PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN

NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATIN TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1863 1 1 1 30.0 2
2 1771 1 1 1 30.0 2
TOTAL 0 2 2 2 60 4

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 05/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

10
11

G
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATIN TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1773 1 1 1 30.0 2
2 1772 1 1 1 30.0 2
3 1765 1 1 1 30.0 2
4 1767 1 1 1 30.0 2
5 1766 1 1 1 30.0 2
6 1759 1 1 1 30.0 2
7 1761 1 1 1 30.0 2
8 1760 1 1 1 30.0 2
9 1753 1 1 1 30.0 2
10 1755 1 1 1 30.0 2
11 1754 1 1 1 30.0 2
12 1747 1 1 1 30.0 2
13 1749 1 1 1 30.0 2
14 1748 1 1 1 30.0 2
TOTAL 0 14 14 14 420 28

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 06/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

8
11
10
12
13
12
12
13
8
12
8
8
12
12
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATIN TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1864 1 1 1 30.0 2
2 1866 1 1 1 30.0 2
3 1865 1 1 1 30.0 2
4 1774 1 1 1 30.0 2
5 1776 1 1 1 30.0 2
6 1775 1 1 1 30.0 2
7 1768 1 1 1 30.0 2
TOTAL 0 7 7 7 210 14

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 07/04/2018
: Team 1

FINAL SET
(per 10blows) REMARKS
(mm)

14
12
12
12
12
14
14
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATIN TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1741 1 1 1 30.0 2
2 1743 1 1 1 30.0 2
3 1742 1 1 1 30.0 2
4 1735 1 1 1 30.0 2
5 1737 1 1 1 30.0 2
6 1736 1 1 1 30.0 2
7 1729 1 1 1 30.0 2
8 1731 1 1 1 30.0 2
9 1730 1 1 1 30.0 2
10 1723 1 1 1 30.0 2
11 1725 1 1 1 30.0 2
12 1724 1 1 1 30.0 2
13 1717 1 1 1 30.0 2
14 1719 1 1 1 30.0 2
15 1718 1 1 1 30.0 2
TOTAL 0 15 15 15 450 30

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 07/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

11
8
9
8
10
12
12
12
14
12
11
12
10
8
12
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATIN TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1770 1 1 1 26.1 2
2 1769 1 1 1 30.0 2
3 1762 1 1 1 30.0 2
4 1764 1 1 1 30.0 2
5 1763 1 1 1 30.0 2
6 1756 1 1 1 30.0 2
7 1758 1 1 1 30.0 2
8 1757 1 1 1 30.0 2
9 1750 1 1 1 30.0 2
10 1752 1 1 1 30.0 2
11 1751 1 1 1 30.0 2
12 1744 1 1 1 30.0 2
13 1746 1 1 1 30.0 2
14 1745 1 1 1 30.0 2
TOTAL 0 14 14 14 416.1 28

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 09/04/2018
: Team 1

FINAL SET
(per 10blows) REMARKS
(mm)

12
12
12
10
10
10
10
10
10
10
12
10
12
12
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1711 1 1 1 30.0 2
2 1713 1 1 1 30.0 2
3 1712 1 1 1 30.0 2
4 1705 1 1 1 30.0 2
5 1707 1 1 1 30.0 2
6 1706 1 1 1 30.0 2
7 1699 1 1 1 30.0 2
8 1701 1 1 1 30.0 2
9 1700 1 1 1 30.0 2
10 1693 1 1 1 30.0 2
11 1695 1 1 1 30.0 2
12 1694 1 1 1 30.0 2
13 1687 1 1 1 30.0 2
14 1689 1 1 1 30.0 2
15 1688 1 1 1 30.0 2
TOTAL 0 15 15 15 450 30

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 09/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

16
10
8
10
10
10
12
10
10
12
8
12
14
12
14
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1738 1 1 1 30.0 2
2 1740 1 1 1 30.0 2
3 1739 1 1 1 30.0 2
4 1732 1 1 1 30.0 2
5 1734 1 1 1 30.0 2
6 1733 1 1 1 30.0 2
7 1726 1 1 1 30.0 2
8 1728 1 1 1 30.0 2
9 1727 1 1 1 30.0 2
10 1720 1 1 1 30.0 2
11 1722 1 1 1 30.0 2
12 1721 1 1 1 30.0 2
13 1714 1 1 1 30.0 2
14 1716 1 1 1 30.0 2
15 1715 1 1 1 30.0 2
TOTAL 0 15 15 15 450 30

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 10/04/2018
: Team 1

FINAL SET
(per 10blows) REMARKS
(mm)

12
12
12
10
10
10
10
10
10
14
10
10
10
8
10
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1681 1 1 1 30.0 2
2 1683 1 1 1 30.0 2
3 1682 1 1 1 30.0 2
4 1675 1 1 1 30.0 2
5 1677 1 1 1 30.0 2
6 1676 1 1 1 30.0 2
7 1669 1 1 1 30.0 2
8 1663 1 1 1 30.0 2
9 1670 1 1 1 30.0 2
10 1664 1 1 1 30.0 2
11 1657 1 1 1 30.0 2
12 1671 1 1 1 30.0 2
13 1685 1 1 1 30.0 2
14 1684 1 1 1 30.0 2
15 1679 1 1 1 30.0 2
TOTAL 0 15 15 15 450 30

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 10/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

10
10
10
12
12
14
14
14
16
12
10
12
12
8
12
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1708 1 1 1 30.0 2
2 1710 1 1 1 30.0 2
3 1709 1 1 1 30.0 2
4 1702 1 1 1 30.0 2
5 1696 1 1 1 30.0 2
6 1690 1 1 1 30.0 2
7 1703 1 1 1 30.0 2
8 1691 1 1 1 30.0 2
9 1697 1 1 1 30.0 2
10 1704 1 1 1 30.0 2
11 1698 1 1 1 30.0 2
12 1692 1 1 1 30.0 2
13 1686 1 1 1 30.0 2
TOTAL 0 13 13 13 390 26

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 11/04/2018
: Team 1

FINAL SET
(per 10blows) REMARKS
(mm)

10
10
10
10
10
12
10
10
10
10
10
10
10
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1678 1 1 1 30.0 2
2 1673 1 1 1 30.0 2
3 1672 1 1 1 30.0 2
4 1665 1 1 1 30.0 2
5 1668 1 1 1 30.0 2
6 1662 1 1 1 30.0 2
7 1667 1 1 1 30.0 2
8 1661 1 1 1 30.0 2
9 1666 1 1 1 30.0 2
10 1660 1 1 1 30.0 2
11 1658 1 1 1 30.0 2
12 1659 1 1 1 30.0 2
13 1680 1 1 1 30.0 2
14 1674 1 1 1 30.0 2
TOTAL 0 14 14 14 420 28

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 11/04/2018
: Team 3

FINAL SET
(per 10blows) REMARKS
(mm)

12
12
16
16
12
16
10
4
10
14
16
14
12
10
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1653 1 0 2 1 30.0 3
2 1652 1 0 2 1 30.0 3
3 1651 1 0 2 1 30.0 3
4 1647 1 0 2 1 30.0 3
5 1645 1 0 2 1 30.0 3
TOTAL 5 0 10 5 150 15

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 22/06/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

4
6
10
6
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1646 1 0 2 1 30.0 3
2 1641 1 0 2 1 30.0 3
3 1639 1 0 2 1 30.0 3
4 1640 1 0 2 1 30.0 3
TOTAL 4 0 8 4 120 12

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 23/06/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

10
5
6
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1483 1 0 2 1 30.0 3
2 1495 1 0 2 1 30.0 3
3 1489 1 0 2 1 30.0 3
4 1484 1 0 2 1 30.0 3
5 1496 1 0 2 1 30.0 3
6 1490 1 0 0 2 30.0 2
7 1485 1 0 0 2 30.0 2
8 1497 1 0 0 2 30.0 2
9 1491 1 0 0 2 30.0 2
10 1486 1 0 0 2 30.0 2
TOTAL 10 0 10 15 300 25

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 25/06/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

8
10
12
8
6
10
8
8
10
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1635 1 0 2 1 30.0 3
2 1633 1 0 2 1 30.0 3
3 1634 1 0 2 1 30.0 3
4 1629 1 0 2 1 30.0 3
5 1627 1 0 2 1 30.0 3
TOTAL 5 0 10 5 150 15

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 25/06/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

8
10
8
7
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1498 1 0 0 2 30.0 2
2 1492 1 0 0 2 30.0 2
3 1487 1 0 0 2 30.0 2
4 1499 1 0 0 2 30.0 2
5 1493 1 0 0 2 30.0 2
6 1488 1 0 0 2 30.0 2
7 1500 1 0 0 2 30.0 2
8 1494 1 0 0 2 30.0 2
9 1501 1 0 0 2 30.0 2
TOTAL 9 0 0 18 270 18

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 26/06/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

8
8
8
12
10
8
8
6
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1513 1 0 0 2 30.0 2
2 1507 1 0 0 2 30.0 2
3 1502 1 0 0 2 30.0 2
TOTAL 3 0 0 6 90 6

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 27/06/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
8
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1628 1 0 2 1 30.0 3
2 1621 1 0 2 1 30.0 3
3 1623 1 0 2 1 30.0 3
4 1622 1 0 2 1 30.0 3
5 1615 1 0 2 1 30.0 3
6 1617 1 0 2 1 30.0 3
7 1616 1 0 2 1 30.0 3
8 1609 1 0 2 1 30.0 3
TOTAL 8 0 16 8 240 24

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 02/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

8
4
12
10
7
8
6
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1514 1 0 0 2 30.0 2
2 1508 1 0 0 2 30.0 2
3 1503 1 0 0 2 30.0 2
4 1515 1 0 0 2 30.0 2
5 1509 1 0 0 2 30.0 2
TOTAL 5 0 0 10 150 10

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 03/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

8
10
8
8
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1504 1 0 0 2 30.0 2
2 1516 1 0 0 2 30.0 2
3 1510 1 0 0 2 30.0 2
4 1505 1 0 0 2 30.0 2
5 1517 1 0 0 2 30.0 2
6 1511 1 0 0 2 30.0 2
7 1506 1 0 0 2 30.0 2
8 1518 1 0 0 2 30.0 2
9 1512 1 0 0 2 30.0 2
TOTAL 9 0 0 18 270 18

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 04/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

10
12
8
8
8
8
12
8
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1611 1 0 2 1 30.0 3
2 1610 1 0 2 1 30.0 3
3 1605 1 0 2 1 30.0 3
4 1603 1 0 2 1 30.0 3
5 1604 1 0 2 1 30.0 3
6 1599 1 0 2 1 30.0 3
TOTAL 6 0 12 6 180 18

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 04/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

8
7
7
8
6
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1519 1 0 0 2 30.0 2
2 1531 1 0 2 1 30.0 3
3 1525 1 0 2 1 30.0 3
4 1520 1 0 2 1 30.0 3
5 1532 1 0 0 2 30.0 2
6 1526 1 0 0 2 30.0 2
7 1521 1 0 0 2 30.0 2
8 1533 1 0 0 2 30.0 2
9 1527 1 0 0 2 30.0 2
10 1522 1 0 0 2 30.0 2
TOTAL 10 0 6 17 300 23

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 05/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
6
8
6
6
8
8
6
8
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1597 1 0 2 1 30.0 3
2 1593 1 0 2 1 30.0 3
3 1591 1 0 2 1 30.0 3
4 1592 1 0 2 1 30.0 3
5 1587 1 0 2 1 30.0 3
6 1585 1 0 2 1 30.0 3
7 1586 1 0 2 1 30.0 3
8 1581 1 0 2 1 30.0 3
9 1581 1 0 2 1 30.0 3
10 1579 1 0 2 1 30.0 3
11 1580 1 0 2 1 30.0 3
TOTAL 11 0 22 11 330 33

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 05/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

6
7
8
4
4
6
8
6
3
7
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1534 1 0 0 2 30.0 2
2 1528 1 0 0 2 30.0 2
3 1523 1 0 0 2 30.0 2
4 1535 1 0 0 2 30.0 2
5 1529 1 0 0 2 30.0 2
6 1524 1 0 2 1 30.0 3
7 1536 1 0 2 1 30.0 3
8 1530 1 0 2 1 30.0 3
TOTAL 8 0 6 13 240 19

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 06/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

8
8
10
6
4
6
6
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1537 1 0 2 1 30.0 3
2 1549 1 0 2 1 30.0 3
3 1543 1 0 2 1 30.0 3
4 1538 1 0 2 1 30.0 3
5 1550 1 0 2 1 30.0 3
6 1544 1 0 2 1 30.0 3
7 1539 1 0 2 1 30.0 3
8 1551 1 0 2 1 30.0 3
9 1545 1 0 2 1 30.0 3
10 1540 1 0 2 1 30.0 3
11 1552 1 0 2 1 30.0 3
12 1546 1 0 2 1 30.0 3
13 1541 1 0 2 1 30.0 3
TOTAL 13 0 26 13 390 39

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 09/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
10
8
6
8
10
8
6
6
8
8
6
12
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1654 1 0 2 1 30.0 3
2 1655 1 0 2 1 30.0 3
3 1656 1 0 2 1 30.0 3
4 1650 1 0 2 1 30.0 3
5 1648 1 0 2 1 30.0 3
6 1649 1 0 2 1 30.0 3
7 1644 1 0 2 1 30.0 3
8 1642 1 0 2 1 30.0 3
9 1643 1 0 2 1 30.0 3
TOTAL 9 0 18 9 270 27

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 09/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

3
4
8
6
4
6
10
9
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1553 1 0 2 1 30.0 3
2 1547 1 0 2 1 30.0 3
3 1542 1 0 2 1 30.0 3
4 1554 1 0 2 1 30.0 3
5 1548 1 0 2 1 30.0 3
6 1555 1 0 2 1 30.0 3
7 1556 1 0 2 1 30.0 3
8 1557 1 0 2 1 30.0 3
9 1558 1 0 2 1 30.0 3
10 1559 1 0 2 1 30.0 3
11 1560 1 0 2 1 30.0 3
TOTAL 11 0 22 11 330 33

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 11/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
6
8
6
8
8
8
8
6
8
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1561 1 0 2 1 30.0 3
2 1573 1 0 2 1 30.0 3
3 1567 1 0 2 1 30.0 3
4 1562 1 0 2 1 30.0 3
5 1574 1 0 2 1 30.0 3
6 1568 1 0 2 1 30.0 3
TOTAL 6 0 12 6 180 18

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 12/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
6
6
6
6
8
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE PILE
DRIVEN
NO PILE REF. Starter Extension JOINT
LENGTH (nos.)
(m)
6m 12 m 6m 12 m
1 1638 1 0 2 1 30.0 3
2 1636 1 0 2 1 30.0 3
3 1637 1 0 2 1 30.0 3
4 1632 1 0 2 1 30.0 3
5 1630 1 0 2 1 30.0 3
6 1631 1 0 2 1 30.0 3
7 1626 1 0 2 1 30.0 3
8 1624 1 0 2 1 30.0 3
9 1625 1 0 2 1 30.0 3
10 1620 1 0 2 1 30.0 3
11 1618 1 0 2 1 30.0 3
12 1619 1 0 2 1 30.0 3
TOTAL 12 0 24 12 360 36

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 12/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

6
6
6
8
2
4
7
7
6
12
8
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE
DRIVEN
NO PILE REF. Starter Extension 10
LENGTH
(m)
6m 12 m 6m 12 m
1 1614 1 0 2 1 30.0 3
2 1612 1 0 2 1 30.0 3
TOTAL 2 0 4 2 60 6

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 13/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

6
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE
DRIVEN
NO PILE REF. Starter Extension 10
LENGTH
(m)
6m 12 m 6m 12 m
1 1578 1 0 2 1 30.0 3
2 1572 1 0 2 1 30.0 3
3 1566 1 0 2 1 30.0 3
TOTAL 3 0 6 3 90 9

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 14/07/2018
: Team 4

FINAL SET
(per 10blows) REMARKS
(mm)

6
10
6
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE
DRIVEN
NO PILE REF. Starter Extension 10
LENGTH
(m)
6m 12 m 6m 12 m
1 1613 1 0 2 1 30.0 3
2 1608 1 0 2 1 30.0 3
3 1606 1 0 2 1 30.0 3
4 1607 1 0 2 1 30.0 3
5 1602 1 0 2 1 30.0 3
6 1600 1 0 2 1 30.0 3
7 1601 1 0 2 1 30.0 3
8 1594 1 0 2 1 30.0 3
TOTAL 8 0 16 8 240 24

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 15/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

8
7
9
8
7
10
10
5
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGAN
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

LOCATION : FLOCCULATION TANK DATE


PILE SIZE : 250mm x 250mm Square Pile TEAM

PILE INSTALLATION (nos)


PILE
DRIVEN
NO PILE REF. Starter Extension 10
LENGTH
(m)
6m 12 m 6m 12 m
1 1596 1 0 2 1 30.0 3
2 1595 1 0 2 1 30.0 3
3 1588 1 0 2 1 30.0 3
4 1590 1 0 2 1 30.0 3
5 1589 1 0 0 2 30.0 2
6 1582 1 0 2 1 30.0 3
7 1584 1 0 2 1 30.0 3
8 1583 1 0 2 1 30.0 3
TOTAL 8 0 14 9 240 23

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
N LOJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

PILING WORK RECORD (DAILY)

: 23/07/2018
: Team 5

FINAL SET
(per 10blows) REMARKS
(mm)

11
6
3
4
3
6
8
5
Verified by :

……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.
PROJECT : PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGANG
NO. KONTRAK : 2081/15/6

SUMMARY PILING WORK RECORD

LOCATION : FLOCCULATI0N TANK DATE


PILE SIZE : 250mm x 250mm SQUARE PILE TEAM

PILE INSTALLATION (nos)


PILE DRIVEN PILE JOINT
DATE Starter Extension LENGTH (m) (nos.)
6m 12 m 6m 12 m
05/04/2018 0 2 2 2 60 4
06/04/2018 0 14 14 14 420 28
07/04/2018 0 22 22 22 660 44
09/04/2018 0 29 29 29 866 58
10/04/2018 0 30 30 30 900 60
11/04/2018 0 27 27 27 810 54
0 124 124 124 3,716.10 248

Prepare by : Verified by :

…………………………………………… ……………………………………
CIPTA WAWASAN MAJU ENGINEERING SDN. BHD. JURUTERA PERUNDING
OJI RAWATAN AIR LABOHAN DAGANG, DAERAH KUALA LANGAT
NO. KONTRAK : 2081/15/6

MMARY PILING WORK RECORD

: 05/04/2018 -
: Team 3

REMARKS

Team 3
Team 3
Team 1, 3
Team 1, 3
Team 1, 3
Team 1, 3
……………………………………………
JURUTERA PERUNDING ZAABA SDN. BHD.