Variance
January
Jan. Hrs/Unit = 7.5 hours ~ 1 hour
16 113 units 15 units
No. of 20
working
= 0.07 hour x 60 mins
days unit 1 hour
Plan 100k = 4 mins /unit
No. of 5,000 Cycle time = 4 mins/unit
units
per day = 15 units/hour
Output 100,239 = 113 units/working
Variance day
March
March Hrs/Unit = 7.5 hours ~ 1 hour
. 16
113 units 15 units
No. of 28
working = 0.07 hour x 60 mins
days unit 1 hour
Plan 130k = 4 mins /unit
No. of 5,455 Cycle time = 4 mins/unit
units
per day
= 15 units/hour
Output 130,063
= 113 units/working
Variance day
May 20 41 181,760
June 27 40 200,448
128 x July
x 21 74
+ 2,208 201,120
Aug 20 63 161,280
Sept 28 50 179200
Oct16 Nov 16 Dec
Oct-Nov-Dec
No. of 21 21 23
Hrs/Unit = 7.5 hours ~ 1 hour
working
days
150 units 20 units
= 3 mins /unit
Plan 175k 150k 150k = 150 units/working day