PT.

MULTICIPTA BANGUN SEMESTA


MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 4TH- 7TH FLOOR
PRODUCTION R0 R1
NO LIST OF DRAWING AMOUNT
RECEIVED SUBMIT RECEIVED STATUS SUBMIT RECEIVED STATUS
1 DENAH PRECAST LANTAI 3 1 14/09/2016 C
2 DENAH BRACKET LANTAI 3 1 14/09/2016 A
3 STANDART DETAIL PRECAST 1 14/09/2016 A
4 WN1B 1 14/09/2016 B
5 WN2B 1 14/09/2016 B
6 WN3B 1 14/09/2016 A
7 WN4B 1 14/09/2016 B
B WN5L1B 1 14/09/2016 B
9 WN5R1B 1 14/09/2016 B
10 WN5L2B 1 14/09/2016 B
11 WN5R2B 1 14/09/2016 B
12 WN6B 6 14/09/2016 A
13 WN7B 1 14/09/2016 C
14 WN8LB 1 14/09/2016 B
15 WN8RB 1 14/09/2016 C
16 WB9B 1 14/09/2016 A
17 WN10B 1 14/09/2016 B
18 WN11B 2 14/09/2016 A
19 WN11LB 1 14/09/2016 C
20 WN11RB 1 14/09/2016 C
21 WN12B 1 14/09/2016 C
22 WN13B 1 14/09/2016 A
23 WN14B 1 14/09/2016 B
24 WN15B 1 14/09/2016 C
25 WN16B 1 14/09/2016 C
26 WN18B 1 14/09/2016 B
27 WN19LB 2 14/09/2016 B
28 WN19RB 1 14/09/2016 B
29 WN20A 1 14/09/2016 A
30 WN20LB 1 14/09/2016 A
31 WN20RB 1 14/09/2016 A
32 WN21LB 2 14/09/2016 A
33 WN21RB 1 14/09/2016 A
34 WN22LB 1 14/09/2016
35 WN22RB 2 14/09/2016
36 WN23LB 2 14/09/2016
37 WN23RB 1 14/09/2016
38 WN24AB 1 14/09/2016
39 WN24B 1 14/09/2016
40 WN25B 1 14/09/2016
41 WN26LB 1 21/09/2016
42 WN26RB 1 14/09/2016
43 WN27B 1 14/09/2016
44 WN28AB 1 14/09/2016
45 WN28BB 1 14/09/2016
46 WN28LB 1 14/09/2016
47 WN28RB 1 14/09/2016
48 WN29B 1 14/09/2016
49 WN3OB 2 14/09/2016
50 WN31B 1 14/09/2016
51 WN32LB 1 14/09/2016
52 WN33B 1 14/09/2016
53 WN34B 1 14/09/2016
54 WN54B 1 14/09/2016
TOTAL 65

: DISETUJUI
: APPROVE BY ACSET : DISETUJUI DEENGAN CATATAN
: REJECT BY ACSET : DIREVISI
: REVIEW PROGRESS IN CM (TCM) : DITOLAK
MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 4TH- 7TH FLOOR
R1 R2
RECEIVED STATUS SUBMIT STATUS RECEIVED STATUS
C A
PT. MULTICIPTA BANGUN SEMESTA
MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 4TH- 7TH FLOOR
PRODUCTION R0 R1
NO LIST OF DRAWING AMOUNT
RECEIVED SUBMIT RECEIVED STATUS SUBMIT RECEIVED STATUS
1 DENAH PRECAST LANTAI 4 - 7 1 21/09/2016 23/09/2016 24/09/2016 A
2 DENAH PRECAST LANTAI 4 - 7 1 21/09/2016 23/09/2016 24/09/2016 A
3 WN - 1 1 21/09/2016 23/09/2016 24/09/2016 A
4 WN - 2 1 21/09/2016 23/09/2016 24/09/2016 A
5 WN - 3 1 22/09/2016 23/09/2016 24/09/2016 A
6 WN - 4 1 24/09/2016 26/09/2016 11/10/2016 A 23/09/2016 24/09/2016 A
7 WN - 5L1 1 22/09/2016 23/09/2016 24/09/2016 A
B WN - 5R1 1 2/11/2016 3/11/2016
9 WN - 5L2 1 24/09/2016 26/09/2016 11/10/2016 B 23/09/2016 24/09/2016 A
10 WN - 5R2 1 24/09/2016 26/09/2016 11/10/2016 A 23/09/2016 24/09/2016 A
11 WN - 6 6 24/09/2016 23/09/2016 24/09/2016 A
12 WN - 7 1 22/09/2016 23/09/2016 24/09/2016 A
13 WN - 8L 1 22/09/2016 23/09/2016 24/09/2016 A
14 WN - 8R 1 22/09/2016 23/09/2016 24/09/2016 A
15 WN - 9 1 21/09/2016 23/09/2016 24/09/2016 A
16 WN - 10 1 21/09/2016 23/09/2016 24/09/2016 A
17 WN - 11 2 22/09/2016 23/09/2016 24/09/2016 A
18 WN - 11L 1 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
19 WN - 11R 1 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
20 WN - 12 1 21/09/2016 23/09/2016 24/09/2016 A
21 WN - 13 1 21/09/2016 23/09/2016 24/09/2016 A
22 WN - 14 1 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
23 WN - 15 1 21/09/2016 23/09/2016 24/09/2016 A
24 WN - 16 1 24/09/2016 26/09/2016 24/09/2016 A
25 WN - 18 1 21/09/2016 23/09/2016 24/09/2016 A
26 WN - 19L 2 21/09/2016 23/09/2016 24/09/2016 B
27 WN - 19R 1 21/09/2016 23/09/2016 24/09/2016 B
28 WN - 20A 1 21/09/2016 23/09/2016 24/09/2016 A
29 WN - 20L 1 22/09/2016 23/09/2016 24/09/2016 A
30 WN - 20R 1 22/09/2016 23/09/2016 24/09/2016 A
31 WN - 21L 2 21/09/2016 23/09/2016 24/09/2016 A
32 WN - 21R 1 21/09/2016 23/09/2016 24/09/2016 A
33 WN - 22L 2 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
34 WN - 22R 2 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
35 WN - 23L 1 21/09/2016 23/09/2016 24/09/2016 A
36 WN - 23R 1 22/09/2016 23/09/2016 24/09/2016 A
37 WN - 24 1 21/09/2016 23/09/2016 24/09/2016 A
38 WN - 24A 1 24/09/2016 26/09/2016 11/10/2016 B
39 WN - 25 1 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016 21/11/2016 A
40 WN - 26L 1 22/09/2016 23/09/2016 24/09/2016 A
41 WN - 26R 1 21/09/2016 23/09/2016 24/09/2016 A
42 WN - 27 1 21/09/2016 23/09/2016 24/09/2016 A
43 WN - 28L 1 21/09/2016 23/09/2016 24/09/2016 B
44 WN - 28R 1 22/09/2016 23/09/2016 24/09/2016 A
45 WN - 28A 1 24/09/2016 23/09/2016 24/09/2016 A
46 WN - 28B 1 21/09/2016 23/09/2016 24/09/2016 A
47 WN - 29 1 21/09/2016 23/09/2016 24/09/2016 A
48 WN - 30 2 21/09/2016 23/09/2016 24/09/2016 A
49 WN - 31 1 22/09/2016 23/09/2016 24/09/2016 A
50 WN - 32L 1 24/09/2016 26/09/2016 11/10/2016 A
51 WN - 33 1 22/09/2016 23/09/2016 24/09/2016 B
52 WN - 34 1 21/09/2016 23/09/2016 24/09/2016 A
53 WN - 54 1 21/09/2016 23/09/2016 24/09/2016 A
TOTAL 64

: DISETUJUI
: APPROVE BY ACSET : DISETUJUI DEENGAN CATATAN
: REJECT BY ACSET : DIREVISI
: REVIEW PROGRESS IN CM (TCM) : DITOLAK
MONITORING SHOP DRAWING
EST VISTA APARTEMENT - PT MBS
ORTH TOWER / 4TH- 7TH FLOOR
R2
SUBMIT RECEIVED STATUS SUBMIT
PT. MULTICIPTA BANGUN SEMESTA
MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 8TH FLOOR
PRODUCTION R0 R1
NO LIST OF DRAWING AMOUNT
RECEIVED SUBMIT RECEIVED STATUS SUBMIT RECEIVED STATUS
1 DENAH PRECAST LANTAI 8 1 5/10/2016 7/10/2016 11/10/2016 A
2 DENAH PRECAST LANTAI 8 ( ZONE - 3 ) 1 5/10/2016 7/10/2016 11/10/2016 A
3 DENAH PRECAST LANTAI 8 ( ZONE - 2 ) 1 5/10/2016 7/10/2016 11/10/2016 C
4 DENAH PRECAST LANTAI 8 ( ZONE - 1 ) 1 5/10/2016 7/10/2016 11/10/2016 A
5 WN1 C 1 5/10/2016 7/10/2016 11/10/2016 A
6 WN2 C 1 5/10/2016 7/10/2016 11/10/2016 B
7 WN3 C 1 5/10/2016 7/10/2016 11/10/2016 C
B WN4 C 1 5/10/2016 7/10/2016 11/10/2016 A
9 WN5L1 C 1 5/10/2016 7/10/2016 11/10/2016 C
10 WN5R1 C 1 5/10/2016 7/10/2016 11/10/2016 C
11 WN5L2 C 1 5/10/2016 7/10/2016 11/10/2016 A
12 WN5R2 C 1 5/10/2016 7/10/2016 11/10/2016 A
13 WN6 C 6 5/10/2016 7/10/2016 11/10/2016 B
14 WN7 C 1 5/10/2016 7/10/2016 11/10/2016 B
15 WN8L C 1 5/10/2016 7/10/2016 11/10/2016 B
16 WN8R C 1 5/10/2016 7/10/2016 11/10/2016 B
17 WN9 C 1 5/10/2016 7/10/2016 11/10/2016 B
18 WN10 C 1 5/10/2016 7/10/2016 11/10/2016 B
19 WN11 C 2 5/10/2016 7/10/2016 11/10/2016 B
20 WN11 L 1 5/10/2016 7/10/2016 11/10/2016 C
21 WN11 R 1 5/10/2016 7/10/2016 11/10/2016 C
22 WN12 C 1 5/10/2016 7/10/2016 11/10/2016 B 14/12/2016
23 WN13 C 1 5/10/2016 7/10/2016 11/10/2016 B
24 WN14 C 1 5/10/2016 7/10/2016 11/10/2016 C
25 WN15 C 1 5/10/2016 7/10/2016 11/10/2016 B
26 WN16 C 1 5/10/2016 7/10/2016 11/10/2016 A
27 WN18 C 1 5/10/2016 7/10/2016 11/10/2016 A
28 WN19L C 2 5/10/2016 7/10/2016 11/10/2016 A
29 WN19R C 1 5/10/2016 7/10/2016 11/10/2016 C
30 WN20A C 1 5/10/2016 7/10/2016 11/10/2016 C
31 WN20L C 1 5/10/2016 7/10/2016 11/10/2016 C
32 WN20R C 1 5/10/2016 7/10/2016 11/10/2016 C
33 WN21L C 2 5/10/2016 7/10/2016 11/10/2016 A
34 WN21R C 1 5/10/2016 7/10/2016 11/10/2016 B
35 WN22L C 2 5/10/2016 7/10/2016 11/10/2016 C
36 WN22R C 2 5/10/2016 7/10/2016 11/10/2016 C
37 WN23L C 1 5/10/2016 7/10/2016 11/10/2016 A
38 WN23R C 1 5/10/2016 7/10/2016 11/10/2016 A
39 WN24A C 1 5/10/2016 7/10/2016 11/10/2016 A
40 WN24 C 1 5/10/2016 7/10/2016 11/10/2016 C
41 WN25 C 1 5/10/2016 7/10/2016 11/10/2016 A
42 WN26L C 1 5/10/2016 7/10/2016 11/10/2016 C 14/12/2016
43 WN26R C 1 14/12/2016
44 WN27 C 1 5/10/2016 7/10/2016 11/10/2016 B 14/12/2016
45 WN28A C 1 5/10/2016 7/10/2016 11/10/2016 A
46 WN28B C 1 5/10/2016 7/10/2016 11/10/2016 A
47 WN28L C 1 5/10/2016 7/10/2016 11/10/2016 A
48 WN28R C 1 5/10/2016 7/10/2016 11/10/2016 C
49 WN29 C 1 5/10/2016 7/10/2016 11/10/2016 A
50 WN30 C 2 5/10/2016 7/10/2016 11/10/2016 B 14/12/2016
51 WN31 C 1 5/10/2016 7/10/2016 11/10/2016 A
52 WN32L C 1 5/10/2016 7/10/2016 11/10/2016 B
53 WN33 C 1 5/10/2016 7/10/2016 11/10/2016 A
54 WN34 C 1 5/10/2016 7/10/2016 11/10/2016 B
55 WN54 C 1 5/10/2016 7/10/2016 11/10/2016 A
TOTAL 66

: DISETUJUI
: APPROVE BY ACSET : DISETUJUI DEENGAN CATATAN
: REJECT BY ACSET : DIREVISI
: REVIEW PROGRESS IN CM (TCM) : DITOLAK
MONITORING SHOP DRAWING
EST VISTA APARTEMENT - PT MBS
NORTH TOWER / 8TH FLOOR
R2
SUBMIT RECEIVED STATUS
PT. MULTICIPTA BANGUN SEMESTA
MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 8TH FLOOR
PRODUCTION R0 R1
NO LIST OF DRAWING AMOUNT
RECEIVED SUBMIT RECEIVED STATUS SUBMIT RECEIVED STATUS
1 21/09/2016 23/09/2016 24/09/2016 A
2 21/09/2016 23/09/2016 24/09/2016 A
3 21/09/2016 23/09/2016 24/09/2016 A
4 21/09/2016 23/09/2016 24/09/2016 A
5 22/09/2016 23/09/2016 24/09/2016 A
6 24/09/2016 26/09/2016 11/10/2016 A
7 22/09/2016 23/09/2016 24/09/2016 A
B 2/11/2016 3/11/2016
9 24/09/2016 26/09/2016 11/10/2016 B 3/11/2016
10 24/09/2016 26/09/2016 11/10/2016 A
11 24/09/2016 23/09/2016 24/09/2016 A
12 22/09/2016 23/09/2016 24/09/2016 A
13 22/09/2016 23/09/2016 24/09/2016 A
14 22/09/2016 23/09/2016 24/09/2016 A
15 21/09/2016 23/09/2016 24/09/2016 A
16 21/09/2016 23/09/2016 24/09/2016 A
17 22/09/2016 23/09/2016 24/09/2016 A
18 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016
19 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016
20 21/09/2016 23/09/2016 24/09/2016 A
21 21/09/2016 23/09/2016 24/09/2016 A
22 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016
23 21/09/2016 23/09/2016 24/09/2016 A
24 24/09/2016 26/09/2016 24/09/2016 A
25 21/09/2016 23/09/2016 24/09/2016 A
26 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016
27 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016
28 21/09/2016 23/09/2016 24/09/2016 A
29 22/09/2016 23/09/2016 24/09/2016 A
30 22/09/2016 23/09/2016 24/09/2016 A
31 21/09/2016 23/09/2016 24/09/2016 A
32 21/09/2016 23/09/2016 24/09/2016 A
33 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016
34 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016
35 21/09/2016 23/09/2016 24/09/2016 A
36 22/09/2016 23/09/2016 24/09/2016 A
37 21/09/2016 23/09/2016 24/09/2016 A
38 24/09/2016 26/09/2016 11/10/2016 B 4/11/2016
39 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016
40 22/09/2016 23/09/2016 24/09/2016 A
41 21/09/2016 23/09/2016 24/09/2016 A
42 21/09/2016 23/09/2016 24/09/2016 A
43 21/09/2016 23/09/2016 24/09/2016 B 4/11/2016
44 22/09/2016 23/09/2016 24/09/2016 A
45 24/09/2016 23/09/2016 24/09/2016 A
46 21/09/2016 23/09/2016 24/09/2016 A
47 21/09/2016 23/09/2016 24/09/2016 A
48 21/09/2016 23/09/2016 24/09/2016 A
49 22/09/2016 23/09/2016 24/09/2016 A
50 24/09/2016 26/09/2016 11/10/2016 A
51 22/09/2016 23/09/2016 24/09/2016 B 4/11/2016
52 21/09/2016 23/09/2016 24/09/2016 A
53 21/09/2016 23/09/2016 24/09/2016 A
TOTAL 0

: DISETUJUI
: APPROVE BY ACSET : DISETUJUI DEENGAN CATATAN
: REJECT BY ACSET : DIREVISI
: REVIEW PROGRESS IN CM (TCM) : DITOLAK
MONITORING SHOP DRAWING
WEST VISTA APARTEMENT - PT MBS
NORTH TOWER / 8TH FLOOR
R1 R2
RECEIVED STATUS SUBMIT STATUS RECEIVED STATUS