1. INTRODUCTION
This Clarification describes specification and standard for post-tensioning operations,
namely tendon installation, stressing and grouting of the tendons.
The anchorage type, location and stressing sequence should follow the description
shown on the shop drawings or specification.
If any problem or comment arising, please confirm to the QA/QC department engineer
and technical department engineer.
2. WORKDESCRIPTION
2.1 Some specifications
Detail at dead end
2.2 Fabrication
After having design drawing. Technical Department will calculate and issue list of
cutting cable ; HPDE duct for sub-construct to cut
After cutting, tendon must be marked name and rolled then put on warehouse to avoid
soil and water make it rusty.
HDPE duct, length of Tendons must be cut following data issued from technical
Department or construction department
2.3 Installation
Donot allow putting tendons on ground without some thing to protect dirty
At duct connection, Plastic tape use 2.5-3 circles for one position except some case
must use more to ensure quality
PREPARED BY DUC Page 2
March 12, 2014 [SPECIFICATION FOR FEBRICATING AND INSTALLING CABLE]
2.4 Stressing
Before stressing, tendons must be clean, equipment must be check and maintenance
Make sure true value of pressure during stressing specially at 10% and 103%
Sub-constructor only is cut cable when CSCC’s engineer allow.
Sequence of stressing tendon must follow as a figure below
chart of stressing