You are on page 1of 2

CHECKLIST FOR PLANNING PERMISSION(KM) APPROVAL

MAJLIS PERBANDARAN SEPANG

LAND OWNER / DEVELOPER


LIST OF DOCUMENTS COPY STATUS
1. Land tittle (Certified True Copy by Land Office) 1 copy
2. Official Search (Original – valid for 6 months ) 1 copy
3. Latest Assessment Receipt 1 copy
Letter from MPSpg Valuation Department (if no 1 copy
4.
assessment receipt)
5. Quit Rent Receipt 1 copy
Power Attorney (if any) – registered with high court & 1 copy
6.
land office
7. Consent letter (if caveated or charged to bank) 1 copy
8. M&A Company, Form 49 & Form 24 1 copy
9. Identity Card of Land owner or company director 1 copy
10. Valuation report 1 copy
Gross Development Value (GDV), Gross Development 1 copy
11.
Cost (GDC) & Gross Development Profit (GDP)
12. Processing Fee / Submission Fee 1 copy
13. Appointment Letter of Town Planner & Engineer (M&E) 1 copy
PLANNER
1. Borang A 1 copy
2. Site Plan – A1 Size (a copy of Linen) 22 copies
3. Site Plan – A3 Size 22 copies
4. Borang Fee 15 copies
5. Laporan Cadangan Pemajuan (LCP) 10 copies
6. Borang Perihal Tanah (OSC 3.0) 3 copies
7. PSP Certificate 1 copy
C&S ENGINEER
1. MASMA Report and OSD Plan 5 copies
2. R&D Plan 5 copies
3. Sewerage Engineering report & Form PDC 1, Sijil Span 1 copy
4. Water Demand Calculation & HSL 4 copies
5. Cross Section of land (hilly areas) 1 copy
6. Surat Pra – rundingan SYABAS (OSC 3.0) 1 copy
7. Cover letter from C&S address to IWK 2 copies
** all document also required in softcopy for submission online
M&E ENGINEER
1. Electric demand Calculation 1 copy
2. Manhole Cabinet Infrastructure Plan 1 copy
3. SKMM Info in Excel Format 1 copy
4. Telekom Clearance letter 1 copy
5. Telecommunication Service Provider clearance letter 1 copy
6. Surat sokongan TNB & SKMM (OSC 3.0) 1 copy
** all document also required in softcopy for submission online
LAND SURVEYOR
1. Certified Plan 1 copy
2. Detailed survey (spot level, BM, ODL) 18 copies
** all document also required in softcopy for submission online
ARCHITECT
1. Detailed floor area calculation softcopy
2. Side, front & rear elevation /section softcopy
3. Floor plan softcopy
4. Perspective softcopy

**An addition document will inform letter


1. Pre-consult for confirmation KM layout with Jabatan Perancang, MPSepang
2. Pelan Kerja Tanah & Pelan Bangunan must be submitted concurrently with
Kebenaran Merancang
3. OSC 3.0 – Clearance letter form SYABAS, TNB, Land Office & SKMM
4. Online Submission for 9 technical departments (Jab Kejuruteraan, Jab.
Bangunan, Jab. Landskap, JPBD, JAS, TNB, SYABAS, JMG & SKMM)
5. Hardcopy submission at counter OSC for 6 technical departments (OSC, JAB.
Perancang, JKR, JPS, IWK, Jab. Penilaian)