PEMBANGUNAN PLTA KERINCI MERANGIN H

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Senin, 15 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:15 0:15 Ventillating
2 7:15 9:50 2:35 Mucking Out (4 DT Howo)
3 9:50 10:20 0:30 Scalling and Cleaning
4 10:20 10:50 0:30 Survey and Marking
5 10:50 13:10 2:20 Drilling Face (95 Hole, 3m Depth)
6 13:10 13:50 0:40 Charging and Blasting
7 13:50 14:00 0:10 Ventillating
8 14:00 16:30 2:30 Mucking Out (4 DT Howo)
9 16:30 17:00 0:30 Scalling and Cleaning
10 17:00 17:45 0:45 Survey and Marking
11 22:00 0:30 2:30 Drilling Face (95 Hole, 3m Depth)
12 0:30 1:05 0:35 Charging and Blasting
13 1:05 1:20 0:15 Ventillating
14 1:20 4:00 2:40 Mucking Out (4 DT Howo)
15 4:00 4:30 0:30 Scalling and Cleaning
16 4:30 5:10 0:40 Survey and Marking
17 5:10 7:00 1:50 Drilling Face (95 Hole, 3m Depth)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- 22:00 - 00:30 WIB Standby Prepare Drilling
-
-
Issue
- Install Ventilation
-

Prepared by

Satria Ronaldo
UNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

AILY REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
aan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5579.995 5576.883 3.112 3.112

5576.883 5574.160 2.723 5.835

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HID

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Selasa, 16 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Jam)
1 7:00 8:00 1:00 Continues Drilling Face (95 Hole, 3m Depth)
2 8:00 8:30 0:30 Charging and Blasting
3 8:30 8:45 0:15 Ventillating
4 8:45 11:20 2:35 Mucking Out (4 DT Howo)
5 11:20 11:50 0:30 Scalling and Cleaning
6 11:50 12:30 0:40 Survey and Marking
7 12:30 14:00 1:30 Prepare Safety Shotcrete
8 14:00 1:30 11:30 Safety Shocrete 50 m³
9 1:30 4:00 2:30 Drilling Face (95 Hole, 3m Depth)
10 4:00 4:35 0:35 Charging and Blasting
11 4:35 4:50 0:15 Ventillating
12 4:50 7:00 2:10 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 05:00 WIB


Shift Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5574.160 5571.733 2.427 8.262

5571.733 5568.771 2.962 11.224

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANG

TUNNEL WORK AD

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Rabu, 17 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:30 0:30 Scalling and Cleaning
2 7:30 8:10 0:40 Survey and Marking
3 8:10 10:15 2:05 Drilling Face (95 Hole, 3m Depth)
4 10:15 10:50 0:35 Charging and Blasting
5 10:50 11:00 0:10 Ventillating
6 11:00 13:30 2:30 Mucking Out (4 DT Howo)
7 13:30 14:10 0:40 Scalling and Cleaning
8 14:10 15:00 0:50 Survey and Marking
9 15:00 17:00 2:00 Drilling Face (95 Hole, 3m Depth)
10 17:00 17:35 0:35 Charging and Blasting
11 17:35 17:50 0:15 Ventillating
12 17:50 20:15 2:25 Mucking Out (4 DT Howo)
13 20:15 20:50 0:35 Scalling and Cleaning
14 20:50 21:30 0:40 Survey and Marking
15 21:30 0:00 2:30 Drilling Face (95 Hole, 3m Depth)
16 0:00 0:25 0:25 Charging and Blasting
17 0:25 0:40 0:15 Ventillating
18 0:40 3:00 2:20 Mucking Out (4 DT Howo)
19 3:00 3:30 0:30 Scalling and Cleaning
20 3:30 4:10 0:40 Survey and Marking
21 4:10 7:00 2:50 Drilling Face (95 Hole, 3m Depth)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
- Install Ventilation

Prepared by

Satria Ronaldo
GUNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

Y REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
rjaan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5568.771 5566.170 2.601 13.825

5566.170 5563.191 2.979 16.804

5563.191 5560.286 2.905 19.709

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Kamis, 18 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:20 0:20 Charging and Blasting
2 7:20 7:30 0:10 Ventillating
3 7:30 10:30 3:00 Mucking Out (4 DT Howo)
4 10:30 11:30 1:00 Scalling and Cleaning
5 11:30 12:10 0:40 Survey and Marking
6 14:45 17:15 2:30 Drilling Face (95 Hole, 3m Depth)
7 17:15 17:50 0:35 Charging and Blasting
8 17:50 18:00 0:10 Ventillating
9 18:00 20:20 2:20 Mucking Out (4 DT Howo)
10 20:20 20:40 0:20 Scalling and Cleaning
11 20:40 21:30 0:50 Survey and Marking
12 21:30 0:00 2:30 Drilling Face (95 Hole, 3m Depth)
13 0:00 0:30 0:30 Charging and Blasting
14 0:30 0:45 0:15 Ventillating
15 0:45 3:00 2:15 Mucking Out (4 DT Howo)
16 3:00 3:30 0:30 Scalling and Cleaning
17 3:30 4:10 0:40 Survey and Marking
18 4:10 7:00 2:50 Drilling Face (95 Hole, 3m Depth)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- 12:10 - 14:45 WIB Standby Drilling Down Stream
-
-
Issue
-
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)
5560.286 5558.103 2.183 21.892

5558.103 5555.095 3.008 24.9

5555.095 5552.72 2.375 27.275

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Jum'at, 19 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:15 0:15 Continues Drilling Face (95 Hole, 3m Depth)
2 7:15 7:55 0:40 Charging and Blasting
3 7:55 8:10 0:15 Ventillating
4 8:10 10:30 2:20 Mucking Out (4 DT Howo)
5 10:30 11:10 0:40 Scalling and Cleaning
6 11:10 12:00 0:50 Survey and Marking
7 12:00 14:00 2:00 Drilling Face (95 Hole, 3m Depth)
8 14:00 14:30 0:30 Charging and Blasting
9 14:30 14:45 0:15 Ventillating
10 14:45 17:10 2:25 Mucking Out (4 DT Howo)
11 17:10 17:40 0:30 Scalling and Cleaning
12 17:40 18:20 0:40 Survey and Marking
13 22:15 0:50 2:35 Drilling Face (95 Hole, 3m Depth)
14 0:50 1:20 0:30 Charging and Blasting
15 1:20 1:35 0:15 Ventillating
16 1:35 3:45 2:10 Mucking Out (4 DT Howo)
17 3:45 4:20 0:35 Scalling and Cleaning
18 4:20 5:00 0:40 Survey and Marking
19 5:00 7:00 2:00 Drilling Face (95 Hole, 3m Depth)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- 18:20 - 22:15 WIB Standby Drilling Down Stream
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5552.72 5549.599 3.121 30.396

5549.599 5546.721 2.878 33.274

5546.721 5544.416 2.305 35.579

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Sabtu, 20 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:40 0:40 Continues Drilling Face (95 Hole, 3m Depth)
2 7:40 8:15 0:35 Charging and Blasting
3 8:15 8:30 0:15 Ventillating
4 8:30 10:45 2:15 Mucking Out (4 DT Howo)
5 10:45 11:15 0:30 Scalling and Cleaning
6 11:15 12:00 0:45 Survey and Marking
7 12:00 14:00 2:00 Drilling Face (95 Hole, 3m Depth)
8 14:00 14:25 0:25 Charging and Blasting
9 14:25 14:40 0:15 Ventillating
10 14:40 16:40 2:00 Mucking Out (4 DT Howo)
11 16:40 17:10 0:30 Scalling and Cleaning
12 17:10 17:45 0:35 Survey and Marking
13 17:45 20:10 2:25 Drilling Face (95 Hole, 3m Depth)
14 20:10 20:45 0:35 Charging and Blasting
15 20:45 21:00 0:15 Ventillating
16 21:00 23:15 2:15 Mucking Out (4 DT Howo)
17 23:15 23:50 0:35 Scalling and Cleaning
18 23:50 0:30 0:40 Survey and Marking
19 3:20 5:45 2:25 Drilling Face (95 Hole, 3m Depth)
20 5:45 6:15 0:30 Charging and Blasting
21 6:15 6:30 0:15 Ventillating
22 6:30 7:00 0:30 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- 00:30 - 03:20 WIB Standby Drilling Down Stream
-
Issue
- Install Ventilation
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5544.416 5541.608 2.808 38.387

5541.608 5538.954 2.654 41.041

5538.954 5535.934 3.02 44.061

5535.934 5533.041 2.893 46.954

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Minggu, 21 Maret 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 8:00 1:00 Continues Mucking Out (4 DT Howo)
2 8:00 8:50 0:50 Scalling and Cleaning
3 8:50 9:30 0:40 Survey and Marking
4 9:30 12:00 2:30 Drilling Face (95 Hole, 3m Depth)
5 12:00 12:30 0:30 Charging and Blasting
6 12:30 12:45 0:15 Ventillating
7 12:45 15:00 2:15 Mucking Out (4 DT Howo)
8 15:00 15:30 0:30 Scalling and Cleaning
9 15:30 16:10 0:40 Survey and Marking
10 17:00 19:30 2:30 Drilling Face (95 Hole, 3m Depth)
11 19:30 20:00 0:30 Charging and Blasting
12 20:00 20:15 0:15 Ventillating
13 20:15 22:30 2:15 Mucking Out (4 DT Howo)
14 22:30 23:00 0:30 Scalling and Cleaning
15 23:00 23:40 0:40 Survey and Marking
16 23:40 2:00 2:20 Drilling Face (95 Hole, 3m Depth)
17 2:00 2:30 0:30 Charging and Blasting
18 2:30 2:45 0:15 Ventillating
19 2:45 5:00 2:15 Mucking Out (4 DT Howo)
20 5:00 5:30 0:30 Scalling and Cleaning
21 5:30 6:10 0:40 Survey and Marking
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- 16:10 - 17:00 WIB Standby Prepare Drilling
- 06:10 - 07:00 WIB Standby Drilling Down Stream
-
Issue
-
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

5533.041 5530.004 3.037 49.991

5530.004 5527.432 2.572 52.563

5527.432 5523.673 3.759 56.322

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs