ITEM KTC BUS STATION LAND SCAPPING QTY UNIT RATE AMOUNT

PRELIMINARY AND GENERAL ITEMS (P & Gs)

ENGINEER'S SUPERVISION EQUIPMENT

Supply Engineer's survey instrument (Fuji yama CW


with horizontal circle Dumpy level) for use in site
topographical survey to be handed over to the client at
beginning of the project. 1 No 6,300 6,300.00

To Collection K 6,300.00

PERIMINARY AND GENERAL ITEMS - TOTAL


CARRIED TO SUMMARY 6,300.00

Manyinga Town Council 1/1


ITEM KTC BUS STATION LAND SCAPPING QTY UNIT RATE AMOUNT

EXCAVATIONS AND EARTHWORKS

Excavation

A Excavate 250 x 200mm Deep trench to receive


foundation blockwork (Kerbs) commencing at reduced
level after levelling of and compaction of the site 16 m3 40 640.00

Excavate 1000x600mm Deep trench for storm water


B drain 57 m3 5 285.00

Excavate 1000x1000mm Deep trench to receive


600mm dia concrete ring culvert- invert level as
C directed 10 m3 5 50.00

EXCAVATIONS AND EARTHWORKS - TOTAL


CARRIED TO SUMMARY 975.00

Manyinga Town Council 1/2


ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

CONCRETE WORK/RING CULVERTS

Plain concrete grade C20 as described

100mm thick concrete in Foundations trenches of


B blockwork (kerbs) 7 m3 1,000 7,000.00

100mm thick concrete in Foundations trenches of


C Storm water drain (kerbs) 8.2 m3 1,000 8,200.00

100mm thick reinforced concrete laid on loading bays


C as shown on the drawing 7.5 m3 1,000 7,500.00

100mm thick reinforced concrete laid on the walkways


C as shown on the drawing 1.8 m3 1,000 1,800.00

800X200mm Cast insitu Concrete head walls 0.6 m3 1,000 600.00

RING CULVERTS

2400mm x 600mm dia Precast concrete culverts 4 No 1,500 6,000.00

Steel fabric reinforcement to BS 4483 (1969)

D "Conforce" reference 86 or other equal and


approved fabric reinforcement with 150mm
side and end laps tied to spacer blocks @ 400mm
spacing laid on the loading bay 75 m2 14 1,050.00

CONCRETE WORK/RING CULVERTS - TOTAL


CARRIED TO SUMMARY K 32,150.00

Manyinga Town Council 1/3


ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

BLOCKWORK /KERBING

Precast concrete hollow blocks (3.5 N/mm2) as


described filled solid with plain concrete mix
20/20 bedded end pointed in cement sand mortar

500 X 200mm Bull nosed kerbs laid on cast insitu


A footing 275 m 94 25,850.00

150mm (6") Constructed for to receive concrete


B 100mm thick walkway 10 m2 140 1,400.00

BLOCKWORK/KERBING - TOTAL
CARRIED TO SUMMARY K 27,250.00

Manyinga Town Council 1/4


ITEM BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

PAVERS INSTALLATION (PAVING BRICKS)

PREAMBLE

Pavers shall strictly be installed as per client's instruction


and in accordance with the supplier's specification
Recommended by the client

SAND BLINDING

A 40mm thick sand blinding 47.1 m3 60 2,826.00

PAVERS

B Installation of THC05 pavers 1178 m2 160 188,480.00

CONCRETE SPOON DRAIN

300X100mm thick concrete spoon drain laid to fall on


C the edge of concrete blockwork (kerb) as directed 3 m3 1,000 3,000.00

PAVERS INSTALLATION - TOTAL


CARRIED TO SUMMARY K 191,480.00

Manyinga Town Council 1/5


ITEM BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

STEELWORKS

MILD STEEL POLES

Bsi Steel products manufactured in accordance with


BS4: part 1 : 1980 and to be fixed as directed

4" Mild steel poles cut as directed by the client approx


A 1.5m length spaced at 2m C/C 118 m 60 7,080.00

1" galvanised chain welded to steel poles spaced at


B 2m length 147 m 45 6,615.00

STEEL GATES

Supply and install Steel gate-Specifications refer to


drawing 4 No 1,500 6,000.00

SIGN POSTS

Supply and install Sign post (40 Km/hr) -Specifications


refer to drawing 2 No 500 1,000.00

Supply and install Sign post (Only Buses allowed


inside the station, Penalty fee of k100 shall be
charged for any vehicle found in side the station)-
Specifications refer to drawing 2 No 500 1,000.00

Supply and install Electric Sign post indicating


(Welcome to Kabompo Bus station)-Specifications
refer to drawing 2 No 3,500 7,000.00

Manyinga Town Council 1/6


STEELWORKS - TOTAL
CARRIED TO SUMMARY K 28,695.00

ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

EXTERNAL LIGHTING

External Lightings

Supply and install flood lights as directed by the client


atached to the Zesco pole located within the proximity
A of the station 3 No 800 2,400.00

EXTERNAL LIGHTING - TOTAL


CARRIED TO SUMMARY K 2,400.00

Manyinga Town Council 1/7


ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

FINISHES

PLASTERING

13mm cement and sand (1:4) plaster in one


coat with steel trowel finish on the following

13mm thick cement sand (1:3) plaster to concrete


A block wall of sides of walk way concrete paving 24 m2 25 600.00

FINISHES - TOTAL
CARRIED TO SUMMARY K 600.00

Manyinga Town Council 1/8


ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

PAINTING AND DECORATING

Painting

Prepare and apply one coat of Gloss oil paint as


described

A Black gloss paint to steel posts and 1" chain 10 m2 25 250.00

B White gloss paint to steel posts 7 m2 25 175.00

C Black gloss paint to Blockwork-Kerbs 109 m2 25 2,725.00

D White gloss paint to blockwork-kerbs 109 m2 25 2,725.00

To Collection K 5,875.00

Manyinga Town Council 1/9


PAINTING AND DECORATING -
TOTAL CARRIED TO SUMMARY K 5,875.00

ITEM BILL No.3 BUS STATION LANDSCAPPING QTY UNIT RATE AMOUNT

BUS STATION GREENS

Supply and lay 150mm thick Good quality black soil for
A the Lawns 72 m2 50 3,600.00

Supply and plant Queen palm trees as directed by the


B client 18 No 80 1,440.00

Supply and plant simber grass on well prepared black


C soil 478 m2 1 478.00

To Collection K 5,518.00

BUS STATION GREENS-


TOTAL CARRIED TO SUMMARY K 5,518.00

Manyinga Town Council 1/10


BUS STATION LANDSCAPPING
ITEM QTY UNIT RATE TOTAL

GENERAL SUMMARY

PRELIMINARY AND GENERAL ITEM K 6,300.00

EXCAVATIONS AND EARTHWORKS K 975.00

CONCRETE WORK/RING CULVERTS K 32,150.00

BLOCKWORK K 27,250.00

PAVERS INSTALLATION K 191,480.00

STEELWORKS K 28,695.00

EXTERNAL LIGHTING K 2,400.00

FINISHES K 600.00

PAINTING K 5,875.00

BUS STATION GREENERIES K 5,518.00

K 301,243.00

Manyinga Town Council 1/11


BUS STATION LANDSCAPPING
ITEM QTY UNIT RATE TOTAL

GENERAL SUMMARY

PRELIMINARY AND GENERAL ITEM K 10,000.00

EXCAVATIONS,EARTHWORKS & GRAVELLING K 20,000.00

CONCRETE WORK/RING CULVERTS K 40,000.00

BLOCKWORK K 20,000.00

PAVERS INSTALLATION K 200,000.00

STEELWORKS K 15,000.00

EXTERNAL LIGHTING K 3,000.00

PAINTING K 5,000.00

BUS STATION GREENERIES K 5,000.00

K 318,000.00

Manyinga Town Council 1/12


Manyinga Town Council 1/13
BUS STATION GRAVELLING & LAND SCAPPING
ITEM QTY UNIT RATE TOTAL

GENERAL SUMMARY

PRELIMINARY AND GENERAL ITEM K 10,000.00

EXCAVATIONS & EARTHWORKS & GRAVELLING K 20,000.00

CONCRETE WORK/RING CULVERTS K 40,000.00

BLOCKWORK K 20,000.00

PAVERS INSTALLATION K 200,000.00

STEELWORKS K 15,000.00

EXTERNAL LIGHTING K 3,000.00

PAINTING K 5,000.00

BUS STATION GREENERIES K 5,000.00

K 318,000.00