Professional Documents
Culture Documents
How To Perform Schedule in Primavera
How To Perform Schedule in Primavera
A Schedule Time Impact Analysis is a method used to determine the extent of impact from potential delay
in the construction process. This schedule analysis method involves inserting additional activities indicating
delays or changes into an updated schedule representing progress up to the point when a delay event
occurred to determine the impact of those delay activities.
Types of Delays
Excusable Delays
Non-Excusable Delays
Excusable delays occur when the affected party is allowed to claim for a time extension, compensation or both.
Meanwhile, non-excusable delays are delays that the contractor or the affected party needs to bear the responsibility.
Consider a simple project with the “As Planned Schedule”, illustrated below:
First-month update:
There is 21 days delay on Excavation due to an unforeseen site condition.
Second-month update:
There is no delay.
Third-month update:
Fourth-month update:
The contractor caused a delay in “Garage Walls” but this activity was not on the critical path.
As long as the delay is within available float there is no effect on the final completion date.
Fifth-month update:
The owner caused a 28-day delay in “Garage Doors”.
This delay only affects 7 days in the critical path. The rest of 21 days delay were absorbed by the
available float. Therefore, there will be only 7 days of “excusable compensable delay.”
Considering the types of delays experienced throughout the project, there is: