S. No.

SOR Ref Description of Work Unit Rate Quantity Amount


No.
1 RCD Item Dismanteling of Concrete Cum 1520 0.405 615.60
No. 2.6 Pavement

2 Market U-Pvc Pipe 160 mm RM 350 3 1050.00


Rate Diameter

3 Market U-Pvc Pipe 160 mm Nos 225 2 450.00


Rate Diameter Socket

4 Market U-Pvc Pipe 160 mm Nos 125 2 250.00


Rate Diameter Coupler

5 BCD 0136 Sewerman Day 270 1 270.00

6 BCD 0L01 Helper (Sewerman) Day 254 1 254.00

Hole making at Boudary Wall


7 BCD0122 Mason Nos 342 0.5 171.00

8 BCD0L01 Helper (Mason) Nos 254 0.5 127.00

Hole making at Inlet Point


9 BCD0122 Mason Nos 342 0.5 171.00

10 BCD0L01 Helper (Mason) Nos 254 0.5 127.00

11 BCD0L27 Plumber Nos 323 0.5 161.50


12 BCD0161 Helper (Plumber) Nos 254 0.5 127.00

13 L/S Repairing Charges for L/S 20 2 40.00


Hole
14 L/S Carriage of Pipe RM 4.58 3 13.74
Transpotation upto 3 km

Total 3827.84
Add contractor profit @ 10 % on non schedule items i.e (1050+ 175.00
Grand Total 4002.84
Remarks

1. As per RCD,the rates are exclusive of GST and


BOCW. The same needs to be added.
2. Moreover, dismantelling of Concrete Pavement is
provided but restoration of the same is not. Please
add
1. Asan item
per for,restoration
RCD 10% profit of concrete
+10% pavment.
overhead needs to
be added, Only 10% profit is added on it. Please
revise
2.The rates are esclusive of GST and BOCW. The
same needs
1. As per RCDto ,be added.
10% profit +10% overhead needs to
be added, Only 10% profit is added on it. Please
revise
2.The rates are esclusive of GST and BOCW. The
same needs
1. As per RCDto ,be added.
10% profit +10% overhead needs to
be added, Only 10% profit is added on it. Please
revise
2.The rates are esclusive of GST and BOCW. The
same needs to ,be
1443/28-03-18 added.
which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
1443/28-03-18 , which is more than one year old,
15% needs to be added to bring the rates at current
rate.
2. As per BCD the rates are esclusive of profit,
overhead, GST and BOCW. The same needs to be
added.
The basic rate for reparing of holes shall be Rs.100
per holes plus profit, overhead, GST and BOCW
Based on current fuel and hire charges at market
rate, and also due to the fact that there will be
multiple shiting & handling required as there is space
constraint for keeping pipes in Karmalichak area, the
basic rate for carriage upto 3 KM shall be Rs.20 per
meter plus profit, overhead, GST and BOCW

The total Rate for one connection shall be as per


Annexure-1