
4. Gates and outlets. the dam safety. The reaction of water load on foundation
of a dam is mild but definite. It takes long time to transfer (a) Due to internal erosion- (piping
the load on foundation and even if the lake level is phenomenon) by seepage. From bottom
reduced the stresses on foundation is not relived to upward direction
completely. These stresses cause accumulated creep (b) Due to internal erosion by seepage from
in foundation and thereby the dam becomes unsafe. downstream side to upstream side.
To improve the foundation condition, grouting technique 2. Dam break of Gravity Dam
is adopted however along with this several new
techniques to consolidation of foundation is being adopted There is less possibility of dam break due to overtopping
so that geologically incompetent foundation can be in case of gravity dam. On the contrary the portion of the
strengthen to enhance the safety of a dam. Off course dam where excessive strain is occurred, the hole of the
this kind of treatment is a site specific and therefore role shape of letter U will form, leading to dam break, eg
of geotechnical engineers is important and necessary. foundation step of a dam.
Spillways: Spillway is the cause of many dam failures. 7.0 RATE OF DAM BREAK
Therefore it is very important component for safety of a
Rate of dam break is different in different countries. Rate
dam. Spillway being in masonry or concrete it’s safety
of Dam break in 100 years in Japan is 13%, in U.S.A
depends on foundation grade bed rock. If we build the
4.7%, Spain 13% as given in the book of Author Edward
dam on relatively weak foundation, we will lead to unsafe
Gruner’s, ‘Dam Disasters and Discussions’. Similarly
dam.
different types of dams have different rate of dam-breaks.
Flood discharging capacity of the dam shall be designed If we have a look at the table of failure of dam prepared
very carefully by doing flood routing with modern by ICOLD (pl see table), Earthen dams have cause major
methods, however most important thing is to decide incidents and damages in U.S.A, on the other hand more
frequency of flood. To decide the frequency of flood, than thousands of earthen dams are still in operation for
rainfall data for long series of years is required. Hungary last hundred years.
is having the rainfall data for past 450 years; India is It means, it is not correct to draw any conclusion from
having data for 125 years and Maharashtra for 70 years. mere statistics. In case of earthen dam it can be said
It is not good to overlook the economy while deciding that the problem of safety becomes easily serious,
frequency of flood, because a person considering 1: 1000 dangerous and beyond control causing failure. This
frequencies has his life of only 70 to 80 years, this is a means this is a managerial problem and not purely
paradox. For this, it is very important to have reliable technical, because as per important observation of Mr.
rainfall data for as many years as possible. Walhev (U.S.A), ‘senior officers assumes that the work
of earthen embankment is simple, and they rely on junior
Gates and Outlets: Dams have become a dynamic
officers for construction’.
system because of installation of gates and outlets; Due
to this human touch, the dams have become more unsafe. 8.0 LESSON FROM DAM FAILURE.
The inherited human errors in handling these gates and
outlets makes the dams unsafe thereby paying the heavy Turbid water occurring at downstream toe is the sign of
cost. internal erosion in case of earthen dam. One important
observation is that the failure due to foundation problem
Normally outlets are made up of different material than is generally immediate after the sunset, it is difficult to
dam, and as a rule, two dissimilar materials cannot stay explain the reasoning of these two things but cause and
together for longer time. Therefore the outlets are also effect may be due to loss of equilibrium due to foundation
major cause of failures in many cases, for example failure problem, sudden change in temperature after sunset
of Panshet Dam. might be trigging the failure. (More research and expert
6.0. METHODS OF DAM BREAKS opinion is needed in this area)
Failure of every types of a dam is typical e.g. Gravity 9.0 DAM SAFETY AND FACTOR OF SAFETY
dam breaches in only overstressed portion, Arch dam Some conclusions drawn by some experts for factor of
collapses completely. Buttress dam fails by failure of a safety needs to be consider for safety of dams.
buttress one by one.
1. Factor of safety of earthen dam increases with
Earthen embankment fails slowly horizontal and erosion
time elapsed.
and downstream side. The general process of failure of
earthen dam is interesting. 2. Factor of safety assumed at the time of reservoir-
planning does not increases after some period
1. Dam break of Earthen Dam. hence dam break fully depends on law of
probability. Therefore factor of safety must be especially in case of earthen dam the pipe
increased considering its damage potential to the conduits & spillway where dissimilar materials are
life and property on downstream side. used shall be vigiled and maintained regularity.
3. In earlier days dams were built in remote areas 2. At the time of first impoundment of reservoir, all
and therefore the factor of safety was less. But in safety measures shall be taken after studying
modern times the dams are being built closer to spillway flood discharging capacity.
human habitat and considering this possibility in 3. Flood forecasting and warning system shall be
future also increasing factor of safety is inevitable. installed and keep in operation for all dams, prone
Considering above conclusions designs of dams’ needs to accidents and having potential downstream
revision. hazards.
10. REMEDIAL MEASURES ON DAM SAFETY 4. Regular pre/post monsoon inspection of dams
shall be done by a dam inspectorate like Dam
Measures are required to be taken during planning, Safety Organization. (DSO) which is established
construction and operation of dams. by Government of Maharashtra on the lines of
Measures during Planning CWC. For this the dams shall be suitably
instrumented and instruments shall be in good
1. The proven dam type which is safest shall be working condition for all the time.
acceptable. Importance shall be given to dam
5. Good documentation of all relevant record of
safety over political and economical reasons.
dams shall be available when needed.
2. To increase the social memories like noting of
6. Operating staff of gates and outlets shall be well
rainfalls, floods etc. This is a long term measure.
trained, considering the various possibilities of
3. Design of dam shall be prepared by only expert floods regulation and mitigation of floods. Dam
and experienced engineers. built in series on a river-system shall be operated
4. To provide breaching section with low factor of considering, it’s cascading effect on a
safety at predetermined location to control the downstream dam. For this a simulation study shall
dam break. be done considering entire river basin for its
safety. ICOLD has done this for a river basin;
Measures during Constructions Water Resources Department of Govt. of
1. Responsibility of dam construction shall be rested Maharashtra has done this in case of Mula, Mutha
on only experienced and expert engineers and and Bhima basin and handled the flood situation
shall be assisted by geologist. skillfully. The cities like Pune, Pandharpur are
handled properly to avoid loss of properties and
2. Good quality control over materials for
lives in the Monsoon of 1983. On this background
construction shall be exercised.
importance of this method can be realized.
3. In case of large dam if number of outlets are more
7. Above mentioned measures are only indicative
they shall be located at different levels.
and dam operators and Dam Safety Organization
Measures during Operation & Maintenance has to play very important role in taking appropriate
1. All components of dams shall be well maintained, and timely measures for safety of dams.
Note :
1. F1 – Dam failed and were not rebuilt
2. F2- Dam failed and were re-built
3. A1- Accidents after operation for some time.
4. A2- Accidents during initial lake filling
5. A3- Accidents before operation of lake filling
6. AR- Accidents Reservoir
7. MR- Major Repairs
8. DDC- Damage during construction.
Table 2 : Reasons of Failures of dams.
Sr.No Country Foundation Overturning Piping Outlets Inadequate Slips Breach Other
Spillway
1 2 3 4 5 6 7 8 9 10
1 Canada 3 5 - - 2 - - -
2 U.K 5 1 1 1 - 1 1 -
3 India 1 4 3 - - - 6 6
4 Spain 1 3 2 - - - - -
5 U.S.A 30 60 22 1 17 6 6 54
Total 40 73 28 2 19 7 13 60
APPENDIX dam is unlike man made atomic energy. ‘Gods Act’ is still
COMPREHENSIVE INSURANCE PLAN FOR DAMS prevailing in dam construction; therefore it is difficult to
rest a responsibility of dam incident due to ‘Gods Act’ on a
Economics of Dams
man. On the other hand in case of Atomic Power Plant the
Construction of dam requires huge capital outlay and thing is different therefore considering its productivity and
State Government is doing this by raising the funds from hazard Potential, most of the countries in the world have
World Bank. If we look at the dam from commercial point made it compulsory to have ‘Insurance Plan’. This paper
of view then the huge investment done for the construction was written before the ‘Chernoville’ Atomic Power plant
of dam shall be productive at earliest. At the same time if incidents in Russia in the year 1998. However fortunately
we give undue importance to safety of dams then this no incident of Atomic Power plant noticed so far,
becomes very costly affair e.g. the flood of 1:1000 nevertheless the conditions of Atomic Power Plant and
frequency considered for the planning means an idle dam being comparable, Mr. Sowthun & Muller has
expenditure for 1000 years, or if factor of safety is higher, propagated the Idea of Insurance- plan for dams.
then the expenditure is unproductive till occurrence of
such event. From this angle if we consider dam as a THIRD-PARTY INSURANCE PLAN
permanent monument then it becomes an unaffordable A futuristic third party insurance plan is mainly for the
thing, on the contrary if we consider it as a ‘commercial compensation of life and property of the citizen living in
product’ then we can curtail the capital cost to a insurance zone of dam break. This scheme consists of
substantial extent. Now question is which of the above three possibilities.
thinking shall be accepted? Because this problem is also
to be taken as a social problem. In western world this 1. Dam owner will be responsible fully for
commercial aspect is getting popular because of a new compensation but he has to share a certain fixed
and innovative idea of Insurance of Dam. This idea has amount and beyond that the Government shall
been put forth to ICOLD. take the responsibility.
2. Legally Dam owner will have a limited
INSURANCE OF DAM
responsibility up to the ‘Acceptable risk’ and he
Hazard potential of dam can be compared to that of Atomic will have the insurance cover up to that, and
Power Plants. Hazard Potential of dam has got beyond that the government shall take the
geographical limitations and potential energy behind the responsibility.
This has came from altogether different thinking respective governments of the nation make the
of Insurance person according to them when a insurance for their country then the rate of
Government gives permission to build a dam, at insurance will come down to the level of
that very instance the population in vicinity of that acceptable reality and the scheme of insurance
comes under potential danger, and even if the of dam may be in actual practice in future.
dam is being built for development of a nation,
this a breach of ‘law of equality’, therefore REFERENCES
government shall be responsible for the Lessons from dam incidents, USA- 1975 ASCE/USCOLD
compensation to that part of population.
1. Catalogue of dam disasters & failures- USBR.
3. In this case responsibility of dam owner is fixed
2. ICOLD IXth Congress Q. No. 34 ‘The Mechanism
to a huge sum, off course this huge sum is also
of dam failure’.
not negotiable by insurance cover neither the dam
owner can afford it. In this situation the difference 3. ICOLD IXth Congress Q. No. 34 R. No.1
between Insured sum and actual compensation ‘Statistical Study of failures, damages and
shall be make good by the government. deterioration of earth dams in Japan
It is difficult to say which out of above three 4. ICOLD Xth Congress- 1970 Q. No. 138 R No. 11
schemes is correct from socio-economic and ‘ Safety and behavior of concrete dams’
technological angle. Only the international 5. ICOLD Xth Congress- 1970 Q. No. 38R No. 20
organization like, ‘UNESCO’ and ‘ICOLD’ in their ‘Comprehensive Insurance of dams, its scope
joint collaboration can handle the problem. and feasibility’.
Hopefully if on the basis of ‘common-need’ if the
ICOLD ACTIVITY
Hon President Prof L. Berga during the Michel de Vivo wasre-appointed for his ICOLD President Dr Jia Jinsheng, and Prof A.Schleiss,
Round Table on Africa. next three-year term as Secretary- President of the Swiss Committee, in the ICOLD
General at the Executive Meeting in 2011Exhibition hall.
Lucerne.
H.E. Dr Jiao Yong, Vice Minister of Water U. Studer, Mayor of Lucerne,and W. Steinmann, Director of the Swiss Federal
Resources, China, who gave a keynote address at Office of Energy, at the opening session of the Symposium.
the Symposium.
For the Zone America, Alejandro Pujol of Argentina was elected, to take over from A. Marulanda of Colombia. For
the Sixth Post, T. Sakamoto of Japan was elected.
Secretary-General Michel de Vivo was also unanimously re-appointed for another three-year term of office.
New Member Countries
Three new member countries were welcomed by the ICOLD Executive: Georgia, Armenia and Uzbekistan. They
will become the 93rd, 94th and 95th member countries, respectively. The Secretary-General reported that interest
in becoming members had also been expressed by Kazakhstan and Kyrgyzstan.
Forthcoming meetings
T. Sakamoto gave an update on arrangements for ICOLD 2012, the 80th Annual Meeting and 24th Congress, which
will take place in Kyoto, Japan, from 2 to 8 June. He began his talk by reporting on rehabilitation work currently
underway in Japan following the M9 earth-quake and tsunami in the northeast of the country, which took place on 11
March. He told delegates that 400 dams had already been inspected, and all had withstood the major events well,
with the exception of a small embankment structure which had failed. He stressed that the area of next year’s
meeting was in no way affected by, or geographically close to, the disaster in the Tohoku region. The one-day
symposium on 5 June next year, Sakamoto said, is to have the theme ‘Dams for a changing world – Need for
knowledge transfer’. Topics will include:
• impacts of climate change;
• benefits of dams;
• knowledge and technology transfer in dam engineering;
• advanced technologies for dam construction;
• earthquakes; and,
• geotechnical aspects of dam foundations.
Voting officers and delegations from Greece, Iceland, Uruguay, Uzbekistan, USA and Vietnam, during the Executive Meeting on 3 June.
A call for papers has already been issued for the symposium, with an abstract deadline of 31 July this year. For
more details, visit the web site: http://icold2012kyoto.org
The four Technical Questions to be discussed at the Congress, as decided in Hanoi last year, will be:
Q92: Environmentally friendly techniques for dams and reservoirs;
Q93: Safety;
Q94: Flood discharge; and, Q95: Ageing and upgrading.
Pre- and Post-Meeting technical study tours are planned to a number of large dams in various parts of Japan, as
well as to schemes in China and Korea.
Sakamoto also gave details of cultural excursions which will be offered in and around Kyoto at the time of the
meetings.
The US Dam Society is to host the 81st Annual Meeting in 2013, and this will take place in the city of Seattle. The
provisional dates suggested are 12 to 16 August. President of USSD, Mike Rogers, described Seattle as the cultural
and educational centre of the Pacific Northwest, and he added that one or more of the study tours would focus on
the dams of the Columbia river, including Bonneville. The theme of the Symposium would be: Changing times:
Infrastructure development to infrastructure management.
For the Annual Meeting in 2014, invitations were put forward from three Asian countries: India (Agra), Sri Lanka
(Colombo) and Indonesia (Bali). The vote for the 2014 venue will be taken next year in Kyoto.
SYMPOSIUM
At the one-day symposium, President of the Swiss Committee, Prof Anton Schleiss, welcomed participants, and
additional welcome addresses were given by U. Studer, Mayor of Lucerne, W. Stein mann, Director of the Swiss
Federal Office of Energy, and Dr Jia Jinsheng, President of ICOLD. Steinmann spoke of Switzerland’s major use of
renewable energy resources, which contributed about 60 per cent of national electricity production.
He spoke of the high value Switzerland placed on its dams and hydro stations, and he described the country’s new
energy strategy and targets, which involved plans to develop new hydro and pumped-storage plants. An additional
6 TWh/year was to be produced by pumped-storage schemes either under way or going ahead, and a further 4
TWh/year would be from conventional hydro schemes.
R. Abdel Malek, President of IHA, gave a short talk on his Association’s hydropower sustainability guide-lines, and
invited delegates to IHA’s conference in Iguassu, Brazil (which took place in June).
A keynote address was presented by China’s Vice Minister of Water Resources, Jiao Yong, during which he discussed
implications of climate change on water resources and water infrastructure in China, where both severe floods and
droughts were already presenting major problems for some regions, as the country’s water resources were very
unevenly distributed. He also referred to the associated aspects of dam safety, noting that 11 small dams had
breached in China during the heavy flooding of 2010. He outlined China’s national plans to adapt to the effects of
cli-mate change, which included strengthening water infrastructure with a large-scale programme of rehabilitation,
accelerating various reforms in the water sector, and ensuring there were clearly defined rules relating to water
resources development and management. Vice Minister Jiao reported that a total of RMB 64.5 billion (about US$9.97
billion) was being invested in the reinforcement of more than 7300 dams and reservoirs. Over the next five years, up
to 41 000 small reservoirs would be reinforced. Flood warning systems were also to be strengthened, he added.
Award to Prof Chen Houqun
A special award was made to honour Prof Chen Houqun of China, during the symposium. His contribution to dam
engineering was recognized, in particular in the field of seismic aspects of dam safety. His work in studying the
behaviour of dams following the Wenchuan earthquake has been reported in our journal (see H& D Issue 3, 2009).
Long-term behaviour of dams
Two sessions of the symposium dealt with this topic, the first was co-chaired by Dr Andy Hughes (Atkins, UK) and
Dr M. Aufleger (University of Innsbruck, Austria), and the sec-ond co-chaired by A. Pujol (Consultant, Argentina)
and R. Charlwood (Consultant, USA).
A. Mellal (Stucky, Switzerland), gave details of a numerical model to analyse the dynamic behaviour of an arch-
gravity dam, based on studying an existing crack, and aimed at assessing seismic safety.
Dr A. Zielinski (BC Hydro, Canada) discussed safety requirements for dams, focusing on risk-informed decision
making; he felt this offered superior insight into all aspects of dam safety, and could take into account the issue of
safety to life in a more appropriate way than traditional methods.
The theme of riskbased approaches to dam safety management continued with a presentation by P. Heinrichs,
(Dam Safety Committee of NSW, Australia). The policy of DSC was to identify, assess and manage risk to the
public, and keep these under review throughout the life of the project.
Xu Zeping (IWRH, China) described numerical analysis of the 186.5 m-high Sanbanxi CFRD in China, where the
face slab had rup-tured after impounding. The study had provided valuable lessons about the cause of the rupture,
including the low modulus of the upstream rockfill.
Dr D. Stematiu (Technical University of Civil Engineering, Romania) described the case of the Poiana Uzului dam
in his country, to demon-strate some of the problems of an age-ing concrete buttress dam. As a result of foundation
conditions, sudden uplift pressures had been induced by tensile cracks in the grout curtain at the upstream toe, and
the drainage system had become clogged, over time.
Dams and Natural Hazards
This session was co-chaired by Dr Martin Wieland (Pöyry, Switzerland), and Dr G. Zenz (TU Graz, Austria).
Dr N. Matsumoto (Japan Dam Engineering Centre) gave a special talk on the Tohoku earthquake and tsunami, and
the behaviour of dams in the region (see also H&D Issues 2 and 3, 2011).
Continuing on the theme of dams and earthquakes, Y. Yamaguchi (Public Works Research Institute, Japan) described
a study based on cumulative damage theory to estimate the settlement of rockfill during major earthquake motion.
F. Løvholt (NGI, Norway), discussed the hazard associated with tsunamis generated by rock slide impact in reservoirs,
and various methods used to quantify the risk. GIS analysis had been used to identify endangered lakes, and
geotechnical and geophysical investigations had been carried out to study rock slope stability. Numerical simulations
had then been done to study rock slide, wave dynamics and overtopping.
H. Seto (Hokkaido Electric Power Co, Japan) spoke about special measures taken to construct an asphalt facing for
the upper reservoir at the Kyogoku pumped-storage scheme, located in one of the coldest regions of Japan.
High RCC Dams
Dr M.R.H. Dunstan (Malcolm Dunstan & Associates, UK) reviewed world progress in RCC dam construction, focusing
particularly on very high structures. Two RCC dams higher than 200 m had already been completed, he pointed out,
and a third was underway, with about five more planned. He described some of the achievements so far in terms of
placement rates, and he focused on some details of the 217 m-high Longtan dam in China. Dunstan concluded that
there was no technical reason why a 300 m-high RCC dam could not be completed quite soon.
Dams and Climate Change
This session was co-chaired by D. Aelbrecht (France) and G. Ruggeri (Italy). A paper presented by J. Boillat (EPFL,
Switzerland) dealt with a decision support system devel-oped for flood prediction and management of a complex of
hydro schemes on the Rhône river. Another, by T. Sugiura (CREARIA, Japan) described the integrated operation of
three dams, to ensure flood control on the upper Nabari river in Japan.
Dams in a Sound Environment
The final session was co-chaired by Dr Th. Strobl (TU Munich, Ger many) and J-P. Chabal (EDF, France). Dr A.
Kryzanowski (University of Ljubljana, Slovenia) presented a cost-benefit evaluation of environmental impacts and
mitigation measures, which had been applied for a hydro plant upgrade. A. Carmona Rodrigues (New University of
Lisbon, Portugal) presented an analysis of water quality in the Alqueva reservoir, and com-pared results with pre-
construction forecasts.
INCOLD Activities
SEMINAR ON
ROLLER COMPACTED CONCRETE DAMS
13-15 APRIL, 2011, NASHIK, MAHARASHTRA
SUMMARY OF PROCEEDINGS
The Seminar on Roller Compacted Concrete Dams was organized by Central Board of Irrigation and Power (CBIP);
Indian Committee on Large Dams (INCOLD); Water Resources Department, Govt. of Maharashtra, Municipal
Corporation of Greater Mumbai, and THDC India Limited on 13-14 April 2011 at Nashik, Maharashtra followed by
one day field visit on 15th April 2011 to the projects site to view progress of construction of Middle Vaitarna RCC Dam.
The seminar was organized with a view to create awareness about this new technology among engineers of the
various agencies in India dealing with different aspects including planning, design, construction, equipment planning,
time & cost aspects, O&M etc. especially highlighting the scope for utilization of bulk quantity of fly ash (approx.
125 million) being produced tons annually in thermal power stations in our country. The construction of RCC dams has
now been universally accepted as a more economical method of dam construction by combining safety, aesthetics
and cost effectiveness with due care to its suitability in Himalayan geological conditions. From the visible trend of RCC
dam engineering, it appears that greater number of dams will be constructed using this technology in the near future.
The seminar was inaugurated by Shri Ramraje Naik-Nimbalkar, Hon’ble Minister for Water Resources (MKVDC),
Govt. of Maharashtra on 13th April 2011. The Inaugural session was graced by Shri M. Gopalakrishnan, Secretary
General, International Commission on Irrigation and Drainage (ICID) Shri D.D. Bhide, Director General, Maharashtra
Engineering Research Institute (MERI), Shri Ankeeneedu Mangati, Managing Director, Soma Enterprise Limited
and Shri V.K. Kanjlia, Secretary, Central Board of Irrigation and Power. A book on ‘An Indian Experience- Roller
Compacted Concrete Dams’ authored by Shri V.C. Shelke, Former Chief Engineer, Koyna Project was also released
by the Hon’ble Minister of Water Resources.
Besides the Plenary Session, there were 5 technical sessions where about 15 presentations were made by the
national as well as international experts who are involved in planning, design, construction and operation &
maintenance of RCC dams. The seminar ended with a Concluding Session. These sessions were very useful and
interactive where experts shared their experience and exchanged the information on the state-of-the-art technology.
The participation of Dr. C.D. Thatte, Former Secretary, Water Resources, Govt. of India, Dr. D.M. More, former
Director General, MERI, S/ Shri M.K. Rehman, Engineer-in-Chief (AW), B.S.N. Reddy, Engineer-in-Chief (I), Irrigation
and CAD Department, Govt. of Andhra Pradesh, Mr. Yves Felix, Vice President, Coyne-et-Billier and Shri I.S.
Reddy, Vice President, Soma Enterprise Limited, and Mr. Georg Dirk, Managing Director, Dirk India signifies the
importance of the seminar. The seminar was sponsored by M/s. Soma Enterprise Limited
Inaugural session of the seminar Hon’ble Minister lighting the lamp while
inaugurating the seminar
15 technical papers contributed by national and international experts formed Proceedings of the seminar, which
added new dimensions to the body of knowledge on the subjects. There were 150 participants from different
Govt. departments, Public Sector Undertakings like NTPC, NHPC, THDC, SJVNL, NEEPCO, WAPCOS as well
as private agencies including participants from France, UK and Bhutan who are involved in the construction of
RCC dams in the country as well abroad to deliberate the various topics of the seminar. The deliberations of the
seminar helped the participants in better understanding of the various aspects of this new technology and its
adoption in a big way.
The Chairman and Co-Chairman for the plenary and technical sessions were Dr. C.D. Thatte, Former Secretary(
Water Resources), Govt. of India, Shri V.V. Gaikwad, Former Secretary ( Irrigation), Govt. of Maharashtra, Dr. D. M.
More, Former Director General, MERI, Shri V.C. Shelke, Former Chief Engineer, Koyna Project, Shri M.
Gopalakrishnan, Secretary General, ICID, Shri M. A. Rehman, Engineer in Chief, Irrigation and CAD Department,
Govt. of Andhra Pradesh, Shri D.D. Bhide, Director General, MERI, Shri H.V. Patel, Managing Director, Multi Mantech,
International Pvt. Ltd., Shri B.S.N. Reddy, Engineer-in-Chief (I) , Irrigation and CAD Department, Govt. of Andhra
Pradesh, Shri P.R. Bhamre, Chief Engineer, CDO, MERI, Shri Balraj Joshi, General Manager - Designs, NHPC ,
Mr. Yves Felix from Coyne-et – Belier and Shri Reddy, Vice President, Soma Enterprise Limited.
The concluding session was chaired by Shri Gopalakrishnan and others on the dais were Dr. D.M. More, Shri V.C.
Shelke, Shri I.S. Reddy, Vice President, SOMA, and Shri A.C. Gupta, Director(Water Resources), CBIP. After the
successful conclusion of the two days seminar, about 60 participants visited the Middle Vaitarna RCC Dam on 15th
April. A list of presentations made during the seminar is appended.
The following issues emerged after two days of deliberations of the seminar:
1. The journey of Concrete Technology over the last 50 years stretches from Rubble/plum concrete being
compacted using needle vibrators to roller compacted concrete (RCC). RCC technology cuts down the time
of construction sizeably and also enables early returns. It is also eco-friendly and cost effective technology.
In view of these prominent advantages of RCC, its applications needs to be expanded to mass concrete
works such as dams, concrete roads etc.
2. About 400 RCC dams having been completed and about 75 in various stages of construction through-out the
world, there is a urgent need to give due importance to this technology in India where so far only 3 dams
having been completed and one under construction using RCC technology.
3. In many cases there is need to remove substantial quantity of weak material of the foundation to raise the
concrete dams. In such cases, the option of using RCC in filling the foundation needs to be considered as it
will save time and cost.
4. Since reinforcements in the dam body or foundation interfere in quick raising of the dams using RCC
technology, there is a need to examine if reinforcements can be avoided. If it is not possible to remove
reinforcements particularly around the openings, the possibility of providing pre- fabricated precast panels
around the opening should also be examined. However, where it is not possible, conventional concrete may
be used.
5. Apprehensions were raised that in absence of any code relating to the subject matter it is difficult to adopt
this technology in general. Keeping in view the Indian experiences gained by the Irrigation department and
Bombay Municipal Corporation of Govt. of Maharashtra who have resorted to this technology for building
Ghatghar projects and Middle Vaitarna RCC dam based on S&T inputs even when no codes had been
formulated in India, apprehensions to opt for RCC can be done away with. Codes or the lack of it should not
forbid an agency or any state or public undertakings in taking up innovative technologies. The execution of
RCC dam projects is nothing new and can be easily opted for dams given the numerous advantages that
emerged in the conference proceedings. . International code of practices and varied experiences available
for execution of RCC dam need to be carefully studied and utilized as was the case in respect of Ghatghar
dams and Middle Vaitarna dam. Indian experience so far developed shall be very useful for drafting our own
code to be prepared in times to come. CBIP can come forward to cooperate with the Maharashtra State
Irrigation Department and bring in desired inputs.
6. Experience of utilizing RCC technology for dam construction in India is now available. The Maharashtra
engineers who are in position or those who retired from State service but were quite involved and and
associated with planning, design and RCC Dam contractors such as Patel Engineering Limited who constructed
three RCC dams of Ghatghar project or SOMA Enterprise Limited who are executing Middle Vaitarna RCC
dam at present and MERI who helped in designing the mix and maintaining quality control, DST, CWC, and
M/s Multi Mantech who had been promoting this technique as Consultants stand out as India’s rich resource
base in respect of RCC in Dams. Their experiences should be utilized for drafting a Guidelines/ or the
standard procedure / specifications in regard to mix design planning, Construction details etc. Central Board
of Irrigation and Power who have successfully executed three seminars on RCC Dams in 2002, 2006,and
now in 2011 besides bringing out a manual on RCC Dams in 2007 may take a lead to constitute a committee
of experts for preparing a draft guideline; later in association with BIS, attempt should be towards adopting
an Indian draft code on RCC Dams.
7. The RCC technology is very sensitive to quality aspects and hence delicate in its application. It involves the
use of sophisticated and equipments like batching plant, conveyor belt, laser mounted spreader, vibratory
roller and so on. Adherence to quality consciousness is a mandatory requirement; Competent agencies to
take up this venture are the need of the day. The continuity in works of similar nature will enable the agencies
to develop confidence in investment and also initiate a climate of fair competition and cost effectiveness in
this specialized field.
8. The Research and Design Wing such as MERI, GERI, CWPRS, CSMRS, CWC and the Design wings of
different states of the country in collaboration with DST’s flyash mission should further the development of
RCC technology in the country by developing an intense dialogue for sharing of experiences in an integrated
manner. This will enable the country to lessen the reliance on dependence on outside consultants and stand
on own legs. The technological support must come from within and not from outside. The databank made
by MERI at the instance of flyash mission by conducting number of tests on samples of flyash collected from
across the country should be made use of extensively.
9. There should be an Apex body consisting of Flyash Producers (Energy), users (Govt. & Pvt.), Contractors,
Researchers, Designers, Environment Engineers and promoters like flyash mission for review and monitoring
of furthering the development of RCC technology in the country in an integrated manner. C.W.C should
make a beginning to form such a group having members predominantly from the State of Maharashtra who
have been exclusively involved in promoting RCC technology. CBIP can as secretariat for this group.
10. For the promotion of RCC technology, there is a need to insist on study of an alternative of using RCC
technology for gravity dam projects. CWC and State Governments need to issue such a directive so that the
project reports have this alternative also.
11. Instruments play a very important role for knowing the behaviour of the dam. The data which have been
collected from RCC dams already constructed in India needs to be studied in detail so as to assess whether
the RCC dam and its foundation has behaved as expected.
12. Processing of flyash should be an integeral part of all our future Thermal projects for efficient utilization of
flyash. The need for a separate BIS standard for “processed flyash”, establishing a few dispersed processing
units around the country well spread geographically also stood acknowledged. The Centre and State agencies
should work towards this goal so that quality ingradients are easily available for adopting RCC technology all
over India.
Dignitaries on the Dais during the Inaugural Session Shri R.N. Khazanchi, MD, Punatsangchu
making a presentation
Dr. C.D. Thatte and Shri V.V. Gaikwad chairing Dr. D.M. More and Shri V.C. Shelke chairing
the Plenary Session the Technical Session - I
Shri M. Gopalakrishnan and Shri M.K. Rehman chairing Shri D.D. Bhide and and Shri H.V. Patel chairing
the Technical Session - II the Technical Session - III
Shri Balraj Joshi and Shri P.R. Bhavre chairing Mr. B.S.N. Reddy and Mr. Yves Felix chairing
the Technical Session - IV the Technical Session - V
WORKSHOP ON
DAM SAFETY MANAGEMENT
29-30TH SEPTEMBER 2011
CONFERENCE HALL OF CBIP, NEW DELHI
Shri V.K. Kanjlia, Shri A.K. Bajaj, Shri S.K. Das and Shri A.K. Bajaj lighting the lamp
Shri R.C. Jha on the Dais
The catastrophic failure of dams have occurred in almost all parts of the world, from the most developed country like
USA to the most under developed parts of the world. It has been reported that there have been almost 200 notable
dam failures in the twentieth century in the world so far and It is estimated that more than 8000 people lost their lives
in these disasters. In India too, there have been quite a few failures. Most of the existing dams were built at a time
when the technology of dam designs and construction were at a developing stage. If these were to be reviewed as
per current practices and standards, they may not fulfill the criteria. Such dams may be potentially hazardous. In
view of this, dam safety evaluation of existing dams needs greater attention. Dam safety is, therefore, considered
as an extremely important aspect not only to safeguard the national interest and benefits derived from it but also to
ensure the safety of human lives and properties in the downstream reaches of the dams.
There is an increasing awareness in recent times, not only among the engineers but also among the general public,
about safety of dams already constructed as well as those planned for construction. It has been recognized that
Shri S.K. Das delivering Lecture during the workshop View of audience
dam safety aspects particularly of the existing dams, are not receiving much attention as they should be, especially
in view of the fact that a number of these old/existing dams are ageing, leading to gradual natural degeneration.
Even safety of some of the dams which have been constructed in the recent past may become questionable, if the
flood characteristics or seismicity of the area has changed. These old dams may need a research under today’s
technology. The safety of dams is of paramount importance.
Dam safety programmes are of vital importance to the society and call for multidisciplinary efforts. Need has been
felt to review the procedures and the criteria of dam design with the objective of establishing the best assurance of
dam safety within the limitations of present state-of-the. An increasing trend in the implementation of various measures
to protect the public from consequences of dam failures can be seen around the world. In this direction, MOWR,
Govt. of India has presented The draft dam safety Bill 2010 in the Lok Sabha, to provide for proper surveillance,
inspection, operation and maintenance of all dams of certain parameters in India to ensure their safe functioning
and for matters connected therewith or incidental thereto. Many Indian States are looking into legalizing the provisions.
Keeping in view the importance of the subject, the Indian Committee on Large Dams (INCOLD) and Central Board
of Irrigation and Power organized two days workshop on “Dam Safety Management” on 29-30th September 2011
in the Conference Hall of Central Board of Irrigation and Power, at New Delhi . The workshop was inaugurated by
Shri R.C. Jha, Chairman, Central Water Commission on 29th September 2011. The other dignitaries who addressed
the participants during the inaugural session are Shri A.K. Bajaj, Former Chairman, CWC ; Shri S.K. Das, Former
Chairman, CWC and Coordinator for the workshop; Shri V.K. Kanjlia, Secretary, CBIP and finally Shri A.C. Gupta
proposed the Vote of thanks. The workshop was sponsored by M/s. Encardio-rite Electronics Pvt. Ltd..The workshop
offered a good scope for interchange of experiences to facilitate exposure of state of art technology in all aspects of
dam safety management, especially considering participation of eminent dam experts. The following topics were
deliberated during the course of two days deliberations of the workshop:
• Introduction to dam safety (describing causes of dam failures, failure modes and lessons on dam incidents)
- Mr. S.K. Das, Former Chairman, CWC
• Investigation to determine the physical condition of dams (structural, geological and geotechnical review
of dams in operation) - Mr. S.K. Das, Former Chairman, CWC
• Hydrological review of existing dams – Mr. Bhopal Singh, Director – HSO, CWC
• Instrumentation for dams (to monitor their performance during operation) – Mr. V.K. Rastogi, Director –
Marketing, Encardio-rite Electronics Pvt. Ltd.
• Rehabilitation of dams in distress – Mr. S.K. Das, Former Chairman, CWC
• Dam safety in India: An Overview and Draft The Dam Safety Bill, 2010 – Dr. B. Ravikumar Pillai, Director –
Dam Safety, CWC
More than 125 professionals from Central and State Govt. agencies, Consultants, Developers, manufacturers etc.
have attended the deliberations of the workshop.
The hydraulic structures spilling excess water from dam reservoirs have been a major engineering concern for a
long time. The transfer of water to the downstream river may scour the dam foundation and the downstream river
bed. On the long term, this scour process may create structural safety problems. Hence, accurate prediction of time
evolution and ultimate scour depth is required which is traditionally estimated by use of empirical or semi-empirical
formulae that partially neglect basic physical processes involved. Especially the role of fluctuating dynamic pressures
in plunge pools and their transfer inside underlying rock joints is unknown. Also, empirical expressions are often
only applicable to the specific conditions for which they were developed. They neglect the influence of aeration on
dynamic pressures and cannot correctly simulate the resistance of the rock against progressive break-up. There
appears a need to create awareness among engineers of the concerned agencies in India about the state-of-the-art
insight and offers techniques that can be used to analyze scour of rock downstream of overtopping dams and in
plunge pools.
Keeping in view the above, the Central Board of Irrigation and Power (CBIP) and Indian Committee on Large Dams
(INCOLD), organized a Short Course on Scour of Rock (downstream of overtopping dams and plunge pools) on 19th
October 2011 at New Delhi. The short course was inaugurated by Shri A.K. Ganju, Member – D&R, Central Water
Commission. During the inaugural session, Shri V.K. Kanjlia welcomed the dignitaries and the participants; Dr.
George Annandale presented a brief overview of the short course and Shri A.C. Gupta proposed the vote of thanks.
The programme was attended by 50 participants from CWC, NTPC, NHPC, and other CPSUs, WR Departments of
State Govrnment.; developers, consultants etc.
Dr. George Annandale, P.E., D.WRE, F.ASCE, Program Leader at Golder Associates, Inc., who has 35 years of
experience as a civil engineer specializing in water resources engineering and is known for the development of the
Erodibility Index Method that can be used to determine the erodibility of any earth material, including rock, was the
instructor for the course.
The short course provided state-of-the-art insight and offers techniques that can be used to analyze scour of rock
downstream of overtopping dams and in plunge pools. Topics that were covered include assessment of the potential
for rock scour, and the maximum depth and rate of scour of rock. Economical solutions to scour problems are often
dependent on knowledge of the rate of scour, i.e. whether the maximum extent of scour occurs almost immediately,
or whether it is time-dependent. Scour that occurs almost instantaneously may require extensive protection, while
scour that is time-dependent and only reaches its full extent after, say, decades, may require only limited protection
if at all. The topics covered are based on technological developments in rock scour assessment developed over the
past 20 years.
The short course offers instruction on processes leading to scour, and on pragmatic methods to quantify the erosive
capacity of water and the erosion resistance of rock, and practical methods for calculating the potential for, extent
and rate of scour. The methodologies presented in the short course have been successfully applied in practice and
have been validated by making use of scour case studies. The participants were provided with the learning objectives
to develop:
Insight into scour processes and how flowing water interacts with rock and leads to scour,
The capability to quantify the ability of rock to resist the erosive capacity of water,
The capability to quantify the erosive capacity of water that can lead to scour of rock,
The capability to calculate the potential for, extent and rate of scour of rock.
ICOLD Events
80th ANNUAL MEETING AND 24th ICOLD CONGRESS
KYOTO INTERNATIONAL CONFERENCE CENTRE, JAPAN
JCOLD welcomes ICOLD members to Kyoto, the ancient capital of Japan, for the 80th Annual Meeting and 24th
Congress. The city contains 17 UNESCO World Cultural Heritage Sites, reflecting the legacy of many ancient
Japanese traditions.
During the Annual Meeting, on 5 June, a one-day International Symposium will take place, with the theme: DAMS
FOR A CHANGING WORLD: Need for Knowledge Transfer across the Generations and the World.
The Symposium themes are: Vice-Chairman : Alejandro PUJOL (Argentina)
(1) Impacts of Climate Change on Dams and the General Reporter: Gerald ZENZ (Austria)
Benefits from Dams Secretary: Y. YAMAGUCHI (Japan)
(2) Dams for Meeting Increasing Demand of Growing Q94 : Flood discharge
World Population
1. Evaluation, revision and selection of extreme and
(3) Knowledge & Technology Transfer in Dam design floods
Engineering
2. Recent trends in spillway design and spillway
(4) Advanced Technologies for Construction of Dams upgrading
(5) New Techniques to Prevent and Manage 3. Special risks from gates operation and floating debris
Incidents & Accidents
4. Energy dissipation: stepped spillway, stilling basin and
(6) Earthquakes downstream erosion
(7) Geotechical Aspects of Dam Foundations
Chairman: B.P. MACHADO (Brazil)
(8) Others Vice-Chairman: E. CIFRES (Spain)
Congress themes are: General Reporter: Guo JUN (China)
Secretary: J. KASHIWAI (Japan)
Q92: Environmentally friendly techniques for dams
and reservoirs Q95 : Ageing and upgrading
1. Environmental and social friendly planning, design 1. Risks associated with long-term behaviour of dam
and construction techniques for dams foundations
2. Mitigation and compensation measures 2. Long-term behaviour of dam materials and structures
3. Water quality and sediment issues 3. Decommissioning or upgrading?
4. Sustainable management of dams and reservoirs 4. Upgrading for seismic safety
Chairman: Imo EKPO (Nigeria) Chairman: R. CHARLWOOD (USA)
Vice-Chairman:Ahmet Mete SAATCHI (Turkey) Vice-Chairman: Ali NOORZAD (Iran)
General Reporter: Joji HARADA (Japan) General Reporter: Bernard HAGIN (Switzerland)
Secretary: K. SOMEYA (Japan) Secretary: J. TAKIMOTO (Japan)
Q93 : Safety The 24th Congress will run from June 6 to 8, and a
1. Accidents and incidents in dams and reservoirs – Technical Exhibition will take place from 5 to 8 June.
Recent case studies A full social and cultural programme has been organized
2. Risks associated with human and organizational for delegates and accompanying persons Study tours will
factors take place before the meetings, to China and Korea, and
3. Legislation, regulatory concepts, guidelines and good after the Meetings to various parts of Japan.
practice For more information, contact: Organizing Committee,
4. Specific risks for small dams ICOLD 2012 Kyoto
5. Risks specific to tailing dams, pump-storage Toranomon-Yatsuka Bldg. 8F, 1-1-11, Atago, Minato-ku,
schemes, flood control structures and other special Tokyo 105-0002 Japan
purpose dams Tel: +81 3 3459 0946
• Fax: +81 3 3459 0948
Chairman : Alain CARRERE (France)
• Email: contact@icold2012kyoto.org
Web:http://icold2012kyoto.org
CALENDAR