Security Un-Restricted
Version 5.0
FINAL
Copyright: This document is the property of Petroleum Development Oman, LLC. Neither
the whole nor any part of this document may be disclosed to others or reproduced, stored
in a retrieval system, or transmitted in any form by any means (electronic, mechanical,
reprographic recording or otherwise) without prior written consent of the owner.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
DOCUMENT Authorisation
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
The following is a brief summary of the three most recent revisions to this document. Details of all
revisions prior to these are held on file by the Document Custodian.
User Notes:
The requirements of this document are mandatory. Non-compliance shall only be authorised by CFDH
Operations Safety through STEP-OUT approval.
A controlled copy of the current version of this document is in Livelink and HSE Web page as well as HSE
for contractors page.. Before making reference to this document, it is the user's responsibility to ensure
that any hard copy, or electronic copy, is current. For assistance, contact the Document Custodian.
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of
this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in
any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written
consent of the owner.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Parent Document(s)
Doc. No. Document Title
CP 122 HSE Management System Manual
The related CMF Documents can be retrieved from the Corporate Business Control
Documentation Register CMF.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contents
1. Introduction ..........................................................................................................................1
1.1 Background............................................................................................................... 1
1.2 Purpose ..................................................................................................................... 1
1.3 Distribution............................................................................................................... 1
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
1. Introduction
1.1 Background
PDO’s Policy Document, PL-04 “Health, Safety and Environment Protection”, requires that a systematic
approach to HSE management be applied which shall require Contractors to manage HSE in line with
PDO’s HSE Policy. PDO’s Code of Practice Document, CP-122 “HSE Management System Manual”, Part 2
Chapter 3, requires that PDO Asset Managers shall ensure Contractors are made aware of PDO’s HSE
management requirements and have adequate business controls in place to meet them.
The International Organization for Standardization (ISO 14001:1996, Para. 4.4.3) requires that
procedures be established and maintained to ensure that relevant environmental requirements are
communicated to Contractors.
1.2 Purpose
Part I details the information that must be followed by Contract Holders There are 25 critical activities
related to Contract HSE management issues are described, together with any Deliverable(s) and relevant
Reference Document(s) that are obtainable on the PDO intranet system Refer to Appendix G for
assistance in accessing PDO and Shell Web Documents.
Part I describes the tasks to be executed by Contract Holders, from strategy definition to close-out of a
contract, to ensure that Contractors achieve the same (or higher) HSE standards as those required by
PDO for its own operations. The Procedure is based on a planned approach with attention being paid to
HSE issues in the early Contract Phases in order to properly address HSE through the entire contract
process.
Appendix H Contract Holder Check Sheet and RASCI
Part II is referenced, in document GU-140 “C-09 HSE Requirements”, to enable Contractors, together
with Contract Holders, to carry out PDO prescribed HSE activities in the manner and at the level required
by PDO. Of particular importance in this section is the detail given for the preparation of the Contractor’s
HSE Plan.
The input to each Contract Phase and the depth of analysis (the “Tasks”) primarily depends on the level
of HSE risk presented by the contract activities, which consequently determines the actions and input
required for the contract execution.
Whether a contract is large or small in scope and value the Tasks are all the same. Preparations for all
contracts shall utilise the same systematic process of hazard identification, assessment, control,
mitigation and recovery (Hazards and Effects Management Process - HEMP), together with the
demonstration that a system is in place to manage these hazards.
1.3 Distribution
This Procedure is a mandatory requirement for Contract Owners and Contract Holders.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
This document shall be reviewed in case of any major changes resulting from recommendation of Audit,
changes in industrial standards or changes in regulation/law as advised by regulatory authority. The
Document Custodian will update the changes as applicable, but no less frequently than every four years.
Any user of this document who encounters a mistake or confusing entry is requested to immediately
notify the Document Custodian
2.1 Scope
This Procedure applies to all contracts tendered by PDO regardless of size and value.
2.2 Description
This Procedure follows the HSE sequence of Tasks in contract management as detailed in the Contract
Holdership Certification Scheme. These activities, specific to HSE in the preparation, evaluation and
execution of a contract, are summarized in Appendix H, “Summary - Contract HSE Management
Procedure”.
The sequence of events in any contract can be described in seven Contract Phases:
The succeeding sections of Part I of PR-1171 detail the Tasks contained in these seven Contract Phases,
finalizing with the summary in Appendix H.
In some of the Tasks, form(s) must be completed for the Contract to proceed. These are detailed in each
Task where required, including any reference documents that relate to the forms. All forms necessary for
the HSE Management of a Contract are given in the various Appendixes in this document.
Each Task paragraph also contains instructions for any relevant Deliverable(s), as well as the document
number and title for any reference material pertinent to that Task.
Appendix G provides guidance for retrieving documents from the PDO electronic system. This could be
required for some of the Shell-origin documents referenced in this Procedure.
Contract Owner shall be an individual with the right level of HSE competence and authority to direct the
contracting process to protect overall PDO and Asset objectives. Where relevant, Contract Owners
should attend Tender board presentations to support Contract Holders. Contract Owner should at all
times be cognizant of HSE issues in each Contract.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holder shall have single point responsibility for the activity management of the Contract and
verification that the control mechanisms are in place (HSE Management tasks 1-25).
Contract Holder shall have single point responsibility for advising Contractor and/or Contractor Personnel
of activities, stated in each relevant Task, requiring their action(s). These activities are not necessarily
repeated in Part II of PR-1171, as they generally arise from the responsibilities and activities of the
Contract Holder as stated in each Task.
It is not expected that Contract Holders can carry out all the activities listed in the following sections.
Rather, Contract Holders shall call upon professional personnel from relevant PDO departments when
assistance with HSE issues is required i.e. HSE Team Leader or other 1Technical Authority 2 (TA2). This
does not in any way remove from Contract Holders the absolute responsibility for ensuring that advice
received and ensuing actions taken are the best possible solutions to any point in the execution of a
Contract.
Contract Holder shall complete the necessary sections of the table in SAP that is part of the Minor
Contracts documentation. If not using SAP, Contract Holder shall complete the necessary sections of the
table in Appendix A.
Contract Holder shall ensure that the Contractor is fully aware of and understands the requirements of
this table.
Contract Holder shall ensure that the Contractor is fully aware of and understands the following
statement (refer document SP-1151, General Conditions for Minor Works & Service Contracts, Article 17):
“Contractor shall operate, and shall cause all sub-contractors and Contractor Personnel to operate, with
the utmost care for the health and safety of Contractor Personnel, Company personnel and third parties,
and for the environment, and in accordance with the Company's health, safety and environmental
regulations (the HSE Specification) in force at the Effective Date, or as subsequently amended by the
Company, and the Contractor shall exercise the strongest discipline in this regard.”
Contract Holder shall ensure that there is a formal HSE monitoring plan for all contracts. Contract holder
shall ensure that the Contractor is fully aware and understands the importance of the quality and
frequency of the performance monitoring.
1
Technical Authority TA2 is a role approved by the relevant Corporate Function Department Head
and may be filled by appropriate person from HSE discipline.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
HSE Team Leader (TA2) to support the Contract holder in developing the HSE assessment.
Contract Holder shall conduct a structured, formal HSE Assessment of the Contract, using the Scope,
Schedule and Strategy documents (as well as any existing HSE information from prior documents related
to the same package of work) with a view to minimizing the HSE exposure and level of risk for the
Contract.
Contract Holder shall use suitably qualified PDO personnel in developing the HSE Assessment. These
personnel shall include Professional HSE Advisors, personnel who will participate in the work to be carried
out under the contract, or those who have prior experience in the execution of contracts.
Identify and assess the major hazards and risks associated with the contract
Hazard and Effects Management Process (HEMP), in accordance with instructions in document CP-122
Define the level of HSE risk presented by the contract
Details shall be formally recorded with future actions identified and, wherever possible, action parties
nominated.
Contract Holder shall confirm the suitability of the Contract HSE Assessment against contract scope,
schedule and strategy with the view to minimizing the HSE exposure and level of risk for the contract.
HSE Team Leader – may be consulted with regard the suitability of the risk assessment against the
contract scope.
Reference Document(s):
C4 Scope of Work
GU-140, C-09 HSE Requirements
CP-122 HSE Management System Manual Signed Contract Risk Assessment form (HSE
web Page)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Detail the requirements for Contractors to examine the proposed Scope of Works (Section C-4), determine
the hazards and consequences and define how those hazards will be managed so that risk is minimized.
Contract Holder shall use the results of the HSE Assessment to develop Document C-09 HSE
Requirements for inclusion in Tender Documents. C-09 HSE Requirements shall be used by the Contract
Holder and the successful Contractor for the duration of the Contract.
Deliverable(s): Note to Contract file, HSE Assessment co-signed by HSE TA2 authority
Contract Holders are encouraged to consult with HSE TA2 (HSE Team Leaders).
In any contract of technical complexity and/or high value, or where a Contractor wishes to be placed on
PDO’s bid list, prequalification of Contractors may be carried out. This enables PDO to ensure that the
contract requirements are met for all technical and financial issues, as well as meeting document C-09
HSE Requirements. Contractors that have been evaluated previously by company may already have an
existing HSE profile i.e. Banding score, and this information will assist the Contract Holder in the pre-
qualification process.
PDO has a policy of encouraging Local Community Contractors (LCC’s). These Contractors often have
little or no background in HSE Management, and a plan to overcome these shortcomings shall be
developed. Such a plan may require additional supervision, more explicit procedures or additional
training before an LCC can be deemed qualified to tender. Contract Holders should supervise this activity,
but not necessarily take an active part in it. However, Contract Holders shall remain responsible for
determining when to prequalify Local Community Contractors.
To ensure that HSE prequalification data obtained on each Contractor is standardized and thus fully
comparable; the use of The HSE Capability Questionnaire in T3 will apply.
The HSE evaluation of the contractors will be completed by a Company HSE Technical Authority Level 2
(TA2). The contractors will be scored and given a ‘Banding Rate’ in line with the company Procedure
PR1997. The Contract Holder MUST ensure that the banding evaluation includes the contractor office
and/or worksite visits of each contractor.
The HSE prequalification questionnaire as provided (T3) is a base case only and should be expanded (or
reduced) to meet any specific HSE management skills required as part of the C4 , Scope. The questionnaire
aims to discover the information required to assess the extent to which the management of HSE is
systematically organized by the Contractor.
Contractor line management shall complete the questionnaire. The Contractor should be advised by the
Contract Holder to cover all activities relating to a contract (including off-site support) and not just those
conducted on PDO sites.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holders MUST emphasize the need for complete answers substantiated by supporting
documentation as far as is practicable. It should be remembered that increasing amounts of detail (and
therefore information required to support it) will need to be requested as risk increases.
If extreme HSE risks are expected then the detail should extend to an HSE Case. An HSE Case is
typically described in a seven-part document. Full details can be obtained from SIEP document EP 95-
0100 (see Reference Documents below). HSE Cases shall be developed by suitably qualified HSE
Professionals, and it is not expected that the Contract Holder will be personally required to develop any
HSE Case necessary for a Contract.
Contractors should be encouraged to identify where they exceed PDO requirements and this excellence
should be recognized.
In all cases where it is deemed necessary that a Contractor shall be pre-qualified, the document
references given below must be used in addition to the HSE prequalification questionnaire included in the
T3 requirements.
Reference Documents:
CP122, Health, Safety and Environmental Management Systems
EP 95-0110, Shell Management of Contractor HSE
PR-1233, Section 4, Item 4 - Selection of Contractors, Bonds and Guarantees - Commercial
Procedures & Guidelines
GU-121, Pre-qualification of Tenderer
GU-143, Data provided by the Tenderer
PR1977 – HSE Banding of Contractors
Tender Board shall review and endorse as appropriate the HSE prequalification criteria submitted by the
Contract Holder.
Contract Holders, having taken the decision that prequalification is required, shall follow the procedures
given in Task 3.
When Contractor submissions are received, the Contract Holder will rate the submissions as described in
Appendix B. The resulting Contractor Bid List will be submitted to the Tender Board with
recommendation to approve. Contractors who are not approved shall be advised and assistance to
prequalify for future Contracts shall be given, particularly in the case of LCCs.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
The Contract Holder shall ensure that the Contractor(s) submits a draft HSE plan to detail the following:
Hazards and Effects Management Process (HEMP), based on the information provided in the
Contract Scope of Works and Document C-09 HSE Requirements.
Details provided shall fully describe the manpower including roles and responsibilities of the
individuals stated in the organisation chart, based on information advised in the C-09
Clearly indicate the policies, procedures and standards to be adopted during each phase of the
contract.
Contract Holder shall arrange a site visit if requested by Contractor(s) or deemed appropriate by the
Contract Holder. The purpose is to allow familiarization with the Contract Scope of Works and the impact
that site conditions may have on all aspects. Depending on the complexity of the scope (C4) consider a
dedicated discussion with the contractors on the HSE aspects of the contract. (HSE TA2 should be invited
to advise the contractor in HSE matters e.g. submission of their HSE plan and the impact of the PDO HSE
Procedures listed in C9.
In any contract of technical complexity and/or high value, the Contract Holder shall visit the site to
become familiar with site conditions, prior to receipt of Tender Documents.
Contract Holder shall hold a clarification meeting with Contractor(s) if requested. See Mandatory
statement below.
Mandatory
Tender clarifications shall be approached with extreme care. Clarifications shall be required where the
evaluation cannot be completed from the Tender due to either ambiguities or discrepancies.
All Tender clarifications and responses shall be issued in written form using the standard template in
EDMS and shall be forwarded by post or fax. The Unit Contract Section shall draft and issue the
clarifications to the Tenderer to ensure that the risk of soliciting a price adjustment is avoided.
Where clarification meetings are held with the individual Contractors these shall be minuted and the
minutes agreed with the Contractors. Unit Contract Section shall be present at any meeting. All
technical meetings shall commence with the statement by the Company that no price change shall result
from these technical discussions. Where technical discussions identify a price impact, the technical issues
only shall be discussed.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Meetings and discussions shall be immediately suspended if commercial/financial issues are raised.
Minutes of a clarification meeting shall be formalised by a letter to the Contractors identifying the points
of discussion and agreement. The Contractors shall confirm, by return, agreement with the contents of
the letter and identify any further points not covered.
The HSE Evaluation of the Contractors to be completed by a HSE TA2 Company Authority and using the
HSE Banding system PR1997. TA2 will deliver a banding report for each contractor.
Contract Holder shall with the assistance of a HSE TA 2 conduct a HSE Evaluation of the contractor
submission. The evaluation includes a review of their submission documents as well as a visit to their
office and/or site
Contract Holder shall communicate or meet with Contractor(s) if further clarification is needed for Tender
submission of C-09. This meeting, if required to be held following written requests for clarification, shall
establish where improvements in proposed HSE risk management will be required if contract is awarded.
Contract Holder shall consider the results of the HSE Banding process and evaluate which Contractor(s)
will require additional PDO supervision to ensure that the management of HSE risk is carried out
correctly.
Contract Holder shall determine the likelihood that levels and classes of manpower, equipment, any other
resources and policies detailed in the Contractor(s) C-09 HSE Requirements Tender submission will
enable the Contractor(s) to manage Contract risk.
HSE equipment and resources would normally include such items as:
Safety equipment, personal protective equipment (PPE)
HSE audits, induction and training, emergency response resources
medical facilities, first aid training, Medevac, health surveillance
waste disposal, promotion schemes, journey management
financial resources of the Contractor that are available for HSE management
The resources allocated for HSE provide only an indication of the Contractor's preparedness (at the time
of tender) to comply with PDO’s HSE requirements. Low HSE resource allocation could indicate that the
Contractor’s organization is at a high level of HSE implementation. Conversely, it could indicate the
Contractor does not understand PDO’s requirements. Contract Holders should be conscious of the fact
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
that thorough understanding of a Contractor’s abilities to manage HSE issues can only be obtained by
careful study of the whole of a Contractor’s HSE management system.
Contract Holder shall make a Contract award recommendation to the Tender Board, based on the
technical and commercial reports as well as the Contractor HSE assessment. The award recommendation
shall highlight any anomalies or additional qualifications accepted from the original Tender documentation
issued.
Contract Holder shall determine that the Contractor’s key HSE personnel are described in the Contractor’s
C-09 Tender submission (refer Task 9). If the list provided in the Contractor’s advisory letter (refer Task
9) are not the same as in C-09, the Contract Holder may withhold approval until the Contractor provides
satisfactory explanations and assurances that no reduction in the quality of key HSE personnel will result
from the changes. CVs shall be provided for any replacement personnel different from those described in
C-09. In all cases, PDO reserve the right to interview Contractor’s HSE personnel.
Contract Holder shall approve the Contractor’s appointed key HSE personnel when satisfied that the
quality of management of HSE risk will be maintained to PDO standards.
Contract Holder shall hold a PDO internal kick off meeting to ensure that:
Company Representative and Company Site Representative(s) are fully aware of their delegated powers
under the Contract.
All personnel involved with the Contract understand the contents of the Contract.
Key factors considered during the Tender period are explained.
Presentation and understanding of the penalties objectives and structures.
Process of instructions, administration and reporting requirements are understood.
Clarification of handover from existing Contractor (where applicable).
As a minimum, the Contract Holder, Company Representative, Company Site Representative(s), HSE
Professional(s), Company TA2 responsible for the Contract and Unit Contracts Sections shall attend the
PDO internal kick off meeting.
Contract Holder shall then conduct a kick off meeting with the Contractor immediately after Contract
award and before the execution of any work. This is essential to ensure that all contractual obligations,
including HSE, are thoroughly and mutually understood. The kick-off meeting is the first formal meeting
between Contract Holder and Contractor after the award of a contract.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
The agendas of the kick-off meetings and the HSE workshop are entirely at the discretion of the Contract
Holder. Should the Contract Holder require HSE assistance with either kick-off meeting or the HSE
workshop, an HSE professional shall be requested to assist.
During either or both of these meetings, the Contract Holder shall ensure the following minimum
objectives are covered:
Contract Holder shall obtain clear, written permission from the Contract Owner that an HSE Workshop
need not be held. In all cases the HSE TA2 shall be consulted.
Contract Holder, following the kick off meeting, the Contract holder shall schedule a HSE Workshop to
focus on all outstanding HSE issues relating to a contract. Ideally the Workshop will be held at the site
where most of the activities will take place. Notwithstanding the Contract Holder may choose to run an
initial Workshop on the coast. The Contract Holder may also choose to run one at the coast and then an
additional workshop(s) at the site(s).
The HSE Workshop is held to bring all the disciplines together from company and Contractor to
interrogate the HSE management proposal from the contractor and in particular the HEMP details
submitted as part of the technical evaluation. It is a useful mechanism to introduce the Contractor to the
details of PDO’s HSE Management Schedule. All activities will be recorded, Hazards identified and a risk
assessment completed. A major focus will be on the control measures proposed to manage the risk and
these are to be recorded and auctioned by the contractor. In addition it is an opportunity to review any
changes to the Specific Contract HSE Management Plan
In the case of Contracts and/or Contractors where all parties agree in writing that a HSE Workshop may
not be required, then:
Contract Manager shall deliver the current Contractor’s HSE Management Plan.
Contract Manager shall submit the Contractor’s HSE Management Plan to the Contract Holder for review
and approval.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holder will consult with a company HSE TA2 before approval.
Contract Holder shall approve the Contractor’s HSE Management Plan once all modifications required by
the Contract Holder (if any) have been incorporated.
This HSE Management plan shall incorporate any PDO comments arising from the kick off meeting and
the HSE Workshop, and also any mandatory PDO training. Full details for the preparation of an HSE
Management Plan are given in PR-1171, Part II, and section 2.6
Task 14 Contract Holder Develops PDO HSE Monitoring Program, review and approve
Appendix C
Contract Holder will consult with a company HSE TA2 before approval.
Contract Holder shall, throughout the period of a Contract, monitors the Contractor’s HSE performance
against the Contractor’s C-09 HSE Requirements Contract document and it’s HSE Management Plan.
Implementation of the PDO HSE monitoring program shall take place when the Contractor commences
mobilization (refer Appendix C).
Contract Holder shall prepare the PDO HSE Monitoring Program using the form contained in Appendix C.
The Program shall be submitted to the Contract Owner for review and approval.
PDO Contract personnel shall complete Contract HSE Performance Reports to detail the results of all
monitoring activities. A template and guidance note for these reports is provided in Appendix D.
Assistance with using the template is also provided in Appendix D. Contract Holder may choose to
develop a different model e.g. ‘Dashboard’ type.
Contract Owner shall approve the proposed HSE monitoring program once confirmation is obtained that
all necessary resources, competencies and capabilities of Contract Holder, Company (PDO)
Representative and Company (PDO) Site Representative to discharge their duties are in place and
appropriate for the level of risk in the Contract.
Contract Holder shall ensure that all PDO and Contractor personnel training has been completed with all
personnel involved receiving approval from HSE trainers. Training records will contain name(s) of
trainee(s), name of training course and completion grade (Satisfactory or Unsatisfactory).
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
HSE TA2 should support the audit as required by the contract holder.
Contract Holder shall conduct a pre-execution HSE audit to determine that the Contractor has achieved
the pre-execution targets stated in the Contractor’s C-09 HSE Requirements Contract document and HSE
Management Plan, and that mobilization is complete.
a. The execution of the post mobilization phase of Contract work shall not be initiated until the
requirements of the pre-execution HSE audit have been met.
b. This often occurs with long mobilization periods. It may then be necessary to specify a list of
HSE audits/checks/verifications to be completed during the mobilization period.
c. The Contract Holder must approve each of the checks before subsequent actions can be started.
For example, the Contractor cannot start transporting material from the Coast until drivers have
been qualified and vehicles have passed inspection checks.
d. In such a situation, the pre-execution HSE audit may consist of the Contract Holder determining
the satisfactory completion of driver training and vehicle inspection before the field site is audited
and fieldwork begins.
e. Mobilization payments may be attached to specific pre-execution requirements don’t let these
override HSE requirements.
f. Following any HSE audit, or any inspection in support of an audit, the resulting findings should be
discussed with the Contractor's site and office management.
g. Contractor shall respond to the Contract Holder, confirming the minutes and advising the
remediation schedule and/or confirming that all audit recommendations will be or have been
carried out.
h. The Contract Holder shall agree with the Contractor on a procedure for monitoring the
implementation of the inspection/HSE audit findings i.e. Action tracking register.
i. The Contract Holder can delegate the necessary authority to the Contractor for undertaking the
administration of these procedures if regular status reports are presented at the contract review
meetings. Contractor shall ensure that the Contract Holder documents this approval.
Deliverable(s):
Contract Holder letter to Contractor giving minutes of inspection/HSE audit findings meeting
Contractor letter to Contract Holder confirming minutes of inspection/HSE audit findings meeting
Contract Holder letter to Contractor documenting delegation of authority to undertake remediation of
inspection/HSE audit findings
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holder ensures that Contract Manager shall complete remediation of all findings resulting from
the pre-execution HSE Audit. HSE TA2 shall support the contract holder to identify all remedial steps in
place.
Deliverable(s): Remediation completed and action items “Signed off” by Contract Manager
The contract holder may acquire the support and co-signature from the Company HSE TA2 before issue.
Contract Manager shall advise, in writing, Contract Holder that all items from the pre-execution audit
requiring remediation have been completed.
Contract Manager shall issue Pre-execution Completion Report and request HSE Commencement
Certificate
Contract Holder shall issue the HSE Commencement Certificate (refer Appendix E) to Contract Manager,
subject to any exceptions noted on the HSE Certificate.
Contract Holder shall withhold issuing the HSE Commencement Certificate if any of the activities listed on
the HSE Certificate require exception that leads to unsafe operating conditions.
Mandatory
Contract Holder shall assume single point responsibility to ensure the effective execution of the Contract
by the Contractor. This shall require proper management of PDO resources and provisions involved in
the execution of the Contract (personnel, facilities, equipment, materials, expenditure forecasts, user
requirements etc), and full compliance with the Contract requirements.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holder/ will implement the Monitoring Plan. Monitor the Contractor’s performance against the
Contractor’s HSE Management Plan, using the PDO HSE Monitoring Program. In addition the Company
can use the Contractor HSE monitoring plan.
Contract Holder shall participate in all planned HSE planned audits, incident investigations, meetings and
reviews. Owner must review?
Contract Holder shall perform a Hazards and Effects Management Process (HEMP) periodically in the
execution of a Contract. In particular, revised HEMP shall be triggered by any additional requirements
that lead to an increased Scope of Works, thereby requiring a Variation in the Contract.
Revision will also allow the incorporation of any additional HSE requirements arising from the process of
Contract execution. Any additional PDO-originated HSE requirements discovered, including those arising
from “Substantial Completion”, shall be advised to the Contract and Procurement Systems and
Procedures Department (FPS) and to the Contractor.
Deliverable(s):
Note to Contract File, Variation to Contract – PDO HSE Requirements
Memo to FPS, Variation to Contract – PDO HSE Requirements
Letter to Contractor, Variation to Contract – PDO HSE Requirements
Contract Holder shall ensure that The Contract Manager will revise the HSE Management Plan as often as
required to accommodate PDO’s advice that additional HSE requirements need to be incorporated. All
unforeseen work activities shall be assessed and incorporated. Authorization for all deviations from
and/or amendments to the Contractor’s HSE Management Plan shall be sought from the Contract Holder.
Deliverable(s):
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Reference Document(s):
Letter to Contractor, Variation to Contract – PDO HSE Requirements
Contractor’s HSE Management Plan
Contract Holder shall review Contractor’s revised HSE Management Plan. Any further revisions required
by PDO shall be advised to Contractor.
Reference Document(s):
Letter to Contractor, Variation to Contract – PDO HSE Requirements
Letter to Contract Holder advising revised Contractor’s HSE Management Plan
Revised Contractor’s HSE Management Plan
Task 21 to be repeated and recorded as required
Company (PDO) Contract Holder (s) shall apply HSE penalties and defaults on the Contractor, as allowed
in the Contract, for unauthorized deviation(s) from the Contractor’s HSE Management Plan and C-09 HSE
Requirements. The Contract Manager is to be advised in writing of all Penalties and Defaults being
imposed.
HSE Penalties and Defaults shall be determined by the Contract holder. It be necessary to deliver the
default in writing.
Deliverable(s): Letter to Contractor advising HSE Penalties and Defaults may include form below,
Contract Holder shall prepare Contract HSE Performance Reports (refer Appendix D) providing feedback
to PDO Management on the overall HSE performance of the Contractor and any sub-Contractors.
Reports to be submitted as frequently as required (usually annually in a long-term contract), or as
requested, to Contract Owner and Service Group Custodian.
Reference Document(s):
PDO HSE Monitoring Program PR1171 Part I Appendix C
Contract HSE Performance Reports
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contract Holder shall ensure that the Contractor demobilizes from the site of work in accordance with all
contractual agreements including the Contractor’s HSE Management Plan.
Contract Holder shall approve the Site Restoration Certificate (refer Appendix F) and issue it to the
Contractor.
Company (PDO) Representative/Site Representative may sign the Site Restoration Certificate at the
discretion and approval of the Contract Holder.
Deliverable(s): Approved Site Restoration Certificate and copy to Corporate HSE (MSE23)
Reference Document(s):
All relevant Contract documents, including the Contractor’s HSE Management Plan.
Contract Holder shall prepare the Final Contract HSE Performance Report to be submitted to the Contract
Owner and Service Group Custodian. The report is to be finalized and submitted not later than 90 days
after demobilization.
Service Group Custodian shall review report, update the Service Group as necessary and file the report
for future use.
Note: The Contract Holder’s responsibility for management of the Contract shall end on completion of the
statement of final account
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Signed:____________________ Date:
Contractor
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contractor: Location:
PDO
Proposed by: Date:
The Default and the recorded Action/s was/were recorded in the Action Register:
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Contractor
The above Corrective Action/s has/have now been completed
Contractor
The Action/s has/have been closed in the ‘Action Tracking Register’ (for Contractor)
Cc. DDC
PDO CSR
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Embedding HSE into our Business
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Inspections
Management
Walkabouts
Audits
Emergency
Exercises / Drills
Follow-up
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Embedding HSE into our Business
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Implementation of Contract HSE Was the Contract HSE Plan followed and updated as
Plan required?
Effectiveness of HSE Were the resources provided adequate?
Organization Did all systems perform to standard?
Did the organization learn from mistakes?
Employee HSE Induction and Completed to standard and on time?
Training
Sub-Contractor HSE Did sub contractors perform to the same standard as
Management the contractor?
Were efforts made to improve when deficiencies were
noted?
HSE Personnel: Competence Were personnel competent?
Did they provide effective training and advice?
Did management respect their role?
HSE Meetings Was a cascaded hierarchy of meetings in place,
effective and attended by all personnel?
Tool Box Talks Were these conducted to standard?
Driving/Journey Management Were all vehicles to specification?
Was journey management followed and controlled?
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Embedding HSE into our Business
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Date_____________________ Date_____________________
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Embedding HSE into our Business
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Vehicle/Plant Accepted
Training Completed:
Required to attend prior to
commencing, C:
Required to attend within 2 months,
M:
Recommended only, R:
Pre-execution Audit Completed
Notes:
On behalf of the Contractor I confirm that the activities stated above have been
carried out and we are capable of performing the work in a healthy, safe, and
environmentally responsible manner.
Name Date Responsibility Signature
Contract
Manager
We hereby agree that the HSE status of this Contract allows work to proceed, subject
to the above exceptions.
Name Ref. Ind. Responsibility Signature
Contract Holder
Representative*
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Embedding HSE into our Business
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
These documents are referenced in PR-1171 as EP 95-0100 etc, and are accessed as follows:
http://sww1.pdo.shell.om/dept/cd/csm/blocks/links/links.html
Choose Shell International Exploration and Production (SIEP) EP search Page
Type the exact document number as given in the Reference Documents in the various PR-1171
HSE Documents
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
Appendix H – Contract HSE Activity Chart & RASCI (Responsibility, Accountability, Support, Consult, Inform)
CONTRACT NO:
Site Rep
Contract Contract Technical Tender Remarks/
(CSR) Contractor
Owner Holder Authority Board Ref to other PR 1171
Contract Manager Date
(CO) (CH) (2) HSE (TB) documents
Task Task definition User Completed
PLANNING
1 Conduct HSE Risk Assessment R C
2 Prepare C-09 HSE Requirement R C
Development of HSE Prequalification A R
3 Criteria
Tender Board- Endorse HSE
R C
4 Prequalification Criteria
R A
5 Prequalify Contractors
TENDER PERIOD
Contractor Submission: Document C-09 R C I
6 HSE Requirement
7 Arrange Site Visit R C I
8 Hold Clarification Meeting R C I
EVALUATION AND CONTRACT AWARD
Review Contractor Submission- R C
9 Document C-09 HSE Requirements BANDING PR1997
CH Approve Contractor Key HSE
R C
10 Personnel
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 3.9
Petroleum Development Oman LLC Effective: March 2012
MOBILIZATION
Hold HSE Kick Off Meeting PDO R C S
11 Internal and External with Contractor
R C S
12 Hold HSE Workshop
Contract Holder Approve HSE R C S
13 Management Plan
Develop PDO HSE Monitoring Program, A R C S
14 review and approve
Assure The arrangements for PDO and
R S
15 Contractor HSE Training
16 Pre-execution HSE Audit of Contractor R C S
Complete Pre-execution HSE Audit
R S
17 Items R
18 Issue HSE Commencement Certificate R C S R
EXECUTION
Monitor Contractors Implementation of
S
19 HSE Management Plan R C
20 Additional HSE Requirements R C S
Contractor - Revise/Review & S To be repeated as often
21 Implement the HSE Management Plan R C as required
22 Consider HSE Penalties and Defaults R C S
23 Contract HSE Performance Reports R C S
DEMOBILIZATION
24 Site Restoration -Certificate Approval C
CLOSE OUT
Final Contract HSE Performance
25 Report A R C S
Overall Complete
Date:
Name:
Sign: A R