7 Erection U Shape Girder (Load Test) 6 days 13-Apr-17 18-Apr-17 SCHEDULLE KRITIS
(Test Load sudah dilakukan)
B Gantry Crane Section - 1
1 Set Up Fix Leg (1st unit) 8 days 31-Mar-17 FINISHED
C Louncher section - 2
1 Transport China to Jakarta 10 days 6-Apr-17 16-Apr-17 SCHEDULLE KRITIS
2 Custom Clearence 3 days 17-Apr-17 19-Apr-17 SCHEDULLE KRITIS
3 Local transport (from Custom - Site) 5 days 20-Apr-17 24-Apr-17 SCHEDULLE KRITIS
4 Set Up Louncher 18 days 25-Apr-17 12-May-17
C Louncher section - 1
1 FAT 4 days 13-Mar-17 16-Mar-17