Professional Documents
Culture Documents
Access to this document was granted through an Emerald subscription provided by emerald-srm:126209 []
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for Authors service
information about how to choose which publication to write for and submission guidelines are available for all. Please
visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company manages a portfolio of
more than 290 journals and over 2,350 books and book series volumes, as well as providing an extensive range of online
products and additional customer resources and services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the Committee on Publication
Ethics (COPE) and also works with Portico and the LOCKSS initiative for digital archive preservation.
Introduction
construction projects during the past years. The increase necessitates the use of proper
and innovative project management techniques to handle the challenges and the risks
create a unique product, service or result (PMBOK, 2013). Project management aims to
deliver the construction project on time, within budget while meeting or exceeding
customer expectations. One way to achieve the delivery of the project at the required
completion date and with the least cost is by the use of the least-cost scheduling
Time-cost trade-offs are one of the most frequent and critical decisions that
project managers usually make. Project managers are frequently required to make time-
cost trade-offs (Liu and Rahbar, 2004). Time-cost trade-off refers to the method where
the project duration is shortened with a minimum added cost (Hegazy and Menesi,
general, project time and cost are linked via a relationship. As the project time is
shortened, the direct cost of critical activities increase, while the indirect cost
(overheads) of the project decreases. When there is a need for crashing the activities and
accelerating project completion, Larson and Gray (2014) mention several options based
on the resources constraints. Options when resources are not constrained include
1
work, or adding additional resources such as extra labors or extra machineries. On the
other hand, the available options when resources are constrained can include reducing
the overall scope of the project, or go with the fast tracking option by changing the
logical relationships between the activities in a way that the critical activities are
Optimizing the project’s duration while maintaining the least crashing cost is
usually needed in order to complete the project activities earlier than originally
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
scheduled or to meet the project deadline with the least additional cost (Larson and
Gray, 2014). When the project duration is reduced, the total float available for
deterministic procedure that is carried out until an optimum value is reached (Hinze,
2012). Available time-cost optimization methods are based on the concept of shortening
the duration of the critical activities in the network progressively while observing the
decrease in total project cost until the optimal solution that provides the shortest project
duration with the minimum total cost is reached (Hinze, 2012). The deterministic
optimization technique doesn’t consider the impact of the float loss within the
noncritical activities when the project duration is being crashed or reduced. Such losses
in total float can impact the project cost and schedule, and may lead to delays in
activities that are in a path; causing a ripple effect on the downstream activities of that
path; and therefore, losing the chance of early finish for these activities.
2014). Project risk management is an important topic for practitioners and academic
2
scholars (Zhang, 2016). Risk assessment is an integral part of project risk management
performed using Monte Carlo Simulation (MCS). When a project is scheduled, the
normal schedule will have certain risks that are measured by the probability of
completing the project on time. As the project duration is shortened, to reduce total cost,
the float is lost resulting in more critical or nearly critical activities. This, in turn, results
in reducing the probability of completing the project on time and increases the risk of
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
schedule delays. There is a need to incorporate that extra risk into the time-cost trade-
off problem. This will result in a more reliable project schedule. This paper proposes a
new framework that incorporates such impact into the time-cost trade-off process.
There are several time-cost trade-off techniques that were developed over the past years.
The traditional time-cost trade-off technique is based on the Critical Path Method
(CPM). Time-cost optimization is based on the idea of shortening the critical activities
with the minimal increase in cost per unit of time (Charoenngam and Popescu, 1995).
Hinze (2012) explained a logical method for crashing that considers the schedule
network as a rigid frame. This technique is based on the use of link lag values that helps
in determining the possible number of times the activity can be crashed. Maximum
3
Deckro et al., 1995, Islam et al., 2004; Chassiakos & Sakellaropoulos, 2005), Non-
linear programming (Klansek & Psunder, 2008), and mixed integer programming (Liu
et al., 1995; Moussourakis & Haksever 2007). Ammar (2011) developed a nonlinear
optimization model for project time cost tradeoff with discounted cash flow.
look for meta-heuristic techniques that can be used to determine the near optimum
solution in less time. Genetic Algorithms (GA) were used by Li & Love (1997), Leu &
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Yang (1999) and Que (2001). Fuzzy logic was used by Castro-Lacouture et al. (2009) to
incorporate the time-cost trade-off into the schedule assuming linear fuzzy relations.
Zahraie and Tavakolan (2009) used fuzzy genetic algorithms and fuzzy sets to solve the
include the use of ant-colony optimization (Ng & Zhang, 2008; Afshar et al. 2009),
Tabu search (Hazir et al. 2011), particle swarm optimization (Zhang & Li, 2010 and
Yang, 2007), Harmony search (Geem, 2010) and simulated annealing (Sonmez and
Bettemir, 2012). Few authors considered risk in the time-cost trade-off problem. There
al. 2008). Feng et al. (2000) developed a stochastic time-cost trade-off approach for
construction projects. Isidore & Back (2001) proposed an improved model in which
variability of activities in terms of cost and time is taken into consideration. Yang
developed a stochastic time-cost optimization model using fuzzy sets. Al Haj and El-
Sayegh (2015) developed a new model for time-cost optimization considering float
4
calculate the float consumption impact. In this paper, the float loss cost is calculated
The float is a measure of the schedule flexibility. Total float can be defined as the
amount of time an activity can be delayed without delaying the project. On the other
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
hand, the free float can be defined as the amount of time an activity can be delayed
without delaying the immediate successor activity (Charoenngam and Popescu, 1995).
Total float should be distinguished from free float as total float belongs to the activities’
path (it is shared by all the activities in the same path), while the free float belongs to a
particular activity. Since free float can’t be shared within the activities, its importance
compared to the total float is limited. Free float can be useful when selecting activities
for resource leveling. As float is a key element in project scheduling, several studies
were raised over this topic over the years. Ziegler (1985) introduced the minimal and
maximal float concept. The concept of minimal float represents the float present in
“worst case” while maximal float represents the float available in the “best case”
(Ziegler, 1985). Gong (1997) developed a method to find the optimum float use in a
project network. Optimum float was defined as the “point at which the sum of the cost
resulting from float use and the cost resulting from project delay due to float use is the
lowest (Gong, 1997). Sakka & El- Sayegh (2007) developed a method to control the
risks associated with the float loss due to delays in construction projects and its effect
on noncritical activities.
5
Float ownership has been subject of debate over the last decades. Wickwire et
al. (1999) recognized that the float is an expiring resource that doesn’t belong to any
party but at the same time it is available to be used by the project parties on a fair basis.
Several approaches can be used in the construction industry to allocate float. Ponce de
Leon (1986) recommended that the total float of each activity is represented as a bar in
the bar chart to observe the critical and noncritical path delays. Householder and
Rutland (1990) developed the contract risk approach where the float is owned by the
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
party that assumes full responsibility for the project risk. De La Garza et al. (1991)
emphasized that the total float should be treated as a commodity that is traded between
the owner and the contractor. Gong and Rowings (1995) introduced the concept of safe
float to project scheduling. This method specifies the range of safe float to be used by
the project parties in general so as to logically minimize the risks associated with delays
(Gong and Rowings, 1995). De la Garza et al. (2007) recommended that the total float
is distributed between the project parties based on a pre-agreed ratio to be stated in the
contract clauses. Al-Gahtani (2009) developed the total risk approach to assign the float
Al-Gahtani and Mohan (2005) emphasized that the float on noncritical activities
leads to efficient resource utilization. The amount of float is essential for resource
leveling and time-cost trade-off (Ammar, 2003). Gong (1997) emphasized that floats
are considered as safe harbor for resource allocation and other purposes without causing
a negative impact on the project duration. Al-Gahtani and Mohan (2005) stated that
each day of the total float available to a contractor is real money. De la Garza et al.
6
(1991) recommended having a trade-in value for float while Gong (1997) recommended
limiting the use of float to reduce the risk of schedule overruns. Sakka and El-Sayegh
(2007) proposed a framework for quantifying the float loss impact on project time and
cost.
The float loss impact is not easily identified as a quantitative value unless the
schedule delay risk due to crashing is realized. During time-cost trade-off, critical
activities are crashed to reduce the project duration. As the project duration is reduced,
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
the float of non-critical activities is also reduced. The probability of completing the
project on time is also reduced. If we keep the probability constant, we get a new
duration. The difference between the new duration and the crashed duration represents
the impact of float loss. Then multiplying that difference by the indirect cost per day
will give us the float cost for each crash. For stochastic schedule analysis, the software
@Risk (an add-on to Microsoft Excel) is used to perform Monte Carlo Simulation
(MCS). To use the software, the project network needs to be modeled in Excel with
assumed that all activities follow normal distribution functions with means and standard
deviations. However, the activity duration can be any distribution that the project
manager sees fit. Additionally, there is a need to specify the number of iterations. In this
research, we used 10,000 runs. However, the project manager may choose different
number of simulation runs as appropriate to the size of the project. For large projects,
simulation runs.
7
The proposed method for calculating float cost can be explained using a simple
example. Assume that the normal deterministic project duration is 40 days. Considering
the risks, the mean duration and standard deviation is 41.39 days and 4.9 days,
respectively (after running MCS on the normal schedule). The probability of completing
distribution). If the project is shortened by one day, the new duration is 39 days.
However, the probability of completing the project on time (within 39 days) is reduced
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
to 0.349 (after running MCS on the crashed schedule). This reduction represents the
added risk due to crashing and the resulting float loss. If the project manager wants to
39.52 days. Thus, the difference is 0.52 days. Assuming that the indirect cost is $2,000
per day, the resulting extra cost due to increased risk (float loss) is $1,045.
As the project duration is shortened, the available float for non-critical activities is
reduced which increases the risk of not completing the project on time. A new
framework is proposed that enables calculating the effect of this float loss and includes
its effect in the trade-off process. Figure 1 illustrates the framework steps via a
flowchart. The calculations are performed in two stages: normal schedule analysis and
8
In stage 1, the normal deterministic schedule analysis is performed in order to calculate
the deterministic duration, determine the critical path and non-critical activities. This is
followed by performing the stochastic analysis through the use of Monte Carlo
Simulation (MCS) for 10,000 runs. The mean project duration and its standard deviation
are then determined. The probability of finishing the project within the deterministic
Schedule compression analysis is performed through several cycles of crashing until the
optimum duration (associated with the minimum total cost) is reached. The number of
cycles depends on the project’s size and complexity. During each crashing cycle, all
critical activities are evaluated to select the activity that has the least impact on project
cost. The impact on project cost includes the extra direct cost due to crashing in addition
to the extra cost associated with float loss. This means that for each crashing cycle, the
For each crashing cycle (i), there is a need to determine the activity associated
with the least impact on the total project cost. For each critical activity (j) that can be
a) Shorten the duration of activity (j) by one day and calculate the new
b) Perform stochastic analysis over the new crashed network by running Monte
9
c) Find the new mean duration (Mij) and standard deviation (Stdij). Also, find
the new probability of finishing (POFi,j) the project within the new
should drop due to the float loss associated with shortening the project
duration.
d) Fix the probability of finishing to the value obtained in the previous cycle
This duration represents the desired duration without increasing project risk.
This is calculated using the probability of finishing at the previous step and
the Mean (Mij) and Standard Deviation (Stdij) found after the new simulation
probabilistic duration and the new deterministic crashed duration at this step
Where;
FLDij = Float loss impact in terms of days for crashed activity j at cycle i.
f) Calculate the Float Loss Cost (FLC) using Equation 2. Equation 2 represents
the float loss cost as a product of the duration difference and the cost
10
FLCij = FLDij x CSPD (2)
Where;
g) Add the float cost to the extra direct cost to find the new total extra cost
h) Steps (a) through (g) are repeated for all identified critical activities. The
activity with the least total extra cost will be crashed at this point.
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
on time of the previous cycle minus the new deterministic duration of the
j) Steps (a) through (i) are repeated progressively until reaching the optimum
solution
If two or more critical paths are available, the following steps must be undertaken:
b) Perform the same steps that were performed when one critical path has
occurred while considering all possible cases occurring, then compare the
impact
11
Application example project
An example project (adopted from Hinze (2012)) is used to explain the proposed
framework. The first part explains the deterministic approach to compute the optimum
project duration and total cost and the minimum project duration and its associated total
cost. Three cycles are needed to reach the optimum project duration, while two extra
cycles are needed to reach the least project duration. The optimum project duration is 23
days with an associated cost of $12,490, while the minimum project duration and its
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Table I presents the project data in terms of durations and costs. The indirect
cost is assumed to be $280 per day. The last two columns; duration mean and duration
standard deviation, are added to Hinze (2012) example in order to use them in the
stochastic analysis.
This section presents the solution cycles using normal deterministic project compression
without considering the effect of float loss. Based on the baseline schedule network
total project cost of $12,860 that consists of a direct cost of $5,300 and indirect cost of
12
For the first crashing cycle (cycle 1), the least expensive activity to expedite is F;
therefore, the decision is to expedite F by 2 days. The new project duration is 25 days
and the new critical path is A, B, F, H, K. The new total cost is calculated as follows:
• New Direct Cost = Direct Cost + Crashing Cost = 5,300 + (2*150) = $5,600
• New Indirect Cost = Duration * indirect cost per day= 25 * 280 = $7,000
• New Total Cost = Direct Cost + Indirect Cost = 5,600 + 7,000 = $12,600
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
cycle 4, activities B& C are crashed by 2 days each. In cycle 5, activity K is crashed by
1 day. Table II illustrates the crashing results performed over cycles zero to five.
Figure 4 illustrates the total project cost vs. duration curve. It can be noticed that the
optimum project duration and total cost are 23 days, $12,490 respectively. Afterwards,
the total cost starts to increase until reaching the cost associated with minimum project
duration of 20 days.
Table III presents the total float available for noncritical activities at the end of each
cycle. Table III clearly shows the float loss associated with time-cost trade-off. For
example, the available float for activity D has dropped from 7 days to 1 day in cycle 5.
This reduces the schedule flexibility and reduces the chances of completing the project
on time.
13
<Insert Table III here>
This section presents the solution cycles using the new proposed stochastic compression
framework considering the impact of float loss within noncritical activities during the
crashing process. The normal schedule is shown in Figure 2. The project duration of the
baseline schedule is 27 days, with a direct cost of $5,300, indirect cost of $7,560, and
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
total cost $12,860. The critical path is A, B, F, H, and K. Using Monte Carlo simulation
for 10,000 runs on the normal schedule, the mean duration is calculated to be 28.1 days
with a standard deviation of 3.47 days. The probability of completing the project within
For cycle 1, the activities available for crashing are: B, F, H, K (activity A can’t
be expedited). Therefore, four crashing scenarios need to be checked to find the best
activity to crash. The first scenario is for crashing activity B by 1 day. After crashing
activity B by 1 day, Monte Carlo Simulation is performed on the crashed schedule. The
resulting mean and standard deviation after crashing activity “B” are 27.5 days and 3.4
days respectively. The probability of completing the project on time dropped to 32.93%.
This drop is due to the loss of float after crashing activity “B”. To calculate the effect of
the float loss and determine the new project cost, the following steps are followed:
According to Equation 1, the difference between the deterministic and the new
14
Float cost FLC1B is calculated according to Equation 2:
The same steps are followed for the other three scenarios namely crashing activities
“F”, “H” and “K” by one day each separately. The results are summarized in Table IV.
According to the total extra cost and total cost, activity F exhibited the least total extra
cost and total cost. Therefore, the decision is to expedite activity F by 1 day.
For cycle 2, the activities available to be expedited are: B, F, H, and K. Based on that,
four available scenarios need to be checked to find the best activity to crash. Table V
According to the total extra cost and total project cost, activity F exhibited the least total
extra cost and total project cost. Based on that, the decision in this cycle is to expedite F
by 1 day. For cycle 3, three available scenarios have to be checked to find the best
activity to crash at cycle three. The three scenarios include either crashing activity B or
15
<Insert Table VI here>
The best activity to crash in cycle 3 is activity “B”. However, the total Cost started to
increase at this cycle; therefore, the optimum project duration and total cost are 25 days
As per the example presented and solved earlier, the optimum duration considering float
consumption impact is 25 days, while the associated optimum total cost is found to be
$12,709. Table VII compares the remaining total float for the noncritical activities
between the deterministic compression method and the new proposed compression
framework.
It can be noticed that the new proposed compression model is better in terms of
remaining float as it finds an optimum solution that can save some total float for future
use. In terms of the probability of finishing the project on time, the probability of
finishing the project within 27 days is found to be 0.375. The probability of finishing
the project within 25 days when float loss impact is considered is 0.331, while the
probability of finishing the project within 23 days when float loss impact is not
considered is 0.237. It can be seen that when float loss impact is considered, the
probability of finishing the project is considerably higher than that when float loss
impact is not considered. Figure 5 compares the results between the optimum solution
16
found using deterministic approach (without float loss effect) and the optimum solution
found considering the float loss effect in terms of total cost curves.
From Figure 5, it is clear that the optimum project total cost considering float
consumption impact is higher than the optimum normal cost. The optimum project
duration, as well, is higher than that when float loss cost isn’t considered. The increase
in the project’s total cost of the curve considering float consumption impact is related to
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
the increase in the direct cost that accounts for the float loss cost in noncritical
activities. The framework presents a curve with a higher cost. The difference between
the optimum total cost when float is considered and the deterministic normal optimum
total cost is equal to $ 219, in this example. This higher cost, if paid, accounts for and
quantifies the float cost impact and can save dollars associated with risks resulting from
the loss of project flexibility. Decision makers or project managers, depending on the
nature of their projects, are free to choose between the two curves; whether to stick to
the normal compression method and bear the risk associated with losing total float, or
use the new curve and be on the safe side while maintaining a compressed schedule.
To best check the applicability of the developed framework, the framework was
tested against five examples selected from literature. The probabilities of finishing the
project on time using the developed framework in all five cases were better than those
using the classical deterministic optimization technique. Table VIII summarizes the
17
Summary and conclusions
reducing the available float for noncritical activities and thus increasing the schedule
risks. Existing deterministic optimization technique doesn’t consider the impact of the
float loss within the noncritical activities when the project duration is being crashed.
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
The proposed framework incorporates float loss impact into the time-cost trade-
off problem. The float loss impact is quantified using Monte Carlo Simulation by
determining the probability of finishing the project at each crashing cycle for each
activity and comparing the total extra direct cost (activity cost slope and float loss cost)
to select the activity that best exhibits the least total cost. As the project duration is
reduced, the available float of non-critical activities is reduced, and the probability of
finishing the project on time is also reduced. The framework measures the difference
between the probabilistic duration and the deterministic duration and translates this loss
The stochastic framework uses Monte Carlo Simulation to calculate the effect of
float loss on risk. This is later translated into an added cost to the trade-off problem.
Five examples, from literature, are solved using the proposed framework in order to test
the applicability of the developed framework. The results confirmed the research
hypothesis that the new optimum solution will be at a higher duration and cost but at a
lower risk compared to traditional methods. The probabilities of finishing the project on
time using the developed framework in all five cases were better than those using the
18
classical deterministic optimization technique. The results indicate that the proposed
framework reduces the risks associated with float loss. As seen in the example, the
probability of finishing the project on time was considerably higher when float loss
impact was considered. Although the optimum duration and cost are higher than those
obtained from traditional methods, the schedule risk is lower. The proposed framework
provides decision makers with a new tool to solve the time-cost trade-off problem with
the least possible risks associated with float loss. The proposed framework allows
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
project managers to determine the optimum project duration at the least cost and risk.
The traditional methods allow project managers to determine the optimum project
duration at the least cost but at a higher risk levels. So, the proposed framework allows
project managers to experience a three-way trade off between time, cost and risk. They
may choose the project duration associated with the minimum cost (ignoring float loss
cost) or they may choose a higher duration with a higher cost (higher than the optimum
This paper introduces a new concept to the time cost trade-off problem, which is
the incorporation of float loss impact. Previous researches on time cost trade off ignored
the effect of float loss that results from shortening the project duration. This research
attempts to fill that gap in literature. Future research may target developing other
19
Appendix A – Notation
FLDij: Float loss impact in terms of days for crashed activity j at cycle i;
STDij: Project duration standard deviation for cycle i after crashing activity j.
20
References
Al-Gahtani, K. (2009), "Float allocation using the total risk approach", Journal of
Construction Engineering & Management, Vol. 135, No. 2, pp. 88-95.
Al-Gahtani, K. and Mohan, S. (2005), “Total float management for delay analysis”,
AACE International Transactions, CDR.16.1-13.
Afshar, A., Ziaraty, A., Kaveh, A. and Sharifi, F. (2009), “Non-dominated archiving
multi-colony ant algorithm in time–cost trade-off optimization”, Journal of
Construction Engineering and Management, Vol. 135, No. 7, pp. 668-674.
Castro-Lacouture, D., Süer, G., Gonzalez-Joaqui, J., and Yates, J. (2009), “Construction
project scheduling with time, cost and material restrictions using fuzzy mathematical
models and critical path method”, Journal of Construction Engineering & Management,
Vol. 135, No.10, pp. 1096-1104.
Choudhry, R., Aslam, M., Hinze, J., and Arain, F. (2014). "Cost and Schedule Risk
Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines", J. Constr.
Eng. Manage., Vol. 140, No. 7, 10.1061/(ASCE)CO.1943-7862.0000857, 04014020.
21
De la Garza, J., Vorster, M. and Parvin, M. (1991), “Total float traded as commodity”,
Journal of Construction Engineering and Management, Vol. 117, No. 4, pp. 716-727.
Deckro, R., Herbert, J., Verdini, W., Grimsrud, P. and Venkateshwar, S. (1995),
“Nonlinear time-cost trade-off models in project management”, Computers ind. Eng,
Vol. 28, No. 2, pp. 219-229.
Feng, C., Liu, L. and Burns, S. (2000), “Stochastic construction time-cost trade-off
analysis”, Journal of Computing in Civil Engineering, Vol. 14, No. 2, pp. 117-126.
Hazir, O., Erel, E. and Gnalay, Y. (2011), “Robust optimization models for the discrete
time/cost trade-off problem”, International Journal of Production Economics, Vol. 130,
No. 1, pp. 87-95.
Hegazy, T. and Menesi, W. (2012), “Heuristic method for satisfying both deadlines and
resource constraints”, Journal of Construction Engineering and Management, Vol. 138,
No. 6, pp. 688-696.Hinze, J. W. (2012), Construction Planning & Scheduling, 4th ed.,
New Jersey, US: Pearson Prentice Hall.
22
Householder, J. and Rutland, H. (1990), "Who owns float?" Journal of Construction
Engineering & Management, Vol. 116, No. 1, pp. 130-133.
Islam, M. N., Rana, M. B., Rafique S., and Aziza T. (2004), “Crashing project time with
least cost: a linear programming approach”, Journal of business research, Vol. 6, pp.
13-28.
Larson, E. and Gray, C. (2014), Project Management: the Managerial Process, 6th ed.,
New York, US: McGraw-Hill Press.
Leu, S. & Yang, C. (1999), “GA-based multi-criteria optimal model for construction
scheduling”, Journal of Construction Engineering & Management, Vol. 125, No. 6, pp.
420-427.
Li, H. & Love, P. (1997), “Using improved genetic algorithms to facilitate time-cost
optimization”, Journal of Construction Engineering & Management, Vol. 123, No. 3,
pp. 233-237, 1997.
Liu, L., Burns, S., and Feng, C. (1995), “Construction time-cost trade-off analysis using
LP/IP hybrid method”, Journal of Construction Engineering & Management, Vol. 121,
No. 4, pp. 446-454.
Ng., S. and Zhang, Y. (2008), “Optimizing construction time and cost using ant colony
optimization approach”, Journal of construction Engineering & Management, Vol. 134,
No. 9, pp. 721-728.
23
PMBOK (2013), A Guide to the Project Management Body of Knowledge, Project
Management Institute Standards Committee, PMI.
Ponce de Leon, G. (1986), "Float ownership: Specs treatment", Cost Engineering, Vol.
28, No. 10, pp. 12-15.
Sakka, Z. and El-Sayegh, S. (2007), “Float consumption impact on cost and schedule in
the construction industry”, Journal of Construction Engineering & Management, Vol.
133, No. 2, pp. 124-130.
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Sonmez, R. and Bettemir, O. H. (2012), “A hybrid genetic algorithm for the discrete
time-cost trade-off problem”, Expert Systems with Applications, Vol. 39, No. 13, pp.
11428-11434.
Yang, I-T. (2007), “Using elitist particle swarm optimization to facilitate bi-criterion
time-cost trade-off analysis”, Journal of Construction Engineering and Management,
Vol. 133, No. 7, pp. 498-505.
24
Zhang, Y. (2016), “Selecting risk response strategies considering project risk
interdependence”, International Journal of Project Management, Vol. 34, No. 5, pp
819-830.
and a Ph.D. degree in construction Engineering and Project Management from Texas
A&M University, College Station, Texas – USA. He worked in project controls with
Institute (PMI).
Rana Al-Haj is a Civil Engineer and a LEED Green Associate Professional. She
has a M.S. degree and a BS degree in Civil Engineering from the American University
Department at Dar AL- Handasah Consultants (Shair and Partners) over Dubai
25
- Precedence Diagram
- PDF* of Activities Durations
Optimum
Stop Crashing YES Solution is NO Continue Crashing
reached?
PDF: Probability Distribution Function MCS: Monte Carlo Simulation Mij: Schedule Mean @ cycle i when activity j is crashed
Stdij: Schedule Standard Deviation @ cycle i when activity j is crashed POF: Probability of Finishing on Time
Ddet. ij: Deterministic Duration for Crashed Activity j at cycle i Dprob. ij: Probabilistic Duration for Crashed Activity j at Cycle i FLDij:
Duration Difference Between Dprob. ij Associated with the POF at the Crashing Cycle in Question & Ddet. ij Sj: Activity j Crashing Slope FLCij:
Float Loss Cost CSPD: Savings Per Day TC: Total Cost TDC: Total Direct Cost IDC: Indirect Cost
Legend ES Dur EF
Act TF
LS act DC LF
Cycle 0
Direct Cost 5300
Indirect Cost 7560
Total Cost 12860
Duration 27 days
C.P. A,B,F,H,K
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
1 7 8 8 3 11 15 7 22
B 0 E 4 H 0
1 1000 8 12 100 15 15 350 22
0 1 1 1 6 7 8 7 15 15 5 20 22 5 27
A 0 C 1 F 0 I 2 K 0
0 800 1 2 300 8 8 500 15 17 700 22 22 450 27
1 3 4 4 8 12 15 3 18
D 7 G 7 J 4
8 400 11 11 200 19 19 500 22
Figure 3
Cycle one – crashed schedule 1
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Figure 4
Total cost vs. duration
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Figure 5
Total cost vs. duration comparison
Table I Example project – normal and crash cost & duration
C 1 1 0 0 0 0
D 7 5 4 3 1 1
E 4 2 2 2 2 2
G 7 5 4 3 1 1
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
I 2 2 2 1 1 1
J 4 4 4 3 1 1
Table IV Simulation results for cycle 1
B F H K
B F H K
B H K
Probability of finishing
28.0318093% 28.79116% 31.605949%
within 24 days (%)
C 0 1
D 3 5
E 2 2
G 3 5
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
I 1 2
J 3 4
Table VIII Summary of the results of the tested five examples
Example One
(Isidore & 20 days $8,215 0.355 12 days $7,940 0.109 17 days $8,146.5 0.253
Downloaded by Florida Atlantic University At 04:59 11 March 2017 (PT)
Back 2001)
Example
Two
24 days $30,520 0.426 17 days $28,870 0.209 18 days $29,742.5 0.250
(Oxley &
Poskitt 1996)
Example
Three
20 days $2,044,000 0.342 16 days $1,990,000 0.122 18 days $2,020,269.525 0.204
(Zeinalzadeh
2011)
Example
Four
59 days $43,875 0.393 51 days $43,545 0.226 54 days $ 43,792.73 0.356
(Elbeltagi
2002)
Example Five
37 days $119,745 0.342 30 days $116,465 0.165 35 days $ 116,604.992 0.338
(Gould 2005)