this means 0.

5 x 60 = 30 minutes
SBR - OPERATION- Full flow
0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 10.5 11 11.5 12
cycle1 SBR Anoxic Fill Aeration React Settle Decant Idle
cycle2 Anoxic Fill Aeration React Settle Decant Idle

Duration of mode, 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570 600 630 660 690 720
(in minutes)
SBR Mode Anoxic Fill Aeration React Settle Decant Idle
Sewage Inlet valve O O O O C C C C C C C C C C C C C C C C C C C C
Air inlet valve C C C C O O O O O O O C C C C C C C C C C C C C
Decanter OutletValve C C C C C C C C C C C C C C O O O O O O O O O C
WAS Line Valve C C C C C C C C C C C C C C C C C C C C C C C O
Remarks C- Closed O-Open WAS-Waste activated sludge