ESTIMASI JADWAL PEKERJAAN

Pekerjaan Erection Girder U Shape


NO. TASK NAME DURATION
A Gantry Crane Section - 2
1 Set Up Fix Leg (1st unit) 7 days FINISHED

2 Install Bracket 2 days FINISHED

3 Set Up Flexible Leg (1 st unit) 7 days FINISHED

4 Set Up Fix Leg (2nd unit) 5 days FINISHED

5 Set Up Flexible Leg (2nd unit) 7 days FINISHED

6 FINAL CHECK 1 days FINISHED

7 Erection U Shape Girder (Load Test) 6 days 13-Apr-17 18-Apr-17 SCHEDULLE KRITIS
(Test Load sudah dilakukan)
B Gantry Crane Section - 1
1 Set Up Fix Leg (1st unit) 8 days 31-Mar-17 FINISHED

2 Fabrication and Install Bracket 8 days 5-Apr-17 FINISHED

3 Set Up Flexible Leg (1 st unit) 8 days 13-Apr-17 FINISHED

4 Set Up Fix Leg (2nd unit) 8 days 20-Apr-17 27-Apr-17

5 Set Up Flexible Leg (2nd unit) 8 days 28-Apr-17 5-May-17

6 FINAL CHECK 1 days 7-May-17

7 Erection Girder (Load Test) 3 days 8-May-17 11-May-17


ESTIMASI JADWAL PEKERJAAN

Pekerjaan Erection Girder U Shape


NO. TASK NAME DURATION

C Louncher section - 2
1 Transport China to Jakarta 10 days 6-Apr-17 16-Apr-17 SCHEDULLE KRITIS
2 Custom Clearence 3 days 17-Apr-17 19-Apr-17 SCHEDULLE KRITIS
3 Local transport (from Custom - Site) 5 days 20-Apr-17 24-Apr-17 SCHEDULLE KRITIS
4 Set Up Louncher 18 days 25-Apr-17 12-May-17

5 Set Up Trolley 7 days 13-May-17 19-May-17

6 Start Install U Shape Using Louncher - days 20-May-17

C Louncher section - 1
1 FAT 4 days 13-Mar-17 16-Mar-17

2 Painting 7 days 17-Mar-17 23-Mar-17

3 Packing and Transport to port 7 days 24-Mar-17 30-Mar-17

4 Transport China to Jakarta 10 days 26-Apr-17 5-May-17

5 Custom Clearence 3 days 6-May-17 8-May-17

6 Local transport (from Custom - Site) 5 days 9-May-17 13-May-17

7 Set Up Louncher 18 days 14-May-17 31-May-17

8 Set Up Trolley 7 days 1-Jun-17 7-Jun-17

9 Start Install U Shape Using Louncher - days 8-Jun-17