WEEKLY STATUS REPORT FOR ELECTRICAL

TO: MR GERRY DE GUZMAN


FROM: MIR MOHAMMED ALI
SUBJECT: WEEKLY ACCOMPLISHMENT REPORT

Activities Completed this Week


 Measurement and installation of fire alarm RGS 3/4’’conduits and Utility
box at share wall near entrance lobby of OME building done.
 Measurement and calculation of LV duct bank of site layout (power) done.
 TQ prepared for power receptacles and fire alarm junction box to re-locate
from column to gypsum board panel and masonry unit submitted.
 Measurement of grounding and power sleeves done at Maintenance
building.
 Installation of grounding and power sleeves done at maintenance building.

Activities Pending
 Installation of 70mm2 grounding cables at OME building pending.

Reasons
 Waiting for material.And electrical foremen and supervisor

Solutions
 Provide material and manpower.

Remarks