Question 28

Marks: 1/1
A dual hierarchy is the salient feature of a:
Choose one answer.
a. bi-modal structure.
b. matrix structure. correct
c. project structure.
d. functional structure.
Correct

Question 29
Marks: 1/1
Staffing fluctuations associated with project completion and initiation are most likely to
occur in organizations that are:
Choose one answer.
a. project structured.
b. functionally structured. correct
c. process structured.
d. matrix structured.
Correct

Question 30
Marks: 0/1
Process management features __________ with respect to project management.
Choose one answer.
a. greater numbers of goals and objectives incorrect
b. lower adherence to established practices
c. greater heterogeneity
d. greater certainty of performance
Incorrect

Question 31
Marks: 1/1
Successful firms use project portfolio planning routinely to:
Choose one answer.
a. develop products with long lead times and plan ahead. correct
b. make quantum jumps from one product to another.