MINISTRY OF TRANSPORT AND GENERAL DIRECTORATE

INFRASTRUCTURE, REPUBLIC OF TURKEY OF HIGHWAYS

Kemal ÇETİN
Suspension Bridge Chief Engineer PUBLIC AND PRIVATE SECTOR
17 March 2022 PARTNERSHIP REGIONAL DIRECTORATE
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
North Marmara
Odayeri-Paşaköy
Kınalı-Odayeri Nakkaş-
Motorway
Motorway Başakşehir
(148 km )
(80 km ) (45 Km)
Edirne-İstanbul Kurt-Akyazı
Motorway Motorway
(170 km )
Marmara Motorway Ring, where
65% of our country's industry and
Marmara-Çanakkale
Motorway trade takes place
(89 km Main Road)
Kınalı-Malkara Motorway
(12 km Access Road) (89 km Motorway + 20 km Access Road)
(127 km)
Our 9 provinces (namely Istanbul, Kocaeli,
İstanbul-Ankara
Motorway
Sakarya, Yalova, Bursa, Çanakkale, Balıkesir,
Çanakkale-Balıkesir Motorway
(129 km Motorway + 7 km Access Road) Manisa and İzmir) that are interacting with the
(136 km)
Marmara Motorway Ring,
Gebze-Orhangazi-İzmir Motorway
(406 km Main Road + 42 km Access Road + 22 km
Constitute the
Bursa West Highway) 37% of the population,
(448 km)
38% of the number of Motor Vehicles,
75% of the exports,
79% of the imports,
65% of the GDP,
25% of the number of touristic overnight
Marmara Motorway Ring is 1.255 Km accommodations, and
Menemen-Aliağa-Çandarlı 43% of the number of commercial enterprises
Motorway
(56 km Main Road + 40 km Access
Put into operation : 846 Km of our country.
Road)
(96 km) Construction works in progress : 146 Km
Not tendered : 263 Km
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
• Project Length : 101 Km. (89 Km Motorway+ 12 Km Connection Road)
• Tender Date : 26 January 2017
• Contract Date : 21 March 2017
• Commencement Date of the Work : 31 March 2017
• Contract Period : 16 Years 2 Months 12 Days (Construction + Operation)
(5 Years 6 Months Construction + 10 Years 8 Months 12 Days-Operation)
• Total Investment Amount : 10.354.576.201,85 TL (2.537.450.977,97 €) Suspension Bridge: % 69
Motorway : % 31
• EPC Contractor : Daelim – Limak – SK - Yapı Merkezi O.G.
• Appointed Company : Çanakkale Otoyol Yatırım ve İşletme A.Ş. (ÇOK A.Ş.)
• Consultant Firm : Tekfen Mühendislik A.Ş. – T Engineering International SA O.G.
• Completion Date of Work : 16 September 2023 Construction / 28 May 2034 Operation
CONTRACT END OF OPERATION
TODAY 18 March 2022 (Target)

CONSTRUCTION PERIOD CONSTRUCTION PERIOD

TENDER CONT. VALIDITY COMPLETION DATE


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
HIGHWAY : 89 KM 40 km shortening in contras
ACCESS ROAD : 12 KM D with the current
TOTAL : 101 KM

ROUTE - 1
ROUTE - 1

ROUTE – 1 : 115 KM MOTORWAY : 75 KM ROUTE – 2 : 93 KM


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Location of the Suspension Bridge


(Km: 181+000 – 185+000)

SÜTLÜCE ŞEKERKAYA
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE OTOYOLU
MALKARA-ÇANAKKALE KESİMİ (1915 ÇANAKKALE KÖPRÜSÜ DAHİL)
No Bridge Name Opening Photo Country Main Span(m)
Türkiye
1 1915 Çanakkale Köprüsü 2022 2.023
Japonya
2 Akashi Kaikyo Köprüsü 1998 1.991
Çin
3 Yangsigang Yangtze River 2019 1.700

Çin
2019
4 Nansha Köprüsü 1.688

Çin
5 Xihoumen Köprüsü 2009 1.650

Danimarka
6 Great Belt Köprüsü 1998 1.624

Türkiye
7 Osmangazi Köprüsü 2016 1.550
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
GENERAL CHARACTERISTICS OF 1915 ÇANAKKALE BRIDGE
4.608 m
3.563 m
Europe Tower Asia Tower
770 m 2.023 m 770 m
Side Span Main Span Side Span
Main Cable Hanger Rope
EUROPE ASIA

365 m 680 m
Deck
EuropeEurope Approaching Viaduct Asia Approaching Viaduct
Europe Tower Foundation Asia Tower Foundation
Anchor Asia Anchor
- 37 - 45
1.600 m x 70 m

Tower Height : 318 m (Water Elevation)


Arrangement of Spans : 770 m (Side) + 2023 m (Middle)+ 770 m (Side)= 3.563 m
Total Length : 4.608 m
Tower Foundation Depth :~37 m (Europe), ~45 m (Asia)
Navigation Width : 1.600 m (B) x 70 m (H)
Distance Between Suspension Ropes : 24 m
Traffic Lane (in both direction) : 3,65 m x 3 lane
Maintenance Way : 3 m (both sides)
Total Deck Width : 45,06 m (9 m including gaps)
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Europe Tower TOWER FOUNDATIONS Asia Tower

EUROPE ASIA
1915 ÇANAKKALE BRIDGE

Asia Anchor Block


Europe Anchor Block
Europe Tower Foundation Asia Tower Foundation

FOR BOTH TOWER FOUNDATION


TYPE OF
UNIT QUANTITY
MANUFACTURING
CONCRETE (m³) 64.260
REINFORCEMENT Ton 19.962
GRAVEL BEDDING (m³) 86.765

INCLUSION PILE Adet 368


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
DREDGING

Dredging Vessel

Seabed Dredging 102.942 m³


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
INCLUSION PILING WORK OF TOWER
FOUNDATION FOR GROUND REINFORCEMENT
Inclusion Piles

Piles Height
Minimum : 21,25 m
Maximum : 46,05 m
2,5 m
Height : 12.314 m
Weight : 18.074 Ton

Europe 203 Ea
Driving of Piles
Asia 165 Ea
TOTAL 368 Ea
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Gravel Bedding and Gravel Levelling for Tower Foundation

Europe 46.921 m³

Gravel Bedding Asia 39.844 m³

Total 86.765 m³
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
CONSTRUCTION OF DRY DOCK
Sheeting Pile Driving in Dry Dock Excavation in Dry Dock

Base-lean Concrete in Dry Dock Caisson Manufacturing in Dry Dock


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Caisson Manufacturing in Dry Dock

Europe Caisson Asia Caisson


- 9,50 m - 10,50 m

Europe (North) Asia (South)

(from Dry Dock to Wet Dock) (from Dry Dock to Wet Dock)
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Caissons Towing Operation From Dry Dock to Wet Dock


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Caisson Construction in Wet Dock

Europe Asia
No. of Caisson : 1 No. of Caisson : 1
Caisson Dimension : 74 m x 83,30 m Caisson Dimension : 74 m x 83,30 m
Concrete : 14.239 m³(including plinth and tie-beam) Concrete : 14.766 m³ (including plinth and tie-beam)

Reinforcement : 2.817 Ton (including plinth and tie-beam) Reinforcement : 2.971 Ton (including plinth and tie-beam)

Floating Depth : 10,23 m (from Wet Dock to final locations) Floating Depth : 11,37 m (from Wet Dock to final locations)
Floating Weight : 61.985 ton Floating Weight : 66.318 ton
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Dry Dock - Final Position : 4.2 Km
Buoyancy Weight : 61.985 Tons
Europe Anchor Europe Caisson
Block Foundation Buoyancy Depth : 10.23 m
Water Used for Immersion : 72.000 m³

Asia Caisson Foundation


Dry Dock
Wet Dock

1915 Çanakkale Bridge


Asia Anchor Tower Caisson
Block
Foundation European Tower Caisson Immersion (08 – 10 May 2019)
Placement on the
Dry Dock – Final Position : 5 Km Seabed
Buoyancy Weight : 66,318 Tons realized between 5 and
Buoyancy Depth : 11.37 m 7 cm.
Amount of water required for immersion : 80.000 m³ (20 cm according to the
standards)

Asian Tower Caisson Immersion (24 – 26 May 2019)


Placement of the caissons in their final positions by immersion
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Plinth Weight : 1.100 Ton


(Steel Mold+Reinforcement+Anchorage Frame)
PLINTH AND TIE-BEAM

Tie Beam
Reinforcement : 453 Ton + Concrete : 794 m³
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
+334.00
Tower Bevelled Section Specifications
TOWERS
+313.50
32.Blok Bottom Section : 11.0 m x 10.5 m Bottom Top
Crossbeam Cross-section Cross-section
Top Section : 8.0 m x 7.5 m
Saddle Elevation: 318 m
418 m EUROPE TOWER

No. of Tower Block: 32 (1 Tower) (128 Block + 6 Tie Beam)


+221.00
Total Tower Fabrication : 2 x 18.120 ton = 36.240 Tonnes
Crossbeam
Tower Block Weight: Vary between 200 Ton and 770 Tonnes
Lifting by Panel
(Tower Crane)

Tower Block Height: Vary between 7,040 m and 11,67 m


318 m
334 m
371 m

+130.00

Crossbeam

+72.842
(Floating Crane)
Lifting by Block

TABLİYE

+9.90
0.00
Sea Elevation
TOWER
-40.00 -37.00
FOUNDATION

-84.00
WELDING TOTAL BOLTS
49 Ton ~ 7.000 m 720.000 Ea
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
ANCHOR BLOCKS
Europe Asia

1915 ÇANAKKALE BRIDGE

Europe Tower Foundation Asia Tower Foundation


Europe Anchor EUROPE ANCHOR ASIA ANCHOR Asia Anchor
WORK ITEM UNIT QUANTITY ACTUAL %'Sİ WORK ITEM UNIT QUANTITY ACTUAL %'Sİ
EXCAVATION (m³) 165.640 165.640 100 EXCAVATION (m³) 150.227 150.227 100
CONCRETE (m³) 68.845 68.453 99 CONCRETE (m³) 92.191 91.793 99
REINFORCEMENT Ton 6.400 6.336 99 REINFORCEMENT Ton 10.832 10.724 99
Total Structure Weight: 165.228 Tons Total Structure Weight : 221.258 Tons

13,00 m 16,00 m
16,00 m

The European Anchor Block has been fabricated at a depth of 16 m from the The Asian Anchor Block has been fabricated at a depth of 29 m from the natural
natural ground level and has been buried into the ground at the height of a 5- ground level and has been buried into the ground approximately at the height of
storey apartment building. a 10-storey apartment building.
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Elastomeric Wrapping MAIN CABLE
Cable Wrapping

PPWS

Strand

PPWS Main Cable Specifications


Tensile Strength 1,960MPa

147 148 Wire Diameter 5,75 mm


145 146
Main Span: 86,9 cm
Side Span: 88,1 cm

No. of wire in strand 127 Adet

No. of Strand 144 (Ana) / 148 (Yan)

Cable Diameter
869 mm - 0,488 m²
(Main Span)
Cable Diameter
881 mm - 0,501 m²
(Side Span)
Cable Weight 33.268 Ton
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
DECKS
45,06 m
22,53 m 22,53 m
Askı halatı 19,00 m 19,00 m Askı halatı
3,65 m 3,65 m 3,65 m 4,50 m 4,50 m 3,65 m 3,65 m 3,65 m
0,585m

0,585 m
0,50 m

0,585 m
1,00 m
mm
1,00 m

0,90 m
0,585
0,90

0,50
m

3,00 m 3,00 m
9,00 m
3,50 m

6,95 m 6,40 m 5,65 m 5,65 m 6,40 m 6,95 m

No. Of Segment (ea) SEGMENT WEIGHT (TON) TOTAL WEIGHT (TON)


153 320 (Appr.) 49.000
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Bridge Deck Slab Assembly


One of the Largest Floating Cranes of the World, Portal Crane
with a Height of 106 m, a Width of 52 m, and
a Bearing Capacity of 5,000 Tons:
ASIAN HERCULES

Side Span First Deck Slab Assembly : 17.06.2021 Mid-Span First Deck Assembly : 20.07.2021
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Loading, Moving and Positioning of the Deck

Transporting of the block to the bridge axle by barge, and positioning of it under the suspension cable to which the deck shall be moored, by means of the
dynamic positioning feature of the barge.
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Bridge Deck Assembly Works


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)

Bridge Deck Assembly Works


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION ( INCLUDING 1915 ÇANAKKALE BRIDGE)
Stone Mastic Asphalt (SMA) Applications

Sand Blasting

Primer Coat

Mastic Asphalt
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)
1915 ÇANAKKALE BRIDGE TOWER CAISSONS
WHEN THE 1915 ÇANAKKALE BRIDGE
TOWER CAISSONS ARE COMPARED IN
74 m TERMS OF AREA

67,5 m

105 m
83,3 m
CAISSON
(7,1 Decare)

Dry Dock Manufacturing Area: 250 m x 180 m: 45 Decares


Tower Caisson Dimension: 83.3 m x 74 m: 6.2 Decares
Area of 1 Caisson is ~ 1 Football Field in size.
Football Field
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)
WITH IT’S MAIN WIRE LENGTH OF 162.000 km ON MAIN CABLE (PPWS)

It can be
wrapped
around the
Earth 4 times

Circumference of the Earth: 40.075 km


KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)

During the placement of the upper tie beam of the 1915 Çanakkale Bridge Towers,
based on the weight (155 tons) / height (318 m) parameters, the largest heavy lifting operation in the world has been carried out.
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)

WITH ITS MAIN SPAN OF 2,023 m, IS THE LONGEST SUSPENDED BRIDGE IN THE WORLD
The middle span of 2,023 meters between the two steel towers of the Suspension Bridge
marks the 100th Anniversary of our Republic.

2.023 m
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)
WITH THE HEIGHT OF 318 m,
IS THE SUSPENSION BRIDGE WITH THE TALLEST TOWER IN THE WORLD
16 m

318 m
334 m

The 318-meter steel towers of the Suspension Bridge refer to 18 March 1915, the
date of the Çanakkale Victory, which is of great importance in terms of both Turkish and
World History.
KINALI-TEKİRDAĞ-ÇANAKKALE-SAVAŞTEPE MOTORWAY
MALKARA-ÇANAKKALE SECTION (INCLUDING 1915 ÇANAKKALE BRIDGE)

The red and white color of the towers represents the Turkish Flag.
MINISTRY OF TRANSPORT AND GENERAL DIRECTORATE
INFRASTRUCTURE, REPUBLIC OF TURKEY OF HIGHWAYS

THANK YOU