You are on page 1of 144

Wide Area Network (WAN)

Consultancy Project
Existing Situation Analyses Document

(ESAD)

Issue Date Revision Number Revision Date

11/06/2018 00

30/07/2018 01 July 30, 2018


Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

CONSULTANCY SERVICES
FOR (Wide Area Network Consultancy Project)

July 30, 2018

REPORT

BY XOKA IT Solution and


Power House Computer Solution

Existing Situation Analyses Document


(SAD)

Page 2
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Table of Contents

Section 1 – Introduction & Overview of Project ................................................................ 4

Section 2 – Existing system: ICT Infrastructure Survey ..................................................... 8


2.1. Purpose of a Network infrastructure Assessment ................................................................... 8

2.2. Assessment Methodology ................................................................................................................ 9

2.3. Client existing LAN and WAN Infrastructure Assessment findings ................................. 10

2.4. Client’s existing Hardware and Software Utilization ............................................................. 15

2.5. Client existing LAN and WAN Devices....................................................................................... 17

2.6. Client’s existing Data Centre devices ......................................................................................... 18

Section 3 - Existing system: Organizational Functions ................................................... 19

Section 4. Conclusion .......................................................................................................... 29

Annex A: Computer Hardware and Software Data Summary ........................................ 30

ANNEX B: Existing Structural Cabling of the Federal Courts ......................................... 43

ANNEX C: Network Infrastructure Distribution Summary ............................................. 61

ANNEX D: Switch Router and Firewall data Summary .................................................... 66

Annex E – Office Locations of Federal Courts .................................................................. 70

Annex F: Existing LAN Layout of Federal Courts ............................................................. 73

Annex G – Observation Report ........................................................................................ 140

Page 3
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Section 1 – Introduction & Overview of Project

1.1. Introduction

One of the key factors that determine effective utilization of information and communication

resources in an organization is the existence of a well-designed network infrastructure and

software.

Network Infrastructure provides a number of different benefits to an organization that have

a number of employees who need access to the same information. Networks can go a long

way in helping organizations to get things done at faster manner which saves man-hours and

money.

Network Infrastructure reduces organizations equipment and communication costs. When

employees share printers, fax machines and CD-ROM's, the need to purchase additional

office equipment is eliminated. Money is saved by eliminating much of the paper that is

necessary because electronic communication becomes the primary method of

communicating between coworkers.

The other area where a network infrastructure benefits an organization is on the consumption

of Software Licenses. Software licensing has become a big issue nowadays, and hence

purchasing software license for each employee is very expensive. Network Infrastructure

reduces software license costs. Money is saved because software can be shared by multiple

users instead of having to be bought for each person that uses a particular program.

Networks make it much easier to perform data backups faster because the files can be shared

from one location. Moreover, a single internet connection can be shared among users of an

organization using the network infrastructure.

Hence based on the above facts and the initiation taken by the Supreme Court to implement

integrated Information Network System (LAN/WAN); Network Infrastructure Requirement

Page 4
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Survey has been conducted for all courts and will recommend LAN/WAN design will be

propose including equipment and supplies needed for the implementation in the next

documents.

As technology continues to evolve, the enterprise network must consider supporting voice,

data, video and multimedia applications. Rapid increases in processing power, the growing

size of networks and the introduction of higher-speed access methods create an

overwhelming need for reliable and manageable network infrastructure, trained ICT

professionals to manage the available resources.

XOKA and Power House believe that a properly designed and installed structured cabling

system will provide a cabling infrastructure that delivers predictable performance as well as

flexibility to accommodate growth and change over an extended period of time. Moreover,

since implementation of the proposed infrastructure in turn would create a high demand for

ICT Specialists; appropriate personnel to put in place has to be planned at the same time so

that they can assist and advice the end-users, as well as for day to day administration,

maintenance and support of computer systems and the networks.

1.2. Background

An independence judiciary at Federal and State levels is established by the Constitution of

the Federal Democratic Republic of Ethiopia (FDRE) and proclamation No.25/96. The Federal

Courts comprise the Federal Supreme Court, the Federal High Court, and the Federal First

Instance Court. They have jurisdiction over cases arising under the Constitution, Federal Laws,

and International Treaties; parties specified in Federal Laws; places specified in the

Constitution or in Federal Laws. The permanent places of sitting of the Federal Courts, as

determined by law are:

▪ Federal Supreme Court in Addis Ababa,

Page 5
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

▪ Federal High Courts in Addis Ababa, and Diredawa,

▪ Federal First Instance Courts in Addis Ababa and Diredawa.

The Federal Supreme Court has around 40 Video conference cites and 5 E-filing sites across

the country. The Federal High Court has 5 branch benches 4 in Addis Ababa, namely, Kality,

Bole, Lideta, and Arada, and one in Diredawa. The Federal First Instance Court has 11

Branches, one at each sub city of Addis Ababa and one at Diredawa.

As governmental power is divided into Federal and Regional administrative structures,

jurisdiction of courts is also divided into Federal and Regional structures. This means the

constitution of the Ethiopian Federal Democratic Republic has facilitated a condition in which

both the Federal and regional courts perform their judicial activities side by side.

Proclamation No.25/96, enacted based on the constitution, has established a three-tiered

court. Those are: - The Federal First Instance Court, the Federal High Court and The Federal

Supreme Court. All the courts have the mandate to preside over civil, criminal and labor cases

brought to them. The Federal Supreme Court is the highest and final judicial organ over

Federal matters.

The Federal Supreme Court is currently using ICT as an enabler in the Federal Supreme Court

of Ethiopia. However, in order to provide centralized, shared services in efficient and effective

way, the branch or circuit benches must be connected with the main office.

To this end, the Federal Supreme Court, by hiring XOKA IT Solution & Power House Computer

Solution, intended to study the required Network infrastructure in order to connect each of

these courts using a local and wide area network, build interconnected data centers, acquire

appropriate software package, and video conferencing facility, and produce a Terms of

Reference document for hiring the actual Network Infrastructure implementing company.

1.3. Overview of the Project

Page 6
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

This project officially kicked off on April 30, 2018. The Project is expected to be completed

on July 30, 2018. Among other activities, assessment of existing network environment done

at all 17 Federal Courts is one. The major deliverables expected from this Project are:

▪ Inception Report

▪ Situational Analyses Document

▪ Weekly Progress Reports

▪ WAN Infrastructure Design Document

▪ Software Recommendation Document

▪ Staffing Recommendation Document

▪ Terms of Reference for WAN Infrastructure Implementation

▪ Project Closure Report

The infrastructure assessment has been done in all 17 Federal Courts, and their result has

been analyzed and presented in this document. The existing Situation Analysis Document

(SAD) is an analysis of existing gaps against Federal Supreme Court requirements.

The Assessment has identified gaps in the following areas:

▪ Client existing LAN and WAN Infrastructure

▪ Client existing Hardware and Software devices with type and model

▪ Client existing datacenter devices including type and model

▪ Client existing manpower with qualifications

This ESAD document is prepared after a thorough analysis of these environmental

requirements for a Wide Area Network Connectivity among Federal Courts.

Page 7
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Section 2 – Existing system: ICT Infrastructure Survey

Network Infrastructure assessment is performed to ensure either smooth operation of

networking in an organization or to analyze the existing system for developing new network

infrastructure or improving the existing system. These types of assessments enable a

company or an organization analyzes its existing network system and identifies issues and

gives a solution for them. It helps to analyze costs for upgrading the existing system to

accommodate current technologies and gives way for further scalabilities. Such kind of

assessments also helps in developing a company or organization information technology

policies regarding internet access, access control, security, device naming etc.

2.1. Purpose of a Network infrastructure Assessment


The main purpose of assessment of the current ICT infrastructure

1. Enables to take inventory of current available network infrastructure

2. Enables to know current status of the network devices

3. Enables to identify current problems and issues

4. Enables reviewing the current architecture

5. Enables to identify security issues

6. Enables to analyze over all problems and give recommendation for addressing the

issues.

To achieve these, our project team has conducted a Site Visit to Understand and analyze the

existing ICT resources and network infrastructure that Federal Supreme, High and First

Instance Courts and their branches have. We assess the existing network infrastructure the

human resources available for running the existing ICT infrastructure. The assessment is done

in collaboration with Supreme, High and First Instance Courts ICT staffs and Branch judiciary

offices’ employees. Its main objective is to check the available ICT infrastructure resources

like computers, servers, switches, routers, firewalls, video conference equipment, software

Page 8
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

and applications status which are working in the ongoing business operations. The report of

the existing system will focus on showing the current available resources on different sites of

the federal court offices.

Our project team has surveyed all the Federal Democratic Republic of Ethiopia supreme

courts, high courts and First Instance courts offices to analyze the existing ICT system &

infrastructure of the Courts’ which includes hardware, software, network infrastructure and

technical support for the existing system in order to evaluate the effectiveness and efficiency

of the system and recommend on areas which needs improvement or change to enable the

company to efficiently utilize ICT and achieve its goals being the major competent in the

court system.

2.2. Assessment Methodology


In order to assess the existing infrastructure and compile a reliable data we used the following

methods of data collection

1. Data collection using structured questionnaires: Site visit to the respective offices

and branches

2. Key informant interviewing: data collected from the ICT personnel and other staffs

3. Observation

The courts use different ICT systems as a supporting tool for a wide range of its activities at

the head and benches. To mention some of the usage of ICT system on the federal courts to

handle data on Court case management system and human resource management system

and resource sharing. In most of the federal court offices ADSL connection is available for

internet access and for the data VPN data connection is available. To use these resources the

Federal Courts, have different ICT related equipment like routers, switches, computers,

printers, ups and different software. The initiative taken by the court to improve the ICT

Page 9
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

infrastructure for its organizational operations and its plan to use current ICT technologies to

make the court continue improving the court management system is very much appreciated

by our team.

Our survey shows that the existing ICT resources within the court are not efficiently utilized

due to the following major reasons:

▪ Benches and Supreme Court do not have WAN connection, all have separated internet

services. There is no wide area network infrastructure to share resources like

documents, printers, scanners, etc from branch to branch.

▪ There is no formal backup system in the court for making a backup of critical data.

▪ There is no central data base system for the court case management system and human

resources

▪ There is no standardized data center all the benches

▪ All most all of the network infrastructures are under standard

▪ In most offices there are no enough highly ICT trained professionals to give prompt

support to computer users, which may result in lag of operation in the court system.

2.3. Client existing LAN and WAN Infrastructure Assessment


findings

The main utilization of the network infrastructure in federal courts is mostly internet service,

local printer sharing (in some offices), and localized court case management system (CCMS)

access. Most of the personal computers are used for Word-processing and spreadsheet

activities. Electronic documents are processed using both English and Amharic languages.

And there is no centralized document and knowledge management information system for

collaboration works except CCMS. There is no centralized backup solution in the federal

courts.

Page 10
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

2.3.1. Structural Cabling Infrastructure

The existing structural cabling of the Federal Courts data is presented on ANNEX B: Existing

Structural Cabling of the Federal Courts. Currently the following locations have network

infrastructure that is functional and accommodated most of the users:

▪ Federal Supreme Court,

▪ Federal High Court Head Office (Lideta),

▪ Kality Federal High Court,

▪ Bole Federal High Court,

▪ Federal First Instance Head Office (Lideta),

▪ Yeka Federal First Instance,

▪ Menagesha Federal First Instance,

▪ Kirkos Federal First Instance,

▪ Arada Federal First Instance,

▪ Addis Ketema First Instance,

▪ Bole Federal First Instance,

▪ Akaki Federal First Instance,

▪ Kolfie Keranio Federal First Instance,

▪ Judicial Execution Directorate of the Federal Supreme Court

The following locations did not have functional network infrastructure

▪ Federal Sheria Supreme Court,

▪ Diredawa Federal first Instance,

▪ Nifas Silk Lafto Federal First Instance,

▪ Diredawa Federal High Court, and,

▪ Arada Federal High Court Court

Page 11
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

A structured cabling system is a complete system of cabling and associated hardware, which

provides a comprehensive telecommunications infrastructure. This infrastructure serves a

wide range of uses, such as to provide telephone service or transmit data through a computer

network. It should not be device dependent.

We further define a structured cabling system in terms of ownership. The structured cabling

system begins at the point where the service provider (SP) terminates. This point is the point

of demarcation or Network Interface Device (NID). Every structured cabling system is unique.

This is due to variations in:

✓ The architectural structure of the building, which houses the cabling installation;

✓ The cable and connection products;

✓ The function of the cabling installation;

✓ The types of equipment the cabling installation will support -- present and future;

✓ The configuration of an already installed system (upgrades and retrofits);

✓ Customer requirements; and

✓ Manufacturer warranties.

The standardization of these installations is necessary because of the need to ensure

acceptable system performance from increasingly complex arrangements.

The U.S. cabling industry accepts the American National Standards Institute (ANSI), in

conjunction with TIA/EIA, as the responsible organization for providing and maintaining

standards and practices within the profession. It has published a series of standards to design,

install, and maintain cabling installations. These help to ensure a proper cabling installation.

The benefits of these standards include consistency of design and installation;

✓ Conformance to physical and transmission line requirements;

✓ A basis for examining a proposed system expansion and other changes; and

✓ Uniform documentation.

Page 12
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

The industry standard term for a network installation that serves a relatively small area (such

as a structured cabling installation serving a building) is a local area network (LAN). There are

also metropolitan area networks (MANs) and wide area networks (WANs).

Structured cabling installations typically include: vertical and horizontal backbone pathways;

vertical and horizontal backbone cables; horizontal pathways; horizontal cables; work area

outlets; equipment rooms; telecommunications closets; cross-connect facilities; multi-user

telecommunications outlet assemblies (MUTOA); transition points; and consolidation points.

Backbone cabling. From the entrance facility, the structured cabling network branches out

to other buildings, as well as from floor to floor within a building on the backbone cabling

system. We use the term backbone to describe the cables handling the major network traffic.

And since the backbone is the major data transferring media from the user to other users, it

has to be good speed and reliable.

Inter-building and intra-building are two types of backbone cables. Inter-building backbone

cable handles traffic between buildings. Intra-building backbone cable handles traffic

between closets in a single building.

As of which the existing backbone cables for amost all Courts are UTP and most of them are

not terminated as per the standard and cascaded. The main components of cabling are:

▪ Cable pathways: shafts, conduits, raceways, and floor penetrations (such as sleeves or

slots) that provide routing space for the cables.

✓ Most of the cable pathways are not properly installed for most of the Courts and at

some of the Courts the Trunkings was installed long time and opened to pull

additional cable, they are damaged.

▪ The actual cables: optical fiber, twisted-pair copper, coaxial copper, or some

combination of these.

✓ Most of the cables installed at all Courts are cat 6 and there are some cat 5e cables

Page 13
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

✓ Most of the cables are pulled outside of cable pathways so it is easily damageable

▪ Connecting hardware: connecting blocks, patch panels, interconnections, cross-

connections, or some combination of these components, and

✓ Most of the patch panels are cat 6 and the cables are terminated

▪ Rack:

✓ Most of the network have rack and the devices are contained on the rack

✓ No power backup is available for all racks

✓ No cable management

ANNEX C: Network Infrastructure Distribution Summary

2.3.2. Node Distribution

Node is the network infrastructure that is sufficient for one computer usage. Hence, we

evaluated the existing infrastructure based on accesses to users:

Number of Number of Number of


Description
Existing node users computers

Supreme Court 311 316 261

Supreme Judiciary Execution court 69 93 50

Supreme Sheria court 0 36 34

Federal High court head office (Lideta) 157 245 174

Kality Federal High Court 126 46 26

Arada Federal High Court 0 15 13

Bole Federal High Court 33 45 37

Diredaw Federal High Court 0 28 25

Federal First Instance Head Office ( Lideta) 63 158 147

Yeka Federal First Instance 17 56 39

Menagesha Federal First Instance 86 61 24

Nifas Silk Lafto Federal First Instance 1 30 28

Page 14
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Kirkos Federal First Instance 56 73 44

Arada Federal First Instance 0 27 45

Addis ketema First Instance 2 35 36

Bole Federal First Instance 71 107 32

Diredawa Federal first Instance 7 33 31

Akaki Federal First Instance 77 90 32

Kolfie Keranio Federal First Instance 30 47 35

2.4. Client’s existing Hardware and Software Utilization


2.4.1. Processor Model and Speed:
The processor is “the brain” of a computer. It reads instructions from the software and tells

the computer what to do. Pentium, PowerPC and 80486 are common processors. The speed

at which the CPU processes information internally is measured in Megahertz (MHz), Gigahertz

(GHz) and so on. Generally; processors with higher MHz or GHz enhance the ability to run

different computer applications at the same time.


2.4.2. Memory (RAM):
RAM stands for Random Access Memory. Every time a program is opened, it gets loaded

from the hard drive into the RAM. This is because reading data from the RAM is much faster

than reading data from the hard drive. Running programs from the RAM of the computer

allows them to function without any lag time. The more RAM the computer has, the more

data can be loaded from the hard drive into the RAM, which can help speed up the computer

data processing power.


2.4.3. Network Interface Card (NIC):
NIC is an acronym for network interface card, a plug-in adapter card that provides the physical

connection to the network.

2.4.4. Hard Disk:

Page 15
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

The computer's hard disk is the part of the computer hardware where users store document

and program files. Typically, on a Windows PC, it will have the drive letter C. The capacity of

hard drive is usually measured in Megabyte, Gigabyte, and Terabyte and so on.
2.4.5. Operating System:

An Operating System is software or set of programs that mediate access between physical

devices (such as a keyboard, mouse, monitor, disk drive or network connection) and

application programs (such as a word processor, spreadsheet, database and the World Wide

Web browser).
2.4.6. Client’s existing Software Utilization

The detail Computer Hardware and Software Data Summary is presented on ANNEX A:

Computer Hardware and Software Data Summary.


2.4.7. Microsoft Office:

Most of users at Courts are using Ms Office 2007 installed on their computers and few users

are still using Ms Office 2003 for word processing and spreadsheet, for their day to day

activities.
2.4.8. Amharic Software:

Since Amharic language is the official working language for the Federal Government of

Ethiopia, users need Amharic software to process documents in Amharic language. There are

two types of Amharic Software installed on the most of the Courts PCs:

▪ Power Geez and

▪ Visual Geez.

Since different types of Amharic software are used, users usually face a problem of reading

documents created on different computers that are using the different types of the software.
2.4.9. Application Software:

Page 16
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

The Courts have application software

1. Court Case Management system

2. Human Resource Management System

3. IBEX Financial System

Even though this applications lack integrity with each other and could not be used over a

network among the different users; the initiations taken by the federal courts in developing

the above applications in try to solve or minimize the data manipulation and storage problem

in the judiciary system is really appreciated by our team.

2.4.10. Antivirus:

Nowadays, security is becoming a big issue because of loss of critical data due to virus and

different attackers or intruders. Hence, latest antivirus and firewall should be installed to

protect PCs from virus and different intruders. Most of the computers of Federal Courts are

installed with Kaspersky Antivirus software. But most of the antiviruses are expired and

centrally uncontrolled. ANNEX A: Computer Hardware and Software Data Summary is

attached herewith.

2.5. Client existing LAN and WAN Devices


2.5.1. Network Active Devices
Most of the federal courts have managed and unmanaged network devices and all of the

federal courts implemented flat network topology. The courts have switches that can be

configured VLAN and increase security, manageability, scalability and the efficiency and

effectiveness of the network, but all of the manageable switches are not yet utilized to their

capacity.

The main advantages of VLAN are listed below.

Page 17
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

• Broadcast Control: Broadcasts are required for the normal function of a network. Many

protocols and applications depend on broadcast communication to function properly. A layer

2 switched network is in a single broadcast domain and the broadcasts can reach the network

segments which are so far where a particular broadcast as no scope and consume available

network bandwidth. A layer 3 device (typically a Router) is used to segment a broadcast

domain. If we segment a large LAN to smaller VLANs we can reduce broadcast traffic as

each broadcast will be sent on to the relevant VLAN only.

• Security: VLANs provide enhanced network security. In a VLAN network environment, with

multiple broadcast domains, network administrators have control over each port and user. A

malicious user can no longer just plug their workstation into any switch port and sniff the

network traffic using a packet sniffer. The network administrator controls each port and

whatever resources it is allowed to use. VLANs help to restrict sensitive traffic originating

from an enterprise department within itself.

• Cost: Segmenting a large VLAN to smaller VLANs is cheaper than creating a routed network

with routers because normally routers costlier than switches.

• Physical Layer Transparency: VLANs are transparent on the physical topology and

medium over which the network is connected.


2.5.2. Server, Router & Computer Quantity Summary
Detail description of the types and models of the routers, switches, and are attached in the

annex. Detail description and location Information about the passive network device and

structural cabling of the Federal Courts. ANNEX D: Switch Router and Firewall Data Summary

is attached herewith.

2.6. Client’s existing Data Centre devices


Data Center

Page 18
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Except few branches of the federal courts, almost all the federal courts do not have dedicated

server room or data center. Out of the 17 branches we have made an assessment, three of

them (Supreme Court, Lideta High Court, Lideta First Instance Court) only have dedicated

server room. But all of the remaining federal courts do not have standard data center.

Section 3 - Existing system: Organizational Functions

The Federal Supreme Court envisioned to further improve its service delivery standard by

introducing ICT systems in to its court administration and management endeavors. As part

of this improvement requirement is the implementation of a Wide Area Network connectivity

among all Federal Courts. The implementation of this infrastructure is also required to bring

about easy communication between federal courts as well as better information management

of cases.

To this end, the Federal Supreme Court has identified that existing information systems need

to be assessed so that a detailed technical and financial recommendation will be available for

management decision making at the end of this assignment.

Accordingly, a thorough assessment of network infrastructure, devices and software systems

have been made across all the 17 federal courts. The methodology employed to conduct this

assessment are:

▪ Assessments made using standard checklists for network infrastructure, hardware and

software existing scenarios

▪ Key Informant Interview (KII) with designated experts of the Federal Supreme, High Court

and First Instance Court

This section provides description of the existing organizational functions, software systems

in place, their desired high-level functionality and current challenges, as well as current

business processes that have been suggested for the improvement when the wide area

network is implemented.

Page 19
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

3.1. Existing Organizational Structure of the Federal Courts

The Federal Supreme Court has currently restructured its organizational structure to support

the Court’s administrative and judicial functions.

Page 20
The Federal High Court Head Quarters is located at Lideta compound, and the same is true for

Federal First Instance Court Head Quarters. The Office of Judicial Execution is located in its own

compound in front of St Yared Music School. The Women and Youth Directorate of the Federal

Supreme Court along with the Federal Sheria Court are located on yet another compound,

away from the Federal Supreme Court. All other Directorates of the Federal Supreme Court,

including the Federal Supreme Court Benches, are located in the Head Quarters building.

All the Directorates, except the benches, of the Federal High Court are located at Lideta Head

Quarters office. The Lideta bench of the Federal High Court is still located in the same

compound as its headquarters. Likewise, all the Directorates of the First Instance Court, except

the benches, are located at Lideta headquarters. Similarly, the Lideta First Instance Court Bench

is at Lidetaheadquarters compound. Office locations of the Federal Courts is attached at

ANNEX D: Office Locations of Federal Courts.

3.2. Existing Business Process of Court Case Management and Judicial Execution
Business Process for Court Case Management

The Federal Courts are tasked with registering incoming cases from the public and appeals

from other Courts, provide a standard process of review of cases, provide appointment(s) and

judgement. This process has the following steps:

a) Case is presented to the Registrar

b) Registrar checks up all the requirements, when basic requirements to file a case are

fulfilled, opens a case

c) Judgement fees, as appropriate, will be paid

d) Documents brought up in support of the case are scanned for soft copy availability

e) Case is assigned to a Judge

f) Court hearing is conducted, and all court conversations are audio-recorded

g) If appropriate, appointment is created, and descriptions of the Appointment are entered

in a software (CCMS)

Page 21
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

h) If appropriate, all required testimonies will be heard, and here also all the court hearing

conversations are audio-recorded

i) Audio recordings are transferred to Transcription Team, who write every sound in the

recording, onto a file, print on it and gets signed by the transcriber

j) Transcribed conversation on a paper is submitted to the judge

k) Judge(s) analyze evidences presented against the law, and deliver judgement

l) When evidence is complete, judgement will be made on the case

m) Formal judgement will be notified to the litigants, and case will be closed

n) Judgement is passed to the Judgement Execution Directorate

However, different case types come to the Court and the process may have branching from its

usual flow of activities. Case types can be of Civil, Criminal, Labor and Religious. Some of the

above steps have been captured to depict the overall process of electronic file management of

cases brought up to the Federal Courts, as shown in Figure 1.

Figure 1: Existing Court Case Management Process Description

Page 22
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Business Process for Judgement Execution Directorate

Once the judgement has been passed, the Judgement Execution Directorate will take over

cases and implement what has been decided. This Directorate provides the following services

to all Federal Courts:

▪ Registration of all incoming cases to the Directorate

▪ Investigation and cost estimation

▪ Auctioning

▪ Distribution of property to

▪ Receive and hand over properties

▪ Effect payment

▪ Administer properties, etc.


Efforts to automate the Court Case Management Process
As part of the continuous automation of the court case management business process, the

Federal Supreme Court is currently using a software called Court Case Management System

(CCMS) that has been deployed to more than 300 Courts nation-wide. This software allows

recording detail case information. It also produces various statistical reports. However, in order

to further improve its service delivery standard, the Court has introduced a number of

improvements to the software, adding the following capabilities:

▪ Touch screen access – for public (stakeholders) to inquire about appointments and case

follow-up

▪ Court List Display – list of cases that will be seen by the Court, in morning and afternoon

sessions

▪ Call Center application – for public (stakeholders) to inquire about appointments and case

follow-up using toll free 992 number

▪ Web-based access – developed by inhouse staff to provide web-based access for public

(stakeholders) on appointments, and case follow-up

Page 23
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

▪ SMS Service – currently under development, and is expected to allow SMS inquiry of

appointments, and case follow-up

▪ Queue Management–for ordered case management of stakeholders (litigants)

The Federal Supreme Court is utilizing various technologies to modernize and automate its

court case management, focusing mostly on allowing public (stakeholders) to easily get

information on the following details:

▪ Appointment Date and Time

▪ Which Court/bench

▪ Case (document) Number

▪ Litigants
Backend and Front-end Technologies of Existing Information Systems

Currently, the following information systems exist at Federal Courts:

▪ Court Case Management System

▪ Human Resources Management System

▪ Judicial Administration Council Management Information System

▪ IBEX Financial System

No. Name of Information System Mode of Access Front End Back end

Desktop MS SQL
1. Court Case Management System Visual Basic
Application Server 2000
Human Resources Management Web-based MS SQL
2. Visual C#
System Access Server 2008
Judicial Administration Council Web-based MS SQL
3. Visual C#
Management Information System Access Server 2008
Web-based Visual Basic
4. IBEX Financial System MS Access
Access .NET

The Web based systems (HRMS and JAC-MIS) are installed at Federal Supreme, High and First

Instance Court Head Quarters only, however, due to unavailability of wide area network, they

Page 24
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

cannot be accessed from the other Federal Courts.Likewise, is the case for the IBEX Financial

System. The CCMS however, is installed in standalone mode in over 300 courts nation-wide.

Challenges of the Existing Court Case Management Business Process

With all these efforts being made by the Court to automate this business process, a number of

serious challenges exist in the current system, as discussed hereunder.


1. Archives and Records Management
The Federal Supreme Court houses court cases of more than 70-80 years, stored in hard copy,

and occupying large number of space in the head quarter offices. Moreover, some of these

files are on the brink of damage, having bad smells, making finding court cases difficult.

In order to organize the archiving process, color-coding of the archive files has been started,

and is ongoing, improving the searching process.

Currently some Directorates of the Federal Supreme Court are located in rented building

because of unavailability of office space in the Head Quarter compound. On the other hand,

large number of archive cases have occupied several offices.

Moreover, currently the cases filed and evidences / supporting documents brought to file cases

are being scanned and put in softcopy availability option. Hence scanning of documents has

been mainstreamed in the main business process.


a. Disaster Recovery of Archive Cases
Large number of case files archived in the HQ of the Federal Supreme Court, and in hardcopy,

are vulnerable to disasters. Disasters such as sudden fire and flooding are serious concerns for

safety of these archive files.


b. Storage Space of Archive Files

The rise in the number of cases filed each year has grown significantly over the last decades

and is also expected to grow significantly in the next years. Storage space requirement for

these case files and archives is increases incrementally.

Page 25
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

2. Audio Recording of Court Hearings

Audio recording of court hearings is carried out to all cases files in Federal Courts. The

recordings are made using a device called Bosch Audio recording machine.

In courtrooms, it is vital that audio is recorded and distributed precisely and efficiently.

Everyone, including the judge, the jury, the prosecution, the defendant, and the witnesses, must

be recorded accurately for subsequent playback and dictation. Many situations require

recordings over individual channels. Sound quality is extremely important since there can be

no doubt as to what has been said. Amplification may also be required, so that the audience

and media can follow proceedings. In some trials it is necessary to display the person speaking

on a large screen, for easier viewing, or there may be a need for video conferencing, especially

when a defendant or witness cannot attend in person1.

These machines allowing saving audio recordings in memory stick, and the files in these

memory sticks are used to transfer files to transcribers. However, sometimes computer viruses

attack these memory stick and files get lost. Some of these files are recording of testimonies,

and witnesses may not be willing or available to witness again, loss of these files with a

computer virus is a serious data safety concern for the Federal Supreme Court.

1
Bosch solutions for reliable courtroom recording, Brochure,
http://resource.boschsecurity.com/documents/Application_note_enUS_8342805771.pdf

Page 26
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

3. Transcribing of Audio Recordings

The transcribing process of audio recordings has been described as the most tiresome and

unhealthy task in the whole court case management business process. It involves listening of

audio recording and writing down every word spoken in the court during the hearing period.

At the end of the transcription process, the transcriber signs on the document, taking

accountability for the document content, and the document is handed over to the judge.

However, the quality of some of the audio recordings may not allow to be transcribed and

hence the court hearing have to be repeated again. Moreover, it has been observed that there

is significant challenge of staff turnover and staff hired as transcribers change frequently. These

problems are also an area of concern for the Federal Supreme Court.
4. Filing of Judgments
Once the judges have all the evidences and information (transcribed court hearings) at hand,

they pass on the appropriate judgement. Those judgements are written by Judges or

secretaries of judges. These softcopy judgements are taken by Flash disk and filed along with

the scanned electronic files. The hardcopies of judgements are also attached with physical case

files. Using unsecured flash disk for taking a backup of files is also a concern for the Federal

Supreme Court.
5. Backup of Databases
Currently database backups of CCMS database, and all other databases of all Federal Courts

are being taken using flash disk and the databases are attached and reports are compiled then

after. Such activities are semi-manual and have high data safety and security concerns for the

Federal Supreme Court.


6. Electric Power Interruption

Electricity power interruption has been a major challenge of the Federal Courts, especially in

connection to database work. The CCMS and other information systems have been put in place

and are providing support for the Court to satisfy its public stakeholders. Besides CCMS, there

Page 27
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

are other systems that demand the uninterrupted supply of electricity such as the HRMS, JAC-

MIS, IBEX Financial System, The Queue Management System, the Touch Screen application, the

Court List Display application. Moreover, additional information systems are being put in place

such as the SMS Service, IVR Service and the Court Case Tracking System for the Judicial

Execution Office, which demand uninterrupted power supply for all Federal Courts.

Page 28
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Section 4. Conclusion

Based on our assessment and findings, we have evaluated the existing networks of Federal

Supreme Court, Federal High Courts and Federal First Instance Courts, and since most of the

network infrastructure of the Federal Courts does not have documentation, it has been difficult

for troubleshooting. Moreover, most of the networks of Federal Courts are not modular, are

not scalable, are not secured and centralized. In addition to tabular statistics, we have also

provided observation report, on ANNEX G – Observation Report.

From our observation of the Sites, we have also

Based on the assessment we have recommended your organization as follows:

Node Distribution in branches Recommendation


Supreme Court New Installation
Federal High court head office (Lideta) New Installation
Kality Federal High Court Expansion
Arada Federal High Court New Installation
Bole Federal High Court Management
Diredaw Federal High Court New Installation
Federal First Instance Head Office ( Lideta) New Installation
Yeka Federal First Instance Expansion
Menagesha Federal First Instance Management
Nifas Silk Lafto Federal First Instance New Installation
Kirkos Federal First Instance Management
Arada Federal First Instance New Installation
Addis ketema First Instance Management
Bole Federal First Instance Management
Diredawa Federal first Instance New Installation
Akaki Federal First Instance Management
KolfieKeranio Federal First Instance Management
FirdAfetasemyared Music supreme court New Installation
Sheria supreme court New Installation

Page 29
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Annex A: Computer Hardware and Software Data Summary


Computer Hardware and Software Data Summary
6.1. Federal Supreme Court
6.1.1. Computer Hardware and Software
Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 10 77 33 1TB-500 146 63
wind 7 151 65 499-400 48 21
win xp 1 0 399-300 9 4
Blank 2 1 299-200 15 6
231 100 <200 9 4
Processor (GHZ) 4 2
Type QTY %age 231 100
>3 189 81.8
3 TO 2 16 6.9 Office Version
<2 0 0.0 Type QTY %age
OTHER 26 11.3 2016 4 2
231 100.0 2013 13 6
RAM (GB) 2010 78 34
Type QTY %age 2007 111 48
>4 155 67.10 unkon 25 11
3GB 11 4.76 231 100
2 GB 53 22.94
<1 GB 7 3.03
BLANK 5 2.16
231 100.00

6.2. LIDETA FHC


Operating System Office Version
Type QTY %age Type QTY %age
win 10 59 38 2016 1 1.3
wind 7 95 61 2013 2 2.6
win xp 1 1 2010 32 41.0
Blank 2 1 2007 41 52.6
157 100 2003 1 1.3
UNKOWN 1 1.3
78 100

Page 30
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Processor (GHZ)
RAM (GB)
Type QTY %age
4 GB 82 53.59
3GB 1 0.65
2 GB 58 37.91
1GB 6 3.92
<1 GB 3 1.96
BLANK 4 2.61
154 100.65
Hard Disk Size (GB)

6.3. KALITY FHC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 21 81 1T 2 8
win 8 0 0 500GB 16 62
win 10 2 8 300GB 3 12
win xp 3 12 100GB 5 19
26 100 26 100

Processor (GHZ) Office Version


Type QTY %age
Type QTY %age
2010 10 38
>3 19 73 2007 6 23
3 to2 7 27 Blank 10 38
26 100 26 100

RAM (GB)
Type QTY %age
>=3 12 46
2 to 1 8 31
<1 5 19
Blank 1 4
26 100

Page 31
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.4. ARADA FHC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 10 2 15 600 2 15
win 7 11 85 500 10 77
13 100 BLANK 1 8
13 100
Processor (GHZ)
Type QTY %age Office Version

3.3 2 15 Type QTY %age


3.6 4 31 2010 5 38
3.7 7 54 2007 8 62
13 100 13 100

RAM (GB)
Type QTY %age
4 GB 12 92
2 GB 1 8
13 100.0

Page 32
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.5. BOLE FHC

Operating System Hard Disk Size (GB)


Type QTY %age Type QTY %age
win 7 36 97.297297 500GB 24 65
Blank 1 2.7027027 300GB 10 27
37 100 100GB 2 5
Processor (GHZ) Blank 1 3
Type QTY %age 37 100
>3 27 72.972973
3 to2 9 24.324324
Blank 1 2.7027027
37 100
RAM (GB)
Type QTY %age
>=3 21 56.756757
2 to 1 15 40.540541
Blank 1 2.7027027
37 100

6.6. DIREDAWA FHC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 12 39 500GB 24 77.4
win 8 18 58 300GB 5 16.1
win xp 1 3 100GB 2 6.5
31 100 31 100
Processor (GHZ) Office Version
Type QTY %age Type QTY %age
>3 27 87 2010 6 19.354839
3 to2 4 13 2007 25 80.645161
31 100 31 100
RAM (GB)
Type QTY %age
>=3 24 77
2 to 1 6 19
<1 1 3
31 100

Page 33
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.7. LIDETA FFIC

Operating System Hard Disk Size (GB)


Office Version
Type QTY %age
Type QTY %age
win 10 2 1
wind 8 7 4 2013 2 1
win 7 149 93 2010 102 64
win xp 2 1 2007 52 33
160 100 unknown 4 3
160 100
Processor (GHZ)
RAM (GB)
Type QTY %age
4 GB 77 48
2 GB 71 44
1GB 6 4
<1 GB 6 4
160 100

6.8. YEKA FFIC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 32 80 1T 4 10
win 8 4 10 500GB 32 80
win 10 3 7.5 400GB 1 2.5
win xp 0 0 100GB 2 5
Blank 1 2.5 Blank 1 2.5
40 100 40 100

Processor (GHZ) Office Version


Type QTY %age Type QTY %age
>3 25 63 2013 14 35
3 to2 13 33 2010 13 32.5
<2 1 3 2007 11 27.5
Blank 1 3 2008 1 2.5
40 100 Blank 1 2.5
40 100

Page 34
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RAM (GB)
Type QTY %age
>=3 13 33
2 to 1 25 63
<1 1 3
Blank 1 3
40 100

6.9. MENAGESHA FFIC

Operating System Hard Disk Size (GB)


Type QTY %age Type QTY %age
win 7 23 77 1T 3 10
win 10 6 20 500GB 22 73
win xp 1 3 400GB 2 7
30 100 300GB 2 7
100GB 1 3
Processor (GHZ)
30 100
Type QTY %age
>3 29 97
3 to2 1 3 Office Version
30 100 Type QTY %age

RAM (GB)
2013 2 7
2010 13 43
Type QTY %age
2007 13 43
>=3 14 47 uknown 2 7
2 to 1 15 50 30 100
<1 1 3
30 100

Page 35
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.10. NIFAS SILK LAFTO FFIC

Operating System Hard Disk Size (GB)

Type QTY %age Type QTY %age


win 7 26 81 1T 1 3
win 8 3 9 500GB 22 69
win 10 2 6 400GB 4 13
win xp 1 3 300GB 1 3
32 100 100GB 4 13
32 100
Processor (GHZ)
Office Version
Type QTY %age Type QTY %age
>3 30 93.75 2013 1 3
3 to2 2 6.25 2010 21 66
32 100 2007 9 28
unknown 1 3
RAM (GB)
32 100
Type QTY %age
>=3 8 25
2 to 1 21 66
<1 3 9
32 100

Page 36
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.11. KIRKOS FFIC

Operating System Hard Disk Size (GB)


Type QTY %age Type QTY %age
>3 37 84 500GB 33 75
3 to2 5 11 400GB 1 2
Blank 2 5 100GB 6 14
44 100 Blank 4 9
44 100
Processor (GHZ) Office Version
Type QTY %age Type QTY %age
>3 37 84 2013 1 2
3 to2 5 11 2010 28 64
Blank 2 5 2007 9 20
44 100 unknown 6 14
44 100
RAM (GB)
Type QTY %age
>=3 16 36
2 to 1 24 55
<1 2 5
Blank 2 5
44 100

Page 37
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.12. ARADA FFIC


RAM (GB) Hard Disk Size (GB)
Office Version
Type QTY %age
Type QTY %age
4 GB 21 47
3 GB 2 4 2013 1 2
2 GB 19 42 2010 30 67
1GB 2 4 2007 14 31
<1GB 1 2 45 100
45 100
Operating System
Type QTY %age
win 10 1 4
win 7 23 92
blank 1 4
25 100

Processor (GHZ)

6.13. ADDIS KETEMA FFIC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 22 76
1T 3 10
win 8 3 10
500GB 23 79
win 10 2 7
100GB 3 10
win xp 2 7
29 100
29 100
Processor (GHZ) Office Version
Type QTY %age
Type QTY %age
>3 29 100
29 100 2013 7 24
RAM (GB) 2010 20 69
Type QTY %age 2007 2 7
>=3 12 41 29 100
2 to 1 14 48
<1 3 10
29 100

Page 38
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.14. BOLE FFIC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 32 86 1T 6 16
Blank 5 14 500GB 22 59
37 100 400GB 1 3
100GB 1 3
Processor (GHZ)
Blank 7 19
Type QTY %age 7 100
>3 30 81
Office Version
3 to2 1 3
Blank 6 16 Type QTY %age
37 100 2013 1 3
2010 4 11
RAM (GB) 2007 7 19
Type QTY %age uknown 25 68
>=3 9 24 37 100
2 to 1 20 54
<1 2 5
Blank 6 16
37 100

Page 39
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.15. DIREDAWA FFIC


Operating System 1.1 Hard Disk Size (GB)

Type QTY %age Type QTY %age


win 7 26 84 1T 1 3
win 10 2 6 500GB 19 61
win xp 3 10 300GB 2 6
31 100 100GB 9 29
31 100
Processor (GHZ)
Type QTY %age Office Version

>3 27 87 Type QTY %age


3 to2 4 13 2010 1 3
31 100 2007 30 97
31 100
RAM (GB)
Type QTY %age
>=3 16 52
2 to 1 11 35
<1 4 13
31 100

Page 40
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.16. AKAKI FFIC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 13 68 1T 2 6
win 8 1 5 500GB 27 77
win 10 3 16 400GB 2 6
win xp 2 11 300GB 1 3
19 100 100GB 3 9
Processor (GHZ) 35 100
Type QTY %age
>3 32 91 Office Version
3 to2 2 6
Type QTY %age
<2 1 3
35 100 2013 2 1
2010 102 64
RAM (GB) 2007 52 33
Type QTY %age uknown 4 3
>=3 20 57 160 100
2 to 1 12 34
<1 3 9
35 100

Page 41
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6.17. KOLFE KERANIO FFIC


Operating System Hard Disk Size (GB)
Type QTY %age Type QTY %age
win 7 33 94 1T 3 9
win 8 1 3 500GB 26 74
win xp 1 3 400GB 1 3
35 100 300GB 2 6
100GB 3 9
Processor (GHZ)
35 100
Type QTY %age
Office Version
>3 30 86
3 to2 5 14 Type QTY %age
35 100 2013 6 17
2010 17 49
RAM (GB)
2007 12 34
Type QTY %age 35 100
>=3 17 49
2 to 1 16 46
<1 2 6
35 100

Page 42
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

ANNEX B: Existing Structural Cabling of the Federal Courts

Federal Supreme Court Head Office

Rack NO (Location): Judge-Building

Trunking: most of thecables are covered using trunking, but the trunking installed was damaged.

Cabling: most of the cables have labeling. Cables punched on patch panel and faceplate.

Wall outlet: there are single and double wall outlets, more details and positions will be on the annex.

Patch cord: different lengths of patch cords available.

Patch Panel: there are two types of patch panels fiber and UTP. Brands of the UTP patch panel are
Surlink. Most of them are 24 port and cat6. The patch panels are highly populated. Scalability is limited.

Rack Size and Cable Management: there are Three 12U racks in the Ground floor and first Floor of
the building. The cables are not managed properly

Active Device: There are 3 different Brand switches, ZTE,TP-Link and Cisco35600 series switches
located at the ground and first floor of the building. The catalyst switch 48 ports and with four combo
ports. The other two has 24 ports

Rack NO (Location): New Registrar-Building

Trunking: Data as well as voice cables are covered using trunking

Page 43
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Cabling: cables are labeled. Easily traceable

Wall outlet: there are wall outlets. their distribution is shown on the annex

Patch cord: different length of patch cords are available

Patch Panel: there are two types of patch panels fiber and UTP. Brands of the UTP patch panel are
Surlink. Most of them are 24 port and cat6. The patch panels are highly populated. Not scalable.

Rack Size and Cable Management: there are Three 12U racks in the Ground floor and first Floor of
the building. The cables are not managed properly

Active Device: There are 2 different series switches, Cisco 2960 and Cisco35600 series

Rack NO (Location): Admin-Building

Trunking: data and voice cables are covered using trunking

Cabling: cables are labeled. All cables are punched on the patch panel.

Wall outlet: wall outlets are distributed according to users in different offices.

Patch cord: patch cords are available at all offices but the patch cords are not uniform and standard,
some are short and some are too long.

Patch Panel: there are two types of patch panels fiber and UTP. Brands of the UTP patch panel are
Surlink. Most of them are 24 port and cat6. The patch panels are highly populated. Not scalable.

Rack Size and Cable Management: there are Three 12U racks in the Ground floor and first Floor of
the building. The cables are not managed properly

Active Device: There are 2 different series switches, Cisco 2960 and Cisco35600 series

Lideta Federal High Court Head Office

Rack NO (Location): Building-1: Third floor

Page 44
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Trunking: all the offices in the 3rd floor are not well covered the cables using trunking. Some cables
are passing outside of the trunk.

Cabling: cables are not well labeled. It is difficult to troubleshoot which cable terminated on which
office and which outlet. They are not well punched on the patch panel.

Wall outlet: wall outlets are not distributed according to users demand. In some offices there are
shortages in some there are excess nodes. The wall outlets are not labeled uniformly some are labeled
some are not. In general it is not standard.

Patch cord: patch cords are available at all offices but the patch cords are not uniform and standard,
some are short and some are too long.

Patch Panel: the brand of the patch panel is Surlink. It is 24 port and cat6. It is highly populated. All
the ports are punched with cables. So it is not scalable.

Rack Size and Cable Management: there are two racks in the 3rd floor with 4u, they contains one
switch and one patch panel. The size of the racks is to small and they are not scalable. Cables are not
managed well and it is to dirty. The power is not standard. The cables are not managed properly

Active Device: There are 2 catalyst Cisco 2960 series switches at each left and right corner of the 3 rd
floor. The switches are 24 ports and with two combo ports. They used for internet access. Both the
switches are highly populated, almost no free port, all are used, if expansion is needed it is difficult
since the size of the rack is 4u. In general it is not standard.

Rack NO (Location): Building-1: Second floor

Trunking: all the offices in the 2nd floor are not well covered the cables using trunking. Some cables
are passing out of the trunk. The data center is found in this floor. Uplink cables are not well covered
and running through trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable
terminates which office and which uplink goes to which floor switch as well as which outlet. They are
not well punched on the patch panel.

Wall outlet: wall outlets are not distributed according to users demand. In some offices there are
shortages in some there are excess nodes. The wall outlets are not labeled uniformly some are labeled
some are not. In general it is not standard and scalable. In the data center there no no node. Cables
are not punched on patch panel simply they are crimped with RJ 45

Patch cord: patch cords are available at all offices but the patch cords are not uniform and standard,
some are short and some are too long.

Page 45
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Patch Panel: the brand of the patch panel is Surlink. It is 24 port and cat6. It is highly populated. All
the ports are punched with cables. so it is not scalable.

Rack Size and Cable Management: there are two racks in the 2nd floor with 4u, they contains one
switch and one patch panel. The size of the racks is too small and they are not scalable. Cables are not
managed well and it is no clean and devices are covered with dusts. The power is not standard installed.
Especially in the data center room there is no standard power nodes.

Active Device: There are two 24 switches one is used all the 24 ports and one with 16 ports. One
switch is catalyst Cisco 2960 series and one is TP-link unmanaged switch. The Cisco switch has
additional two combo ports. Both the switches used for internet access. The Cisco switch is highly
populated, no free port is available. The unmanaged TP-Link switch populated only 16 ports of the 24
ports. In this floor still the scalability is difficult

Rack NO (Location): Building-1: First floor

Trunking: all the offices in the 1st floor are not well covered the cables using trunking. Some cables
are installed out of the trunk. Uplink cables are not well covered and running through trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes to
which office and terminated to which outlet. They are not well punched on the patch panel.

Wall outlet: wall outlets are not distributed according to user’s distribution. In some offices there are
shortages outlets, in some offices there are excess nodes. The wall outlets are not labeled uniformly
some are labeled some are not. In general it is not standard and scalable.

Patch cord: patch cords which available in the offices are not uniform and standard, some are short
and some are too long. No well managed.

Patch Panel: the brand of the patch panel is Surlink. It is 24 port and cat6. It is highly populated. All
the ports are punched with cables. So it is not scalable.

Rack Size and Cable Management: there are two racks in the 1st floor with 4u, they contains Two 24
Cisco catalyst 2960 series switch . The size of the racks is too small and they are not scalable. Cables
are not managed well and it needs cleaning and devices are covered with dusts. The power is not
installed in standard way.

Active Device: There are two 24 switches. Both the switches are Cisco catalyst 2960 series switch. The
switches ports are almost fully populated. The switches have additional two combo ports. Both the
switches used for internet access.

Page 46
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack NO (Location): Building-1: Ground Floor

Trunking: all the offices in the Ground floor are not well covered the cables using trunking. Some cables
are installed out of the trunk. Uplink cables are not well covered and running through trunking. Cables
specially at the counter offices are not well managed there is no trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes to
which office and terminated to which outlet. They are not well punched on the patch panel. The cables
in the counter offices are not managed well. Simple crimped cables help the computers to connected
for data access.

Wall outlet: wall outlets are not distributed according to user’s distribution. In some offices there are
shortages outlets, in some offices there are excess nodes. The wall outlets are not labeled uniformly
some are labeled some are not. In general it is not standard and scalable. The computers in the counter
have no wall outlet, uses crimped with RJ 45 cables.

Patch cord: patch cords which available in the offices are not uniform and standard, some are short and
some are too long. No well managed. Specially the cables in the counter offices are now well organized
and not standard, simple long cables running from the computer to the un managed switch (hub)

Patch Panel: the brand of the patch panel is Surlink. It is 24 ports and cat6 there are two patch panels
at the right most and left most corners mounted on the 4u rack. It is highly populated. All the ports are
punched with cables. So it is not scalable.

Rack Size and Cable Management: there are two racks in the Ground floor with 4u at the far right
most and left most corners. Each rack contains one 24 Cisco catalyst 2960 series switches. The size of
the racks is too small and they are not scalable. Cables are not managed well and it needs cleaning and
devices are covered with dusts. The power is not installed in standard way. The two un managed switches
found at the left and right side counter are not mounted on racks.

Active Device: There are four 24 port switches. Two of the four switches are Cisco catalyst 2960 series
switches. The Cisco switches ports are almost fully populated. The switches have additional two combo
ports. Both the switches used for internet access. There are two un managed 24 port 3com and D-Link
switches at both the left and right counters. The switches in the counter offices are partially populated.

Rack NO (Location): Building-2

Trunking: all the offices in this block are not well covered the cables using trunking. Some cables are
installed out of the trunk.

Page 47
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Cabling: cables are not well labeled. It is difficult which cable terminates which office and which outlet.
They are not well punched on the patch panel.

Wall outlet: wall outlets are not distributed according to user’s demand. In some offices there are
shortages in some there are excess nodes. The wall outlets are not labeled uniformly some are labeled
some are not. In general it is not standard.

Patch cord: patch cords are available at all offices but the patch cords are not uniform and standard,
some are short and some are too long.

Patch Panel: No patch panel

Rack Size and Cable Management: there is one rack installed at Ground floor right side corner. The
size of the rack is 4u with one un managed switch and un managed 19 cables crimped with RJ 45. The
rack is not clean and it is not standard.

Active Device: There is one TP-Link un managed switch right corner of the ground floor. The switch
is 24 ports. It uses for internet access. the 19 ports of the switch used, there are 4 port unused, if
expansion is needed it is difficult since the size of the rack is 4u. In general it is not standard.

Rack NO (Location): Building-3-Ground floor

Trunking: Not all the cables in building 3 ground floors are covered with trunking. Some cables are
installed out of the trunk.

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes
to which office and terminated to which outlet. They are not well punched on the patch panel.

Wall outlet: wall outlets are not distributed according to user’s distribution. In some offices there are
shortages of node, in some offices there are excess nodes. The wall outlets are not labeled uniformly
some are labeled some are not

Patch cord: patch cords which available in the offices are not uniform and standard, some are short
and some are too long

Patch Panel: the brand of the patch panel is Surlink. It is 48 ports and cat6. 11 ports are punched
with cables.

Rack Size and Cable Management: there is one rack in the Ground floor with 4u at the right corners.
The rack contains one 24 Cisco switches. The size of the rack is too small and it is not scalable. Cables
are not managed well and it needs cleaning and devices are covered with dusts. The power is not
installed in standard way.

Page 48
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Active Device: There is one Cisco catalyst 2960 24 port switch. The Cisco switch ports is not fully
populated.. The switch has additional two combo ports. The switches used for internet access.

Rack NO (Location): Building-3-First floor

Trunking: Not all the cables in building 3 first floors are covered with trunking. Some cables are
installed out of the trunk.

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes
to which office and terminated to which node. They are not well punched on the patch panel. Some
cables are plugged directly to the switch with out punching on the patch panel.

Wall outlet: wall outlets are not distributed according to user’s distribution. In some offices there are
shortages of node, in some offices there are excess nodes. The nodes are not labeled uniformly some
are labeled some are not. Cables directly connected with the switch plugged to the computer directly.

Patch cord: patch cords which available in the offices are not uniform and standard, some are short
and some are too long

Patch Panel: the brand of the patch panel is Surlink. It is 48 ports and cat5. 15 ports are punched
with cables.

Rack Size and Cable Management: there is one rack in the first floor with 6u at the right corners.
The rack contains one 3com switches. The size of the rack is standard and scalable. Cables are not
managed well and it needs cleaning and devices are covered with dusts. The power is not installed in
standard way.

Active Device: There is one 3com switch. 22 ports of the switch are used. The switches used for
internet access.

Rack NO (Location): Building-4-Ground floor

Trunking: all the cables in building 4 ground floors are not covered with trunking.

Page 49
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes
to which office and terminated to which node. They are not well punched on the patch panel. Some
cables are plugged directly to the switch without punching on the patch panel.
Wall outlet: Cables are directly connected to switch plugged to the computer directly.

Patch cord: cables running from the switches use as patch cord

Patch Panel: no patch panel.

Rack Size and Cable Management: there is one rack in the first floor with 4u at the right corners.
The rack contains one D-Link switch. The size of the rack is no standard and scalable. Cables are not
managed well and it needs cleaning and devices are covered with dusts. The power is not installed in
standard way.
Active Device: There is one D-Link switch. 20 ports of the switch are used. The switches used for data
access.

Rack NO (Location): Building-4-First floor

Trunking: all the cables in building 4 first floors are no covered with trunking

Cabling: cables are not well labeled, even the cables that are uplinks. It is difficult which cable goes
to which office and terminated to which computer.

Wall outlet: No wall out let. Cables from the switch directly connected to the computer

Patch cord: no standard patch cord

Patch Panel: no patch panel in this floor.

Rack Size and Cable Management: there is no rack in the first floor building 4

Active Device: There is one D-Link switch. 22 ports of the switch are used. The switches used for data
access.
Rack NO (Location): Building-5-Ground floor--store

Trunking: all the cables in building 5 Ground floors are not covered with trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. Computers directly connected
to switches with crimping cables.

Wall outlet: no wall outlet.

Patch cord: no standard patch cord in this room

Patch Panel: no patch panel

Page 50
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack Size and Cable Management: No rack

Active Device: There is one D-Link switch. 6 ports of the switch are used. The switches used for data
access.

Rack NO (Location): Building-5-First floor-office 12,17,20

Trunking: all the cables in building 5 Ground floors are no covered with trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. Computers directly connected
to switches with crimping cables.

Wall outlet: no wall outlet.

Patch cord: no standard patch cord in this room

Patch Panel: no patch panel

Rack Size and Cable Management: No rack

Active Device: There are three D-Link with 8, 16, and 24port switch. Total 20 ports of the switches
are used. The switches used for data access.

Rack NO (Location): Closed Files

Trunking: all the cables in building 5 Ground floors are no covered with trunking.

Cabling: cables are not well labeled, even the cables that are uplinks. Computers directly connected
to switches with crimping cables.

Wall outlet: no wall outlet.

Patch cord: no standard patch cord in this room

Patch Panel: no patch panel

Rack Size and Cable Management: No rack

Active Device: There is one 8 port D-Link switch. Total 8 ports of the switches are used. The switches
used for data access.

Conclusion: In general the cables, racks and truncking are not structured and installed in a standard
way. Cables are scattered here and there in different offices.

Bench High Court Offices

Page 51
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack NO (Location): Arada bench High Court

Trunking: There is no trunking in all the offices.

Cabling: cables are pulled through windows and gates from one office to next office or from floor to
floor.

Wall outlet: no wall outlet.

Patch cord: no patch cord at all.

Patch Panel: no patch panel

Rack Size and Cable Management: No rack

Active Device: There are two D-Link with 16, port switch. Total 10 ports of the switches are used. The
switches used for data access and internet access.

Rack NO (Location): Menagesha Bench High Court(Amsit Kilo)

Trunking: most of the cable in this bench is pulled through trunking.

Cabling: cables in the offices are running through terminated using RJ 45.

Wall outlet: data nodes are terminated with wall outlet.

Patch cord: there are different lengths of patch cord.

Patch Panel: no patch panel

Rack Size and Cable Management: there are two 4u racks in this sub bench. The size of the rack is
too small and cables are not managed in a standard way.

Active Device: There are two D-Link with 16, port switch. Total 10 ports of the switches are used. The
switches used for data access and internet access.

Rack NO (Location): Menagesha Bench High Court(Semen Mezegaja)

Trunking: most of the cable in this bench is pulled through trunking.

Cabling: most of the cables in these offices are covered with trunking and terminated with patch
panel.

Wall outlet: data nodes are terminated with wall outlet..

Patch cord: there are different lengths of patch cord.

Patch Panel: there are total three 24 patch panels one at each racks

Page 52
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack Size and Cable Management: there are three 4u racks in this sub bench. The size of the rack
is too small and cables are partially managed using patch cords inside the rack.

Active Device: There are three D-Link with 24 port switch and one switch 16 ports.. The switches used
for data access only.

Rack 1(location 3rd floor right side) :Bole Bench High Court
RACK 2(location 3rd floor left side)

Trunking: most of the 3rd floor cables are covered using trunking. Some cables are installed out of
the trunk.
Cabling: the cables installed in the patch panel are well labeled, even the cables that are uplinks. But
it is not giving service. They use unmanaged cables that are connected with D-link from room to
room. It is difficult which cable goes to which office and terminated to which outlet. They are not well
punched on the patch panel.
Wall outlet: wall outlets are not distributed according to computer distribution. In some offices there
are shortages outlets, in some offices there are excess nodes. The wall outlets are not considering the
number of users per room.
Patch cord: patch cords which available in the offices are not uniform and standard, some are short
and some are too long. No well managed.
Patch Panel: the brand of the patch panel is LINKBASIC. It is 48 port each Rack and cat6.half of the
ports are punched with cables in each patch panel. So It can be scalable to fill the gap of users and
wall outlet per room.
Rack Size and Cable Management: there are two racks in the 3rd floor with 6u, they contain Two 24
patch panel with punched cables only.
Active Device: There are six 16 port D-link switches, one 8 port D-link switch and one ADSL used as
Switch.
Summary: as general two Rack are installed with one 48 patch panel each and full trunking from each
node in the 3rd floor. But there is no active device in the new rack because of those devices they are
not get service from this infrastructure. They use unmanaged cables that connect with D-link from
room to room. It is difficult which cable goes to which office.
Number of users: 45
Number of wall outlet installed: 31 double wall outlets one for data one for telephone
Number of computers :36

Page 53
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack NO (Location): Diredewa Bench High Court

Trunking: no Trunking

Cabling: no cable

Wall outlet: no wall outlet

Patch cord: some non-factory standard patch cords are connected with d link

Patch Panel: no patch panel

Rack Size and Cable Management: no Rack

Active Device: 4 d-link switches

Conclusion: there is no network infrastructure installed. as General in the Old building some
computers are connected with d-link to access internet and woreda net

Federal First Instance Court (FFIC), Kirkos Bench

Rack NO (Location):

Trunking: cables starting from the racks at each floor are covered with trunking.

Cabling: most of the cables in these offices are covered with trunking and terminated at one end with
patch panel and at the other end with wall outlet.

Wall outlet: nodes are terminated with wall outlet..

Patch cord: there are different lengths of patch cord.

Patch Panel: there are total six cat 6 with 24 ports patch panels mounted one at each racks

Rack Size and Cable Management: there are six 4u racks in this bench.

Active Device: There are seven D-Link switches. Five of the 24 port and two of the switches are 16
ports.

Federal First Instance Court, Yeka Bench

Rack NO (Location):

Trunking: cables starting from the racks at each floor are covered with trunking.

Page 54
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Cabling: cables are terminated with patch panel and keystones.

Wall outlet: cables at each office are terminated with wall outlet.

Patch cord: there are different lengths of patch cord.

Patch Panel: there are total six cat 6 with 24 ports patch panels mounted one at each racks

Rack Size and Cable Management: there are six 4u racks in this bench.

Active Device: There are nine D-Link switches. six of them are with 24 port , two of them switches
are 16 ports and one is 48 port.

NO RACK: Addis Ketema First Instance

Trunking: all the cables in building are not covered with trunking.

Cabling: some cables are connected with D-link but it is difficult and complex to identify witch cable
is connected to witch d-link

Wall outlet: no wall outlet

Patch cord: no patch cord

Patch Panel: no patch panel

Rack Size and Cable Management: there is no Rack.

Active Device:
one non manageable d-link switch
Two TP-link switches with 16 ports each.

Conclusion: as general there is no network infrastructure in this branch except three D-link switches
and some unmanageable cables used to connect with some users.
Number of users:35
Number of computers :28

Rack NO (Location): Diredawa First Instance Court

Trunking: no Trunking

Cabling: no cable

Page 55
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Wall outlet: some wall outlet and some cables in 3rd floor and 2nd floor are installed. But those wall
outlet and cables are not connected with patch panel because there is no Rack and patch panel.

Patch cord: no patch cord

Patch Panel: no patch panel

Rack Size and Cable Management: no Rack

Active Device: there are four d-link switches connected with computers in different room.

Conclusion: as general There is no network infrastructure except some d-link connected with some
computers.
Number of users:33
Number of computers :30
Number of wall outlet: 8 but not connected with patch panel.

Rack 1 (Location Judge office 105): Akaki First Instance Court


Rack 2(Location outside corridor 108)
RACK3(Location ICT office)
RACK4(Location ICT office)

Trunking: Most of the cables in the building are covered with trunking form Rack 1 and Rack 2 to
each node. But some trunking are not properly installed.

Cabling: Cat 6 cable are installed from RACK 1 and Rack 2 to each node with protected trunking. But
some of them are not properly protected

Wall outlet: wall outlets are not distributed according to users demand. In some offices there are
shortages in some there are excess nodes. The wall outlets are not labeled uniformly some are labeled
some are not. In general, it is not standard.

Patch cord: some standard one-meter patch cords are used to connect patch panel and D-link switch
but the other patch cords are not standard.

Patch Panel: There are two patch panel installed in Rack 1 and one Patch panel installed in Rack 2
48 patch panel: Rack 1
24 patch panel: Rack 1
24 patch panel: Rack 2

Rack Size and Cable Management:

Page 56
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RACK 1: 6U and it is managed by one-meter patch cord


Rack 2: 6u and it is managed by one-meter patch cord
Rack 3: 24U
Rack 4: 4u

Active Device:
one 48 port D-link installed in Rack 1
one 24 port D-link installed in Rack 1
one 24 port D-link installed in Rack 1
One 24 port D-link installed in Rack 2
One 24 Port D-link installed in Rack 4

Conclusion: The network Infrastructure is installed by the owner of the Building


Number of Wall outlet: 72
Number of Users: 87
Number of Computers: 42

Rack 1 (Location G-F left corridor) : Bole First Instance Court


Rack 2(location G-F right corridor)
Rack 3(location 1st-F left corridor)
Rack 4(location 1st –F right corridor)
Rack 5(location 2nd –F left corridor)
Rack 6(location 2nd –F right corridor)

Trunking: all the cables installed from the Rack on offices in the 2nd floor, 1st floor and Ground floor
is well covered using trunking. Some cables are installed out of the Rack and trunk from floor to floor.

Cabling: the cables installed in the patch panel are well labeled, even the cables that are uplinks. But
it is not giving service. They use unmanaged cables that connect with D-link from room to room. It is
difficult which cable goes to which office and terminated to which outlet. They are not well punched
on the patch panel.

Wall outlet: wall outlets are distributed according to computer distribution. In some offices there are
shortages outlets, in some offices there are excess nodes. The wall outlets are not considering the
number of users per room. Because users change their office from room to room through time. Thus
leads the users and wall outlet to difference.

Page 57
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Patch cord: patch cords which available in the offices are not uniform and standard, some are short
and some are too long. No well managed.

Patch Panel: the brand of the patch panel is LINKBASIC. It is 48 port each Rack and cat6.half of the
ports are punched with cables in each patch panel. So It can be scalable to fill the gap of users and
wall outlet per room.

Rack Size and Cable Management: there are two racks per floor in the 2nd ,1st and ground floor
with 6u, they contain Two 24 patch panel per floor with punched cables only.

Active Device: There is one ZTE access switch with 24 access ports.

Summary: as general two Rack are installed with one 48 patch panel each and full trunking from
each node in the 3rd floor. But there is no active device in the new rack because of those devices they
are not get service from this infrastructure. They use unmanaged cables that connect with D-link from
room to room. It is difficult which cable goes to which office.
Number of users:45
Number of wall outlet installed:31 double wall outlet one for data one for telephone
Number of computers :36

Rack NO (Location): Diredawa First Instance Court

Trunking: no Trunking

Cabling: no cable

Wall outlet: some wall outlet and some cables in 3rd floor and 2nd floor are installed. But those wall
outlet and cables are not connected with patch panel because there is no Rack and patch panel.

Patch cord: no patch cord

Patch Panel: no patch panel

Rack Size and Cable Management: no Rack

Active Device: there are four d-link switches connected with computers in different room.
Conclusion: as general There is no network infrastructure except some d-link connected with some
computers.
Number of users:33
Number of computers :30
Number of wall outlet: 8 but not connected with patch panel.

Page 58
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack 1(2nd floor right toilet side) : Kirkos First Instance Court
RACK 2(2nd floor Left toilet side)
Rack 3(1st floor right toilet side)
Rack 4(1st floor left toilet side)
Rack 5(G-f right toilet side)
Rack 6(G-f left toilet side)

Trunking: the cables in all the offices in the 2nd, 1st, & Ground floors are well covered using
trunking. But Some cables are installed out of the trunk.

Cabling: the cables installed in the patch panel are well labeled.

Wall outlet: wall outlets are not distributed according to computer distribution. In some offices
there are shortages outlets, in some offices there are excess nodes. The wall outlets are not
considering the number of users per room. Because users change their office from room to
room through time. Thus leads the users and wall outlet to difference.

Patch cord: patch cords which available in the offices are not uniform and standard, some are
short and some are too long. No well managed.

Patch Panel: the brand of the patch panel is BDN+. It is 24 port each Rack.

Rack Size and Cable Management: there are two racks in each floor with 4u, they contain one
24 patch panel each with punched cables and D-links. So the racks installed in the building are
not scalable they cannot add more patch panels and active devices.

Active Device: one D-link per patch panel is installed on each rack and also one d-link is
installed on social science office.

Conclusion: as General in the building there are six 4U Racks installed with one 24 port patch
panel and one d-link each. cables also installed from each node to nearest rack through
protected trunks. The racks installed in this branch are not scalable because they are very small
racks they cannot add additional devices.
Number of users:53
Number of wall outlet installed:36 single wall outlet
Number of computers :25

Page 59
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack 1(location 2nd floor right side): Yeka First Instance Court
RACK 2(location 2nd floor left side)
Rack 1(location 1st floor right side)
RACK 2(location 1st floor left side)
Rack 1(location Gr floor right side)
RACK 2(location Gr floor left side)

Trunking: the cables in all the offices in the 1st, 2nd and Ground floors are well covered using
trunking. But Some cables are installed out of the trunk.

Cabling: the cables installed in the patch panel are well labeled, even the cables that are uplinks.

Wall outlet: wall outlets are not distributed according to computer distribution. In some offices
there are shortages outlets, in some offices there are excess nodes. The wall outlets are not
considering the number of users per room. Because users change their office from room to
room through time. Thus leads the users and wall outlet to difference

Patch cord: patch cords which available in the offices are not uniform and standard, some are
short and some are too long. Not well managed.

Patch Panel: the brand of the patch BDN+. It is 24 port patch panel and each Rack contains
one 24 port patch panel. Above half of the ports are punched with cables in each patch panel

Rack Size and Cable Management: there are two racks in each floor with 4u, they contain one
24 patch panel per rack with punched cables. So the Racks are not scalable because they cannot
add additional devices

Active Device: there are three d-links in ground floor, four d-links in 1st floor and two d-links
in 2nd floor are installed.

Summary: as general two Rack are installed with one 24 patch panel each and full trunking
from each node in the 2nd, 1st and ground floor. But the rack installed in each floor are not
scalable because their size is 4u. nine d-link also installed in the building.
Number of users:45
Number of wall outlet installed:19
Number of computers :40

Page 60
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

ANNEX C: Network Infrastructure Distribution Summary


C-1: Federal Supreme Court
User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node

384 314 357


Rack, Patch panel distribution
Type № of port/ № of Used
panel brand QTY Model Rack Size
(PORT) rack Port
D-LINK 1
LINKBASIC 6 CAT 6 24 144 96 2*6U
Sur-Link 23 CAT 6 24 552 306 9*6U &4*12U

Page 61
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

CAT 5 1 CAT 5 16 16 1 6U
Inf-link 1
NO BRAND 9 FIBER 24 216 11 4*6U, 1*12U & 1*4U

C-2: LIDETA FHC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
272 199 173

Rack, panel distribution


Type № of Used
panel brand QTY Model № of port Rack Size
(PORT) Port
CNET 10 CAT 6 24 240 145 6*4U, 1*6U, 1*27U
AMP 1 CAT 6 24 24 0 1*6U
CAT5 e 1 CAT5 e 48 48 15 1*6U
D-LINK 1 CAT 6 48 48 11 1*4U
NO PANEL 6 0 1*4U

C-3: KALITY FHC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
46 26 126

Rack panel distribution


№ of Used Rack Rack installed
panel brand QTY Model Type № of port
Port Size Location
Link Basic 10 CAT 6 9X24,1X48 288 29 12u
Mini pro 2 CAT 6 48 96 0 12u

C-4: ARADA FHC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
4 6 0

C-5: BOLE FHC

Page 62
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

User, Computer Vs Node Distribution summary


Total № of User Total № of Computer Total № of Node
45 30 66

Rack, patch panel distribution


Type
Patch panel brand QTY Model № of port № of Used Port Rack Size
(PORT
LINK BASIC 3 CAT 6 48 144 0 2*6U

C-6: DIREDAWA FHC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
28 25 0

Rack, Patch panel distribution


C-7: LIDETA FFIC
User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
135 147 62

C-8: YEKA FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node

56 39 17

Rack Patch panel distribution

panel brand QTY Model Port № of port № of Used Port Rack Size

BON+ 6 CAT 6 24 144 48 6*4U ZTA

C-9: MENAGESHA FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node

61 24 86

Rack Patch panel distribution

Page 63
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

№ of Used Rack installed


panel brand QTY Model Type № of port Rack Size
Port Location
No panel 1*24U
No panel 2*4U

C-10: NIFAS SILK LAFTO FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
30 28 1

Rack, Patch panel distribution


Patch panel № of port/ № of Used Rack Rack installed
QTY Model Type
brand rack Port Size Location
NO NO NO NO NO NO 1*4 U

C-11: KIRKOS FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
73 44 57

Rack, Patch panel distribution


Patch panel № of Used Rack Rack installed
QTY Model Port № of port
brand Port Size Location
BDN+ 6 CAT 6 24 144 72 4U

C-12: ARADA FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node

27 27 0

Rack, Patch panel distribution


No rack & panel
C-13: ADDIS KETEMA FFIC
User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
35 36 2

Page 64
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack, Patch panel distribution


No rack& panel
C-14: BOLE FFIC
User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
107 32 142

Rack, Patch panel distribution

Patch panel brand QTY Model Type № of port № of Used Port Rack Size

Link Basic 6 Cat 6 48 288 142 6*6U

C-15: DIREDAWA FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
33 28 7

Rack, Patch panel distribution


No rack & patch panel
C-16: AKAKI FFIC
User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
90 32 77

Rack, Patch panel distribution


Patch panel
QTY Model Type № of port № of Used Port Rack Size
brand
S-Link 2 SL-F624 24 48 15 1*4U &1*6U
APKR 1 APKR 48 48 24 6U

C-17: KOLFE KERANIO FFIC


User, Computer Vs Node Distribution summary
Total № of User Total № of Computer Total № of Node
47 34 30

Page 65
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Rack, Patch panel distribution


Patch panel № of port/ № of Used Rack Rack installed
QTY Model Type
brand rack Port Size Location
24U 1

ANNEX D: Switch Router and Firewall data Summary

Switch Router and Firewall data summary per Branch


C-2-1: Federal Supreme Court Switch, Router & Firewall Data summary
Switch Router Type Total № Total № of
Model QTY Service
Brand Brand (port) of Port Used Port

ZTE cisco 2 x R10 3928A 7 24 168 139 Internet access


internet access & DATA
cisco 2960 15 24 360 198 CERVICE

D-link DES 1008A 1 8 8 8 internet ACCESS

HUWAIE AR 2200 2 2 4 4 internet access

Page 66
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

TP-LINK TL-SP-1048 2 48 96 63 internet access


" TL-SP-1024 1 24 24 18 internet access
internet access & Data
3 COM 3 COM 2 24 48 47 service

C-2-2: LIDETA FHC Switch, Router & Firewall Data summary


Switch Router Total № of Total № of
Model QTY № of Port Service
Brand Brand Port Used Port

CISCO 2960 9 24 216 191 ACCESS

" 3560 1 24 24 10 DISTIBUTION

CISCO 1841 2 2 4 2 INTERNET


DLINK DES 1024 2 24 48 18 ACCESS

DES 1016 2 16 32 12 ACCESS

DES 1008 2 8 16 16 ACCESS


3.COM Base2024 2 24 48 33 ACCESS
TPLINK TL-SF 1024D 2 24 48 40 ACCESS
Td1008A 1 8 8 8 ACCESS

C-2-3: KALITY FHC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-LINK DES-1024A 3 24 72 0 ACCESS SWITCH

C-2-4: ARADA FHC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D- LINK DES 10-16 2 16 32 16 INTERNET

TPLINK TL-SF-1024 1 24 24 7

C-2-5: BOLE FHC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-Link DES-1016D 5 16 80 42 access switch
DES-1008D 1 8 8 4 access switch

Page 67
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

C-2-6: DIREDAWA FHC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-Link DES-1008A 2 8 16 12 Access Switch

D-Link DES-1016A 1 16 16 16 Access Switch

Tp-link Tp-link 1 8 8 8 Access Switch

C-2-7: LIDETA FFIC Switch, Router & Firewall Data summary


Switch Router № of Total № of Total № of
Model QTY Service
Brand Brand Port Port Used Port

cisco 1920 serie 1 2 2 2 internet access

cisco 2900 2 24 48 31 internet access


internet distribution
D-Link
DES 1024D 8 24 192 82 & access

DES 1016D 2 16 32 25 internet access

V1416-24 19663A
HP 8 24 192 136 internet access
Rsrlc1100 1 8 8 4 internet access

TPLINK 1 16 16 11

3 COM 1 24 24 16

C-2-8: YEKA FFIC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-LINK DES-1016D 2 16 32 10 Access switch
D-LINK DES-1024D 6 24 144 65 Access switch

D-LINK DES-1050G 1 48 48 4 Access switch

C-2-9: MENAGESHA FFIC Switch, Router & Firewall Data summary


Total № Total № of
Brand Model QTY № of Port Service
of Port Used Port

D-LINK DES-1016 16 DATA ACCESS


1 16 8

Page 68
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

D-LINK DES-1024 120 DATA ACCESS


5 24 101

C-2-10: NIFAS SILK LAFTO FFIC Switch, Router & Firewall Data summary
Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
BASELINE 3 COM 1 24 24 3 ACCESS

D-LINK DES-1016 1 16 16 3 ACCESS


D-LINK DES-1024 1 24 24 11 DISTRIBUTION

TIPLINK TLSF 1024 3 24 72 37 ACCESS

C-2-11: KIRKOS FFIC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-LINK DES 1016 2 16 116 ACCESS SWITCH

D-LINK DES 1024 5 24 60 ACCESS SWITCH

C-2-12: ARADA FFIC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D- LINK DES 10-16D 2 16 32 19 INTERNET

DES 10-24D 2 24 48 16 INTERNET & DATA

C-2-13: ADDIS KETEMA FFIC Switch, Router & Firewall Data summary
Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
TP-link TLSF1016 2 16 32 13 access switch

D-link DES-1024D 1 24 24 22 access switch


C-2-14: BOLE FFIC Switch, Router & Firewall Data summary
Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
ZTE 3928A ZYR 10 1 28 28 16 Access switch

C-2-15: DIREDAWA FFIC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-LINK DES-1008D 1 8 8 8 ACCESS SWITCH

D-LINK DES-1016D 2 16 32 23 ACCESS SWITCH

D-LINK DES-1024D 1 24 24 0 ACCESS SWITCH

Page 69
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

C-2-16: AKAKI FFIC Switch, Router & Firewall Data summary


Total № of Total № of
Brand Model QTY № of Port Service
Port Used Port
D-Link DES-1024D 3 24 72 14 access

DES-1050G 1 50 50 36 access

C-2-17: KOLFE KERANIO FFIC Switch, Router & Firewall Data summary
Brand Model QTY № of Port Total № of Total № of Service
Port Used Port
D-Link DES-1024D 3 24 72 14 access
DES-1050G 1 50 50 36 access

Annex E – Office Locations of Federal Courts

The following table summarizes the Office locations of the Federal Courts:

No. Name of Directorate /Court Office Location

Sidist Kilo, above the Ministry of


1. Federal Supreme Court Head Quarter
Finance and Economic Cooperation

2. Federal High Court Head Quarter Lideta Sub City

Page 70
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

No. Name of Directorate /Court Office Location

3. Federal First Instance Court Head Quarter Lideta Sub City

4. Diredawa Federal High Court Dire Dawa

5. Diredawa Federal First instance Court Dire Dawa

Sidist Kilo, in front of St Yared Music


6. Office of Judicial Execution
School

Women and Youth Directorate of the Federal


7. Sidist Kilo, opposite to Sanford
Supreme Court
International School
8. Federal Sheria Court

9. Bole Federal High Court Bole Sub City

10. Arada Federal High Court Arada Sub City

11. Kality Federal High Court Akaki Kality Sub City

12. Lideta Federal High Court Lideta Sub City

13. Lideta Federal First Instance Court Lideta Sub City

14. Akaki Kality Federal First Instance Court Akaki Kality Sub City

15. Addis Ketema Federal First Instance Court Addis Ketema Sub City

16. Arada Federal First Instance Court Arada Sub City

17. Bole Federal First Instance Court Bole Sub City

18. Menagesha Federal First Instance Court Gulele Sub City

19. Kirkose Federal First Instance Court Kirkose Sub City

20. Kolfe Keraniyo Federal First Instance Court Kolfe Keraniyo Sub City

21. Nefas Silk Lafto Federal First Instance Court Nefas Silk Lafto Sub City

22. Yeka Federal First Instance Court Yeka Sub City

Page 71
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

The 17 Federal Courts are currently operating in these locations, and wide area networking of

all of these locations is being studied by this project.

Page 72
Annex F: Existing LAN Layout of Federal Courts

Yeka FFIC Layout

1 Node

1 Node

1 Node
007 005
Casher Room 006 Judge Room Family Council
Court Sec
1 Node
1 Node 1 Node 1 Node
2 Node

1 Node

0
2 Node

03
Social Workers

1 Node

1 Node Registrar
3 Node
012 2 Node
Info Desk

1 Node Design By

014 Project YEKA FFIC


Client Complain
Reception Building
Single Data Node
Double Data Node
RACK
Legend
Total N0 of
20
Nodes

GROUND FLOOR

Page 73
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

104
Judge
1 Node
Room

2 Node

3 Node 3 Node 3 Node


1 Node

1 Node

1 Node Office

1 Node
Up

6 Node

1 Node 1 Node 1 Node


3 Node

Design By

Project YEKA FFIC

Building
Up
Single Data Node
Double Data Node

RACK
Legend
Total N0 of
27
Nodes

1ST FLOOR

Page 74
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

1 Node

1 Node

3 Node
3 Node 2 Node
2 Node
5 Node

1 Node

Office

2 Node

5 Node
1 Node
3 Node

1 Node 2 Node
1 Node

Design By

Project YEKA FFIC

Building 2ND FLOOR

Up
Single Data Node
Double Data Node

RACK
Legend
Total N0 of
Nodes
33

ND
2 FLOOR

Page 75
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Akaki FFIC Layout

1 1
2 node 2 node
1 node 2 node 2 node node
node 1
4 node node
126
130 122 120
129 128 124 123 121 118
1 1
node 127 117 node
4 node

116 1
131 node
1
115 node

1
node 1 105 106
1 107 1
1 node node
node 2 node
132 139 node 140
3 node 1 141
node
1 114
node 108
133 10 node
102
104 4 node
134 1 109
4 node node
1 112
138 node 2 node
Archive
142 103
3 node 1
2 node
135 node 111
136 137 8 node

Page 76
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Kality FHC Layout

2 node
9
2 node
1 6

2 node
10
Up 5

2 node
11

12

13
7 node

18
1 14
node
15
2 node

17
2 node

Page 77
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up

Page 78
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

3 node

27 3 8

Up
11
6 node 5 2 node
ICT
12

9 10 13
25
8 node 18
24 23
15

17
28
18
3 node 3 node
19
20
22
29 21

Page 79
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

3 node
2 node 11
3 node
Up
27 5 12
5 node 9 10
9
28 node
26 24

4 node
25
4 node

29 3 node

23 15
16
30 22 21
17
1 NODE
5 node 18
7 20 19
node

BOLE FFIC Layout


Page 80
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up
Page 81
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

6 Node 8 Node 8 Node 2 Node 2 Node


Up

106 105 104 103 102 101

107

Up
1 Node

108
1 Node

Judges Café

Page 82
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

2 Node
4 Node 8 Node 8 Node 6 Node 1 Node
Up

206 105 204 203 202 201


1 Node

Up
214

1 Node

212
213
2 Node

207 208 209 210 211

2 Node 2 Node 2 Node 2 Node 2 Node

BOLE FHC Layout

Page 83
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

3 Node 3 Node 3 Node 4 node 2 node 2 node

206 205 204 203 202 201

Up
219
213 214 215 216 217 218

2 node 2 node 2 node 1 node 1 node

MENAGESHA 5 KILO BRANCH Layout

Page 84
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Secretary &
5 Node Voice Cash Room
Recorder
8 Node 4 Node
6 Node Data Base
Information
Desk 4th Criminal Bench
TRANSCRIBER R.Nº 5 Judge Office
R.Nº 4 R.Nº 7
R.Nº 3

R.Nº 3
R.Nº 2
R.Nº 3

Registrar

Page 85
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

1st Criminal
Bench

4th Criminal Bench

2 Node
R.Nº 12
R.Nº 9
3rd Criminal

R.Nº 11
Bench Judge
Office
R.Nº 10

2 Node Judge Office

Page 86
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Menagesha FFIC SEMEN MAZEGAJA Layout

4 Node
2 Node

INFORMATION R. Nº 3
DESK

R. Nº 2
Up

SEMEN MAZEGAJA
GROUND FLOOR

Page 87
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Toilet

SEMEN MAZEGAJA
1ST FLOOR

Page 88
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

1st Fitabiher Judge

R.Nº
1ST, 2ND, 3RD Work
Argument bench

R.Nº 11

R.Nº 10
4 Node

JUDGE OFFICE
Toilet
4 Node

Page 89
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

4 Node

R.Nº 11
4 Node
R.Nº 12

Toilet

SEMEN MAZEGAJA 3 FLOOR

Page 90
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

LEDETA FHC

8 Court

Up
Up
2 Criminal 18 Criminal 15 Criminal 5 & 6 Criminal
Court Room Court Room

13 Criminal court
Court Room Court Room
3 Criminal court

2 Criminal court

1 Criminal court
14&16 Criminal

11&12 Criminal

Plasma Room
10 Criminal
5 & 6 Court
Judge

Judge

Judge
Judge

Court
court

Court
8 Court

15 Court
TOILET
202

204

TOILET
40198mm

Design By

Project LIDETA-FHC

Building FHC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 42 Nodes

Ground Floor

Page 91
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

411 Court Sec

415 Court Head


412 Registrar

414 Messenger
413 416 Registrar 417 Server Room 410 IT 419 Secretary

425 Photo
428 427 Database Copy 424 423 422 421 420

Up
Toilet Toilet
Toilet

Design By

Project LIDETA-FHC

Building FHC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 46 Nodes

SECOND

Page 92
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

509 Library
Conference Room

503 Finance Director 505 Court MGR sec. Human Resource 507 Team Leader 508 Property MGT
502 Audit

518 Finance Head 517 Finance 516 Casher 515 Budget 514 513 Director 512 MGT 511 510 HR

Up
Toilet
Toilet Toilet

Design By

Project LIDETA-FHC

Building FHC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 46 Nodes

THIRD FLOOR

Page 93
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

803

804

802

805

801 Court

806 Court

Toilet
Toilet

GROUND B2

808 Court

807 Court

Design By

Project LIDETA-FHC

Building FHC BUIL- 2

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 7 Nodes

Ground Floor

Page 94
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

811
812

Data encoder
B2

809 816

Up
Design By

Project LIDETA-FHC

Building FHC BUIL- 2

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 4 Nodes

FIRST FLOOR

Page 95
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Toilet

Toilet

707 706

705

708 704 Court

B-3

701 Design By

702 705
Project LIDETA-FHC

Building FHC BUIL- 3

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 5 Nodes

Ground Floor

Page 96
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

710 709

711 714

712 713

Design By

Project LIDETA-FHC

Building FHC BUIL- 3

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 9 Nodes

FIRST Floor

Page 97
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

602

Up
603

601 Court Room

604 Court Room

608 Court Room

605 Court Room

607
606

Toilet

Design By

Toilet Project LIDETA-FHC

Building FHC BUIL- 4

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 6 Nodes

GROUND Floor

Page 98
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

610 Transcriber 609 Court sec.

612 court sec.

611 611

Design By

Project LIDETA-FHC

Building FHC BUIL- 4

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 4 Nodes

FIRST Floor

Page 99
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up
6 5 4 3 2 1

B-5
White House

100 Info. Desk

Page 100
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

20 27

13 12

Up

LEDETA FFIC Layout

Page 101
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

006

Up
007

TOILET
008

TOILET
005

009
012

004
011
r
te
n
u
o
C

Up

LIFT
Office

002 003

Page 102
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

113 114 1 NODE

115 116 117


101

Lift

102 112

111
103

109
2 NODE

p
U
108 118
104

107

p
U
Design By

Project LIDETA-FFIC

105 106
Up

Building FFIC BUIL Lift


Single Data Node
Double Data Node
1 NODE
RACK
Legend
Total N0 of
Rack 4 Nodes

FIRST FLOOR

Page 103
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

2 NODE 1 NODE
2 NODE 1 NODE
212 211
213
215 214 210

Lift Lift

216
201
3 NODE Up

217 209
2 NODE

3 NODE 2 NODE
218
208
202
219

3 NODE
207
203

Design By 206

Project LIDETA-FFIC 2 NODE


Building FFIC BUIL

Single Data Node 1 NODE 204


Double Data Node
205
Legend
RACK Lift Lift
Up

Total N0 of
Rack 22 Nodes

SECOND FLOOR

Page 104
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

314
2 NODE

313 312 311

315 Up

2 NODE

31
0
1N
OD
E

31
6
301
1 NODE

30
9
7
30
8
30
302
4N

6
4 NODE

30
OD
E
1N
OD
E

303
304 305
Up

1N
OD
E

Design By

Project LIDETA-FFIC

Building FFIC BUIL

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 16 Nodes

THIRD FLOOR

Page 105
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

1 NODE 1 NODE 1 NODE 1 NODE

415 414 413 412


416

Up

3 NODE

426
3 NODE 4 NODE
42 411
41 5
8 42
4
41 42 422 409
417 9 3
42
0
2 NODE

42
1
410

2 NODE
1 NODE
401

408

407 3 NODE
402

403 404 405 406

1 NODE
1 NODE

Design By

Project LIDETA-FFIC

Building FFIC BUIL

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 24 Nodes

FOURTH FLOOR

Page 106
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

KIRKOS FFICE Layout


0 0

014

Up

1 Node 1 Node
013 Archive
018 017

09 01 02

0 2 Node

004
012
0

005
1 Node
008 007 006
Cafeteria

Office
t
011 Toile Cafeteria 0 0

010 0
1 Node 1 Node 1 Node

Design By

Project KIRKOS-FFIC

0
Building FFIC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 8 Nodes

GROUND FLOOR

Page 107
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

0 0

Up

4 Node
1 Node
0

4 Node 116 1 Node


ICT Judge Judge Judge
Database

101 102 103 104 105


1 Node
Secretary 115 Office

1 Node
106
112 111 110
0

100 107
108
0
0

114 2 Node 2 Node


3 Node
113 0
2 Node

1 Node Design By

Project KIRKOS-FFIC

0
Building FFIC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 22 Nodes

FIRST FLOOR

Page 108
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

0 0

Up

3 Node 0

5 Node
201
3 Node
218

202 203 204


205

1 Node Office
215 2 Node
206

211 210 209


0 2 Node
0

205 207
208
0
0

213
1 Node 3 Node 3 Node 2 Node
0

Judges Design By

office Project KIRKOS-FFIC

0
Building FFIC

Single Data Node


Double Data Node
RACK
Legend
Total N0 of
Rack 25 Nodes

SECOND FLOOR

Page 109
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

0 0

Up

Office

0
0

Page 110
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

NIFAS SILK LAFTO FFIC Layout

Up
Secretary Judge

2 6

Judge

Information
Desk
Judge

Page 111
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

13 12

16 17

Up
Up

Page 112
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

13 12

16 17

Up
Up

Page 113
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

ARADA FHC Layout

Office office O.NO-03

Toilet

Court Hell
Judges

Up
ARADA FHC 1ST F

Page 114
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Judges
O.NO-08 Meeting Hell

Secretarial Record and


Archive

Up
ARADA FHC 2ND F

Page 115
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

O.NO-30

O.NO-04
Court Hell

Up
ARADA FHC 3RD F

Page 116
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

O.NO-11 O.NO-10
ICT
O.NO-12

O.NO-09

O.NO-13 O.NO-08 Toilet


O.NO-07

Up
ARADA FHC 4TH F

Page 117
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

ARADA FFIC Layout

O.NO-07 O.NO-08

O.NO-03

Waiting Area

O.NO-06
O.NO-03

O.NO-05 O.NO-04 O.NO-01 O.NO-02

Up
ARADA FFIC 1ST F

Page 118
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

O.NO-07 O.NO-08

O.NO-03

Waiting Area

O.NO-06
O.NO-03

O.NO-05 O.NO-04 O.NO-01 O.NO-02

Up
ARADA FFIC 1ST F

Page 119
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Lobby

Waiting Area
Cabinet
File
Toilet
O.NO-30

Cabinet

Toilet
O.NO-29

File

Toilet
O.NO-04
Waiting Area

O.NO-32 O.NO-26 O.NO-27 O.NO-28

Up
ARADA FFIC 3RD F

O.NO-25

Federal Supreme Court 6 KILLO Layout

Page 120
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

R.Nº 1 PROPERTY
R.Nº 2 R.Nº 3 R.Nº 4 R.Nº 5
ADMIN

1 Node 3 Node
COURT

SEBER COURT

PRISIONER
WAITING
ROOM

Page 121
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

COURT 1ST & 2ND COURT TRANSCRIBE


SECRETARY SCAN TENABABI TRANSCRIBER R
SECRETARY
4 Node 2 Node

CHILDREN LAW

CHILD JUSTICE
PROTECTION

PROTECTION

8 Node
OFFICE
4 Node
R.Nº 8 PHOTOCOPY
ROOM

4 Node
2 Node

SOCIAL
PHYICOLOGY
R.Nº 7
SERVICE
8 Node

R.Nº 6

1ST & 2ND COURT


SERVICE SECRETARY

FEDERAL
2 Node POLICE

TRANS
PORT

SECURITY

Page 122
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

4 Node
4 Node Federal Judge Federal
Operator Court Judges
MGT Dicplene

ARCHIVE

GROUND FLOOR

AMHARA
Court Archive Ethics REGIONAL
STATE
4 Node Up
TOILET

TOILET

TOILET
R 201 R 203 R 204 R 205
1 Node 4 Node

4 Node R 213 R 214 R 215 R 216


R 210 R 211 R 212
4 Node Up
4 Node

Page 123
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

TOILET
3 Node TOILET
R.Nº 302 R.Nº 306 R.Nº 307
R.Nº 301
R.Nº 303 R.Nº 304 R.Nº 305
6 Node 6 Node

2ND FLOOR

R.Nº 314
R.Nº 310
R.Nº 311 R.Nº 312 R.Nº 315
2 Node 2 Node 2 Node
2 Node Up

TOILE
T
TOILET R.Nº 406
R.Nº 407
R.Nº 405 R.Nº 404

R.Nº 403

MEETING HALL 3RD FLOOR

R.Nº 401 R.Nº 402

Up

Page 124
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

9 Node
TOILET ICT
ICT DEP DIRECTOR
JUDGE
OFFICE
TOILET
COURT
SECRETARY
1 Node
R.Nº 101 R.Nº 102 R.Nº 103 R.Nº 113
R.Nº 111

Up
GROUND
R 105 R.Nº 108 R.Nº 110
R.Nº 104 FLOOR

JUDGE ICT COURT


OFFICE 1 TEAM
Node

VP
SECRETARY

2
Up

1ST FLOOR

R.Nº 201 R.Nº 202 R.Nº 203 R.Nº 204 R.Nº 205 R.Nº 206 R.Nº 207 R.Nº 209
1

VICE
PRESEDENT

Page 125
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Public 3 Node
Relation and 15
Management Finance

Audit 1 Node
2 Node
Directorate

Up

2 Node

Court
2

Finance
Directorate 6
4 Node

Finance General

Up
Directorate Accountant
2 Node Court
Management
1 Node

Page 126
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up
Casher Library Casher

22 1 Node
16 1 Node

25 Public
24 Relation
directorate 20
1 Node
Public
Relation

Up

HRM
27
26
4 Node
18 19

General
Services

Page 127
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

2 NODE
7 NODE
Scam Court Secretary Database Casher Registrar
17 NODE

Secretary Court Secretary Database

7 NODE 7 NODE

Federal Supreme Sheria Court - Layout


Page 128
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up
Up

18

19
Design By

20 26 Project SHERIA
25

21 Building
24
Single Data Node
22 23
Double Data Node

RACK
Legend
Total N0 of
0
Nodes

Basement FLOOR

Page 129
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

8 6 5

Up

Up

Design By 4

Project SHERIA

Building
3
Single Data Node
Double Data Node

RACK
Legend
2
Total N0 of
0
Nodes

GROUND FLOOR 1

Page 130
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Up
Up

18

19
Design By

20 26 Project SHERIA
25

21 Building
24
Single Data Node
22 23
Double Data Node

RACK
Legend
Total N0 of
0
Nodes

1ST FLOOR

Page 131
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

32 31 30 29 28
27

Up

Up

Design By

Project SHERIA

Building
Single Data Node
Double Data Node

RACK
Legend
Total N0 of
0
Nodes

2ND FLOOR

Page 132
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

38 37 36 35 34 33

Up

Up

Design By

Project SHERIA

Building
Single Data Node
Double Data Node

RACK
Legend
Total N0 of
0
Nodes

3RD FLOOR

Page 133
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

44 41
43 42 40 39

Up

Up

Design By

Project SHERIA

Building
Single Data Node
Double Data Node

RACK
Legend
Total N0 of
0
Nodes

4TH FLOOR

Page 134
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

FEDERAL SUPREME COURT Judiciary Execution


RACK

Page 135
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RACK

Page 136
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RACK

Page 137
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RACK

Page 138
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

RACK

Page 139
Annex G – Observation Report

SERVER ROOM

In most of the sites no separate server room are prepared. Servers found in the ICT room

or Database room. In some locations, the allocated room does not full fill the room or data

centre requirements for the server safety such as air conditioner, fire extinguisher or cable

manager.

Rack

• The installed rack size is small cannot accommodate the network device and cables pulled

in the area. It doesn’t allow further network expansion

• The cables in the rack are not managed

Node

There is no adequate node for users/computers in most of the courts. Some nodes are not

installed properly but installed just to fulfil the immediate necessity. Moreover, some

networks have been made available by pulling outside trunking, patch panel and switch.

Page 140
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Cabling

Copper cable

No uniform cable utilization is observed. Even in one site, two or more types of cables are

used at the same time (like CAT6, CAT 6e, BMT) which are different in thickness. In some

locations, cables are pulled outside the trunking which cause damage to the cable and

shorten its life time.

Page 141
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

Fiber cable

Fiber cable is used for cascading network from data centre to different rack in different

places as backbone. At the Federal Supreme Court most of the rack has fiber backbone

except for one building. The back draws observed on fiber cable installation is they used

telecommunication pole for fiber cable pulling root if tele want to change its pole they may

get affected. Building to building pulling system advantageous since increases the height

from the ground and reduce risk of damage by loaded vehicle. In other courts the cable for

uplink and backbone is copper.

Trunking

Their size is small to accommodate the existing cable and if it need expansion not possible.

Some of them are old and damaged

Patch panel and access switch

Page 142
Document: Identification Number:

Existing Situation Analyses Document XOKA/R/01

There is no uniform utilization of network device in the racks. Some of them has patch panel

but no switch like Bole FHC in other place just only switches place in the rack without patch

panel like Lideta FFIC. The types of switches exist in majority of the places are not

manageable.

Configuration

There is no switch, router configuration except Network Address Translation (NAT) on the

routers for all Federal Courts.

Page 143

You might also like