WEEKLY PROGRESS REPORT

WORK AREA : ADIT 3 - Down Stream


PERIOD : 01 Maret 2021 To : 07 Maret 2021
WEEKLY PROGRESS
ACTIVITIES WEEKLY PROGRESS
DATE 1-Mar-21 2-Mar-21 3-Mar-21 4-Mar-21 5-Mar-21 6-Mar-21 7-Mar-21
PROGRESS

THIS WEEK LAST WEEK PLAN WEEK

METHOD Blasting Blasting Blasting - Blasting Blasting - Blasting Blasting 6 x


EXCAVATION (m) 2.812 2.635 2.184 - 2.920 2.497 - 2.434 15.482
STA / CHAINAGE (FROM STA-TO STA) 6810.818 - 6813.630 6816.265 6818.449 - 6821.369 6823.866 - 6826.300 6813.630 - 6826.300
DRILLING MACHINE Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28
HOLE (PCS) 72 72 72 72 72 72 72 72 432
BLASTING
DETAILS

DEPTH (M) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3-4m
DIA HOLE (MM) 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm
DETONATOR (PCS) 86 86 86 86 86 86 86 86 516
DAYAGEL (PCS/KG) 600 600 600 600 600 600 600 600 3600
CORTEX (M) - - - - - - - - -
SAFETY SHOTCRETE (FROM STA-TO STA) - - - - - - 6775.461 - 6821.369 - 46 m
FULL SHOTCRETE 10-15 CM (FROM STA-TO STA) - - - - - - - -
SUPPORT
ROCK

WIRE MESH (FROM STA-TO STA) - - - - - - - -


FOREPOLING(FROM STA-TO STA)/ PCS - - - - - - - -
TREAD BAR BOLT(FROM STA-TO STA) / PCS 6810.818 - 6813.630 6816.265 6818.449 - 6821.369 6823.866 - 6826.3 -
STEEL RIB (SET) - - - - - - - -
GROUTING - - - - - - - -
GEOLOGIC

GICAL

ROCK MASS CLASS FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III)
AL

RMR
MAPPING SHEET . NO
COORDINATE
SURVEY

KOORDINAT ( X )
KOORDINAT ( Y )
ELEVASI ( Z )
1. Safety Shotcrete 18
m³, 3x Mixing with Dux
REMARKS: Truck

PT.KERINCI MERANGIN HIDRO PT.KERINCI MERANGIN HIDRO

Muh Hasfan Hamrullah Satria Ronaldo


WEEKLY PROGRESS REPORT

WORK AREA : ADIT 3 - Down Stream


PERIOD : 08 Maret 2021 To : 14 Maret 2021
WEEKLY PROGRESS
ACTIVITIES WEEKLY PROGRESS
DATE 8-Mar-21 9-Mar-21 10-Mar-21 11-Mar-21 12-Mar-21 13-Mar-21 14-Mar-21
PROGRESS

THIS WEEK LAST WEEK PLAN WEEK

METHOD - Blasting Blasting Blasting Blasting Blasting Blasting Blasting Blasting Blasting 8 x
EXCAVATION (m) - 2.402 2.263 2.537 3.067 2.605 2.226 2.945 2.627 20.672
STA / CHAINAGE (FROM STA-TO STA) - 6826.300 - 6828.702 6830.965 6833.502 6836.569 6839.174 6841.400 6844.345 6846.972 6828.702 - 6846.972
DRILLING MACHINE Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28
HOLE (PCS) 72 72 72 72 72 72 72 72 72 432
BLASTING
DETAILS

DEPTH (M) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3-4m
DIA HOLE (MM) 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm
DETONATOR (PCS) 86 86 86 86 86 86 86 86 86 516
DAYAGEL (PCS/KG) 600 600 600 600 600 600 600 600 600 3600
CORTEX (M) - - - - - - - - - -
SAFETY SHOTCRETE (FROM STA-TO STA) - - - - - - - - - -
FULL SHOTCRETE 10-15 CM (FROM STA-TO STA) - - - - - - - - -
SUPPORT
ROCK

WIRE MESH (FROM STA-TO STA) - - - - - - - - -


FOREPOLING(FROM STA-TO STA)/ PCS - - - - - - - - -
TREAD BAR BOLT(FROM STA-TO STA) / PCS - 6826.300 - 6828.702 6830.965 6833.502 6836.569 6839.174 6841.4 6844.345 6846.972 -
STEEL RIB (SET) - - - - - - - - -
GROUTING - - - - - - - - -
GEOLOGIC

GICAL

ROCK MASS CLASS FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III)
AL

RMR
MAPPING SHEET . NO
COORDINATE
SURVEY

KOORDINAT ( X )
KOORDINAT ( Y )
ELEVASI ( Z )

REMARKS:

PT.KERINCI MERANGIN HIDRO PT.KERINCI MERANGIN HIDRO

Muh Hasfan Hamrullah Satria Ronaldo


WEEKLY PROGRESS REPORT

WORK AREA : ADIT 3 - Down Stream


PERIOD : 15 Maret 2021 To : 21 Maret 2021
WEEKLY PROGRESS
ACTIVITIES WEEKLY PROGRESS
DATE 15-Mar-21 16-Mar-21 17-Mar-21 18-Mar-21 19-Mar-21 20-Mar-21 21-Mar-21
PROGRESS

THIS WEEK LAST WEEK PLAN WEEK

METHOD Blasting Blasting Blasting Blasting Blasting Blasting Blasting Blasting Blasting Blasting 9 x
EXCAVATION (m) 2.016 1.842 2.590 2.780 2.927 2.586 2.195 2.577 2.578 22.091
STA / CHAINAGE (FROM STA-TO STA) 6846.972 - 6848.988 6850.830 6853.420 6856.200 6859.127 6861.713 6863.908 6866.485 6869.063 6848.988 - 6869.063
DRILLING MACHINE Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28
HOLE (PCS) 72 72 72 72 72 72 72 72 72 504
BLASTING
DETAILS

DEPTH (M) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3-4m
DIA HOLE (MM) 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm
DETONATOR (PCS) 86 86 86 86 86 86 86 86 86 602
DAYAGEL (PCS/KG) 600 600 600 600 600 600 600 600 600 4200
CORTEX (M) - - - - - - - - - -
SAFETY SHOTCRETE (FROM STA-TO STA) - - - - - - - - - -
FULL SHOTCRETE 10-15 CM (FROM STA-TO STA) - - - - - - - - -
SUPPORT
ROCK

WIRE MESH (FROM STA-TO STA) - - - - - - - - -


FOREPOLING(FROM STA-TO STA)/ PCS - - - - - - - - -
TREAD BAR BOLT(FROM STA-TO STA) / PCS 6846.972 - 6848.988 6850.83 6853.42 6856.2 6859.127 6861.713 6863.908 6866.485 6869.063 -
STEEL RIB (SET) - - - - - - - - -
GROUTING - - - - - - - - -
GEOLOGIC

GICAL

ROCK MASS CLASS FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III)
AL

RMR
MAPPING SHEET . NO
COORDINATE
SURVEY

KOORDINAT ( X )
KOORDINAT ( Y )
ELEVASI ( Z )

REMARKS:

PT.KERINCI MERANGIN HIDRO PT.KERINCI MERANGIN HIDRO

Muh Hasfan Hamrullah Satria Ronaldo


WEEKLY PROGRESS REPORT

WORK AREA : ADIT 3 - Down Stream


PERIOD : 22 Maret 2021 To : 28 Maret 2021
WEEKLY PROGRESS
ACTIVITIES WEEKLY PROGRESS
DATE 22-Mar-21 23-Mar-21 24-Mar-21 25-Mar-21 26-Mar-21 27-Mar-21 28-Mar-21
PROGRESS

THIS WEEK LAST WEEK PLAN WEEK

METHOD Blasting Blasting Blasting - Blasting Blasting - Blasting Blasting 6 x


EXCAVATION (m) 0.000
STA / CHAINAGE (FROM STA-TO STA) 6813.630 -
DRILLING MACHINE Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28
HOLE (PCS) 72 72 72 72 72 72 72 72 432
BLASTING
DETAILS

DEPTH (M) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3-4m
DIA HOLE (MM) 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm
DETONATOR (PCS) 86 86 86 86 86 86 86 86 516
DAYAGEL (PCS/KG) 600 600 600 600 600 600 600 600 3600
CORTEX (M) - - - - - - - - -
SAFETY SHOTCRETE (FROM STA-TO STA) - - - - - - 6775.461 - 6821.369 - 46 m
FULL SHOTCRETE 10-15 CM (FROM STA-TO STA) - - - - - - - -
SUPPORT
ROCK

WIRE MESH (FROM STA-TO STA) - - - - - - - -


FOREPOLING(FROM STA-TO STA)/ PCS - - - - - - - -
TREAD BAR BOLT(FROM STA-TO STA) / PCS 0 0 0 0 0 0 0 0 -
STEEL RIB (SET) - - - - - - - -
GROUTING - - - - - - - -
GEOLOGIC

GICAL

ROCK MASS CLASS FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III)
AL

RMR
MAPPING SHEET . NO
COORDINATE
SURVEY

KOORDINAT ( X )
KOORDINAT ( Y )
ELEVASI ( Z )
1. Safety Shotcrete 18
m³, 3x Mixing with Dux
REMARKS: Truck

PT.KERINCI MERANGIN HIDRO PT.KERINCI MERANGIN HIDRO

Muh Hasfan Hamrullah Satria Ronaldo


WEEKLY PROGRESS REPORT

WORK AREA : ADIT 3 - Down Stream


PERIOD : 29 Maret 2021 To : 04 April 2021
WEEKLY PROGRESS
ACTIVITIES WEEKLY PROGRESS
DATE 29-Mar-21 30-Mar-21 31-Mar-21 1-Apr-21 2-Apr-21 3-Apr-21 4-Apr-21
PROGRESS

THIS WEEK LAST WEEK PLAN WEEK

METHOD Blasting Blasting Blasting - Blasting Blasting - Blasting Blasting 6 x


EXCAVATION (m) 0.000
STA / CHAINAGE (FROM STA-TO STA) 6813.630 -
DRILLING MACHINE Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28 Leg drill Yt 28
HOLE (PCS) 72 72 72 72 72 72 72 72 432
BLASTING
DETAILS

DEPTH (M) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3-4m
DIA HOLE (MM) 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm 36 mm
DETONATOR (PCS) 86 86 86 86 86 86 86 86 516
DAYAGEL (PCS/KG) 600 600 600 600 600 600 600 600 3600
CORTEX (M) - - - - - - - - -
SAFETY SHOTCRETE (FROM STA-TO STA) - - - - - - 6775.461 - 6821.369 - 46 m
FULL SHOTCRETE 10-15 CM (FROM STA-TO STA) - - - - - - - -
SUPPORT
ROCK

WIRE MESH (FROM STA-TO STA) - - - - - - - -


FOREPOLING(FROM STA-TO STA)/ PCS - - - - - - - -
TREAD BAR BOLT(FROM STA-TO STA) / PCS 0 0 0 0 0 0 0 0 -
STEEL RIB (SET) - - - - - - - -
GROUTING - - - - - - - -
GEOLOGIC

GICAL

ROCK MASS CLASS FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III) FAIR (III)
AL

RMR
MAPPING SHEET . NO
COORDINATE
SURVEY

KOORDINAT ( X )
KOORDINAT ( Y )
ELEVASI ( Z )
1. Safety Shotcrete 18
m³, 3x Mixing with Dux
REMARKS: Truck

PT.KERINCI MERANGIN HIDRO PT.KERINCI MERANGIN HIDRO

Muh Hasfan Hamrullah Satria Ronaldo

You might also like