Professional Documents
Culture Documents
Contents
1 General ........................................................................................................................ 1-3
2 Structure ...................................................................................................................... 2-1
2.1 Structural System ................................................................................................. 2-1
2.2 Axis ...................................................................................................................... 2-3
2.3 Cross-Section ....................................................................................................... 2-3
2.3.1 Cross-Section of the Main Girder ................................................................. 2-3
2.3.2 Cross-Section of the Piers ............................................................................. 2-3
2.3.3 Define the Pylon Segment (‘Pier Segment”) Relative to ‘Main Girder
Segment’ ................................................................................................................ 2-3
2.3.4 Define the Cable Segments ........................................................................... 2-4
2.3.5 Export the Structure to RM .......................................................................... 2-4
3 Lesson 1: Construction of the Axis............................................................................. 3-1
3.1 Activating an Axis ............................................................................................... 3-1
3.2 Construction of the Axis in Plan View ................................................................ 3-2
3.2.1 Definition of a Starting Point and a Starting Direction ................................ 3-2
3.2.2 Definition of a Straight Line ......................................................................... 3-2
3.3 Construction of the Axis in Elevation (Vertical Projection)................................ 3-3
4 Lesson 2: Definition of Cross-Sections ...................................................................... 4-1
4.1 Definitions ........................................................................................................... 4-1
4.1.1 Construction Lines (CL) ............................................................................... 4-1
4.1.2 Cross-Section ................................................................................................ 4-1
4.1.3 Cross-Section Elements ................................................................................ 4-1
4.1.4 Parts .............................................................................................................. 4-1
4.1.5 Reference Point ............................................................................................. 4-2
4.1.6 Reference Points Definition .......................................................................... 4-2
5 Lesson 3: Definition of the Segments ......................................................................... 5-1
5.1 Main Girder Segments ......................................................................................... 5-1
5.1.1 Creating the Main Girder Segment ............................................................... 5-1
1 General
The items that are required for defining the structural system for this example are briefly
described in this introduction to GP.
Definitions:
an axis The geometry defining the road centre line layout.
a cross-section A typical concrete box section will be defined.
a segment Different logical units of a bridge could be assigned to the
same segment. i.e. If the type of deck cross-section
changes (say Tee beam to Box girder) only one segment
is required.
the structural model The complete structural model will be defined – ready for
load application and analysis using RM.
The three-dimensional bridge axis (or stake line) is defined in the horizontal and vertical
projections.
The distance measured along the axis is called the station.
The portion of the axis that contains the bridge girder is sub-divided into segments.
The segments are be sub-divided by segment points.
The cross-section is assigned to the segment.
The structural system of the bridge is defined by the axis together with the cross-section
and segment definitions.
The portions between the segment points will be transformed into elements and segment
points will be transformed into nodes when the data is imported into RM.
The minimum requirement for a structural system comprises one axis, one segment and
one cross-section.
There are no limits for the maximum definition.
The current example consists of one axis, one 440m long segment for the main girder,
further segments for each pier and the pylon and segments for each cable. The cross-
section of the main girder (MG) is a hollow-box of steel the cross-sections of the piers
are box girders of concrete.
2 Structure
85
Elem 101 – 111 Elem 112 - 155 Elem 156 - 199 Elem 200 - 210
38
44 176 176 44
18,0m
3,5m 11,0m 3.5m
0.6m 5,5m 5,5m
0.6m 0.15m
1.8m
2,5m 2,65m
0.85m 0.3m
0.5m 0,5m
1.4m
2.2 Axis
Define the project axis in both plan and elevation.
This procedure is quite straight forward and is described in detail in the GP ‘Getting
Started’ manual as well as (though more briefly) in the Cable Stayed Bridge training
example (now available to all RM users)
2.3 Cross-Section
Prepare of all the cross-sections for the project – deck, pier, pylon etc.
Define all the additional points required in the cross-sections for the analysis (such as
stress points, connection points, temperature distribution, reinforcement etc..). The defi-
nition of these additional points is described in detail in the GP ‘Getting Started’ Man-
ual.
Note: Each stay cable must be individually connected to the pylon and the deck via ‘Connection Points’.
The deck cross-section and the pylon cross-section must therefore have connection points
defined in the appropriate positions for these cables.
2.3.3 Define the Pylon Segment (‘Pier Segment”) Relative to ‘Main Girder
Segment’
Assign the pylon cross-section to the pylon segment.
Define the variable dimension tables for the pylon cross-section and define the element
and node numbers for the pylon segment.
Define the connection between the pylon and the deck (New Spring) and between the
pylon and the ground (New Spring-0).
Figure 3-5. Displayed picture of the vertical axis definition for the main girder.
By clicking on the icon shown on the left you can switch between graphic and table
view of the axis.
This window is an information window - parameters cannot be changed here. The last
element is always a point that is generated automatically by the program.
The cross-section list window opens blank as no cross-sections have been defined yet.
A new cross-section definition is started by selecting the ‘insert’ button at the top
left hand side of the main screen. Before clicking <OK> to create a new cross-
section assign a name or accept the default name (‘cross1”).
Confirm the selection by clicking <OK> - the cross-section will then be activated.
4.1 Definitions
4.1.2 Cross-Section
The geometry of a cross-section is defined by connecting intersection points of con-
struction lines to outline the cross-section elements. Each cross-section is partitioned
into elements.
4.1.4 Parts
Elements of the cross-section with different properties can be grouped into parts. For
example these parts can be used for composite cross-sections. In the current example the
cross-section consists of one part.
Figure 4-1. Input window for the definition of a cross-section including all reference and control points.
The distances of Construction lines which represents the basis of the element definition
can be defined as fixed values in the input field ‘Variable’ or as variables in the ‘varia-
ble list’ by clicking on the arrow. To the specified values of these variables, given by
the user, (e.g. variable height of the cross-section) later formulas resp. tables can be as-
signed easily (see chapter 5.1.2.3 and chapter 5.1.2.4).
Figure 5-7. Input window for creating a new segment (Type ‘Pier’).
If the defined angle of the pier is accepted with 0.000 the pier stays exactly vertical. In
the lower part of the input window (marked with the red ellipse in Figure 5-7) the geo-
metric position of the connection of the pier to e.g. the ‘main girder” has to be specified.
By selecting the reference segment (main girder), the segment point where the pier
segment should be insert (segment point 12) as well as the connection point in the cross-
section of the reference segment (cp0, see Figure 5-8). This presumes that a connection
point in the cross-section of the main girder has been already defined. Geometrically
now the pier is connected with the main girder segment. This procedure can be repeated
for a all new pier segments.
Cable1 Cable2
Cp1 Cp2
Cp0
Figure 5-8. Defined connection points in the cross-section of the main girder.
Main girder
cp0
Position 1 Position 2
Figure 6-2. Definition of support springs within the cross-section of the main girder.
The spring 1100 is a spring to earth. It goes from node ‘0’ to a new defined free node
1100. From this node two spring elements 1101 and 1102 are defined. They are posi-
tioned at the connection points cp1 and cp2 (see Figure 5-8) and have an eccentric con-
nection to the structural node 101.
7 Export to RM
This is the final step in a GP session. Geometric data which is generated in GP is ex-
ported into the RM data base according to some basic rules which can be specified in
the input-window shown in Figure 7-1.
You can choose if you want to export the complete project or only cross-sections or the
active segment instead of all.
There also exists the possibility to export a *.tcl file that has been created e.g. for the
definition of a series of cross-members by activating the check box.
See RM for more information.