TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST SUBMITTED
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER LOCATION OWNER DESIGNER CONTRACTOR BY
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT.
285’-340’ Contractor
BRIDGE 450’-380’ Mined Shafts redesign I-008, 40 mi
OVER Pine Valley 266’ & grouted C.I.P. Balanced Membrane 1971 from draped 2@42’ $ 10.48 M 144,144 $72.68 East of CALTRANS CALTRANS Dyckerhoff J.Hare
WATER Creek (Parallel not anchors Cantiliver & AC strand to San Diego & Widmann
same) straight bars
26" sq. 36"
BRIDGE 120’ diam. Precast C.I.P. Balanced
OVER Napa River to prestress + P.C. Cantiliver 2" AC 1974 62’ $ 8.17 M 138,260 $59.07 Route 29 CALTRANS CALTRANS Guy F.Atkinson J.Hare
WATER 250’ cast-in-drilled Lightweight & span/span near Napa
hole 16"
BRIDGE 375’
OVER Beltway B over to 24" dia. C.I.P. Balanced Asphalt 1979 3 Webs 59’4" $ 19.5 M 88,875 $219.90 Houston TxDOT HNTB Williams M.Miller
WATER Ship Channel 750’ Pipe piles Cantilever Texas Bros.
BRIDGE
OVER Long Key 118’ P.C. Span/Span 1979 38’ $ 14.5 M 468,400 $31.00 Florida Keys FL DOT Figg Michael A. Moreton
WATER Engineering Construction
BRIDGE
OVER Seven Mile 135’ P.C. Span/Span 1979 38’ $ 43.0 M 1,376,300 $31.20 Florida Keys FL DOT Figg Misener A. Moreton
WATER Engineering Marine Const.
BRIDGE
OVER Dauphin 118’-400’ P.C. Balanced 1980 85’ Clearance 102’ $ 13.0 M 166,666 $78.00 Alabama AL DOT Figg Brown & Root Figg
WATER Island Cantiliver Engineering Engineering
BRIDGE
OVER Niles Channel 118’ P.C. Span/Span 1981 38’ $ 7.7 M 175,600 $43.90 Florida Keys FL DOT Figg Michael A. Moreton
WATER Engineering Construction
BRIDGE
OVER Channel Five 135’0 P.C. Span/Span 1981 38’ $ 4.63 M 91,300 $50.70 Florida Keys FL DOT Figg Michael A. Moreton
WATER Engineering Construction
Latex Modif.
BRIDGE Columbia River 260’-450’ 70T C.I.P. Concrete WSDOT
OVER Bridges 450’-450’ Steel Piles Haunched Balanced Overlay 1981 3 main spans 63’-3" $ 23.8 M $ 22.7 M 236,555 $95.96 Richland WSDOT BRIDGE & Johnson Chuck Ruth
WATER @ Richland 260’ @End Piles Segmental Cantiliver After of 450’ each Washington STRUCTURES Bros
Grinding
BRIDGE Muskspan
OVER River 270’ C.I.P. Span/Span Latex 1982 46’ $ 4.6 M 44,160 $104.23 Big Rapids Michigan HNTB M.Miller
WATER Bridge Michigan DOT
219’-285’-
BRIDGE Columbia 480’-660’- C.I.P. Latex Modif.
OVER River at 660’-660’- Haunched Balanced Overlay 1984 49.3’ $19.3 M $ 15.9 M 165,726 $96.03 Umatilla WSDOT WSDOT Johnson Bros. J.A. Weigel
WATER Umatilla 480’-330’- Segmental Cantilever after Oregon
251’ Grinding
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST SUBMITTED
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER LOCATION OWNER DESIGNER CONTRACTOR BY
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT.
BRIDGE Centenial
OVER Memorial 540’ Spread C.I.P. Balanced Latex 1988 Cocur Idaho HNTB Maseman M.Miller
WATER Bridge Footing Cantiliver d’A’ens DOT
BRIDGE
OVER Baldwin Bridge 177’ - 275’ P.C. Balanced Overlay 1989 86’-0", $ 93.8 M $ 93.8 M 411,935 $227.71 Old Saybrook, Connecticut Parsons Perini/PCL/O&G P. Hartsfield
WATER Cantilever 76’-11" Connecticut DOT Brinckerhoff
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST TIME
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER ADJUST LOCATION OWNER DESIGNER CONTRACTOR
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT. COST
BRIDGE
OVER Bath-Woolwich 203'-420' 8' Diameter P.C. Balanced 1997 89' $ 46.6 M $ 42.1 M 221,647 $190.00 $194.84 Bath. Maine Maine DOT Figg Flatiron
WATER Drilled Shaft Cantiliver Engineering
BRIDGE Delaware
OVER Sailboat 122' 108" Drilled P.C. Span/Span 1998 2 @ 41'-4" $ 20.4 M $ 20.4 M 252,052 $80.90 $82.33 County OK DOT Figg Traylor Bros.
WATER Bridge Shaft Grand Lake Engineering
Oklahoma
BRIDGE 182'
OVER Putnam St. 322' 72" Drill C.I.P. Balanced Microsilica 1998 70' $ 11.1 M $ 7.9 M 48,000 $164.58 $167.49 Marietta Washington HNTB/Finley Kokosing
WATER 182' Shaft Cantiliver WS Ohio County McNary
Fender System
BRIDGE 164' Class V Cofferdam & Daytona
OVER Broadway to 48" & 60" P.C. Balanced Grinding 1998 Seal in Ftgs 48.4' $ 30.9 M $ 25.9 M 291,189 $89.04 $90.61 Beach FDOT Figg Misener Marine
WATER 262' Drill Shafts Variable Depth Cantiliver & Grooving Architectural Florida Engineering
Features
High Level
BRIDGE Memorial 84" Variable Depth Clearwater Florida HDR and PCL
OVER Causeway 168' to 360' Drilled Shafts CIP Balanced Grinding and 2001 VECP 112' 7" $ 47.02 M $ 29.54 M 263,445 $112.16 $112.16 Florida DOT JMI/Earthtech
WATER Cantilever Grooving
BRIDGE Ringling
OVER Bridge 300' 96" CIP-Pier Seg. Balanced Grinding and 2001 106' $ 76.0 M $ 56.0 M 328,255 $170.60 $170.60 Sarasota Florida JMI PCL
WATER Replacement Drilles Shafts PC-Other Seg. Cantilever Grooving Florida DOT
279.52
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST SUBMITTED
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER LOCATION OWNER DESIGNER CONTRACTOR BY
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT.
153.5’
VIADUCT SR- 90 DENNY 166-188’ NONE C.I.P. Span/Span 1981 52’ $ 11.4 M 187,351 $60.80 SR90 WSDOT Dickerhoff Hensel Phelps M.Myint Lwin
CREEK BRIDGE 166’-144’ Denny Creek & Widmann Construction
131.4’
Beiswenger
VIADUCT Ramp "I" Over 116’-224’ 18" PC P.C. Balanced Grinding 1982 42’-9" $ 4.97 M 91,271 $54.44 Dade County FDOT Hock and Capaletti Bros. L.M.Vargas
Fla. Tturnpike Cantiliver & Grooving Florida Associates
I-75/I-595 Beiswenger
VIADUCT Interchange 60’ - 206’ 18" PC P.C. Balanced Grinding 1984 42’-9" $ 27.10 M $ 8.77 M 251,680 $34.85 Ft. Lauderdale FDOT Hoch and Cianbro L.M. Vargas
Phase I Cantiliver & Grooving Florida Associates Corporation
VIADUCT Palmetto 84’ to 215’ P.C. Balanced 1984 $ 7.83 M 197,700 $39.60 Florida FDOT A. Moreton
Cantiliver
VIADUCT Airport 85’ to 162’ P.C. Balanced 1985 $ 5.29 M 124,500 $42.50 Florida FL DOT A. Moreton
Cantiliver
VIADUCT US 441 / I-595 124’ to 224’ P.C. Balanced 1986 $11.94 M 177,199 $67.10 Florida FL DOT A. Moreton
Cantiliver
VIADUCT French Creek 200’/210’ 66" drilled P.C. Balanced Bituminous 1987 33’-6" $ 2.78 M 44,220 $63.03 Glenwood HNTB Flatiron M.Miller
Viaduct shafts Cantilever Paving Canyon,CO.
Steel H &
VIADUCT Bridge F-08-3H 200’/210’ Drilled P.C. Balanced Bituminous 1987 33’-6" $ 7.12 M 113,700 $62.63 Glenwood HNTB Flatiron M.Miller
Caissons Cantilever Paving Canyon,CO.
Overlay Recchi
VIADUCT C & D CANAL 150’ P.C. 24" P.C. Span/Span and 1991 58’-4" $ 58.0 M $ 34.3 M 444,463 $71.17 Middletown, DelDOT Figg America Em.Rosiello
Bridge Grooving Delaware Engineering Inc
VIADUCT H3-North Halawa 350’ - 375’ CIHD C.I.P. Balanced Overlay 1991 Overhead 2 x 41’ /ea $ 149.4 M 479,000 $311.90 Honolulu,HI Hawaii DOT T.Y. Lyn Kiewit Pacific,Co. Paul Giuntini
Cantiliver Gantry International
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST SUBMITTED
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER LOCATION OWNER DESIGNER CONTRACTOR BY
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT.
450’ Engineering
VIADUCT LA River Bridge Segmental CIDH C.I.P. Balanced n/a 1993 Rail 27.5’ $ 13.4 M 38,913 $344.36 Los Angeles,CA Los Angeles Management Kiewit Pacific,Co. Paul Giuntini
140’ Cantiliver County, MTA Consultants
conv.falsework
Span/Span
VIADUCT US 183 Viaduct 135’ to 180’ P.C. & Overlay 1993 26’ - 58’ X 2 $ 71.3 M 1,300,000 $39.00 Austin, Tx TxDOT TxDOT Eby-Flatiron D. VanLanduyt
Balanced
Cantiliver
Greater
95’ Concrete Erected Cleveland
VIADUCT GCRTA Conrail 158’-139’-158’ Filled Pipe P.C. Balanced Rail Bridge 1994 over active 28’ $ 8.4 M $ 8.4 M 18,000 $465.00 Cleveland, Regional Parsons Kokosing Finley McNary
Bridge 95’ Piles Cantiliver N/A RR Ohio Transit Brickenhoff Construction Co. T. Stelmack
Authority
56’ WMATA
VIADUCT WMATA to P.C. 14" P.C. Span/Span n/a 1995 Narrow 32’-5" $ 44.0 M $ 10.2 M 84,940 $119.95 Washington WMATA Figg Recchi America, Em.Rosiello
Branch Avenue 150’ Curved D.C. Engineering Inc.
VIADUCT SR 87 Arizona 235’ to 405’ C.I.P. Balanced Overlay 1996 $ 7.0 M $145.00 Arizona AZDOT T. Y. Lin Edward T. Y. Lin
Cantiliver International Kreemer International
High Seismic
I-95 / US 95 92’ - 6" Span/Span Region Erected 26’ - 7"
VIADUCT Interchange to Drilled Shaft P.C. & Grooving 1997 over I-95 & & $ 92.0 M $ 24.0 M 253,270 $94.76 Las Vegas, NV Nevada Parsons Walter & SCI Finley McNary
(Spaghetti Bowl) 212’ - 6" Balanced US-95 Complex 38’ - 5" Superstr. Superstr. DOT Brickenhoff T. Stelmack
Cantiliver Geometry Only Only
100’ Appr.
I-205 Bridge Span Single 96" 1998 High Seismic 39,730
VIADUCT Portland Light 180’ Diameter Balanced Rail Bridge Design Region 34’ - 3" Total Portland, OR Tri-Met Finley Bechtel Finley McNary
Rail Airport 2 - 250’ Drilled Cantiliver n/a Build Erected over 29,455 McNary Infrastructure T. Stelmack
Max Extension 180’ Shafts I-205 Segmental
Span/Span
VIADUCT I-93 Viaducts 90’ to 204’ Drilled Shafts C.I.P. & 1998 22’ - 46’ $ 79.3 M 520,000 $152.00 Boston, MA Mass DOT Figg Modern Figg
and Ramps 7’ - 8’ - 9’ Balanced Engineering Continental Emgineering
Cantiliver
I-895
VIADUCT Main Line 192’ to 141’ H Piles P.C. Balance Microsilica 1998 57’ +/- $ 125.9 M $ 42.82 M 374,047 $114.47 Richmond VDOT Parsons Recchi America, C. Bellero
East - West Cantiliver Virginia Brickenhoff Inc.
Approach
VIADUCT I-895 135’ +/- H Piles P.C. Span/Span Microsilica 1998 30’ +/- $ 125.9 M $ 17.97 M 128,043 $140.34 Richmond VDOT Parsons Recchi America, C. Bellero
Ramps E, G, H Virginia Brickenhoff Inc.
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST TIME
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER ADJUST LOCATION OWNER DESIGNER CONTRACTOR
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT. COST
I-25/I-40 32'-6"
VIADUCT Interchange 150' --> 203' Drilled P.C. Balance Grinding 2000 & $ 222.0 M $ 26.60 M 321,290 $82.79 $82.79 Albuquerque NMSHTD URS Twin Mountain
Big I Shafts Cantiliver Grooving 42'-4" New Mexico Kiewit
Single
Palm Beach No Excuse Lane 40' Modern
VIADUCT International Airport 115' to 236' 24" Piles P.C. Balance Grinding 2000 Bonus 1030 Dual $ 110.0 M $ 50.0 M 500,979 $99.80 $99.80 West Palm FDOT BHA Continental
SR9/i95 Interchange Cantiliver days to Lane 58' Beach, Florida South
Complete
Jacksonville South 134' to 239 Ramp G-2 25' 6" $ 5.8 M 55,412 $105.74 $105.74 Parsons
VIADUCT Interchange 134' to 219' 24" Piles P.C. Balance Grinding and 2001 Ramp H-1 42' 6" $ 99.8 M $ 12.7 M 142,826 $88.85 $88.85 Jacksonville FDOT Transportation AMEC Civil
SR9A/i95/i295 144' to 246' Cantilever Grooving Ramp I-2 42' 6" $ 9.0 M 104,582 $86.25 $86.25 Florida Group
Ft. Lauderdale
VIADUCT Airport 120' to 220' 18" Piles P.C. Balance Grinding and 2000 Design-Build 55' Max $ 88 M $ 24 M 241,215 $99.00 $99.00 Ft. Lauderdale Broward BHA PCL
Interchange Cantilever Grooving Florida County
Demolition of
Viaducts/C09C1 Steel 16" Dia. Existing Struc. Massachusetts
VIADUCT I-93 / I90 and Drilled P.C. 1996 not included $ 108.6 M $ 27.64 M 138,400 $199.71 $214.12 Boston, MA Highway Modern
Interchange Shafts 9' in cost of new Department Continental
bridge
Viaducts/C009C4 Massachusetts
VIADUCT P.C. 1997 $ 17.6 M 43,250 $406.93 $436.28 Boston, MA Highway
Department
Viaducts/C009C2 Massachusetts
VIADUCT P.C. 1997 $ 45.7 M 130,800 $349.39 $374.59 Boston, MA Highway
Department
Tampa
VIADUCT Leroy Selmon Drill Shafts P.C. Span by Span 2002 Large wing $ 158.8 M Tampa Hilsborough Figg PCL Civil
Bridge Curved bottom Florida Xway Authority Engineering
and sides
Rev. 11/99 3
AMERICAN SEGMENTAL BRIDGE INSTITUTE
TYPE PROJECT SPAN TYPE C.I.P SPAN/SPAN OVERLAY YEAR SPECIAL BRIDGE TOTAL TOTAL SQ. FT. COST SUBMITTED
OF NAME RANGE OF P.C. BALANCE GRINDING BID CONDITION WIDTH COST OF COST OF OF PER LOCATION OWNER DESIGNER CONTRACTOR BY
BRIDGE PILE OTHER OTHER GROOVING PROJECT BRIDGE BRIDGE SQ. FT.
470’ Overlay
CABLE Talmage 1100’ Steel H C.I.P. Balanced and 1987 79’ $ ? M $ 34.0 M 161,160 $211.00 Savannah Ga DOT DRC Monterey-Groves B. West
STAYED Bridge 470’ Cantilever Grooving Georgia J.V.
Overlay
CABLE C & D CANAL 750’ P.C. 24" P.C. Cantiliver and 1991 58’-4" $ 58.0 M $ 17.7 M 95,497 $185.35 Middletown, DelDOT Figg Recchi America, Em.Rosiello
STAYED Bridge Construction Grooving Delaware Engineering Inc
Varies
2 Approach Over Total from
CABLE Foss 138’/148’ 9_’ - 12’ C.I.P. Falsework None 1994 water/urban 117.2’ $ 17.9 M $16.8 M 102,531 $164.50 Tacoma WsDOT Max J. Kuney J.A. Weigel
STAYED Waterway 375’/32’ Drilled Shaft Supported area to Washington
89.2’
625’
CABLE Sidney 1250’ 72" Diam. C.I.P. Balanced Grooving 1996 Two Rock Isl. 79’-6" $ 65.4 M $ 53.6 M 198,750 $269.95 Brunswick Ga DOT DRC Recchi/GLF B. West
STAYED Lanier 625’ Drill Shafts Cantilever Georgia J.V.