Professional Documents
Culture Documents
ENMG 632
Project Control
Lesson 1: Basic Concepts
Introduction
Project schedules are, without a doubt, considered a valuable tool only if used
properly.
Colorful bar charts and precedence networks can be no more than decoration on
the walls of the job trailer. They can also be a mere fulfillment of bid or contract
requirements.
But if well prepared and then used seriously, consistently, and intelligently
throughout the life cycle of the project, they can be an effective tool that schedulers
and the project management team can rely upon to manage projects.
The project management team then deals with this deviation, analyzes it, and
suggests solutions to bring the schedule back on track, if possible.
When discrepancies are noted , adjustments must be made to the CPM network.
This process is known as schedule updating.
• It reflects actual project information at a given data date regarding completed and in-
progress activities.
• It indicates as well any changes to future work beyond the data date (i.e. remaining
activities).
• The person who originally developed the network may have envisioned one way of
sequencing the project activities, while the field superintendent now thinks another
approach is more convenient.
• In some cases, the logic of the network must be reorganized in order to accommodate new
constraints imposed on the project, such as limited resources.
• In some other cases, the logic must be reorganized simply because some of the activity
durations exceeded expectations.
Overall, schedule updating is not needed if all duration estimates are accurate and
if the sequencing of the activities is exactly as originally scheduled.
The amount of work progress that occurred during the period may overwhelm the
scheduler.
Also, the field personnel or project manager may forget when an activity actually started
or finished if the activity occurred a month ago and was not formally documented.
Having a long reporting period may encourage procrastinators to put off corrective
measures by using the logic „„We‟ll do it later. There is plenty of time!‟‟
Typically, the frequency of updating increases at certain times, such as in the last
month or two of a project, or during a „„crunch time,‟‟ such as before a deadline.
It is worth noting that project updating is tied to payment requests so the frequency
of updating affects when requests are issued.
The scheduler discusses the new situation with the project manager and makes
sure that no more changes or adjustments are needed (in other words, he or she
obtains the project manager‟s approval for producing the reports).
The scheduler prints new reports that show the updated schedule and delivers them
to the project manager who, in turn, distributes them to the involved parties:
(different reports to different parties).
For example, if the expected finish date of the project was pushed back a few days,
the scheduler may give the reason (e.g., a predecessor activity was supposed to
finish by a certain date but did not).
The scheduler tracks the delay from the end and works his or her way back to the
activity or activities that caused the delay.
The scheduler must filter any such feedback through the project manager.
Only one point of contact (usually the project manager) should have the authority to
approve any information before it is implemented in the schedule.
Some schedule feedback received after the reports are printed may be kept till the
next update.
When the next updating cycle is due, the same steps are repeated.
ENMG 632: Project Planning, Scheduling, and Control 16
Lesson 3: Schedule Updating- Example
Example – Original Baseline Schedule
• Activities A and D are complete, actual dates: A (0, 2), D (5, 9).
• Activity B started on day 5. Remaining duration = 2 days.
• Activity C started on day 2. Some problems were encountered. Remaining
duration = 4 days.
• The duration for activity F was adjusted to 8 days.
• Activity J has been canceled.
• The duration for a new activity P is 4 days, its IPAs are E and F and its
immediately succeeding activity (ISA) is K.
5,9
B E P K
2 6 4 5
17,19 19,25 25,29 29,34
10, 10 14,22
10,14 34,37
F
C 8 22,34 N
Data Date 4 3
14,22 I
10,14 12 34,37
14,22 22,26
22,34
10,10
G M
8 4
10,18 22,28
14,22 30,34
H L
8 6
20,28 28,34
Something that has not yet been discussed in detail is the extent to which CPM can be
used as a cost-monitoring system.
But is it possible to also determine how well the project is adhering to its “cost
schedule,” or cost estimate ?
However, this figure alone could be very misleading; costs may be very low because
the project is well behind its schedule!
It is necessary to know what actual project costs are relative to expected costs while
also knowing where the project is on a time basis.
But what is the basis of that assessment? It could be based on the percent of time
that has been utilized, the percentage of the value of construction put in place, or
some other measure.
In the early to mid-1960s, the U.S. defense agencies promulgated guides and
requirements related to the integration of cost and schedule data into a single
system EARNED VALUE
While the earned value concept was originally oriented toward owners/clients, it
found its way into other systems such as contractor systems.
• Determine how much work you have done and how much you should have done
according to the plan.
• Determine how much money you have earned and how much money you have spent.
• Calculate the time (schedule) and money (budget) deviations (variances) so far.
• Analyze the causes for the major deviations and determine possible remedies.
• % Complete
• At the activity level, % Complete (a) = Actual Quantity/Total Quantity
• At the project level, % Complete (p) = ∑ %Complete (Act i) * allocated weight (Act i)
FCV= CV/%Complete
NOTE: The work is sequential and not parallel the contractor works on the first task till it is finished then
starts the next one and so on.
ENMG 632: Project Planning, Scheduling, and Control 34
Example- Solution
50,000
7,800/20,000 = 39%
17,950
%Complete * Act. Budget= 39% * 50,000= 19,500
Act. Budget * 15/40= 50,000* 15/40= 18,750
BCWP-ACWP= 19,500-17,950=1,550
BCWP-BCWS= 19,500-18,750=750
SV($)/Daily planned budget= 750/[(50,000+44,000+82,500)/40]= 0.17
BCWP/ACWP= 19,500/17,950=1.09
BCWP/BCWS= 19,500/18,750=1.04
CV/%Complete = 1,550/0.39= 3,974
SV (days)/%Complete = 0.17/0.39= 0.44
ENMG 632: Project Planning, Scheduling, and Control 35
Example- Solution (cont‟d)
CE Clay Rock
Looking at the overall budget, we find that the Mass Excavation operation is slightly over budget by $ 2,100
Looking at the overall schedule, we find that the Mass Excavation operation is behind schedule by 2 days
Looking at forecasted variances indicates that, if work continues at the same pace and in the same pattern,
the Mass Excavation operation will finish 6 days behind schedule and with a $6,434 deficit.
Expected project duration = 40+6= 46 days & EAC = BAC –FCV = 176,500 – (-6434) = $ 182,934
The schedule variance (SV) may be positive, but the schedule update may show that
the project is behind, or vice versa.
CPM-based schedule updating still gives the most accurate readings on whether the
project is ahead of or behind schedule.
To be an effective project control tool, it is important that the schedule have the
following attributes:
• Suitably versatile to allow for corrections as necessary to keep the schedule current or up
to date.
ENMG 632: Project Planning, Scheduling, and Control 44
Conclusion (cont‟d)
It is vital that main project participants have viable measures of project performance.
With front-end loading on billings, it is clear that the cash position on a project can be
very misleading.
A project could have a strong cash position in terms of costs and revenues, yet be headed
for a net loss.
The measure that is needed to establish the proper status of a project must not be
biased.
ENMG 632: Project Planning, Scheduling, and Control 45
Conclusion (cont‟d)
Earned value measurements provide the means of assessing the status of a project
without the bias introduced by many other measures commonly used in project
management.
For the owner wishing to monitor the progress of a contractor, the pitfalls of using the
schedule of values/BOQ must be recognized.
While the owner may have little recourse other than using the budgeted costs as a
measure, the schedule of values and the project schedule should be carefully
evaluated before using these as a means of evaluating performance.
An evaluation must be made of how to get the project back on schedule and what it
will cost.
Alternatives must be identified: line up a new sub, accelerate the project, allow project
to slip, etc.
ENMG 632: Project Planning, Scheduling, and Control 47
Conclusion (cont‟d)
These must be evaluated according to the economic costs and benefits as
determined by performing time–cost trade-offs with critical path method networks
and principles.
Only the shortening of the duration of one or more subsequent activities on the
critical path will permit a recovery from the project‟s delay (i.e. recovery schedules).