You are on page 1of 134

LPIC-EPC4 NGL PIPELINE AND OGC 32” GAS LOOPLINE

HDD METHOD STATEMENT FOR INSTALLATION OF 14” & 32” CS


PIPES (For Canal Crossing)

DOCUMENT NO.

F900-CN-MST-00001-00-PGEP (LPIC)
FAH/SHR-9-3013-001-R1-4-A (OGC)

CONTRACT NO.: 4600002122 (LPIC)


OGC/01/2016 (OGC)

VENDOR/SUPLLIER NAME AND ADRESS:

GULF ENGINEERING PROJECTS LLC, MUSACT, OMAN

LOA/PO NO.: PLL/ORPIC/HDD/001 REV:00

This document is the property of Oman Gas Company SAOC. & Orpic Plastic LLC. Neither the whole nor any part of this document
may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means (electronic,
mechanical, reprographic recording or otherwise) without prior written consent of the owner.

Mina Al Fahal, Muscat PO Box 3568, PC: 112, Sultanate of Oman TEL +968 2210 5000 ‫هاتف‬ ‫ سلطنة عمان‬،334 <‫ الرمز البريدي‬578: <‫ب‬.‫< ص‬ ‫م‬، ‫م نا ال‬
Sohar Industrial Port, PO Box 282, PC: 322, Sultanate of Oman TEL +968 2210 6000 ‫هاتف‬ ‫ سلطنة عمان‬544 <‫ الرمز البريدي‬4:4 <‫ب‬.‫ا < ص‬ < ‫ا ال ناع‬ ‫م نا‬

Mina Al Fahal Refinery | Sohar Refinery | Aromatics Plant | Polypropylene Plant ‫ل‬ ‫ر‬ ‫البول‬ ‫| م ن‬ ‫ال طريا‬ ‫| م ن‬ ‫ا‬ ‫ا‬ ‫| م‬ ‫ا م نا ال‬ ‫م‬
www.orpic.om | info@orpic.om

Oman Oil Refineries & Petroleum Industries Company SAOC:

Mina Al Fahal, Muscat PO Box 3568, PC: 112, Sultanate of Oman TEL +968 2210 5000 ‫هاتف‬ ‫ سلطنة عمان‬،334 <‫ الرمز البريدي‬578: <‫ب‬.‫< ص‬ ‫م‬، ‫م نا ال‬
Sohar Industrial Port, PO Box 282, PC: 322, Sultanate of Oman TEL +968 2210 6000 ‫هاتف‬ ‫ سلطنة عمان‬544 <‫ الرمز البريدي‬4:4 <‫ب‬.‫ا < ص‬ < ‫ا ال ناع‬ ‫م نا‬

Mina Al Fahal Refinery | Sohar Refinery | Aromatics Plant | Polypropylene Plant ‫ل‬ ‫ر‬ ‫البول‬ ‫| م ن‬ ‫ال طريا‬ ‫| م ن‬ ‫ا‬ ‫ا‬ ‫| م‬ ‫ا م نا ال‬ ‫م‬
Oman Gas Company SAOC:
www.orpic.om | info@orpic.om
PO Box 799, PC 133 , Al Khuwair, Sultanate of Oman ‫ سلطنة عمان‬،‫ الخوير‬، 355 <‫ الرمز البريدي‬9;; <‫ب‬.‫ص‬
Tel: (+968) 24466000 Fax: (+968) 24466900 )+;8:( 46688;22 <‫ فاكس‬، )+;8:( 46688222 <‫هاتف‬
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

DOCUMENT CONTROL & DISTRIBUTION:

Document Title : HDD Method Statement for installation of 14” & 32” CS pipes

Document No.: F900- CN-MST-00001-00-PGEP (LPIC)


FAH/SHR-9-3013-001-R1-4-A (OGC)

ANIL KUMAR
Issued for MAHFOOZ NAVAZ SHAIKH
C 13-May-18 MANAGING
Approval QA/QC Engineer DRILLING Manager
DIRECTOR
ANIL KUMAR
Issued for MAHFOOZ NAVAZ SHAIKH
B 25-April-18 MANAGING
Approval QA/QC Engineer DRILLING Manager
DIRECTOR
ANIL KUMAR
Issued for Review 15-April - MAHFOOZ NAVAZ SHAIKH
A MANAGING
Approval 18 QA/QC Engineer DRILLING Manager
DIRECTOR
Revision Date of
Rev. Originated by Checked by Approved by
Descriptions Issue

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 2 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

REFERENCES: As per Sno-3, Page-5

HOLDS: Nil

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 3 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

INDEX

Sr. No. CONTENTS PAGE No.

01 PURPOSE 5

02 SCOPE 5

03 REFERENCE DOCUMENTS 5

04 DEFINITIONS / ABBREVIATIONS 5

05 RESPONSIBILITIES 5

06 HSE REQUIREMENTS 8

07 MAN POWER, EQUIPMENT / TOOLS 8

08 SEQUENCE OF ACTIVITIES 8

09 DOCUMENTATION

10 ATTACHEMENTS

A SCOPE MATRIX 8

B PROJECT DRAWINGS ( PIPELINE ALIGNMENT SHEET) 11

C JHA/HMEP 12

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 4 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

1.0 PURPOSE

The purpose of this method statement is to establish, monitor and control all
activities involved in the procedure for installation of 14” & 32” dia API 5L GR X 65
pipes under the Asphalt Road and SIPC Water Canal by using the Horizontal
directional drilling (HDD) method at SOHAR IND. PORT, between Entry and Exit Pits,
in accordance to the project specification, reference codes and standards.
Separate Method statement will be applicable for pipe fabrication, Hydrotesting handling
during pulling operation.

2.0 SCOPE

The scope of this method statement is applicable to the installation of Scope (1)14” and
02 no. of 4 inch GI Casing & (2) 32” dia CS pipes underground by using the Horizontal
directional drilling (HDD) method beneath SIPC Roads and SWR Canal at SOHAR IND.
PORT- ORPIC project as per CONSULTANT / CLIENT approved specification, method
statement and construction drawings.

3.0 REFERENCE DOCUMENTS

 Drawing no. Bore Profile For 14” ( GEP/PUNJ/OPRIC/CS-02) and 32” Pipe line –OGC(
GEP/PUNJ/OPRIC /CS-01) FAHUD-SOHAR Project
 NACE TM-0102-2002 ASCE MOP 108 Pipeline HDD
 CDT Test ( by Punj Lloyd)
 14 inch HDD Static calculations
 32 inch HDD static Calculation
 HDD Dynamic Calculations
 Site layout Plan.
 Project HSE Emergency Response Plan ( of Punj Lloyd)
 Site Organogram
 Geotechnical Borehole Date Report by ACES- SO16000031-34 Rev 0
 Alignment Sheet Numbers F900-PL-ALN-00242 and F950-PL-ALN-00242

DOC NO. REV DOC TITLE

F900-QA-PRO-00023-00-PNJL 0 PROCEDURE FOR STRINGING


PROCEDURE FOR MAINLINE WELDING OF CLASS 1
F900-QA-PRO-00025-00-PNJL 0
PIPELINE

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 5 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

F900-QA-PRO-00026-00-PNJL 0 PROCEDURE FOR TIE-IN WELDING - 14" NGL PIPELINE

F900-QA-PRO-00027-00-PNJL 0 PROCEDURE FOR WELDING REPAIR - 14" NGL PIPELINE

F900-QA-PRO-00028-00-PNJL 0 PROCEDURE FOR FIELD JOINT COATING AND REPAIR

F900-QA-PRO-00029-00-PNJL 1 PROCEDURE FOR PRE-PADDING AND LOWERING

F900-QA-PRO-00030-00-PNJL B PROCEDURE FOR HDPE DUCT LAYING


PROCEDURE FOR HYDROSTATIC TESTING OF 14” NGL
F900-QA-PRO-00035-00-PNJL B
PIPELINE
PROCEDURE FOR FIELD JOINT COATING (For HDD and
F900-QA-PRO-00063-00-PNJL A
Bored Crossings using DIRAX)
F900-TL-PRO-00001-00-PNJL 0 FOC INSTALLATION PROCEDURE FOR 14" NGL PIPELINE

4.0 DEFINITIONS / ABBREVIATIONS

4.1 DEFINITIONS

COMPANY - Oman Gas Company S.A.O. C (OGC) & Liwa Plastics LLC
(Orpic)
CONTRACTOR - Punj Lloyd Limited
HDD SUB-CONTRACTOR - Gulf Engineering Projects LLC
DOCUMENT / DATA - A term meaning any written or tabulated Information it may be
in the form of any type of media – either soft or hard copy.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 6 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

4.2 ABBREVIATIONS

 AFC : Approved For Construction


 ASME : American Society of Mechanical Engineers
 COMPANY : Oman Gas Company SAOC & Orpic Plastics LLC
 CONTACTOR : Punj Lloyd Limited
 SUB-CONTRACTOR : Gulf Engineering Projects LLC

 HSE : Health Safety Environment


 PPE : Personnel Protective Equipment
 ITP : Inspection and Test Plan.
 QA/QC : Quality Assurance and Quality Control.
 Rev. : Revision
 PTW : Permit to Work
 BS : British Standards

 ASTM : American Society for Testing & Materials


 IP : Interface Point
 RFI : Request for Inspection
 DGS : Design General Specification
 HDD : Horizontal Directional Drilling
 NDRC : Non Disruptive Road Crossing
 NACE : NACE International Institute
 CDT : Coating Conductance Test

5.0 RESPONSIBILITIES

5.1 Construction / Project Manager

 Shall Report to MAIN CONTRACTOR’s Site Manager.


Shall be overall responsible for control and monitoring of HDD activities.
 Shall have overall responsibility to ensure safety at site for the working group and
environment.
 Shall have overall responsibility for the quality of installation works at site.
 Shall be responsible for the execution of work in accordance with project HSE and
Quality requirements

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 7 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

5.2 Site Engineer

 Shall report to Construction Manager


 Shall ensure that HDD activities are on-going as per project specification
requirements and as per the latest drawings.
 Prepare technical deviation, concession request if necessary.
 Shall be responsible for execution of work in compliance to the project HSE and
Quality requirements.

5.3 Site Supervisor


 Shall report to Site Engineer
 Shall ensure that personnel working are HSE inducted and are complying with
Project HSE Requirements.
 Shall conduct HSE tool box talk to all concerned personnel prior to start of work
 Control Execution of HDD works, material storage, tracking of the material received
at site.
 Co-ordinate with QA/QC Inspector while performing Inspection as per the ITP.
 Shall ensure the HDD works are as per AFC drawings and schedule.
 All activity must comply with PTW system.

5.4 HDD Rig Operator

 Shall Report to Site Engineer


 Shall Ensure that all personnel’s working under him are trained to Project HSE
requirements
 Shall ensure that all underground Tools and Tackles are inspected prior to start of
an installation work
 Shall verify the HDD Machine and equipments with respect to the work load
/capacity
 Shall ensure that all the HDD equipment’s are inspected and certified by third party

5.5 QC Inspector (MAIN CONTRACTOR)

 Shall report to QA/QC Manager


 Shall monitor & Inspect QA/QC activities against approved ITP, Project
specification, drawings.
 Shall liaise with Client Inspection Personnel during inspection.
 Prepare and maintain Inspection documents, test packages for the relevant activity.
 Shall inspect the incoming materials as per design general specification and
purchase order requirements.
 Shall monitor the WPS/ Welders qualification status.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 8 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

 Shall ensure that all IMTE are duly calibrated and certified

5.6 Wire Line Engineer

 Shall report to Construction Manager.


 Shall co-ordinate Driller at the time of pilot hole drilling with the help of “Paratack”
Profile software to locate and control the Mud Motor to meet designed Crossing
Profile.
 Generate the As-built record from “ Paratrack” software for installed Bore path.

CVs for key personnel e.g Driller and Steering Engineering will be submitted to Owners for approval.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 9 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

5.7 Welding Supervisor (MAIN CONTRACTOR)

 Shall be reporting to Welding Superintendent


 Shall ensure that only qualified welders are deployed on job.
 Shall be responsible for the issue and control of welding consumable
 Shall ensure that all personnel working in welding are HSE Inducted and familiar
with project HSE & Quality requirements
 Shall conduct tool box talk prior to start of work

5.8 Material controller (MAIN CONTRACTOR)

 Shall report to Material Manager


 Shall ensure that all materials are stored and Preserved in accordance with the
project specification requirements.
 Shall ensure that all bought out project materials are inspected & certified by
concern authority.
 Shall ensure that all materials/spools are issued for modification works are in
accordance with material request.

5.9 Safety Officer (MAIN CONTRACTOR)


 Shall Report to Safety Manager
 Shall ensure that all equipment, tools and tackles are certified & color coded with
site HSE requirements.
 Shall inspect safety requirements are implemented and tool box meetings are
conducted.
 Shall verify that all the personnel’s involving installation operations are undergone
safety induction program.
 Shall verify that equipment’s are in good and safe working condition
 Ensure safety requirements are implemented and adequate safety measures are
undertaken to prevent any damage to the work group, public, environment as well
as properties.
 Shall monitor the HSE implementation as per this method statement and Project
HSE Plan.

6.0 HSE REQUIREMENTS (MAIN CONTRACTOR )


 All Personnel must attend CLIENT/CONSULTANT induction and valid pass to be hold
 All personnel must comply project PPE requirements.
 Permit to work shall be obtained from company before any Activity commencing

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 10 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

 All applicable requirements mentioned in the Project HSE Plan and specific TRA shall
be implemented at the construction site.
 Daily Task risk must be briefed through toolbox talk
 All lifting gears must certified by third party and valid third-party certificate must be at
working location.
 Competent riggers / Banks man must be trained by third party and certificate must
hold before commencing the activity.
 Scaffolding Walkways shall be provided for cross over pipes to prevent slip and trip as
needed.
 Personnel movement under the suspended loads shall be avoided. All the lifting
activities shall be carried out under the strict supervision of experienced foreman /
charge hands.
 Suitable fire extinguishers shall be provided in all equipment’s, where required. And
Fire water inside plant, fire proof tarpaulin/Fire Blanket shall be provided during
welding/Hot works areas.
 Sign boards & hard barricades shall be placed around work location except where
active work requires opening of such devices and then only such portion of the
barricade needed for work access will be removed.
 Danger signs shall be provided and warning sign shall be written in English and/or
Hindi.
 No lifting operations shall be carried out in the heavy wind and bad weather
conditions.
 During extended hours or night operations shall be carried out only with the prior
permissions from COMPANY

7.0 MAN POWER & EQUIPMENT


7.1 MAN POWER
 Construction Manager / Project Manager
 Site Engineer
 Site Supervisor
 HDD Rig Operator
 HDD Tracker / Steering Engineer
 Foremen

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 11 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

 HDD Technicians/ crews (Underground Tools /


Bentonite Mixing/ Mechanic)
 Skilled / Unskilled Labour

7.2 EQUIPMENT
 Vermeer D330x500 (150 Ton) & D100x120 (47 Ton) HDD Rigs
 Vermeer RX12T Mud Reclaimer System / Mud pumps
 Inrock Wireline HDD Tracking System (Paratrack)
 Vermeer MX240 Bentonite Fluid Mixing System
 Generators related to the HDD equipments
 Walkie Talkies for communication
 Cranes , excavator, Water/Trash Pumps as required.
 Inspection report for all Equipments and Drilling Rods will be available at work
location.
 Both wireline tracking system and Mud Recycling unit will have Callibration cert.

For SOHAR IND. PORT commissioning area, only Company approved crew shall be
allowed to perform HDD activities.

8.0 SEQUENCE OF ACTIVITIES (MAIN CONTRACTOR)

8.1 Drawing Control


 Applicable approved drawings shall be issued to site engineer by the
document controller or controlled copy issuing authority
 Site engineer shall issue the relevant drawings to the erection site
according to the erection plan and front availability
 Site supervisor shall ensure that all drawings are properly filed and
maintained at site or at the work location throughout the installation
process
 All superseded drawings /Documents shall be removed from the file
to avoid any unintended use
 Based on approved drawings for construction, dossier will be
prepared for HDD works with a copy to company including
following information (line description, P&ID mark up’s, HDD

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 12 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

crossing’s list and location, isometrics with schedule etc.)

8.2 Material control (MAIN CONTRACTOR)


 Site engineer shall request for the welded CS line as per the program
provided by Field Engineering / planning department.
 Materials issue voucher shall be prepared and issued to Project stores
to withdraw Erection items
 Materials received shall be segregated with respect to the type of
materials and kept separately
 Materials received for standard supports shall be in accordance to
the standard support specification
 Preservation and storage of Bentonite and other additives shall be
ensured in accordance with project specification.

8.2.1 Consumable Control


 Consumable storage and issue shall be in accordance with Project
Procedure for control of welding consumables
 Welding foreman (MAIN CONTRACTOR) shall ensure that only
one type of welding consumable is issued to welder at a time.
 Inspection certificate for all equipment and Drill pipes will be available
at site.

8.2.2 Installation of 14” & 4 inch GI (FOC Casing) & 32” CS Pipelines
(under SIPC Asphalt road & water canal)
Scope of this Method statement is only for HDD crossing activities for mentioned product,
and for FOC installation, Method statement F 900-CN-MST-00009-00-PNJL to be referred.
However at the time of 4 casing installation, a pull string should be installed ( by PLL) along
with GI Casing.

8.2.3 PROTECTION OF EXISTING SURROUNDING FACILITIES.


a) Prior to start of Directional boring activity, all the surrounding utilities /
Facilities if any shall be covered and protected as required.
b) Goal Post Shall be provided for the marking OH Cables.

8.2.3 PREPARATION.
a) All the equipments shall be inspected by CLIENT prior to start the activity.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 13 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

b) Prior to start any activities area will be barricaded.


c) Install Hard Barricade along the perimeter of Entry and receiving pit.
d) Adequate sign boards shall be installed by HDD Subcontractor, GEPCO.

8.2.4 LAYOUT & MARKING


a) Layout & marking shall be done by the surveyor using calibrated
surveying equipment; QC shall verify the layout as per C O M P A N Y
AFC drawings
b) Approval of site layout and entry and exit locations shall be approved by
Owner.
c) A temporary bench mark shall be established at work site & shall be kept
safe till the activities are completed.
d) ParaTrack is a turn-key service that includes a Vector Magnetics Steering
Probe, a ParaTrack Guide Wire Power Supply for injecting AC current into
the surface wire, and RivCross software which provides a graphical
environment for managing the job from end to end. Configurations may
include closed loop tracking, single wire with earth return, or even tracking
wire installed in existing bores for precise spacing of multiple bores.
Options include the Pressure Module providing annular and drill pipe
pressure readings and the At Bit Inclination Assembly (ABIA) which
provides real-time monitoring of at-bit inclination - an industry first.

8.2.5 HDD WORK PROCEDURE IN DETAIL


PRELIMINARY WORKS:-

 Check location of underground utilities by digging trial pits.


 Goal Post shall be provided to mark the OH Cable crossing.
 Work areas or Access roads shall be marked
 Check all CS pipes free of damage.
 Shift the CS pipes to the required location and weld them.
 Construct entry / exit pits (4x4x2 m ) or as required, depending on soil conditions.
 Provide Sheet pile for anchoring the HDD machine.
 Setup the HDD machine near to Entry side as per the attached drawing.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 14 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

 Setup Wireline tracking system on-site.


 Surveyor to mark route position on Asphalt Road /Canal which is to be drilled
under.
 Survey will complete the baseline survey for road surface elevations
 The CS pipes shall be prepared and to be set for pulling on rollers
and assist with lifting equipment such as Side Booms with arrangement
in compliance with Method statement for pipeline lowering F900-QA-PRO-
0029-00-PNJL-Rev1 .

8.2.6 DIRECTIONAL BORING PROCEDURE

A - Cross Check all above mentioned points.


B – All works will be planned and performed in the day shift due to vibration monitoring is part
of the complete HDD process. In case night shift is required for contingency, special permit will
be obtained from SIPC.

C - Drill the pilot Bore with guidance of our INROCK Wire line system (Para track).

D - Pull back with suitable back reamer (12 to 46 inches) from exit point to entry point.

E - Drill with different size back reamer / Barrel reamer and final clean pass to the exit point.

F - Taking out the back reamer and fixing the pipes with swivel & puller and pulling
back to entry point.

Carrier Pipe Reamer No. of Passes Remarks


diameter diameter after Pilot Hole

14” 28” 10,14,18,22,26 As per Driller


discretion
32” 46” 10,14,18,22,26, based on site
30,36,40,46 condition.

All drilling operations will be conducted from the rig side location. The high capacity
rig, situated on the rig side will commence with the pilot bore and drill towards the
exit point location on the other side.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 15 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Bentonite drilling fluid will be utilized in all stages of the drilling operations; all steps
will be taken to minimize any environment impact.

The reaming phase will involve the enlargement of the pilot bore, by means of
backward reaming; this will be in gradual steps to ensure the integrity of the hole.

Once the reaming phase has been concluded, the bore hole will be cleaned and
conditioned by passing a series of barrel reamers through the hole, the number of
passes will be deemed from data received on site.

Once the hole has been conditioned, the higher Ton drilling unit (D 330X 500) will
be connected to the welded product pipes using a swivel and pulled towards the
drilling rig from the exit point location. The swivel allows the drilling rig operator to
rotate the drill string without rotating the pipe. This operation is called pipe pull back
with low pulling force.
Following is the plan for utilization of Rigs for Completion of Works. (D100x120)
will be used to achieve following activities:-

A. Pilot Bore, Complete Reaming and Pulling Operations (for 14” CS Pipe & FOC
conduit)
B. Pilot Bore, Reaming Operations up to 36 inches (for 32” CS pipe)

D 330 X 500, which is 150 Ton Rig, will be used to complete Reaming process
above 36 inch dia hole and until 46 inch dia hole and including pulling of 32 inch
Product pipeline.

In line with detailed design calculation (Settlement), it is established that


considering drilling below 10 meter from Canal bed, only 7.7 mm ground settlement
is estimated and as such will not cause vibration, however It is planned to install a
“Vibration sensor” at the edge of canal to measure the vibration, Instruments
expected to be similar to one use in measuring the vibration during Rock Controlled
Blasting or equivalent one.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 16 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Maximum peak particle velocity shall not be more than 2.5 mm/ sec at any point of
time of HDD process. This shall be recorded and monitored continuously at the
time of drilling and reaming process.

Post Pilot hole successful completion, all reaming passes will be performed using
Recycle of Drilling Rods, based on actual site condition experienced.

8.2.7 Communication & Locating Tools

 For locating process, INROCK wireline HDD locating system (Para track) shall
be used in this proposed HDD crossings.

 Internal Fuild pressure will be monitored continuously throughout drilling and


reaming process.

 For communication between HDD locating technicians and HDD operator, 6 km


range Motorola TLKRT4 model walkie talkie radios will be utilized.

 Refer Procedure- Method statement for Steering Engineer


The HDD operations are to be carried out in three phases:

 Pilot Bore

 Reaming Operation

 Pipe Pulling

8.2.8 The Guided Pilot Hole

The Pilot Bore is the initial phase in the drilling operation. Predetermined design
profiles will govern the path from the entry point location to the exit point location.

The HDD surveyor will mark out and set up the down hole assembly (DHA),
depending on formation and soil conditions.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 17 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

A typical motor down hole assembly (DHA) for the HDD rig, comprises of: a 6 3/4”
mud motor complete with a 8 3/4” or 9 7/8 sealed tri-cone bit, an adjustable bent
housing set to
1.83 degrees, non-magnetic drill collars, steering tool often housed within the
nonmagnetic collars and steel 6 5/8” drill pipe.

A Steering tool or survey probe will ensure the integrity of the pilot bore, constantly
transmitting information to an interface box, which converts the signal accordingly
and sends it to the HDD surveyor’s computer situated in the driller’s control cabin.
There are two main systems that are operational in the field today, the Para track II
and the Tru- Tracker Steering Systems.
HDD Contractor will get approval of the pilot hole as built from the Owner before
proceeding to the next phase.

8.2.9 Operation
On completion of the pilot bore, the hole will be enlarged using a sequence of hole-
openers, by backward reaming methodology. The hole will ultimately be opened to
approximately 28” to 46” OD to accommodate the 14” (350mm) + 2 off 4 inch GI
Conduit and 32” (800mm) CS PIPES.

The hole-openers will be attached to the drill string on the pipe side location (SIPC
Side), rotated and pulled towards the entry point and rig side location. By
employing the conventional backward reaming process, the majority of the
Bentonite mud returns and down hole cuttings will exit on the pipe side location.
Once the hole has been sufficiently reamed to size, the reaming assembly will be
removed and replaced with the pipe pulling assembly.

As an option 6 M x 3 M X 3 M slurry pit will be made on both entry and exist sides
with the help of Earth bund, depending on site requirements.

Refer Attachment Appendix E for the reference to Frac out contingency.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 18 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Refer AnnexureE.Contingency Plan for Horizontal Directional Drill

Final Clean Pass with 44” (Barrel Reamer)

Once the final reaming cutter has exited the bore hole, the reamer will be
removed and replaced with the cleaning assembly, only when this operation has
taken place can the cleaning phase commence.

Drill Mud
“Drilling mud” is normally utilized to lubricate the cutting head during
the drilling operation and stabilize the reamed bore path prior to and
during pull-back. The “drilling mud” usually consists of a mixture of fresh
water and bentonite clay; however, other materials such as polymers
and/ or Soda Ash are sometimes used. Same will be decided and
implemented at site based on actual site conditions from stocked quantity
at site. Bentonite is a naturally occurring clay mineral that forms a
mud when mixed with water. Drilling fluids are characterized by their
viscosity, gel strength, filtration, fluid loss, fluid density, pH, and
lubricity. The principal functions of drilling fluids used in HDD are,

1. Transporting drill cuttings to the surface by suspending and carrying


them in slurry that flows in the annulus between the bore wall and the
drill/product pipe.
2. Cleaning build-up on drill bits or reamer cutters by directing fluid
streams at the cutters.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 19 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

3. Cooling the down hole tools and electronic equipment


4. Lubricating to reduce the friction between the drill pipe/product and the bore
wall.
5. Stabilizing the bore path, especially in loose or soft soils, by
building a low- permeability filter cake and exerting a positive
hydrostatic pressure against the bore path wall. The filter cake and
positive hydrostatic pressure reduce obstruction of the bore path and
prevent formation fluids (i.e., groundwater) from flowing into the bore,
or drilling fluids from exiting the bore path into the formation (loss of
circulation).
6. For HDD, the proper drilling fluid mixture and delivery pressure is
heavily dependent upon the type of soil encountered. It must be
formulated for the anticipated geological conditions. For simplicity,
soil conditions may be defined as either a coarse soil (sand and
gravel) or a fine soil (clay, silt, and shale). In general, for coarse
soils bentonite should be used, while for fine soils polymers added
to a bentonite.
7. Before start of Drilling operation, Driller in consultation with the Steering
Engineer shall decide upon the anticipated Mud pressure (for hole
envelope) and to maintain the integrity of hole from frac out.
8. In the event of any additives are required to be used in Drilling Fluid,
prior Client/Company approval will be obtained.

Applications/Functions
1) Form a thin filter cake with low permeability
2) Seal down hole instrumentation in test and observation holes
3) Reduce filtrate invasion into permeable formations
4) Improve hole-cleaning capability of drilling fluid
5) Provide lubricity for drilling fluids
6) Mix with fresh water to form a low-solids drilling fluid for general drilling
applications
7) Mix with foaming agents to make "gel/foam" drilling fluids for
air/foam drilling applications.

Advantages
1) Single-sack product and cost effective
2) Mixes easily and quickly reaches maximum viscosity

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 20 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

3) Excellent for environment in drilling potable water wells


4) Yields more than twice viscosity as an equal weight of API oilfield grades
of Benton.
5) Added MSDS sheets of Bentonite and Polymer for your reference.

Disposal of Bentonite or Drilling Mud :

Although the bentonite-water, or commonly used polymer-water, slurry is not inherently a


hazardous material. In order to maintain a neat, orderly work site, occasional small pits
must be available for collecting the excess drilling fluid or slurry exiting from the bore hole.
A clean work site will help ensure the installation of a clean product pipe, reducing the
need to later flush out mud or debris from within the pipe and provide a safe work area.

In our case, we shall use Vermeer R9X12T Mud reclaimer (catalogue attached) to recycle
the bentonite fluid. The dry sand discharged from mud reclaimer can be shifted safely with
Six Wheel trucks and the excess bentonite slurry collected in the entry / exit pits during
HDD operation can be removed by using sucking tankers as well.

Excessive drilling fluid and mud in the area may impair the connections and associated
grounding characteristics of the equipotential grid mat system. Pits may already be present
or required such as for utility access or connections at the ends or along the bore, thereby
serving as convenient receptacles. If not otherwise present, small pits shall be provided at
the ends, and possible intermediate points to serve this function. The pits shall be emptied
as necessary.

Removal of Debris

Once the pipe is pulled and pipe string is installed and the puller is detached from the
pipe, both pits can be cleaned from any drilling leftovers such as water, drilling Mud in
line with approved SIPC disposal procedure and also in compliance with applicable
Municipality having jurisdiction (as applicable), to facilitate Tie-ins with pipeline
section.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 21 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Post HDD works

Post pulling the pipeline section, area will be reinstated to original dimensions.

As already explained Bentonite slurry dozed with required additives is used in the
HDD and forms a mud cake around the installed pipe as annulus. In view of the
environment friendly characteristics of the Bentonite and the additives (Polymer and
Soda Ash) are used, the surplus left over Bentonite slurry will be just like any ordinary
sand. It dries out in one day and easily blends with the soil. The main component is
clay from the earth made in to fine powder so it will be easily absorbed in the soil
without any harmful effect. In city areas, the waste bentonite slurry shall be shifted by
using sucking tankers.

Post HDD work completion, HDD pipe section will be tied in with main pipeline
section in compliance with approved Method statement and work procedure.

REQUIREMENTS FOR NON-DISRUPTIVE ROAD CROSSINGS (NDRC)

A) Monitoring System in respect of Crossings of Municipality Roads

For purposes of monitoring for ground surface movement on the roadway, suitable
marking shall be made in a grid pattern with approximately 2.0 meter centers.
The monitoring points shall cover the entire width of the roadway along the drive and shall
extend outwards in each direction to a short distance of the depth below the road surface.

Contractor (MAIN CONTRACTOR) shall conduct survey at all monitoring points and
record in the drawings the precise survey information on each point:

 Prior to commencement of NDRC construction.


 Upon completion of NDRC construction.
 At a subsequent time after completion of NDRC construction to ensure there is no
settlement of the road surfaces.

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 22 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Notes:-
 The equipment used in the SOHAR IND. PORT commissioning area must be
fitted with spark arrestor/chalwyn valve.
 All employees must comply HSE requirements prior to commencing the activities.

 The work will not be performed inside restricted control area without prior
notification
 Any work performed inside the SOHAR IND. PORT commissioning area
should follow PTW procedure

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 23 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

9.0 DOCUMENTATION
9.1 Daily Progress Report,

10.0 ATTACHMENT
10.1 Task Risk Assessment for Existing pipeline fabrication, erection at SOHAR IND.
PORT

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 24 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Pictures of HDD Equipments

INROCK Wireline (HDD Tracking System)

Down Hole Tools

INROCK Wireline HDD Tracking Tools

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 25 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

Down Hole Tools

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 26 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for Installation of 14” & 32” CS pipes

D100x120 HDD Rig

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC) Rev. A Page 27 of 30


FAH/SHR-9-3013-001 - R1-4-A (OGC)
D330x500 HDD Rig
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for
Installation of 14” & 32” CS pipes

1. Records

a. Site Survey – Survey sheets and RFI as per ITP for Survey works
b. Carrier pipe preparation – Weld records as per ITP for Pipeline works
c. Excavation – As per approved project specific civil ITP and SP-1279
d. Dewatering – No record for client inspection proposed.
e. HDD works –Actual bore Profile Log and other details required by Client
f. Pilot Hole As Built Path Approval Record
g. Mud Pressure Report.

2. ANNEXURES

A. Scope Matrix

Description GEP PLL (Main


(HDD) Contractor)
HDD at Road crossing X
Preparation of carrier pipe
32” Pipe Welding, NDT, HSS application X

leveling of carrier pipe to maintain zero to zero degree profile X

14” Pipe Welding, NDT, HSS X


leveling of carrier pipe to maintain zero to zero degree profile X

Preparatory works for HDD


Approvals from ORPIC, OGC and various authorities for HDD X
works
Site Survey, marking of Entry pit & Exit pit away from the X X
edge of asphalt road
Trial pit excavation to Identify Existing services at site X

Mobilization of Equipment and specialized personnel by HDD X


vendor
site leveling and cleaning, Preparation of Entry pit & Exit pit X

HDD of 32” Pipeline


Setting up of drilling equipment X

pilot bore drilling (Zero to Zero) by directionally guiding the X


drill head along with tracking system from entry point (rig
side)
Pre-Reaming from the exit pit toward the entry pit, in stages X
8”, 12”, 16”, 20”, 28” &36”
Pipe pulling from the exit pit side towards the entry pit side X
(rig side)
HDD of 14” Pipeline
Setting up of drilling equipment X

pilot bore drilling (Zero to Zero) by directionally guiding the X


drill head along with tracking system from entry point (rig
side)

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC)


FAH/SHR-9-3013-001 - R1-4-A (OGC) Rev. A Page 29 of 30
Project Title: LPIC - EPC4 NGL Pipeline
OGC – 32” Gas Loopline
Document Title – HDD Method Statement for
Installation of 14” & 32” CS pipes

Pre-Reaming from the exit pit toward the entry pit, in stages X
8”, 12”, 16” & 20”
Pipe pulling from the exit pit side towards the entry pit side X
(rig side)
Post HDD works
Removal of Debris from site after completion and disposal of X
excess bentonite and other fluids from the work location

Post-padding of trench, laying sleeve for HDE duct of FOC, X


Backfilling
CDT Testing X

B. PROJECT DRAWINGS ( PIPELINE ALIGNMENT SHEET) – as attached below

C. JHA/HMEP

HAZARDS AND EFFECTS MANAGEMENT PROCESS (HEMP)

Below systematic approach to follow for hazard identification and risk management which
is aimed at effective control of all occupational health and safety risks as well as risks to
assets, environment and company reputation

Doc. No. F900-CN-MST-00001-00-PGEP (LPIC)


FAH/SHR-9-3013-001 - R1-4-A (OGC) Rev. A Page 30 of 30
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 14"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-02

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of pipes by HDD
are as follows:

A. INPUT VALUES AND PARAMETERS:


1 Pipe Dia D 35.56 cm Given
2 Wall Thickness t 1.11 cm Given
3 Internal Dia 33.34 cm Calculated
4 Pipe Grade X65 Grade Given
5 Specified Min. Yield Strength S 4588.73 kg/cm2 Given
6 Cross Sectional Area As 120.13 cm2 Calculated
7 Moment of Inertia I 17,840.26 cm4 Calculated
8 Section Modulus of Pipe Z 1,003.39 cm3 Calculated
9 Weight of empty Pipe in air Wp 0.94 kg/cm Calculated
10 Weight of Water Filled Pipe in air Ww 1.816 kg/cm Calculated
11 Modulus of Elasticity E 2038902 kg/cm2 Given
12 Soil Friction Angle 30 Degrees Standard
13 Design Pressure 122.4 kg/cm2 Calculated
14 Pre Hydrotest Pressure Prh 266.27 kg/cm2 Calculated(261.119bar)
15 Post Hydrotest Pressure Poh 149.39 kg/cm2 Calculated(146.5bar)
16 Operating Pr. Of Pipeline Pop 89.74 kg/cm2 Calculated
17 Length of Crossing L 30000 cm Calculated
18 Entry Angle 8 Degrees Designed
19 Exit Angle 8 Degrees Designed
20 Poisson's ratio m 0.3 Standard
21 Fluid drag coeff (betn slurry and pipe) f 0.00352 kg/cm2 Standard
22 Coeff of friction between pipe and soil f' 0.3 Standard
23 Buoyant weight of pipe w 1.192 kg/cm calculated
24 Density of mud used Db 0.0012 kg/cm3 Standard
25 Max depth of crossing h 1750 cm Given
26 Column height from water level to Bed Level Hw 450 cm Given
27 Maximum ht. of soil above pipe Hs 1750 cm Given
28 Soil Density Ds 0.00185 kg/cm3 Geotech
29 Water Density Dw 0.001 kg/cm3 Standard
30 Coeff of Linear Expansion a 0.0000117 /oC Standard
31 Difference in Temperature during operation D 10 Assumed
32 Proposed ROC R 120000 cm Calculated
33 Hoop Stress Limitation 0.9 of SMYS Given
34 Bending Stress limitation 0.9 of SMYS Given
35 Surface Area of Pipe 3351451.0 cm2 Calculated
36 Rig Pulling Capacity 150 Tons To be Used
37 OFC OD 0.00 cm Given
38 OFC w.t. 0.00 cm Given
39 OFC weight 0.00 Kg/cm Given
40 OFC net Bouyancy 0.00000 Kg/cm Calculated
41 Roller Spacing 12.00 m
Notes & Calculations

A. GIVEN:
To Install 35.56 cm x 1.11 cm W.T. API 5L Gr. X65 steel pipelines by Horizontal Directional
Drilling technique as per ASME B31.8

B. PURPOSE:
Pipelines to be used for gas transmission. P = 89.74 kg/ cm2

C. REFERENCE:
i) Specifications, ASME B31.8 for Gas Transmissions in Pipelines
ii) Angle of Soil Shearing resistance ASTM D-3080 methods (30 degrees)
iii) Average coeff of friction between pipe & soil; recommended values between 0.21 to 0.30 (Maidla)
Maidla, EE: “Borehole friction assessment and. application to oilfield casing design in directional. wells”,
Ph.D. Thesis, Louisiana State University (1987)
iv) Drag Coeff of Friction taken as 0.05 psi (Empirical)
NEN 3650 - Requirements for steel pipeline transportation system. Dutch Standard – 1993

Page 1 of 8
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 14"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-02

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of pipes by HDD
are as follows:
v) Soil Investigation data

D. CALCULATIONS:

1 OVERBURDEN PRESSURE AND COLLAPSE PRESSURE


The collapse pressure is determined from the theoretical elastic curve equation
Pc = 2E / [(1-µ2)(D/t)(D/t-1)2 ]
Where: D/t = 35.56 / 1.11 = 32.04
= 145.22 kg/cm2
The collapse pressure, Pc = 145.22 kg/cm2

Ovality compensation factor = A/4pi(3V/4pi)⅔


f₀ = 0.4 Where: A - Area; V - Volume

Tension pull reduction factor theoritically


fr =0.25 So the Pipe is safe

The maximum overburden pressure


Po = (h*Db + hs*Ds + hw*Dw)
Po = 1750 x 0.0012 + 1750 x 0.00185 + 450 x 0.001
= 5.79 kg/cm2
Po/Pc = 3.99%
Since Overburden is only 3.99% of Collapse Pressure, Pipe is safe

2. BOUYANCY OF PIPE
Pipe Volume
Displacement of pipeline in drilling mud where volume
V, = 3.14 (D)(D)/4
D = 35.56 cm
V = 993.15 cc/linear cm.
Buoyancy
Buoyancy in drilling mud where mud density
B = Volume of Mud Displacement by pipe x mud density
= V x Db
B = 993.15 x 0.0012
= 1.192 kg/cm
Net Buoyancy
Net buoyancy when pipeline is empty and fully submerged
= B-W or 1.192 - 0.943
= 0.249
= 0.2487 kg/cm force

3 COATING STRESSES
The maximum shear stress in the pipeline coating during installation depends upon relative movements
of the pipeline and the surrounding soil. Using bentonite mud, the low-friction soil-coating interface
will be at a minimum.
Coating Failure Check
PE coatings Resistance = 2.5 kg/sq.cm. Std. Peel Test Value
Longitudinal Soil Stress. t = t = N(2-sin d)tan d
where ,
N is the force normal to the pipeline due to buoyancy
Net buoyancey force = 0.2487 kg/ cm
Friction Angle (d) = 30 (as per soil investigation report)
N = Net buoyancy force/(30/360*3.14*D)
= 0.0267 kg/sq.cm.
2-sin 30o = 1.5
t = (N x 1.5 x tan(30)
= 0.0231 kg/sq.cm.
Which is negligible as compared to the adhesive force of 2.5 kg/sq.cm that is 0.926%
So, Coating is safe.

4. Max Tensile Stress During Pull


Allowable stress = 90 % of SMYS
T = 0.9 x S x As
= 4,96,131.66 kg
Check for Tensile Stress
Max long stress that can be applied by Rig = 150 Tons

Page 2 of 8
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 14"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-02

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of pipes by HDD
are as follows:
= 150000 / As
= 1248.62 kg/sq.cm.
Percentage of SMYS = 27.21% of SMYS
Since Max. Tensile Stress is within limits and thus SAFE
Check for Bending Stress
For Long Bending Stress During installation at ROC = 120000 cm
= Ec/r E = modulus of elasticity
= 302.10 kg/cm2 c = distance of natural axis from edge of section
Percentage of Total SMYS = 6.58% of SMYS r = radius of curvature (ROC)

Hence Long. Bending Sress at above radius is safe.

5. Radius of Curvature Calculations

A. Before Installation
Pulling Load = 0 kg
Bending Load = 90 % of SMYS during Overbend or on rollers
Hoop Stresses = 90 % of SMYS on ground before overbend

Before Installation
Min Radius for Temporary Pipe Handling
Limiting SMYS = 90%
Bending Stress S = Ec/r
or R = 8778 cm
= 87.78 meters
B. During Installation

Max Pulling Load = 150 Tons


P=F/As = 1,248.617 kg/sqcm
Bending Stress Radius 120000 cm
= 302.10 kg/sqcm
Hydrotest Stress = 0.00 kg/sqcm
TOTAL Stress = 1550.71 kg/sqcm
Total Percent of SMYS = 33.79%

C. After Installation (Post Hydrotesting will be done at this stage)


Bending Stress at ROC = Ec/R
Longitudinal Stress at Test Pressure = pd/4t
Pulling Load = 0
Min Radius for Permanent Pipe Installation
As per ANSI B 31.4 factor of 1.85
Permanent Radius of Curvature - R = Ec/(0.75.S.SMYS-pd/4t)
Where S is design factor of 0.72
= 36251677.56 / [ 2478 - 1196.45 ]
= 28289.28 cm
= 282.893 meters
Taking 10% higher ROC = 311.2 meters
Permanent Radius Calc Check:
Bending Stress at ROC = Ec/R
= 302.10 kg/sqcm

Longitudinal Stress at Test Pressure = pd/4t


= 1196.45 kg/sqcm

Total Stresses = 1498.55 kg/sqcm


Stresses as Percent of SMYS = 32.66%

6. Combined Equivalent . Stresses


A: Before Installation

Page 3 of 8
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 14"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-02

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of pipes by HDD
are as follows:
Hoop Stress Sh = pd/2t
Test Pressure Pt = 266.27 kg/sqcm
= 4265.07 kg/sqcm
= 92.95% of SMYS

Bending Moment for Pipe at 1200 cm Supports


= Ww.L2/12
= 2,17,932.00 kg-cm
Bending Stress Sb = BM/Polar MI
= 217.196 kg/sqcm

Combined Long Stress Sl1 = m x Sh + Sb Or m x Sh - Sb


= 1279.52 + 217.20 = 1279.52 - 217.20
2
= 1496.72 kg/cm = 1062.33 kg/cm2

Resultant Eq. Stress


Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2) Or Sqrt (Sl12- Sl1xSh+Sh2)
= 3747.98 kg/cm2 3845.58 kg/cm2
= 81.68% of SMYS 83.80% of SMYS

B: After Installation
Pressure at Final Hydrotest = 149.39 kg/cm2
Hoop Stress Sh = 2392.90 kg/cm2
Bending stress at give radius Sb = Ec/r
= 302.10 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 717.87 - 0.00 + 302.10
= 1019.97 kg/cm2

Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb


= 717.87 - 0.00 - 302.10
= 415.77 kg/cm2
Resultant Eq. Stress
Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2) VON MISES' EQUATION
= 2079.81 kg/cm2
= 45.32% of SMYS
Resultant 2 = Sqrt (Sl22- Sl2xSh+Sh2)
= 2214.48 kg/cm2
= 48.26% of SMYS
C: During Operation
Operating Pressure = 89.74 kg/cm2
Hoop Stress Sh = pd/2t
= 1437.46
Bending stress at give radius Sb = Ec/r
= 302.10 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 431.24 - 238.55 + 302.10
= 494.78 kg/cm2

Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb


= 431.24 - 238.55 - 302.10
= -109.41 kg/cm2
Resultant Eq. Stress
Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2)
= 1264.86 kg/cm2
= 27.56% of SMYS
Resultant 2 = Sqrt (Sl22- Sl2xSh+Sh2)
= 1495.17 kg/cm2
= 32.58% of SMYS

Page 4 of 8
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 14"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-02

Calculations required in accordance with ANSI code B31.8 for Gas Transmissions across Pipelines for the installation of pipes by HDD
are as follows:

7 ROLLER SPACING DURING PULL


Allowable Bending Moment for Roller Spacing = 90% SMYS
= 4129.86 kg/cm2
Max Tensile force that can be applied = 150 tons
P=F/As = 1,248.62 kg/cm2

Available Stress for Bending Fb = 2881.24 kg/cm2

Bending Moment = Z*Fb


28,91,003.82 kg-cm
This bending moment will determine the roller spacing

For Simple spans (In between Rollers) BM = wL2/12


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 28,91,003.82 x 12 / 0.943 )
= 6065.26 cm
= 60.653 meters max

For Cantilever (On last Roller) BM = wL2/2


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 28,91,003.82 x 2/ 0.943 )
= 2476.13 cm
= 24.761 meters max

8 PULLING REQUIREMENTS
Pulling loads is divided into 3 main forces. Viz:
= Fluid Drag Resistance + Soil Drag Resistance + Fluid Weight on Pull Head
= pDLf + f'wL + DbhA
= 11797.108 + 10725.98 + 2085.6
= 24608.70 kg
= 24.61 Tons

Total Pulling Force Required = 27.07 Tons cosidering safety factor 1.1
% of Force Required to Rig Capacity = 18.05%

Page 5 of 8
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 32"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-01

Calculations required in accordance with ANSI code B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons for the
installation of pipes by HDD are as follows:

A. INPUT VALUES AND PARAMETERS:


1 Pipe Dia D 81.28 cm Given
2 Wall Thickness t 1.91 cm Given
3 Internal Dia 77.46 cm Calculated
4 Pipe Grade X65 Grade Given
5 Specified Min. Yield Strength S 4588.73 kg/cm2 Given
6 Cross Sectional Area As 476.26 cm2 Calculated
7 Moment of Inertia I 3,75,244.06 cm4 Calculated
8 Section Modulus of Pipe Z 9,233.37 cm3 Calculated
9 Weight of empty Pipe in air Wp 3.74 kg/cm Calculated
10 Weight of Water Filled Pipe in air Ww 8.451 kg/cm Calculated
11 Modulus of Elasticity E 2038902 kg/cm2 Given
12 Soil Friction Angle 30 Degrees Standard
13 Design Pressure 94.52 kg/cm2 Calculated(92.7 bar)

14 Pre Hydrotest Pressure Prh 198.81 kg/cm2 Calculated(194.97bar)

15 Post Hydrotest Pressure Poh 118.98 kg/cm2 Calculated(116.68bar)

16 Operating Pr. Of Pipeline Pop 86.68 kg/cm2 Calculated


17 Length of Crossing L 30000 cm Calculated
18 Entry Angle 8 Degrees Designed
19 Exit Angle 8 Degrees Designed
20 Poisson's ratio m 0.3 Standard
21 Fluid drag coeff (betn slurry and pipe) f 0.00352 kg/cm2 Standard
22 Coeff of friction between pipe and soil f' 0.3 Standard
23 Buoyant weight of pipe w 6.226 kg/cm calculated
24 Density of mud used Db 0.0012 kg/cm3 Standard
25 Max depth of crossing h 1750 cm Given
26 Column height from water level to Bed Level Hw 450 cm Given
27 Maximum ht. of soil above pipe Hs 1750 cm Given
28 Soil Density Ds 0.00185 kg/cm3 Geotech
29 Water Density Dw 0.001 kg/cm3 Standard
30 Coeff of Linear Expansion a 0.0000117 /oC Standard
31 Difference in Temperature during operation D 10 Assumed
32 Proposed ROC R 120000 cm Calculated
33 Hoop Stress Limitation 0.9 of SMYS Given
34 Bending Stress limitation 0.9 of SMYS Given
35 Surface Area of Pipe 7660459.5 cm2 Calculated
36 Rig Pulling Capacity 150 Tons To be Used
37 OFC OD 0.00 cm Given
38 OFC w.t. 0.00 cm Given
39 OFC weight 0.00 Kg/cm Given
40 OFC net Bouyancy 0.00000 Kg/cm Calculated
41 Roller Spacing 12.00 m
Notes & Calculations

A. GIVEN:
To Install 81.28 cm x 1.91 cm W.T. API 5L Gr. X65 steel pipelines by Horizontal Directional
Drilling technique as per ASME B31.4

B. PURPOSE:
Pipelines to be used for Oil transmission. P = 86.68 kg/cm2

C. REFERENCE:
i) Specifications, ASME B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons
ii) Angle of Soil Shearing resistance ASTM D-3080 methods (30 degrees)
iii) Average coeff of friction between pipe & soil; recommended values between 0.21 to 0.30 (Maidla)
Maidla, EE: “Borehole friction assessment and. application to oilfield casing design in directional. wells”,
Ph.D. Thesis, Louisiana State University (1987)
iv) Drag Coeff of Friction taken as 0.05 psi (Empirical)
NEN 3650 - Requirements for steel pipeline transportation system. Dutch Standard – 1993

Page 1 of 5
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 32"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-01

Calculations required in accordance with ANSI code B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons for the
installation of pipes by HDD are as follows:
v) Soil Investigation data

D. CALCULATIONS:

1 OVERBURDEN PRESSURE AND COLLAPSE PRESSURE


The collapse pressure is determined from the theoretical elastic curve equation
Pc = 2E / [(1-µ2)(D/t)(D/t-1)2 ]
Where: D/t = 81.28 / 1.91 = 42.55
= 60.98 kg/cm2
The collapse pressure, Pc = 60.98 kg/cm2

Ovality compensation factor = A/4pi(3V/4pi)⅔


f₀ = 0.4 Where: A - Area; V - Volume

Tension pull reduction factor theoritically


fr =0.25 So the Pipe is safe

The maximum overburden pressure


Po = (h*Db + hs*Ds + hw*Dw)
Po = 1750 x 0.0012 + 1750 x 0.00185 + 450 x 0.001
= 5.79 kg/cm2
Po/Pc = 9.49%
Since Overburden is only 9.49% of Collapse Pressure, Pipe is safe

2. BOUYANCY OF PIPE
Pipe Volume
Displacement of pipeline in drilling mud where volume
V, = 3.14 (D)(D)/4
D = 81.28 cm
V = 5,188.68 cc/linear cm.
Buoyancy
Buoyancy in drilling mud where mud density
B = Volume of Mud Displacement by pipe x mud density
= V x Db
B = 5,188.68 x 0.0012
= 6.226 kg/cm
Net Buoyancy
Net buoyancy when pipeline is empty and fully submerged
= B-W or 6.226 - 3.739
= 2.488
= 2.4878 kg/cm force

3 COATING STRESSES
The maximum shear stress in the pipeline coating during installation depends upon relative movements
of the pipeline and the surrounding soil. Using bentonite mud, the low-friction soil-coating interface
will be at a minimum.
Coating Failure Check
PE coatings Resistance = 2.5 kg/sq.cm. Std. Peel Test Value
Longitudinal Soil Stress. t = t = N(2-sin d)tan d
where ,
N is the force normal to the pipeline due to buoyancy
Net buoyancey force = 2.4878 kg/ cm
Friction Angle (d) = 30 (as per soil investigation report)
N = Net buoyancy force/(30/360*3.14*D)
= 0.1169 kg/sq.cm.
2-sin 30o = 1.5
t = (N x 1.5 x tan(30)
= 0.1013 kg/sq.cm.
Which is negligible as compared to the adhesive force of 2.5 kg/sq.cm that is 4.050%
So, Coating is safe.

4. Max Tensile Stress During Pull


Allowable stress = 90 % of SMYS
T = 0.9 x S x As
= 19,66,864.68 kg
Check for Tensile Stress
Max long stress that can be applied by Rig = 150 Tons

Page 2 of 5
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 32"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-01

Calculations required in accordance with ANSI code B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons for the
installation of pipes by HDD are as follows:
= 150000 / As
= 314.96 kg/sq.cm.
Percentage of SMYS = 6.86% of SMYS
Since Max. Tensile Stress is within limits and thus SAFE
Check for Bending Stress
For Long Bending Stress During installation at ROC = 120000 cm
= Ec/r E = modulus of elasticity
= 690.51 kg/cm2 c = distance of natural axis from edge of section
Percentage of Total SMYS = 15.05% of SMYS r = radius of curvature (ROC)

Hence Long. Bending Sress at above radius is safe.

5. Radius of Curvature Calculations

A. Before Installation
Pulling Load = 0 kg
Bending Load = 90 % of SMYS during Overbend or on rollers
Hoop Stresses = 90 % of SMYS on ground before overbend

Before Installation
Min Radius for Temporary Pipe Handling
Limiting SMYS = 90%
Bending Stress S = Ec/r
or R = 20064 cm
= 200.64 meters
B. During Installation

Max Pulling Load = 150 Tons


P=F/As = 314.957 kg/sqcm
Bending Stress Radius 120000 cm
= 690.51 kg/sqcm
Hydrotest Stress = 0.00 kg/sqcm
TOTAL Stress = 1005.47 kg/sqcm
Total Percent of SMYS = 21.91%

C. After Installation (Post Hydrotesting will be done at this stage)


Bending Stress at ROC = Ec/R
Longitudinal Stress at Test Pressure = pd/4t
Pulling Load = 0
Min Radius for Permanent Pipe Installation
As per ANSI B 31.4 factor of 1.85
Permanent Radius of Curvature - R = Ec/(0.75.S.SMYS-pd/4t)
Where S is design factor of 0.72
= 82860977.28 / [ 2478 - 1265.80 ]
= 68360.62 cm
= 683.606 meters
Taking 10% higher ROC = 752 meters
Permanent Radius Calc Check:
Bending Stress at ROC = Ec/R
= 690.51 kg/sqcm

Longitudinal Stress at Test Pressure = pd/4t


= 1265.80 kg/sqcm

Total Stresses = 1956.31 kg/sqcm


Stresses as Percent of SMYS = 42.63%

6. Combined Equivalent . Stresses


A: Before Installation

Page 3 of 5
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 32"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-01

Calculations required in accordance with ANSI code B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons for the
installation of pipes by HDD are as follows:
Hoop Stress Sh = pd/2t
Test Pressure Pt = 198.81 kg/sqcm
= 4230.18 kg/sqcm
= 92.19% of SMYS

Bending Moment for Pipe at 1200 cm Supports


= Ww.L2/12
= 10,14,132.00 kg-cm
Bending Stress Sb = BM/Polar MI
= 109.833 kg/sqcm

Combined Long Stress Sl1 = m x Sh + Sb Or m x Sh - Sb


= 1269.05 + 109.83 = 1269.05 - 109.83
= 1378.89 kg/cm2 = 1159.22 kg/cm2

Resultant Eq. Stress


Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2) Or Sqrt (Sl12- Sl1xSh+Sh2)
= 3736.68 kg/cm2 3786.09 kg/cm2
= 81.43% of SMYS 82.51% of SMYS

B: After Installation
Pressure at Final Hydrotest = 118.98 kg/cm2
Hoop Stress Sh = 2531.60 kg/cm2
Bending stress at give radius Sb = Ec/r
= 690.51 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 759.48 - 0.00 + 690.51
= 1449.99 kg/cm2

Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb


= 759.48 - 0.00 - 690.51
= 68.97 kg/cm2
Resultant Eq. Stress
Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2) VON MISES' EQUATION
= 2200.15 kg/cm2
= 47.95% of SMYS
Resultant 2 = Sqrt (Sl22- Sl2xSh+Sh2)
= 2497.82 kg/cm2
= 54.43% of SMYS
C: During Operation
Operating Pressure = 86.68 kg/cm2
Hoop Stress Sh = pd/2t
= 1844.33
Bending stress at give radius Sb = Ec/r
= 690.51 kg/cm2
Combined Long Stress Sl1 = m x Sh - Ea.dT + Sb
= 553.30 - 238.55 + 690.51
= 1005.26 kg/cm2

Combined Long Stress Sl2 = m x Sh - Ea.dT - Sb


= 553.30 - 238.55 - 690.51
= -375.76 kg/cm2
Resultant Eq. Stress
Resultant 1 = Sqrt (Sl12- Sl1xSh+Sh2)
= 1599.40 kg/cm2
= 34.85% of SMYS
Resultant 2 = Sqrt (Sl22- Sl2xSh+Sh2)
= 2058.10 kg/cm2
= 44.85% of SMYS

Page 4 of 5
HDD DESIGN CALCULATION OF CANAL CROSSING FOR 32"
PROJET: 14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
Cient : GULF ENGINERING PROJECTS
Contractor : Punj Lloyd
Drawing No: GEP/PUNJ/ORPIC/CS-01

Calculations required in accordance with ANSI code B31.4 for Pipeline Transportation Systems for Liquid Hydrocarbons for the
installation of pipes by HDD are as follows:

7 ROLLER SPACING DURING PULL


Allowable Bending Moment for Roller Spacing = 90% SMYS
= 4129.86 kg/cm2
Max Tensile force that can be applied = 150 tons
P=F/As = 314.96 kg/cm2

Available Stress for Bending Fb = 3814.90 kg/cm2

Bending Moment = Z*Fb


3,52,24,357.74 kg-cm
This bending moment will determine the roller spacing

For Simple spans (In between Rollers) BM = wL2/12


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 3,52,24,357.74 x 12 / 3.739 )
= 10633.04 cm
= 106.33 meters max

For Cantilever (On last Roller) BM = wL2/2


Where w is the weight of pipe in air
Max spacing between rollers = L = sqrt ( 3,52,24,357.74 x 2/ 3.739 )
= 4340.92 cm
= 43.409 meters max

8 PULLING REQUIREMENTS
Pulling loads is divided into 3 main forces. Viz:
= Fluid Drag Resistance + Soil Drag Resistance + Fluid Weight on Pull Head
= pDLf + f'wL + DbhA
= 26964.818 + 56037.79 + 10896.2
= 93898.85 kg
= 93.90 Tons

Total Pulling Force Required = 103.29 Tons cosidering safety factor 1.1
% of Force Required to Rig Capacity = 68.86%

Page 5 of 5
                                 

Contingency Plan
P for Horizont
H tal Directtional Drrilling:
Thee purpose off a Continge ency Plan or
o “Frac-out” plan is to: Minimizze the poten ntial
for a collapse /frac-out associated with horizzontal directional drilling activitties.
Thee timely de etection of collapse/ffrac-outs att protect areas
a that are conside
ered
environmentally sensitive e (dry lands, access roads, otther biological resourrces,
culttural resourrces) Ensurre an organnized, timely, and “minimum-impact” respo onse
in the event off collapses.. Ensure thaat all appro
opriate notiifications are made to
o the
concerned Authorities.

Ensuure that preventive


p and respoonsive mea asures to be implem mented by the
contractor. De esign proto ocols to be
e implemen nted for the protectioon of sensiitive
culttural and biiological re
esources. Deesign proto ocols to req
quire a geottechnical sttudy
to m
make recom mmendation ns regarding the suita ability of th
he formatio
ons to be bo ored
to m
minimize thhe potentiall for collapssing soil con
nditions.

Prio
or to constrruction, sen
nsitive cultural and biiological re
esources willl be proteccted
by implementing the follo owing meassures:

• A pedestrian surve ey will be conducted


c of the drilling entry and
a exit arreas,
surrounnding work k areas, and the drrilling routte (to the e extent it i is
accessible) to enssure that there are no cultural resources present on the
surfacee.
• The driilling entry and exit areas
a will be
b clearly marked,
m ex
xcavation oof all
entry or
o exit points to be mo onitored annd proper shoring
s and
d dewaterin ng to
be provvided if neccessary. Cle
early marke ed Barriers and warninng tapes willl be
erected d between the bore site and nearbyn sen ources prior to
nsitive reso
drilling. Ensure thhat all field
d personnel understan nd their reesponsibilityy for
timely reporting of collapse/frac-outts maintaining necesssary respo onse
equipm ment on-site
e or at a re eadily acceessible loca
ation and inn good worrking
order.
• Monitorring for the duratio on of entiire drilling g activitiess by qualiified
personn nel.
• Access and egress locations will
w be desig gnated and clearly ma arked.
• To minimize the potential extent
e of im
mpacts, HD DD team to o be notice the
pressurre readingss on the drilling
d equuipment att regular intervals. Early
E
detection is key too minimizing the area of potentia al impact.

Conntingency Response:
R O
Once a colllapse is ide
entified, alll works to be
b stopped and
the entire areea should beb barricad ded or closed to avoid potential damage from f
vehicles enteriing the area
a. Determin ne the locaation and exxtent of thee Collapse. The
Projject team shall provvide notificcation to all a concerne ed authorities about the
incident, clean
n-up, post-constructio on maintenance, and restoration n shall be done
d
by authority
a ap
pproved spe ecialist contractor as required
r byy them.

HDD Works – Soharr Industrial Portt Company ‐ OM
MAN 
DYNAMIC LOAD CALCULATION FOR DRILLING
Given data:

275 M

Pilot bore profile

 Pipe Dia (D) = 32 inch


 Pipe Grade = X65 Grade
 Length of Crossing (L) = 275m
 Max depth of crossing (h) = 17.5m
 Soil Density (Ds) = 1850 Kg/m3
 Water Density (Dw) = 1000 Kg/m3

ISSUE:
The drilling is laid by Horizontal Directional Drilling (HDD), under the canal may collapse the canal due to dynamic
load.

INTRODUCTION:
To prove that there won’t be any damage to the canal during installation of 32 inch pipe in 48 inch reamed hole.
To analyse the dynamic load Of 32 inch pipe during installation.

EXPLANATION:
Considering the apprehensions of canal, following explanation/ measures are being proposed by us to resolve the
issues: -

We were decided to do the drilling by HDD instead of open cut trench method. This will minimize the creation of pits
to only entry & exit pits (3m x3m) required only at an interval of >300 m.

It may be noted, while drilling by HDD, the annular space in drilled hole remains filled with bentonite and remains of
reamed earth. The water in the bentonite slurry eventually dries out. The bentonite slurry during the process of pilot
hole drilling/reaming is being pushed into the surrounding soil at a very high pressure. The kinetic energy of the
pressurized bentonite slurry shall be converted into the potential energy of the surrounding soil causing compression
and compaction, resulting in stabilization of canal.
The bentonite seeps in leaving a hard shell of bentonite clay solids around the surrounding soil leaving very small
voids. The bentonite shell has stiffness associated with it which keeps the canal intact and prevents the canal from
collapse during the process of HDD. Further annular space which is already filled with solidified bentonite shall be
further consolidated by natural interaction of soil, bentonite in due course of drilling time. As the drilling is being laid
at a depth of 10 m below canal bottom level, negligible loads shall get transmitted at the canal levels.

Further, arching effect in the surrounding soil contributes to the stability of the canal during & after installation
because of the arching behaviour of the soil. The arching behaviour of the soil results in further reducing the vertical
soil load which minimizes the chances of any collapse. While drilling the arching effect stays intact. As a result, the
arching around the canal is permanent as is the reduced vertical soil load. Pre- compression of soil during process of
reaming also adds to the stability of reamed hole in addition to the arching effect mentioned above. Though there
will be no effect on the stability of canal due to while drilling by HDD method.

CONCLUSION
Since technically there are no issues while drilling under the canal by HDD method, shall not cause any damage to
the canal, hence it is once again requested to grant permission for drilling under the canal by HDD method.

Note: See the mathematical calculation on the next page.


Mathematical Calculation
The objective of this below details is to mathematically calculate and explain the actual stresses transmitted in the
soil, based on the already established theories.

VERTICAL STRESS BELOW APPLIED LOAD


As per Boussinesq Equation, the vertical stress directly below the point load on its axis of loading at certain Depth
shall be calculated as

0.4775 Q / 𝑧 2

Where,
Q = Wheel Load
z = depth

In the present case, Q is assumed as 6525 kg (6.525 Tonne) and vertical stress is calculated at 10m depth
Vertical Stress at 10m depth = 0.4775 x 6525 / (10 x 10) = 31.15 kg/m2

Wheel load assumption:


When buried pipes are installed, principles of analysis for single pipes still apply. Soil cover must be greater than
minimum. However, the design of buried pipes requires an additional analysis for heavy surface loads. Above the live
load effect was found by the Boussinesq equation. As per Boussinesq equation ‘Q’ is assumed to be a point load
directly over the pipe. If wheel load ‘Q’ is assumed to be a distributed surface pressure, the Newmark integration
can be used.

ARCHING OF SOIL
Based on the theory of Terzaghi (1943) it is considered that arching occurs when the thickness of the soil mass
extending above the pipe is larger than 4 times the width of the soil column in shear (2B1). The width

1 1
𝐵1 = 𝐷0 + 𝐷0 × tan 45° − 𝜑 Is defined as:
2 2

With:
B1 is half the width of the soil column in shear m
Do is the outside diameter of product pipe m
Φ is the internal angle of friction °

In case of HDD sections, the contribution of the vertical inter-granular pressure at soil covers H > 8B1 (when arching
is assumed), the actual vertical inter-granular pressure at top of pipe level is reduced considerably.
Based on the above figure, it can be noted that for soil columns extending above the pipe smaller than 8B1 the
actual vertical inter-granular pressure is taken into account. For larger soil columns arching will occur and the vertical
inter-granular pressure then is assumed to be zero.

In the present case, outside diameter of Product Pipe 32’’ i.e. 0.8128 m and assumed internal angle of friction is 30
degrees.

Therefore B1 = 0.5 x 0.8128 + 0.8128 x tan (45° – 0.5 x30°) = 0.875 m

So, 8 B1 = 8 x 0.875 m = 7 m from ground level.

Hence, arching effect will occur at a depth of 7 m for 32 inch pipe in 48 inch reamed hole. So the pressure will not be
transmitted to the pipe.

Hypothesis:
The main characteristics of arches are the presence of Horizontal thrust induced at the support because of
unyielding supports which prevents the curved sections from straightening under vertical loads. The horizontal
thrust acts towards the arch. It produces compression stresses at all sections of the arch.

Analogy:
In the present case, annular space in the reamed hole behaves similar to arch. The presence of horizontal thrust
induced at the supports because of surrounding soil prevents the curved section from straightening under already
reduced vertical loads (account of arching effect of soil). The surrounding soil acts towards the soil resulting in
compression stresses at all sections of the soil above the annular space. This results in overall stability of soil above
the reamed hole.
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG

Rev.1 : 14-May-2018

C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG

FRAC-OUT CONTINGENCY PLAN


Introduction

Gulf Engineering Projects is engaged in Horizontal Directional Drilling Projects in the Sultanate of Oman. The
company is drilling under paved roads, Wadis and Water Canals. One of the few issues involved in HDD is
bentonite frac out which is mainly due to non-return of the slurry to the entry or exit pits.
Installation of HDEP/M.S pipes would include the use of trenchless excavation methods known as a guided
bore. This widely used technique accomplishes the installation of buried utilities with minimal impact, by
routing the utility under a sensitive feature (such as a stream, river or wetland). The guided bore procedure uses
bentonite slurry, a fine clay material as a drilling lubricant (drilling mud). Although bentonite is non-toxic, a
potential environmental risk associated with conducting guided bores under sensitive features occurs when
bentonite is released to the surface during construction (sometimes referred to as “frac-out”). The objective of
this frac-out contingency plan is to:

1. Minimize the potential for a frac-out associated with HDD activities;

2. Provide for the timely detection of frac-outs;

3. Ensure an organized, timely, and “minimum-impact” response in the event a frac-out and release of
drilling mud occur

Measures to be used as part of the contingency plan include site inspection, proper training of the HDD crews,
development of response procedures, provision of containment materials, and implementation of appropriate
clean up procedures. These measures are described in detail below:

Site Personnel Responsibilities

Our crew has overall responsibility for implementing this Frac-out Contingency Plan (FCP). The personnel
would be familiar with the aspects of the drilling activity, the contents of the FCP and the conditions of approval
under which the activity is permitted to take place. The crew members would provide a copy of this plan to the
appropriate construction personnel. They would ensure that workers are properly trained and familiar with the
necessary procedures for response to a frac-out, prior to initiation of drilling operations. We would provide the
anticipated schedule of boring operations around protected streams, roads and canals to the site inspector
responsible for the HSE officer prior to commencement of work.
The crew would be notified promptly when a frac-out is detected. The client would also be notified promptly, as
described below, when a frac-out is detected. The site supervisor a n d the HSE officer would have the authority
to stop work and commit the resources (personnel and equipment) necessary to implement this plan.

C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG
The crew on site and/or the site supervisor are responsible for promptly notifying the HSE officer of the
frac-out, and coordinating personnel to oversee proper clean-up and disposal of recovered material.
The HSE officer would be on the right-of-way, available during drilling operations to consult with boring
personnel and conduct inspections. The HSE officer would inspect the drilling operation for the purpose of
identifying signs of frac-out and would coordinate with the site Supervisor to implement the appropriate
measures to address a frac-out. Should a frac-out occur, the HSE officer would evaluate the situation and would
determine the appropriate level of response to the incident based on the guidelines contained in this FCP. The
HSE officer would consult with the client , who is the pipeline contractor , to determine appropriate measures to
contain and clean up inadvertent returns, and operational controls to prevent a reoccurrences such as reducing
mud pressure, changing drilling rate, change in mud viscosity, etc.

During operation of a bored crossing, pipeline construction personnel would monitor the pipeline drill path
throughout the process. Field crews would provide timely notifications and responses to observed frac-outs
in accordance with procedures identified in this FCP.

Training

Prior to the start of drilling, the site supervisor and HSE officer would verify that the construction field crew
members receive the following site-specific training: review provisions of the FCP, equipment maintenance
and site-specific permit and monitoring requirements; review location of sensitive environmental resources at
the site and relevant permit conditions; review inspection procedures for frac-out prevention and be familiar
with containment equipment and materials; review crew obligation to temporarily suspend forward progress of
the drilling upon first evidence of the occurrence of a frac-out and to report any frac-outs to the HSE officer ;
review operation of frac-out control equipment and the location of frac-out control materials, as necessary and
appropriate; and review protocols for reporting observed frac-outs and communication with appropriate
regulatory agencies.

Response

In the event a frac-out is observed during a bored crossing, the frac-out would be assessed to determine the
amount of slurry being released and potential for the frac-out to reach a surface water body. Response measures
would vary based on the location of frac-out as described below.

Wetland Location

• Temporarily suspend forward drilling and promptly notify the site supervisor and HSE officer.

• As soon as practicable after a frac-out event occurs in a site, notify the client As long as such
notification is possible through mobile phone and it does not interfere with response activities, the client
would be notified within two (2) hours of the Frac-Out event.

C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG

• The site Supervisor and HSE officer would evaluate the frac-outs and, in consultation with the crew on
site and client where practicable, implement appropriate response and cleanup measures. Frac-out
slurries in or adjacent to the site would be removed to the extent practical and the area restored to its
previous condition. Efforts to contain and recover slurry on affected site may result in further
disturbance by equipment and personnel, and possibly offset the benefit gained in removing the slurry.
Because it is difficult to predict the effect of a frac-out and attempts to recover the slurry, frac-out on
site would be evaluated on a case-by- case basis, and an appropriate level of response would be
implemented.

• If the amount of the frac-out slurry is too small to allow the practical physical collection from the
affected area, it would be diluted with fresh water and/or the fluid would be allowed to dry and dissipate
naturally.

• If the amount of the slurry exceeds that which can be contained with hand-placed barriers, small
collection sumps (less than 5 cubic yards) may be used to remove the slurry.

• If the amount of the slurry exceeds that which can be contained and collected using small sumps,
drilling operations would be suspended until the frac-out can be brought under control.

• The slurry would be stored in a temporary holding tank or other suitable structure, out of the stie area
and 30 meter buffer, for reuse or disposal.

In-Stream Locations
We have designed the bore to minimize the potential for frac-out in the canal. However, if an inadvertent frac-
out is observed, the following measures would be implemented:

• Temporarily suspend forward progress and notify the site supervisor and HSE officer. The HSE officer
would monitor the extent of the frac-out slurry plume.

• As soon as practicable after a frac-out event in the canal, notify the appropriate client staff. As long as
such notification is possible (e.g., there is cell phone service) and it does not interfere with response
activities, the client would be notified within two (2) hours of the Frac-Out event.

• Initiate containment measures and recovery of the frac-out slurry as appropriate. Containment is not
always feasible for in-stream frac-outs. However, conditions would be assessed as to whether hand-
placed containment, recovery or other measures, such as silt curtains and turbidity barriers, would be
effective and beneficial at the specific frac-out location. Returns would be contained using sandbags
and contained mud recovered by pumping or other means effectively removing the mud to the best
extent practical.

C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG

• Evaluate the current drill profile (e.g., drill pressures, pump volume rates, drilling mud consistency) to
identify means to prevent further frac-out events. Drilling operations would be suspended if the release
poses a threat to human health and safety or the environment.

• Once the return is mitigated and controlled, forward progress of the drilling may resume.
Containment Materials

At a minimum, the following containment, response, and clean-up equipment would be available at each
bored crossing location at the time such crossing occurs:

• sand bags - 10 Nos

• silt fence - 1

• plastic sheeting

• turbidity barriers

• shovels, pails; -1

• JCB - 1

• pumps and sufficient hose

• mud storage tanks -1

*** The decision of the quantity requirements is site based it will be taken by the operator base on site conditions.

Clean Up and Restoration

Site-specific clean up measures would be developed by the HSE officer and the site Supervisor following a frac-
out, in consultation with the client where practicable. Restoration measures should be developed in consultation
with the client prior to the site being restored. However, the following measures are considered appropriate.

• Drilling mud would be cleaned up by hand using hand shovels, buckets and JCB buckets as possible
without causing damage to existing vegetation. Fresh water washes would be employed if deemed
beneficial and feasible.
• Containment structures would be pumped out and the ground surface scraped to bare topsoil without
causing undue loss of topsoil or ancillary damage to existing and adjacent vegetation. Material would be
collected in containers for temporary storage prior to removal from the site.
C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
GULF ENGINEERING PROJECTS
D R I L L I N G C O N T R A C T I N G T R A D I NG

Documentation

The site Supervisor and HSE officer would record the frac-out event in his or her daily log. The log would
include the following: details of the frac-out incident, location and time of frac-out, the size of the impacted
area, notifications made, summary of the response and the success of the clean-up action.

C.R: 1264479 P O BOX 2033, P.C 133 M:+968 95111511/96279120 O/F: 220 999 28
QUOTATION@GEPROJECTSOMAN.COM GEPCOMAN@GMAIL.COM
Horizontal drilling using a wireline system to track the bit position.
A common used wireline system is the ParaTrack II system from Vector Magnetics.
This system has a high end steering tool which is connected to a wireline. The data from the steering
tool is transferred over the wireline to surface. This means you have always real time data from the
steering tool.

The ParaTrack II system is basically a double system.


The steering tool has three Inclinometers, three AC-Magnetometers and a temperature sensor on
board. These sensors are needed to get 3-dimensional readings.
First, it calculate the bit position over the distance that is drilled, using Inclination and Azimuth.
Second, using a coil which is placed on surface.

This coil is a single wire, most of the times 6mm2 cable, depending on the total length of the coil. The
coil will be energised by a special box, called the “Guidance Power Supply”. This box generates an AC-
signal which will generate an electromagnetic field. The coil can be seen as the heartbeat of the
system. Therefore is must be measured with a Total Station or GPS-system. These coordinates are
then put in the RivCross program using a Windows based computer. This program is connected with
an Interface box which then connect, via de wireline inside the drill pipe, with the steering tool. At
the end of every drill pipe, a survey will be taken to track the drill path. This data is projected in a
“Plan View” (Topo View) and “Section View” (Profile View) window.

The steering engineer will check:


 The feasibility of the planned horizontal crossing.
 Advice, if necessary, a new drill plan to increase the change of a successful crossing.
 Set-out the coil in the best possible way, which is a rectangular in a perfect world, under the
circumstances at the jobsite.
 All the data of the proposed drill (AutoCAD drawing)
 Check the ParaTrack II system to make sure it is in a good condition.
 Build the DHA (Down Hole Assembly).
 Set-up the RivCross program and enter the given coordinates from the coil (given by a land
surveyor).
 Give instruction to the driller with regards to the proposed drill.
o When jetting, he will tell the driller the Inclination and Azimuth needed at the end of
the drill pipe.
o When using a mud-motor, the steering engineer will tell the driller how many meters
he needs to rotate or steer in the desired direction.
 At the end of every drill pipe, a survey is taken and processed. This means that the position of
the drill head is checked, to make sure the required drill path is followed. If this is the case,
then the next drill pipe will be installed. If not, corrective action will be taken to correct the
position of the drill head.
 The steering engineer will also make sure that the drill radius is met and stays within the
given limits, therefore the change of a successful product pipe pull will be increased.
 After punch-out, the steering engineer will make the final As-build, so the client will know
where this installed product pipe is in the ground. If provided, it can also be plotted in the
AutoCAD drawing. This is very important for future reference.
Proposed Organization Chart
Chief Executive Officer
Qasim Al Lawati ( 95111511) Accounts Manager PMO - Office
Muscat
Admin Manager
Managing Director
Anil Kumar (99899451)
HR Manager

Project Manager
Navaz( 96278237)

Planning / Design HSE Officer (Ansari)


Engineer(TBA) -PTW (91722625)

Project Project
Supervisor/Op Supervisor/ HSE Supervisor
erator Operator
(PTW)- Mahfooz -
Umesh Saddam 96278817
(96270135) (96030438)
PTW PTW Logistics
Project Areas-Fahud-Sohar Coordinator(TBA)
Skilled Labor/6 Skilled Labor
People /6 People)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A
CL OF 14''Ø PROPOSED PIPELINE

N
B

B
SERVICE ROAD

EMBANKMENT
MAIN ROAD
C

C
CANAL
D

D
E

E
DRILLING LENGTH - 300.00 m PRODUCT PIPE 14" OD,

POSSIBILITY OF POWER CABLE (MAJIS)1.2m DEPTH


4" CS CONDUIT PIPE
HORIZONTAL CROSSING LENGTH - 250.00

SANITARY WASTE WATER(MAJIS) 4m DEPTH


F

F
TELECOM 1.2m (OMANTEL)DEPTH

TELECOM(OOREDOO) 1.0m DEPTH


TELECOM(OMANTEL) 1.2m DEPTH

SERVICE MAIN MAIN MAIN CANAL


BENTONITE SLURRY
ROAD EMBANKMENT
ROAD ROAD ROAD 28" Ø REAMED HOLE
G

G
25.000 m 25.000 m
SECTION "A-A"
(1:15)


6.81
4.55
H

H
10.0
17.50
R1200.00
250.45 250.45
I

I
J

J
K

K
L

L
PROPOSED DRAWING
M

M
STATUS SUBJECT OF REVISION
REVISION PERFORMER CHECKER APPROVER
N

N
CLIENT:

E:\Master bckup\backup1\Gulf\logo\gepco logo.jpg

GULF ENGINERING PROJECTS


CONTRACTOR:

Punj Lloyd
O

O
PROJECT:14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
TITLE:

PROPOSED HDD CROSS SECTION OF CANAL CROSSING


P

P
SIZE : A1 DRAWING NUMBER : REV.
SCALE : 1:1 GEP/PUNJ/ORPIC/CS-02 00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A
N CL OF 32''Ø PROPOSED PIPELINE
B

B
SERVICE ROAD

EMBANKMENT
MAIN ROAD
C

C
CANAL
D

D
DRILLING LENGTH - 300.00 m
E

E
PRODUCT PIPE 32" OD

POSSIBILITY OF POWER CABLE (MAJIS)1.2m DEPTH


HORIZONTAL CROSSING LENGTH - 270.00

SANITARY WASTE WATER(MAJIS) 4m DEPTH


F

F
TELECOM 1.2m (OMANTEL)DEPTH

TELECOM(OOREDOO) 1.0m DEPTH


TELECOM(OMANTEL) 1.2m DEPTH
SERVICE MAIN MAIN MAIN CANAL BENTONITE SLURRY
ROAD EMBANKMENT
ROAD ROAD ROAD

G

G
46" Ø REAMED HOLE

15.00 m
15.000 m SECTION "A-A"
(1:15)

6.81


4.55
H

H
10.0
17.50
R1200.00
270.60 270.60
I

I
J

J
K

K
L

L
PROPOSED DRAWING
M

M
STATUS SUBJECT OF REVISION
REVISION PERFORMER CHECKER APPROVER
N

N
CLIENT:

GULF ENGINEERING PROJECTS


CONTRACTOR:

Punj Lloyd
O

O
PROJECT:14"NGL Pipeline & 32" Gas Pipeline Project For
Oman Refineries & Petroleum Industries SAOC (ORPIC) Oman.
TITLE:

PROPOSED HDD CROSS SECTION OF CANAL CROSSING


P

P
SIZE : A1 DRAWING NUMBER : REV.
SCALE : 1:1 GEP/PUNJ/ORPIC/CS-01 00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Job Description:

1. General

2. Vehicle & Related Hazards

3. Medical & Environmental – Physical Hazards – Climatic

4. Psychological Factors

5. Mobilization at site

6. Material Handling

7. Preparation of HDD for Asphalt Road Crossing

8. Horizontal Directional Drilling

9. Confined space entry

10. Heat Stress and Emergency Response

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 1 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
1. General
 Communication Lack of  Provision of Interpreter / English – Arabic speakers Site Supervisor/
Language problems. communication Permit Holder/
B0
Barrier /misunderstanding 4 B B4 Crew members
will lead to
Wrong operation
Cultural  Lack of  Local disturbance  Provide local briefing pack at induction. Site Supervisor/
understanding  Legal issue,  Provision of translator / cultural advisor. Permit Holder/
C0
of local culture Protest 3 C C3  Daily Liaison with Project representative on security
and customs, Crew members
situation.
security threat,
violence.
 Deterioration of  Local disturbance  Supply and Chain Management Strategy to be Site Supervisor/
1 High relationship  Legal issue transparent with maximum local content in line with Permit Holder/
expectations between the  Protest technical & commercial requirements of the project Crew members
for use of Project and  Impact on  Explain Procurement and Purchasing Strategy to
local communities Company Locals
procurement due to Reputation  Transparency in Procurement process
and supplies disappointment
3 C C3  Audits C0
from locals who 
are not able to
get contracts for
supply,
procurement
and services
 Actions to
obstacle the

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 2 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Project progress
2. Vehicle Related hazard
 Poor vehicle  Personal injury  Vehicles to be maintained to manufacturer’s Driver and Journey
Vehicle Road condition  Property Damage standards. Conduct and record pre-survey vehicle Manager
4 C 4C C1
Worthiness  Impact to inspection and morning roadworthiness inspection.
Environment  Use approved drivers and restraint belt
 Road traffic  Personal injury  Defensive driving training and skills / pedestrian Do
On road accident  Property Damage awareness.
driving  Insurance  Impact to  Drivers not to use Mobile Phone while driving
4 C 4C C1
liability, PLL / Environment  Use of restraint belt and approved drivers.
OWNER  Legal Action  Usage of IVMS
reputation  Implementation of Journey Management System
 Unsuitable Personal injury  Ensure all vehicles are suitable and well equipped Do
Off Road vehicles, injury for terrain and conditions (PLL’s Construction H&S
2 Driving to personnel, Property Damage Plan).
damage to  Use approved drivers, defensive driving training.
property Impact to  Drivers not to use Mobile Phone while driving
 Lack of driver Environment 4 C 4C  Use of restraint belt and approved drivers. C1
experience.  Usage of IVMS
 Camel crossing Legal Action  Implementation of Journey Management System
the ROW and
meeting with an
accident
 Driver error Personal injury  As per road to better driving and JMP, ensure Do
Driver fatigue leading to adequate driver rest periods
4 C 4C C1
accident. Property Damage  Driver hours in accordance with Sultanate of Oman
Environment Impact legislation

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 3 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
 Driver error Personal injury  No Driving during adverse driving condition. Do
Adverse leading to  If in case stuck in adverse weather condition during
Weather accident. Property Damage the journey, then strictly follow JMP
condition/  Experience and trained drivers.
Fog/ dust Impact to 4 C 4C  No driving during dense fog and if the visibility is
cloud Environment less then stop the vehicle away from road and put
hazard warning light.
 No overtaking and rash driving during fog/ Dust
cloud
 Other drivers / Personal injury  No night travel other than approved deviations Do
Night driving road traffic
accident, Property Damage
4 C 4C C1
serious injury
Impact to
Environment
 Stranded in Personal injury  Provision of emergency / desert survival kit (water, Do
Vehicle Desert / isolated food, etc.) to be in vehicles at all times.
3 C 3C C0
breakdown location.  Usage of IVMS
 Implementation of Journey Management System
 Poor co- Personal injury  Daily Journey Management Plan. Do
Logistics / ordination, lost  Ensure vehicles are refuelled each evening
Poor mapping personnel.  Local arrangements between sub-contractors for
 Lack of fuel. fuel sharing and compensation
3 C 3C C0

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 4 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
3. Medical & Environmental – Physical Hazards – Climatic
Climate  Heat and cold Personal Injury  Temp/climate. Communication with weather Centre. Site Supervisor/
Extremes – stress,  Emergency Teams, Male Nurse with Ambulance at a Permit Holder/
Temperature dehydration Heat stroke strategic location on site/Emergency Response. Crew members
Variations/mo  Muscle strains 3 C C3  Allow acclimatisation at arrival in summer Training of C1
bilisation  Viral upper Expats. PPE provision.
respiratory tract  Provision of chilled drinking water in summer
infections.
Work in  Sunburns; Heat Personal Injury  Provision of chilled drinking water in summer Site Supervisor/
extreme of Rash, Fatigue,  Make available fluid, salts replacements Permit Holder/
temperatures: Cramps, Heat stroke (electrolytes) and first aid Crew members.
Exhaustion  Tents/shelter, work schedules, plan heavy work
heat and (shock), and accordingly
3 C C3 C1
heat Stroke
humidity
3 (coma)
(EXPAT  Dehydration
especially)  Urinary calculi,
renal colic
Non  Serious illness – Personal Injury  Adequate Pre-Employment Medical Examination Site Supervisor/
occupational Cardiac  Adequate vaccination Permit Holder/
health problems,  Clinic at camp for timely diagnosis and treatment Crew members
problems of Appendicitis,
Hernia, Malaria,
project 3 C C3 C1
Hepatitis etc.
employees

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 5 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
4. Psychological Factors
All except  Fatigue, home Disturbance lead to  Adapted recreation facilities and accommodation Site Supervisor/
local area sickness, work stoppage standards to the drawbacks of remoteness Permit Holder/
workforce depression,  Adapt the daily work schedules, shifts, and rotations Crew members
alcohol / drug Legal issue to allow optimal performance and minimise stress
Remoteness, abuse /  Camp Strategy
inadequate
violence,
Protest  Visit to near by town/ Market as per agreed schedule
isolation, with site management
recreational anxiety, panic
Impact on Company  Planned leave schedule
facilities / attacks, 3 C C3 C0
habitability, insomnia, Reputation
sexual depression
frustration (boredom),
impairment and
4 increased risk of
injury, illness,
reduced
effectiveness.
Expatriates  As above plus in Disturbance lead to  To recruit work force with Gulf experience Site
(early stages) addition: work stoppage  For Site (desert area) workers / Lone Workers:
deterioration of social games, reliable telecoms and transport, Supervisor/Engr.
Cultural pre-existing Legal issue survey risk assessment and mitigation, efficient
shock, health medical emergency response and emergency HR
3 C C3 C1
conditions response plan, regular rotation
exposure to Protest
(fragile patients  Town residents: social activities, recreational
alien culture, in hostile activities, fitness promoting activities, hobbies,
climate, low environment) Impact on Company
cultural immersion, reliable medical services and
standards of  Higher risk of Reputation
reassuring medevac and evacuation procedures

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 6 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
health care in physical and  Adequate pre-employment physical check
remote areas, mental stress.
lack of  Lack of
specialized efficiency,
resignation,
medicines
deterioration of
from abroad. medical
Unresolved / condition, are
unexpected much more
domestic likely
problems
back home
5. Mobilization at site
Loading /  Loads falling Personal Injury  Site Specific Method Statement / Risk Assessment. Site Supervisor/
unloading of from trucks Property Damage  Training Permit Holder/
equipment  Trapping limbs  STARRT / Tool Box Talk Crew members.
in pinch points Environment Impact  Supervision
3 C C3 C1
 Escort of equipment while shifting
 Prior inspection of equipment
5  Barricading and signage near loading and unloading
area
Lifting  Failure of Personal Injury  3rd Party inspection and certification Site
equipment / equipment. Property Damage  Colour coding
 Untrained 3 C C3  Lifting Plan C1 Supervisor/Engr.
Rigging
personnel Environment Impact  Riggers/Foreman/Operators third party certifications. Riggers

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 7 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Condition of  Failure of Personal Injury  Pre / Post Inspection / Inspection and Maintenance Site
vehicles / components Property Damage of vehicles/ Machinery vehicle certification Supervisor/Engr.
machinery  Injury to 3 C C3  Valid RAS certification C0
personnel Environment Impact  Periodic Maintenance
 Daily vehicle checklist in vehicle
Rigging  Pinching limbs Personal Injury  Test certification and inspection of chains, binders, Site
in pinch points strops etc. Supervisor/Engr.
 Falling object  Colour coding
2 C 2C  Trained Personnel C0
 Tool box talk by site management Riggers
 Barricading and signage.
 Use of proper PPE as per work requirements.
Alcohol / drug  Accidents, Personal Injury  Alcohol / drug abuse policy. Project Manager/
abuse organic and  Training on Alcohol / drug abuse as a part of HSE/
mental Property Damage induction HR/Individual
disorders, impair  Random checks of drivers and operators specially
performance, Legal issue  Drivers and operators counseling
time loss and 3 C C3  Drug and alcohol policy shall be strictly followed C1
resignation. Impact on company  Non compliance shall be dealt strictly with
Violence. Reputation disciplinary action.
 Action by local
authority /
punishment
Driver  Lack of training Legal issue  Driver certification, license, defensive driving Journey Manager
certification training.
0 C C0 C0
Impact on company  Drivers shall be medically fit.
Reputation  Behaviors base training to the drivers

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 8 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Rash driving  Accident Personal Injury  Speed restrictions. Do
 Overturning Property Damage  Strict policy no us e of mobile phone while driving.
4 C C4 C1
 Awareness and implementation of Journey
Management Plan
Storage of  Poor Access Personal Injury  Lay down areas, parking areas Site
materials / and egress Property Damage  Availability of MSDS Supervisor/Engr.
equipment  Fire  Availability of Method of statement/ JHA/
4 C C4 C1
 Slip and fall Manufacturer instruction.
 Adequate warning signboard
 Internal training for the team
Permits (road  Damage to Property Damage  Permits to move vehicles / machinery as per ROP Site
use, local) property and requirements. Supervisor/Engr.
facilities/ Roads Legal Issues
 Inconvenience 3 B B3 B1
to local people Impact on company
 Traffic violation Reputation
Overhead  Electrocution Personal Injury  Risk assessment, flagging / goal posts, signage. Site
transmission  STARRT & Tool Box Talk Supervisor/Engr.
lines, bridges, Property Damage 5 B B5  Briefing in induction B1
load  Counseling to the driver and operators for over head
Power Disruption crossing
restrictions
Spillage  Significant effect Enfironment Impact  Spill kits to be available, Training of personnel in the Site
(vehicles, to environment use of kits Supervisor/Engr.
machinery) Loss of revenue -
3 B B3  Disposal of contaminated soil as per local legislative B1
paying for requirements.
compensation,
medical expenses,

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 9 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
production loss or
deferment
6. Material Handling
Plant &  Failure of sling Personal Injury  Certification of equipment C1 Site Supervisor/
equipment  Fall of load 4 C C4  Colour coding Permit Holder/
Property Damage  Pre/ post inspection Crew members
Loading /  Overloading Personal Injury  Planning schedule, C1 Site Supervisor/
unloading  Fall of loose  Training of personnel. Permit Holder/
material Property Damage  Method statement / loading specification Crew members.
 Damage to pipe  Color coding of lifting gear and equipment.
/ equipment Disruption in  Weight of the load and lifting capacity of the
production 4 C C4
equipments shall be known.
 Availability of TPI certification of crane/ operators/
Impact on company Riggers etc.
Reputation  Strictly follow vendor loading and unloading
6
instructions
Transportatio  Material falling Third party damage  Secure load by proper latching C1 Site Supervisor/
n of Material from truck 3 C C3  Use certified belts / slings Permit Holder/
Loss of property  Vehicle certifications Crew members
Lifting  Failure of Personal Injury  Certification, test regime, test procedures. C1 Site Supervisor/
equipment equipment  Trained personnel Permit Holder/
Property Damage  Licensed Operator Crew members
 Trained first aid personal
4 C C4
 Signnag and Barricades on the lifting zone
 Color coding of lifting gear and equipment
 Periodic inspection of lifting equipments
 Use of checklist for inspection

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 10 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Use of public  Inconvenience  Disturbance lead  Permits, defensive driving training, flagging on C0 Site
roads to local peoples. to work stoppage trailers Supervisor/Engr.
 Legal issue  Communication to local communities through Public
3 C C3
 Impact on relation officer (PRO)
Company
Reputation
Crane  Topple down  Personal Injury  Trained & certified operators C1 Site
operations  Improper  Property Damage  Certification of lifting equipment and gears Supervisor/Engr.
slinging  Use of non-metallic slings to avoid damage of
 Fall of Load coating
 Outrigger  Colour coding
4 C C4
position  Rigging Foreman to ensure outriggers on firm ground
 Ensure Center of Gravity of load for slinging
 Safe Lifting Training
 Signaling to the operator will be by one/ single
competent person only.
Spillage  Significant impact  Provision of spill kits, training of personnel in the use C0 Site
on environment of kits. Supervisor/Engr.
3 C 3C
 Disposal of contaminated soil as per local legislative
requirements
7. Preparation of HDD for Asphalt Road Crossing
Survey to  Unaware of the  Damage to UG  Carry out route survey for the pipeline or cable by C1 Surveyor/ Site
locate route of UG Water pipeline/ using as built drawing
underground water pipeline cable  Identify any availability of route marker Supervisor/Engr.
7 3 C C3
services  No route  Service  Check with the local authority and get assistance if
marker interruption needed.
 None  If in doubt carry out trail pit excavation.

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 11 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
availability of
as build
drawing
Presence of  Rupture of  Loss of primary  Permit to work system. Site
Underground existing content.  Carry as built drawing
services pipeline.  Pipeline damage  Use cable locator/pipe locator. Supervisor/Engr.
 Damage to  Cable damage  Trial pit to be made for pipe identification.
3 C C3 C1
underground  Interruption of  Pipe once located to be protected and supported.
cables if any. services  Manual excavation method to be adopted.
 After cable or pipe get exposed, it shall be protected
suitably.
Presence of  Hydrocarbon  Fire  Gas test to be performed in the hazardous area Review for
hydrocarbon/ gas in  Explosion  Competent gas tester. improvement
gas vapour combustible  Calibrated gas detector. opportunities –
range coming 3 C C3 C1
Line Management
in contact with supervision
ignition source required
Work on  Inconvenience  Personal injury  Permit to work should be followed. Review for
public roads/ to local people  Local community  Daily tool box to be carried out. improvement
road diversion  Vehicle and issues  JHA to be reviewed and amended based on site opportunities –
animal falling condition if required. Line Management
into trench  Reflective Signage, clearly marked diversion and supervision
4 C C4 C1 required
use flickering lights to warn public
 If needed a diversion road to be provided
 Trench should be as per approved method
statement.
 Ladders to be used for safe access and egress if

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 12 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
required.
 Trench should have safe access/egress during
emergency.
 Notify local population and other contractors working
in the region
 Training of personnel to be ensured.
 All Project personnel to wear high visibility vests
 Traffic Management to be implemented.
 Flagman to be deployed for traffic management.
 Reinstatement of road to original condition on
completion of work.
 Appropriate PPE to be used.
Permits (road  Damage to  Personal injury  Permit from local bodies to be obtained. Site Supervisor/
use, local) roads and  Property Damage  Permits to move vehicles / machinery. Permit Holder/
facilities 3 C C3  Construct a diversion with proper barricade C1 Crew members
 Inconvenience  Flagging / signage
to local people
Machinery  Failure of  Personal injury  Experienced operators / drivers Site Supervisor/
and equipment  Property Damage  Only competent driver should carry out the activity. Permit Holder/
4 C C4 C1
equipment  Improper use  TPI inspection of equipment to be done. Crew members
 Reverse alarms & horns
Access /  Trapping of  Personal injury  Approved standard access and egress from Site Supervisor/
egress persons trenches Permit Holder/
3 C C4 C0
 Provide ladder for access and egress Crew members
 Trained and qualified First Aid personnel

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 13 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Deep  Limited  Personal injury  Proper barricade of pit and warning sign. Site
excavation accessibility  Property Damage  If required, Diversion road to be provided Supervisor/Engr.
 Confined  Proper signage to be provided
space  Ladders to be used for safe access and egress
 Unstable  Vehicles and equipment’s to be parked away from
ground strata the pit and in down wind direction
 Excavated material shall be kept at a safe distance
3 C C3 from the pit location. C1
 Water sprinkling shall be done to suppress dust and
trench collapse.
 All persons shall have attended confined space
training
 Follow confined space permit to work requirements.
 Mandatory PPE to be used.

Work Area  Waste  Environmental  Regular disposal of waste material, debris and C0 Site
accumulation impact scrape to designated waste storage area. Supervisor/Engr.
 Health Hazard 3 C C3  Provide waste drums/containers.
 Good housekeeping to be carried out in the area
Dust  Health (Dust  Throat /skin  Site supervisor shall ensure adequate dust control Site
entering eyes, irritation measure. Supervisor/Engr.
nose, lungs)  Respiratory 3 C C3  Appropriate PPE including dust Mask to be used.
 Poor vision problems  Adequate lighting o be checked.
 Sprinkling of water for dust control.
Heat  Sunburns; Heat  Personal Injury  Provision of chilled drinking water in summer Site
Rash, Fatigue,  Heat stroke 3 C C3  Make available fluid, salts replacements Supervisor/Engr.
Cramps, (electrolytes) and first aid

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 14 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Exhaustion  Tents/shelter, work schedules, plan heavy work
(shock), and accordingly
heat Stroke
(coma)
 Dehydration
 Urinary calculi,
renal colic
Noise &  Health effect  NIHL (Noise  Adequate rest Site
Vibration Induced Hearing  Appropriate PPE Supervisor/Engr.
Loss)  Job Rotation
 HAVS(Hand-Arm  Inspection of equipment
3 C C3
Vibration
Syndrome )
 MSD(Musculoske
letal disorders )
Water  Men/ Vehicle/  Flooding  Certified banks man to be provided to guide the C1 Site
logging due Live stock may  Trench Collaps operator of the equipment, Supervisor/Engr
to excavation: fall in trench  Personal injury  Install warning light/ signboards to warn others
 Damage to 3
rd
3 C C3  Barricade the area.
party  Ensure proper collection and disposal of water.
 Environmental
impact
8. Horizontal Directional Drilling - HDD.
Horizontal Damage to the  Personal injury  Trained and experience personnel at site. C1 CM/Site In
Directional existing u/g  Property Damage  Obtained valid permit to work charge/Permit
3 C C3
Drilling facilities  Environmental  Follow the steps mentioned in the approved method Holder/Operator
Impact of statement.

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 15 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Pilot Head, Reamers  No unauthorized personnel / vehicle /equipment are
Underground Struck at work site location.
 Bentonite shall be kept in a collection pond/ bunded
Vehicle accident area without contaminating the environment.
while working near  Workforce shall be aware of MSDS for Bentonite
busy roads/ crossing  Bentonite shall be disposed as per the sultanate of
Oman legislative requirements.
road from launcher
 While crossing the road, both the side of the road
to receiver and shall be checked for any vehicle movement.
reverse.  Banksmen shall be deployed to control person/ alert
for any vehicle movement while carrying out survey
Collapse of side on the asphalt road with locator.
walls of trench  In no case persons take chance to cross the road.
 Daily tool box talk shall be carried out to make them
Use of bentonite aware hazard associated with working near busy
road.
Men/ Material  Close competent supervision and HSE standby must
Falling in entry exit be ensured during HDD activity.
pit
 Ensure pre-use inspection is done with check list.
 Suitable reflective signage’s and barricading shall be
Eye irritation/
provided to alert other drivers to reduce the speed-
suffocation
Work in progress, Men at work, Reduce speed etc.
during bentonite
 Project specific PPE shall be worn at all the time and
mixing works all persons shall be with high visibility reflective vest.

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 16 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Placement of  Collapse of  Personal injury  Welded Pipe section to be at least at a distance of C0 CM/Site In
pipe section trench  Property Damage 1.5m from the trench charge/Permit
too close to  Injury to  Delay I work  Above ground supervision of people working inside Holder/Operator
trench people if inside progress trench for immediate rescue in case of emergency
3 C C3
the trench or  Use of ladder for emergency exit
burial in case  Restricted and limited personnel inside the trench
of trench
collapse
Trench  Insect  Personal injury  De-watering trench/ Water to be removed and C0 CM/Site In
Flooding breading  Property Damage diverted to approved area charge/Permit
where water (mosquito’s )  Project get 2 C C2  Proper fencing to prevent fall of person and animals Holder/Operator
table is high  Fall of person / delayed like camel falling into trench filled with water
camel  Proper and adequate signage and barricading.
9. Working in confined space
Working in Toxic gases  Personal injury  Permit to work should be followed. C0 CM/Permit Holder/
confined  Fatality  JHA to be reviewed and amended based on site HSE
space Oxygen deficiency  Impact of condition if required. officer/Individuals/
company  Ensure emergency access and rescue plans before Hole watcher/
Inadequate access reputation entry. Confined space
to outside  Make ready of all rescue equipment at site such as entrants.
harness, additional rope, ladder, access/ egress to
9 Lack of 3 C C3
bring down IP
communication /  Toolbox meeting covering all the hazards and
buddy system controls.
 Continuous gas monitoring to be carried out. At least
Trapping of 1 entrant must have a multi gas detector on his
persons inside. person at all times
 Assigned trained hole watcher and entrants for the

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 17 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
Heat stress due to job.
working in hot  Continuous circulation of air arrangement shall be
climate or doing hot provided
work.  Maintain uninterrupted contact with the workers by
the standby person.
 Keep only minimum number of persons for work to
avoid congestion
 Entrants to be rotated at regular intervals for rest
periods
 Supervisor and standby man to ensure record of all
persons working in confined space.
 Provide adequate cold water
 Ensure adequate ventilation.
 Maintain buddy system.
 Provide alternate egress arrangement before cutting
and removing the installed ladder.
 Use of mandatory PPE with clear glass and ear plug
to be worn at all the time.
10. Heat Stress and Emergency Response
Heat Stress & Heat exhaustion  Personal injury  Toolbox Talk to be conducted in language was Site
Emergency  Property Damage workers will easily understand. Heat stress Supervisor/Engr.
preparedness Illness awareness and importance of drinking water to be
discussed during Toolbox talk on a daily basis. Work
10 3 C C3 C1
& Rest ratio should be identified and cascaded to
Heat Cramps
work crew in the TBT.
 Heat stresses prevent procedures to be strictly
Heat stroke followed.

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 18 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Activity Potential

(after control in
Residual Risk
Consequence

Risk Ranking
(Identify

(Frequency-
Probability

place)
(Severity

Number)
number)
Sl. applicable

(letter &
Hazard/ Threat Impact / Effect Control Measures Acceptability

letter)
rating
No activity
associated
with the
work)
 Frequent breaks to be followed during hot season
Acclimatization especially when flag color changes.
 Eat/take food on time; don’t skip breakfast &dinner
Lone Working and Shelter to be provided if necessary.
 Do not stay / work on direct sunlight for long time,
take intervals.
 Comfortable and approved clothing to be worn.
 Water source to be made available at work site and
all personnel need to carry water thermos all time on
work site.
 Need to provide proper ventilation if required.
 Watch for any changes on the weather and follow
the rules accordingly.
 Any persist of stress symptom should be reported
immediately.
 Supervisor must be monitor his people all the times
and check any signs of heat stress.
 Number of emergency response team must be
known by all workers including the locations of
Muster point.
 Buddy system must be applied & Cold water should
be available at site.
 Acclimatization should be identified and avoided.
 Heat stress awareness training should be conducted
& project Heat Stress Procedure should be followed.

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 19 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
RISK ASSESSMENT FORM
14” NGL Pipeline of Orpic &
EPC of 32” Gas Pipeline of OGC- Fahud to Sohar, Oman
Activity: Horizontal Directional Drilling- HDD

Legend

Job step - Sequence of work activities


Hazard - The potential to cause harm (Health, injury, property damage, environment etc
Cause - Possible causes that will potentially release the Hazard
Consequences - The harm which could possibly occur
Potential risk H/M/L - With no controls in place
Recommended Controls - Describe additional controls that are required
Residual Risk H/M/L - With control in place

Mandatory Requirements:

1. Daily Tool Box talks


2. Permit to Work
3. Mandatory Personal Protective Equipment i.e.
(Coverall, Safety Shoes and hardhat) Job related
PPE – Hand gloves, Safety Harness etc.
4. Drinking water and Rest Shelter
5. Emergency Standby Vehicle
6. First Aider with adequate First Aid Kit.
7. Safety supervisor on site
8. Full time supervision

CONTRACT NO. DOCUMENT NO. REV. SHEET


OGC/01/2016 – 32” Pipeline
F900- CN-MST-00001-00-PGEP (LPIC) A Page 20 of 20
4600002122 – 14” Pipeline
FAH/SHR-9-3013-001-R1-4-A (OGC)
D 1 0 0 x 1 2 0 s e r i e s II n a v i g a t o r H D D

D 1 0 0 x 1 2 0 S E R I E S I I N A V I G AT O R ®
H O R I Z O N TA L D I R E C T I O N A L D R I L L
Efficiency at its best.

The D100x120 Series II was designed with


the operator in mind. A climate-controlled
cab with 360-degree visibility, a
state-of-the-art operator’s station and dual
joystick controls all help to increase operator
efficiency in the field.

The D100x120 Series II delivers 12,000 ft-lb


(16,269.8 Nm) of rotational torque and
100,000 lb (444 kN) of thrust/pullback force
to perform a wide range of bores in difficult
ground conditions. Equipped with a 225
hp (167.8 kW) John Deere diesel engine to
handle larger product, the D100x120 Series
II features a 150 gpm (567.8 L/min) or 200
gpm (757.1 L/min) onboard pump for
increased back-reaming efficiency and
power to downhole mud motors.

A self-cleaning rack-and-pinion carriage


drive helps reduce maintenance time by
eliminating chains. In addition, bolt-on gear
rack sections make replacement easy when
compared to welded gear-rack sections.

1: A climate-controlled cab provides 360-degree 2: The state-of-the-art operator’s station is elevated 3: An optional telescopic crane allows the drill operator to change
visibility for easy monitoring of the drilling operations. with an electrically operated swivel-and tilt-control out rod boxes without the use of an excavator or backhoe.
Independent heating and airconditioning controls allow the seat. Dual joysticks control functions for drilling fluid The remote-controlled crane gives the operator freedom to move
operator to control the cab climate and enhance comfort flow, breakout vise and throttle, and are integrated around the drill for improved visibility when replacing rod boxes.
in all weather conditions, including snow, rain and summer into the thrust and rotation controls. This feature The crane has a lift capacity of 7530 lb (3415.6 kg) and a
heat. A full-size hinged door provides easy access to the provides the operator fingertip control over repetitive maximum reach of over 20.6' (6.3 m).
operator’s station, while tinted glass windows help reduce drill functions.
glare and heat from the sun.
D100x120 Series II vermeer.com
1 2

4 5

4: Rack-and-pinion drive. This simple system 5: Measured to exact tolerances. Firestick® drill stem from
provides smooth operation. The D100x120 Series II Vermeer is designed to handle high-torque drilling situations
unique narrow rack-and-pinion design helps maintain while retaining a large inside diameter for superior drilling
a small footprint for accessability in congested areas. fluid flow. Constructed of Vermeer specified high-carbon
alloy steel, Firestick drill stem features one-piece, forged
rods that have been heat-treated for uniform strength
and consistent quality.
D 10 0 x 12 0 S E R I E S II
S P E C I F I C AT I O N S

GENERAL DIMENSIONS crane


AND WEIGHTS Max lifting capacity: 7530 lb (3415.5 kg)
Length: 34.1' (10.4 m) Max lifting capacity (at full reach): 2350 lb
Width (transport): 93" (236.2 cm) (1065.9 kg)
Height (crane option): 11' (3.4 m) Rotation: 200 degrees
Weight (without drill rod): 37,870 lb (17,177.5 kg) Max reach: 20.6' (6.3 m)
Weight (crane option, short rod box): 43,500 lb
(19,731.3 kg) DRILL ROD
Type: Firestick
POWER Length: 20' (6.1 m)
Engine: John Deere 6068 Joint diameter: 4.375" (11.1 cm)
Gross power rating: 225 hp (167.8 kW) Pipe diameter: 3.5" (8.9 cm)
Rated rpm: 2400 Rod weight: 351 lb (159.2 kg)
EPA certification: Tier 3 (Stage IIIA) Clip weight: 6090 lb (2762.4 kg)
Min bend radius: 197.4' (60.2 m)
fluid capacities Rod carrying capacity: 300' (91.4 m)

Engine oil (including filter): 8.3 gal (31.4 L)


Fuel tank: 75 gal (283.9 L) SAFETY
Hydraulic tank: 85 gal (321.8 L) Remote lockout: Yes
Electrical strike alert: Yes

OPERATIONAL
Thrust/Pullback: 100,000 lb (444 kN)
Max spindle torque (low at max engine rpm):
12,000 ft-lb (16,269.8 Nm)
Max spindle torque (medium at max engine rpm):
9000 ft-lb (12,202.4 Nm)
Max spindle torque (high at max engine rpm):
6000 ft-lb (8134.9 Nm)
Max ground drive speed: 3.2 mph (5.15 km/hr)
Drill rack angle: 22 – 33 degrees

DRILLING FLUID system — One


Max flow: 150 gpm (567.8 L/min)
Max pressure: 1100 psi (75.8 bar)

DRILLING FLUID system — TWO


Max flow: 200 gpm (757.1 L/min)
Max pressure: 1100 psi (75.8 bar)
D100x120 Series II vermeer.com
To help ensure smooth-running operations, your local Vermeer
dealer offers everything from training and tooling, to electronics
and software.

The Vermeer BORESTORE™ is your complete It’s in the mix. Select Vermeer drilling fluid
HDD tooling and accessories warehouse systems feature a modular design for flexible
accessible to you online and over the phone. mounting options.
Go to borestore.com or see your Vermeer
dealer for more information.

Pick up bentonites, polymers and wetting agents The family of DCI DigiTrak® locators offers the
from your Vermeer dealer. industry standard in technology and ease of use.

The global team of Vermeer Navigator specialists Vermeer e-CALC estimates project emissions
provide localized training and expertise to the and can demonstrate environmental advantage
drilling conditions in your area. to trenchless over competitive methods.

D100x120 Series II vermeer.com


T H E V E R M E E R D E A L E R N E T W O R K :
RELIABLE SUPPORT, ALL OVER THE WORLD.

Vermeer Asia Pacific Vermeer Corporation Vermeer Latin America


Singapore 608586 Pella, Iowa 50219 U.S.A. Valhinhos, São Paulo - Brazil
Phone: +65 6516 9560 Phone: (641) 628-3141 Phone: +55 19 3517-9400
Fax: +65 6515 9218 Fax: +55 19 3517-9401

Vermeer EMEA
(Europe, Middle East, Africa and CIS)
the Netherlands
Phone: +31 113 272700
Fax: +31 113 272727

Call toll-free 1-888-VERMEER


1-888-837-6337 (USA only)
www.vermeer.com

A G L O B A L I N I T I AT I V E
Equipment shown is for illustrative purposes only and may display optional accessories or components. Please contact your local Vermeer dealer for more information about machine specifications.
Vermeer Corporation reserves the right to make changes in engineering, design and specifications; add improvements; or discontinue manufacturing at any time without notice or obligation.
Vermeer, the Vermeer logo, Navigator, Firestick and BORESTORE are trademarks of Vermeer Manufacturing Company in the U.S. and/or other countries.
John Deere is a registered trademark of John Deere & Co.

4/13.1.5K ©2013 Vermeer Corporation. All Rights Reserved. PN 296260760


D330x500
M A X I R I G / H O R I Z O N TA L D I R E C T I O N A L D R I L L
D330x500

OuR SELF-CONTAINED MAXI RIG TAkES VERMEER RELIAbILITy AND pRODuCTIVITy TO THE
NEXT LEVEL, TuRNING HIGH-quALITy DESIGN INTO pERFORMANCE yOu CAN COuNT ON.

Robust vise design uses Excavator-style track pads reduce Bolt-on rack-and-pinion system Our Parts Center has drive motors,
a planetary gear for impact on paved surfaces. Standard features sectional design rotation motors, gear boxes,
breakout power. track width is 20" (50.8 cm); 30" for serviceability. pumps, valves, coolers and many
(76.2 cm) tracks are available for other major components in stock
increased flotation. and ready for delivery.

M A X I R I G S / H O R I Z O N TA L D I R E C T I O N A L D R I L L S
D330x500

When it comes to production, quality and reliability, Vermeer drills have long been at the forefront. With 50,000 ft-lb (67,790.9 Nm)
of rotational torque for drilling in difficult ground formations and turning large backreamers, and 330,000 pounds (1467.9 kN) of
thrust / pullback force, the D330x500 packs an impressive amount of muscle for those long and large-diameter drilling projects.

All drilling functions can be Onboard diagnostics include fault AutoDrill lets the operator preset Self-contained design allows
performed from the cabin, for codes for enhanced serviceability thrust / pullback for convenience. easy setup and convenient
ultimate comfort and convenient and troubleshooting. highway transport.
operation.

M A X I R I G S / H O R I Z O N TA L D I R E C T I O N A L D R I L L S
D330x500
S P E C I F I CAT I O N S

Specifications
Additional Components
Drill Unit Drilling Fluid System Drill Stem
Width: 100" (254 cm) Utilizes an auxillary standalone fluid system Type: Standard oil field
Height: 134" (340.4 cm) Length: Up to 32' (9.8 m)
Weight: 90,000 lb (40,823.3 kg) Features Pipe diameter: 4.5" – 6" (11.4 cm – 15.2 cm)
Length: 53.3' (16.2 m) Breakout system
Drilling lights Fluid Capacities
Operational Flow indicator Fuel tank: 210 gal (794.9 L)
Max spindle torque: Digital display with built-in diagnostic tool Hydraulic reservoir: 200 gal (757.1 L)
@ 44 rpm: 50,000 ft-lb (67,790.9 Nm) Stakedown system: Pad mount
@ 59 rpm: 37,500 ft-lb (50,843.2 Nm) Cab: Integrated 2-person all climate
@ 88 rpm: 25,000 ft-lb (33,895.4 Nm)
Max spindle speed: 88 rpm Power
Thrust (actual): 330,000 lb (1467.9 kN) Engine: CAT C-15 Tier 3
Pullback (actual): 330,000 lb (1467.9 kN) Gross power rating: 540 hp (402.7 kW)
Min bore diameter: 6.5" (16.5 cm) Net power rating: 486 hp (362.4 kW)
Max ground drive speed: 3 mph (4.8 km/h) Rated rpm: 2100 rpm
Max carriage speed: 56 fpm (17.1 m/min)
Drill rack angle: 13 – 30°
Remote lockout: Yes
Strike alert: Yes

M A X I R I G S / H O R I Z O N TA L D I R E C T I O N A L D R I L L S
D330x500
HYDRAULIC SYSTEM

Pump Layout / Carriage Assembly


puMpS
Travel pumps
(2) Sauer-Danfoss Series 90 100CC
Rotation pumps
(2) Sauer-Danfoss Series 90 100CC
Auxiliary pumps
(1) Sauer-Danfoss PC 45CC
(1) Gear pump 0.40 CID
H/C pump
(1) Eaton 36CC Gear pump
Flush pump
(1) Eaton 36CC Gear pump
(12) Poclain MS18
Travel Motors

Pinion gear

Rotation Gear Box Cutaway


(2) Rotation motors Input gear
Rotation Gear Box

Brake

Pullback bearing
* tapered roller bearing

Water swivel
Thru shaft Output gear
3" Water course
Thrust bearing
* tapered roller bearing

M A X I R I G S / H O R I Z O N TA L D I R E C T I O N A L D R I L L S
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

SODA ASH (Sodium Carbonate)


Commercial Chemical: pH Control
PRODUCT NAME: SODA ASH
1. PRODUCT & COMPANY IDENTIFICATION

SODIUM CARBONATE- SODA ASH

Company identification: S3 FLUIDS LLC

PO BOX: 26522, DIP 1, JEBEL ALI DUBAI UAE

Emergency Telephone: Tel: +971 48 8484 33 / +971 488 000 24

Product Name: Sodium Carbonate, Anhydrous

Alternate Product Name(s) Soda Ash, Disodium Carbonate

Also: Dense Soda Ash, Soda Ash Light, Synthetic Light Soda Ash, Soda Ash Liquid, Natural Light Soda Ash,
Natural Light HA

Soda Ash Chemical Formula Na2CO3

Product Use: Glass manufacture, detergent manufacture, sodium chemicals and carbonate chemicals
manufacture, pulp and paper, brine treatment, water hardness removal, pH adjustment in water or
wastewater, flue gas desulphurization, coal treatment, ion exchange resin regeneration.

This chemical is certified to ANSI/NSF Standard 60, Drinking Water Chemicals – Health Effects (as packaged
in the original, unopened container). Concentration not to exceed 100 ppm when used for corrosion
control or scale control pH adjustment.

2. Chemical Name CAS # Wt. % EC No. EC Class HS CODE

Sodium Carbonate 497-19-8 99.8 207-838-8 Xi, R36 28363000

3. Hazards Identification Emergency Overview: White, odorless, granular solid. Product is non-
combustible. Reacts with acids to release carbon dioxide gas and heat. May irritate skin and eyes. Dusts
may irritate respiratory tract. Not expected to be toxic to the environment, nor to aquatic organisms.
Avoid simultaneous exposure to soda ash and lime dust. In the presence of moisture (i.e. perspiration)
the two materials combine to form caustic soda (NaOH), which may cause burns.

Page | 1
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Potential Health Effects: Skin Prolonged contact may cause skin irritation (red, dry, cracked skin). Eyes
Irritating to the eyes. Ingestions although low in toxicity, ingestion may cause nausea, vomiting, stomach
ache, and diarrhea.

Inhalation: Prolonged inhalation of product dusts may irritate nose, throat, and lungs.

Chronic Effects: Excessive, long term contact may produce “soda ulcers” on hands and perforation of the
nasal septum.

Sensitivity reactions may occur from prolonged and repeated exposure.

This product does not contain any ingredient designated by IARC, NTP, ACGIH or OSHA as probable or
suspected human carcinogens.

4. First Aid Measures:

Skin: Wash with plenty of soap and water. Get medical attention if irritation occurs and Persists.

Eyes: Immediately flush with water for at least 15 minutes lifting the upper and lower eyelids
intermittently. See a medical doctor or ophthalmologist as necessary.

Ingestions: Rinse mouth with water. Dilute by giving 1 or 2 glasses of water. Do not induce vomiting. Never
give anything by mouth to an unconscious person.

Contact a doctor or poison control center. Inhalation: Remove to fresh air. If breathing difficulty or
discomfort occurs and persists, obtain medical attention. Advice to Physician While internal toxicity is low,
irritant effects of high concentrations may produce corneal opacities, and vesicular skin reactions in
humans with abraded skin only. Treatment is symptomatic and supportive.

5. Fire Fighting Measures

Extinguishing Media: Not combustible, use extinguishing method suitable for surrounding fire.
Fire/Explosion Hazards: Not applicable.

Fire Fighting Procedures: Wear full protective clothing and self-contained breathing apparatus

Flammable Limits: Not applicable

Auto ignition Temperature: Not applicable

Hazardous Combustion Products: Carbon dioxide.

Sensitivity to Impact: None / Sensitivity to Static Discharge: None

Page | 2
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

6. Accidental Release Measures

Personal Precautions: Refer to Section 8 “Exposure Controls / Personal Protection”

Containment: Prevent large quantities of this product from contacting vegetation or waterways; large
spills could kill vegetation and fish.

Clean Up: This product, if spilled, can be recovered and re-used if contamination does not present a
problem. Vacuum or sweep up the material. If the spilled product is unusable due to contamination,
consult state or federal environmental agencies for acceptable disposal procedures and locations. See
Section 13 “Disposal Considerations”.

Notification Requirements: Federal regulations do not require notification for spills of this product. State
and local regulations may contain different requirements; consult local authorities.

7. Handling and Storage Handling:

Use air conveying / mechanical systems for bulk transfer to storage. For manual handling of bulk transfer
use mechanical ventilation to remove airborne dust from railcar, ship or truck.

Use approved respiratory protection when ventilation systems are not available. Selection of respirators
is based on the dust cloud generation. Keep material out of lakes, streams, ponds and sewer drains.

Avoid eye contact or prolonged skin contact. Avoid breathing dusts. When dissolving, add to water
cautiously and with stirring; solutions can get hot. Use good personal hygiene and housekeeping.

Storage: Store in a cool dry area, away from acids. Prolonged storage may cause product to cake from
atmospheric moisture.

8. Exposure Controls / Personal Protection Engineering Controls:

Where possible, provide general mechanical and/or local exhaust ventilation to prevent release of
airborne dust into the work environment.

Eye wash facility should be provided in storage and general work area.

Personal Protective Equipment: Eyes and Face: For dusty or misty conditions, or when handling solutions
where there is reasonable probability of eye contact, wear chemical safety goggles and hardhat.

Under these conditions do not wear contact lenses. Otherwise, appropriate eye and face protection
equipment (ANSI Z87 approved) should be selected for the particular use intended for this material.

Safety glasses with side shields are recommended.

Respiratory: Whenever dust in the worker’s breathing zone cannot be controlled with ventilation or other
engineering means, workers should wear respirators or dust masks approved by NIOSH/MSHA, EU CEN or
comparable certification organization to protect them against airborne dust.

Page | 3
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Hands, Arms, and Body: Wear long-sleeve shirt and trousers, and impervious gloves for routine product
use. Cotton gloves are sufficient for dry product; wear impervious (e.g., rubber, neoprene, etc.) gloves
when handling solutions.

Exposure Guidelines: Federal guidelines treat the ingredient(s) in this product as a nuisance dust, as no
product-specific guidelines have been issued for exposure. As with all nuisance dusts, worker breathing
zone concentrations should be measured by validated sampling and analytical methods. The following
limits (OSHA and MSHA) apply to this material: Particulates Not Otherwise Regulated: OSHA (PEL / TWA):
15 mg/m3 (total dust); 5 mg/m3 (rasp fraction) MSHA (PEL / TWA): 10 mg/m3 (total dust) Avoid
simultaneous exposure to soda ash and lime dust. In the presence of moisture (i.e. perspiration) the two
materials combine to form caustic soda (NaOH), which may cause burns.The information noted above
provides general guidance for handling this product. Specific work environments and material handling
practices will dictate the selection and use of personal protective equipment (PPE).

9. Physical and Chemical Properties

Appearance: White, granular solid

Odour: Odourless / Formula: Na2CO3

Molecular Weight: Bulk Density (g/l) Dense grades: 0.9 – 1.1

Natural light grade: 0.7 – 0.9 Synthetic light grade: 0.5 – 0.7

Specific Gravity: 2.533 (vs. water)

Boiling Point: Decomposes Melting Point: 854oC (1569oF)

Evaporation Rate: Not applicable / Percent Volatile: 0%

Vapor Density: Not applicable / Vapor Pressure: Not applicable

pH (1% solution) 11.3 / Flash Point None

10. Stability and Reactivity

Stability: Stable Conditions to Avoid: Contract with acids will release carbon dioxide, heat. Contract with
lime dust in the presence of moisture can produce corrosive sodium hydroxide. Materials to avoid May
react with aluminum, acids, fluorine, lithium, and 2,4,6- Trinitrotoluene.

Polymerization: Will not occur. Hazardous Decomposition When heated to decomposition, carbon dioxide
is released.

Products Other Precautions: When dissolving, add to water cautiously and with stirring; solutions can get
hot.

Page | 4
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

11. Toxicological Information

Eye: Severe irritant (50 mg, rabbit).

Skin: Mild irritant (500 mg/24hr, rabbit). Minor irritation may occur on abraded skin. Not a sensitizer
(tested at 0.25% solution).

Oral: LD50, rat: 4,090 mg/kg Inhalation: LC50, rat, 2hr 2.3 mg/l 24 – hour LC50: 800 mg/m3, 20 h exposure
(guinea pig) (moderate toxicity)

Chronic: Excessive, long term contact may produce “soda ulcers” on hands and perforation of the nasal
septum. Sensitivity reactions may occur from prolonged and repeated exposure.

Carcinogenicity: Not designated by IARC, NTP, ACGIH or OSHA as probable or suspected human
carcinogens.

12. Ecological Information

Acute ecotoxicity: 96 – hour LC50: 265 – 565 mg/l (daphnia magnia) (low toxicity) 300 – 320 mg/l (blue gill
sunfish) (low toxicity) 96 – hour TLm: 1200 mg/l (mosquito-fish) 48 – hour TLm: 840 mg/l (mosquito-fish)
48 – hour EC50: 265 mg/l (daphnia magnia) 5 Day EC 50: 242 mg/l (Nitszcheria linearis)

Chronic ecotoxicity: 7 Day EC, biomass: 14 mg/l (phytoplankton)

Mobility: Air: Not Applicable Water: Considerable solubility and mobility. Soil / sediments: Non-significant
adsorption Abiotic degradation:Water (hydrolysis): degradation’s products: carbonate (pH>10) /carbonic
acid / carbon dioxide (pH<6). Soil: Hydrolysis as a function of pH.

Biotic degradation: Aerobic / anaerobic: Not applicable (inorganic compound)

Potential for bioaccumulation: Not applicable (ionizable inorganic compound) Observed effects are
related to alkaline properties of the product. Product is not significantly hazardous for the environment.

13. Disposal Considerations

Disposal: When this product is discarded or disposed of, as purchased, it is neither a Method:
characteristic nor a listed hazardous waste according to US Federal RCRA regulations (40 CFR 261).

As a non-hazardous waste the material may be disposed of in a landfill in accordance with government
regulations; check local or state regulations for applicable requirements prior to disposal. Any processing,
usage, alteration, chemical additions to, or contamination of, the product may alter the disposal

Requirements. Under Federal regulations, it is the generator’s responsibility to determine if a waste is a


hazardous waste.

Page | 5
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

14. Transportation Considerations

Proper Shipping Name: Not regulated

Primary Hazard Class / Division: Not regulated

UN / NA Number: Not applicable Label(s), Placard(s),

Marking(s): Not applicable Reportable Quantity (RQ) None 49 STCC Number: Not Applicable ADR (EU),
TDG (Canada) Not regulated IMDG (sea) , ICAO (air), IATA (air) Not regulated

15. Regulatory Information

UNITED STATES: SARA Title III (Superfund Amendments and Reauthorization Act) Section 302 Extremely
Hazardous Substances: 40CFR355, Appendix A Not listed Section 311 Hazard Class 40CFR370 Immediate
(acute) Section 312 Threshold Planning Quantity (TPQ) 40CFR370 No TPQ listed for sodium carbonate.
Section 313 Reportable Ingredients 40CFR372 Not listed CERCLA (Comprehensive Environmental
Response Compensation and Liability Act): 40CFR302.4 – There is no listed RQ (reportable quantity) for
this product. TSCA (Toxic Substance Control Act) This product is listed on the TSCA Inventory of Chemical
Substances.

No other TSCA rules affect this product State Regulations: This product does not contain any components
that are regulated under California Proposition 65. Other: Clean Water Act (CWA) – Section 301/ 311: Not
listed Clean Air Act (CAA) – Section 112: Not regulated Method: characteristic nor a listed hazardous waste
according to US Federal RCRA regulations (40 CFR 261).

As a non-hazardous waste the material may be disposed of in a landfill in accordance with government
regulations; check local or state regulations for applicable requirements prior to disposal.

Any processing, usage, alteration, chemical additions to, or contamination of, the product may alter the
disposal requirements.

Under Federal regulations, it is the generator’s responsibility to determine if a waste is a hazardous waste.

16. Other Information HMIS (Hazardous Material Identification System)

Health 2 Flammability 0 Physical Hazard 0 Personal Protection (PPE) B Protection = B (Safety glasses and
gloves) 4 = Severe, 3 = Serious, 2 = Moderate, 1 = Slight, 0 = Minimal NFPA (National Fire Protection

Association System) Health 2 Flammability 0 Reactivity 0 Special None 4 = Extreme, 3 = High, 2 = Moderate,
1 = Slight, 0 = Insignificant EC Labeling Name of substance to appear on label. Sodium Carbonate Symbol(s)
Xi – irritating Label Phrases R36: Irritating to eyes. S2: Keep out of reach of children. S22: Do not breathe

Page | 6
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

dust. S26: In case of contact with eyes, rinse immediately with plenty of water and seek medical advice.
Other Information: Soda ash is produced in three principal grades: Dense, natural light and synthetic light
soda ash. When these products are mixed in water they may be known as liquid soda ash. These grades
differ only in physical characteristics such as bulk density and size and shape of particles, which influence
flow characteristics and angle of repose. Other physical properties, as well as chemical as chemical
properties of solutions, are common to each grade of soda ash. Certified to ANSI / NSF 60 Concentration
not to exceed 100 ppm when used for corrosion control or scale control pH adjustment

DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or
accuracy. This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using
this product. Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular
purpose. S3 FLUIDS makes no representations or warranties, either expressed or implied, including without limitation any warranties of
merchantability, fitness for a particular purpose with respect to the information set forth herein or the product to which the information refers.
Accordingly, S3 FLUIDS will not be responsible for damages resulting from use of or reliance upon this information.

Page | 7
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

SODA ASH (Sodium Carbonate)


Commercial Chemical: pH Control
PRODUCT NAME: SODA ASH
1. PRODUCT & COMPANY IDENTIFICATION

SODIUM CARBONATE- SODA ASH

Company identification: S3 FLUIDS LLC

PO BOX: 26522, DIP 1, JEBEL ALI DUBAI UAE

Emergency Telephone: Tel: +971 48 8484 33 / +971 488 000 24

Product Name: Sodium Carbonate, Anhydrous

Alternate Product Name(s) Soda Ash, Disodium Carbonate

Also: Dense Soda Ash, Soda Ash Light, Synthetic Light Soda Ash, Soda Ash Liquid, Natural Light Soda Ash,
Natural Light HA

Soda Ash Chemical Formula Na2CO3

Product Use: Glass manufacture, detergent manufacture, sodium chemicals and carbonate chemicals
manufacture, pulp and paper, brine treatment, water hardness removal, pH adjustment in water or
wastewater, flue gas desulphurization, coal treatment, ion exchange resin regeneration.

This chemical is certified to ANSI/NSF Standard 60, Drinking Water Chemicals – Health Effects (as packaged
in the original, unopened container). Concentration not to exceed 100 ppm when used for corrosion
control or scale control pH adjustment.

2. Chemical Name CAS # Wt. % EC No. EC Class HS CODE

Sodium Carbonate 497-19-8 99.8 207-838-8 Xi, R36 28363000

3. Hazards Identification Emergency Overview: White, odorless, granular solid. Product is non-
combustible. Reacts with acids to release carbon dioxide gas and heat. May irritate skin and eyes. Dusts
may irritate respiratory tract. Not expected to be toxic to the environment, nor to aquatic organisms.
Avoid simultaneous exposure to soda ash and lime dust. In the presence of moisture (i.e. perspiration)
the two materials combine to form caustic soda (NaOH), which may cause burns.

Page | 1
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Potential Health Effects: Skin Prolonged contact may cause skin irritation (red, dry, cracked skin). Eyes
Irritating to the eyes. Ingestions although low in toxicity, ingestion may cause nausea, vomiting, stomach
ache, and diarrhea.

Inhalation: Prolonged inhalation of product dusts may irritate nose, throat, and lungs.

Chronic Effects: Excessive, long term contact may produce “soda ulcers” on hands and perforation of the
nasal septum.

Sensitivity reactions may occur from prolonged and repeated exposure.

This product does not contain any ingredient designated by IARC, NTP, ACGIH or OSHA as probable or
suspected human carcinogens.

4. First Aid Measures:

Skin: Wash with plenty of soap and water. Get medical attention if irritation occurs and Persists.

Eyes: Immediately flush with water for at least 15 minutes lifting the upper and lower eyelids
intermittently. See a medical doctor or ophthalmologist as necessary.

Ingestions: Rinse mouth with water. Dilute by giving 1 or 2 glasses of water. Do not induce vomiting. Never
give anything by mouth to an unconscious person.

Contact a doctor or poison control center. Inhalation: Remove to fresh air. If breathing difficulty or
discomfort occurs and persists, obtain medical attention. Advice to Physician While internal toxicity is low,
irritant effects of high concentrations may produce corneal opacities, and vesicular skin reactions in
humans with abraded skin only. Treatment is symptomatic and supportive.

5. Fire Fighting Measures

Extinguishing Media: Not combustible, use extinguishing method suitable for surrounding fire.
Fire/Explosion Hazards: Not applicable.

Fire Fighting Procedures: Wear full protective clothing and self-contained breathing apparatus

Flammable Limits: Not applicable

Auto ignition Temperature: Not applicable

Hazardous Combustion Products: Carbon dioxide.

Sensitivity to Impact: None / Sensitivity to Static Discharge: None

Page | 2
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

6. Accidental Release Measures

Personal Precautions: Refer to Section 8 “Exposure Controls / Personal Protection”

Containment: Prevent large quantities of this product from contacting vegetation or waterways; large
spills could kill vegetation and fish.

Clean Up: This product, if spilled, can be recovered and re-used if contamination does not present a
problem. Vacuum or sweep up the material. If the spilled product is unusable due to contamination,
consult state or federal environmental agencies for acceptable disposal procedures and locations. See
Section 13 “Disposal Considerations”.

Notification Requirements: Federal regulations do not require notification for spills of this product. State
and local regulations may contain different requirements; consult local authorities.

7. Handling and Storage Handling:

Use air conveying / mechanical systems for bulk transfer to storage. For manual handling of bulk transfer
use mechanical ventilation to remove airborne dust from railcar, ship or truck.

Use approved respiratory protection when ventilation systems are not available. Selection of respirators
is based on the dust cloud generation. Keep material out of lakes, streams, ponds and sewer drains.

Avoid eye contact or prolonged skin contact. Avoid breathing dusts. When dissolving, add to water
cautiously and with stirring; solutions can get hot. Use good personal hygiene and housekeeping.

Storage: Store in a cool dry area, away from acids. Prolonged storage may cause product to cake from
atmospheric moisture.

8. Exposure Controls / Personal Protection Engineering Controls:

Where possible, provide general mechanical and/or local exhaust ventilation to prevent release of
airborne dust into the work environment.

Eye wash facility should be provided in storage and general work area.

Personal Protective Equipment: Eyes and Face: For dusty or misty conditions, or when handling solutions
where there is reasonable probability of eye contact, wear chemical safety goggles and hardhat.

Under these conditions do not wear contact lenses. Otherwise, appropriate eye and face protection
equipment (ANSI Z87 approved) should be selected for the particular use intended for this material.

Safety glasses with side shields are recommended.

Respiratory: Whenever dust in the worker’s breathing zone cannot be controlled with ventilation or other
engineering means, workers should wear respirators or dust masks approved by NIOSH/MSHA, EU CEN or
comparable certification organization to protect them against airborne dust.

Page | 3
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Hands, Arms, and Body: Wear long-sleeve shirt and trousers, and impervious gloves for routine product
use. Cotton gloves are sufficient for dry product; wear impervious (e.g., rubber, neoprene, etc.) gloves
when handling solutions.

Exposure Guidelines: Federal guidelines treat the ingredient(s) in this product as a nuisance dust, as no
product-specific guidelines have been issued for exposure. As with all nuisance dusts, worker breathing
zone concentrations should be measured by validated sampling and analytical methods. The following
limits (OSHA and MSHA) apply to this material: Particulates Not Otherwise Regulated: OSHA (PEL / TWA):
15 mg/m3 (total dust); 5 mg/m3 (rasp fraction) MSHA (PEL / TWA): 10 mg/m3 (total dust) Avoid
simultaneous exposure to soda ash and lime dust. In the presence of moisture (i.e. perspiration) the two
materials combine to form caustic soda (NaOH), which may cause burns.The information noted above
provides general guidance for handling this product. Specific work environments and material handling
practices will dictate the selection and use of personal protective equipment (PPE).

9. Physical and Chemical Properties

Appearance: White, granular solid

Odour: Odourless / Formula: Na2CO3

Molecular Weight: Bulk Density (g/l) Dense grades: 0.9 – 1.1

Natural light grade: 0.7 – 0.9 Synthetic light grade: 0.5 – 0.7

Specific Gravity: 2.533 (vs. water)

Boiling Point: Decomposes Melting Point: 854oC (1569oF)

Evaporation Rate: Not applicable / Percent Volatile: 0%

Vapor Density: Not applicable / Vapor Pressure: Not applicable

pH (1% solution) 11.3 / Flash Point None

10. Stability and Reactivity

Stability: Stable Conditions to Avoid: Contract with acids will release carbon dioxide, heat. Contract with
lime dust in the presence of moisture can produce corrosive sodium hydroxide. Materials to avoid May
react with aluminum, acids, fluorine, lithium, and 2,4,6- Trinitrotoluene.

Polymerization: Will not occur. Hazardous Decomposition When heated to decomposition, carbon dioxide
is released.

Products Other Precautions: When dissolving, add to water cautiously and with stirring; solutions can get
hot.

Page | 4
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

11. Toxicological Information

Eye: Severe irritant (50 mg, rabbit).

Skin: Mild irritant (500 mg/24hr, rabbit). Minor irritation may occur on abraded skin. Not a sensitizer
(tested at 0.25% solution).

Oral: LD50, rat: 4,090 mg/kg Inhalation: LC50, rat, 2hr 2.3 mg/l 24 – hour LC50: 800 mg/m3, 20 h exposure
(guinea pig) (moderate toxicity)

Chronic: Excessive, long term contact may produce “soda ulcers” on hands and perforation of the nasal
septum. Sensitivity reactions may occur from prolonged and repeated exposure.

Carcinogenicity: Not designated by IARC, NTP, ACGIH or OSHA as probable or suspected human
carcinogens.

12. Ecological Information

Acute ecotoxicity: 96 – hour LC50: 265 – 565 mg/l (daphnia magnia) (low toxicity) 300 – 320 mg/l (blue gill
sunfish) (low toxicity) 96 – hour TLm: 1200 mg/l (mosquito-fish) 48 – hour TLm: 840 mg/l (mosquito-fish)
48 – hour EC50: 265 mg/l (daphnia magnia) 5 Day EC 50: 242 mg/l (Nitszcheria linearis)

Chronic ecotoxicity: 7 Day EC, biomass: 14 mg/l (phytoplankton)

Mobility: Air: Not Applicable Water: Considerable solubility and mobility. Soil / sediments: Non-significant
adsorption Abiotic degradation:Water (hydrolysis): degradation’s products: carbonate (pH>10) /carbonic
acid / carbon dioxide (pH<6). Soil: Hydrolysis as a function of pH.

Biotic degradation: Aerobic / anaerobic: Not applicable (inorganic compound)

Potential for bioaccumulation: Not applicable (ionizable inorganic compound) Observed effects are
related to alkaline properties of the product. Product is not significantly hazardous for the environment.

13. Disposal Considerations

Disposal: When this product is discarded or disposed of, as purchased, it is neither a Method:
characteristic nor a listed hazardous waste according to US Federal RCRA regulations (40 CFR 261).

As a non-hazardous waste the material may be disposed of in a landfill in accordance with government
regulations; check local or state regulations for applicable requirements prior to disposal. Any processing,
usage, alteration, chemical additions to, or contamination of, the product may alter the disposal

Requirements. Under Federal regulations, it is the generator’s responsibility to determine if a waste is a


hazardous waste.

Page | 5
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

14. Transportation Considerations

Proper Shipping Name: Not regulated

Primary Hazard Class / Division: Not regulated

UN / NA Number: Not applicable Label(s), Placard(s),

Marking(s): Not applicable Reportable Quantity (RQ) None 49 STCC Number: Not Applicable ADR (EU),
TDG (Canada) Not regulated IMDG (sea) , ICAO (air), IATA (air) Not regulated

15. Regulatory Information

UNITED STATES: SARA Title III (Superfund Amendments and Reauthorization Act) Section 302 Extremely
Hazardous Substances: 40CFR355, Appendix A Not listed Section 311 Hazard Class 40CFR370 Immediate
(acute) Section 312 Threshold Planning Quantity (TPQ) 40CFR370 No TPQ listed for sodium carbonate.
Section 313 Reportable Ingredients 40CFR372 Not listed CERCLA (Comprehensive Environmental
Response Compensation and Liability Act): 40CFR302.4 – There is no listed RQ (reportable quantity) for
this product. TSCA (Toxic Substance Control Act) This product is listed on the TSCA Inventory of Chemical
Substances.

No other TSCA rules affect this product State Regulations: This product does not contain any components
that are regulated under California Proposition 65. Other: Clean Water Act (CWA) – Section 301/ 311: Not
listed Clean Air Act (CAA) – Section 112: Not regulated Method: characteristic nor a listed hazardous waste
according to US Federal RCRA regulations (40 CFR 261).

As a non-hazardous waste the material may be disposed of in a landfill in accordance with government
regulations; check local or state regulations for applicable requirements prior to disposal.

Any processing, usage, alteration, chemical additions to, or contamination of, the product may alter the
disposal requirements.

Under Federal regulations, it is the generator’s responsibility to determine if a waste is a hazardous waste.

16. Other Information HMIS (Hazardous Material Identification System)

Health 2 Flammability 0 Physical Hazard 0 Personal Protection (PPE) B Protection = B (Safety glasses and
gloves) 4 = Severe, 3 = Serious, 2 = Moderate, 1 = Slight, 0 = Minimal NFPA (National Fire Protection

Association System) Health 2 Flammability 0 Reactivity 0 Special None 4 = Extreme, 3 = High, 2 = Moderate,
1 = Slight, 0 = Insignificant EC Labeling Name of substance to appear on label. Sodium Carbonate Symbol(s)
Xi – irritating Label Phrases R36: Irritating to eyes. S2: Keep out of reach of children. S22: Do not breathe

Page | 6
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

dust. S26: In case of contact with eyes, rinse immediately with plenty of water and seek medical advice.
Other Information: Soda ash is produced in three principal grades: Dense, natural light and synthetic light
soda ash. When these products are mixed in water they may be known as liquid soda ash. These grades
differ only in physical characteristics such as bulk density and size and shape of particles, which influence
flow characteristics and angle of repose. Other physical properties, as well as chemical as chemical
properties of solutions, are common to each grade of soda ash. Certified to ANSI / NSF 60 Concentration
not to exceed 100 ppm when used for corrosion control or scale control pH adjustment

DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or
accuracy. This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using
this product. Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular
purpose. S3 FLUIDS makes no representations or warranties, either expressed or implied, including without limitation any warranties of
merchantability, fitness for a particular purpose with respect to the information set forth herein or the product to which the information refers.
Accordingly, S3 FLUIDS will not be responsible for damages resulting from use of or reliance upon this information.

Page | 7
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

FLUIDSOL 40
High Yield Bentonite for Drilling Works

PRODUCT NAME: FLUIDSOL 40


PRODUCT & COMPANY IDENTIFICATION

SODIUM MONTMORILLONITE CLAY, SODIUM BENTONITE

Company identification: S3 FLUIDS LLC

PO BOX: 26522, Dubai UAE

Emergency Telephone: Tel: +971 4 884 84 33

1. Physical/Chemical Characteristics

Appearance and Odor: Brown /Pale greenish to creamy yellowish, pinkish or white color, No odor

Boiling Point: NA

Specific Gravity: 2.6

Solubility in water: Negligible pH: 8-10

CAS# 1302-78-9, EU # 215-108-5

HS CODE: 25081000

2. Fire and Explosion Hazard data

Flash Point: NA

Lower Explosive Limit: NA

Upper Explosive Limit: NA

Extinguishing Media: Media suitable for surrounding fire

2.1. Classification of the substance or mixture

Classification according CLP regulation (Regulation (EC) No. 1272/2008, as amended)

Not classified, Bentonite does not meet the criteria for classification.

Classification according EC Directive (67/548/EEC or 1999/45/EC, as amended)

Not classified, Bentonite does not meet the criteria for classification.

3. Chemical Composition / Ingredients Information

Chemical characterization

Synonyms: Bentonite, sodian; Bentonite, calcian; Montmorillonite, Sodium-activated Bentonite


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Bentonite is a UVCB substance, sub-type 4. The purity of the product is 100 % w/w.

Impurities are not applicable for a UVCB substance.

CAS number : 1302-78-9 / EC number: 215-108-5 / HS CODE: 25081000

4. Health Hazard Data

Route Of Entry- Inhalation: No

Route Of Entry - Skin: No

Route Of Entry - Ingestion: No

Health Hazards, Acute and Chronic: NO SPECIFIC HEALTH HAZARD KNOWN. THE Si O 2 IS PRIMARILY
COMBINED AS A COMPLEX ALUMINOSILICATE MINERAL & NOT AS A FREE OXIDE. HOWEVER, IT MAY CONTAIN
A MINOR AMOUNT OF SILICA IN THE FORM OF QUARTZ.

Carcinogenicity - NTP: No

Carcinogenicity - IARC: No

Accidental Release/ Spill: SWEEP OR SCOOP UP SPILLED MATERIAL. PLACE IN

CONTAINER MARKED NONHAZARDOUS MATERIALS.

Neutralizing Agent: NONE SPECIFIED BY MANUFACTURER.\ Waste Disposal Method: DISPOSAL MUST BE I/A/W
FEDERAL, STATE & LOCAL REGULATIONS

Precautions-Handling/Storing: SLIPPERY WHEN WET.

5. Emergency Overview

As part of good industrial and personal hygiene and safety procedure, avoid all unnecessary exposure to the
chemical substance and ensure prompt removal from skin, eyes and clothing.

Flammability Rating: 0 – None

Reactivity Rating: 0 – None

Contact Rating: 0 - None

Lab Protective Equip: GOGGLES; LAB COAT; VENT HOOD; PROPER GLOVES

Storage Color Code: Orange (General Storage)

6. EXPOSURE CONTROLS:

DNEL/DMEL values : DNEL/DMEL values are not available.

PNEC values: PNEC values are not available.


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Exposure controls

Appropriate engineering controls


Minimize airborne dust generation. Use process enclosures, local exhaust ventilation or other
engineering controls to keep airborne levels below specified exposure limits. If user
operations generate dust, fumes or mist, use ventilation to keep exposure to airborne
particles below the exposure limit. Apply organizational measures e.g. by isolating personnel
from dusty areas. Remove and wash soiled clothing
Respiratory protection : Local ventilation to keep levels below established threshold
values is recommended. In case of prolonged exposure to
airborne dust concentrations, a suitable particle filter mask
that complies with the requirements of national legislation is
recommended, depending on the expected exposure levels.
Hand protection : Use a high fat protective cream after cleaning skin. Wear suitable gloves.
Eye protection : Do not wear contact lenses. Safety glasses with side-shields
Ensure that eyewash stations and safety showers are close to
the workstation location.
Body protection : Long sleeved clothing

6. FIRST AID MEASURES

Inhalation: Remove to fresh air. Get medical attention for any breathing difficulty.

Ingestion: Give several glasses of water to drink to dilute and get medical advice.

Skin Contact: Wash exposed area with soap and water. Get medical advice if irritation develops.

Eye Contact: Wash thoroughly with running water for about 20 min. Get medical advice if Irritation/
reddishness develops.

7. FIRE FIGHTING MEASURES

Fire: Not considered to be a fire hazard.

Explosion: Not considered to be an explosion hazard.

Fire Extinguishing Media: Use any means suitable for extinguishing surrounding fire.

Special Information: In the event of a fire, wear full protective clothing and self-contained breathing apparatus
with full- face piece operated in the pressure demand or other positive pressure mode.

7. HANDLING & STORAGE

7.1. Precautions for safe handling Advice on safe handling


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Avoid dust formation. Provide sufficient air exchange and/or exhaust in work rooms. In case of insufficient
ventilation, wear suitable respiratory equipment. For personal protection see section 8. Handle and open
container with care. If you require advice on safe handling techniques or specific uses, please contact your

supplier or check the further information referred to in section 16.

Hygiene measures : Wash hands before breaks and at the end of workday.

7.2. Conditions for safe storage, including any incompatibilities

Requirements for storage areas and containers

Minimize airborne dust generation and prevent wind dispersal during loading and unloading.Keep containers
closed and store packaged products so as to prevent accidental bursting.

Advice on storage compatibility: No conditions to be specially mentioned.

Storage stability: Stable under recommended storage conditions.

8. PHYSICAL & CHEMICAL PROPERTIES:

Information on basic physical and chemical properties

Physical state : solid

Form : Fine Granular, powder

Colour : Cream / Grey / Brown


Odour : none
pH value : 6 - 11 (20 °C)
Method : Aqueous suspension
Melting point/range : > 450 °C Method : EU A.1
Boiling point/boiling range : not applicable (solid with a melting point > 450 °C)
Flash point : not applicable (solid with a melting point > 450 °C)
Evaporation rate : not applicable (solid with a melting point > 450 °C)
Flammability : does not ignite Method : EU A.10
Lower explosion limit : non explosive (void of any chemical structures commonly
associated with explosive properties)
Vapour pressure : not applicable (solid with a melting point > 450 °C)
Vapour density relative to air : not applicable
Solubility in water : < 0,9 g/l (20 °C) Method : Directive 84/449/EEC, A.6
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Octanol/water partition coefficient (log Pow) : not applicable inorganic


Self-ignition temperature : Method : Directive 92/69/EEC, A.6
no relative self-ignition temperature below 400 °C
Thermal decomposition : No decomposition if used as directed.
Viscosity (dynamic) : not applicable (solid with a melting point > 450 °C)
Oxidizing properties : no oxidizing properties (Based on the chemical structure, the
substance does not contain a surplus of oxygen or any structural groups known to be correlated with a
tendency to react exothermally with combustible material)

9 . STABILITY / REACTIVITY:

9.1. Reactivity : Stable under recommended storage conditions.


9.2. Chemical stability : The product is chemically stable.
9.3. Possibility of hazardous reactions : None known.
9.4. Conditions to avoid : Forms slippery/greasy layers with water.
9.5. Incompatible materials : inert, not reactive.
Avoid storing together with materials that may be affected by dust.
9.6. Hazardous decomposition products : Not relevant

10. TOXILOGICAL INFORMATION:

Acute oral toxicity : LD50 > 2 g/kg (rat) Method : OECD Test Guideline 420
Acute dermal toxicity : no data available
Bentonite is almost insoluble and has a low absorption through the skin.
Acute inhalation toxicity : no data available
Irritant effect on skin : not irritant (rabbit) Method : OECD 404
Irritant effect on eyes : not irritant (rabbit) Method : OECD 405
Sensitization : no data available

Bentonite is considered not to be a skin sensitizer based on

experience in handling and low absorption through the skin.

Genetic toxicity in vitro : Test type : In vitro gene mutation study in bacteria

Result : negative Method : OECD 471

Test type : In vitro chromosome aberration test

Result : negative Method : OECD 473


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Test type : In vitro gene mutation study in mammalian cells

Result : negative Method : OECD 476

Carcinogenicity : Based on available data, the classification criteria are not met.

Toxicity to reproduction/fertility Based on available data, the classification criteria are not met.

Specific target organ toxicity No organ toxicity observed in acute tests.

(STOT) - single exposure : Based on available data, the classification criteria are not met

Aspiration hazard : No aspiration toxicity classification

Remarks

Specific symptoms in animal studies (likely route of exposure):

In case of ingestion:No acute or long term effects were seen in animal studies following oral exposure.

In case of skin contact: No acute effects were seen in an animal study following acute dermal exposure.
Bentonite is not a skin irritant

In case of inhalation: No acute effects were seen in an animal study following acute inhalation exposure.

11. ACCIDENTAL RELEASE MEASURES

Ventilate area of leak or spill. Wear appropriate personal protective equipment as specified. Spills: Sweep up
and containerize for reclamation or disposal. Vacuuming or wet sweeping may be used to avoid dust dispersal.

12. ECOLOGICAL INFORMATION:

12.1. Toxicity

Information related to the product itself:

Fish toxicity : LC50 16 g/l (96 h, Oncorhynchus mykiss (rainbow trout))

LC50 2,8 - 3,2 g/l (24 h, Marine water fish)

Daphnia toxicity : EC50 > 100 mg/l (48 h, daphnia ( magna ))

Method : OECD 202

EC50 81,6 mg/l (96 h, Metacarcinus magister)

EC50 24,8 mg/l (96 h, Pandalus danae)

Algae toxicity : EC50 > 100 mg/l (72 h, Scenedesmus subspicatus)

Toxicity to terrestrial plants : 84,4 mg/kg (Phaseolus vulgaris)

No effect on the growth was observed.

84,4 mg/kg (Zea mays)


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
No effect on the growth was observed.

12.2. Persistence and degradability

Information related to the product itself:

Biodegradability : The methods for determining biodegradability are not applicable to inorganic substances.

12.3. Bioaccumulative potential


Information related to the product itself: Bioaccumulation: Not relevant for inorganic substances
12.4. Mobility in soil :
Bentonite is almost insoluble and thus presents a low mobility in most soils.
12.5. Results of PBT and vPvB assessment :
The substance does not meet the criteria for PBT or vPvB substance.
12.6. Other adverse effects
Additional ecotoxicological remarks none

13. DISPOSAL CONSIDERATIONS

Whatever cannot be saved for recovery or recycling should be managed in an appropriate and approved waste
facility. Although not a listed RCRA hazardous waste, this material may exhibit one or more characteristics of
a hazardous waste and require appropriate analysis to determine specific disposal requirements. Processing,
use or contamination of this product may change the waste management options. State and local disposal
regulations may differ from federal disposal regulations. Dispose of container and unused contents in
accordance with federal, state and local requirements.

14. TRANSPORT INFORMATION

This product is NOT classified as dangerous goods according to international regulations for transport by land,
inland waterways, and seas or by air.

ADR not restricted


ADN not restricted
RID not restricted
IATA not restricted
IMDG not restricted

15. REGULATORY INFORMATION

The product does not require a hazard warning label in accordance with EC directives on dangerous goods.

Safety, health and environmental regulations/legislation specific for the substance or


mixture
Water Hazard Class (Ger.) : not water endangering
Other regulations
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Bentonite is not a SEVESO substance, not an ozone depleting substance and not a persistent organic pollutant.
The product (bentonite) is not separately classified by the Occupational Health and Safety Administration
(OSHA). The product has not been classified as a human carcinogen by OSHA , the International Agency for
Research on Cancer (IARC) and the National Toxicology Program (NTP).

16. OTHER RELEVANT INFORMATION:


Social Dialogue on Respirable Crystalline Silica:

A multi-sectoral social dialogue agreement on Workers Health Protection through the Good Handling and Use of
Crystalline Silica and Products Containing it was signed on 25 April 2006. This autonomous agreement, which receives
the European Commission’s financial support, is based on a Good Practices Guide. The requirements of the Agreement
came into force on 25 October 2006. The Agreement was published in the Official Journal of the European Union (2006/C
279/02). The text of the Agreement and its annexes, including the Good Practices Guide, are available from
http://www.nepsi.eu and provide useful information and guidance for the handling of products containing respirable
crystalline silica. Literature references are available on request from EUROSIL, the European Association of Industrial
Silica Producers.
Prolonged and/or massive exposure to respirable crystalline silica-containing dust may cause silicosis, a nodular
pulmonary fibrosis caused by deposition in the lungs of fine respirable particles of crystal. In 1997, IARC (the International
Agency for Research on Cancer) concluded that crystalline silica inhaled from occupational sources can cause lung cancer
in humans. However it pointed out that not all industrial circumstances, nor all crystalline silica types, were to be
incriminated. (IARC Monographs on the evaluation of the carcinogenic risks of chemicals to humans, Silica, silicates dust
and organic fibres, 1997, Vol. 68, IARC, Lyon, France.) In June 2003, SCOEL (the EU Scientific Committee on Occupational
Exposure Limits) concluded that the main effect in humans of the inhalation of respirable crystalline silica dust is So there
is a body of evidence supporting the fact that increased cancer risk would be limited to people already suffering from
silicosis. Worker protection against silicosis should be assured by respecting the existing regulatory occupational
exposure limits and implementing additional risk management measures where required (see section 16 below).
DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or accuracy.
This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using this product.
Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular purpose. S3 FLUIDS
makes no representations or warranties, either expressed or implied, including without limitation any warranties of merchantability, fitness for a
particular purpose with respect to the information set forth herein or the product to which the information refers. Accordingly, S3 FLUIDS will not be
responsible for damages resulting from use of or reliance upon this information.
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

FLUIDSOL 40
High Yield Bentonite for Drilling Works

PRODUCT NAME: FLUIDSOL 40


PRODUCT & COMPANY IDENTIFICATION

SODIUM MONTMORILLONITE CLAY, SODIUM BENTONITE

Company identification: S3 FLUIDS LLC

PO BOX: 26522, Dubai UAE

Emergency Telephone: Tel: +971 4 884 84 33

1. Physical/Chemical Characteristics

Appearance and Odor: Brown /Pale greenish to creamy yellowish, pinkish or white color, No odor

Boiling Point: NA

Specific Gravity: 2.6

Solubility in water: Negligible pH: 8-10

CAS# 1302-78-9, EU # 215-108-5

HS CODE: 25081000

2. Fire and Explosion Hazard data

Flash Point: NA

Lower Explosive Limit: NA

Upper Explosive Limit: NA

Extinguishing Media: Media suitable for surrounding fire

2.1. Classification of the substance or mixture

Classification according CLP regulation (Regulation (EC) No. 1272/2008, as amended)

Not classified, Bentonite does not meet the criteria for classification.

Classification according EC Directive (67/548/EEC or 1999/45/EC, as amended)

Not classified, Bentonite does not meet the criteria for classification.

3. Chemical Composition / Ingredients Information

Chemical characterization

Synonyms: Bentonite, sodian; Bentonite, calcian; Montmorillonite, Sodium-activated Bentonite


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Bentonite is a UVCB substance, sub-type 4. The purity of the product is 100 % w/w.

Impurities are not applicable for a UVCB substance.

CAS number : 1302-78-9 / EC number: 215-108-5 / HS CODE: 25081000

4. Health Hazard Data

Route Of Entry- Inhalation: No

Route Of Entry - Skin: No

Route Of Entry - Ingestion: No

Health Hazards, Acute and Chronic: NO SPECIFIC HEALTH HAZARD KNOWN. THE Si O 2 IS PRIMARILY
COMBINED AS A COMPLEX ALUMINOSILICATE MINERAL & NOT AS A FREE OXIDE. HOWEVER, IT MAY CONTAIN
A MINOR AMOUNT OF SILICA IN THE FORM OF QUARTZ.

Carcinogenicity - NTP: No

Carcinogenicity - IARC: No

Accidental Release/ Spill: SWEEP OR SCOOP UP SPILLED MATERIAL. PLACE IN

CONTAINER MARKED NONHAZARDOUS MATERIALS.

Neutralizing Agent: NONE SPECIFIED BY MANUFACTURER.\ Waste Disposal Method: DISPOSAL MUST BE I/A/W
FEDERAL, STATE & LOCAL REGULATIONS

Precautions-Handling/Storing: SLIPPERY WHEN WET.

5. Emergency Overview

As part of good industrial and personal hygiene and safety procedure, avoid all unnecessary exposure to the
chemical substance and ensure prompt removal from skin, eyes and clothing.

Flammability Rating: 0 – None

Reactivity Rating: 0 – None

Contact Rating: 0 - None

Lab Protective Equip: GOGGLES; LAB COAT; VENT HOOD; PROPER GLOVES

Storage Color Code: Orange (General Storage)

6. EXPOSURE CONTROLS:

DNEL/DMEL values : DNEL/DMEL values are not available.

PNEC values: PNEC values are not available.


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Exposure controls

Appropriate engineering controls


Minimize airborne dust generation. Use process enclosures, local exhaust ventilation or other
engineering controls to keep airborne levels below specified exposure limits. If user
operations generate dust, fumes or mist, use ventilation to keep exposure to airborne
particles below the exposure limit. Apply organizational measures e.g. by isolating personnel
from dusty areas. Remove and wash soiled clothing
Respiratory protection : Local ventilation to keep levels below established threshold
values is recommended. In case of prolonged exposure to
airborne dust concentrations, a suitable particle filter mask
that complies with the requirements of national legislation is
recommended, depending on the expected exposure levels.
Hand protection : Use a high fat protective cream after cleaning skin. Wear suitable gloves.
Eye protection : Do not wear contact lenses. Safety glasses with side-shields
Ensure that eyewash stations and safety showers are close to
the workstation location.
Body protection : Long sleeved clothing

6. FIRST AID MEASURES

Inhalation: Remove to fresh air. Get medical attention for any breathing difficulty.

Ingestion: Give several glasses of water to drink to dilute and get medical advice.

Skin Contact: Wash exposed area with soap and water. Get medical advice if irritation develops.

Eye Contact: Wash thoroughly with running water for about 20 min. Get medical advice if Irritation/
reddishness develops.

7. FIRE FIGHTING MEASURES

Fire: Not considered to be a fire hazard.

Explosion: Not considered to be an explosion hazard.

Fire Extinguishing Media: Use any means suitable for extinguishing surrounding fire.

Special Information: In the event of a fire, wear full protective clothing and self-contained breathing apparatus
with full- face piece operated in the pressure demand or other positive pressure mode.

7. HANDLING & STORAGE

7.1. Precautions for safe handling Advice on safe handling


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Avoid dust formation. Provide sufficient air exchange and/or exhaust in work rooms. In case of insufficient
ventilation, wear suitable respiratory equipment. For personal protection see section 8. Handle and open
container with care. If you require advice on safe handling techniques or specific uses, please contact your

supplier or check the further information referred to in section 16.

Hygiene measures : Wash hands before breaks and at the end of workday.

7.2. Conditions for safe storage, including any incompatibilities

Requirements for storage areas and containers

Minimize airborne dust generation and prevent wind dispersal during loading and unloading.Keep containers
closed and store packaged products so as to prevent accidental bursting.

Advice on storage compatibility: No conditions to be specially mentioned.

Storage stability: Stable under recommended storage conditions.

8. PHYSICAL & CHEMICAL PROPERTIES:

Information on basic physical and chemical properties

Physical state : solid

Form : Fine Granular, powder

Colour : Cream / Grey / Brown


Odour : none
pH value : 6 - 11 (20 °C)
Method : Aqueous suspension
Melting point/range : > 450 °C Method : EU A.1
Boiling point/boiling range : not applicable (solid with a melting point > 450 °C)
Flash point : not applicable (solid with a melting point > 450 °C)
Evaporation rate : not applicable (solid with a melting point > 450 °C)
Flammability : does not ignite Method : EU A.10
Lower explosion limit : non explosive (void of any chemical structures commonly
associated with explosive properties)
Vapour pressure : not applicable (solid with a melting point > 450 °C)
Vapour density relative to air : not applicable
Solubility in water : < 0,9 g/l (20 °C) Method : Directive 84/449/EEC, A.6
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Octanol/water partition coefficient (log Pow) : not applicable inorganic


Self-ignition temperature : Method : Directive 92/69/EEC, A.6
no relative self-ignition temperature below 400 °C
Thermal decomposition : No decomposition if used as directed.
Viscosity (dynamic) : not applicable (solid with a melting point > 450 °C)
Oxidizing properties : no oxidizing properties (Based on the chemical structure, the
substance does not contain a surplus of oxygen or any structural groups known to be correlated with a
tendency to react exothermally with combustible material)

9 . STABILITY / REACTIVITY:

9.1. Reactivity : Stable under recommended storage conditions.


9.2. Chemical stability : The product is chemically stable.
9.3. Possibility of hazardous reactions : None known.
9.4. Conditions to avoid : Forms slippery/greasy layers with water.
9.5. Incompatible materials : inert, not reactive.
Avoid storing together with materials that may be affected by dust.
9.6. Hazardous decomposition products : Not relevant

10. TOXILOGICAL INFORMATION:

Acute oral toxicity : LD50 > 2 g/kg (rat) Method : OECD Test Guideline 420
Acute dermal toxicity : no data available
Bentonite is almost insoluble and has a low absorption through the skin.
Acute inhalation toxicity : no data available
Irritant effect on skin : not irritant (rabbit) Method : OECD 404
Irritant effect on eyes : not irritant (rabbit) Method : OECD 405
Sensitization : no data available

Bentonite is considered not to be a skin sensitizer based on

experience in handling and low absorption through the skin.

Genetic toxicity in vitro : Test type : In vitro gene mutation study in bacteria

Result : negative Method : OECD 471

Test type : In vitro chromosome aberration test

Result : negative Method : OECD 473


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Test type : In vitro gene mutation study in mammalian cells

Result : negative Method : OECD 476

Carcinogenicity : Based on available data, the classification criteria are not met.

Toxicity to reproduction/fertility Based on available data, the classification criteria are not met.

Specific target organ toxicity No organ toxicity observed in acute tests.

(STOT) - single exposure : Based on available data, the classification criteria are not met

Aspiration hazard : No aspiration toxicity classification

Remarks

Specific symptoms in animal studies (likely route of exposure):

In case of ingestion:No acute or long term effects were seen in animal studies following oral exposure.

In case of skin contact: No acute effects were seen in an animal study following acute dermal exposure.
Bentonite is not a skin irritant

In case of inhalation: No acute effects were seen in an animal study following acute inhalation exposure.

11. ACCIDENTAL RELEASE MEASURES

Ventilate area of leak or spill. Wear appropriate personal protective equipment as specified. Spills: Sweep up
and containerize for reclamation or disposal. Vacuuming or wet sweeping may be used to avoid dust dispersal.

12. ECOLOGICAL INFORMATION:

12.1. Toxicity

Information related to the product itself:

Fish toxicity : LC50 16 g/l (96 h, Oncorhynchus mykiss (rainbow trout))

LC50 2,8 - 3,2 g/l (24 h, Marine water fish)

Daphnia toxicity : EC50 > 100 mg/l (48 h, daphnia ( magna ))

Method : OECD 202

EC50 81,6 mg/l (96 h, Metacarcinus magister)

EC50 24,8 mg/l (96 h, Pandalus danae)

Algae toxicity : EC50 > 100 mg/l (72 h, Scenedesmus subspicatus)

Toxicity to terrestrial plants : 84,4 mg/kg (Phaseolus vulgaris)

No effect on the growth was observed.

84,4 mg/kg (Zea mays)


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
No effect on the growth was observed.

12.2. Persistence and degradability

Information related to the product itself:

Biodegradability : The methods for determining biodegradability are not applicable to inorganic substances.

12.3. Bioaccumulative potential


Information related to the product itself: Bioaccumulation: Not relevant for inorganic substances
12.4. Mobility in soil :
Bentonite is almost insoluble and thus presents a low mobility in most soils.
12.5. Results of PBT and vPvB assessment :
The substance does not meet the criteria for PBT or vPvB substance.
12.6. Other adverse effects
Additional ecotoxicological remarks none

13. DISPOSAL CONSIDERATIONS

Whatever cannot be saved for recovery or recycling should be managed in an appropriate and approved waste
facility. Although not a listed RCRA hazardous waste, this material may exhibit one or more characteristics of
a hazardous waste and require appropriate analysis to determine specific disposal requirements. Processing,
use or contamination of this product may change the waste management options. State and local disposal
regulations may differ from federal disposal regulations. Dispose of container and unused contents in
accordance with federal, state and local requirements.

14. TRANSPORT INFORMATION

This product is NOT classified as dangerous goods according to international regulations for transport by land,
inland waterways, and seas or by air.

ADR not restricted


ADN not restricted
RID not restricted
IATA not restricted
IMDG not restricted

15. REGULATORY INFORMATION

The product does not require a hazard warning label in accordance with EC directives on dangerous goods.

Safety, health and environmental regulations/legislation specific for the substance or


mixture
Water Hazard Class (Ger.) : not water endangering
Other regulations
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

Bentonite is not a SEVESO substance, not an ozone depleting substance and not a persistent organic pollutant.
The product (bentonite) is not separately classified by the Occupational Health and Safety Administration
(OSHA). The product has not been classified as a human carcinogen by OSHA , the International Agency for
Research on Cancer (IARC) and the National Toxicology Program (NTP).

16. OTHER RELEVANT INFORMATION:


Social Dialogue on Respirable Crystalline Silica:

A multi-sectoral social dialogue agreement on Workers Health Protection through the Good Handling and Use of
Crystalline Silica and Products Containing it was signed on 25 April 2006. This autonomous agreement, which receives
the European Commission’s financial support, is based on a Good Practices Guide. The requirements of the Agreement
came into force on 25 October 2006. The Agreement was published in the Official Journal of the European Union (2006/C
279/02). The text of the Agreement and its annexes, including the Good Practices Guide, are available from
http://www.nepsi.eu and provide useful information and guidance for the handling of products containing respirable
crystalline silica. Literature references are available on request from EUROSIL, the European Association of Industrial
Silica Producers.
Prolonged and/or massive exposure to respirable crystalline silica-containing dust may cause silicosis, a nodular
pulmonary fibrosis caused by deposition in the lungs of fine respirable particles of crystal. In 1997, IARC (the International
Agency for Research on Cancer) concluded that crystalline silica inhaled from occupational sources can cause lung cancer
in humans. However it pointed out that not all industrial circumstances, nor all crystalline silica types, were to be
incriminated. (IARC Monographs on the evaluation of the carcinogenic risks of chemicals to humans, Silica, silicates dust
and organic fibres, 1997, Vol. 68, IARC, Lyon, France.) In June 2003, SCOEL (the EU Scientific Committee on Occupational
Exposure Limits) concluded that the main effect in humans of the inhalation of respirable crystalline silica dust is So there
is a body of evidence supporting the fact that increased cancer risk would be limited to people already suffering from
silicosis. Worker protection against silicosis should be assured by respecting the existing regulatory occupational
exposure limits and implementing additional risk management measures where required (see section 16 below).
DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or accuracy.
This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using this product.
Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular purpose. S3 FLUIDS
makes no representations or warranties, either expressed or implied, including without limitation any warranties of merchantability, fitness for a
particular purpose with respect to the information set forth herein or the product to which the information refers. Accordingly, S3 FLUIDS will not be
responsible for damages resulting from use of or reliance upon this information.
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

POLYMATRIX HV
Refined Grade Viscosifier & Fluid Loss Control Agent
PRODUCT NAME: POLYMATRIX HV
1. PRODUCT & COMPANY IDENTIFICATION

ANIONIC WATER SOLUBLE POLYMER

Company identification: S3 FLUIDS LLC

PO BOX: 331179, Dubai UAE

Emergency Telephone: Tel: +971 48 8484 33 / Fax: +971 4 88 000 24

2. COMPOSITION / INFORMATION ON INGREDIENTS

Identification of the preparation: Anionic water-soluble polymer.

CAS Number: 9004-32-4

HS CODE: 39123100

3. HAZARDS IDENTIFICATION

Aqueous solutions or powders that become wet render surfaces extremely slippery.

Caution : Spilt material is slippery ; sweep up from floor. This powder when dispersed in air represents an
explosion hazard.

Short term exposure : No permanent effects on humans known from discontinuous short-term exposure when
used as directed.

Long term exposure : No permanent effects on humans known from discontinuous long-term exposure when
used as directed.

Ecology : No long-term ecological effects

4. FIRST AID MEASURES

Inhalation: Move to fresh air.

Skin Contact: Wash with water and soap as a precaution. In case of persistent skin irritation, consult a
physician.

Eyes Contact: Rinse thoroughly with plenty of water, also under the eyelids. In case of persistent eye irritation,
consult a physician.

Ingestion: The product is not considered toxic based on studies on laboratory animals.
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

5. FIRE-FIGHTING MEASURES

Conditions to avoid: Keep away from heat, sparks and flames.

Avoid excess dust in the atmosphere since this is an explosion hazard in the presence of electrical sparks and
static discharges.

Fire-fighting Measures: Fight the fire using water spray, sand, dry powder, carbon dioxide or foam.

Protective equipment: Impervious gloves. Use goggles. Use a dust mask.

Combustion products: Carbon monoxide, carbon dioxide, steam and smoke.

6. ACCIDENTAL RELEASE MEASURES

Personal precautions: No special precautions required.

Environmental precautions: Do not contaminate water.

Methods for cleaning up: Do not flush with water. Clean up promptly by scoop or vacuum. Keep in suitable
and closed containers for disposal. After cleaning, flush away traces with water.

7. HANDLING AND STORAGE

Handling: Avoid contact with skin and eyes. Avoid dust formation. Do not breathe dust. Wash hands before
breaks and at the end of work day.

Storage: Keep in a dry, cool place (0-35°C).

8. EXPOSURE CONTROLS / PERSONAL PROTECTION

Engineering measures to reduce Use local exhaust if dusting occurs. Natural ventilation is adequate in
exposure: absence of dusts.

Personal protection equipment Respiratory protection: Dust safety masks are recommended where
concentration of total dust is more than 10 mg/m3. Hand protection: Rubber gloves.

Eyes protection: Safety glasses with side-shields. Do not wear contact lenses.

Skin and body protection: Chemical resistant apron or protective suit if splashing or repeated contact with
solution is likely.

Hygiene measures: Wash hands before breaks and at the end of workday. Handle in accordance with good
industrial hygiene and safety practice.

9. PHYSICAL AND CHEMICAL PROPERTIES

Appearance: Free flowing powder of granulate


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Color: Light cream to white

Odour : Odourless

pH Value (25°C): 5.5 – 8.5 (2% solution)

Boiling Point (°C): Not Applicable / Flash Point (°C): Not Applicable

Water Solubility: Soluble

Solubility (Other): / Explosion Limit – Lower (g/m3): 156

CAS Number: 9004-32-4

10. STABILITY AND REACTIVITY

Stability: Product is stable, no hazardous polymerization will occur.

Materials to avoid: Oxidizing agents may cause exothermic reactions.

Hazardous decomposition products: Thermal decomposition may produce: nitrogen oxides (NOx), carbon
oxides.

11. TOXICOLOGICAL INFORMATION

Dermal: This product is not absorbed percutaneously in rats, rabbits or humans.

This product is believed not to cause irritation or sensitization.

Eyes: This product is believed not to be an irritant.

Oral: We believe that this product has a low order of toxicity. LD 50 > 2000mg/kg. The ingestion of small
amounts over a long period of time will not cause any adverse effects.

Inhalation: No effects known

12. ECOLOGICAL INFORMATION

12.1. Toxicity Information related to the product itself: Fish toxicity: LC50 > 100 mg/l (96 h, Oncorhynchus
mykiss (rainbow trout))

12.2. Persistence and degradability Information related to the product itself: Biodegradability: The product is
only slowly biodegradable.

Hydrolyze: Not expected to hydrolyse.

Biodegradation: Not readily biodegradable Log Pow: 0

Bioaccumulation: None
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

13. DISPOSAL CONSIDERATIONS

Waste from residues / unused products: In accordance with local and national regulation

Contaminated packaging: Rinse empty containers with water and use the rinse water to prepare the working
solution. Can be landfilled or incinerated, when in compliance with local regulations.

14. TRANSPORT INFORMATION

This product is NOT classified as dangerous goods according to international regulations for transport by land,
inland waterways, and seas or by air.

ADR not restricted


ADN not restricted
RID not restricted
IATA not restricted

IMDG not restricted

15. REGULATORY INFORMATION

This product is not a hazardous article and need not to be labelled according to EC-Directives as amended.

Inventory status: EINECS (Europe): Existing polymer according to the definition in the 7th Amendment to
Directive 67/548/EEC. All starting materials and additives are listed in EINECS. TSCA (USA) : Complies with all
applicable rules or orders under TSCA. DSL (Canada) : All components listed on inventory.

AICS (Australia): All components listed on inventory. MITI (Japan): All components listed on inventory. ECL
(Korea): All components listed on inventory. NEPA (China): All components listed on inventory. PICCS
(Philippines): All components listed on inventory.

16. OTHER INFORMATION

Person to contact Amit Carvalho

The information provided in this Safety Data Sheet is correct to the best of our knowledge, information and
belief at the date of its publication. The information given is designed only as a guidance for safe handling,
use, processing, storage, transportation, disposal and release, and is not to be considered as a warranty or
quality specification. The information relates only to the specific material designated and may be valid for such
material used in combination with any other materials or in any process unless specified in the text.

REGULATORY INFORMATION

The product does not require a hazard warning label in accordance with EC directives on dangerous goods.

DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or accuracy.
This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using this product.
Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular purpose. S3 FLUIDS
makes no representations or warranties, either expressed or implied, including without limitation any warranties of merchantability, fitness for a
particular purpose with respect to the information set forth herein or the product to which the information refers. Accordingly, S3 FLUIDS will not be
responsible for damages resulting from use of or reliance upon this information.
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

POLYMATRIX HV
Refined Grade Viscosifier & Fluid Loss Control Agent
PRODUCT NAME: POLYMATRIX HV
1. PRODUCT & COMPANY IDENTIFICATION

ANIONIC WATER SOLUBLE POLYMER

Company identification: S3 FLUIDS LLC

PO BOX: 331179, Dubai UAE

Emergency Telephone: Tel: +971 48 8484 33 / Fax: +971 4 88 000 24

2. COMPOSITION / INFORMATION ON INGREDIENTS

Identification of the preparation: Anionic water-soluble polymer.

CAS Number: 9004-32-4

HS CODE: 39123100

3. HAZARDS IDENTIFICATION

Aqueous solutions or powders that become wet render surfaces extremely slippery.

Caution : Spilt material is slippery ; sweep up from floor. This powder when dispersed in air represents an
explosion hazard.

Short term exposure : No permanent effects on humans known from discontinuous short-term exposure when
used as directed.

Long term exposure : No permanent effects on humans known from discontinuous long-term exposure when
used as directed.

Ecology : No long-term ecological effects

4. FIRST AID MEASURES

Inhalation: Move to fresh air.

Skin Contact: Wash with water and soap as a precaution. In case of persistent skin irritation, consult a
physician.

Eyes Contact: Rinse thoroughly with plenty of water, also under the eyelids. In case of persistent eye irritation,
consult a physician.

Ingestion: The product is not considered toxic based on studies on laboratory animals.
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

5. FIRE-FIGHTING MEASURES

Conditions to avoid: Keep away from heat, sparks and flames.

Avoid excess dust in the atmosphere since this is an explosion hazard in the presence of electrical sparks and
static discharges.

Fire-fighting Measures: Fight the fire using water spray, sand, dry powder, carbon dioxide or foam.

Protective equipment: Impervious gloves. Use goggles. Use a dust mask.

Combustion products: Carbon monoxide, carbon dioxide, steam and smoke.

6. ACCIDENTAL RELEASE MEASURES

Personal precautions: No special precautions required.

Environmental precautions: Do not contaminate water.

Methods for cleaning up: Do not flush with water. Clean up promptly by scoop or vacuum. Keep in suitable
and closed containers for disposal. After cleaning, flush away traces with water.

7. HANDLING AND STORAGE

Handling: Avoid contact with skin and eyes. Avoid dust formation. Do not breathe dust. Wash hands before
breaks and at the end of work day.

Storage: Keep in a dry, cool place (0-35°C).

8. EXPOSURE CONTROLS / PERSONAL PROTECTION

Engineering measures to reduce Use local exhaust if dusting occurs. Natural ventilation is adequate in
exposure: absence of dusts.

Personal protection equipment Respiratory protection: Dust safety masks are recommended where
concentration of total dust is more than 10 mg/m3. Hand protection: Rubber gloves.

Eyes protection: Safety glasses with side-shields. Do not wear contact lenses.

Skin and body protection: Chemical resistant apron or protective suit if splashing or repeated contact with
solution is likely.

Hygiene measures: Wash hands before breaks and at the end of workday. Handle in accordance with good
industrial hygiene and safety practice.

9. PHYSICAL AND CHEMICAL PROPERTIES

Appearance: Free flowing powder of granulate


PRODUCT MATERIAL SAFETY DATASHEET (MSDS)
Color: Light cream to white

Odour : Odourless

pH Value (25°C): 5.5 – 8.5 (2% solution)

Boiling Point (°C): Not Applicable / Flash Point (°C): Not Applicable

Water Solubility: Soluble

Solubility (Other): / Explosion Limit – Lower (g/m3): 156

CAS Number: 9004-32-4

10. STABILITY AND REACTIVITY

Stability: Product is stable, no hazardous polymerization will occur.

Materials to avoid: Oxidizing agents may cause exothermic reactions.

Hazardous decomposition products: Thermal decomposition may produce: nitrogen oxides (NOx), carbon
oxides.

11. TOXICOLOGICAL INFORMATION

Dermal: This product is not absorbed percutaneously in rats, rabbits or humans.

This product is believed not to cause irritation or sensitization.

Eyes: This product is believed not to be an irritant.

Oral: We believe that this product has a low order of toxicity. LD 50 > 2000mg/kg. The ingestion of small
amounts over a long period of time will not cause any adverse effects.

Inhalation: No effects known

12. ECOLOGICAL INFORMATION

12.1. Toxicity Information related to the product itself: Fish toxicity: LC50 > 100 mg/l (96 h, Oncorhynchus
mykiss (rainbow trout))

12.2. Persistence and degradability Information related to the product itself: Biodegradability: The product is
only slowly biodegradable.

Hydrolyze: Not expected to hydrolyse.

Biodegradation: Not readily biodegradable Log Pow: 0

Bioaccumulation: None
PRODUCT MATERIAL SAFETY DATASHEET (MSDS)

13. DISPOSAL CONSIDERATIONS

Waste from residues / unused products: In accordance with local and national regulation

Contaminated packaging: Rinse empty containers with water and use the rinse water to prepare the working
solution. Can be landfilled or incinerated, when in compliance with local regulations.

14. TRANSPORT INFORMATION

This product is NOT classified as dangerous goods according to international regulations for transport by land,
inland waterways, and seas or by air.

ADR not restricted


ADN not restricted
RID not restricted
IATA not restricted

IMDG not restricted

15. REGULATORY INFORMATION

This product is not a hazardous article and need not to be labelled according to EC-Directives as amended.

Inventory status: EINECS (Europe): Existing polymer according to the definition in the 7th Amendment to
Directive 67/548/EEC. All starting materials and additives are listed in EINECS. TSCA (USA) : Complies with all
applicable rules or orders under TSCA. DSL (Canada) : All components listed on inventory.

AICS (Australia): All components listed on inventory. MITI (Japan): All components listed on inventory. ECL
(Korea): All components listed on inventory. NEPA (China): All components listed on inventory. PICCS
(Philippines): All components listed on inventory.

16. OTHER INFORMATION

Person to contact Amit Carvalho

The information provided in this Safety Data Sheet is correct to the best of our knowledge, information and
belief at the date of its publication. The information given is designed only as a guidance for safe handling,
use, processing, storage, transportation, disposal and release, and is not to be considered as a warranty or
quality specification. The information relates only to the specific material designated and may be valid for such
material used in combination with any other materials or in any process unless specified in the text.

REGULATORY INFORMATION

The product does not require a hazard warning label in accordance with EC directives on dangerous goods.

DISCLAIMER: S3 FLUIDS provides the information contained herein in good faith but makes no representation as to its comprehensiveness or accuracy.
This document is intended only as a guide to the appropriate precautionary handling of the material by a properly trained person using this product.
Individuals receiving the information must exercise their independent judgment in determining its appropriateness for a particular purpose. S3 FLUIDS
makes no representations or warranties, either expressed or implied, including without limitation any warranties of merchantability, fitness for a
particular purpose with respect to the information set forth herein or the product to which the information refers. Accordingly, S3 FLUIDS will not be
responsible for damages resulting from use of or reliance upon this information.
PARATRACK

MASTERING THE ART OF HOLE OPENING


PARATRACK

Paratrack 1 - Basic underground tracking system utilizing


Guidance System Products a coil wire installed on surface or inside an adjacent product
line (underground) with a return coil configuration. A known,
HDD Guidance technology, developed and measurable magnetic field utilizing DC current is generated
manufactured by Vector Magnetics’, is rapidly being adopted which allows tracking of the borehole drilling assembly. This
as the HDD industry’s recognized standard for underground feature is compatible with the majority of prior generation
guidance accuracy. Paratrack’s unique multiple source magnetic steering tools presently in the HDD market.
tracking capabilities continue to expand HDD installation
applications. Inrock is Vector Magnetics’ authorized distributor Paratrack 2 - HDD’s most advanced, multiple feature guidance
and HDD partner, providing Paratrack equipment sales, rental, system.
service and support.
Paratrack 2 utilizes proprietary AC current technology providing
The Paratrack Steering Tool system is used to provide a multiple source magnetic tracking options enabling continuous
secondary means of verification of the positioning of the drill development of creative, technical guidance solutions. The
head when magnetic interference is encountered. A magnetic array of guidance features now available include:
field is induced which overcomes the interference caused by
ferrous materials along the bore path. Used in conjunction with • Single Guide Wire Tracking - Surface or underground
the Vector Magnetics downhole Steering Tool, Paratrack sets tracking, with or without return wire
the industry standard for trenchless construction by providing • Magnet Field Tracking Flexibility - Standard magnetic
accurate guidance of the bit even with magnetic interference. field grid positioning is no longer necessary
Lateral and vertical accuracy measures 0.2 ft/10ft of borehole
• Parallel Tracking - Precision underground tracking of
depth (2%).
multiple parallel bores

Paratrack system allows the engineer the flexibility to construct


coils in a manor previously unimaginable by prior steering tool
systems. The Paratrack system allows the engineer to use both
DC and AC current in the coil configurations.
• Intersections - Precision underground tracking of
two separate or multiple boreholes approaching from
varying directions for the purpose of joining these together.
Paratrack 2 intersect technology enables HDD installations
of much greater length than previously considered.

• Beacon Tracking System - Precision WIRELESS


underground tracking enables combination wire/wireless
or totally wireless HDD installations where previously wire
guided installations were difficult or not feasible.
Typical Performance Summary
• Pressure - PWD - Pressure While Drilling – Measures
Equipment Required:
annular and drill pipe pressures, enabling monitoring of • Paratrack Steering Tool, Drillers Console Interface, Power Guide
drill string and drilling total performance and borehole Supply, Computer
frac-out detection. • Wire to Construct surface or down hole coils 10 to 14 gauge wire
is usually sufficient
• AC Power Source - Computer Power Guide
The Paratrack® System allows the HDD contractor to bore with
confidence when magnetic interference is encountered along Accuracy:
• Paratrack is accurate to +/- 2% of the vertical depth of the
the bore path. borehole

Depth Capabilities:
• Paratrack is capable of working to depths in excess of 1000 feet.

Operations of the System:


Paratrack is the most advanced tracking systems in the HDD market
allowing the engineer creativity to utilize several magnetic sources and
methods for tracking
HDD Products
• Drill Bits • Drill Pipe (4-1/2” IF to 6-5/8” FH)
• Jetting Assemblies • Sonde Housings
• Non-Mag Drill collars • Crossover / Orientation Subs
• Directional Drilling Motors • Drilling Fluids
• Paratrack® Guidance Systems • Small Rig Rock Tooling
• Wireline Consumables • Geotechnical Analysis
• Digitrack® Systems • Project Planning & Feasibility
• HDX® Hard Rock Bits & Reamers • Drilling Tool Selection
• Rock Reamers • Time/Cost Estimates
• Hole Openers • Field Supervision & Training
• Centralizers • Guidance Training Certification
• Fly Cutters & Barrel Reamers • Drill Data™ Monitoring
• DCD Pull Back Swivels • BMR Reaming Product Lines
• Safety Tongs™ • XTR™ Reaming Product Lines

INROCK U.S.A
6000 BRITTMOORE
HOUSTON, TX 77041
(877) 2-INROCK

INROCK UK
HOVE TECHNOLOGY CENTRE
ST. JOSEPH’S CLOSE
BN3 7ES EAST SUSSEX UK
+ (44) 1273-735-500

INROCK LTD.
8207 39th St.
LEDUC, ALBERTA
CANADA T9E 8M7
(780) 486-1992
sales@inrock.com

www.INROCK.com
R9x12T
RECLAIMER

IMPROVE PERFORMANCE. Depending on the IN THE MIX. An integrated mixing hopper offers LIGHT UP YOUR JOBSITE. Equipped with
drilling conditions, the operator can select either simultaneous mixing and recycling within a single telescoping lights for around-the-clock operations.
a linear or orbital shaker motion to improve system, helping to eliminate the need for an
recycling performance. additional onsite drilling fluid mixing system.

FLUID PROTECTION. Inlet fluid is routed through A CLEAR VIEW. Controls for the main system PROTECTION FROM THE ELEMENTS.
mud boxes helping reduce premature wear to functions and optional mix hopper are located An enclosure helps protect critical components,
shaker decks/screens caused by larger material. on a single working level. Design considerations such as the generator set, fuel tank and electrical
centralize access to main controls to a single-level equipment from the elements. The enclosure
work area to reduce movement by crew members. features a service entry for accessibility and helps
reduce noise.

VERMEER.COM
R9x12T RECLAIMER
GENERAL WEIGHTS AND DIMENSIONS CLEANING SYSTEM
Weight: 65,500 lb (29,710.3 kg) Shaker type: Linear or orbital
Length: 51.8' (15.8 m) Number of shakers: 4 (2 motors/shakers)
Width: 8.5' (2.6 m) Shaker bed area – each: 26 sq ft (2.4 sq m)
Height: 13.4' (4.1 m) Number of screens per shaker: 3
Screen dimension: 25" x 49.3" (63.5 cm x 125.2 cm)
FRAME Cleaning capacity (first cut): 600 gpm (2271 L/min)
Type: Fifth-wheel trailer
Desander capacity: 1500 gpm (5678.1 L/min)
Suspension: Triple axle with air-ride
Desander quantity/size: 3 - 10" (25.4 cm) cones
Axles: 10-bolt, hub-piloted, ABS
Desilter capacity: 1280 gpm (4542.5 L/min)
Certifications: DOT lighting and braking
Desilter quantity/size: 16 - 5" (12.7 cm) cones

TANK CAPACITIES GENERATOR SET


Max capacity: 8560 gal (32,403.1 L) Generator: 3 phase 250 kW (313 kVA)
Number of tanks: 3
Clean/Mix tank capacity: 3197 gal (12,102 L) FEATURES
Agitator system: 3 – 2 hp (1.5 kW) stainless steel bladed mixers
Ancillary electrical system: 120/240 VAC
Work lights: 3 – 42W 12V LED

NOTES:

Vermeer Corporation reserves the right to make changes in engineering, design and specifications; add improvements; or discontinue manufacturing at any time without notice or obligation.
Equipment shown is for illustrative purposes only and may display optional accessories or components. Please contact your local Vermeer dealer for more information on machine specifications.
Vermeer, the Vermeer logo and Equipped to Do More are trademarks of Vermeer Manufacturing Company in the U.S. and/or other countries.
© 2015 Vermeer Corporation. All Rights Reserved. Printed in the U.S.A. Please recycle.

10/15.2000 PN 296431526

You might also like