LNG Tank Ningbo - China

for
CNOOC Zhejiang Ningbo LNF Co. Ltd., China

PROJECT DATA:

 Location: Beilun, Ningbo, Zhejiang Province China


 Owner: CNOOC Ningbo LNG Co., Ltd.
 Contractor: TGE/CHENGDA
 Year of Completion: 2012
 TGE Project Number: 5059 Zhejiang LNG Receiving Terminal Project

PROJECT DESCRIPTION:

 LNG Storage Tank:

The scope of work defines three 160,000m3 full containment LNG storage tanks. The primary standard
of LNG Tanks shall be EN14620-2006 for design, manufacture, inspection and testing, drying, purging
and cool down. The main features of the LNG storage tanks are listed as below:
- Piling and Foundation
- A concrete outer tank consisting of a reinforced concrete base slab, a post tensioned concrete
wall connected rigidly to the slab, and a reinforced concrete roof, rigidly connected to the wall.
The LNG storage tanks shall be elevated base slab foundation.
- A carbon steel liner covering all inside surfaces of the concrete outer tank and acting as a va-
pour barrier. The roof liner is the formwork for the roof concrete and may act as a composite
structure with the reinforced concrete roof.
- A 9% nickel steel open top inner tank
- A thermal protection system (TPS) acting as Thermal Corner Protection System, it includes insula-
tion as Foam Glass Blocks, covered by a 9% nickel steel shell . The top of the TPS shall be anc-
hored into the concrete wall

TGE Gas Engineering GmbH Tel: +49 (0) 228 60448 0


Mildred-Scheel-Str. 1 Fax: +49 (0) 228 60448 888
53175 Bonn, Germany tge-gas.com / info@tge-gas.com
- A suspended deck, supported by hanger from the roof. The suspended deck shall be made of
aluminum alloy, stainless steel, or 9% nickel steel
- A tank insulation system including insulation under the inner tank bottom, insulation between the
steel inner tank shell and the concrete outer tank, insulation on the suspended deck and insula-
tion of the roof penetrations and internal piping.
- A set of nozzles and relevant internal piping
- Internal access and structural steel works
- External access and structural steel works including roof platform
- External piping on the tank roof and wall with its supports
- Tank instrumentation for level, pressure and temperature recording, leak detection, and cool-
down control, and any other tank instrumentation specified.
- Safety valves for pressure and vacuum protection, with interlocked isolating valves and tail pipes.
- A settlement monitoring system for the outer tank
- Electrical equipment
- Submerged pumps
- A lifting device for submerged pump handling
- A fire detection system
- A fire fighting system

TGE SCOPE:

EPC turn-key contractor:


- Authority Engineering
- Basic Engineering
- Procurement Off Shore
- Detail Engineering
- Construction
- Installation
- Mechanical completion
- Commissioning
- Start-up
- Performance Guarantee testing
- Technical support during run test

Main Dimensions and Quantity Parameters:


 Inner Diameter Tank: 82.00 m
 Tank Top Level at Centre Point: 50.50 m
 Bottom Slab Thickness: 1.00 m
 Concrete Wall Thickness: 0.70 m
 Diameter Piles: 1.50 m
 Concrete Volume Piles: 105.000 m3
 Concrete Volume Tanks: 70.000 m3
 9% Nickel Steel: 6.000 tons