Professional Documents
Culture Documents
This paper was prepared for presentation at the PSIG Annual Meeting held in Williamsburg,
Virginia, 11 October – 13 October 2006.
INTRODUCTION
This paper was selected for presentation by the PSIG Board of Directors following review of
In any pipeline designed and operated around the world,
information contained in an abstract submitted by the author(s). The material, as presented, “Transmission Capacity” definition is a controversial issue.
does not necessarily reflect any position of the Pipeline Simulation Interest Group, its officers,
or members. Papers presented at PSIG meetings are subject to publication review by Editorial
Committees of the Pipeline Simulation Interest Group. Electronic reproduction, distribution, or
storage of any part of this paper for commercial purposes without the written consent of PSIG
The life of a pipeline suffers a lot of changes and
is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 transformations in its own structure and in its border
words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, Pipeline conditions. At the time of design a lot of assumptions are
Simulation Interest Group, P.O. Box 22625, Houston, TX 77227, U.S.A., fax 01-713-586-5955. made about demand, peak and average flows, gas
specifications, environmental constrains, climate, route
classifications, performance estimations, operational
ABSTRACT philosophy, next expansions, regulatory changes, etc.
The “Transmission Capacity” of a Natural Gas Pipeline is However, this circumstances generally changes and clearly
generally a definition based on certain assumptions made by this are unpredictable in the design time, thus the pipeline
the operator. Meanwhile, the “Design Capacity” is an became incapable to comply with new demands or border
assumption made before the pipeline construction. condition changes.
“Transmission Capacity” is defined after the commercial
pipeline operation, verifying real performance, and assuming
sometimes arbitrarily, certain hypothesis. In theory, the main As the design capacity is an assumption made before the pipe
difference is based on time and amount of the available construction, the “real capacity” is a performance result
information. obtained after the start-up and the beginning of the
commercial operation. Clearly, any definition of the
Any definition of “Capacity” is a picture of a vision in steady transmission capability requires a complete description of the
state of pipe operation. When somebody mentions 400 Mcf/d framework and operational environment in which that capacity
of Capacity (millions of cubic feet day), it means “…in is estimated.
sometime of the pipe operation … under certain circumstance
assumed...” Clearly, a research to define a framework, the The system of TGN (Northern Gas Transmission Company) in
precedent conditions and the meaning of capacity definition, Argentina is one of the several cases that could be taken as an
could be a useful instrument to show a common understanding example.
of the “Nominal Capacity” concept.
TGN is mainly composed by two main pipelines called
“North” and “Central West” with a nominal capacity of 1,984
This paper analyzes the main variables involved, contractual
Mcf/d (56.2 Mm3/d) (43% North – 57% C.West) covering the
services obligations, demand curve, border conditions to be
Northern part of the country along 2,000 miles of R/W and
specified, transient vs. steady state, cost benefit analysis, peak
more than 300,000 HP of installed power in compression
hourly vs. average daily flow rate design, operational policy, ,
stations.
etc. Finally, conclusions and recommendations are presented
as a procedure to define “Nominal Transmission Capacity” Along the time a lot of expansions were made to fulfill the
and to produce a “Nominal Transmission Capacity Technical customers’ requierements, starting from 870 Mcf/d in 1993 to
Report” under the concept of arbitrary specific assumptions the current 1,984 Mcf/d.
for further analysis and discussions.
2 ALVAREZ, CARRANZA, PILLON PSIG 0609
2500
However, for many reasons we need to set or define a state of
2000 reference to share and communicate a common understanding
of the capacity or capability of the pipe or a system of pipes.
1500
C.West
Mcfd
94
95
96
97
98
99
00
01
02
03
04
05
•
19
19
19
19
19
19
19
20
20
20
20
20
20
Model Adopted
• Fluid Specifications
Figure 1 - 1993-2005 TGN Expansion • Demand Characteristics
• Operational Philosophy
As currently happens in most of the systems the gas • Contractual Obligations - Border Conditions
transported is frecuently distribuited along the pipes, and only • Regulatory Conditions (such as noise levels)
a small amount of gas reaches the final point of the systems.
Obviously, the whole pipe is designed for that condition, that Pipeline design methodology
means that the Nominal Capacity does not say to much about
the real Capability of the system. There are several classic methods for designing a new pipe; a
wide range of possibilities is available for engineers.
>50
512 Q(n,t)
P(0 t) t
This limitation of the Nominal Capacity Definition is not Q(x,t)
saved even using the “Transmition Momentum Concept”, it is Q(0,t)?
defining TM= Capacity*distance, as it was said a lot of PC stand by in t(o)
additional information must be done to give a significance at
any figure related with Capacity.
x(0,t) t
TDC =T ± OLP
4 ALVAREZ, CARRANZA, PILLON PSIG 0609
For daily operations, under the same assumptions the analysis A special paragraph is necessary to describe the operation
would be extended to other terms, Weekly, Monthly and philosophy, according the gas control organization and
Quaterly. structure, available human resources and the general client
satisfaction policy, a coefficient would be adopted to have a
Finally, whatever conclusions of the analysis were, the more confident operation, generally reducing the capacity
changes into obligations established in the Transmission available.
Contract will affect the design, and the necessary upgrade of
the pipe, in order to agree with the new contractual terms, The model or technique of choose of simulation is another
must be made. Another important issue is the Special Clauses important point that could also modify the results
of the Transmission Contract that would contain certain relief
as swaps or exceptions to the obligation of supply for some Several changes occur during the life of the pipeline and we
days, and others mitigation measures as Insurance Policy. get a new configuration: 4 segments (spreads), 3 compression
plants, 2 inlet points with 2 supplier, and 3 city gates with 3
Nominal transmission capacity definition clients (assumed shippers) is showed in Figure 4. For each
Due to Gas Pipeline constraints in commercial operation, the point the gas specifications, minimal contractual, pressures,
estimation of the “Capacity” is a subjective decision. As etc, are well known.
before mentioned the definition of certain “Transmission
Capacity” of a gas pipeline will be subject to certain variables
and constraints:
• Pipe/Network topology and physical characteristics.
Diameter, length, input/output nodes, branches locations,
compressions unit data, wall thickness.
• Operation philosophy. Operational flexibility and The input data collection is completed defining the Border
reliability standards, maintenance practice, stand by and Conditions, rate flows, maximum and minimum operative
spare parts policy, physical constraints. pressures.
PSIG 0609 Nominal Gas Pipeline Transmission Capacity 5
The Method adopted for simulation is based on steady state its power.
with some transient scenarios to verify special contractual
obligations. The result of the study shows that the system can support the
imposed border conditions (Design conditions) without any
At this moment a definition of Nominal Transmission difficulty. The table 2 shows the results and the figure 5, 6 and
Capacity is: “the total gas quantity capable to be injected in a 7 gives additional information.
gas pipeline system, expressed in Mcf/d (Mm3/d), to give a Variable Design New
firm transmission service to a group of clients in agreement Conditions Conditions
with the assumptions described in the Nominal Transmission Capacity 611 646
Capacity Technical Report. (NTCTR) (See Appendix 1)” (Mcf/d)
Peak Daily Flow 769 802
TDC (Mcf/d)
PIPELINE SIMULATION Maximum power
An example of simulation to answer the topics required in required (HP)
CS1 (9,000 inst) 8,994 5.100
NTCTR.
CS2 (12,500 inst) 11,221 12,200
CS3 (10,500 inst) 10,366 9,000
Description
Utilization factor 100% 100%
In the system described in Figure 3, defined as “Design
Utilization time (hs) 24 24
Condition” contrains the following assumptions:
Overloading factor 1.26 1.24
• The system supplies natural gas for a LDC located at the
Overloading time (hs) 19.04 19.3
end of the pipe in the spread 4 (called metering point 1).
Table 2: Sumary of results
• The Capacity required for that client was 611Mcf/d
Desing Condition - OILFILE 1
(17,3Mcm/d)(Table 1). Based on that assumptions the
system was designed in a steady state considering only one 650 960
Presure (psig)
(psig) (Mcfd) (psig) (Mcfd 600 880
) 590
860
81 Mi 840
570
31 OF2 - - 909 282 820
560
S2 81 CS1 638/ 611 710/ 646
93 Mi 953 953 550
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
800
600 800
590
Flow( M SCFD)
Presure (psig)
560
The term of study is 120 hours and the following facts were 550 600
540
taken into account: 530
a) The pressure injections remain constant along the 520
500
c) The compression stations (CS1, CS2 and CS3) Time (hour) Flow
Discharge Pressure
Succion Pressure
worked at discharge pressure constant and limited by Figure 6 Design condition – Compresor Station 3
6 ALVAREZ, CARRANZA, PILLON PSIG 0609
Flow( M SCFD)
Presure (psig)
650
380
Flow( M SCFD)
Presure (psig)
925
370
600 500
360 920
350
550 915
400 340
330 910
500
320
300 905
310
450
300 900
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
400 200 Time (hour)
Flow Pressure
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
Time (hour)
Flow Pressure
Figure 8: New Condition – Oilfield 1
Figure 7 Design condition – Metering Point 1
New Condition - OILFILE 2
400 914
Probably, but not certain, some spare capacity could be 390
possible, but always will depend on the change of the border 380
370 912
conditions. 360
350
910
340
Due to changes in the LDC requirements and the natural gas 330
320
producer availability, new border conditions had to be
Flow( M SCFD)
Presure (psig)
908
310
established. 300
290
906
280
The LDC has now 3 metering points (called MP1, MP2 and 270
260
904
MP3) totalizing a capacity required by 646 Mcf/d (18,3 250
240
Mm3/d) as is showed in Table 2. Simultaneously the gas is 230 902
suppled by 2 differents nodes (called OF1 and OF2), showed 220
210
in figure 4, 8 and 9. 200 900
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
Time (hour)
Flow Pressure
800 900
700 800
700
600
600
500
Flow( M SCFD)
Presure (psig)
300
300
200
200
100 100
Flow 1 Flow 3
Pressure 1 Pressure 3
0 0
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
Time (hour)
700
Flow( M SCFD)
Presure (psig)
The results of the simulations could be call “Nominal
150 650
Capacity” only if it is based on a Technical Report. Without
600
100
this complement information the Capacity losses all the
550
meaning. In other words, the Capacity of 646 Mcf/d calculated
50
500 above, means nothing if it is not supported by a NTCTR
450
0 400
A short example of NTCTR for this case is:
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121
Time (hour)
Flow 2 Pressure 2
NTCTR –“System figures 4”
Figure 11: Metering Point 2
New Condition - Compresor Station 3
1. Description: The current report is made to define the
“Nominal Transmision Capacity“ of the “Systems
550 1000
540
described in figure 4” and to describe the border
530 900
conditions and constrains under which the NTC is
520 defined.
510
800
500 2. General Information : see Appendix A
490
Flow( M SCFD)
Presure (psig)
700
480
3. Vocabulary, Definitions: (Not Applied).
470
600
460
450
4. System description: Figures 4. Tables 1 and 2.
500
440
430
5. Demand: Table 1 and defined gas specs.
420 400
Figure 12: Compressor Station 3 7. Operation philosophy: All the compression stations
and pipelines are able to operate at the mechanichal
A new pipeline simulation is necessary to know if it is design conditions.
possible to agree with the new customers requierements.
8. Simulation: The result of simulation are summarized
With the new border conditions and the same method, steady all in the tables 1 and 2 and the figures 5 to 12.
state plus transient simulation, we verified the customers’
requierements who asked us about the necessary investment 9. Conclusions and notes: The system can supply the
The results are: new requirement. The Nominal Transmission
Capacity for the system described under the current
a) The system Capacity could be 646 Mcf/d for the new report is 646 Mcfd (18,3 Mcm/d).
conditions, without any significant additional
investment. 10. Third Party additional comments: any objection made
b) The minimum pressures are higher than the obtained to the current report performed by third parties must
for the “Design Condition” be summarized in this section. It does not apply for
c) The Power of the Compression Stations is enough for this case.
the new conditions. However, it works at 100% with
limitations of discharge pressures in short terms. 11. Procedures to upgrade the report: for example, “this
report will be upgraded under any of the following
This results let us to conclude that the system can supply a circumstances (any of which occurs first)
new capacity of 646 Mcfd (18.3 Mcm/d) without additional
investments and according the border conditions assumed. a. For the next 39th PSIG by October 2007
Tables 1 and 2, and figures 8 to 12 summarize the results.
b. Any time a client requires a new service
8 ALVAREZ, CARRANZA, PILLON PSIG 0609
BIOGRAPHIES Appendix A
Oscar G. Alvarez has Civil Engineering Degree from
Universidad Tecnológica Nacional in Buenos Aires, Nominal Transmission Capacity
Argentina. He has more than 20 years worked in several
positions into the gas transmission industry. He is currently Technical Report
working as System Planning Supervisor for TGN. He is a
Professor in postgrade courses and author of several technical
papers. Contents
Hugo A. Carranza has Electrical Engineering Degree from 1. Introduction, purpose , description
Universidad Tecnológica Nacional in Buenos Aires, 2. General information: company, gas pipeline system,
Argentina. He has postgraduate studies in Natural Gas in date
Universidad Naconal de Buenos Aires. He worked in several 3. Vocabulary, Definitions
positions into the energy transmission industry. He is currently 4. System description
working as Technical Manager in TOTAL Gas Transmission a. Topology
Argentina. He is a University Professor in grade and b. Technical data
c. Compression facilities
postgraduate courses and author of several technical papers.
d. Reception and deliveries facilities
5. Demand
Fernando J. Pillon has Chemical Engineering Degree from
a. Contractual capacity required
Universidad Nacional de Buenos Aires, Argentina and
b. Type of services
Systems Dynamics Specialization from Universtat Politècnica
c. Boundaries contractual obligation (Minimum,
de Catalunya, Barcelona, Spain. With more than 9 years
maximum)
experience in gas transmission including 2 in the area of
d. Relief clauses
process analyzing and improvement, actually he is working in
e. Demand curve shape and contractual obligations
Gas Control for TGN.
f. Gas spec
g. Special clauses
6. Hydraulic Model
ACKNOWLEDGEMENTS a. Simulation methodology- model utilization
description
The authors want to thank their companies staff and directors b. Description of the model utilized
for their drive and cooperations to prepare an present this c. Description of the simulation methodology
paper. utilized
d. Main assumptions of the model (state equation,
roughness, heat transfer coefficients, etc)
7. Operational philosophy
a. Gas Control and dispatch criterions
b. Operational flexibility standards
c. Operational reliability standards
d. Border condition assumed (set points)
i. Receive and delivery nodes
ii. Flow rates and pressure by nodes
iii. Gas spec by receive nodes
iv. Contractual obligations in delivery
nodes
8. Simulation
a. Results of the simulation
b. Nominal capacity calculated chart
9. Conclusions and notes
10. Third party additional comments
11. Procedures to upgrade the report.